KR101345405B1 - Construct method of plate coping girder form - Google Patents

Construct method of plate coping girder form Download PDF

Info

Publication number
KR101345405B1
KR101345405B1 KR1020110134520A KR20110134520A KR101345405B1 KR 101345405 B1 KR101345405 B1 KR 101345405B1 KR 1020110134520 A KR1020110134520 A KR 1020110134520A KR 20110134520 A KR20110134520 A KR 20110134520A KR 101345405 B1 KR101345405 B1 KR 101345405B1
Authority
KR
South Korea
Prior art keywords
installation method
beam member
pier
ground station
formwork
Prior art date
Application number
KR1020110134520A
Other languages
Korean (ko)
Other versions
KR20130067696A (en
Inventor
한준수
Original Assignee
한준수
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한준수 filed Critical 한준수
Priority to KR1020110134520A priority Critical patent/KR101345405B1/en
Publication of KR20130067696A publication Critical patent/KR20130067696A/en
Application granted granted Critical
Publication of KR101345405B1 publication Critical patent/KR101345405B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

본 발명은 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에 있어서, 지면에 수직으로 설치된 철재 빔 소재의 교각기둥과 상기 교각기둥 상측에 횡방향 결합되고 다수개 이루어진 횡빔부재와 종방향으로 다수개 결합되는 종빔부재를 설치하는 1단계, 상기 교각기둥에 끝단에 부싱너트를 포함한 지지봉부재를 설치하는 2단계, 상기 교각기둥에 거푸집을 설치한 후 상기 지지봉부재 끝단까지 콘크리트를 타설하여 양생하는 3단계, 상기 지지봉부재에 앙카브라켓과 결합되는 지지부재를 체결한 후, 상측에 사각으로 된 스프래드 밴드폼를 상기 횡빔부재 하측에 설치하는 4단계, 상기 스프래드 밴드폼 상측으로 상기 횡빔부재와 상기 종빔부재에 메인폼을 설치하고, 상기 횡빔부재를 상호간 지지하는 보강부재 형성시키는 5단계로 이루어져, 도심의 도로에서 지상정거장 및 교각기둥의 코핑은 도로 차선 중앙선에서 중심으로 구조물이 형성되되, 도로의 교통이 원활하고 작업 공간이 확보되어 안전사고를 예방할 수 있다.The present invention is a steel formwork and installation method of the coping structure of the ground station and pier pillars, the pier beam of the steel beam material vertically installed on the ground and the horizontal beam member and a plurality of transverse beam members formed in the transverse direction on the upper side of the pier pillar 1 step of installing a longitudinal beam member coupled to the dog, 2 steps of installing a support rod member including a bushing nut at the end of the pier pillar, 3 to install the formwork on the pier pillar and to cure by pouring concrete to the end of the support rod member Step 4, after fastening the support member coupled to the anchor bracket to the support rod member, the step 4 to install a square band spread on the lower side of the horizontal beam member, the horizontal beam member and the longitudinal beam to the upper side of the spread beam form The main form is installed in the member, and consists of five steps of forming a reinforcing member for mutually supporting the lateral beam member. In urban roads, copings of ground stations and pier columns are formed around the center line of the road lanes, but the road traffic is smooth and work space is secured to prevent safety accidents.

Description

지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법{CONSTRUCT METHOD OF PLATE COPING GIRDER FORM}Formwork and installation method of coping structure of ground station and pier pillar {CONSTRUCT METHOD OF PLATE COPING GIRDER FORM}

본 발명은 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에 관한 것으로, 교각 상부에 있는 코팅의 철재 거푸집, 철근, 콘크리트 작업하중이 적게는 수십톤에서 수백톤의 하중을 지지할 수 있으며 작업공간인 코핑철재 거푸집 밑으로 차량 및 인도에 보행자가 원활하게 통행할 수 있는 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에 관한 것이다.
The present invention relates to a steel formwork and installation method of the coping structure of the ground station and the pier pillar, the steel formwork, reinforcement, concrete work load of the coating on the top of the pier can support a load of several tens of tons to hundreds of tons The present invention relates to a steel formwork and installation method of a coping structure of a ground station and a pier to allow a pedestrian to pass smoothly to vehicles and sidewalks under a coping steel formwork, which is a space.

일반적으로 지상 정거장 및 교각기둥의 코핑등에 사용하기 위하여 지상의 콘크리트 구조물을 뜻한 지상정거장 및 교각기둥의 코핑형상은 타원형 중심정방형, 중공정방형, 중심장방형, 중공 장방형, 평형정방형, 평형장방형등 다양한 현상으로 지상에서 큰크리트 구조물이 형성하게 된다.In general, the coping shape of ground station and pier pillar, which refers to the concrete structure of the ground, is used for various kinds of phenomena such as oval center square, medium process square, center square, hollow rectangle, equilibrium square, and equilibrium square. Large concrete structures will form on the ground.

일반적인 정거장 및 교각기둥의 코핑은 철근 및 콘크리트로 구성된 구조물이므로 거푸집은 철재 거푸집, 목재 거푸집을 사용하고 하부지지는 지주식 동바리 및 강지보재를 제작하여 하중을 지탱하거나, 철재 거푸집인 경우 기둥에 스리부파이프를 관통시켜 스루 바 볼트(thru-bar bolt)를 기둥속에 있는 스리부 파이프(sleeve pipe)속으로 관통시켜 앙카 브라켓(anchor-bracket)을 체결 후 앙카 브라켓 상부에 스크류 잭을 설치한 후 철재 거푸집을 스크류 잭 상부에 안착 시키는 방법과 구조계산후 좌측, 우측에 처짐이 발생시 스루 바 볼트를 기둥속에 있는 스리부 파이프속으로 스리부 바 볼트를 관통시켜 캔트레버(cantlever)설치 후 캔트레버 상부에 스크류잭을 안착 시킨후 스크류 잭위에 트러스 에이치 빔(truss h-beam) 또는 아이 빔(i-beam)등의 강재를 올린 후 코핑철재 폼을 올리는 방법이었다.Since the coping of the general station and piers is composed of reinforcing steel and concrete, the formwork uses steel formwork and wooden formwork, and the lower support is made of strut-type copper and steel support to support the load, or in the case of steel formwork, Penetrate the pipe through the thru-bar bolt into the sleeve pipe in the column to fasten the anchor bracket, install the screw jack on the top of the anchor bracket, and then form the steel formwork. Method of mounting the upper part of the screw jack and when the deflection occurs on the left and right sides after the structural calculation, the through bar bolt penetrates the slit bar bolt into the sribu pipe in the column and installs a canverver. After mounting the steel, such as truss h-beam or i-beam on the screw jack, It was how to raise the foam.

하지만, "S.C.R"교각 코핑의 구조물은 구조물 중심에 프렌지(F.L.G)웨이브(W.E.B)로 구성된 아이빔, 에이치빔이 설치되어 있으며 철골 구조물 주변으로 철근 배근 후 콘크리트 타설하는 내진설계 1등급 구조물이다.However, the structure of "S.C.R" pier coping is a seismic design class 1 structure in which the I-beam and H-beam consisting of F.L.G wave (W.E.B) are installed at the center of the structure, and concrete is poured after reinforcing the steel structure.

프렌지 웨이브로 구성된 아이빔, 에이치빔의 철골 구조물에 산소로 천공할 수 없으며 손상을 줄수 없으므로, 슬리브 파이프를 기둥에 관통 시킬 수 없다.Steel pipe structure of i-beam and H-beam consisting of flanged wave cannot be perforated with oxygen and can not damage, so sleeve pipe cannot be penetrated to pillar.

