KR101293683B1 - Suspention method for buried structures using joint member - Google Patents

Suspention method for buried structures using joint member Download PDF

Info

Publication number
KR101293683B1
KR101293683B1 KR1020120046094A KR20120046094A KR101293683B1 KR 101293683 B1 KR101293683 B1 KR 101293683B1 KR 1020120046094 A KR1020120046094 A KR 1020120046094A KR 20120046094 A KR20120046094 A KR 20120046094A KR 101293683 B1 KR101293683 B1 KR 101293683B1
Authority
KR
South Korea
Prior art keywords
obstacle
wing
wing member
hanging
upper support
Prior art date
Application number
KR1020120046094A
Other languages
Korean (ko)
Inventor
양성호
박부성
우동인
이타
Original Assignee
쌍용건설 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 쌍용건설 주식회사 filed Critical 쌍용건설 주식회사
Priority to KR1020120046094A priority Critical patent/KR101293683B1/en
Application granted granted Critical
Publication of KR101293683B1 publication Critical patent/KR101293683B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/06Separating, lifting, removing of buildings; Making a new sub-structure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Electrochemistry (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE: A suspension method for an obstruction using a wing member is provided to improve workability and stability of a work and to prevent an obstruction from being damaged. CONSTITUTION: A suspension method for an obstruction using a wing member comprises as follows. An upper support unit (100) is installed on the upper part of an obstruction (1). A side of the obstruction is preliminarily excavated. A wing member (200) is individually installed on both sides of the obstruction. The wing member and the upper support unit are connected by a connection member (300). The lower part of the obstruction is excavated.

Description

날개부재를 이용한 지장물 매달기 공법{SUSPENTION METHOD FOR BURIED STRUCTURES USING JOINT MEMBER}Hanging obstacles using wing member {SUSPENTION METHOD FOR BURIED STRUCTURES USING JOINT MEMBER}

본 발명은 건설 분야에 관한 것으로서, 상세하게는 지장물의 매달기 공법에 관한 것이다.The present invention relates to the construction field, and more particularly, to a hanging method of obstacles.

하수관로, 전선관로 등의 지장물(1)이 매설된 구간의 하부에 개착식 공법에 의해 지하도로, 전철 등의 지중구조물(a)을 시공하여야 하는 경우, 공사구간에 노출되는 지장물(1)은 별도의 임시구조물에 의해 임시로 매달아 두는 것이 필요하다(도 1,2).Obstacles (1) exposed to the construction section when underground structures (a) such as underground roads and trains must be constructed by the submerged construction method in the lower part of the section where the obstacles (1) such as sewer pipes and wire conduits are buried. It is necessary to temporarily hang by a separate temporary structure (Fig. 1,2).

도 1,2는 종래의 지장물 매달기 공법을 설명하기 위한 도면이다.1 and 2 are views for explaining a conventional obstacle hanging method.

도시된 바와 같이, 먼저 말뚝(11)에 의해 지지되는 폭방향 빔(13)을 설치하고, 지장물(1)의 양측을 굴착한 후, 양단이 폭방향 빔(13)에 의해 지지되는 와이어(2)를 지장물(1)을 둘러 설치한다.As shown in the drawing, first, the widthwise beam 13 supported by the pile 11 is installed, and both sides of the obstacle 1 are excavated, and then both ends of the wire supported by the widthwise beam 13 ( Install 2) around obstacles (1).

지장물(1)이 사각형 단면의 구조인 경우, 와이어(2)가 직접 지장물(1)의 모서리에 접촉하면 꺾임에 의한 파손의 문제가 있으므로, 와이어(2)와 지장물(1) 사이에는 각목 등의 간격재(3)를 설치하여, 모서리 영역에서 와이어(2)가 완만한 각도로 절곡되도록 한다.In the case where the obstacle 1 has a rectangular cross-sectional structure, there is a problem of breakage due to bending when the wire 2 directly contacts the edge of the obstacle 1, so that the obstacle 2 between the wire 2 and the obstacle 1 Spacers 3, such as wood, are installed so that the wires 2 are bent at a gentle angle in the corner region.

이 상태에서 지장물(1)의 하부를 굴착하고, 메인말뚝(12)에 설치된 브라켓(21)에 서브 빔(22) 및 메인 빔(23)을 설치하여, 메인 빔(23)이 지장물(1)의 하단에 접촉함으로써, 지장물(1)이 상측으로 지지되도록 한다.In this state, the lower part of the obstacle 1 is excavated, and the sub beam 22 and the main beam 23 are installed in the bracket 21 provided on the main pile 12, so that the main beam 23 is the obstacle ( By contacting the lower end of 1), the obstacle 1 is supported upward.

