KR101401645B1 - Poor ground improvement method and system by forming cast-in-place plain concrete column and using separated doughnut auger having suction duct - Google Patents

Poor ground improvement method and system by forming cast-in-place plain concrete column and using separated doughnut auger having suction duct Download PDF

Info

Publication number
KR101401645B1
KR101401645B1 KR1020120003291A KR20120003291A KR101401645B1 KR 101401645 B1 KR101401645 B1 KR 101401645B1 KR 1020120003291 A KR1020120003291 A KR 1020120003291A KR 20120003291 A KR20120003291 A KR 20120003291A KR 101401645 B1 KR101401645 B1 KR 101401645B1
Authority
KR
South Korea
Prior art keywords
auger
gravel
sand
cement
silo
Prior art date
Application number
KR1020120003291A
Other languages
Korean (ko)
Other versions
KR20130082219A (en
Inventor
이승재
Original Assignee
이승재
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이승재 filed Critical 이승재
Priority to KR1020120003291A priority Critical patent/KR101401645B1/en
Priority to PCT/KR2012/002995 priority patent/WO2013105705A1/en
Publication of KR20130082219A publication Critical patent/KR20130082219A/en
Application granted granted Critical
Publication of KR101401645B1 publication Critical patent/KR101401645B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/62Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes

Abstract

본 발명은 이중오거의 이용 및 현장타설무근콘크리트 기둥의 형성에 의한 연약지반 개량 공법 및 시스템에 관한 것으로, 보다 상세하게는 연약지반에 구조물을 시공함에 있어, 해당 구조물의 기초 구조물이 시공되는 지반의 지질정보에 기초하여 모래, 자갈, 시멘트 및 물을 포함하는 콘크리트의 비율을 산출하고, 산출된 비율에 따라 해당 구조물의 기초 구조물을 시공함으로써, 해상 등의 연약지반에 시공되는 구조물의 구조적 안전성을 향상시킬 수 있다
또한, 본 발명은 해당 구조물의 기초 구조물 시공시, 해당 지반 및 구조물에 대응하여 최적화된 계획고를 조절하여 시공할 수 있으며, 상대적으로 낮은 지질 개량률로도 충분한 압축강도를 얻을 수 있으므로, 공사기간을 단축할 수 있고 공사비용 절감을 할 수 있는 효과가 있다.
더불어, 본 발명은 동일한 강도를 구현할 경우, 이산화탄소를 배출시키는 시멘트를 보다 적게 사용함으로써, 구조물 시공에 따른 환경오염문제를 감소시킬 수 있는 장점이 있다.
따라서, 해상 등의 연약지반에서의 구조물 시공분야에서 구조물의 구조적 안전성과 시공상의 경쟁력 및 해당 구조물에 대한 신뢰성을 향상시킬 수 있다.
The present invention relates to a method and a system for improving a soft ground by using a double auger and forming a concrete pillar on a site, and more particularly, to a method and a system for constructing a foundation in a soft foundation, By calculating the ratio of concrete containing sand, gravel, cement and water based on the geological information, and by constructing the foundation structure of the structure in accordance with the calculated ratio, the structural safety of the construction applied to the soft ground such as the sea is improved Be able to
In addition, the present invention can be applied by adjusting the plan height optimized for the foundation and the structure at the time of constructing the foundation structure of the structure, and since the sufficient compression strength can be obtained even at a relatively low lipid improvement rate, And the construction cost can be reduced.
In addition, the present invention has the advantage of reducing the environmental pollution problem due to the construction of the structure by using less cement for discharging carbon dioxide when the same strength is realized.
Therefore, it is possible to improve the structural safety of the structure, the competitiveness in construction, and the reliability of the structure in the construction field of the soft ground such as the sea.

Description

흡입구가 장착된 이중오거의 이용 및 현장타설무근콘크리트 기둥의 형성에 의한 연약지반 개량 공법 및 시스템{Poor ground improvement method and system by forming cast-in-place plain concrete column and using separated doughnut auger having suction duct}BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method and system for improving a ground by using a double auger equipped with a suction port,

본 발명은 케이싱과 오거가 서로 반대 방향으로 회전되면서 굴착하는 이중오거(SDA: Separated Doughnut Auger 또는 DRA)를 이용하고, 굴착된 곳에 현장타설무근콘크리트 기둥의 형성에 의한 연약지반 개량 공법 및 시스템에 관한 것으로서, 보다 상세하게는 해상 등의 연약지반에 시공되는 구조물의 구조적 안전성 및 시공성을 향상시키기 위한 것이다.The present invention relates to a method and system for improving soft ground by using a double auger (SDA: Separated Donut Auger or DRA) excavated while rotating casing and auger in opposite directions, And more particularly to improve the structural safety and workability of a structure to be applied to soft ground such as marine.

특히, 본 발명은 연약지반에 구조물을 시공함에 있어, 해당 구조물의 기초 구조물이 시공되는 지반의 지질정보에 기초하여 원지반토에 시멘트 밀크를 교반 혼합하는 심층혼합처리공법(DCM: Deep soil stabilization by chemical method) 대신 이중오거의 이용 및 현장타설무근콘크리트 기둥 형성에 의해 연약지반을 개량하는 공법 및 그 시스템에 관한 것이다.
Particularly, the present invention relates to a method for producing a deep soil stabilization by chemical (DCM) method in which a cement milk is mixed with a ground soil based on the geological information of the ground on which the foundation structure of the structure is installed, This paper deals with a method and system for improving the soft ground by using double auger instead of the method and forming a concrete column in the field.

심층혼합처리공법(DCM : Deep soil stabilization by chemical method)은 석회나 시멘트 등을 심층의 지반 속에 교반 및 혼합하여 지반을 단단히 다짐으로써, 강도를 증가시키는 공법으로, 우수한 화학적 지반 개량 공법이다.Deep soil stabilization by chemical method (DCM) is an excellent chemical soil improvement method by strengthening the ground by mixing and mixing lime or cement in deep ground.

특히, 연약지반과 안정제가 혼합하면서 발생하는 수화반응을 통해서 물리적 및 화학적으로 고형화된 지중 구조체를 시공할 수 있다.In particular, it is possible to construct an underground structure that is physically and chemically solidified through hydration reaction generated by mixing soft ground and stabilizer.

이러한 장점으로 인해, 현재 대부분의 연약지반에서의 구조물 시공에는 심층혼합처리공법이 이용되고 있다.Due to these advantages, the deep mixing treatment method is currently used for construction of most soft grounds.

한편, 연약지반, 특히 해상의 연약지반은 점토가 다량 함유될 수 있다.On the other hand, soft grounds, especially marine soft grounds, can contain large amounts of clay.

이러한 지반에서 심층혼합처리공법을 이용한 기초 구조물 시공의 경우, 많은 양의 시멘트를 투여한다 하더라도, 원하는 강도가 발현되지 못하는 경우가 발생할 수 있다.In the case of the foundation construction using the deep mixing treatment method in such a ground, even if a large amount of cement is administered, the desired strength may not be expressed.

또한, 다축오거(Auger)의 동작시 각각의 로드는 굴착심도가 깊을수록, 상부에서 제거되지 않고 존재하는 원지반토와 지중에서 가해지는 저항이 증가하게 된다. 따라서, 풍화토층(목표층)까지 교반되지 않았음에도 불구하고 과부하로 인해 장비가 멈추거나 로드가 더 이상 내려가지 않고 헛도는 경우를 볼 수 있다.In addition, the deeper excavation depths of the individual rods during multi-axis auger operation lead to an increase in the resistance of the existing ground piles and ground that are not removed from the top. Therefore, even though the weathering layer (target layer) is not agitated, it can be seen that the equipment is stopped due to overload, or the load is no longer lowered and idling.

이를 확인하기 위하여, 확인보링을 하더라도 시공된 선단부분부터 풍화토층까지 수 cm 내지 수십 cm의 점토가 뭉쳐 있는 코어가 발생될 수 있고, 이러한 코어의 점토부분은 해당 구조물의 안전성을 확보하기 위한 강도를 가지지 못하게 되어, 시간이 경과되면 해당 구조물이 침하하는 원인이 될 수 있다.In order to confirm this, even if confirmation boring is performed, clusters of several centimeters to several tens of centimeters of clay may be generated from the applied tip to the weathering layer, and the clay portion of such core may have a strength for securing the safety of the structure And it may cause the structure to settle when the time elapses.