따라서, 스루 바 볼트, 앙카 브라켓, 캔트레버를 설치 할 수 없으므로 교각 상부에 있는 코핑의 철재 거푸집, 철근, 콘크리트 작업하중이 적게는 수십톤에서 수백톤의 하중을 지지할 수 없어 공사 자체가 불가능하고, 도심의 도로에서 지상정거장 및 교각기둥의 코핑은 도로 차선 중앙선에서 중심으로 구조물이 형성되므로, 도로의 교통이 마비되고 작업 공간이 협소하여 중장비, 크레인 작업시 작업이 극한 상태이며 주변의 건물, 통행자, 신호등, 가로등 고압전선등에 간섭을 받아 안전사고가 빈번하다.
Therefore, it is impossible to install through bar bolts, anchor brackets, and canvers, so the steel formwork, rebar, and concrete work loads of the copings on the upper part of the piers cannot support the loads of tens to hundreds of tons. In urban roads, copings of ground stations and pier columns are formed from the center line of the road lanes, so traffic on the roads is paralyzed and the working space is narrow. Now, safety accidents are frequent due to interference from traffic lights, street lamps and high voltage cables.

본 발명은 상기의 문제점들을 해결하기 위해서 안출된 것으로, 교각 상부에 있는 코팅의 철재 거푸집, 철근, 콘크리트 작업하중이 적게는 수십톤에서 수백톤의 하중을 지지할 수 있으며, The present invention has been made to solve the above problems, the steel formwork, reinforcement, concrete work load of the coating on the top of the pier can support a load of several tens to hundreds of tons,

또한, 도심의 도로에서 지상정거장 및 교각기둥의 코핑은 도로 차선 중앙선에서 중심으로 구조물이 형성되되, 도로의 교통이 원활하고 작업 공간이 확보되는 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법을 제공하는 데 있다.
In addition, the coping of ground stops and pier pillars in urban roads is based on the center line of the road lanes, and the formwork and installation methods of steel formwork and installation of coping structures of ground stops and pier pillars provide smooth traffic on the road and secure working space. To provide.

본 발명은 상기의 문제점들을 해결하기 위해서 안출된 것으로, 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에 있어서, 지면에 수직으로 설치된 철재 빔 소재의 교각기둥과 상기 교각기둥 상측에 횡방향 결합되고 다수개 이루어진 횡빔부재와 종방향으로 다수개 결합되는 종빔부재를 설치하는 1단계, 상기 교각기둥에 끝단에 부싱너트를 포함한 지지봉부재를 설치하는 2단계, 상기 교각기둥에 거푸집을 설치한 후 상기 지지봉부재 끝단까지 콘크리트를 타설하여 양생하는 3단계, 상기 지지봉부재에 앙카브라켓과 결합되는 지지부재를 체결한 후, 상측에 사각으로 된 스프래드 밴드폼를 상기 횡빔부재 하측에 설치하는 4단계, 상기 스프래드 밴드폼 상측으로 상기 횡빔부재와 상기 종빔부재에 메인폼을 설치하고, 상기 횡빔부재를 상호간 지지하는 보강부재 형성시키는 5단계로 이루어지는 것을 특징으로 한다. The present invention has been made in order to solve the above problems, in the ground station and the coping structure steel formwork and installation method of the piers pillars, the pier pillars of the steel beam material installed perpendicular to the ground and the lateral coupling on the pier pillars And a first step of installing a plurality of longitudinal beam members and a plurality of longitudinal beam members coupled in the longitudinal direction, and two steps of installing a support rod member including a bushing nut at the end of the pier pillar, and installing the formwork on the pier pillar. 3 steps to cure by pouring concrete to the end of the support bar member, 4 steps to install a square band spread on the lower side of the horizontal beam member after fastening the support member coupled to the anchor bracket to the support bar member, the soup The main form is installed on the lateral beam member and the longitudinal beam member, and the lateral beam member is positioned upward. It characterized by comprising the step of forming the reinforcing member 5 for supporting the liver.

그리고, 상기 지지봉부재는 상기 교각기둥에 용접되는 스루바와, 상기 스루바 외주에 다수개 설치되는 원형 후렌지와, 상기 스루바 끝단에 설치되는 부싱너트로 이루어지는 것을 특징으로 한다. The support rod member may include a through bar welded to the pier pillar, a circular flange installed on the outer circumference of the through bar, and a bushing nut installed at the end of the through bar.

그리고, 상기 3단계에서 콘크리트가 타설되어 상기 부싱너트로 인입되는 것을 방지하기 위해 상기 부싱너트에 스치로품을 삽입하여 청테이프로 밀봉 마감처리하는 것을 특징으로 한다. In addition, in order to prevent the concrete from being poured into the bushing nut in the third step, a stirrer product is inserted into the bushing nut to seal the finish with blue tape.

그리고, 제 3단계와 상기 4단계 사이에는 상기 교각기둥에 상기 지지봉부재 하측으로 작업용밴드폼을 설치하고, 상기 작업용밴드폼 단부에 수직으로 핸드레일파이프를 수직으로 설치하여 작업자가 낙하하는 것을 방지하는 것을 특징으로 한다. And, between the third step and the fourth step to install the work band form to the lower side of the support rod member on the pier pillar, and to install the handrail pipe vertically perpendicular to the end of the work band form to prevent the worker from falling. It is characterized by.

그리고, 상기 지지부재는 상기 부싱너트에 결합되는 앙카브라켓과, 상기 앙카브라켓 단부에 수직으로 가변되는 스크류잭이 형성되는 것을 특징으로 한다. The support member may include an anchor bracket coupled to the bushing nut, and a screw jack vertically variable to an end of the anchor bracket.

그리고, 상기 메인폼은 스프래드 밴드폼에 형성되되 상기 횡빔부재 하측에 위치하는 하단사이드폼과, 상기 하단사이드폼 상측에 형성되되 종빔부재 하측에 형성되는 중간사이드품과, 상기 중간사이드품 상측에 형성되는 상단사이드폼으로 이루어지고, 상기 하단사이폼은 상측에 바닥폼이 설치되고, 상기 상단사이드폼은 상부에 탑타이가 형성되는 것을 특징으로 한다. And, the main form is formed on the spreading band form, the lower side foam positioned below the lateral beam member, the intermediate side formed on the lower side of the lower side foam formed on the lower side of the longitudinal beam member, and formed on the upper side of the intermediate side The upper side foam is formed, the lower side foam is a bottom foam is installed on the upper side, the upper side foam is characterized in that the top tie is formed on the top.

그리고, 상기 상단사이드폼은 하부면에 다수개의 삽입홈이 형성되어, 상기 종빔부재가 상기 삽입홈으로 삽입되는 것을 특징으로 한다. The upper side foam has a plurality of insertion grooves formed on a lower surface thereof, and the vertical beam member is inserted into the insertion groove.

그리고, 상기 메인폼은 다수개 연속적으로 형성되는 것을 특징으로 한다. And, the main form is characterized in that a plurality of consecutively formed.

그리고, 상기 스프래드 밴드폼에서 수평으로 돌출되는 스테빌리티빔과 상기 스테빌리티빔의 단부에 경사지게 결합되어 상기 하단사이드폼 외주면에 접촉되는 길이가 가변되는 경사부재에 의해 지지되는 것을 특징으로 한다. In addition, the stability beam protruding horizontally from the spread band form and the end of the stability beam is inclined coupled to be supported by the inclined member is variable in length in contact with the outer peripheral surface of the lower side form.