메인 빔(23)과 지장물(1)의 하단의 안정적인 접촉을 위하여, 그 사이에 충전재(24)를 설치한다.In order to ensure stable contact between the main beam 23 and the lower end of the obstacle 1, a filler 24 is provided therebetween.

이후, 지장물(1)의 하부를 완전굴착하고 지중구조물(a)을 시공한다.Then, the bottom of the obstacle (1) is completely excavated and the underground structure (a) is constructed.

그런데, 이러한 종래의 공법은 다음과 같은 문제가 있었다.However, such a conventional method has the following problems.

첫째, 지장물(1)을 둘러 지지하기 위해 설치되는 와이어(2)는 가요성 재질로서 비교적 변형이 큰 재질이므로, 메인 빔(23) 없이 와이어(2)에 의해 지장물(1)이 지지되는 상태에서 지장물(1)의 처짐현상이 발생한다는 점이다.First, since the wire 2 installed to surround the obstacle 1 is a flexible material having a relatively large deformation, the obstacle 1 is supported by the wire 2 without the main beam 23. In this state, deflection of the obstacle 1 occurs.

지장물(1)이 콘크리트 관로인 경우, 일부지점에서 처짐의 발생은 지장물(1)의 균열로 연결된다는 점에서 그 문제가 심각하다.If the obstacle 1 is a concrete pipeline, the problem is serious in that the occurrence of deflection at some points is connected to the crack of the obstacle 1.

둘째, 와이어(2)에 의해 지장물(1)이 지지되는 상태는 위와 같이 와이어(2)의 변형으로 인하여 위험한 상태이므로, 지장물(1)의 하부 굴착 시 작업의 안정성이 문제된다.Second, since the obstacle 1 is supported by the wire 2 is a dangerous state due to the deformation of the wire 2 as described above, the stability of the work when the lower excavation of the obstacle 1 is problematic.

셋째, 지장물(1)의 양측을 굴착한 후 서브 빔(22)을 설치하고, 지장물(1)의 하부를 관통하여 굴착을 진행하여 메인 빔(23)을 설치하여야 하는데, 협소한 공간에서 이러한 자재의 운반 및 설치작업을 하여야 하므로 시공성이 좋지 못하다.Third, after digging both sides of the obstacle (1) to install the sub-beams 22, through the lower portion of the obstacle (1) to proceed with the excavation to install the main beam 23, in a narrow space The workability is poor because it is necessary to transport and install these materials.

넷째, 메인 빔(23)과 지장물(1)의 하단이 정확히 접촉하도록 메인 빔(23)을 시공하는 것이 대단히 어려우므로, 별도의 충전재(24)에 의한 충전이 필요한데, 이에 과도한 수고와 비용이 소요된다.Fourth, since it is very difficult to construct the main beam 23 so that the lower end of the main beam 23 and the obstacle (1) exactly contact, it is necessary to charge by a separate filler 24, which is excessive labor and cost It takes

본 발명은 상기와 같은 문제점을 해결하기 위하여 도출된 것으로서, 지장물의 손상 우려가 없고, 작업의 안정성 및 시공성이 우수한 지장물 매달기 공법을 제시하는 것을 그 목적으로 한다.The present invention has been made to solve the above problems, and there is no fear of damaging the obstacles, and an object of the present invention is to propose a obstacle hanging method excellent in work stability and workability.

상기 과제의 해결을 위하여, 본 발명은 지장물(1)의 하부에 지중구조물(a)을 시공하기 위하여, 상기 지장물(1)을 임시로 매달아 두는 매달기 공법에 있어서, 상기 지장물(1)의 상부에 상부 지지부(100)를 설치하는 상부 지지부(100) 설치단계; 상기 지장물(1)의 측부를 굴착하는 예비굴착 단계; 상기 지장물(1)의 양측면에 각각 날개부재(200)를 설치하는 한 쌍의 날개부재 설치단계; 상기 날개부재(200)와 상기 상부 지지부(100)를 연결부재(300)에 의해 연결하는 상부 지지부 연결단계; 상기 지장물(1)의 하부를 본굴착하는 본굴착 단계;를 포함하는 날개부재를 이용한 지장물 매달기 공법을 제시한다.In order to solve the above problems, the present invention, in order to construct the underground structure (a) in the lower portion of the obstacle (1), in the hanging method of temporarily hanging the obstacle (1), the obstacle (1) An upper support part 100 installing step of installing the upper support part 100 on an upper part of the upper part; Pre-excavation step of excavating the side of the obstacle (1); A pair of wing member installation steps of installing wing members 200 on both sides of the obstacle 1, respectively; An upper support part connecting step of connecting the wing member 200 and the upper support part 100 by a connection member 300; The present invention provides a method for hanging obstacles using a wing member including a main excavation step of digging the lower portion of the obstacle 1.

상기 상부 지지부(100)는 상기 지장물(1)의 좌우측에 각각 길이방향으로 설치된 한 쌍의 길이방향 빔(110); 상기 한 쌍의 길이방향 빔(110)에 의해 지지되도록, 폭방향으로 설치된 폭방향 빔(120);을 포함하고, 상기 연결부재(300)는 상기 폭방향 빔(120)에 의해 상측으로 지지되도록 설치된 것이 바람직하다.The upper support part 100 includes a pair of longitudinal beams 110 installed in the longitudinal direction on the left and right sides of the obstacle 1, respectively; And a widthwise beam 120 installed in the width direction so as to be supported by the pair of longitudinal beams 110. The connecting member 300 is supported upward by the widthwise beam 120. It is preferred to be installed.

상기 상부 지지부(100)는 상기 한 쌍의 길이방향 빔(110)을 지지하도록 매설된 파일(111);을 포함하는 것이 바람직하다.The upper support part 100 preferably includes a pile 111 embedded to support the pair of longitudinal beams 110.

상기 상부 지지부(100)는 상기 폭방향 빔(120)에 의해 지지되도록, 길이방향으로 설치된 제2 길이방향 빔(130);을 포함하고, 상기 연결부재(300)는 상기 제2 길이방향 빔(130)에 의해 상측으로 지지되도록 설치된 것이 바람직하다.The upper support part 100 includes a second longitudinal beam 130 installed in a longitudinal direction so as to be supported by the widthwise beam 120, and the connection member 300 includes the second longitudinal beam ( 130 is preferably installed to be supported upward.

상기 날개부재(200)에는 상기 연결부재(300)가 관통하여 결합하도록 상하방향으로 연결부재 관통홈(201)이 형성된 것이 바람직하다.The wing member 200 preferably has a connection member through-hole 201 formed in the vertical direction so that the connection member 300 penetrates and engages.

상기 날개부재 설치단계는 상기 지장물(1)의 측면에 앵커(210)를 설치하여 외측으로 돌출되도록 하는 단계; 상기 지장물(1)의 측면을 감싸도록 거푸집(202)을 설치하는 단계; 상기 거푸집(202)에 콘크리트를 타설하여 상기 날개부재(200)를 형성하되, 상기 앵커(210)와 일체로 결합하도록 하는 단계;를 포함하는 것이 바람직하다.The wing member installation step is to install an anchor 210 on the side of the obstacle (1) to protrude to the outside; Installing a formwork 202 to surround the side of the obstacle (1); Placing concrete on the formwork 202 to form the wing member 200, to be integrally coupled to the anchor 210; preferably.

상기 날개부재 설치단계는 상기 지장물(1)의 측면에 결합부재 설치홈(221) 또는 결합부재 설치공(222)을 형성하는 단계; 폭방향을 따라 결합부재 관통공(223)이 형성된 프리캐스트 부재(200a)를 제조하는 단계; 상기 결합부재 관통공(223)을 관통하는 결합부재(220)를 상기 결합부재 설치홈(221) 또는 결합부재 설치공(222)에 결합함으로써, 상기 프리캐스트 부재(200a)를 상기 지장물(1)의 측면에 설치하여 상기 날개부재(200)를 형성하는 단계;를 포함하는 것이 바람직하다.The wing member installation step is to form a coupling member installation groove 221 or a coupling member installation hole 222 on the side of the obstacle (1); Manufacturing a precast member 200a having a coupling member through hole 223 formed along a width direction thereof; By coupling the coupling member 220 penetrating the coupling member through-hole 223 to the coupling member mounting groove 221 or the coupling member mounting hole 222, the precast member 200a to the obstacle (1). It is preferable to include; forming on the side of the) to form the wing member 200.

상기 연결부재(300)는 강봉 또는 강연선인 것이 바람직하다.The connection member 300 is preferably a steel bar or strand.

본 발명은 지장물의 손상 우려가 없고, 작업의 안정성 및 시공성이 우수한 지장물 매달기 공법을 제시한다.The present invention provides a obstacle hanging method excellent in the stability and workability of work without fear of damage to the obstacle.

도 1은 종래의 지장물 매달기 공법에 관한 횡단면도.
도 2는 종래의 지장물 매달기 공법에 관한 종단면도.
도 3 이하는 본 발명의 실시예를 도시한 것으로서,
도 3 내지 6은 제1 실시예의 공정도.
도 7은 지장물 및 날개부재의 사시도.
도 8은 제2 실시예의 공정도.
도 9는 제3 실시예의 공정도.
도 10은 제4 실시예의 공정도.
1 is a cross-sectional view of a conventional obstacle hanging method.
2 is a longitudinal sectional view of a conventional obstacle hanging method.
3 or less shows an embodiment of the present invention,
3 to 6 are process diagrams of the first embodiment.
7 is a perspective view of the obstacle and the wing member.
8 is a process diagram of the second embodiment.
9 is a process diagram of the third embodiment.
10 is a process chart of a fourth embodiment.

이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 3 이하에 도시된 바와 같이, 본 발명은 기본적으로 지장물(1)의 하부에 지중구조물(a)을 시공하기 위하여, 지장물(1)을 임시로 매달아 두는 매달기 공법에 관한 것으로서, 다음과 같은 공정에 의해 이루어진다.As shown below in Figure 3, the present invention basically relates to a suspension method for temporarily hanging the obstacle (1) in order to construct the underground structure (a) in the lower portion of the obstacle (1), It is made by the same process.

지장물(1)의 상부에 길이방향 빔(110), 폭방향 빔(120) 등의 상부 지지부(100)를 설치한다(도 3).The upper support part 100, such as the longitudinal beam 110, the width | variety beam 120, is installed in the upper part of the obstacle 1 (FIG. 3).

지장물(1)의 측부를 굴착하는데, 지장물(1)의 하부는 모두 굴착하지 않고 중앙부는 남겨둠으로써, 그 부분에 의해 지장물(1)이 상측으로 지지된 상태에 있도록 한다(도 4).Excavating the sides of the obstacle 1, but the lower portion of the obstacle 1 is not excavated, but the center part is left, so that the obstacle 1 is in a state of being supported upward by the portion (Fig. 4). ).

지장물(1)의 양측면에 각각 날개부재(200)를 설치하는데, 이는 현장타설 방식, 프리캐스트 부재의 결합방식 등을 취할 수 있다(도 5).The wing members 200 are respectively installed on both sides of the obstacle 1, which may take a field casting method, a coupling method of a precast member, and the like (FIG. 5).

양측에 설치된 한 쌍의 날개부재(200)에 의해 지장물(1)이 상측으로 지지될 수 있도록, 날개부재(200)와 상부 지지부(100)를 연결부재(300)에 의해 연결한다(도 6).The wing member 200 and the upper support part 100 are connected by the connection member 300 so that the obstacle 1 is supported upward by a pair of wing members 200 installed at both sides (FIG. 6). ).

이로써 지장물(1)의 안정적인 매달기 구조가 완성되므로, 이후 지장물(1)의 하부를 본굴착하고 지중구조물을 형성한다.As a result, a stable suspension structure of the obstacle 1 is completed, and thus, the bottom of the obstacle 1 is mainly excavated to form an underground structure.

본 발명에 의한 공법은 다음과 같은 효과가 있다.The method according to the present invention has the following effects.

첫째, 지장물(1)의 처짐에 의한 파손의 우려가 없다.First, there is no fear of damage due to sagging of the obstacle 1.

종래의 공법에서는 하나의 부재에 의해 지장물(1)을 둘러 지지해야 하므로, 가요성 재질인 와이어를 사용할 수밖에 없음에 따라 지장물(1)의 처짐 문제가 있었다.In the conventional method, since the obstacle 1 must be surrounded by one member, there is a problem of sagging of the obstacle 1 due to the use of a flexible wire.

그러나 본 발명은 지장물의 하부 양측 가장자리에 별도의 날개부재(200) 한 쌍을 설치하고, 그 한 쌍의 날개부재(200)를 각각 연결부재(300)에 의해 연결하여 지장물(1)을 지지하는 구조를 취하므로, 변형이 적은 재질에 의해 연결부재(300)를 만들어 사용하면 되는바, 종래의 공법과 같은 문제를 해소할 수 있다.However, in the present invention, a pair of separate wing members 200 is installed at both lower edges of the obstacle, and the pair of wing members 200 are connected to each other by the connection member 300 to support the obstacle 1. Since it takes a structure to make, the connection member 300 by using a material with less deformation can be used, it can solve the same problem as the conventional method.

둘째, 지장물(1)의 하부 굴착 시 작업의 안정성이 우수하다.Second, when the lower excavation of the obstacle (1) the work stability is excellent.

본 발명에 의한 공법은 종래와 같이 지장물(1)을 임시로 와이어(2)에 의해 지지한 상태에서 지장물(1)의 하부를 굴착하는 것이 아니라, 지장물(1)의 하부 중 중앙부를 굴착하지 않은 상태에서, 날개부재(200) 등에 의한 지지구조를 완성하고, 이후 비로소 지장물(1)의 하부 본굴착 작업을 수행하므로, 안전한 작업이 가능하다.The method according to the present invention does not excavate the lower part of the obstacle 1 in a state where the obstacle 1 is temporarily supported by the wire 2 as in the prior art, and the center portion of the lower part of the obstacle 1 is not excavated. In the non-drilled state, the support structure by the wing member 200, etc. is completed, and since the bottom main excavation work of the obstacle 1 is performed afterwards, a safe operation is possible.

셋째, 시공성이 우수하다.Third, the workability is excellent.

날개부재(200), 연결부재(300)는 종래의 공법에 사용되는 서브 빔(22), 메인 빔(23)에 비해 그 규모가 작아도 관계가 없으므로, 협소한 공간이라 하더라도 우수한 시공성을 기대할 수 있다.Since the wing member 200 and the connection member 300 have a smaller size than the sub beam 22 and the main beam 23 used in the conventional method, even when the space is narrow, excellent workability can be expected. .

넷째, 수고와 비용을 줄일 수 있다.Fourth, labor and cost can be reduced.

지장물(1)의 하부 가장자리 굴착 후, 날개부재(200)를 지장물(1)의 측면에 정확히 설치할 수 있으므로, 종래의 공법과 같이 별도의 충전재(24) 설치작업이 불필요한바, 작업에 소요되는 수고와 비용을 크게 줄일 수 있다.After excavation of the lower edge of the obstacle 1, since the wing member 200 can be accurately installed on the side of the obstacle 1, it is unnecessary to install a separate filler 24 as in the conventional method. The labor and cost of doing so can be greatly reduced.

이하, 본 발명에 의한 공법의 구체적 내용에 관한 실시예에 대하여 설명한다.
EMBODIMENT OF THE INVENTION Hereinafter, the Example regarding the specific content of the construction method by this invention is described.

상부 지지부(100)는 지장물(1)의 상부에 설치되어, 상하방향 연결부재(300)를 상측으로 지지할 수 있는 구조이면 어느 것이나 관계없으나, 지장물(1)의 좌우측에 각각 길이방향으로 설치된 한 쌍의 길이방향 빔(110); 한 쌍의 길이방향 빔(110)에 의해 지지되도록, 폭방향으로 설치된 폭방향 빔(120);을 포함하고, 상하방향 연결부재(300)는 폭방향 빔(120)에 의해 상측으로 지지되도록 설치된 구조를 취하는 것이 구조적 안정성을 위하여 바람직하다(도 6).The upper support part 100 may be installed on the obstacle 1, and may have any structure that can support the vertical connecting member 300 upwards, but may be in the longitudinal direction on the left and right sides of the obstacle 1, respectively. A pair of longitudinal beams 110 installed; And a widthwise beam 120 installed in the width direction so as to be supported by the pair of longitudinal beams 110. The vertically connecting member 300 is installed to be supported upward by the widthwise beam 120. Taking the structure is preferred for structural stability (FIG. 6).

견고한 지반의 경우에는, 그 지반 위에 한 쌍의 길이방향 빔(110)을 설치하더라도 문제가 없을 것이나, 연약지반의 경우에는 별도의 파일(111)을 매설 시공하고, 이에 의해 한 쌍의 길이방향 빔(110)이 지지되도록 하는 것이 바람직하다(도 6).In the case of solid ground, there would be no problem even if a pair of longitudinal beams 110 were installed on the ground, but in the case of soft ground, a separate pile 111 was buried, whereby a pair of longitudinal beams were installed. It is desirable to allow 110 to be supported (FIG. 6).

폭방향 빔(120)에 의해 지지되도록, 길이방향으로 제2 길이방향 빔(130);을 설치하고, 상하방향 연결부재(300)는 위 제2 길이방향 빔(130)에 의해 상측으로 지지되도록 설치하는 것이 구조적 안정성 및 시공성 측면에서 더욱 바람직하다.And a second longitudinal beam 130 in the longitudinal direction so as to be supported by the widthwise beam 120, and the vertical connecting member 300 is supported upward by the second longitudinal beam 130. It is more preferable to install in terms of structural stability and workability.

날개부재(200)와 연결부재(300)의 결합구조는 지장물(1)의 안정적인 매달기 구조가 확보되는 것이면 어느 것이나 관계없으나, 날개부재(200)에 상하방향으로 연결부재 관통홈(201)이 형성되고, 이를 통해 연결부재(300)가 관통하여 결합하는 구조를 취하는 것이 구조적 안정성을 위하여 바람직하다(도 6,7).The coupling structure of the wing member 200 and the connecting member 300 may be any type as long as a stable hanging structure of the obstacle 1 is secured, but the connecting member through groove 201 is vertically connected to the wing member 200. It is formed, it is preferable to take the structure through which the connecting member 300 is coupled through it for structural stability (Figs. 6 and 7).