또한, 심층혼합처리공법은 원지반토에 시멘트밀크를 교반함으로 인해 투입된 시멘트밀크의 체적만큼 전체 체적이 증가하며, 시공 후 시공부분이 슬러지로 인해 융기가 되고, 계획고를 맞추기 위해 준설해야 하며, 준설된 토양은 시멘트가 혼합되어 있어 산업폐기물 처리를 해야 한다.In addition, in the deep mixing process, the volume of the cement milk is increased by the volume of the cement milk introduced by the agitation of the cement milk in the ground pile soil, the construction part is raised by the sludge, Soils should be treated with industrial waste mixed with cement.

반면, SDA(Separated Doughnut Auger) 공법은 이중오거 공법이라 하며, 현장에서는 DRA(Double Rod Auger)공법이라고도 한다. SDA공법은 원래 PHC(Pretensioned Spun High strength Concrete) 기둥을 시공하기 위한 공법으로 고안되었으나, 해상에서 항타가 용이하지 않으며 항타를 위해 필요한 공정, 다시 말해, PHC파일의 수송, 보관 등이 난이하여 시공성의 저하와 시공비의 상승을 유발하기 때문에, 이 공법은 현장타설무근콘크리트 기둥을 제작하는데 사용될 수 있다.On the other hand, the SDA (Separated Donut Auger) method is called double auger method, and it is also called DRA (Double Rod Auger) method in the field. The SDA method was originally designed as a method for constructing a PHC (Pretensioned Spun High Strength Concrete) column. However, it is not easy to hose at sea and it is difficult to transport, This method can be used to produce concrete columns that are installed on site because it causes deterioration and increase of construction cost.

SDA공법은 케이싱(Casing)으로 공벽붕괴와 지중압력을 막고, 스크류오거(Screw Auger)로 케이싱 내부의 토사를 제거함으로써, 상부에서 작용하는 압력을 받지 않아 오거의 과부하나 헛도는 현상을 감소시킬 수 있다.The SDA method uses a casing to prevent air collapse and underground pressure, and by removing the soil inside the casing with a screw auger, it is not subjected to the pressure applied at the top, thereby reducing the overgrowth of the auger .

공정에서 항타가 필요하지 않기 때문에 스크류오거와 케이싱을 동시에 인발해도 되며, 이에 스크류오거와 케이싱을 회전시키는 오거모터의 일체화와 다축화로 시공성과 경제성을 높일 수 있다.
Since the hanger is not required in the process, the screw auger and the casing can be drawn at the same time, and the screw auger and the auger motor rotating the casing can be integrated and multi-shaft can improve the workability and economy.

본 발명은 해상 등의 연약지반에 시공되는 구조물의 구조적 안전성을 충분히 보장할 수 있도록 이중오거를 이용한 현장타설무근콘크리트 기둥의 형성을 통해 연약지반 개량 공법 및 시스템을 제공하는데 목적이 있다. An object of the present invention is to provide a method and system for improving soft ground by forming a concrete pillar on site using a double auger so as to sufficiently guarantee the structural safety of a structure to be applied to soft ground such as marine.

이를 위하여, 본 발명은 연약지반에 구조물을 시공함에 있어, 해당 구조물의 기초 구조물이 시공되는 지반의 지질정보에 기초하여 모래, 자갈, 시멘트 및 물의 비율을 산출하고, 산출된 비율에 따라 해당 구조물의 기초 구조물을 시공함으로써, 해당 구조물의 구조적 안전성을 향상시킬 수 있는 이중오거의 이용 및 현장타설무근콘크리트 기둥의 형성에 의한 연약지반 개량 공법 및 시스템을 제공하는 것을 목적으로 한다.To this end, in the construction of a structure on a soft ground, the present invention calculates the ratio of sand, gravel, cement and water based on the geological information of the ground on which the foundation structure of the structure is installed, It is an object of the present invention to provide a method and a system for improving soft ground by using a double auger to improve the structural safety of the structure by constructing a foundation structure and forming a concrete pillar on a site.

본 발명의 상기 목적과 여러 가지 장점은 이 기술분야에 숙련된 사람들에 의해 본 발명의 바람직한 실시예로부터 더욱 명확하게 될 것이다.
The above objects and various advantages of the present invention will become more apparent from the preferred embodiments of the present invention by those skilled in the art.

상기와 같은 목적을 달성하기 위해서, 본 발명에 따른 이중오거의 이용 및 현장타설무근콘크리트 기둥의 형성에 의한 연약지반 개량 공법은 a) 설정된 지점을 굴착하고, 해당 굴착심도가 설정심도에 도달하면, 해당 설정심도의 지질정보에 기초하여 산출된 모래, 자갈, 시멘트 및 물의 비율에 대응하여 모래/자갈 사일로, 시멘트 사일로 및 물공급펌프의 동작을 제어하는 단계; b) 해당 굴착공에 제어된 비율의 모래, 자갈, 시멘트 및 물을 포함하는 콘크리트를 주입하여 현장타설무근콘크리트 기둥을 형성하는 공법(DCX공법: Deep plain concrete Column eXpress)에 의한 기초 구조물의 기둥을 형성하는 단계; 및 c) 상기 형성된 기둥의 상부에 계획고에 대응하도록 높이가 조절된 기초 시공 구조물을 시공하는 단계를 포함한다.In order to accomplish the above object, the present invention provides a method of improving soft ground by using a double auger and forming a concrete pillar on a site, comprising the steps of: a) excavating a set point and, when the corresponding depth of cut reaches a set depth, Controlling operation of the sand / gravel silo, cement silo and water supply pump corresponding to the ratio of sand, gravel, cement and water calculated based on the geological information of the set depth; b) By pouring concrete containing sand, gravel, cement and water at a controlled rate into the excavation pits, the pillar of the foundation structure is formed by the method (DCX method: Deep plain concrete column eXpress) ; And c) constructing a base construction having a height that is adjusted to correspond to the plan height on top of the formed column.

상기 단계 a)는 a-1) 상기 설정된 지점을 굴착하면서 굴착한계도달여부를 확인하는 단계; a-2) 상기 확인결과, 굴착한계에 도달하면 해당 굴착심도가 설정심도인지를 확인하는 단계; a-3) 상기 확인결과, 해당 굴착심도가 설정심도인 경우, 해당 굴착지점의 지질정보를 확인하여 모래, 자갈, 시멘트 및 물의 주입량 또는 비율을 산출하는 단계; 및 a-4) 상기 산출된 모래, 자갈, 시멘트 및 물의 주입량 또는 비율에 대응하여 모래 사일로, 자갈 사일로, 시멘트 사일로 및 물공급펌프 중 적어도 하나의 동작을 제어하는 단계를 포함한다.The step a) comprises: a-1) confirming whether the excavation limit is reached while excavating the set point; a-2) confirming whether the drilling depth is a set depth when the drilling limit is reached; a-3) calculating the injection amount or ratio of sand, gravel, cement, and water by confirming the geological information of the excavation site when the corresponding excavation depth is the set depth; And a-4) controlling the operation of at least one of a sand silo, a gravel silo, a cement silo, and a water supply pump corresponding to the amount or the ratio of the sand, gravel, cement, and water.

상기 단계 c)는 c-1) 상기 기초 시공 구조물의 계획고를 확인하는 단계; c-2) 상기 계획고 조절을 위한 시공방법을 확인하는 단계; c-3) 상기 확인된 계획고 조절 시공방법이 방출법인 경우, 상기 기둥 시공 후 콘크리트 타설에 의한 슬라브를 형성하는 단계를 포함한다.The step c) includes the steps of: c-1) confirming the planned height of the foundation construction; c-2) confirming the construction method for the height adjustment; c-3) In the case where the above-described high-modulus construction method is a discharge method, the slab is formed by casting concrete after the column is installed.