그리고, 상기 보강부재는 상기 횡빔부재의 상호간 결합강도를 높이기 위해, 일측이 상기 횡빔부재 각각에 접촉되고, 타측이 상기 스프래드 밴드폼에 형성되는 것을 특징으로 한다. In addition, the reinforcing member is characterized in that one side is in contact with each of the lateral beam members, and the other side is formed in the spread band form in order to increase the mutual coupling strength of the lateral beam members.

그리고, 상기 보강부재는 상기 횡빔부재을 상호간 연결하는는 상부사각판과, 상기 상부사각판에 수직으로 삽입되어 상기 스프래드 밴드폼과 상기 바닥폼을 관통하는 앙카와, 상기 앙카 상측에서 결합되어 상기 상부사각판을 누르는 상체결합볼트와, 상기 앙카 하측에서 결합되어 상기 스프래드 밴드폼 하측을 조으는 하체결합볼트로 이루어지는 것을 특징으로 한다. The reinforcing member includes an upper square plate connecting the lateral beam members to each other, an anchor inserted perpendicularly to the upper square plate and penetrating the spread band form and the bottom foam, and coupled to an upper portion of the anchor. The upper body coupling bolt for pressing the plate, and the lower body coupling bolt is coupled to the lower side of the anchor bolt to tighten the lower side characterized in that it consists of.

그리고, 상기 횡빔부재는 개방된 상부면에 경첩으로 개폐가능한 게이트를 설치한 후, 상기 게이트와 횡빔부재의 간극을 실리콘으로 마감하는 것을 특징으로 한다.
The lateral beam member is provided with a hinge that can be opened and closed on an open upper surface, and then the gap between the gate and the lateral beam member is finished with silicon.

이상에서 상술한 바와 같이, 교각 상부에 있는 코팅의 철재 거푸집, 철근, 콘크리트 작업하중이 적게는 수십톤에서 수백톤의 하중을 지지할 수 있어, 대규모 공사가 가능하고,As described above, the steel formwork, reinforcing bar, and concrete work load of the coating on the upper part of the bridge can support a load of several tens to hundreds of tons, so that large-scale construction is possible.

또한, 도심의 도로에서 지상정거장 및 교각기둥의 코핑은 도로 차선 중앙선에서 중심으로 구조물이 형성되되, 도로의 교통이 원활하고 작업 공간이 확보되어 안전사고를 예방할 수 있다.
In addition, while the coping of the ground station and the pier pillar in the city road is a structure formed from the center line of the road lane, the traffic on the road is smooth and work space is secured to prevent safety accidents.

도 1은 본 발명에 따른 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에서 지지봉부재와 지지부재를 도시하는 개념도.
도 2는 본 발명에 따른 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에서 스프래드 밴드폼이 설치된 실시도.
도 3은 본 발명에 따른 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에서 메인폼이 설치된 실시도.
도 4는 본 발명에 따른 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에서 보강부재를 도시사는 개념도.
도 5는 본 발명에 따른 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에서 상단사이드폼을 설치하는 실시도.
1 is a conceptual diagram showing a support rod member and a support member in the formwork and installation method of the steel coping structure of the ground station and pier pillar according to the present invention.
Figure 2 is an embodiment installed the spread band form in the formwork and installation method of the steel formwork and coping structure of the ground station and the pier pillar according to the present invention.
Figure 3 is an embodiment installed main form in the coping structure steel formwork and installation method of the ground station and pier pillar according to the present invention.
Figure 4 is a conceptual diagram showing the reinforcing member in the formwork and installation method of the steel coping structure of the ground station and pier pillar according to the present invention.
Figure 5 is an embodiment to install the upper side foam in the formwork and installation method of the steel formwork and coping structure of the ground station and the pier pillar according to the present invention.

이하, 첨부된 도면을 참조로 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법을 설명하기로 한다.Hereinafter, with reference to the accompanying drawings will be described the ground formwork and the steel formwork and installation method of the pier pillar pillar coping structure.

도 1은 본 발명에 따른 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에서 지지봉부재와 지지부재를 도시하는 개념도이고, 도 2는 본 발명에 따른 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에서 스프래드 밴드폼이 설치된 실시도이고, 도 3은 본 발명에 따른 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에서 메인폼이 설치된 실시도이고, 도 4는 본 발명에 따른 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에서 보강부재를 도시사는 개념도이고, 도 5는 본 발명에 따른 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에서 상단사이드폼을 설치하는 실시도이다.
1 is a conceptual view showing a support rod member and a support member in the coping structure steel formwork and installation method of the ground station and the pier pillar according to the present invention, Figure 2 is a coping structure steel formwork of the ground station and pier pillar according to the present invention and Spread band form is installed in the installation method, Figure 3 is the ground station according to the present invention and the coping structure steel formwork and installation method of the pier pillar according to the present invention, Figure 4 is the ground station according to the present invention And a conceptual diagram illustrating a reinforcing member in a coping structure steel formwork and installation method of a pier pillar, Figure 5 is an embodiment of installing the top side foam in the coping structure steel formwork and installation method of the ground station and pier pillar according to the present invention. .

도 1 내지 도 5에 도시된 바와 같이, 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에 있어서, 지면에 수직으로 설치된 철재 빔 소재의 교각기둥(10)과 상기 교각기둥 상측에 횡방향 결합되고 다수개 이루어진 횡빔부재(20)와 종방향으로 다수개 결합되는 종빔부재(30)를 설치하는 1단계, 상기 교각기둥(10)에 끝단에 부싱너트(130)를 포함한 지지봉부재(100)를 설치하는 2단계, 상기 교각기둥(10)에 거푸집을 설치한 후 상기 지지봉부재(100) 끝단까지 콘크리트를 타설하여 양생하는 3단계, 상기 지지봉부재(100)에 앙카브라켓(210)과 결합되는 지지부재(200)를 체결한 후, 상측에 사각으로 된 스프래드 밴드폼(300)를 상기 횡빔부재(20) 하측에 설치하는 4단계,상기 스프래드 밴드폼(300) 상측으로 상기 횡빔부재(20)와 상기 종빔부재(30)에 메인폼(50)을 설치하고, 상기 횡빔부재(20)를 상호간 지지하는 보강부재(400) 형성시키는 5단계로 이루어져, 교각 상부에 있는 코팅의 철재 거푸집, 철근, 콘크리트 작업하중이 적게는 수십톤에서 수백톤의 하중을 지지할 수 있어, 대규모 공사가 가능하고,As shown in Figures 1 to 5, in the coping structure steel formwork and installation method of the ground station and the pier pillar, the pier pillar 10 of the steel beam material vertically installed on the ground and the lateral coupling on the pier pillar And a first step of installing a plurality of horizontal beam members 20 and a longitudinal beam member 30 coupled in a plurality of longitudinal directions, and supporting rod members 100 including bushing nuts 130 at ends of the piers 10. Step 2 to install, after installing the formwork on the pier pillar (10) and three steps to cure by pouring concrete to the end of the support rod member 100, the support coupled to the anchor bracket 210 to the support rod member 100 After fastening the member 200, four steps of installing the square band foam 300 formed on the lower side of the lateral beam member 20 below the horizontal beam member 20 above the lateral beam member 20. ) And the main form 50 in the vertical beam member 30 And, it consists of five steps to form the reinforcing member 400 to mutually support the lateral beam member 20, the steel formwork of the coating on the top of the piers, reinforcement, concrete to support a load of several tens tons to hundreds of tons I can do it, and large-scale construction is possible,

또한, 도심의 도로에서 지상정거장 및 교각기둥(10)의 코핑은 도로 차선 중앙선에서 중심으로 구조물이 형성되되, 도로의 교통이 원활하고 작업 공간이 확보되어 안전사고를 예방할 수 있다.
In addition, the coping of the ground station and pier pillar 10 in the city road is a structure is formed from the center line of the road lane, the road traffic is smooth and work space is secured to prevent safety accidents.