날개부재(200)는 현장타설 방식, 프리캐스트 부재의 결합방식 등에 의해 설치할 수 있다(도 5).The wing member 200 may be installed by a field casting method, a coupling method of a precast member, and the like (FIG. 5).

전자의 경우, 지장물(1)의 측면에 앵커(210)를 설치하여 외측으로 돌출되도록 하는 단계; 지장물(1)의 측면을 감싸도록 거푸집(202)을 설치하는 단계; 거푸집(202)에 콘크리트를 타설하여 날개부재(200)를 형성하되, 앵커(210)와 일체로 결합하도록 하는 단계;에 의해 구성되는 것이 바람직하다(도 8).In the former case, installing an anchor 210 on the side of the obstacle (1) to protrude outward; Installing a formwork 202 to surround the side of the obstacle (1); Forming the wing member 200 by pouring concrete in the formwork 202, to be integrally coupled with the anchor 210; is preferably configured by (Fig. 8).

후자의 경우, 지장물(1)의 측면에 결합부재 설치홈(221) 또는 결합부재 설치공(222)을 형성하는 단계; 폭방향을 따라 결합부재 관통공(223)이 형성된 프리캐스트 부재(200a)를 제조하는 단계; 결합부재 관통공(223)을 관통하는 결합부재(220)를 상기 결합부재 설치홈(221) 또는 결합부재 설치공(222)에 결합함으로써, 프리캐스트 부재(200a)를 지장물(1)의 측면에 설치하여 상기 날개부재(200)를 형성하는 단계;에 의해 구성되는 것이 바람직하다(도 9.10).In the latter case, forming a coupling member installation groove 221 or coupling member installation hole 222 on the side of the obstacle (1); Manufacturing a precast member 200a having a coupling member through hole 223 formed along a width direction thereof; By coupling the coupling member 220 penetrating the coupling member through hole 223 to the coupling member mounting groove 221 or the coupling member mounting hole 222, the precast member 200a is provided on the side surface of the obstacle 1. Forming the wing member 200 by installing in the; is preferably configured by (Fig. 9.10).

지장물(1)의 벽체의 두께가 두꺼운 경우에는, 지장물(1)의 측면에 결합부재 설치홈(221)을 형성하고, 이에 결합부재(220)를 설치하는 것이 바람직하고, 지장물(1)의 벽체의 두께가 얇은 경우에는, 지장물(1)의 측면에 결합부재 설치공(222)을 관통형성하고, 이에 결합부재(220)를 관통하여 설치하는 것이 바람직하다.When the wall of the obstacle 1 is thick, it is preferable to form the coupling member mounting groove 221 on the side of the obstacle 1, and to install the coupling member 220, and the obstacle 1 When the thickness of the wall is thin, it is preferable to penetrate the coupling member mounting hole 222 on the side surface of the obstacle 1 and to penetrate the coupling member 220.

연결부재(300)는 강연선 등의 연성 재질에 의해 형성할 수도 있고, 강봉 등의 경성 재질에 의해 형성할 수도 있는데, 전자의 경우에는 강연선을 긴장하여 받침부(200)에 정착하는 것이 바람직하다.The connection member 300 may be formed of a flexible material such as a stranded wire, or may be formed of a rigid material such as a steel bar. In the former case, the connection member 300 is preferably tensioned and fixed to the support 200.

이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit or scope of the invention as defined in the appended claims. It is to be understood that both the technical idea and the technical spirit of the invention are included in the scope of the present invention.

1 : 지장물 100 : 상부 지지부
110 : 길이방향 빔 111 : 파일
120 : 폭방향 빔 130 : 제2 길이방향 빔
200 : 날개부재 300 : 연결부재
1: obstacle 100: upper support
110: longitudinal beam 111: file
120: widthwise beam 130: second longitudinal beam
200: wing member 300: connection member

Claims (8)

지장물(1)의 하부에 지중구조물(a)을 시공하기 위하여, 상기 지장물(1)을 임시로 매달아 두는 매달기 공법에 있어서,
상기 지장물(1)의 상부에 상부 지지부(100)를 설치하는 상부 지지부(100) 설치단계;
상기 지장물(1)의 측부를 굴착하는 예비굴착 단계;
상기 지장물(1)의 양측면에 각각 날개부재(200)를 설치하는 한 쌍의 날개부재 설치단계;
상기 날개부재(200)와 상기 상부 지지부(100)를 연결부재(300)에 의해 연결하는 상부 지지부 연결단계;
상기 지장물(1)의 하부를 본굴착하는 본굴착 단계;를
포함하는 날개부재를 이용한 지장물 매달기 공법.
In the hanging method of temporarily hanging the obstacle (1) in order to construct the underground structure (a) in the lower portion of the obstacle (1),
An upper support part 100 installation step of installing an upper support part 100 on an upper part of the obstacle 1;
Pre-excavation step of excavating the side of the obstacle (1);
A pair of wing member installation steps of installing wing members 200 on both sides of the obstacle 1, respectively;
An upper support part connecting step of connecting the wing member 200 and the upper support part 100 by a connection member 300;
A main excavation step of digging the lower portion of the obstacle 1;
Hanging obstacle method using a wing member containing.
제1항에 있어서,
상기 상부 지지부(100)는
상기 지장물(1)의 좌우측에 각각 길이방향으로 설치된 한 쌍의 길이방향 빔(110);
상기 한 쌍의 길이방향 빔(110)에 의해 지지되도록, 폭방향으로 설치된 폭방향 빔(120);을 포함하고,
상기 연결부재(300)는
상기 폭방향 빔(120)에 의해 상측으로 지지되도록 설치된 것을 특징으로 하는 날개부재를 이용한 지장물 매달기 공법.
The method of claim 1,
The upper support part 100
A pair of longitudinal beams 110 installed in the longitudinal direction on the left and right sides of the obstacle 1, respectively;
And a width beam 120 installed in the width direction so as to be supported by the pair of longitudinal beams 110.
The connecting member 300 is
Hanging obstacles using the wing member, characterized in that installed so as to be supported upward by the width beam (120).
제2항에 있어서,
상기 상부 지지부(100)는
상기 한 쌍의 길이방향 빔(110)을 지지하도록 매설된 파일(111);을
포함하는 것을 특징으로 하는 날개부재를 이용한 지장물 매달기 공법.
The method of claim 2,
The upper support part 100
A pile 111 embedded to support the pair of longitudinal beams 110;
Obstruction hanging method using a wing member comprising a.
제2항에 있어서,
상기 상부 지지부(100)는
상기 폭방향 빔(120)에 의해 지지되도록, 길이방향으로 설치된 제2 길이방향 빔(130);을 포함하고,
상기 연결부재(300)는
상기 제2 길이방향 빔(130)에 의해 상측으로 지지되도록 설치된 것을 특징으로 하는 날개부재를 이용한 지장물 매달기 공법.
The method of claim 2,
The upper support part 100
And a second longitudinal beam 130 installed in the longitudinal direction so as to be supported by the width beam 120.
The connecting member 300 is
The obstacle hanging method using the wing member, characterized in that installed so as to be supported by the second longitudinal beam (130) upward.
제1항에 있어서,
상기 날개부재(200)에는
상기 연결부재(300)가 관통하여 결합하도록 상하방향으로 연결부재 관통홈(201)이 형성된 것을 특징으로 하는 날개부재를 이용한 지장물 매달기 공법.
The method of claim 1,
The wing member 200
Hanging method using a hedge member, characterized in that the connecting member through groove 201 is formed in the vertical direction so that the connecting member 300 is coupled through.
제5항에 있어서,
상기 날개부재 설치단계는
상기 지장물(1)의 측면에 앵커(210)를 설치하여 외측으로 돌출되도록 하는 단계;
상기 지장물(1)의 측면을 감싸도록 거푸집(202)을 설치하는 단계;
상기 거푸집(202)에 콘크리트를 타설하여 상기 날개부재(200)를 형성하되, 상기 앵커(210)와 일체로 결합하도록 하는 단계;를
포함하는 것을 특징으로 하는 날개부재를 이용한 지장물 매달기 공법.
The method of claim 5,
The wing member installation step is
Installing an anchor 210 on the side of the obstacle (1) to protrude to the outside;
Installing a formwork 202 to surround the side of the obstacle (1);
Placing concrete in the formwork 202 to form the wing member 200, to be integrally coupled to the anchor 210;
Obstruction hanging method using a wing member comprising a.
제5항에 있어서,
상기 날개부재 설치단계는
상기 지장물(1)의 측면에 결합부재 설치홈(221) 또는 결합부재 설치공(222)을 형성하는 단계;
폭방향을 따라 결합부재 관통공(223)이 형성된 프리캐스트 부재(200a)를 제조하는 단계;
상기 결합부재 관통공(223)을 관통하는 결합부재(220)를 상기 결합부재 설치홈(221) 또는 결합부재 설치공(222)에 결합함으로써, 상기 프리캐스트 부재(200a)를 상기 지장물(1)의 측면에 설치하여 상기 날개부재(200)를 형성하는 단계;를
포함하는 것을 특징으로 하는 날개부재를 이용한 지장물 매달기 공법.
The method of claim 5,
The wing member installation step is
Forming a coupling member installation groove 221 or a coupling member installation hole 222 on the side of the obstacle 1;
Manufacturing a precast member 200a having a coupling member through hole 223 formed along a width direction thereof;
By coupling the coupling member 220 penetrating the coupling member through-hole 223 to the coupling member mounting groove 221 or the coupling member mounting hole 222, the precast member 200a to the obstacle (1). Installed on the side of the blade to form the wing member 200;
Obstruction hanging method using a wing member comprising a.
제1항에 있어서,
상기 연결부재(300)는 강봉 또는 강연선인 것을 특징으로 하는 날개부재를 이용한 지장물 매달기 공법.
The method of claim 1,
The connecting member 300 is hanging obstacle method using a wing member, characterized in that the steel bar or strand.
KR1020120046094A 2012-05-02 2012-05-02 Suspention method for buried structures using joint member KR101293683B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020120046094A KR101293683B1 (en) 2012-05-02 2012-05-02 Suspention method for buried structures using joint member

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120046094A KR101293683B1 (en) 2012-05-02 2012-05-02 Suspention method for buried structures using joint member

Publications (1)

Publication Number Publication Date
KR101293683B1 true KR101293683B1 (en) 2013-08-06

Family

ID=49219968

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120046094A KR101293683B1 (en) 2012-05-02 2012-05-02 Suspention method for buried structures using joint member

Country Status (1)

Country Link
KR (1) KR101293683B1 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0762898A (en) * 1992-04-30 1995-03-07 Ishikawajima Constr Materials Co Ltd Reinforcing method for existing tank
KR200263526Y1 (en) 1999-06-24 2002-02-06 박정진 Hanging semi down up system
KR100619272B1 (en) 2006-01-23 2006-09-07 주식회사 도화종합기술공사 Height adjusting apparatus of water supply and drainage pipe

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0762898A (en) * 1992-04-30 1995-03-07 Ishikawajima Constr Materials Co Ltd Reinforcing method for existing tank
KR200263526Y1 (en) 1999-06-24 2002-02-06 박정진 Hanging semi down up system
KR100619272B1 (en) 2006-01-23 2006-09-07 주식회사 도화종합기술공사 Height adjusting apparatus of water supply and drainage pipe

Similar Documents

Publication Publication Date Title
CN103410174A (en) GXJ underground continuous wall rubber waterproof connector tool and construction method thereof
KR20110077334A (en) Retaining wall structure and construction method of the retaining wall structure
KR101255027B1 (en) Precast rahmen type box culvert
JP2017179734A (en) Construction joint structure of underground continuous wall
KR20190022132A (en) Top-down method using precast-concrete colum
KR101521556B1 (en) Underground wall construction method using wall members
KR101035404B1 (en) Slurry wall and slab junction structure and its using top-down construction method
KR101314764B1 (en) Retaining wall using corrugated steel plate and construction method thereof
KR101293683B1 (en) Suspention method for buried structures using joint member
JP6364211B2 (en) Construction method of the end structure of the leading element, the reinforcing steel frame and the continuous underground wall
CN104314104B (en) Deformation joint setting method for oblique crossing with underground box culvert
JP6192972B2 (en) Calvert
KR101249603B1 (en) Steel pipe installing structure for resistance in vertical stress of none-excavation underground structure and construction method at the same
KR101293682B1 (en) Suspention method for buried structures
JP2009019370A (en) Construction joint structure of underground wall and forming implement and constructing method of construction joint part of underground wall
CN209329658U (en) A kind of assembly type cable slot
KR20150010422A (en) Mid supporting beam for temporary soil sheathing work
KR20140110526A (en) A fixing coupler used a burial slab of an outer wall of an underground construction and a burial slab construction method using it
JP2018009388A (en) End structure of preceding element and construction method of underground continuous wall
KR20120134677A (en) The precast concrete closed conduit that is reinforced by the shear connector and constructing method of it
KR101866792B1 (en) Temporary retaining wall structure
JP4616125B2 (en) Precast beam for tunnel construction and tunnel construction method
CN103758155B (en) Underground diaphragm wall joint and construction method thereof
JP2007146460A (en) Sheet pile type timbering structure for excavated groove
JP6397321B2 (en) Construction method of water stop plate mounting member, water stop plate, rebar mount and continuous underground wall

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160726

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170726

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20190730

Year of fee payment: 7