상기 단계 c)는 c-1) 상기 기초 시공 구조물의 계획고를 확인하는 단계; c-2) 상기 계획고 조절을 위한 시공방법을 확인하는 단계; c-3) 상기 확인된 계획고 조절 시공방법이 가변두법인 경우, 상기 기둥 시공 후 적어도 하나의 높이조절용 단위블럭을 적층하여 가변캡을 설치하는 단계를 포함한다.The step c) includes the steps of: c-1) confirming the planned height of the foundation construction; c-2) confirming the construction method for the height adjustment; c-3) In the case where the determined plan height adjustment construction method is a variable two method, at least one height-adjusting unit block is stacked after installing the column to install a variable cap.

본 발명에 따른 이중오거의 이용 및 현장타설무근콘크리트 기둥의 형성을 위한 연약지반 개량 시스템은 현장타설무근콘크리트 기둥을 형성하는 공법(DCX공법: Deep plain concrete Column eXpress)을 기반으로 시공되는 기초 구조물의 기둥을 형성하기 위한 모래 및 자갈을 각각 분리하여 공급하는 모래/자갈 공급장치; 상기 모래/자갈 공급장치에 의해 각각 분리되어 공급되는 모래 및 자갈을 각각 분리하여 저장하고, 상기 기초 구조물이 시공되는 설정심도의 지질정보에 기초하여 산출된 모래 및 자갈의 비율에 대응하여 입력되는 제어신호에 따라 저장된 모래 및 자갈 중 적어도 하나의 공급량을 제어하는 모래/자갈 사일로; 상기 기초 구조물이 시공되는 설정심도의 지질정보에 기초하여 산출된 물의 비율에 대응하여 입력되는 제어신호에 따라 물의 공급량을 제어하는 물공급펌프; 상기 기초 구조물이 시공되는 설정심도의 지질정보에 기초하여 산출된 시멘트의 비율에 대응하여 입력되는 제어신호에 따라 시멘트의 공급량을 제어하는 시멘트 사일로; 상기 모래/자갈 사일로, 물공급펌프 및 시멘트 사일로부터 공급되는 모래, 자갈, 시멘트 및 물을 혼합하는 콘크리트용 믹서; 및 상기 기초 구조물이 시공될 위치를 굴착하고, 굴착 시 발생되는 산물을 외부로 배출하는 베이스머신;을 포함하며, 상기 베이스머신은 이중오거를 포함하되, 상기 이중오거는 케이싱과, 상기 케이싱 내에 배치되며, 내부에 중공이 형성된 오거와, 상기 오거의 하부에 형성되며, 상기 물공급펌프로부터 공급되는 물이 토출되는 토출구와, 상기 오거 상부의 로드에 삽입 결합되되, 내주면에 베어링이 구비되어 상기 로드의 회전에 연동되지 않고 위치 고정되는 고정구 및 상기 케이싱 내면과 상기 오거 사이에 배치되되, 상기 고정구에 결합 고정되며, 상기 토출구에서 토출되는 물 및 굴착 시 발생되는 부산물을 흡입하는 흡입구를 포함한다.The soft ground improvement system for the use of the double auger according to the present invention and for the formation of the non-rigid concrete column in the field is based on the DCX method (Deep plain concrete column eXpress) A sand / gravel supply device for separately supplying sand and gravel for forming columns, respectively; The sand and gravel separated and supplied by the sand / gravel supply device are separately stored, and the control is performed in accordance with the ratio of the sand and gravel calculated based on the geological information of the set depth, A sand / gravel silo for controlling the feed rate of at least one of sand and gravel stored according to the signal; A water supply pump for controlling a supply amount of water in accordance with a control signal inputted corresponding to a ratio of water calculated on the basis of the set depth of the foundation structure; A cement silo for controlling a supply amount of cement according to a control signal input corresponding to a ratio of cement calculated based on geological information of a set depth to which the foundation structure is applied; A concrete mixer for mixing sand, gravel, cement and water supplied from the sand / gravel silo, water supply pump and cement silo; And a base machine for excavating a position where the foundation structure is to be installed and discharging the product generated during excavation to the outside, wherein the base machine includes a double auger, wherein the double auger comprises a casing, A discharge port formed at a lower portion of the auger for discharging water supplied from the water supply pump and a bearing inserted in the rod at the upper portion of the auger, And a suction port which is disposed between the inner surface of the casing and the auger and is fixedly coupled to the fixture and sucks water discharged from the discharge port and by-products generated during excavation.

상기 시공된 기초 구조물의 기둥 상부에 계획고에 기초하여 상기 기초 구조물의 높이를 조절하기 위한 가변캡을 시공하는 가변캡 설치장치를 더 포함한다.And a variable cap installation device for installing a variable cap for adjusting the height of the foundation structure based on the plan height on the column of the constructed foundation structure.

상기 가변캡 설치장치는 상기 장주의 상부에 결합설치되는 중공의 캡형 결합구; 상기 결합구의 상부에 적층설치되는 적어도 하나의 높이조절용 단위블럭; 및 상기 단위블럭의 상부에 고정설치되는 마감구를 순차적으로 적층하도록 구성 및 동작되는 것이 바람직하다.
The variable cap installation device includes: a hollow cap-shaped coupling member coupled to an upper portion of the longitudinal shaft; At least one height-adjusting unit block stacked on top of the coupling means; And a finishing tool fixedly installed on the upper portion of the unit block are sequentially stacked.

상기와 같은 해결수단에 의해, 본 발명은 해상 등의 연약지반에 시공되는 구조물의 구조적 안전성을 충분히 보장할 수 있는 장점이 있다.According to the above-mentioned solution, the present invention has an advantage that the structural safety of a structure applied to soft ground such as marine can be sufficiently secured.

또한, 본 발명은 해당 구조물의 기초 구조물 시공시, 해당 지반 및 구조물에 대응하여 최적화된 계획고를 조절하여 시공할 수 있는 장점이 있다.In addition, the present invention has an advantage in that it is possible to adjust the planned height in accordance with the ground and structure when the foundation structure of the structure is constructed.

특히, 본 발명은 기존의 심층혼합처리공법에 비하여 상대적으로 낮은 지질 개량률로도 충분한 압축강도를 얻을 수 있으므로, 공사기간을 단축할 수 있고 공사비용 절감을 할 수 있는 효과가 있다.In particular, since the present invention can obtain a sufficient compressive strength even at a relatively low lipid improvement rate as compared with the existing deep-sea mixing treatment method, the construction period can be shortened and the construction cost can be reduced.

또한, 기초 구조물 시공시 심층에 현장타설무근콘크리트 기둥을 형성하는 공법을 이용함에 따라, 기초 사석을 놓을 필요가 없으며, 이 또한 공사기간을 단축할 수 있고 공사비용 절감을 할 수 있는 효과가 있다.In addition, by using a method of forming an in-situ concrete concrete column in the deep layer when constructing a foundation structure, there is no need to lay a foundation stone, which can shorten the construction period and reduce the construction cost.

더불어, 본 발명은 대체적으로 점토가 주성분인 해양 원지반토가 아닌 모래/자갈을 이용함으로 인해 비교적 적은 양의 시멘트로도 목표하는 강도를 실현할 수 잇어, 이산화탄소를 배출시키는 시멘트의 사용을 줄여 지구온난화 방지에 도움이 될 수 있는 장점이 있다.In addition, since the present invention generally uses sand / gravel rather than a marine ground sole mainly composed of clay, it is possible to realize a desired strength even with a relatively small amount of cement, thereby reducing the use of cement for discharging carbon dioxide to prevent global warming There is an advantage that can be helpful.

따라서, 해상 등의 연약지반에서의 구조물 시공분야에서 구조물의 구조적 안전성과 시공상의 경쟁력 및 해당 구조물에 대한 신뢰성을 향상시킬 수 있다.
Therefore, it is possible to improve the structural safety of the structure, the competitiveness in construction, and the reliability of the structure in the construction field of the soft ground such as the sea.