이하, 각 구성을 상세히 설명하기로 한다.Hereinafter, each configuration will be described in detail.

본 발명에 따른 1단계는 지면에 수직으로 설치된 철재 빔 소재의 교각기둥(10)과 상기 교각기둥(10) 상측에 횡방향 결합되고 다수개 이루어진 횡빔부재(20)와 종방향으로 다수개 결합되는 종빔부재(30)를 설치하는 단계이다.In the first step according to the present invention, the pier pillar 10 of the steel beam material installed perpendicular to the ground and the lateral beam member 20 which is laterally coupled to the pierry pillar 10 and formed in plural number are longitudinally coupled to each other. The vertical beam member 30 is installed.

상기 교각기둥(10)은 지면에서 일정 높이를 이격시키기 위함으로, 철재 빔으로 된 소재를 지면과 수직방향으로 설치하게 된다.The pier pillar 10 is to be spaced a certain height from the ground, the material of the steel beam is installed in the vertical direction with the ground.

여기서, 보통 철재 빔은 에이치(H)빔으로 이루어지게 한다.Here, the steel beam is usually made of H (H) beam.

그리고, 상기 횡빔부재(20)는 철재 빔으로 상기 교각기둥(10)에 횡방향으로 결합되게 된다.In addition, the lateral beam member 20 is coupled to the pier pillar 10 in the transverse direction with an iron beam.

그리고, 상기 종빔부재(30)는 상기 횡빔부재(20)에 결합되되, 상기 교각기둥에서 종방향으로 결합되게 된다.In addition, the longitudinal beam member 30 is coupled to the lateral beam member 20, and is coupled in the longitudinal direction at the piers.

한편, 상기 교각기둥(10)이 강도와 경도가 강한 철재 빔이기 때문에 내부를 관통하여 거푸집등을 지지하는 부재를 설치할 수 없게 된다.
On the other hand, since the pier pillar 10 is a steel beam with strong strength and hardness, it is impossible to install a member that penetrates the interior and supports the formwork.

본 발명에 따른 2단계는 상기 교각기둥(10)에 끝단에 부싱너트(130)를 포함한 지지봉부재(100)를 설치하는 단계이다.Step 2 according to the present invention is a step of installing the support rod member 100 including a bushing nut 130 at the end of the pier pillar (10).

이는, 전술한 바와 같이 상기 교각기둥(10)은 강도와 경도가 강한 부재이므로 내부를 관통할 수 없으므로, 교각기둥(10) 외주측에 콘크리트를 타설한 후 후술되는 스프래드 밴드폼(300)을 지지하는 부재가 필요하게 된다.This is because, as described above, since the pier pillar 10 is a member having strong strength and hardness, it cannot penetrate the inside thereof, and after pouring concrete on the outer circumferential side of the pier pillar 10, the spread band form 300 to be described later is described. A supporting member is necessary.

따라서, 상기 지지봉부재(100)를 상기 교각기둥(10)에 용접으로 설치한 후 상기 스프래드 밴드폼(300)을 지지하게 된다.Therefore, the support rod member 100 is welded to the piers 10 to support the spread band form 300.

그리고, 지지봉부재(100)는 상기 교각기둥에 측면 둘레를 따라 전,후,좌,우다수개 설치되는 것이 좋으며, 2,4,6개등 짝수로 이루어지게 된다.In addition, the support rod member 100 is preferably installed in the pier pillar before, after, left, right along the side circumference, it is made of even number, such as 2, 4, 6.

바람직하게는, 상기 지지봉부재(100)는 상기 교각기둥(10)에 용접되는 스루바(110)와, 상기 스루바(110) 외주에 다수개 설치되는 원형 후렌지(120)와, 상기 스루바(110) 끝단에 설치되는 부싱너트(130)로 이루어지는 것이 좋다.Preferably, the support bar member 100 includes a through bar 110 welded to the pier pillar 10, a circular flange 120 installed on the outer circumference of the through bar 110, and the through bar ( 110) It is preferable to consist of a bushing nut 130 is installed at the end.

여기서, 상기 스루바(110)가 상기 교각기둥(10)에 용접되는 부분으로, 끝단부가 지면에 평형하게 용접되게 된다.Here, the through bar 110 is a portion welded to the pier pillar 10, the end portion is to be welded in parallel to the ground.

상기 원형 후렌지(120)는 상기 스루바(110) 외주에 다수개가 간격을 두고 설치되게 된다. 이는, 상기 스프래드 밴드폼(300)을 지지할 경우 발생되는 하중을 상기 원형 후렌지(120)로 분산하기 위함이다.The plurality of circular flanges 120 are installed on the outer periphery of the through bar 110 at intervals. This is to distribute the load generated when supporting the spread band form 300 to the circular flange 120.

그리고, 상기 부싱너트(130)는 상기 스루바(110)의 타측단부에 결합되어, 후술하는 지지부재(200)가 결합되게 된다.
And, the bushing nut 130 is coupled to the other end of the through bar 110, the support member 200 to be described later is coupled.

본 발명에 따른 3단계는 상기 교각기둥(10)에 거푸집을 설치한 후 상기 지지봉부재(100) 끝단까지 콘크리트를 타설하여 양생하게 된다.In the third step according to the present invention, after installing the formwork in the pier pillar 10, the concrete is poured to the end of the support rod member 100 to cure.

거푸집을 상기 지지봉 끝단까지 설치하여, 상기 교각기둥(10)과 거푸집 사이에 콘크리트를 타설하여 양생시키게 한다.By installing the formwork to the end of the support rod, the concrete is poured between the bridge pillar 10 and the formwork to cure.

여기서, 콘크리트는 상기 지지봉부재(100) 끝단까지 타설되도록 한다. 따라서, 상기 지지봉부재(100)의 부싱너트(130)의 단부까지 타설되게 된다.Here, concrete is to be poured to the end of the support rod member (100). Therefore, the end of the bushing nut 130 of the support rod member 100 is poured.

즉, 상기 부싱너트(130)의 전방 개구된 부분이 콘크리트 타설된 외주면에 일치하게 된다.That is, the front opening portion of the bushing nut 130 coincides with the outer circumferential surface of the concrete.

바람직하게는, 상기 3단계에서 콘크리트가 타설되어 상기 부싱너트(130)로 인입되는 것을 방지하기 위해 상기 부싱너트(130)에 스치로품을 삽입하여 청테이프로 밀봉 마감처리하는 것이 좋다.Preferably, in order to prevent the concrete from being poured into the bushing nut 130 in the third step, it is preferable to insert a squeegee product into the bushing nut 130 and seal it with a clean tape.

이는, 거푸집 타설 후 다량의 콘크리트가 타설될 때, 측면으로 분출되어 상기 부싱너트(130) 전측으로 인입되던지, 거푸집보다 상기 부싱너트(130)가 내측으로 되는 경우도 부싱너트(130) 전측으로 콘크리트가 인입될 수 있으므로, 이를 방지하기 위해서 부싱너트(130) 전측으로 스치로품을 삽입하여 청테이프로 부싱너트(130) 전측을 밀봉 마감처리 한다.
This is, when a large amount of concrete is poured after the formwork is poured into the front side of the bushing nut 130 is poured into the side, or even if the bushing nut 130 to the inside than the formwork bushing nut 130 to the front side Since concrete may be drawn in, a seal product is inserted into the front side of the bushing nut 130 to prevent the sealing, and the front side of the bushing nut 130 is sealed with a blue tape.

