KR101370981B1 - Cage rail climbing system - Google Patents

Cage rail climbing system Download PDF

Info

Publication number
KR101370981B1
KR101370981B1 KR1020110050072A KR20110050072A KR101370981B1 KR 101370981 B1 KR101370981 B1 KR 101370981B1 KR 1020110050072 A KR1020110050072 A KR 1020110050072A KR 20110050072 A KR20110050072 A KR 20110050072A KR 101370981 B1 KR101370981 B1 KR 101370981B1
Authority
KR
South Korea
Prior art keywords
cage
rail
lifting
interlayer
fixing
Prior art date
Application number
KR1020110050072A
Other languages
Korean (ko)
Other versions
KR20120131710A (en
Inventor
권종규
Original Assignee
권종규
주식회사 근하기공
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 권종규, 주식회사 근하기공 filed Critical 권종규
Priority to KR1020110050072A priority Critical patent/KR101370981B1/en
Publication of KR20120131710A publication Critical patent/KR20120131710A/en
Application granted granted Critical
Publication of KR101370981B1 publication Critical patent/KR101370981B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/30Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
    • E04G3/32Hoisting devices; Safety devices
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Types And Forms Of Lifts (AREA)

Abstract

본 발명은 타워 크레인을 사용하지 않고 레일과 슈에 의해 연결된 케이지를 승강 및 하강시킬 수 있는 케이지 레일 클라이밍 시스템을 개시한다.
본 발명은 케이지의 양측에 구비된 레일과; 시공 중인 건축물에 고정되며, 상기 레일을 상기 건축물에 근접시켜 지지하여 낙하를 방지하는 슈와; 상기 케이지의 무게중심선상에 인양고리가 형성되며, 상기 인양고리에 와이어가 탈착되어 상기 레일이 슈에 연결된 상태로 케이지를 승, 하강 시키는 권양기와; 상기 권양기를 층간에 걸쳐 고정시키는 층간 고정구로 구성된 것이며,
이에 따라 본 발명은 케이지가 항시 슈와 레일로 고정되어 있기 때문에 풍압으로 인한 흔들림과 낙하의 위험성을 감소시키므로 별도의 안전시설이 불필요하게 되며, 자유롭게 케이지를 승강 및 하강시키는 것이 가능하여 골조 공사의 스케줄과 상관없이 독립적으로 골조 공사가 끝난 다수의 층에 대하여 마감 공사를 실시할 수 있으므로 효과적인 인력 운영이 가능할 뿐만 아니라 공사 기간도 획기적으로 단축시킬 수 있는 유용한 효과를 얻을 수 있다.
The present invention discloses a cage rail climbing system capable of lifting and lowering a cage connected by a rail and a shoe without using a tower crane.
The present invention is a rail provided on both sides of the cage; A shoe fixed to the building under construction and supporting the rail in close proximity to the building to prevent falling; Lifting ring is formed on the center of gravity line of the cage, the lifting device is detachable wire to the lifting ring for lifting and lowering the cage with the rail connected to the shoe; It is composed of an interlayer fixture for fixing the winch over the interlayer,
Accordingly, the present invention, because the cage is always fixed to the shoe and the rail to reduce the risk of shaking and falling due to wind pressure, no additional safety facilities are required, it is possible to freely lift and lower the cage, the schedule of frame construction Irrespective of this, the finishing work can be carried out on a large number of floors that have been independently framed, which enables effective manpower operation and a significant reduction in the construction period.

Description

케이지 레일 클라이밍 시스템{CAGE RAIL CLIMBING SYSTEM}Cage RAIL CLIMBING SYSTEM

본 발명은 케이지 레일 클라이밍 시스템에 관한 것으로 특히 건축물의 외벽 마감 작업을 위한 케이지가 레일과 슈로 연결된 상태에서 권양기로 승강 및 하강시킬 수 있어서, 타워 크레인을 사용하지 않고 작업 진행 상황에 따라 케이지만을 단독으로 인양할 수 있으며, 케이지를 다양한 마감 작업용으로 사용할 수 있도록 하는 케이지 레일 클라이밍 시스템에 관한 것이다.
The present invention relates to a cage rail climbing system, and in particular, the cage for finishing the outer wall of the building can be lifted and lowered by a winch in the state connected with the rail and the shoe, so that only the cage alone according to the work progress without using a tower crane Cage rail climbing systems that can be lifted and allow cages to be used for various finishing applications.

주지하는 바와 같이, 종래에 운영되는 마감 공사용 가설 자재는 곤도라, 워킹 플랫폼, 케이지 등이 있으며, 이러한 대부분의 마감 공사용 가설 자재는 골조 공사가 12층 이상 진행된 후, 또는 골조 공사가 완료된 후에나 작업이 가능하였으며, 이로 인하여 마감 공사의 시작 시기가 늦어져 공사기간이 증가되는 단점이 있다.As is well known, conventionally installed temporary construction materials include gondolas, working platforms, cages, etc., and most of these temporary construction temporary materials can be worked after framing work is performed more than 12 stories or after the completion of framing work. As a result, the start time of the finishing work is delayed, resulting in an increase in the construction period.

이뿐만 아니라 곤도라나 워킹 플랫폼의 경우 공종별로 한층씩 작업을 실시하여야 하므로 공사 기간이 길어지게 되며, 일정 층 간격 마다 안전망 등과 같은 별도의 안전시설을 반드시 설치하여야 하므로 설비비용 및 시공, 해체를 위한 추가적인 인력, 비용, 시간이 소요되는 문제점이 있다.In addition, as the gondola and walking platform have to work one by one for each type of construction, the construction period becomes longer, and additional safety facilities such as safety net must be installed at regular intervals. There is a problem of manpower, cost, and time.

이러한 문제점을 해결하기 위하여 골조 공사를 위해 사용되는 거푸집(갱폼)의 하단에 안전발판이 구비된 케이지를 연결하여 다음 층의 골조 공사를 위해 승강되는 거푸집과 함께 상기 케이지가 승강 되도록 하므로 골조 공사와 마감 공사가 동시에 이루어지도록 할 수 있으나 골조 공사에 비하여 상대적으로 공사 시간이 짧은 마감 공사는 골조 공사가 끝나 다음 층으로 거푸집이 승강되기 전까지 케이지가 다음 층으로 승강되지 않아 다음 층의 작업을 할 수 없게 되어 비효율적으로 인력 운영이 이루어지게 되는 문제점이 발생하며, 거푸집의 무게를 증가 시키고, 강풍으로부터 케이지가 흔들리는 것을 방지하기 위하여 케이지도 거푸집과 같은 방법으로 시공 중인 벽체에 고정 볼트 등으로 고정하여야 하므로 거푸집의 승강 시마다 고정 볼트의 해체 및 조립 공정이 2배로 증가하게 되어 골조 공사의 시공기간을 증가 시키게 되는 문제점이 있다.In order to solve this problem, by connecting the cage with a safety scaffold at the bottom of the formwork (gangform) used for framing construction so that the cage is elevated with the formwork being elevated for the next floor framing construction, so that the frame construction and finishing The construction can be done at the same time, but the finishing work, which is relatively shorter than the construction work, will not be able to work on the next floor because the cage will not be raised to the next floor until the formwork is lifted to the next floor after the construction work is completed. The problem of inefficient manpower operation occurs, and in order to increase the weight of the formwork and to prevent the cage from swinging from the strong wind, the cage is also fixed to the wall under construction in the same way as the formwork with the fixing bolts. Dismantling of Shimada Fixing Bolt The assembly process is the two-fold increase, there is a problem that increases the construction period of the frame construction.

또한 이러한 문제점을 해소하고자 거푸집과 케이지를 분리하여 각각 크레인 등으로 인양한다 하더라도 건축물 전체의 골조공사가 완료되어 거푸집을 완전히 해체한 상태가 아니라면 거푸집이 케이지보다 외벽으로부터 더 많이 돌출되어 있기 때문에 건축물의 최상층보다 높은 타워크레인과 거푸집 아래에 위치한 케이지를 연결하여 인양하게 되면 타워크레인의 케이블이 거푸집에 간섭되어 타워크레인의 케이블이 단선되는 안전사고, 케이지가 낙하되는 낙하사고 등이 발생될 수 있게 되는 문제점이 있다.
In addition, even if the formwork and the cage are separated and lifted with a crane, etc. to solve this problem, unless the formwork is completely dismantled and the structure is completely dismantled, the formwork protrudes more from the outer wall than the cage, so the top floor of the building If the tower crane and the cage located under the formwork are lifted and lifted, the cable of the tower crane interferes with the formwork, causing the safety of disconnection of the cable of the tower crane, and the fall of the cage falling. have.

본 발명의 목적은 이러한 문제점을 해결하기 위하여 골조 공사와 함께 마감 공사를 실시할 수 있도록 하며, 별도의 안전시설을 설치할 필요 없이 풍압에 의한 흔틀림과 위험성을 감소시키고, 동시에 골조 공사의 스케줄과 상관없이 다수 층의 마감작업을 실시할 수 있도록 케이지를 승, 하강 시키는 것이 가능한 케이지 레일 클라이밍 시스템을 제공함에 있다.
The purpose of the present invention is to enable the finishing work in conjunction with the frame work to solve this problem, and to reduce the wobble and risk due to wind pressure without installing a separate safety facility, and at the same time correlate with the schedule of the frame work To provide a cage rail climbing system that allows cages to be raised and lowered to allow for multiple floor finishing operations.