도 1은 본 발명의 일 실시예에 따른 이중오거의 이용 및 현장타설무근콘크리트 기둥의 형성에 의한 연약지반 개량 시스템을 개략적으로 나타낸 구성도이다.
도 2는 도 1의 이중오거를 개략적으로 나타낸 개략도이다.
도 3은 본 발명의 일 실시예에 따른 이중오거의 이용 및 현장타설무근콘크리트 기둥의 형성에 의한 연약지반 개량 공법을 설명하는 흐름도이다.
도 4는 도 3의 단계 'S100'에 대한 구체적인 일 실시예를 설명하는 순서도이다.
도 5는 도 3의 단계 'S300'에 대한 구체적인 일 실시예를 설명하는 순서도이다.
도 6은 도 3의 공법 중 방출법을 설명하기 위한 도면이다.
도 7은 도 3의 공법 중 가변두법을 설명하기 위한 도면이다.
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a schematic view showing a system for improving a soft ground by using a double auger according to an embodiment of the present invention and forming a concrete pillar on a site.
Fig. 2 is a schematic view schematically showing the double auger of Fig. 1;
3 is a flowchart illustrating a method of improving soft ground by using a double auger according to an embodiment of the present invention and forming a concrete pillar in a field installation.
FIG. 4 is a flowchart illustrating a specific embodiment of step 'S100' of FIG.
5 is a flowchart illustrating a specific embodiment of step S300 of FIG.
Fig. 6 is a view for explaining the release method in the method of Fig.
Fig. 7 is a view for explaining the variable bending method in the method of Fig.

본 발명에 따른 흡입구가 장착된 이중오거의 이용 및 현장타설무근콘크리트 기둥의 형성에 의한 연약지반 개량 공법 및 시스템에 대한 예는 다양하게 적용할 수 있으며, 이하에서는 첨부된 도면을 참조하여 가장 바람직한 실시예에 대해 설명하기로 한다.Examples of the method of improving the soft ground by the use of the double auger equipped with the inlet according to the present invention and the formation of the concrete pillar in the field can be variously applied. An example will be described.

본 발명의 연약지반 개량 공법을 설명하기 전에 이에 사용되는 시스템에 대해 먼저 설명하고, 연약지반 개량 공법에 대해 설명하기로 한다.
Before describing the soft ground improvement method of the present invention, the system used there will be described first, and the soft ground improvement method will be described.

도 1은 본 발명의 일 실시예에 따른 이중오거의 이용 및 현장타설무근콘크리트 기둥의 형성에 의한 연약지반 개량 시스템을 개략적으로 나타낸 구성도이며, 도 2는 도 1의 이중오거를 개략적으로 나타낸 개략도이다.FIG. 1 is a schematic view of a soft ground improvement system by using a double auger according to an embodiment of the present invention and forming a concrete pillar without a spot; FIG. 2 is a schematic view schematically showing the double auger of FIG. to be.

도 1 및 도 2를 참조하면, 연약지반 개량 시스템(100)은 모래/자갈 공급장치(110), 모래/자갈 사일로(120), 물공급펌프(130), 시멘트 사일로(140), 콘크리트용 믹서(150), 콘크리트용 교반기(160), 콘크리트용 펌프(170) 및 오거(190)가 구비된 베이스머신(180)을 포함한다.1 and 2, the soft ground improvement system 100 includes a sand / gravel feeder 110, a sand / gravel silo 120, a water feed pump 130, a cement silo 140, A concrete machine 150, a concrete stirrer 160, a concrete pump 170, and an auger 190.

모래/자갈 공급장치(110)는 심층에 현장타설무근콘크리트 기둥을 형성하는 공법(DCX공법: Deep plain concrete Column eXpress;이하 'DCX공법'으로 지칭한다)을 기반으로 시공되는 기초 구조물의 기둥(또는 장주)을 형성하기 위한 모래 및 자갈을 각각 분리하여 공급한다. 예를 들어, 모래/자갈 공급장치(110)는 자동제어되는 굴삭기를 포함할 수 있다.The sand / gravel supply unit 110 is a column (or column) of the foundation structure to be constructed based on a DCX method (DCX method) in which a spot-free concrete column is formed in the deep layer Sand and pebbles are separately supplied to form a long sandy shale. For example, the sand / gravel feeder 110 may include an automatically controlled excavator.

모래/자갈 사일로(120)는 모래/자갈 공급장치(110)에 의해 각각 분리되어 공급되는 모래 및 자갈을 각각 분리하여 저장 후 공급한다. 일 실시예에서, 모래/자갈 사일로(120)는 모래 사일로(121) 및 자갈 사일로(122)를 포함한다. 예를 들어, 모래 사일로(121) 및 자갈 사일로(122)는 각각 별도의 저장공간을 갖도록 구획되어 구성되며, 각 사일로는 저장된 모래 또는 자갈의 공급량을 개별적으로 제어할 수 있도록 구성될 수 있다.The sand / gravel silo 120 separately separates and supplies sand and gravel separated and supplied by the sand / gravel feeder 110, and supplies the sand and gravel. In one embodiment, the sand / gravel silo 120 includes a sand silo 121 and a gravel silo 122. For example, the sand silo 121 and the gravel silo 122 may be separately configured to have a separate storage space, and each silo may be configured to individually control the supply amount of the stored sand or gravel.

모래/자갈 사일로(120), 물공급펌프(130) 및 시멘트 사일로(140)는 각각 모래, 자갈, 시멘트 및 물을 콘크리트용 믹서(150)에 공급할 수 있다.The sand / gravel silo 120, the water supply pump 130 and the cement silo 140 may supply sand, gravel, cement and water to the concrete mixer 150, respectively.

콘크리트용 믹서(150)는 모래/자갈 사일로, 물공급펌프 및 시멘트 사일로부터 공급되는 모래, 자갈, 시멘트 및 물을 혼합한다.The concrete mixer 150 mixes sand, gravel, cement and water supplied from a sand / gravel silo, a water supply pump and a cement silo.

콘크리트용 믹서(150)에서 혼합된 콘크리트는 콘크리트용 교반기(160) 및 콘크리트용 펌프(170)를 통해 베이스머신(180)에 공급된다.The concrete mixed in the concrete mixer 150 is supplied to the base machine 180 through the concrete mixer 160 and the concrete pump 170.

베이스머신(180)은 이중오거(190)를 포함하되, 이중오거(190)는 흡입구(191), 케이싱(192), 토출구(193), 오거(194) 및 고정구(195)를 포함한다.The base machine 180 includes a double auger 190 which includes an inlet 191, a casing 192, an outlet 193, an auger 194 and a fixture 195.

여기서, 케이싱(192)과 오거(194)는 회전되되, 서로 반대 방향으로 회전되는 것으로 이를 이중오거라 하며, 상기 이중오거 중 일반적인 기술에 대하여는 그 상세한 설명은 생략하기로 하고, 새롭게 추가된 구성에 대하여만 설명하기로 한다.Here, the casing 192 and the auger 194 are rotated and rotated in opposite directions to each other, and a detailed description thereof will be omitted for the general description of the double auger. .

상기 흡입구(191)는 별도의 흡입펌프와 연결된 관 형상으로, 케이싱(192) 내에 삽입되어 케이싱(192) 내면과 오거(194) 사이에 배치되되, 오거(194)가 결합된 로드를 지지대 삼아 베어링을 이용하여 고정되어 오거(194)에 의하여 굴착 시 지반에 포함된 흙, 모래, 자갈 등과 토출구(193)를 통해 공급되는 물을 흡입하여 외부의 토운선으로 이송시킨다. The intake port 191 is inserted into the casing 192 and is disposed between the inner surface of the casing 192 and the auger 194. The outer surface of the auger 194 is supported by a bearing Sand, gravel, and the like contained in the ground during the excavation by the auger 194 and the water supplied through the discharge port 193 to the outer tractor.

즉, 흡입구(191)의 고정은 고정구(195)에 의하는데, 상기 고정구(195)는 로드에 삽입 결합되되, 로드와의 사이에 베어링이 개재되어 오거(194)의 회전을 방해하지 않으면서 흡입구(191)를 로드에 고정 결합시킬 수 있다.That is, the suction port 191 is fixed to the fixture 195, and the fixture 195 is inserted into the rod, and the bearing is interposed between the fixture 195 and the rod, (191) to the rod.

토출구(193)는 굴착시 물을 공급할 수 있다. 여기서, 공급되는 물은 굴착을 용이하게 하고 굴착과정에서 발생되는 흙, 모래, 자갈 등이 흡입구(191)로 원활하게 흡입될 수 있도록 할 수 있다. 일 실시예에서, 토출구(193)는 굴착이 완료되면, 본 발명에 의해 혼합된 콘크리트를 주입할 수 있다.The discharge port 193 can supply water at the time of excavation. Here, the supplied water facilitates excavation and enables the soil, sand, gravel, and the like generated during the excavation process to be sucked into the suction port 191 smoothly. In one embodiment, the discharge port 193 is capable of injecting the mixed concrete by the present invention once the excavation is completed.