본 발명에 따른 4단계는 상기 지지봉부재(100)에 앙카브라켓(210)과 결합되는 지지부재(200)를 체결한 후, 상측에 사각으로 된 스프래드 밴드폼(300)를 상기 횡빔부재(20) 하측에 설치하는 단계이다. In the fourth step according to the present invention, after fastening the support member 200 coupled with the anchor bracket 210 to the support rod member 100, the horizontal band member 300 is formed on the upper side of the square band form 300. ) It is a step to install on the lower side.

이는, 상기 스프래드 밴드폼(300)을 설치하여, 거푸집인 상기 메인폼(50)을 차례대로 설치하기 위함이다.This is to install the spread band form 300, to install the main form 50 formwork in order.

그리고, 상기 지지부재(200)는 상기 부싱너트(130)에 결합되는 앙카브라켓(210)과, 상기 앙카브라켓(210) 단부에 수직으로 가변되는 스크류잭(220)이 형성되는 것이 좋다.In addition, the support member 200 may include an anchor bracket 210 coupled to the bushing nut 130 and a screw jack 220 vertically variable at an end of the anchor bracket 210.

상기 앙카브라켓(210)은 상기 부싱너트(130)에 결합되어 상기 스프래드 밴드폼(300)을 지지하는 하부 부재가 되며, 상기 스크류잭(220)이 상기 앙카브라켓(210) 단부에 설치되어 상기 스프래드 밴드폼(300) 하부면에 접촉되어, 스프래드 밴드폼(300)을 지지하게 된다.The anchor bracket 210 is coupled to the bushing nut 130 to be a lower member supporting the spread band form 300, and the screw jack 220 is installed at the end of the anchor bracket 210 In contact with the lower surface of the spread band form 300, to support the spread band form 300.

여기서, 상기 스크류잭(220)은 가변되도록 하여, 상기 스프래드 밴드폼(300)이 하부면에 완전하게 접촉되도록 한다.
Here, the screw jack 220 is variable, so that the spread band form 300 is in complete contact with the lower surface.

바람직하게는, 제 3단계와 상기 4단계 사이에는 상기 교각기둥(10)에 상기 지지봉부재(100) 하측으로 작업용밴드폼(350)을 설치하고, 상기 작업용밴드폼(350) 단부에 수직으로 핸드레일파이프(360)를 수직으로 설치하여 작업자가 낙하하는 것을 방지하는 것이 좋다.
Preferably, between the third step and the fourth step, the work band form 350 is installed in the pier pillar 10 below the support rod member 100 and the hand is perpendicular to the end of the work band form 350. It is good to prevent the worker from falling by installing the rail pipe 360 vertically.

본 발명에 따른 5단계는 상기 스프래드 밴드폼(300) 상측으로 상기 횡빔부재(20)와 상기 종빔부재(30)에 메인폼(50)을 설치하고, 상기 횡빔부재(20)를 상호간 지지하는 보강부재(400) 형성시키는 단계이다.In the fifth step according to the present invention, the main form 50 is installed on the lateral beam member 20 and the longitudinal beam member 30 to the upper side of the spread band form 300, and the lateral beam member 20 is reinforced to support each other. The forming of the member 400 is performed.

상기 메인폼(50)은 일반적인 거푸집으로 상기 횡빔부재(20)와 상기 종빔부재(30)에 콘크리트가 타설되도록 상기 스프래드 밴드폼(300) 상측에 설치한다.The main form 50 is installed on the upper side of the spread band form 300 so that concrete is poured into the horizontal beam member 20 and the vertical beam member 30 as a general formwork.

여기서, 상기 횡빔부재(20)와 상기 종빔부재(30)의 구조적 형상에 의해 상기 메인폼(50)은 다수개의 폼으로 나뉘어져 설치하게 된다.Here, the main form 50 is divided into a plurality of foams and installed by the structural shapes of the lateral beam member 20 and the longitudinal beam member 30.

바람직하게는, 상기 메인폼(50)은 스프래드 밴드폼(300)에 형성되되 상기 횡빔부재(20) 하측에 위치하는 하단사이드폼(52)과, 상기 하단사이드폼(52) 상측에 형성되되 종빔부재(30) 하측에 형성되는 중간사이드품(54)과, 상기 중간사이드품(54) 상측에 형성되는 상단사이드폼(56)으로 이루어지고, 상기 하단사이폼은 상측에 바닥폼(57)이 설치되고, 상기 상단사이드폼(56)은 상부에 탑타이(58)가 형성되는 것이 좋다.Preferably, the main form 50 is formed on the spread band form 300, the lower side form 52 and the lower side formed on the lower side of the horizontal beam member 20, the lower side form 52 is formed on the longitudinal beam The intermediate side article 54 formed below the member 30 and the upper side form 56 formed above the intermediate side article 54, and the lower side foam, the bottom foam 57 on the upper side Is installed, the top side foam 56 is preferably a top tie 58 is formed on the top.

바람직하게는, 상기 메인폼(50)은 다수개 연속적으로 형성되는 것이 좋다.Preferably, the main form 50 is preferably formed in plurality continuously.

먼저, 상기 하단사이드폼(52)을 상기 스프래드 밴드폼(300)에 설치하게 된다. 여기서, 상기 하단사이드폼(52)은 상기 횡빔부재(20)의 길이방향으로 설치되게 되고, 각종 체결부재(볼트,너트,나사,못등)에 의해 결합되게 된다.First, the lower side form 52 is installed on the spread band form 300. Here, the lower side form 52 is installed in the longitudinal direction of the lateral beam member 20, and is coupled by various fastening members (bolts, nuts, screws, nails, etc.).

또한, 상기 횡빔부재(20)의 길이방향의 폭이 일정하지 않으므로, 상기 하단사이드폼(52) 상호간은 상기 횡빔부재(20)의 길이방향으로 다수개 연결 결합이 가능하다.In addition, since the width of the longitudinal direction of the lateral beam member 20 is not constant, the lower side form 52 can be connected to a plurality of lateral beam member 20 in the longitudinal direction of each other.

그리고, 상기 하단사이드폼(52) 상부를 폐쇄시키기 위해 상측면을 덮는 바닥폼(57)을 설치하게 된다.Then, in order to close the upper portion of the lower side foam 52, a bottom foam 57 covering the upper side is installed.

이는, 콘크리트가 상기 바닥폼(57)을 기준으로 타설되기 위함이다.This is for concrete to be poured on the basis of the bottom foam (57).

다음으로, 상기 횡빔부재(20)를 상호간 지지하는 보강부재(400) 형성시킨다.Next, the reinforcing member 400 for supporting the transverse beam member 20 is formed.

이는, 상기 횡빔부재(20)는 상기 종빔부재(30)를 하중을 지지해야 하므로, 상호간 결합력을 증대시기 위함이다.This is because the lateral beam member 20 is required to support the load of the longitudinal beam member 30, so as to increase the mutual coupling force.

즉, 상기 횡빔부재(20) 상호간 상기 보강부재(400)를 설치하므로, 상기 교각기둥(10)을 중심으로 좌우로 흔들리거나 어긋나지 않게 된다.That is, since the reinforcing members 400 are installed between the lateral beam members 20, the horizontal beam members 20 do not shake or shift left and right about the piers 10.