본 발명은 이러한 목적을 달성하기 위하여 케이지의 양측에 구비된 레일과, 시공 중인 건축물에 고정되며, 상기 레일을 상기 건축물에 근접시켜 지지하여 낙하를 방지하는 슈가 구성된 케이지 레일 클라이밍 시스템에 있어서, 상기 슈는 상기 레일의 일면을 건축물에 밀착시키는 회동 가능한 암이 구비된 헤드와, 상기 헤드를 건축물에 고정시키는 고정부재로 구성되며; 상기 레일은 H빔의 형태로 측면에 구비된 통공과, 상기 통공을 기준으로 회동 가능하도록 일단이 고정되되, 타단의 상측은 상기 헤드의 암으로 감싸진 H빔의 전면빔 내측면에 지지되어 상방으로의 회동이 제한되며, 타단의 하측은 상기 암의 상단에 지지되어 케이지의 낙하를 방지하는 낙하방지 부재가 구성되고; 상기 케이지의 무게중심선상에 인양고리가 형성되며, 상기 인양고리에 와이어가 탈착되어 상기 레일이 슈에 연결된 상태로 케이지를 승하강 시키는 권양기와; 상기 권양기를 층간에 걸쳐 고정시키는 층간 고정구가; 구성된 케이지 레일 클라이밍 시스템을 제공하는 것이다.The present invention provides a cage rail climbing system comprising a rail provided on both sides of the cage, and a structure fixed to the building under construction, the shoe to support the rail in close proximity to the building to prevent the fall, the shoe It is composed of a head having a rotatable arm for closely contacting one side of the rail to the building, and a fixing member for fixing the head to the building; The rail has a through hole provided on the side in the form of an H beam, and one end is fixed to be rotatable based on the through hole, and the upper end of the other end is supported by an inner surface of the front beam of the H beam wrapped by the arm of the head and upwards. Rotation to is limited, the lower end of the other end is supported on the upper end of the arm is configured to prevent the falling of the cage; Lifting ring is formed on the center of gravity line of the cage, the lifting device is attached to the lifting ring for lifting and lowering the cage while the rail is connected to the shoe; An interlayer fixture for fixing the winches over the interlayer; It is to provide a configured cage rail climbing system.

또한 본 발명은 일면 양측에 레일이 구비되고 갱폼에 연결된 케이지가, 상기 케이지의 레일을 건축물에 근접시켜 지지하며 낙하를 방지하는 슈에 의해 건축물에 고정된 상태에서 상기 케이지를 인양하는 권양기의 롤러 암이 외벽 밖으로 돌출될 수 있도록 벽체에 인양공이 형성되는 인양공 형성 단계와; 상기 인양공 형성 단계에서 형성된 인양공을 통해 권양기의 롤러 암이 벽체를 통과하여 돌출되도록 권양기가 설치되어 케이지의 인양고리에 연결된 권양기의 와이어를 지지하도록 하며, 인양되는 케이지의 레일과 연결될 슈가 설치되는 설치 단계와; 상기 권양기의 상층 방향으로 돌출된 원뿔형의 고정돌기가 층간 고정구의 고정부에 형성된 원뿔형의 요홈에 삽입 고정되도록 층간 고정구가 세워지며, 층간 고정구의 외관과 내관이 겹쳐져 이어진 정도를 지지핀에 의해 조절되어 층간 고정구의 일단에 형성된 지지부가 상기 권양기가 설치된 층의 상층 하면에 지지되도록 하여 권양기가 층간에 걸쳐 고정되는 권양기 고정 단계와; 상기 권양기 고정 단계에서 고정된 권양기의 와이어가 롤러 암의 지지를 받으며 케이지의 인양고리에 연결되고, 상기 케이지와 연결된 갱폼을 벽체에 고정시키는 갱폼고정구가 제거되며, 갱폼이 벽체로부터 이격되는 인양 준비 단계와; 상기 건축물에 고정된 상기 슈와, 케이지의 레일에 구비된 낙하방지부재에 의해 케이지의 낙하가 방지되는 상태로 상기 권양기에 의해 갱폼을 포함한 케이지가 상층으로 인양되는 인양 단계와; 상기 인양 단계에서 인양이 완료 된 후 상기 갱폼이 벽체 형성을 위해 상기 건축물에 고정되며, 상기 슈에 의해서 케이지가 낙하 방지 되는 상태로 상기 권양기를 고정하고 있는 층간 고정구가 분리고, 상기 권양기가 다음 인양을 위해 이동되는 분리 단계와; 상기 건축물의 벽체 마감 작업 시 상기 인양공 형성 단계에서 형성된 인양공을 막는 인양공 마감 단계로; 구성되거나,In addition, the present invention is provided with a rail on both sides of one side and the cage connected to the gang form, the roller arm of the hoisting machine to lift the cage in a state fixed to the building by a shoe that supports the rail of the cage in close proximity to the building and prevents falling A lifting hole forming step in which a lifting hole is formed in the wall to protrude out of the outer wall; The hoisting machine is installed so that the roller arm of the hoisting machine protrudes through the wall through the lifting hole formed in the lifting hole forming step to support the wire of the hoisting machine connected to the lifting ring of the cage, and the shoe to be connected to the rail of the cage being lifted is installed. An installation step; The interlayer fixture is erected so that the conical fixing protrusion protruding in the upper layer direction of the hoisting machine is inserted into the concave groove formed in the fixing portion of the interlayer fixture, and the degree of overlapping the appearance of the interlayer fixture and the inner tube is controlled by the support pin. A winch holder fixing step in which a support part formed at one end of the interlayer fixture is supported on the upper and lower surfaces of the layer on which the winch is installed; The wire of the winch fixed in the winch fixing step is supported by the roller arm and connected to the lifting ring of the cage, the gangform fixture for fixing the gangform connected to the cage is removed, the lifting preparation step of the gangform is spaced apart from the wall Wow; A lifting step in which a cage including a gang foam is lifted to an upper layer by the winch in a state in which the drop of the cage is prevented by the shoe fixed to the building and the drop preventing member provided on the rail of the cage; After the lifting is completed in the lifting step, the gangform is fixed to the building to form a wall, the interlayer fasteners fixing the winch in the state that the cage is prevented from falling by the shoe is separated, and the winch is lifted next A separation step moved for; Lifting ball finishing step of blocking the lifting hole formed in the lifting hole forming step during the wall finishing work of the building; Configured,

마감 작업이 이루어져야 하는 작업 대상층에 케이지와 연결될 슈와, 상기 케이지를 인양할 권양기가 설치되는 설치 단계와; 상기 권양기의 상방으로 돌출된 원뿔형의 고정돌기가 층간 고정구의 고정부에 형성된 원뿔형의 요홈에 삽입 고정되도록 층간 고정구가 세워지며, 층간 고정구의 외관과 내관이 겹쳐져 이어진 정도를 지지핀에 의해 조절되어 층간 고정구의 일단에 형성된 지지부가 상기 권양기가 설치된 층의 상층 하면에 지지되도록 하여 권양기가 층간에 걸쳐 고정되는 권양기 고정 단계와; 상기 권양기 고정 단계에서 고정된 권양기의 와이어가 케이지의 인양고리에 연결되어 케이지가 상층으로 인양되되, 상기 건축물에 고정된 상기 슈와, 케이지의 레일에 구비된 낙하방지부재에 의해 케이지의 낙하가 방지되며 건축물에 밀착된 상태로 인양되는 인양 단계와; 상기 인양 단계를 통해 인양된 케이지에서 마감 작업이 완료된 후 다음 마감 작업을 위해 상기 슈에 의해서 케이지가 낙하 방지 되는 상태로 상기 권양기를 고정하고 있는 층간 고정구가 분리되고, 상기 권양기를 이동시켜 상기 설치 단계가 반복 실시되도록 하는 분리 단계로; 구성된 케이지 레일 클라이밍 시스템을 제공하는 것이다.
An installation step of installing a shoe to be connected to the cage to the work target layer to be finished, and a winch to lift the cage; The interlayer fixture is erected so that the conical fixing protrusion protruding upward of the hoisting machine is inserted and fixed in the conical groove formed in the fixing portion of the interlayer fixture, and the degree of the overlap between the appearance of the interlayer fixture and the inner tube is controlled by the support pin. A winch holder fixing step in which the support part formed at one end of the fixture is supported on the upper and lower surfaces of the layer on which the winch is installed; The wire of the winch fixed in the winch fixing step is connected to the lifting ring of the cage and the cage is lifted to the upper layer, and the fall of the cage is prevented by the shoe fixed to the building and the drop preventing member provided on the rail of the cage. A lifting step of lifting in a state of being in close contact with the building; After the finishing work is completed in the cage lifted through the lifting step, the interlayer fasteners fixing the winches in a state that the cage is prevented from falling by the shoe for the next finishing work is separated, and the installation step by moving the winches In a separation step such that is repeated; It is to provide a configured cage rail climbing system.

이와 같이 하여 본 발명은 케이지가 항시 슈와 레일로 고정되어 있기 때문에 풍압으로 인한 흔들림과 낙하의 위험성을 감소시키므로 별도의 안전시설이 불필요하게 되며, As such, the present invention reduces the risk of shaking and falling due to wind pressure because the cage is always fixed with a shoe and a rail, so that a separate safety facility is unnecessary.