오거(194)는 해당 지중을 굴착하는 것으로, 오거(194)의 종단부에는 굴착용 스크류(194a)가 구비될 수 있고, 상기 토출구(193)와 연통되도록 내부에 중공이 형성된다.The auger 194 excavates the ground. The excavation screw 194a may be provided at the end of the auger 194 and a hollow may be formed inside the auger 194 to communicate with the discharge port 193.

즉, 오거(194)에 의한 굴착 시 물공급펌프(130)로부터 공급된 물은 오거(194)의 중공을 통해 토출구(193)로 배출된다.That is, the water supplied from the water supply pump 130 at the time of excavation by the auger 194 is discharged to the discharge port 193 through the hollow of the auger 194.

일 실시예에서, 이중오거를 이용한 연약지반 개량 시스템은 시공된 기초 구조물의 기둥 상부에, 계획고에 기초하여 해당 기초 구조물의 높이를 조절하기 위한 가변캡을 시공하는 가변캡 설치장치(도시하지 않음)를 더 포함할 수 있다.In one embodiment, the soft ground improvement system using the double auger comprises a variable cap installation device (not shown) for installing a variable cap for adjusting the height of the foundation structure on the basis of the plan height, ).

예를 들어, 가변캡 설치장치는 도 7에 나타난 바와 같은 기둥의 상부에 결합설치되는 중공의 캡형 결합구(31), 결합구(31)의 상부에 적층 설치되는 적어도 하나의 높이조절용 단위블럭(32) 및 단위블럭(32)의 상부에 고정설치되는 마감구(33)를 순차적으로 적층하도록 구성 및 동작될 수 있다.For example, the variable cap mounting apparatus includes a hollow cap type coupling member 31 coupled to an upper portion of a column as shown in FIG. 7, at least one height adjusting unit block 32 and a finishing hole 33 fixedly installed on the upper portion of the unit block 32 are sequentially stacked.

다른 예로, 가변캡 설치장치는 기둥에 결합구(31) 또는 마감구(33) 중 적어도 하나를 설치할 수 있다. 다시 말해, 당업자의 필요에 의해 단위블럭(32)을 설치하지 않을 수 있다.As another example, the variable cap installation apparatus may be provided with at least one of the coupling hole 31 and the finishing hole 33 on the column. In other words, the unit block 32 can be omitted depending on the needs of the person skilled in the art.

이상에서 설명된 각 장치의 구체적인 구성 및 결합관계는 당업자의 요구에 따라 다양한 변형이 가능하므로, 특정한 것에 한정하지 않음은 당연하다.
The specific configurations and coupling relationships of the respective devices described above can be variously modified according to the needs of those skilled in the art, and therefore, it is obvious that they are not limited to specific ones.

이하에서, 상기 설명된 연약지반 개량 시스템(100)을 이용하여 해당 연약지반을 개량하는 방법에 대해 설명하기로 한다.Hereinafter, a method for improving the soft ground using the soft ground improvement system 100 will be described.

도 3은 본 발명의 일 실시예에 따른 이중오거의 이용 및 현장타설무근콘크리트 기둥의 형성에 의한 연약지반 개량 공법을 설명하는 흐름도이고, 도 4는 도 3의 단계 'S100'에 대한 구체적인 일 실시예를 설명하는 순서도이며, 도 5는 도 3의 단계 'S300'에 대한 구체적인 일 실시예를 설명하는 순서도이고, 도 6은 도 3의 공법 중 방출법을 설명하기 위한 도면이며, 도 7은 도 3의 공법 중 가변두법을 설명하기 위한 도면이다.FIG. 3 is a flowchart illustrating a method of improving a soft ground by using a double auger according to an embodiment of the present invention and forming a concrete pillar on a site. FIG. 4 is a flowchart illustrating a concrete implementation of step S100 of FIG. FIG. 5 is a flow chart for explaining a specific embodiment of the step 'S300' of FIG. 3, FIG. 6 is a view for explaining the release method in the method of FIG. 3, 3 is a view for explaining the variable bending method.

도 3을 참조하면, 연약지반 개량 시스템을 이용하여 특정 지역(구조물이 시공될 지역)의 지반을 개량함에 있어, 굴착용 베이스머신(180)의 오거(Auger)(190)를 이용하여 설정된 지점을 굴착한다(단계 S100). 일 실시예에서, 모래/자갈 사일로(120)는 모래 사일로(121) 및 자갈 사일로(122)를 포함한다. Referring to FIG. 3, in the course of improving the ground of a specific area (area where a structure is to be constructed) using the soft ground improvement system, a set point is set by using an auger 190 of the excavation base machine 180 (Step S100). In one embodiment, the sand / gravel silo 120 includes a sand silo 121 and a gravel silo 122.

굴착용 베이스머신(180)에 의해 원하는 굴착심도로 굴착이 완료되면, 해당 굴착공에 모래, 자갈, 시멘트 및 물을 포함하는 콘크리트를 주입하여 DCX(Deep plain concrete Column eXpress)공법에 의한 기초 구조물의 기둥을 형성한다(단계 S200). 일 실시예에서, 기초 구조물의 기둥은 일정간격으로 반복되도록 시공될 수 있다.After completion of the excavation at a desired excavation depth by the excavation base machine 180, concrete containing sand, gravel, cement and water is injected into the excavation hole to form a concrete structure of a foundation structure by DCX (Deep Plain Concrete Column eXpress) Thereby forming a column (step S200). In one embodiment, the pillars of the foundation structure can be constructed to be repeated at regular intervals.

형성된 기둥의 상부에 계획고에 대응하도록 높이가 조절된 기초 시공 구조물을 시공한다(단계 S300). 일 실시예에서, 계획고의 조절은 DCX공법의 방출법(Release Method) 또는 가변두법(Variable-Head Method)에 의해 조절될 수 있다. 예를 들어, 방출법은 기둥 시공 후 콘크리트 타설에 의한 슬라브(20) 시공으로 계획고를 조절할 수 있다. 다른 예로, 가변두법은 기둥(10)의 상부에 가변캡(30)을 시공하여 계획고를 조절할 수 있다.A foundation construction having a height adjusted to correspond to the planned height is constructed on the top of the formed column (step S300). In one embodiment, the adjustment of the planning height can be controlled by the Release Method or the Variable-Head Method of the DCX method. For example, the release method can be adjusted by constructing a slab (20) by pouring concrete after pillar construction. As another example, the variable roofing method can adjust the planned height by installing the variable cap 30 on the top of the column 10.

도 4를 참조하면, 해당 굴착공을 굴착함에 있어, 베이스머신(180)의 오거(190)를 통해 물을 주입하면서 해당 굴착공을 굴착할 수 있다(단계 S101). 일 실시예에서, 굴착시 주입되는 물은 굴착된 흙, 모래 및 자갈 등과 섞일 수 있으므로, 굴착 시 발생되는 물, 흙, 모래, 자갈 등은 흡입구(191)를 통해 흡입되어 토운선으로 이송할 수 있다.4, in excavating the excavation hole, the excavation hole can be excavated while injecting water through the auger 190 of the base machine 180 (step S101). In one embodiment, the water injected during excavation can be mixed with the excavated soil, sand and gravel, so that water, soil, sand, gravel, etc. generated during excavation can be sucked through the suction port 191 and transferred to the toe line .

베이스머신(180)의 오거(190)를 이용하여 설정된 지점을 굴착하면서 굴착한계도달여부를 확인할 수 있다(단계 S102).It is possible to confirm whether or not the excavation limit is reached while excavating the set point using the auger 190 of the base machine 180 (step S102).