바람직하게는, 상기 보강부재(400)는 상기 횡빔부재(20)의 상호간 결합강도를 높이기 위해, 일측이 상기 횡빔부재(20) 각각에 접촉되고, 타측이 상기 스프래드 밴드폼(300)에 형성되는 것이 좋다.Preferably, the reinforcing member 400, in order to increase the mutual coupling strength of the lateral beam member 20, one side is in contact with each of the lateral beam member 20, the other side is formed in the spread band form 300 It is good to be.

이는, 상기 보강부재(400)의 일측이 상기 횡빔부재(20)에 접촉되어 상호간 결합시키고, 타측이 상기 스프래드 밴드폼(300)에 걸리게 형성시켜 지지하도록 하기 위함이다.This is to allow one side of the reinforcing member 400 to be in contact with the lateral beam member 20 to be coupled to each other, and to support the other side to be caught by the spread band form 300.

더욱 바람직하게는, 상기 보강부재(400)는 상기 횡빔부재(20)을 상호간 연결하는 상부사각판(410)과, 상기 상부사각판(410)에 수직으로 삽입되어 상기 스프래드 밴드폼(300)과 상기 바닫폼을 관통하는 앙카(420)와, 상기 앙카(420) 상측에서 결합되어 상기 상부사각판(410)을 누르는 상체결합볼트(430)와, 상기 앙카(420) 하측에서 결합되어 상기 스프래드 밴드폼(300) 하측을 조으는 하체결합볼트(440)로 이루어지는 것이 좋다.More preferably, the reinforcing member 400 is inserted into the upper square plate 410 and the upper square plate 410 vertically connecting the lateral beam member 20, the spread band form 300 And an anchor 420 penetrating the bar foam, an upper coupling bolt 430 coupled to the anchor 420 to press the upper square plate 410, and coupled to the anchor 420 below. The lower band form 300 is preferably made of a lower coupling bolt 440 tightening the lower side.

상기 상부사각판(410)은 스틸강판으로 상기 횡빔부재(20) 상호간 상측면에 접촉되어 상기 상체결합볼트(430)가 상기 상부사각판(410)을 압착하여, 횡빔부재(20)가 벌어지거나 움직이는 것을 억제하게 한다.The upper square plate 410 is a steel steel plate in contact with the upper side surface of the lateral beam member 20, the upper coupling bolt 430 compresses the upper square plate 410, the horizontal beam member 20 is opened or It keeps you from moving.

상기 앙카(420)는 상기 상부사각판(410)에 삽입되어 상기 스프래드 밴드폼(300)과 상기 바닥폼(57)을 관통하게 된다.The anchor 420 is inserted into the upper square plate 410 to pass through the spread band form 300 and the bottom form (57).

따라서, 상기 상부결합볼트는 상기 앙카(420)의 상측에서 결합되어 상기 상부사각판(410)을 상부면에서 조으고, 상기 하부결합볼트는 상기 스프래드 밴드폼(300) 하측에서 결합되어 하부면을 조으게 된다.Therefore, the upper coupling bolt is coupled from the upper side of the anchor 420 to tighten the upper square plate 410 from the upper surface, the lower coupling bolt is coupled from the lower side of the spread band form 300 lower surface Tighten.

이로 인해, 상기 상부결합볼트와 상기 하부결합볼트가 상하에서 누르는 힘에 의해 상기 횡빔부재(20)가 벌어지거나 움직이는 것을 억제하게 한다.As a result, the horizontal coupling member 20 is prevented from being opened or moved by the pressing force of the upper coupling bolt and the lower coupling bolt up and down.

다음으로, 상기 중간사이드품(54)을 상기 하단사이드폼(52) 상측을 따라 설치하게 된다. 여기서, 상기 중간사이드품(54)의 높이는 상기 횡빔부재(20)의 상측면을 넘지 않도록 한다.Next, the intermediate side article 54 is installed along the upper side of the lower side form 52. Here, the height of the intermediate side article 54 does not exceed the upper surface of the transverse beam member 20.

다음으로, 상기 상단사이드폼(56) 하측면과 상기 중간사이드품(54) 상측면을 체결부재를 통해 체결하게 된다.Next, the lower side surface of the upper side foam 56 and the upper side surface of the intermediate side article 54 are fastened through the fastening member.

바람직하게는, 상기 상단사이드폼(56)은 하부면에 다수개의 삽입홈(59)이 형성되어, 상기 종빔부재(30)가 상기 삽입홈(59)으로 삽입되는 것이 좋다.Preferably, the upper side form 56 is formed with a plurality of insertion grooves 59 on the lower surface, it is preferable that the longitudinal beam member 30 is inserted into the insertion groove (59).

그리고, 상기 횡빔부재(20)는 개방된 상부면에 경첩으로 개폐가능한 게이트(21)를 설치한 후, 상기 게이트와 횡빔부재의 간극을 실리콘으로 마감하는 것이 좋다. In addition, the horizontal beam member 20 may be provided with a hinge 21 on the open upper surface, which may be opened and closed by a hinge, and then the gap between the gate and the horizontal beam member may be finished with silicon.

상술하면, 횡빔부재는 'H'자 형상으로 이루어지므로, 콘크리트 타설시 상부에 개구된 공간으로 콘크리트가 인입될 가능성이 있으므로, 이를 방지하기 위해 상기 횡빔부재 상부면에 경첩으로 개폐가능한 게이트를 설치하고, 상기 게이트와 횡빔부재의 간극을 실리콘으로 마감하는 처리 하는 것이 좋다.
In detail, since the lateral beam member is formed in an 'H' shape, concrete may be introduced into the space opened at the time of concrete placement, and thus, a gate that can be opened and closed by a hinge is installed on the upper surface of the lateral beam member to prevent this. In addition, the gap between the gate and the lateral beam member may be treated to finish with silicon.

이는, 상기 종빔부재(30) 종방향에는 다수개의 횡빔부재(20)들이 결합되어 있으므로, 상기 삽입홈(59)을 통해 상기 종빔부재(30)들이 끼이도록 한다.This is because a plurality of the horizontal beam members 20 are coupled in the longitudinal direction of the longitudinal beam member 30, so that the longitudinal beam members 30 are pinched through the insertion groove 59.

다음으로, 상기 상단사이드폼(56) 상측에 탑타이(58)가 형성되게 한다.Next, the top tie 58 is formed on the upper side form 56.

그러면, 상기 메인폼(50)이 다 설치되면, 콘크르트를 타설하여 양생을 하게 된다. Then, when the main form 50 is all installed, the concrete is poured to cure.

바람직하게는, 상기 스프래드 밴드폼(300)에서 수평으로 돌출되는 스테빌리티빔(420)과 상기 스테빌리티빔(420)의 단부에 경사지게 결합되어 상기 하단사이드폼(52) 외주면에 접촉되는 길이가 가변되는 경사부재(430)에 의해 지지되는 것이 좋다.Preferably, the length of the stability beam 420 protruding horizontally from the spread band form 300 and the end of the stability beam 420 is inclined to contact the outer peripheral surface of the lower side form (52) It is preferably supported by the variable inclined member 430.

이는, 상기 중간사이드품(54), 상기 바닥폼(57), 상기 상단사이드폼(56) 및 상기 탑타이(58)등을 원활하게 설치하기 위함으로, 상기 스테빌리티빔(420)을 상기 스프래드밴드폼에서 외측으로 수평하게 설치하고, 가변되는 경사부재(430)를 상기 하단사이드폼(52)에 접촉시켜 하단사이드폼(52)이 움직이지 않도록 길이를 조절하게 된다.This is to smoothly install the middle side article 54, the bottom form 57, the top side form 56 and the top tie 58, the stability beam 420 to the soup. It is installed horizontally outward from the red band form, the variable inclined member 430 is in contact with the lower side form 52 to adjust the length so that the lower side form 52 does not move.