분리 가능한 층간 고정구에 의해 간편하게 탈착이 가능한 동시에 안전하게 고정되는 권양기와 케이지를 연결하여 상기 레일을 따라 케이지를 자유롭게 승강 및 하강시키는 것이 가능하므로 골조 공사의 스케줄과 상관없이 독립적으로 골조 공사가 끝난 다수의 층에 대하여 마감 공사를 실시할 수 있어서 효과적인 인력 운영이 가능할 뿐만 아니라 공사 기간도 획기적으로 단축시킬 수 있는 유용한 효과가 있다.The detachable interlayer fixture enables easy lifting and lowering of the cage along the rail by connecting the winch and the cage, which can be easily detached and secured, so that multiple floors have been independently framed regardless of the schedule of the framework. As the final construction work can be carried out for not only effective manpower operation but also shortening the construction period has a useful effect.

이러한 케이지와 갱폼이 연결되어 있으면, 갱폼 및 케이지의 인양 시 운영비용이 높고, 운영 시간이 긴 타워 크레인을 사용하지 않고도 간편하며, 안전하고, 저 비용, 단시간에 인양할 수 있게 되는 것이어서 건설 비용 및 공기를 단축할 수 있게 되는 유용한 효과가 있다.
When these cages and gangforms are connected, the lifting costs of the gangforms and cages are simple, safe, low cost, and short, without the need for high operating tower cranes. There is a useful effect of being able to shorten the air.

도1,2는 본 발명에 의한 케이지 레일 클라이밍 시스템의 구체적인 실시예가 발코니 구간에 적용된 구성을 나타내는 사시도.
도3,4는 본 발명에 의한 케이지 레일 클라이밍 시스템의 구체적인 실시예가 슬라브 구간에 적용된 구성을 나타내는 사시도.
도5,6은 본 발명에 의한 케이지 레일 클라이밍 시스템의 구체적인 실시예가 옹벽 구간에 적용된 구성을 나타내는 사시도.
도7,8은 본 발명에 의한 케이지 레일 클라이밍 시스템의 슈와 레일의 구체적인 구성을 예시하는 사시도.
1 and 2 are perspective views showing a configuration in which a cage rail climbing system according to the present invention is applied to a balcony section.
3 and 4 are perspective views showing a configuration in which a cage rail climbing system according to the present invention is applied to a slab section.
5 and 6 are perspective views showing a configuration in which a cage rail climbing system according to the present invention is applied to a retaining wall section.
7 and 8 are perspective views illustrating specific configurations of the shoe and the rail of the cage rail climbing system according to the present invention;

이러한 본 발명을 첨부된 도면을 참조하여 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명하면 다음과 같다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

본 발명에 의한 케이지 레일 클라이밍 시스템의 구체적인 실시예의 전체적인 구성을 도 1 내지 도 6으로 도시하였다.1 to 6 show the overall configuration of a specific embodiment of the cage rail climbing system according to the present invention.

이에서 볼 수 있는 바와 같이, 본 발명에 의한 케이지 레일 클라이밍 시스템은 케이지(100)의 일면 양측에 구비된 레일(120)과, 시공 중인 건축물에 고정되며, 상기 레일(120)을 상기 건축물에 근접시켜 지지하여 낙하를 방지하는 슈(200)가 구성된 케이지(100) 레일(120) 클라이밍 시스템에 있어서,As can be seen from this, the cage rail climbing system according to the present invention is fixed to the rail 120 and the building under construction, provided on both sides of the cage 100, the rail 120 is close to the building In the climbing system of the cage 100, rail 120 of the shoe 200 is configured to support and prevent the fall,

상기 슈(200)는 상기 레일(120)의 일면을 건축물에 밀착시키는 회동 가능한 암(211)이 구비된 헤드(210)와, 상기 헤드(210)를 건축물에 고정시키는 고정부재(220)로 구성되며;The shoe 200 is composed of a head 210 provided with a rotatable arm 211 to closely contact one surface of the rail 120 to the building, and a fixing member 220 to fix the head 210 to the building. Become;

상기 레일(120)은 H빔의 형태로 측면에 구비된 통공(124)과, 상기 통공(124)을 기준으로 회동 가능하도록 일단이 고정되되, 타단의 상측은 상기 헤드(210)의 암(211)으로 감싸진 H빔의 전면빔(122) 내측면에 지지되어 상방으로의 회동이 제한되며, 타단의 하측은 상기 암(211)의 상단에 지지되어 케이지(100)의 낙하를 방지하는 낙하방지 부재(125)가 구성되고;The rail 120 has a through hole 124 provided on the side in the form of an H beam and one end is fixed to be rotatable based on the through hole 124, and an upper side of the other end is an arm 211 of the head 210. Is supported by the inner surface of the front beam 122 of the H-beam wrapped in the upper side is limited to rotate upwards, the lower end of the other end is supported on the upper end of the arm 211 to prevent the fall of the cage 100 Member 125 is configured;

상기 케이지(100)의 무게중심선상에 인양고리(110)가 형성되며, 상기 인양고리(110)에 와이어(311)가 탈착되어 상기 레일(120)이 슈(200)에 연결된 상태로 케이지(100)를 승하강 시키는 권양기(300)와; 상기 권양기(300)를 층간에 걸쳐 고정시키는 층간 고정구(400)가; 구성될 수 있다.The lifting ring 110 is formed on the center of gravity line of the cage 100, and the wire 311 is detached from the lifting ring 110 so that the rail 120 is connected to the shoe 200. Hoist 300 to raise and lower); An interlayer fastener 400 for fixing the winches 300 over an interlayer; Lt; / RTI >

이를 각 구성요소별로 더욱 상세하게 설명하면, Describing this in more detail for each component,

상기 슈(200)의 헤드(210)는 도 7과 도 8에서 보는 바와 같이, 슈(200)의 무게를 줄이고, 헤드(210)가 고정부재(220)와 탈착이 용이하도록 헤드(210)의 일측에 개방홈(213)이 형성되며, 상기 헤드(210)의 양 옆에서 전개 가능하도록 설치되어 상기 레일(120)의 일면을 헤드(210)에 밀착시키는 암(211)과, 상기 암(211)을 헤드(210)에 고정하며, 암(211)과 헤드(210) 사이의 간격을 조절할 수 있는 고정핀(212)이 구성될 수 있다. As shown in FIGS. 7 and 8, the head 210 of the shoe 200 reduces the weight of the shoe 200, and the head 210 of the head 210 is easily detachable from the fixing member 220. An open groove 213 is formed at one side, and is installed to be deployed on both sides of the head 210, and an arm 211 for closely contacting one surface of the rail 120 to the head 210 and the arm 211. ) Is fixed to the head 210, the fixing pin 212 that can adjust the gap between the arm 211 and the head 210 may be configured.

또한 상기 슈(200)의 고정부재(220)는 도 1 내지 도 5에서 도시한 바와 같이, 발코니 구간, 수벽 구간, 슬라브 구간, 옹벽 구간 등 각각의 구간 구조/형태에 적합한 형태로 결합될 수 있도록 상기 헤드(210)와 분리되어 다양한 형태와 결합방법으로 구성될 수 있다. 즉 상기 고정부재(220)는 앵커, 바이스, 층간 고정구(400) 중 어느 하나로, 상기 헤드(210)가 고정되어야 하는 건축물의 발코니 구간, 수벽 구간, 슬라브 구간, 옹벽 구간 각각의 형태에 결합될 수 있도록 상기 헤드(210)와 분리되어 교체될 수 있는 것이며, 특히 슬라브 구간에 상기 슈(200)의 헤드(210)를 고정시키는 고정부재(220)는 상측면에 층간에 걸쳐 고정시키는 층간 고정구(400)의 일단이 삽입되어 고정될 수 있는 고정홈(221)이 형성될 수 있다.In addition, as shown in FIGS. 1 to 5, the fixing member 220 of the shoe 200 may be combined in a form suitable for each section structure / shape, such as a balcony section, a water wall section, a slab section, and a retaining wall section. Separated from the head 210 may be configured in various forms and coupling methods. That is, the fixing member 220 may be coupled to any one of an anchor, a vise, an interlayer fixing device 400, and a balcony section, a water wall section, a slab section, and a retaining wall section of a building in which the head 210 is to be fixed. In order to be separated from the head 210 so that it can be replaced, in particular, the fixing member 220 for fixing the head 210 of the shoe 200 in the slab section is an interlayer fastener 400 for fixing over the interlayer on the upper side One end of the can be inserted into the fixing groove 221 can be fixed.