일 실시예에서, 확인결과, 굴착한계에 도달하면 해당 굴착심도가 설정심도인지를 확인할 수 있다(단계 S103). 예를 들어, 해당 굴착심도가 설정심도인 경우(단계 S104), 해당 굴착지점의 지질정보를 확인할 수 있다(단계 S105). 다른 예로, 해당 굴착심도가 설정심도가 아닌 경우(단계 S104), 굴착심도를 설정심도에 대응되도록 하는 보정굴착을 수행할 수 있다(단계 S106).In one embodiment, when the excavation limit is reached, it can be confirmed whether the excavation depth is the set depth (step S103). For example, if the excavation depth is the set depth (step S104), the geological information of the excavation point can be confirmed (step S105). As another example, if the corresponding excavation depth is not the set depth (step S104), the excavation depth can be corrected to correspond to the set depth (step S106).

일 실시예에서, 해당 굴착지점의 지질정보가 확인되면, 해당 지질정보에 기초하여 모래 및 자갈의 주입량 또는 비율을 산출할 수 있고(단계 S107), 산출된 모래 및 자갈의 주입량 또는 비율에 대응하여 모래 사일로(121), 자갈 사일로(122), 물공급펌프(130) 및 시멘트 사일로(140) 중 적어도 하나의 동작을 제어할 수 있다(단계 S107).In one embodiment, when the geological information at the corresponding excavation point is confirmed, the amount or the ratio of the sand and the gravel can be calculated based on the geological information (step S107), and the calculated amount or proportion of the sand and gravel The operation of at least one of the sand silo 121, the gravel silo 122, the water supply pump 130, and the cement silo 140 can be controlled (step S107).

도 5를 참조하면, 기초 구조물의 장주 시공이 완료되면, 해당 기초 시공 구조물의 계획고를 확인할 수 있고(단계 S301), 확인된 계획고 조절을 위한 시공방법을 확인할 수 있다(단계 S302).Referring to FIG. 5, when the long construction of the foundation structure is completed, the plan height of the foundation construction structure can be confirmed (step S301), and the construction method for the confirmed plan height adjustment can be confirmed (step S302).

일 실시예에서, 확인된 계획고 조절 시공방법이 방출법인 경우(단계 S302), 도 6에 나타난 바와 같이 시공된 기둥(10)(단계 S303)의 상부에 콘크리트 타설(단계 S304)에 의해 슬라브(20)를 형성(단계 S305)할 수 있다. 예를 들어, 방출법은 슬라브(20)의 두께를 조절하여 콘크리트 타설함으로써, 계획고를 조절할 수 있다.In one embodiment, if the identified planned height adjustment construction method is the discharge method (step S302), a concrete slab (step S304) is placed on top of the applied column 10 (step S303) 20) (step S305). For example, the discharge method can adjust the height of the slab 20 by adjusting the thickness of the slab 20 to pour the concrete.

다른 일 실시예에서, 슬라브(20)를 시공하지 않고, 기둥(10)만으로 시공하는 경우, 또는 보다 높은 정밀도의 계획고 조절이 필요한 경우, 또는 슬라브(20) 시공으로 인한 공사비 증가를 방지하기 위한 경우에는, 계획고 조절 및 기둥(10)의 상부 파손을 방지하기 위하여 도 7에 나타난 바와 같이 가변캡 설치장치에 의해 시공되는 가변캡(30)을 이용하여 계획고를 조절할 수 있다.In another embodiment, when the slab 20 is not installed, only the column 10 is used, or a higher precision plan height adjustment is required, or in order to prevent an increase in the construction cost due to the slab 20 construction In order to prevent the upper limit of the height of the column 10 from being adjusted, the plan height can be adjusted by using the variable cap 30 installed by the variable cap installation apparatus as shown in FIG.

이를 보다 상세히 살펴보면, 확인된 계획고 조절 시공방법이 가변두법인 경우(단계 S302), 기둥 시공 후(단계 S306) 적어도 하나의 높이조절용 단위블럭을 적층하여(단계 S307) 가변캡(30)을 설치할 수 있다(단계 S308). 예를 들어, 기둥(10)의 상부에 결합구(31)를 설치하고, 결합구(31)의 상부에 높이 조절을 위한 단위블럭(32)을 적층한 후, 마감구(33)를 설치하여 장주(10)의 상단부 파손을 방지하도록 할 수 있다. 여기서, 결합구(31)와 단위블럭(32) 및 마감구(33)에는 각각 기둥(10)의 철근(11)에 대응하는 관통공(미부호)이 형성될 수 있다.In more detail, if the determined height adjustment method is variable (step S302), at least one height adjusting unit block is stacked after the column is constructed (step S306) (step S307) to install the variable cap 30 (Step S308). For example, a coupling hole 31 is provided on the top of the column 10, a unit block 32 for height adjustment is stacked on the coupling hole 31, and a finishing hole 33 is provided It is possible to prevent breakage of the upper end portion of the longitudinal groove 10. Through holes (not shown) corresponding to the reinforcing bars 11 of the column 10 may be formed in the coupling hole 31, the unit block 32 and the finishing hole 33, respectively.

이상에서 본 발명에 의한 이중오거의 이용 및 현장타설무근콘크리트 기둥의 형성에 의한 연약지반 개량 공법 및 시스템에 대하여 설명하였다. 이러한 본 발명의 기술적 구성은 본 발명이 속하는 기술분야의 당업자가 본 발명의 그 기술적 사상이나 필수적 특징을 변경하지 않고서 다른 구체적인 형태로 실시될 수 있다는 것을 이해할 수 있을 것이다.In the foregoing, the use of the double auger according to the present invention and the method of improving the soft ground by the formation of the concrete pillar in the field have been described. It will be understood by those skilled in the art that the technical features of the present invention may be embodied in other specific forms without departing from the spirit or essential characteristics thereof.

그러므로 이상에서 기술한 실시예들은 모든 면에서 예시적인 것이며, 한정적인 것이 아닌 것으로서 이해되어야 하고, 본 발명의 범위는 전술한 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지는 것이므로, 특허청구범위의 의미 및 범위 그리고 그 등가 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.
Therefore, it is to be understood that the embodiments described above are intended to be illustrative, and not restrictive, in all respects, and that the scope of the invention is indicated by the appended claims rather than the foregoing description, And all equivalents and modifications that come within the meaning and range of equivalency of the claims are to be embraced within their scope.

100 : 연약지반 개량 시스템
110 : 모래/자갈 공급장치 120 : 모래/자갈 사일로
121 : 모래 사일로 122 : 자갈 사일로
130 : 물공급펌프 140 : 시멘트 사일로
150 : 콘크리트용 믹서 160 : 콘크리트용 교반기
170 : 콘크리트용 펌프 180 : 베이스머신
190 : 이중오거
100: Soft ground improvement system
110: sand / gravel supply device 120: sand / gravel silo
121: Sandy silo 122: Gravel silo
130: Water supply pump 140: Cement silo
150: Mixer for concrete 160: Mixer for concrete
170: Concrete pump 180: Base machine
190: Double Auger

Claims (7)