그리고, 상기 경사부재(430) 상측으로, 작업에 용이하도록 작업용밴드폼(350)등을 설치하여, 상기 중간사이드품(54), 상기 바닥폼(57), 상기 상단사이드폼(56) 및 상기 탑타이(58)등이 설치되도록 한다.
And, the upper side of the inclined member 430, by installing a work band form 350, etc. to facilitate the work, the middle side product 54, the bottom form 57, the top side form 56 and the The top tie 58 is to be installed.

이상과 같이, 지상정거장 및 교각기둥의 코핑 구조물에 철재 거푸집을 설치하는 것을 기본적인 기술적 사상으로 하며, 이는 예시적인 것에 불과하며, 당해 분야에서 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 실시예가 가능하다는 점을 이해할 것인바, 본 발명의 진정한 기술적 보호범위는 첨부된 청구범위에 한해서 정해져야 할 것이다.As described above, it is a basic technical idea to install steel formwork in the coping structure of the ground station and the pier pillar, which is merely exemplary, and those skilled in the art have various modifications and equivalent implementation therefrom. It will be appreciated that examples are possible, and the true technical scope of the invention should be defined only by the appended claims.

10: 교각기둥 20: 횡빔부재
30: 종빔부재 50: 메인폼
52: 하단사이드폼 54: 중간사이드폼
56: 상단사이드폼 57: 바닥폼
58: 탑타이 100: 지지봉부재
200: 지지부재 300: 스프래드 밴드폼
400: 보강부재
10: pier pillar 20: transverse beam member
30: longitudinal beam member 50: main form
52: lower side foam 54: middle side foam
56: top side foam 57: bottom foam
58: top tie 100: support rod member
200: support member 300: spread band foam
400: reinforcing member

Claims (12)

지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법에 있어서,
지면에 수직으로 설치된 철재 빔 소재의 교각기둥(10)과 상기 교각기둥 상측에 횡방향 결합되고 다수개 이루어진 횡빔부재(20)와 종방향으로 다수개 결합되는 종빔부재(30)를 설치하는 1단계;
상기 교각기둥(10)에 끝단에 부싱너트(130)를 포함한 지지봉부재(100)를 설치하는 2단계;
상기 교각기둥(10)에 거푸집을 설치한 후 상기 지지봉부재(100) 끝단까지 콘크리트를 타설하여 양생하는 3단계;
상기 지지봉부재(100)에 앙카브라켓(210)과 결합되는 지지부재(200)를 체결한 후, 상측에 사각으로 된 스프래드 밴드폼(300)를 상기 횡빔부재(20) 하측에 설치하는 4단계;
상기 스프래드 밴드폼(300) 상측으로 상기 횡빔부재(20)와 상기 종빔부재(30)에 메인폼(50)을 설치하고, 상기 횡빔부재(20)를 상호간 지지하는 보강부재(400) 형성시키는 5단계로, 이루어지는 것윽 특징으로 하는 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법.
In the steel formwork and installation method of the coping structure of the ground station and piers,
The first step of installing the pier pillar 10 of the steel beam material vertically installed on the ground and the longitudinal beam member 30 coupled in the longitudinal direction with the lateral beam member 20 which is laterally coupled to the upper side of the pier pillar ;
Installing a supporting rod member (100) including a bushing nut (130) at the end of the pier (10);
After installing the formwork to the pier pillar (10) three steps of curing by pouring concrete to the end of the support rod member (100);
After fastening the support member 200 coupled with the anchor bracket 210 to the support rod member 100, a fourth step of installing the square band form 300 on the lower side of the horizontal beam member 20 is provided. ;
The main form 50 is installed on the lateral beam member 20 and the longitudinal beam member 30, and the reinforcement member 400 supporting the lateral beam member 20 is formed to the upper side of the spread band form 300. Steps, consisting of the steel formwork and installation method of the coping structure of the ground station and piers pillars.
제 1항에 있어서,
상기 지지봉부재(100)는,
상기 교각기둥(10)에 용접되는 스루바(110)와;
상기 스루바(110) 외주에 다수개 설치되는 원형 후렌지(120)와;
상기 스루바(110) 끝단에 설치되는 부싱너트(130)로 이루어지는 것을 특징으로 하는 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법.
The method of claim 1,
The support rod member 100,
A through bar 110 welded to the piers 10;
A circular flange 120 installed on the outer circumference of the through bar 110;
Coping structure steel formwork and installation method of the ground station and the piers pillars, characterized in that consisting of a bushing nut 130 is installed at the end of the through bar (110).
제 2항에 있어서,
상기 3단계에서 콘크리트가 타설되어 상기 부싱너트(130)로 인입되는 것을 방지하기 위해 상기 부싱너트(130)에 스치로품을 삽입하여 청테이프로 밀봉 마감처리하는 것을 특징으로 하는 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법.
3. The method of claim 2,
In order to prevent the concrete from being poured into the bushing nut 130 in the third step, a ground stop and a pier pillar are inserted into the bushing nut 130 and sealed with a chunky tape. Coping structures steel formwork and installation method.
제 1항에 있어서,
제 3단계와 상기 4단계 사이에는,
상기 교각기둥(10)에 상기 지지봉부재(100) 하측으로 작업용밴드폼(350)을 설치하고, 상기 작업용밴드폼(350) 단부에 수직으로 핸드레일파이프(360)를 수직으로 설치하여 작업자가 낙하하는 것을 방지하는 것을 특징으로 하는 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법.
The method of claim 1,
Between the third step and the fourth step,
The work band form 350 is installed below the support bar member 100 in the pier pillar 10, and the handrail pipe 360 is vertically installed vertically at the end of the work band form 350, thereby causing the worker to drop. Coping structure steel formwork and installation method of ground stations and piers pillars characterized in that to prevent.
제 1항에 있어서,
상기 지지부재(200)는,
상기 부싱너트(130)에 결합되는 앙카브라켓(210)과, 상기 앙카브라켓(210) 단부에 수직으로 가변되는 스크류잭(220)이 형성되는 것을 특징으로 하는 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법.
The method of claim 1,
The support member 200,
An anchor bracket 210 coupled to the bushing nut 130 and a screw jack 220 that is vertically variable at an end of the anchor bracket 210 are formed. And installation method.
제 1항에 있어서,
상기 메인폼(50)은,
스프래드 밴드폼(300)에 형성되되 상기 횡빔부재(20) 하측에 위치하는 하단사이드폼(52)과, 상기 하단사이드폼(52) 상측에 형성되되 종빔부재(30) 하측에 형성되는 중간사이드품(54)과, 상기 중간사이드품(54) 상측에 형성되는 상단사이드폼(56)으로 이루어지고,
상기 하단사이드폼(52)은 상측에 바닥폼(57)이 설치되고, 상기 상단사이드폼(56)은 상부에 탑타이(58)가 형성되는 것을 특징으로 하는 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법.
The method of claim 1,
The main form 50,
A middle side formed on the spread band form 300, but is formed on the lower side form 52 and the lower side form 52, the lower side side foam 52 formed on the lower side of the longitudinal beam member 30 The article 54 and the upper side foam 56 formed above the intermediate side article 54,
The bottom side foam 52 is a bottom foam 57 is installed on the upper side, the top side foam 56 is a coping structure of the ground station and piers pillars characterized in that the top tie 58 is formed on the top Formwork and installation method.
제 6항에 있어서,
상기 상단사이드폼(56)은,
하부면에 다수개의 삽입홈(59)이 형성되어, 상기 종빔부재(30)가 상기 삽입홈(59)으로 삽입되는 것을 특징으로 하는 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법.
The method according to claim 6,
The upper side foam 56,
A plurality of insertion grooves (59) is formed on the lower surface, the longitudinal beam member 30 is a coping structure steel formwork and installation method of the ground station and piers pillars, characterized in that inserted into the insertion groove (59).
제 6항에 있어서,
상기 메인폼(50)은,
다수개 연속적으로 형성되는 것을 특징으로 하는 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법.
The method according to claim 6,
The main form 50,
Coping structure steel formwork and installation method of the ground station and piers pillars characterized in that a plurality of consecutively formed.
제 6항에 있어서,
상기 스프래드 밴드폼(300)에서 수평으로 돌출되는 스테빌리티빔(420)과 상기 스테빌리티빔(420)의 단부에 경사지게 결합되어 상기 하단사이드폼(52) 외주면에 접촉되는 길이가 가변되는 경사부재(430)에 의해 지지되는 것을 특징으로 하는 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법.
The method according to claim 6,
An inclined member having a length varying in contact with an outer circumferential surface of the lower side form 52 by being inclinedly coupled to the end of the stability beam 420 and the stability beam 420 protruding horizontally from the spread band form 300. Coping structure steel formwork and installation method of the ground station and piers pillars, characterized in that supported by (430).
제 1항에 있어서,
상기 보강부재(400)는,
상기 횡빔부재(20)의 상호간 결합강도를 높이기 위해, 일측이 상기 횡빔부재(20) 각각에 접촉되고, 타측이 상기 스프래드 밴드폼(300)에 형성되는 것을 특징으로 하는 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법.
The method of claim 1,
The reinforcing member 400,
In order to increase the mutual coupling strength of the lateral beam member 20, one side is in contact with each of the lateral beam members 20, the other side of the ground station and the piers pillars, characterized in that formed on the spread band form 300 Coping Structure Steel Formwork and Installation Method.
제 10항에 있어서,
상기 보강부재(400)는,
상기 횡빔부재(20)을 상호간 연결하는는 상부사각판(410)과, 상기 상부사각판(410)에 수직으로 삽입되어 상기 스프래드 밴드폼(300)과 바닥폼(57)을 관통하는 앙카(420)와, 상기 앙카(420) 상측에서 결합되어 상기 상부사각판(410)을 누르는 상체결합볼트(430)와, 상기 앙카(420) 하측에서 결합되어 상기 스프래드 밴드폼(300) 하측을 조으는 하체결합볼트(440)로 이루어지는 것을 특징으로 하는 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법.
The method of claim 10,
The reinforcing member 400,
An anchor 420 connecting the lateral beam members 20 to each other is inserted into the upper square plate 410 and vertically inserted into the upper square plate 410 and penetrates the spread band form 300 and the bottom form 57. ) And the upper coupling bolt 430 coupled to the upper side of the anchor 420 to press the upper square plate 410, and coupled to the lower side of the anchor 420 to tighten the lower side of the spread band form 300. Coping structure steel formwork and installation method of the ground station and piers pillars characterized in that the lower body coupling bolt (440).
제 6항에 있어서,
상기 횡빔부재(20)는,
개방된 상부면에 경첩으로 개폐가능한 게이트(21)를 설치한 후, 상기 게이트(21)와 횡빔부재(20)의 간극을 실리콘으로 마감하는 것을 특징으로 하는 지상정거장 및 교각기둥의 코핑 구조물 철재 거푸집 및 설치 방법.

The method according to claim 6,
The transverse beam member 20,
After installing the gate 21 that can be opened and closed by a hinge on the open upper surface, the steel formwork of the ground station and the piers pillars, characterized in that the gap between the gate 21 and the transverse beam member 20 to finish with silicon And installation method.

KR1020110134520A 2011-12-14 2011-12-14 Construct method of plate coping girder form KR101345405B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110134520A KR101345405B1 (en) 2011-12-14 2011-12-14 Construct method of plate coping girder form

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110134520A KR101345405B1 (en) 2011-12-14 2011-12-14 Construct method of plate coping girder form

Publications (2)

Publication Number Publication Date
KR20130067696A KR20130067696A (en) 2013-06-25
KR101345405B1 true KR101345405B1 (en) 2013-12-30

Family

ID=48863472

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110134520A KR101345405B1 (en) 2011-12-14 2011-12-14 Construct method of plate coping girder form

Country Status (1)

Country Link
KR (1) KR101345405B1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112252167B (en) * 2020-10-14 2022-05-06 浙江世润建创科技发展有限公司 Bridge capping beam and construction method
CN113073554A (en) * 2021-03-08 2021-07-06 中国葛洲坝集团路桥工程有限公司 Large-tonnage anchorage structure on steep slope and construction method thereof
KR102572275B1 (en) 2021-03-11 2023-08-28 김용태 Mounting bracket of concrete beam, Constructing method for Mounting bracket of concrete beam

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100809886B1 (en) * 2006-05-02 2008-03-06 한성산업(주) Coping form system and method for constructing bridge pier using thereof
KR20090041189A (en) * 2007-10-23 2009-04-28 삼성물산 주식회사 Pier and the construction method for the same

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100809886B1 (en) * 2006-05-02 2008-03-06 한성산업(주) Coping form system and method for constructing bridge pier using thereof
KR20090041189A (en) * 2007-10-23 2009-04-28 삼성물산 주식회사 Pier and the construction method for the same

Also Published As

Publication number Publication date
KR20130067696A (en) 2013-06-25

Similar Documents

Publication Publication Date Title
CN108729354B (en) Downstream bridge movable formwork and construction method thereof
KR101129698B1 (en) Hanger type temporary resources for cantilever and method for construction of cantilever part of bridge using the temporary resources
KR102321338B1 (en) Segmental precast concrete ventilating slabs of structure and construction way in tunnel for rapid installation
KR101345405B1 (en) Construct method of plate coping girder form
CN102277835A (en) Method for constructing single-column bent cap by adopting hoop and A-frame composite system
CN106930315B (en) A kind of moving tower crane foundation structure and construction method
CN103046475A (en) Tool type movable formwork for large-span multi-span continuous beam and construction method of formwork
CN103321155A (en) Viaduct pier construction platform system and method for building system and pouring piers
KR101092151B1 (en) A green arch bridge use of arch panel
KR20140139272A (en) A beam mold and a saddle moving and supporting the beam mold
CN102733599A (en) Fastener type steel pipe scaffold framework support applicable to steel reinforced concrete beam
KR101176846B1 (en) Structure for reinforcing proof stress of girder
CN101793012B (en) Novel non-bracket bridge constructing method
JP6374353B2 (en) How to build a bridge
KR101661449B1 (en) Methods for controlling the camber of the cantilever truss half precast panel and, constructing methods using the same
TWM641106U (en) Hollow cladding board
CN203307733U (en) Construction platform system of concrete pier of viaduct
CN102913007B (en) Steel reinforcement processing shed and construction method therefor
CN214993171U (en) Bridge bent cap construction is with assembled sectional shelf-unit platform
CN211420881U (en) Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam
CN107761574B (en) Midspan folding device for swivel groove-shaped continuous beam of service line of electrified railway
KR200432268Y1 (en) Cover Plate integrated with the Frame
CN219059775U (en) Supporting system for bent cap construction
CN111779169B (en) Support-free assembled formwork device for ribbed floor and construction method
CN112144655B (en) Steel structure traveling protection channel system in building and construction method thereof

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application
AMND Amendment
X701 Decision to grant (after re-examination)
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20161219

Year of fee payment: 4

LAPS Lapse due to unpaid annual fee