이와 같이 다양한 건축물의 외벽 구간에 적합하고, 안정적으로 고정되는 슈(200)의 헤드(210)에 암(211)에 의해 고정 지지되는 상기 케이지(100)의 레일(120)은 도 7에서 보는 바와 같이, 케이지(100)에 고정되는 후면빔(121)과 케이지(100)와 이격되어 있는 전면빔(122)이 측면빔(123)으로 연결 형성된 H빔의 형태로 구성되는 것이 바람직하며, 이러한 레일(120)의 전면빔(122)이 상기 슈(200)의 헤드(210)와 암(211) 사이에 위치되어 암(211)에 의해 헤드(210)에 물려 있게 되므로 레일(120)과 함께 케이지(100)가 건축물의 외벽 벽체(10)에 밀착되는 것이고,As shown in FIG. 7, the rails 120 of the cage 100 fixed and supported by the arm 211 to the head 210 of the shoe 200, which are suitable for the outer wall sections of various buildings, are stably fixed. Likewise, the rear beam 121 fixed to the cage 100 and the front beam 122 spaced apart from the cage 100 are preferably configured in the form of an H beam connected by the side beam 123, such a rail. The front beam 122 of 120 is positioned between the head 210 of the shoe 200 and the arm 211 so that the front beam 122 is held by the arm 211 to the head 210 so that the cage together with the rail 120 100 is in close contact with the outer wall wall 10 of the building,

상기 레일(120)의 측면빔(123)에 통공(124)이 형성되고, 상기 통공(124)을 기준으로 회동 가능하도록 일단이 고정되되, 타단의 상측은 상기 헤드(210)의 암(211)으로 감싸진 H빔의 전면빔(122) 내측면에 지지되어 상방으로의 회동이 제한되며, 하방으로 회동되더라도 내부에 구비된 탄성체에 의해 다시 전면빔(122) 내측면에 지지되는 상태로 복원되고, 타단의 하측은 상기 암(211)의 상단에 지지되어 케이지(100)의 낙하를 방지하는 낙하방지 부재(125)가 구성될 수 있어서, 레일(120)과 함께 케이지(100)가 상층으로 인양됨에 따라 레일(120)의 전면빔(122)을 감싸고 있는 슈(200)의 암(211)을 지나칠 때에는 상기 낙하방지 부재(125)가 하방으로 회동되어 상기 암(211)을 통과 시키나, 통과된 낙하방지 부재(125)는 상기 탄성체에 의해 다시 원 위치로 회동되고, 이러한 상태에서 인양이 완료되면 낙하방지 부재(125)의 타단의 상측이 상기 전면빔(122) 내측면에 지지되어 상방으로의 회동이 제한되는 상태에서 타단의 하측이 상기 슈(200)의 암(211)의 상단에 지지되므로 레일(120) 및 케이지(100)의 낙하가 방지되는 것이다.A through hole 124 is formed in the side beam 123 of the rail 120, and one end is fixed to be rotatable based on the through hole 124, and an upper side of the other end is an arm 211 of the head 210. It is supported on the inner surface of the front beam 122 of the H-beam wrapped in the upper direction is limited, and even if rotated downward, restored to the state supported on the inner surface of the front beam 122 by the elastic body provided therein again The lower end of the other end may be supported by the upper end of the arm 211 to prevent the fall prevention member 125 to prevent the fall of the cage 100, the cage 100 with the rail 120 is lifted to the upper layer When passing through the arm 211 of the shoe 200 surrounding the front beam 122 of the rail 120, the drop preventing member 125 is rotated downward to pass through the arm 211, but passed The anti-drop member 125 is rotated back to its original position by the elastic body, and in this state, When the top of the other end of the drop preventing member 125 is completed is supported on the inner surface of the front beam 122, the lower side of the other end is the upper end of the arm 211 of the shoe 200 in a state in which the upward rotation is limited. Since supported by the rail 120 and the cage 100 is to be prevented from falling.

본 발명은 이와 같이 낙하가 방지되며 건축물의 외벽의 벽체(10)에 밀착되어 있는 케이지(100)를 타워크레인으로 인양하는 것이 아닌, 권양기(300)로 케이지(100) 각각을 인양하는 것이다. 즉, 케이지(100)의 양단은 레일(120)과 슈(200)에 의해 낙하가 방지되며 벽체(10)에 밀착된 상태에서 케이지(100)를 용이하게 상층으로 인양하기 위한 가장 바람직한 인양고리(110)의 위치는 도 1, 도 3, 및 도 5로 도시한 바와 같이, 케이지(100)의 세로 방향의 무게중심선상이면 어느 위치에서나 상층으로 힘을 가하면 용이하게 인양할 수 있기 때문에 상기 케이지(100)의 무게중심선상이며, 이러한 케이지(100)의 무게중심선상에 인양고리(110)가 형성되는 것이 바람직한 것이고, 이러한 케이지(100)의 인양고리(110)에 와이어(311)를 연결하여 연결된 와이어(311)를 감거나 풀 수 있는 권양기(300)로 케이지(100)의 낙하가 방지되면서 인양될 수 있는 것이다.In the present invention, the fall is prevented and the cage 100, which is in close contact with the wall 10 of the outer wall of the building, is not lifted by the tower crane, but the cages 100 are lifted by the winches 300. That is, both ends of the cage 100 are prevented from falling by the rail 120 and the shoe 200, and the most preferable lifting ring for easily lifting the cage 100 to the upper layer in a state of being in close contact with the wall 10 ( 1, 3, and 5, the position of the cage 100 can be easily lifted by applying a force to the upper layer at any position as long as it is on the longitudinal center of gravity of the cage 100. It is preferable that the lifting ring 110 is formed on the center of gravity line of the cage 100, and the wire 311 is connected to the lifting ring 110 of the cage 100. It can be lifted while the fall of the cage 100 is prevented by the hoist 300 to wind or loosen (311).

여기에서 권양기(300)는 중량체인 케이지(100)를 끌어올릴 수 있도록 단단히 고정되어야 하는 동시에, 인양이 완료된 후에는 다음 인양을 위하여 이동될 수 있어야 하기 때문에 설치 및 해체가 용이하면서도 안정적으로 고정되어야 하는 것이며, 케이지(100)를 끌어올리는 힘의 방향이 건축물 외벽의 벽면과 평행한 것이 바람직하기 때문에 케이지(100)와 연결된 와이어(311)가 상기 외벽의 벽면과 평행하도록 하는 것이 매우 중요하며 이를 위하여 상기 케이지(100)와 연결되는 와이어(311)를 권취하는 권취롤(310)과, 상기 권취롤(310)을 감속기어에 의해 회전시켜 상기 와이어(311)를 감거나 푸는 모터(320)가 구비된 상기 권양기(300)는 도 6에서 보는 바와 같이, 상기 케이지(100)와 연결되어 권취롤(310)에 감기는 와이어(311)를 건축물 외벽의 벽면과 평행하도록 지지하는 롤러가 일단에 구비된 롤러 암(330)이 돌출 형성될 수 있으며, 상기 롤러 암(330)이 돌출된 방향의 반대 방향에서 상층을 향하여 돌출되어 권양기(300)를 건축물에 고정시키는 층간 고정구(400)와 결합되는 원뿔형의 고정돌기(340)가 형성될 수 있고, 이러한 권양기(300)의 몸체에 권양기(300)를 제어하는 프로세서(350) 및 버튼 또는 스위치 등으로 된 입력장치가 구비될 수 있다. Here, the hoist 300 should be firmly fixed to lift the cage 100 which is a heavy body, and should be easily and reliably installed and dismantled since it should be able to be moved for the next lifting after the lifting is completed. Since the direction of the force that pulls up the cage 100 is preferably parallel to the wall surface of the building exterior wall, it is very important that the wire 311 connected to the cage 100 is parallel to the wall surface of the exterior wall. A winding roll 310 winding the wire 311 connected to the cage 100 and a motor 320 for winding or unwinding the wire 311 by rotating the winding roll 310 by a reduction gear. As shown in FIG. 6, the hoist 300 supports the wire 311 connected to the cage 100 and wound around the take-up roll 310 to be parallel to the wall surface of the building outer wall. A roller arm 330 having a roller at one end thereof may be formed to protrude, and the interlayer fixture 400 which protrudes toward the upper layer in a direction opposite to the direction in which the roller arm 330 protrudes to fix the hoist 300 to the building. Conical fixing protrusion 340 is coupled to the) can be formed, the processor 350 for controlling the winch 300 and the input device of a button or switch may be provided in the body of the winch 300. .

여기에서 상기 층간 고정구(400)는 길이 가변이 가능한 봉 형태로 겹쳐져 이어지는 외관(410)과 내관(420), 및 상기 외관(410)과 내관(420)이 겹쳐져 이어지는 정도를 조절하는 지지핀(430)과, 일단에 미끄럼 방지구가 구비된 지지부(411)와, 타단에 원뿔형의 요홈(422)이 형성된 고정부(421)가 구성된 것으로, 상기 고정부(421)의 원뿔형 요홈(422)과 권양기(300)의 고정돌기(340)가 결합된 상태로 층간 고정구(400)의 외관(410)과 내관(420)이 겹쳐져 이어진 정도가 조절되어 상기 지지부(411)가 상층 하면에 지지되므로 층간에 걸쳐 상기 권양기(300)를 안정적으로 고정시킬 수 있게 되는 것이며, 층간 고정구(400)의 상기 지지핀(430)을 조절하는 것만으로 층간 고정구(400)의 길이를 가변 시킬 수 있어서, 용이하게 층간 고정구(400)의 고정 상태를 해제할 수 있기 때문에 권양기(300)의 이동 설치 또한 용이하게 되는 것이다.Here, the interlayer fastener 400 has an outer appearance 410 and an inner tube 420, which are overlapped in a rod shape having a variable length, and a support pin 430 for adjusting the degree of overlapping the outer appearance 410 and the inner tube 420. ), A support portion 411 having an anti-slip at one end, and a fixing portion 421 having a concave groove 422 formed at the other end thereof, and having a conical groove 422 and a winch of the fixing portion 421. As the fixing protrusion 340 of the 300 is coupled to the outer 410 and the inner tube 420 of the interlayer fastener 400 are coupled to each other, the degree of overlap is controlled so that the support part 411 is supported on the lower surface of the upper layer. It is to be able to stably fix the winch 300, it is possible to vary the length of the interlayer fixture 400 only by adjusting the support pin 430 of the interlayer fixture 400, it is easy to interlayer fixture ( 400 can release the fixed state of the winch 300 Mobile installation is also facilitated.

또한 상기 권양기(300)는 상기 모터(320)의 회전속도, 회전 방향등을 제어할 수 있는 상기 프로세서(350)와 유, 무선으로 통신하여 상기 모터(320)의 작동을 원격으로 제어할 수 있는 리모컨 등으로 구성된 컨트롤러(360)가 구비될 수 있어서, 케이지(100)의 인양 상태, 정도 등을 용이하게 파악할 수 있는 최적의 위치에서 안전을 고려하며 상기 컨트롤러(360)를 통해 원격으로 권양기(300)를 제어하여 케이지(100)를 인양할 수 있는 것이며, 이러한 컨트롤러(360)가 동시에 여러 개의 권양기(300)를 제어하여 다수의 케이지(100)를 동시에 인양할 수도 있음은 물론이다.In addition, the winch 300 is capable of remotely controlling the operation of the motor 320 by communicating in a wired or wireless manner with the processor 350 that can control the rotation speed, rotation direction, etc. of the motor 320. The controller 360 may be provided with a remote controller, and so on, considering the safety at an optimal position to easily grasp the lifting state, degree, etc. of the cage 100, the winch 300 remotely through the controller 360. It is possible to lift the cage 100 by controlling the control panel, such that the controller 360 may simultaneously control the multiple winch 300 to lift a plurality of cages (100) of course.

이와 같이 본 발명은 케이지(100)가 항시 슈(200)와 레일(120)로 고정되어 있기 때문에 풍압으로 인한 흔들림과 낙하의 위험성을 감소시키므로 별도의 안전시설이 불필요하게 되는 것이며, 분리 가능한 층간 고정구(400)에 의해 간편하게 탈착이 가능한 동시에 안전하게 고정되는 권양기(300)와 케이지(100)를 연결하여 상기 레일(120)을 따라 케이지(100)를 자유롭게 승강 및 하강시키는 것이 가능하므로 골조 공사의 스케줄과 상관없이 독립적으로 골조 공사가 끝난 다수의 층에 대하여 마감 공사를 실시할 수 있어서 효과적인 인력 운영이 가능할 뿐만 아니라 공사 기간도 획기적으로 단축시킬 수 있게 되는 것이며, 이러한 케이지(100)와 갱폼(20)이 연결되어 있으면, 갱폼(20) 및 케이지(100)의 인양 시 운영비용이 높고, 운영 시간이 긴 타워 크레인을 사용하지 않고도 간편하며, 안전하고, 저 비용, 단시간에 인양할 수 있게 되는 것이어서 건설비용 및 공기를 획기적으로 단축할 수 있게 되는 것이다.As described above, the present invention reduces the risk of shaking and falling due to wind pressure because the cage 100 is always fixed to the shoe 200 and the rail 120, so that a separate safety facility is not necessary. It is possible to freely lift and lower the cage 100 along the rail 120 by connecting the winch 300 and the cage 100 which can be easily detached and secured at the same time by the 400 and the schedule of frame construction Regardless of whether the finishing work can be carried out on a plurality of floors independently completed, not only effective manpower operation is possible, but also the construction period can be drastically shortened. Such a cage 100 and a gang form 20 If connected, the lifting cost of lifting the gangform 20 and the cage 100 is high, and the operation time is long without using a tower crane Easy, safe and geotyieoseo being able to salvage a low-cost, short time will be able to significantly reduce the construction cost and air.

아울러 본 발명에 의한 케이지(100) 레일(120) 클라이밍 시스템은 케이지(100)가 갱폼(20)의 하단에 연결된 것일 경우에, 일면 양측에 레일(120)이 구비되고 갱폼(20)에 연결된 케이지(100)가, 상기 케이지(100)의 레일(120)을 건축물에 근접시켜 지지하며 낙하를 방지하는 슈(200)에 의해 건축물에 고정된 상태에서 상기 케이지(100)를 인양하는 권양기(300)의 롤러 암(330)이 외벽 밖으로 돌출될 수 있도록 벽체(10)에 인양공(11)이 형성되는 인양공(11) 형성 단계와;In addition, the cage 100 according to the present invention rail 120 climbing system, when the cage 100 is connected to the lower end of the gangform 20, the rail 120 is provided on both sides of one side and the cage connected to the gangform 20 The hoist 300 for lifting the cage 100 in a state in which the rail 100 of the cage 100 is supported to the building by being fixed to the building by the shoe 200 which prevents the falling of the cage 100. A lifting hole 11 forming step in which the lifting hole 11 is formed in the wall 10 so that the roller arm 330 of the roller arm 330 can protrude out of the outer wall;

상기 인양공(11) 형성 단계에서 형성된 인양공(11)을 통해 권양기(300)의 롤러 암(330)이 벽체(10)를 통과하여 돌출되도록 권양기(300)가 설치되어 케이지(100)의 인양고리(110)에 연결된 권양기(300)의 와이어(311)를 지지하도록 하며, 인양되는 케이지(100)의 레일(120)과 연결될 슈(200)가 설치되는 설치 단계와;The hoisting device 300 is installed so that the roller arm 330 of the hoisting machine 300 protrudes through the wall 10 through the lifting hole 11 formed at the step of forming the lifting hole 11 to lift the cage 100. An installation step of supporting the wires 311 of the winches 300 connected to the ring 110 and installing a shoe 200 to be connected to the rails 120 of the cage 100 to be lifted;

상기 권양기(300)의 상층 방향으로 돌출된 원뿔형의 고정돌기(340)가 층간 고정구(400)의 고정부(421)에 형성된 원뿔형의 요홈(422)에 삽입 고정되도록 층간 고정구(400)가 세워지며, 층간 고정구(400)의 외관(410)과 내관(420)이 겹쳐져 이어진 정도를 지지핀(430)에 의해 조절되어 층간 고정구(400)의 일단에 형성된 지지부(411)가 상기 권양기(300)가 설치된 층의 상층 하면에 지지되도록 하여 권양기(300)가 층간에 걸쳐 고정되는 권양기(300) 고정 단계와;The interlayer fastener 400 is erected so that the conical fixing protrusion 340 protruding in the upper layer direction of the hoist 300 is inserted into and fixed to the conical groove 422 formed in the fixing part 421 of the interlayer fastener 400. The degree of overlapping the outer 410 and the inner tube 420 of the interlayer fastener 400 is controlled by the support pin 430 so that the support part 411 formed at one end of the interlayer fastener 400 is the winch 300. A step of fixing the winch device 300 to be supported on the upper and lower surfaces of the installed floor, the winch device 300 being fixed across the floors;

상기 권양기(300) 고정 단계에서 고정된 권양기(300)의 와이어(311)가 롤러 암(330)의 지지를 받으며 케이지(100)의 인양고리(110)에 연결되고, 상기 케이지(100)와 연결된 갱폼(20)을 벽체(10)에 고정시키는 갱폼(20)고정구가 제거되며, 갱폼(20)이 벽체(10)로부터 이격되는 인양 준비 단계와;The wire 311 of the winch 300, which is fixed in the winch 300 fixing step, is supported by the roller arm 330 and connected to the lifting ring 110 of the cage 100, and connected to the cage 100. A gang form 20 fixing tool for fixing the gang form 20 to the wall 10 is removed, and the gang form 20 is separated from the wall 10 by the lifting preparation step;

상기 건축물에 고정된 상기 슈(200)와, 케이지(100)의 레일(120)에 구비된 낙하방지 부재(125)에 의해 케이지(100)의 낙하가 방지되는 상태로 상기 권양기(300)에 의해 갱폼(20)을 포함한 케이지(100)가 상층으로 인양되는 인양 단계와;By the winch 300 in a state in which the fall of the cage 100 is prevented by the shoe 200 fixed to the building and the drop preventing member 125 provided on the rail 120 of the cage 100. A lifting step in which the cage 100 including the gangform 20 is lifted to an upper layer;

상기 인양 단계에서 인양이 완료 된 후 상기 갱폼(20)이 벽체(10) 형성을 위해 상기 건축물에 고정되며, 상기 슈(200)에 의해서 케이지(100)가 낙하 방지 되는 상태로 상기 권양기(300)를 고정하고 있는 층간 고정구(400)가 분리고, 상기 권양기(300)가 다음 인양을 위해 이동되는 분리 단계와;After the lifting is completed in the lifting step, the gangform 20 is fixed to the building to form the wall 10, the cage 100 in the state that the cage 100 is prevented from falling by the shoe 200 300 Separation between the fixing fixture 400 is fixed, the winch 300 is moved for the next lifting;

상기 건축물의 벽체(10) 마감 작업 시 상기 인양공(11) 형성 단계에서 형성된 인양공(11)을 막는 인양공(11) 마감 단계로; 구성될 수 있다.In the finishing step of the lifting hole (11) to block the lifting hole (11) formed in the lifting hole (11) forming step during the wall 10 finishing work of the building; Lt; / RTI >

여기에서 갱폼(20)과 함께 연결된 케이지(100)는 일반적으로 3층 내지 4층 정도의 크기를 갖기 때문에 최상층의 벽체(10) 시공이 완성되어 다음층 시공을 위해 갱폼(20)과 함께 케이지(100)를 상층으로 인양하기 위하여 차상층 외벽의 벽체(10)에 인양공(11)을 형성하고, 이러한 인양공(11)을 통해 상기 권양기(300)의 롤러 암(330)을 돌출시켜 와이어(311)를 벽체(10)면과 수평하게 지지하며, 이러한 와이어(311)를 케이지(100)의 수직방향의 무게중심선상의 하방에 형성된 인양고리(110)에 연결하므로 타워 크레인을 사용하지 않고도 갱폼(20)을 포함한 케이지(100)를 인양할 수 있게 되는 것이다.Since the cage 100 connected with the gangform 20 generally has a size of about 3 to 4 floors, the construction of the wall 10 of the uppermost layer is completed, and the cage together with the gangform 20 for the next floor construction. In order to lift 100 to the upper layer, a lifting hole 11 is formed in the wall 10 of the outer wall of the vehicle-level layer, and the roller arm 330 of the hoisting machine 300 protrudes through the lifting hole 11 to wire. 311 is supported horizontally with the wall 10, and the wire 311 is connected to the lifting ring 110 formed below the center of gravity in the vertical direction of the cage 100, so the gang form without using a tower crane. It will be able to lift the cage 100, including 20.

또한 이러한 갱폼(20)과 함께 케이지(100)를 인양하는 권양기(300)는 안정적으로 고정되는 동시에 다음 인양을 위하여 이동될 수 있어야 하기 때문에 상기 권양기(300) 고정 단계와 분리 단계와 같이, 길이 가변이 가능한 봉 형태로 겹쳐져 이어지는 외관(410)과 내관(420) 및 상기 외관(410)과 내관(420)이 겹쳐져 이어지는 정도를 조절하는 지지핀(430)과, 일단에 미끄럼 방지 패드가 구비된 지지부(411)와, 타단에 원뿔형의 요홈(422)이 형성된 고정부(421)가 구성된 층간 고정구(400)를 이용하여 층간에 걸쳐 안정적으로 권양기(300)를 고정시킬 수 있게 되는 것이며, 인양이 완료된 후에는 층간 고정구(400)의 지지핀(430)에 의해 외관(410)과 내광이 겹쳐져 이어진 정도를 조절하여 용이하게 분리시킬 수 있게 되는 것이다.In addition, the lifting device 300 lifting the cage 100 together with the gang form 20 should be stably fixed and can be moved for the next lifting, so the length of the hoisting device 300 is fixed, as in the fixing step and separation step, The rod 410 and the inner tube 420 and the support pin 430 for adjusting the degree of overlapping the outer tube 420 and the inner tube 420 are overlapped in a possible rod shape, and a support portion provided with an anti-slip pad at one end thereof. 411, and using the interlayer fastener 400 consisting of a fixing portion 421 formed with a concave groove 422 at the other end is to be able to stably secure the hoist 300 across the floor, the lifting is completed Afterwards by the support pin 430 of the interlayer fixture 400 will be able to be easily separated by adjusting the degree that the exterior 410 and the internal light is overlapped.

따라서 케이지(100)에 구비된 레일(120)과 건축물에 고정된 슈(200)가 낙하방지 부재(125)에 의해 낙하가 방지되면서 연결된 상태에서, 분리 가능한 층간 고정구(400)에 의해 간편하게 탈착이 가능한 동시에 안전하게 고정되는 권양기(300)와 케이지(100)를 연결하여 상기 레일(120)을 따라 케이지(100)를 자유롭게 승강 및 하강시키는 것이 가능하므로 운영비용이 높고, 운영 시간이 긴 타워 크레인을 사용하지 않고도 간편하며, 안전하고, 저 비용, 단시간에 인양할 수 있게 되는 것이어서 건설 비용 및 공기를 단축할 수 있게 되는 것이다.Therefore, the rail 120 provided in the cage 100 and the shoe 200 fixed to the building are connected to each other while being prevented from being dropped by the drop preventing member 125, and the detachable interlayer fixture 400 is easily detachable. It is possible to freely lift and lower the cage 100 along the rail 120 by connecting the winch 300 and the cage 100 which is securely fixed at the same time, so that the operation cost is high and the operation time is long, and the tower crane is used. Without the need for simple, safe, low cost, and short lifting time, construction costs and air can be reduced.

또한 본 발명에 의한 케이지(100) 레일(120) 클라이밍 시스템은 갱폼(20)과 독립적으로 케이지(100)만을 단독으로 인양하는 경우, 마감 작업이 이루어져야 하는 작업 대상층에 케이지(100)와 연결될 슈(200)와, 상기 케이지(100)를 인양할 권양기(300)가 설치되는 설치 단계와;In addition, the cage 100 according to the present invention rail 120 climbing system when the sole lifting the cage 100 independently of the gang form 20, the shoe to be connected to the cage 100 to the work target layer to be finished ( 200 and an installation step of installing a hoist 300 to lift the cage 100;

상기 권양기(300)의 상방으로 돌출된 원뿔형의 고정돌기(340)가 층간 고정구(400)의 고정부(421)에 형성된 원뿔형의 요홈(422)에 삽입 고정되도록 층간 고정구(400)가 세워지며, 층간 고정구(400)의 외관(410)과 내관(420)이 겹쳐져 이어진 정도를 지지핀(430)에 의해 조절되어 층간 고정구(400)의 일단에 형성된 지지부(411)가 상기 권양기(300)가 설치된 층의 상층 하면에 지지되도록 하여 권양기(300)가 층간에 걸쳐 고정되는 권양기(300) 고정 단계와;The interlayer fastener 400 is erected so that the conical fixing protrusion 340 protruding upward of the hoist 300 is inserted into and fixed to the conical groove 422 formed in the fixing part 421 of the interlayer fastener 400. The support 411 is formed on one end of the interlayer fixture 400 by adjusting the degree of overlap of the exterior 410 and the inner tube 420 of the interlayer fixture 400 by the support pin 430, and the winches 300 are installed. A step of fixing the hoist 300 so that the hoist 300 is fixed across the floor so as to be supported on the upper and lower surfaces of the floor;

상기 권양기(300) 고정 단계에서 고정된 권양기(300)의 와이어(311)가 케이지(100)의 인양고리(110)에 연결되어 케이지(100)가 상층으로 인양되되, 상기 건축물에 고정된 상기 슈(200)와, 케이지(100)의 레일(120)에 구비된 낙하방지 부재(125)에 의해 케이지(100)의 낙하가 방지되며 건축물에 밀착된 상태로 인양되는 인양 단계와;The wire 311 of the winch 300 fixed in the winch 300 is connected to the lifting ring 110 of the cage 100 so that the cage 100 is lifted to the upper floor, the shoe fixed to the building A lifting step in which the fall of the cage 100 is prevented by the drop preventing member 125 provided on the rail 120 of the cage 100 and lifted in a state in which it is in close contact with the building;

상기 인양 단계를 통해 인양된 케이지(100)에서 마감 작업이 완료된 후 다음 마감 작업을 위해 상기 슈(200)에 의해서 케이지(100)가 낙하 방지 되는 상태로 상기 권양기(300)를 고정하고 있는 층간 고정구(400)가 분리되고, 상기 권양기(300)를 이동시켜 상기 설치 단계가 반복 실시되도록 하는 분리 단계로; 구성될 수 있어서, 케이지(100)가 항시 슈(200)와 레일(120)로 고정되어 있기 때문에 풍압으로 인한 흔들림과 낙하의 위험성을 감소시키므로 별도의 안전시설이 불필요하게 되며, After finishing the finishing work in the cage 100 lifted through the lifting step, the interlayer fixture for fixing the winch 300 in a state that the cage 100 is prevented to fall by the shoe 200 for the next finishing work (400) is separated, the separation step to move the winch 300 to the installation step is repeated; Since the cage 100 is always fixed to the shoe 200 and the rail 120, the risk of shaking and falling due to wind pressure is reduced, so that a separate safety facility is unnecessary.

분리 가능한 층간 고정구(400)에 의해 간편하게 탈착이 가능한 동시에 안전하게 고정되는 권양기(300)와 케이지(100)를 연결하여 상기 레일(120)을 따라 케이지(100)를 자유롭게 승강 및 하강시키는 것이 가능하므로 골조 공사의 스케줄과 상관없이 독립적으로 골조 공사가 끝난 다수의 층에 대하여 마감 공사를 실시할 수 있어서 효과적인 인력 운영이 가능할 뿐만 아니라 공사 기간도 획기적으로 단축시킬 수 있게 되는 것이다.It is possible to freely lift and lower the cage 100 along the rail 120 by connecting the winch 300 and the cage 100 which can be easily detached and secured by the detachable interlayer fixture 400 and are secured at the same time. Regardless of the construction schedule, finishing work can be carried out on a large number of floors that have been independently framed, enabling effective manpower management and significantly shortening the construction period.