현장타설무근콘크리트 기둥을 형성하는 공법(DCX공법: Deep plain concrete Column eXpress)을 기반으로 시공되는 기초 구조물의 기둥을 형성하기 위한 모래 및 자갈을 각각 분리하여 공급하는 모래/자갈 공급장치;
상기 모래/자갈 공급장치에 의해 각각 분리되어 공급되는 모래 및 자갈을 각각 분리하여 저장하고, 상기 기초 구조물이 시공되는 설정심도의 지질정보에 기초하여 모래 및 자갈 중 적어도 하나를 공급하는 모래/자갈 사일로;
상기 기초 구조물이 시공되는 설정심도의 지질정보에 기초하여 물을 공급하는 물공급펌프;
상기 기초 구조물이 시공되는 설정심도의 지질정보에 기초하여 시멘트를 공급하는 시멘트 사일로;
상기 모래/자갈 사일로, 물공급펌프 및 시멘트 사일로부터 공급되는 모래, 자갈, 시멘트 및 물을 혼합하는 콘크리트용 믹서; 및
상기 기초 구조물이 시공될 위치를 굴착하고, 굴착 시 발생되는 산물을 외부로 배출하는 베이스머신;을 포함하며,
상기 베이스머신은 이중오거를 포함하되, 상기 이중오거는 케이싱과, 상기 케이싱 내에 배치되며, 내부에 중공이 형성된 오거와, 상기 오거의 하부에 형성되며, 상기 물공급펌프로부터 공급되는 물이 토출되는 토출구와, 상기 오거 상부의 로드에 삽입 결합되되, 내주면에 베어링이 구비되어 상기 로드의 회전에 연동되지 않고 위치 고정되는 고정구 및 상기 케이싱 내면과 상기 오거 사이에 배치되되, 상기 고정구에 결합 고정되며, 상기 토출구에서 토출되는 물 및 굴착 시 발생되는 부산물을 흡입하는 흡입구를 포함하고,
상기 오거의 종단부에는 굴착용 스크류가 구비되고, 상기 토출구와 연통되도록 내부에 중공이 형성되어 상기 오거에 의한 굴착 시 상기 물공급펌프로부터 공급된 물은 상기 오거의 중공을 통해 토출구로 배출되며,
상기 시공된 기초 구조물의 기둥 상부에,
계획고에 기초하여 상기 기초 구조물의 높이를 조절하기 위한 가변캡을 시공하는 가변캡 설치장치를 더 포함하되,
상기 가변캡 설치장치는,
장주의 상부에 결합설치되는 중공의 캡형 결합구;
상기 결합구의 상부에 적층설치되는 적어도 하나의 높이조절용 단위블럭; 및
상기 단위블럭의 상부에 고정설치되는 마감구를 순차적으로 적층하도록 구성 및 동작되는 것을 특징으로 하는 이중오거의 이용 및 현장타설무근콘크리트 기둥의 형성을 위한 연약지반 개량 시스템에 의하여,
a) 설정된 지점을 굴착하고, 해당 굴착심도가 설정심도에 도달하면, 해당 설정심도에 모래, 자갈, 시멘트 및 물의 공급을 위해 모래/자갈 사일로, 시멘트 사일로 및 물공급펌프를 동작시키는 단계;
b) 해당 굴착공에 미리 설정된 모래, 자갈, 시멘트 및 물을 포함하는 콘크리트를 주입하여 현장타설무근콘크리트 기둥을 형성하는 공법(DCX공법: Deep plain concrete Column eXpress)에 의한 기초 구조물의 기둥을 형성하는 단계; 및
c) 상기 형성된 기둥의 상부에 계획고에 대응하도록 높이가 조절된 기초 시공 구조물을 시공하는 단계를 포함하고,
상기 단계 a)는,
a-1) 상기 설정된 지점을 굴착하면서 굴착한계도달여부를 확인하는 단계;
a-2) 상기 굴착한계도달여부의 확인결과, 굴착한계에 도달하면 해당 굴착심도가 설정심도인지를 확인하는 단계;
a-3) 상기 굴착한계도달여부의 확인결과, 해당 굴착심도가 설정심도인 경우, 해당 굴착지점의 지질정보를 확인하여 모래, 자갈, 시멘트 및 물의 주입량 또는 비율을 산출하는 단계; 및
a-4) 상기 산출된 모래, 자갈, 시멘트 및 물의 주입량 또는 비율에 대응하여 모래 사일로, 자갈 사일로, 시멘트 사일로 및 물공급펌프 중 적어도 하나를 동작시키는 단계를 포함하며,
상기 단계 c)는,
c-1) 상기 기초 시공 구조물의 계획고를 확인하는 단계;
c-2) 상기 계획고 조절을 위한 시공방법을 확인하는 단계;
c-3) 상기 확인된 계획고 조절 시공방법이 방출법인 경우, 상기 기둥 시공 후 콘크리트 타설에 의한 슬라브를 형성하는 단계를 포함하고, 상기 확인된 계획고 조절 시공방법이 가변두법인 경우, 상기 기둥 시공 후 적어도 하나의 높이조절용 단위블럭을 적층하여 가변캡을 설치하는 단계를 포함하는 것을 특징으로 하는 이중오거의 이용 및 현장타설무근콘크리트 기둥의 형성에 의한 연약지반 개량 공법.
A sand / gravel supply system for separating and supplying sand and gravel to form a column of a foundation structure to be installed on the basis of a method (DCX method: Deep plain concrete column eXpress) for forming a spot-free concrete column;
A sand / gravel silo for supplying at least one of sand and gravel on the basis of geological information of set depth to which the foundation structure is installed, ;
A water supply pump for supplying water based on geological information at a set depth at which the foundation structure is installed;
A cement silo for supplying cement based on geological information at a predetermined depth at which the foundation structure is installed;
A concrete mixer for mixing sand, gravel, cement and water supplied from the sand / gravel silo, water supply pump and cement silo; And
And a base machine for excavating a site where the foundation structure is to be installed and discharging the product generated during excavation to the outside,
The base machine includes a double auger, wherein the double auger includes a casing, an auger disposed in the casing, the auger having a hollow formed therein, and water formed at a lower portion of the auger, A fixture which is inserted into the rod of the upper portion of the auger and has a bearing on an inner circumferential surface thereof and is fixed in position without being interlocked with the rotation of the rod, And a suction port for sucking water discharged from the discharge port and by-products generated during excavation,
A hollow is formed in the end portion of the auger so as to communicate with the discharge port and water supplied from the water supply pump is discharged to the discharge port through the hollow of the auger when excavated by the auger,
On the pillar of the constructed foundation structure,
Further comprising: a variable cap mounting device for mounting a variable cap for adjusting the height of the foundation structure based on the plan height,
The variable cap installation device includes:
A hollow cap-type coupling unit coupled to an upper portion of the longitudinal shaft;
At least one height-adjusting unit block stacked on top of the coupling means; And
And a finishing tool fixedly installed on the upper portion of the unit block are sequentially stacked. By using the double auger and the soft ground improvement system for forming the on-site reinforced concrete column,
a) operating a sand / gravel silo, cement silo and water supply pump for the supply of sand, gravel, cement and water to the set depth when the set point is drilled and the depth of the drilling reaches the set depth;
b) Forming a pillar of foundation structure by DCX method (Deep plain concrete Column eXpress) by injecting concrete containing sand, gravel, cement and water set in advance into the excavation hole step; And
c) constructing a base construction having a height adjusted to correspond to a plan height on top of the formed column,
The step a)
a-1) confirming whether the excavation limit is reached while excavating the set point;
a-2) confirming whether the excavation depth is a set depth when the excavation limit is reached as a result of checking whether the excavation limit is reached;
a-3) calculating the injection amount or ratio of sand, gravel, cement, and water by confirming the geological information of the excavation site when the excavation depth is the set depth as a result of checking whether or not the excavation limit is reached; And
a-4) operating at least one of a sand silo, a gravel silo, a cement silo, and a water supply pump corresponding to the amount or ratio of the calculated amounts of sand, gravel, cement and water,
The step c)
c-1) confirming the planned height of the foundation construction;
c-2) confirming the construction method for the height adjustment;
c-3) forming the slab by pouring the concrete after the column is installed, if the confirmed high-regulation construction method is a discharge method, and if the confirmed high-regulation construction method is variable, And a step of stacking at least one height-adjusting unit block after installation to provide a variable cap. The method of improving the soft ground by using a double auger and forming a concrete column in a field installation.
삭제delete 삭제delete 삭제delete 현장타설무근콘크리트 기둥을 형성하는 공법(DCX공법: Deep plain concrete Column eXpress)을 기반으로 시공되는 기초 구조물의 기둥을 형성하기 위한 모래 및 자갈을 각각 분리하여 공급하는 모래/자갈 공급장치;
상기 모래/자갈 공급장치에 의해 각각 분리되어 공급되는 모래 및 자갈을 각각 분리하여 저장하고, 상기 기초 구조물이 시공되는 설정심도의 지질정보에 기초하여 모래 및 자갈 중 적어도 하나를 공급하는 모래/자갈 사일로;
상기 기초 구조물이 시공되는 설정심도의 지질정보에 기초하여 물을 공급하는 물공급펌프;
상기 기초 구조물이 시공되는 설정심도의 지질정보에 기초하여 시멘트를 공급하는 시멘트 사일로;
상기 모래/자갈 사일로, 물공급펌프 및 시멘트 사일로부터 공급되는 모래, 자갈, 시멘트 및 물을 혼합하는 콘크리트용 믹서; 및
상기 기초 구조물이 시공될 위치를 굴착하고, 굴착 시 발생되는 산물을 외부로 배출하는 베이스머신;을 포함하며,
상기 베이스머신은 이중오거를 포함하되, 상기 이중오거는 케이싱과, 상기 케이싱 내에 배치되며, 내부에 중공이 형성된 오거와, 상기 오거의 하부에 형성되며, 상기 물공급펌프로부터 공급되는 물이 토출되는 토출구와, 상기 오거 상부의 로드에 삽입 결합되되, 내주면에 베어링이 구비되어 상기 로드의 회전에 연동되지 않고 위치 고정되는 고정구 및 상기 케이싱 내면과 상기 오거 사이에 배치되되, 상기 고정구에 결합 고정되며, 상기 토출구에서 토출되는 물 및 굴착 시 발생되는 부산물을 흡입하는 흡입구를 포함하고,
상기 오거의 종단부에는 굴착용 스크류가 구비되고, 상기 토출구와 연통되도록 내부에 중공이 형성되어 상기 오거에 의한 굴착 시 상기 물공급펌프로부터 공급된 물은 상기 오거의 중공을 통해 토출구로 배출되며,
상기 시공된 기초 구조물의 기둥 상부에,
계획고에 기초하여 상기 기초 구조물의 높이를 조절하기 위한 가변캡을 시공하는 가변캡 설치장치를 더 포함하되,
상기 가변캡 설치장치는,
장주의 상부에 결합설치되는 중공의 캡형 결합구;
상기 결합구의 상부에 적층설치되는 적어도 하나의 높이조절용 단위블럭; 및
상기 단위블럭의 상부에 고정설치되는 마감구를 순차적으로 적층하도록 구성 및 동작되는 것을 특징으로 하는 이중오거의 이용 및 현장타설무근콘크리트 기둥의 형성을 위한 연약지반 개량 시스템.
A sand / gravel supply system for separating and supplying sand and gravel to form a column of a foundation structure to be installed on the basis of a method (DCX method: Deep plain concrete column eXpress) for forming a spot-free concrete column;
A sand / gravel silo for supplying at least one of sand and gravel on the basis of geological information of set depth to which the foundation structure is installed, ;
A water supply pump for supplying water based on geological information at a set depth at which the foundation structure is installed;
A cement silo for supplying cement based on geological information at a predetermined depth at which the foundation structure is installed;
A concrete mixer for mixing sand, gravel, cement and water supplied from the sand / gravel silo, water supply pump and cement silo; And
And a base machine for excavating a site where the foundation structure is to be installed and discharging the product generated during excavation to the outside,
The base machine includes a double auger, wherein the double auger includes a casing, an auger disposed in the casing, the auger having a hollow formed therein, and water formed at a lower portion of the auger, A fixture which is inserted into the rod of the upper portion of the auger and has a bearing on an inner circumferential surface thereof and is fixed in position without being interlocked with the rotation of the rod, And a suction port for sucking water discharged from the discharge port and by-products generated during excavation,
A hollow is formed in the end portion of the auger so as to communicate with the discharge port and water supplied from the water supply pump is discharged to the discharge port through the hollow of the auger when excavated by the auger,
On the pillar of the constructed foundation structure,
Further comprising: a variable cap mounting device for mounting a variable cap for adjusting the height of the foundation structure based on the plan height,
The variable cap installation device includes:
A hollow cap-type coupling unit coupled to an upper portion of the longitudinal shaft;
At least one height-adjusting unit block stacked on top of the coupling means; And
And a finishing tool fixedly installed on the upper portion of the unit block are sequentially stacked. The system for improving the soft ground for use of the double auger and the formation of the unfilled concrete column in the field.
삭제delete 삭제delete
KR1020120003291A 2012-01-11 2012-01-11 Poor ground improvement method and system by forming cast-in-place plain concrete column and using separated doughnut auger having suction duct KR101401645B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
KR1020120003291A KR101401645B1 (en) 2012-01-11 2012-01-11 Poor ground improvement method and system by forming cast-in-place plain concrete column and using separated doughnut auger having suction duct
PCT/KR2012/002995 WO2013105705A1 (en) 2012-01-11 2012-04-19 Method and system for improving weak soil by using separated donut auger (sda) having intake port mounted thereon and through forming unreinforced concrete column poured onsite