이상과 같이, 본 발명은 전술한 실시예에 한정되지 않고, 본 발명이 의도하는 요지 및 개념 내에서 다양하게 변화시켜 실시하는 것이 가능하다.
As described above, the present invention is not limited to the above-described embodiments, but can be variously changed within the spirit and concept of the present invention.

10:벽체 11:인양공 20:갱폼
100:케이지 110:인양고리 120:레일
121:후면빔 122:전면빔 123:측면빔
124:통공 125:낙하방지부재 200:슈
210:헤드 211:암 212:고정핀
213:개방홈 220:고정부재 221:고정홈
300:권양기 310:권취롤 311:와이어
320:모터 330:롤러 암 340:고정돌기
350:프로세서 360:컨트롤러 400:층간 고정구
410:외관 411:지지부 420:내관
421:고정부 422:요홈 430:지지핀
10: wall 11: salvage 20: gang form
100: cage 110: salvage ring 120: rail
121: rear beam 122: front beam 123: side beam
124: through hole 125: fall prevention member 200: shoe
210: head 211: arm 212: fixing pin
213: opening groove 220: fixing member 221: fixing groove
300: winching machine 310: winding roll 311: wire
320: motor 330: roller arm 340: fixed protrusion
350: processor 360: controller 400: interlayer fixture
410: appearance 411: support portion 420: inner view
421: fixed part 422: groove 430: support pin

Claims (9)

삭제delete 케이지의 양측에 구비된 레일과, 시공 중인 건축물에 고정되며, 상기 레일을 상기 건축물에 근접시켜 지지하여 낙하를 방지하는 슈가 구성된 케이지 레일 클라이밍 시스템에 있어서,
상기 슈는 상기 레일의 일면을 건축물에 밀착시키는 회동 가능한 암이 구비된 헤드와, 상기 헤드를 건축물에 고정시키는 고정부재로 구성되며;
상기 레일은 H빔의 형태로 측면에 구비된 통공과, 상기 통공을 기준으로 회동 가능하도록 일단이 고정되되, 타단의 상측은 상기 헤드의 암으로 감싸진 H빔의 전면빔 내측면에 지지되어 상방으로의 회동이 제한되며, 타단의 하측은 상기 암의 상단에 지지되어 케이지의 낙하를 방지하는 낙하방지 부재가 구성되고;
상기 케이지의 무게중심선상에 인양고리가 형성되며, 상기 인양고리에 와이어가 탈착되어 상기 레일이 슈에 연결된 상태로 케이지를 승하강 시키는 권양기와; 상기 권양기를 층간에 걸쳐 고정시키는 층간 고정구가 구성되되,
상기 헤드는 양 옆에서 전개 가능하도록 설치되어 상기 레일의 일면을 헤드에 밀착시키는 암과,
상기 암을 헤드에 고정하며, 암과 헤드 사이의 간격을 조절할 수 있는 고정핀이 구성된 것임을 특징으로 하는 케이지 레일 클라이밍 시스템.
In the cage rail climbing system comprising a rail provided on both sides of the cage, and a shoe fixed to the building under construction, the shoe to support the rail in close proximity to the building to prevent the fall,
The shoe is composed of a head having a rotatable arm for closely contacting one surface of the rail to the building, and a fixing member for fixing the head to the building;
The rail has a through hole provided on the side in the form of an H beam, and one end is fixed to be rotatable based on the through hole, and the upper end of the other end is supported by an inner surface of the front beam of the H beam wrapped by the arm of the head and upwards. Rotation to is limited, the lower end of the other end is supported on the upper end of the arm is configured to prevent the falling of the cage;
Lifting ring is formed on the center of gravity line of the cage, the lifting device is attached to the lifting ring for lifting and lowering the cage while the rail is connected to the shoe; An interlayer fastener is configured to fix the winch over the interlayer,
The head is installed so as to be deployed on both sides and the arm to close one side of the rail to the head,
Fixing the arm to the head, cage rail climbing system, characterized in that the fixing pin is configured to adjust the distance between the arm and the head.
제 2 항에 있어서,
상기 고정부재는 앵커, 바이스, 층간 고정구 중 어느 하나로, 상기 헤드가 고정되어야 하는 건축물의 발코니 구간, 수벽 구간, 슬라브 구간, 옹벽 구간 각각의 형태에 결합될 수 있도록 상기 헤드와 분리되어 교체됨을 특징으로 하는 케이지 레일 클라이밍 시스템.
3. The method of claim 2,
The fixing member is one of an anchor, a vise, an interlayer fixture, and is separated and replaced with the head so that the head can be coupled to each of a balcony section, a water wall section, a slab section, and a retaining wall section of the building to which the head is to be fixed. Cage rail climbing system.
제 2 항에 있어서,
상기 고정부재는 상측면에 층간에 걸쳐 고정시키는 층간 고정구의 일단이 삽입 고정되는 고정홈이 형성된 것임을 특징으로 하는 케이지 레일 클라이밍 시스템.
3. The method of claim 2,
The fixing member is a cage rail climbing system, characterized in that the fixing groove is formed is fixed to one end of the interlayer fastener for fixing over the interlayer on the upper side.
제 2 항에 있어서,
상기 권양기는 케이지와 연결되는 와이어를 권취하는 권취롤과, 상기 권취롤을 감속기어에 의해 회전시켜 상기 와이어를 감거나 푸는 모터와, 상기 케이지와 연결되어 권취롤에 감기는 와이어를 건축물 외벽의 벽면과 평행하도록 지지하는 롤러가 일단에 구비된 롤러 암과, 상기 롤러 암이 돌출된 방향의 반대 방향에서 상층을 향하여 돌출되어 권양기를 건축물에 고정시키는 층간 고정구와 결합되는 원뿔형의 고정돌기로 구성됨을 특징으로 하는 케이지 레일 클라이밍 시스템.
3. The method of claim 2,
The winding machine is a winding roll for winding a wire connected to a cage, a motor for winding or unwinding the wire by rotating the winding roll by a reduction gear, and a wire connected to the cage and wound on a winding roll to a wall surface of a building exterior wall. And a roller arm having a roller supporting at one end thereof and a conical fixing protrusion coupled to an interlayer fastener which protrudes toward the upper layer in a direction opposite to the direction in which the roller arm protrudes and fixes the winch to the building. Cage rail climbing system.
제 5 항에 있어서,
상기 권양기는 모터의 작동을 제어하는 프로세서와, 상기 프로세서와 유, 무선으로 통신하여 상기 모터의 작동을 원격으로 제어하는 컨트롤러가 구비됨을 특징으로 하는 케이지 레일 클라이밍 시스템.
The method of claim 5, wherein
The hoisting machine is a cage rail climbing system comprising a processor for controlling the operation of the motor, and a controller for remotely controlling the operation of the motor by communicating with the processor in a wired or wireless manner.
제 2 항에 있어서,
상기 층간 고정구는 길이 가변이 가능한 봉 형태로 겹쳐져 이어지는 외관과 내관 및 상기 외관과 내관이 겹쳐져 이어지는 정도를 조절하는 지지핀과, 일단에 미끄럼 방지구가 구비된 지지부와, 타단에 원뿔형의 요홈이 형성된 고정부가 구성된 것임을 특징으로 하는 케이지 레일 클라이밍 시스템.
3. The method of claim 2,
The interlayer fastener has a support pin for adjusting the appearance and the inner tube and the degree of overlapping the outer and inner tube overlapping in the form of a rod of variable length, a support portion provided with an anti-slip at one end, and a conical groove at the other end. Cage rail climbing system, characterized in that the fixed portion is configured.
일면 양측에 레일이 구비되고 갱폼에 연결된 케이지가, 상기 케이지의 레일을 건축물에 근접시켜 지지하며 낙하를 방지하는 슈에 의해 건축물에 고정된 상태에서 상기 케이지를 인양하는 권양기의 롤러 암이 외벽 밖으로 돌출될 수 있도록 벽체에 인양공이 형성되는 인양공 형성 단계와,
상기 인양공 형성 단계에서 형성된 인양공을 통해 권양기의 롤러 암이 벽체를 통과하여 돌출되도록 권양기가 설치되어 케이지의 인양고리에 연결된 권양기의 와이어를 지지하도록 하며, 인양되는 케이지의 레일과 연결될 슈가 설치되는 설치 단계와,
상기 권양기의 상층 방향으로 돌출된 원뿔형의 고정돌기가 층간 고정구의 고정부에 형성된 원뿔형의 요홈에 삽입 고정되도록 층간 고정구가 세워지며, 층간 고정구의 외관과 내관이 겹쳐져 이어진 정도를 지지핀에 의해 조절되어 층간 고정구의 일단에 형성된 지지부가 상기 권양기가 설치된 층의 상층 하면에 지지되도록 하여 권양기가 층간에 걸쳐 고정되는 권양기 고정 단계와,
상기 권양기 고정 단계에서 고정된 권양기의 와이어가 롤러 암의 지지를 받으며 케이지의 인양고리에 연결되고, 상기 케이지와 연결된 갱폼을 벽체에 고정시키는 갱폼고정구가 제거되며, 갱폼이 벽체로부터 이격되는 인양 준비 단계와,
상기 건축물에 고정된 상기 슈와, 케이지의 레일에 구비된 낙하방지부재에 의해 케이지의 낙하가 방지되는 상태로 상기 권양기에 의해 갱폼을 포함한 케이지가 상층으로 인양되는 인양 단계와,
상기 인양 단계에서 인양이 완료 된 후 상기 갱폼이 벽체 형성을 위해 상기 건축물에 고정되며, 상기 슈에 의해서 케이지가 낙하 방지 되는 상태로 상기 권양기를 고정하고 있는 층간 고정구가 분리고, 상기 권양기가 다음 인양을 위해 이동되는 분리 단계와,
상기 건축물의 벽체 마감 작업 시 상기 인양공 형성 단계에서 형성된 인양공을 막는 인양공 마감 단계로 구성됨을 특징으로 하는 케이지 레일 클라이밍 시스템.
The roller arm of the hoist which lifts the cage protrudes out of the outer wall in the state which the rail is provided in both sides and the cage connected to the gang form is fixed to the building by the shoe which supports the rail of the cage close to the building and prevents the fall. Lifting hole forming step in which the lifting hole is formed on the wall,
The hoisting machine is installed so that the roller arm of the hoisting machine protrudes through the wall through the lifting hole formed in the lifting hole forming step to support the wire of the hoisting machine connected to the lifting ring of the cage, and the shoe to be connected to the rail of the cage being lifted is installed. Installation steps,
The interlayer fixture is erected so that the conical fixing protrusion protruding in the upper layer direction of the hoisting machine is inserted into the concave groove formed in the fixing portion of the interlayer fixture, and the degree of overlapping the appearance of the interlayer fixture and the inner tube is controlled by the support pin. A winch holder fixing step of allowing the supporter formed at one end of the interlayer fixture to be supported on the upper and lower surfaces of the layer on which the winch is installed;
The wire of the winch fixed in the winch fixing step is supported by the roller arm and connected to the lifting ring of the cage, the gangform fixture for fixing the gangform connected to the cage is removed, the lifting preparation step of the gangform is spaced apart from the wall Wow,
A lifting step in which a cage including a gang form is lifted to an upper layer by the winch in a state in which the drop of the cage is prevented by the shoe fixed to the building and the drop preventing member provided on the rail of the cage;
After the lifting is completed in the lifting step, the gangform is fixed to the building to form a wall, the interlayer fasteners fixing the winch in the state that the cage is prevented from falling by the shoe is separated, and the winch is lifted next A separation step that is moved for
Cage rail climbing system, characterized in that consisting of the lifting hole finishing step to prevent the lifting hole formed in the lifting hole forming step when the wall finishing work of the building.
마감 작업이 이루어져야 하는 작업 대상층에 케이지와 연결될 슈와, 상기 케이지를 인양할 권양기가 설치되는 설치 단계와,
상기 권양기의 상방으로 돌출된 원뿔형의 고정돌기가 층간 고정구의 고정부에 형성된 원뿔형의 요홈에 삽입 고정되도록 층간 고정구가 세워지며, 층간 고정구의 외관과 내관이 겹쳐져 이어진 정도를 지지핀에 의해 조절되어 층간 고정구의 일단에 형성된 지지부가 상기 권양기가 설치된 층의 상층 하면에 지지되도록 하여 권양기가 층간에 걸쳐 고정되는 권양기 고정 단계와,
상기 권양기 고정 단계에서 고정된 권양기의 와이어가 케이지의 인양고리에 연결되어 케이지가 상층으로 인양되되, 상기 슈와, 케이지의 레일에 구비된 낙하방지부재에 의해 케이지의 낙하가 방지되며 건축물에 밀착된 상태로 인양되는 인양 단계와,
상기 인양 단계를 통해 인양된 케이지에서 마감 작업이 완료된 후 다음 마감 작업을 위해 상기 슈에 의해서 케이지가 낙하 방지 되는 상태로 상기 권양기를 고정하고 있는 층간 고정구가 분리되고, 상기 권양기를 이동시켜 상기 설치 단계가 반복 실시되도록 하는 분리 단계로 구성됨을 특징으로 하는 케이지 레일 클라이밍 시스템.
An installation step in which a shoe to be connected to the cage and a winch to lift the cage are installed on the target object layer to be finished;
The interlayer fixture is erected so that the conical fixing protrusion protruding upward of the hoisting machine is inserted and fixed in the conical groove formed in the fixing portion of the interlayer fixture, and the degree of the overlap between the appearance of the interlayer fixture and the inner tube is controlled by the support pin. A winch holder fixing step in which a support part formed at one end of the fixture is supported on the upper and lower surfaces of the layer on which the winch is installed, and the winch machine is fixed across the layers;
The wire of the hoisting device fixed in the hoisting step is connected to the lifting ring of the cage so that the cage is lifted to the upper layer, and the fall of the cage is prevented by the drop preventing member provided on the shoe and the rail of the cage, and closely adhered to the building. The lifting stage to be lifted into the state,
After the finishing work is completed in the cage lifted through the lifting step, the interlayer fasteners fixing the winches in a state that the cage is prevented from falling by the shoe for the next finishing work is separated, and the installation step by moving the winches Cage rail climbing system, characterized in that consisting of a separation step to be repeated.
KR1020110050072A 2011-05-26 2011-05-26 Cage rail climbing system KR101370981B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110050072A KR101370981B1 (en) 2011-05-26 2011-05-26 Cage rail climbing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110050072A KR101370981B1 (en) 2011-05-26 2011-05-26 Cage rail climbing system

Publications (2)

Publication Number Publication Date
KR20120131710A KR20120131710A (en) 2012-12-05
KR101370981B1 true KR101370981B1 (en) 2014-03-10

Family

ID=47515481

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110050072A KR101370981B1 (en) 2011-05-26 2011-05-26 Cage rail climbing system

Country Status (1)

Country Link
KR (1) KR101370981B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103899079A (en) * 2014-04-22 2014-07-02 云南西润投资控股有限公司 Falling-preventing device
KR102534964B1 (en) * 2022-07-15 2023-05-26 이승준 Guide apparatus for climbing gang forms

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104153561B (en) * 2014-08-26 2016-09-07 广东建星建筑设备有限公司 Template is climbed drop preventer
JP6728602B2 (en) * 2015-09-07 2020-07-22 株式会社大林組 Scaffold lifting device and construction method
KR20190106089A (en) 2018-03-07 2019-09-18 이경화 Outside wall finishing cage
KR20200103589A (en) 2020-08-24 2020-09-02 이경화 Outside wall finishing cage
CN112982935B (en) * 2021-03-03 2021-10-26 淮安市博彦土木工程科学研究院有限公司 Pull-up scaffold for wide-scene balcony and construction method thereof
CN114592677B (en) * 2022-04-01 2024-04-02 安徽道元建筑科技有限公司 Tool type scaffold anti-falling system

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07229310A (en) * 1994-02-21 1995-08-29 Kajima Corp Lifting device of building device and materials by use of slide type load receiving frame base
KR101006402B1 (en) * 2008-10-13 2011-01-10 권종규 Level Guide Climbing System of

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07229310A (en) * 1994-02-21 1995-08-29 Kajima Corp Lifting device of building device and materials by use of slide type load receiving frame base
KR101006402B1 (en) * 2008-10-13 2011-01-10 권종규 Level Guide Climbing System of

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103899079A (en) * 2014-04-22 2014-07-02 云南西润投资控股有限公司 Falling-preventing device
KR102534964B1 (en) * 2022-07-15 2023-05-26 이승준 Guide apparatus for climbing gang forms

Also Published As

Publication number Publication date
KR20120131710A (en) 2012-12-05

Similar Documents

Publication Publication Date Title
KR101370981B1 (en) Cage rail climbing system
KR101345146B1 (en) Winch and rail climbing system
US9701520B2 (en) Hoisting platform system
KR100928870B1 (en) Retractable prop
US20140054110A1 (en) Method for accessing the outer surface of wind turbine towers and device for use with this method
CN110593128B (en) Concrete bridge tower building method
CN110644375A (en) Multifunctional integrated intelligent tower building device
JP2006299559A (en) Self climbing scaffold and self climbing method by use of it
KR101068229B1 (en) Dismantled tower crane cargo handling system and cargo handling method using thereof
CN211420875U (en) Multifunctional integrated intelligent tower building device
JP3122935U (en) Lifting structure of scaffolding and curing net in steel tower
CN104652803B (en) Attached electric lifting guide rail scaffold
JP2014047479A (en) Method for lifting demolishing heavy machine to building to be demolished
KR101254501B1 (en) Method of finish construction using safety rail climbing system
JP2010064867A (en) Method for demolishing tower crane
JP5773343B2 (en) Method for constructing multi-story building and lifting device for multi-story scaffold used therefor
JP5150313B2 (en) Three-dimensional parking device in void and its construction method
JPH08120936A (en) Method and device for constructing multistoried building
JP2012233344A (en) Method for connecting mast, and device for use in the same
EP2911971B1 (en) Hoisting platform system
KR20190106089A (en) Outside wall finishing cage
CN211597666U (en) Steel construction laced beam installation appurtenance
JP6987089B2 (en) Aerial work platform
JP2011106114A (en) Method for constructing stage for high-place work
JP5410322B2 (en) Structure building method and structure building jig used therefor

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E90F Notification of reason for final refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20161226

Year of fee payment: 4

LAPS Lapse due to unpaid annual fee