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120003291A KR101401645B1 (en) 2012-01-11 2012-01-11 Poor ground improvement method and system by forming cast-in-place plain concrete column and using separated doughnut auger having suction duct

Publications (2)

Publication Number Publication Date
KR20130082219A KR20130082219A (en) 2013-07-19
KR101401645B1 true KR101401645B1 (en) 2014-06-02

Family

ID=48781633

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120003291A KR101401645B1 (en) 2012-01-11 2012-01-11 Poor ground improvement method and system by forming cast-in-place plain concrete column and using separated doughnut auger having suction duct

Country Status (2)

Country Link
KR (1) KR101401645B1 (en)
WO (1) WO2013105705A1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100840191B1 (en) * 2007-12-24 2008-06-23 노윤근 The bridge section expansion method of construction for which steel synthetic concrete steel pipe and this were used
JP2009275378A (en) * 2008-05-13 2009-11-26 Takenaka Komuten Co Ltd Fiber-reinforced cement-based soil improvement method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4480819B2 (en) * 1999-10-08 2010-06-16 大平洋機工株式会社 Concrete manufacturing method and concrete manufacturing apparatus
JP4148842B2 (en) * 2003-05-30 2008-09-10 佐藤工業株式会社 Ground improvement method
KR20090080598A (en) * 2008-01-22 2009-07-27 주식회사 스마텍엔지니어링 Concrete Pile and Method for Constructing Concrete Pile
KR100940802B1 (en) * 2009-04-29 2010-02-05 최성희 The deep mixing method of soil stabilization for which a hardener for weak soil stabilization, this mix processor and this were used

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100840191B1 (en) * 2007-12-24 2008-06-23 노윤근 The bridge section expansion method of construction for which steel synthetic concrete steel pipe and this were used
JP2009275378A (en) * 2008-05-13 2009-11-26 Takenaka Komuten Co Ltd Fiber-reinforced cement-based soil improvement method

Also Published As

Publication number Publication date
KR20130082219A (en) 2013-07-19
WO2013105705A1 (en) 2013-07-18

Similar Documents

Publication Publication Date Title
CN202337976U (en) In-hole impact high-pressure jet grouting equipment
AU2021106928A4 (en) Construction method for excavation of deep pit with triaxial mixing pile waterstop curtains and rotary bored cast-in-place pile supports
CN102296630A (en) Construction method of long-screw high-pressure mix jetting cement diaphragm wall
CN106592658B (en) Tear down and build the foundation construction method of house foundation
JP4520913B2 (en) Ground improvement method and existing structure foundation reinforcement method
CN107587502B (en) Construction method for rotary drilling hole-forming pressure-grouting cement soil occlusion curtain pile
KR102097919B1 (en) Melioration wall and replacement wall mixed retaining wall construction method
JP5075090B2 (en) Cast-in-place pile construction method and cast-in-place pile
KR101401645B1 (en) Poor ground improvement method and system by forming cast-in-place plain concrete column and using separated doughnut auger having suction duct
KR20100095070A (en) Method and apparatus for improving ground using cement grouting
CN106192987A (en) A kind of construction method that stake periphery is crushed geology reinforcing
CN108978742A (en) One kind cutting stake forced-landing tilt correcting structure, method
CN113309128B (en) Construction method of dumbbell-shaped cement soil curtain pile in peat soil stratum
CN105625301A (en) Soft foundation processing construction technology
CN102979095A (en) Method for constructing triaxial cement-soil mixing piles in ultra-hard soil layer
JP2005282043A (en) Earth retaining wall reinforcing method
CN102477737A (en) Construction method of cement fly-ash gravel (CFG) pile on collapsible loess foundation of highway
KR102260596B1 (en) Site Construction Method Of Base Top Pile For Ground Reinforcement
CN214423369U (en) Deep silt geology foundation ditch retaining structure
KR20130102254A (en) Front edge expanded bulb constructing system and method
JP2009138332A (en) Creation method for permeable layer
KR20160109395A (en) Agitating road for excavating using soil earth cement mixing method and mixing agitator using the same
JP2006312866A (en) Method for replacing and constructing column, and replaced column
CN106638621A (en) Implanting method of prefabricated plate pile
CN207750041U (en) Four axis twist bits

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee