KR101248825B1 - Construction method of drain apparatus - Google Patents

Construction method of drain apparatus Download PDF

Info

Publication number
KR101248825B1
KR101248825B1 KR1020110039289A KR20110039289A KR101248825B1 KR 101248825 B1 KR101248825 B1 KR 101248825B1 KR 1020110039289 A KR1020110039289 A KR 1020110039289A KR 20110039289 A KR20110039289 A KR 20110039289A KR 101248825 B1 KR101248825 B1 KR 101248825B1
Authority
KR
South Korea
Prior art keywords
drainage
mandrel
construction
depth
layer
Prior art date
Application number
KR1020110039289A
Other languages
Korean (ko)
Other versions
KR20120121460A (en
Inventor
신민식
김동해
이준석
노진택
Original Assignee
주식회사 동아지질
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 동아지질 filed Critical 주식회사 동아지질
Priority to KR1020110039289A priority Critical patent/KR101248825B1/en
Publication of KR20120121460A publication Critical patent/KR20120121460A/en
Application granted granted Critical
Publication of KR101248825B1 publication Critical patent/KR101248825B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B11/00Drainage of soil, e.g. for agricultural purposes
    • E02B11/005Drainage conduits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D1/00Investigation of foundation soil in situ
    • E02D1/02Investigation of foundation soil in situ before construction work
    • E02D1/022Investigation of foundation soil in situ before construction work by investigating mechanical properties of the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Soil Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Mechanical Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

본 발명은 연약지반 개량을 위한 배수재 시공방법에 관한 것으로, 더욱 상세하게는 시공현장에서 맨드럴을 사용하여 지층 분석을 행한 후 지층 분석을 통해 획득한 복토층의 깊이, 개량대상층의 깊이 등의 데이터에 부합되게 시공현장에 비치된 가공장치를 통해 배수재를 불투과층 코팅 및 필요 시공 길이만큼 절단한 다음 맨드럴로 연약지반 내부로 관입시켜 시공하는 방법을 제공함에 따라, 연약지반의 지층 분석, 배수재의 가공, 배수재의 시공 등의 모든 작업을 시공현장에서 연속적으로 행함으로써, 배수재의 시공 효율을 극대화시킬 수 있도록 한 연약지반 개량을 위한 배수재 시공방법에 관한 것이다.
본 발명에 따르면, 시공장비에 설치된 맨드럴을 연약지반 내부로 관입시켜 맨드럴의 관입 속도와 맨드럴을 가동시키는 유압장치의 시간에 따른 압력 변화를 통해 복토층의 깊이와 개량대상층의 깊이를 획득하는 단계와; 복토층의 깊이와 개량대상층의 깊이를 이용하여 시공하고자 하는 배수재의 불투과층 형성을 위한 코팅 길이와 전체 필요 시공길이 만큼 배수재의 절단 길이를 산출하는 단계; 가공장치를 사용하여 불투과층의 코팅 길이와 배수재의 절단 길이에 대응되게 배수재를 시공현장에서 가공하는 단계; 가공된 배수재의 상단을 윈치에 의해 작동되는 와이어에 결속시켜 맨드럴의 상부로 인발시키는 단계와; 맨드럴의 상부로 인발된 배수재의 하단에 일정길이의 보호비닐을 씌운 후 맨드럴에 고정된 정착구를 연결하는 단계와; 유압장치를 통해 맨드럴을 가동하여 맨드럴을 연약지반 내부로 관입시켜 배수재의 시공을 완료하는 단계;를 포함하여 구성됨을 특징으로 한 연약지반 개량을 위한 배수재 시공방법이 제공된다.
The present invention relates to a drainage construction method for improving the soft ground, and more specifically, to the data such as the depth of the cover layer, the depth of the improvement target layer obtained through the stratum analysis after the stratum analysis using the mandrel in the construction site According to the process equipment installed at the construction site, the drainage material is cut through the impermeable layer and the required construction length, and then the mandrel is used to penetrate into the soft ground. The present invention relates to a drainage construction method for improving the soft ground by maximizing the construction efficiency of drainage materials by continuously performing all operations such as processing and drainage construction at a construction site.
According to the present invention, by injecting the mandrel installed in the construction equipment into the soft ground to obtain the depth of the cover layer and the depth of the improvement target layer through the change of the mandrel penetration rate and the pressure over time of the hydraulic device to operate the mandrel Steps; Calculating the cutting length of the drainage material by the coating length and the total required construction length for forming the impermeable layer of the drainage material to be constructed using the depth of the cover layer and the depth of the improvement target layer; Processing the drainage material at a construction site corresponding to the coating length of the impermeable layer and the cutting length of the drainage material using a processing device; Binding an upper end of the processed drainage to a wire actuated by the winch to draw the upper end of the mandrel; Connecting a fixing fixture fixed to the mandrel after covering a predetermined length of protective vinyl on the bottom of the drainage drawn to the upper portion of the mandrel; The operation of the mandrel through the hydraulic system to inject the mandrel into the soft ground to complete the construction of the drainage; there is provided a drainage construction method for improving the soft ground, characterized in that it comprises a.

Description

연약지반 개량을 위한 배수재 시공방법{Construction method of drain apparatus}Construction method of drain apparatus for improvement of soft ground

본 발명은 연약지반 개량을 위한 배수재 시공방법에 관한 것으로, 더욱 상세하게는 시공현장에서 맨드럴을 사용하여 지층 분석을 행한 후 지층 분석을 통해 획득한 복토층의 깊이, 개량대상층의 깊이 등의 데이터에 부합되게 시공현장에 비치된 가공장치를 통해 배수재를 절단 가공한 다음 맨드럴로 연약지반 내부로 관입시켜 시공하는 방법을 제공함에 따라, 연약지반의 지층 분석, 배수재의 가공, 배수재의 시공 등의 모든 작업을 시공현장에서 연속적으로 행함으로써, 배수재의 시공 효율을 극대화시킬 수 있도록 한 연약지반 개량을 위한 배수재 시공방법에 관한 것이다.
The present invention relates to a drainage construction method for improving the soft ground, and more specifically, to the data such as the depth of the cover layer, the depth of the improvement target layer obtained through the stratum analysis after the stratum analysis using the mandrel in the construction site In accordance with this, the drainage is cut and processed through the processing equipment installed at the construction site, and then the mandrel is used to penetrate into the soft ground to provide construction methods. The present invention relates to a drainage construction method for the improvement of soft ground to maximize the construction efficiency of drainage by performing the work continuously at the construction site.

일반적으로 연약지반의 개량을 위해서는 연약지반 속에 포함된 간극수를 외부로 흡출시켜 배수하는 간극수의 배수 작업이 선행되어야 한다. 이러한 간극수의 배수 작업을 효과적으로 시행하기 위하여 개별 진공 압밀 공법을 사용한다. In general, in order to improve the soft ground, drainage work of the gap water to drain and drain the gap water contained in the soft ground to the outside should be preceded. Individual vacuum consolidation methods are used to effectively perform this drainage work.

상기와 같은 개별 진공 압밀 공법은 성토하중으로 간극수를 흡출하여 배수하는 기존의 공법을 개량 발전시킨 것으로, 성토하중을 이용하지 않고 진공펌프에 의한 진공압으로 간극수를 흡출하여 배수하는 공법이다. The individual vacuum consolidation method as described above is an improvement and development of the existing method of sucking and draining the pore water by the fill load, and is a method of sucking and draining the pore water by vacuum pressure by a vacuum pump without using the fill load.

따라서 간극수의 배수 작업을 신속하고 원활하게 이루어짐에 따라 균일한 지반 안정이 가능하여 가장 많이 사용되고 있다. 이러한 개별 진공 압밀 공법을 행하기 위해서는 진공압을 통해 간극수를 흡출하는 복수의 배수재를 연약지반 내부에 일정간격으로 시공해야 한다. Therefore, since the drainage work of the pore water is made quickly and smoothly, the uniform ground stability is possible and is most frequently used. In order to perform such an individual vacuum consolidation method, a plurality of drainage materials which suck out the gap water through vacuum pressure should be installed at a predetermined interval inside the soft ground.

상기한 연약지반 개량을 위한 배수재는, 복수의 배수통로가 수직으로 구획된 골조와, 상기 골조의 외측에 설치된 부직포와, 상기 부직포의 상단 외면부에 형성된 불투과층으로 구성된다. The waste material for improving the soft ground is composed of a frame in which a plurality of drain passages are vertically divided, a nonwoven fabric provided on the outside of the framework, and an impermeable layer formed on the upper outer surface of the nonwoven fabric.

따라서 연약지반의 개량대상층 상부에 인력으로 매트를 격자형태로 설치하고 매트 상부에 소형 장비를 이용하여 양질의 토사를 포설하여 복토층을 형성한 후, 복토층 상부에서 중장비를 동원하여 배수재를 시공하고 있다.
Therefore, the mat is installed in a lattice form on the upper part of the improvement target layer of the soft ground, and the high quality soils are laid by using small equipment on the mat, and then the drainage is constructed by mobilizing heavy equipment on the upper layer.

상기와 같이 배수재를 연약지반에 시공하기에 앞서 연약지반의 지층 분석이 선행되어야 한다. 이러한 연약지반의 지층 분석은 복토층의 깊이, 개량대상층의 깊이 등에 대한 데이터를 획득하기 위한 것이다. As described above, before the drainage material is installed on the soft ground, the strata analysis of the soft ground should be preceded. This fragile ground analysis is to obtain data on the depth of the cover layer, the depth of the improvement target layer.

이는 연약지반의 지층 분석에서 획득한 복토층의 깊이, 개량대상층의 깊이 등의 데이터에 따라 배수재의 절단 길이, 배수재의 상단에 코팅 처리되는 불투과층의 코팅 길이가 결정되기 때문이다. This is because the cutting length of the drainage material and the coating length of the impermeable layer coated on the top of the drainage material are determined according to data such as the depth of the cover layer and the depth of the improvement target layer obtained in the analysis of the soft ground.

즉, 배수재의 절단 길이 또는 불투과층의 코팅 길이가 맞지 않아 배수재의 불투과층이 복토층 하부 개량대상층의 일부 깊이까지 관입되지 않거나 복토층 외부로 완전히 노출되면, 흡출된 간극수가 외부로 배출되지 않고 복토층으로 흡수되거나 복토층을 통해 복토층 상부의 대기 및 표면수를 흡출하여 진공압이 배수재에 작용하지 못하여 개량대상층의 간극수의 흡출이 불가능하게 된다. That is, if the cut length of the drainage material or the coating length of the impermeable layer does not match, and the impermeable layer of the drainage material does not penetrate to some depth of the lower cover layer improvement layer or is completely exposed outside the cover layer, the adsorbed pore water is not discharged to the outside and the cover layer is not discharged to the outside. It is absorbed by the air or through the cover layer to extract the air and surface water on the top of the cover layer, the vacuum pressure does not act on the drainage, it is impossible to suck out the gap water of the improvement target layer.

그리고 배수재의 절단 길이가 맞지 않아 배수재의 하단이 지하수가 존재하는 하부지지층까지 도달하게 되면, 진공압이 배수재로 원활하게 공급되더라도 개량대상층 하부의 지하수와 공기의 흡출로 인해 간극수의 흡출이 원활하지 못하게 된다.When the cutting length of the drainage material does not match, the lower end of the drainage material reaches the lower support layer where the groundwater is present. do.

따라서 시공현장에서 중장비를 이용하는 시추 등의 방식을 통해 연약지반의 지층 분석을 행하여, 복토층의 깊이, 개량대상층의 깊이 등에 대한 데이터를 획득한다. Therefore, by analyzing the geological layer of the soft ground by drilling using heavy equipment at the construction site, data about the depth of the cover layer, the depth of the target layer for improvement, etc. are obtained.

그런 다음 생산공장에서 지층 분석을 통해 획득한 데이터를 이용하여 배수재의 절단 길이와 불투과층의 코팅 길이를 산출한 후 가공장치를 산출된 데이터에 부합되게 배수재를 절단하고 그 상단에 불투과층을 형성시키는 가공 작업을 행한다. Then, the cutting length of the drainage material and the coating length of the impermeable layer are calculated using the data obtained through the geological analysis in the production plant, and the processing equipment is cut in accordance with the calculated data. The forming work to be formed is performed.

마지막으로 생산공장에서 가공이 완료된 배수재를 시공현장으로 운반한 후 맨드럴이 장착된 시공장비를 이용하여 연약지반 내부에 관입시켜 시공함으로써 배수재의 시공을 완료하게 된다. Finally, after the processed wastewater is transported to the construction site in the production plant, the drainage is completed by injecting it into the soft ground using the construction equipment equipped with the mandrel.

그러나 상기와 같은 종래의 배수재 시공 방법은, 지층 분석을 시공현장에서 행하고, 배수재의 가공을 가공장치가 마련된 생산공장에서 행하며, 배수재의 시공을 시공현장에서 행하므로, 장소별로 작업이 분리되어 연속적인 작업이 이루어지지 않았다. However, in the conventional drainage construction method as described above, the geological analysis is carried out at the construction site, the processing of the drainage is carried out at the production plant equipped with the processing apparatus, and the construction of the drainage is performed at the construction site, so that the work is separated by place and continuous. No work was done.

즉, 시공현장에서 지층 분석을 행한 다음 생산 현장에서 배수재를 가공한 후 이를 다시 시공현장으로 운반하여 연약지반 내부에 관입시켜 시공하므로, 공기가 길어질 수밖에 없고 배수재를 가공한 상태로 시공현장으로 운반하고 있으므로 부피도 증대되고 운반도 용이하지 못하여, 배수재 시공 효율을 크게 떨어지는 문제점이 있었다. In other words, after analyzing the stratum at the construction site and processing the drainage material at the production site, it is transported back to the construction site and inserted into the soft ground. Therefore, the air has to be long, and the drainage is processed and transported to the construction site. Therefore, the volume is also increased and not easy to transport, there was a problem that greatly reduces the drainage construction efficiency.

그러므로 본 발명은 상기한 종래의 문제점에 대한 해결책을 제시하기 위하여, 지층 분석을 통해 획득한 데이터를 통해 시공현장에서 바로 배수재를 가공한 후 즉시 시공함으로써 배수재의 시공 효율을 향상시킬 수 있도록 한 연약지반 개량을 위한 배수재 시공방법을 제공함에 그 목적이 있다.
Therefore, the present invention is to provide a solution to the above-mentioned conventional problems, the soft ground to improve the construction efficiency of the drainage material by immediately after construction immediately after the drainage material from the construction site through the data obtained through the geological analysis The purpose is to provide a drainage construction method for improvement.

본 발명은 상기와 같은 문제점을 해소하기 위하여 발명된 것으로, 시공장비에 설치된 맨드럴을 연약지반 내부로 관입시켜 맨드럴의 관입 속도와 맨드럴을 가동시키는 유압장치의 시간에 따른 압력 변화를 통해 복토층의 깊이와 개량대상층의 깊이를 획득하는 단계와; 복토층의 깊이와 개량대상층의 깊이를 이용하여 시공하고자 하는 배수재의 절단 길이와 배수재가 배수재관이나 수평배수재 등에 연결하기 위하여 복토층 상부에 일부 노출되고, 개량대상층에 일부 깊이까지 관입 가능한 불투과층의 코팅 길이를 산출하는 단계와; 시공장비를 사용하여 배수재의 절단 길이와 불투과층의 코팅 길이에 대응되게 배수재를 시공현장에서 가공하는 단계와; 가공된 배수재의 상단을 윈치에 의해 작동되는 와이어에 결속시켜 맨드럴의 상부로 인발시키는 단계와; 맨드럴의 상부로 인발된 배수재의 하단에 일정길이의 보호비닐을 씌운 후 맨드럴에 고정된 정착구를 연결하는 단계와; 유압장치를 통해 맨드럴을 가동하여 맨드럴을 연약지반 내부로 관입시켜 배수재의 시공을 완료하는 단계;를 포함한 연약지반 개량을 위한 배수재 시공방법을 제공한다.
The present invention has been invented to solve the above problems, the cover layer through the mandrel installed in the construction equipment into the soft ground to change the penetration rate of the mandrel and the pressure over time of the hydraulic device to operate the mandrel Obtaining a depth of a depth and a depth of a layer to be improved; Using the depth of the cover layer and the depth of the improvement target layer, the cutting length and the drainage of the drainage material to be constructed are partially exposed in the upper part of the cover layer to connect to the drainage pipe or the horizontal drainage material, and the coating of the impermeable layer that can penetrate to the depth of the improvement target layer to a certain depth. Calculating a length; Using the construction equipment to process the drainage at the construction site corresponding to the cutting length of the drainage and the coating length of the impermeable layer; Binding an upper end of the processed drainage to a wire actuated by the winch to draw the upper end of the mandrel; Connecting a fixing fixture fixed to the mandrel after covering a predetermined length of protective vinyl on the bottom of the drainage drawn to the upper portion of the mandrel; It provides a drainage construction method for improving the soft ground, including; the step of completing the construction of the drainage by injecting the mandrel into the soft ground by operating the mandrel through the hydraulic device.

본 발명은 연약지반의 지층 분석, 배수재의 가공, 배수재의 시공 등의 모든 작업을 시공현장에서 연속적으로 행할 수 있을 뿐만 아니라 배수재의 시공 작업시 배수재가 바람에 날려 엉키는 폐단도 방지할 수 있으므로, 시공의 용이성이 증대되어 배수재의 시공 효율을 높이고 배수재 시공 기간을 단축하는 효과가 있다.
The present invention not only can continuously perform all operations such as strata analysis of soft ground, processing of drainage materials, and construction of drainage materials at the construction site, but also prevents wastewater from being blown and entangled during drainage construction work. Increased ease of use has the effect of increasing the construction efficiency of the drainage and shortening the drainage construction period.

도 1은 배수재를 도시한 사시도 및 일부 확대 사시도.
도 2는 본 발명의 시공 과정을 도시한 예시도.
도 3은 본 발명에 의한 배수재의 시공 상태도.
1 is a perspective view and a partially enlarged perspective view showing a drain.
2 is an exemplary view showing a construction process of the present invention.
Figure 3 is a construction state of the drain material according to the present invention.

이하 본 발명의 바람직한 실시예를 첨부한 도면을 참조하여 상세하게 설명하면 다음과 같다. Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

본 발명은 개별 진공 압밀 공법을 이용하여 연약지반을 개량할 때 간극수를 외부로 흡출하기 위하여 연약지반 내부에 관입되는 것으로, 도 1과 같이 복수의 배수통로(10)가 수직으로 구획된 골조(20)와 상기 골조(20)의 외측에 설치된 부직포(30)와 상기 부직포(30)의 상단 외면부에 형성된 불투과층(40)으로 구성된 연약지반 개량을 위한 배수재(100)를 시공하는 방법이다. The present invention is to penetrate into the soft ground in order to draw out the gap water to the outside when using the individual vacuum consolidation method to improve the soft ground, as shown in Figure 1, the plurality of drainage passages 10 are vertically divided frame 20 And a non-woven fabric 30 installed on the outside of the frame 20 and an impermeable layer 40 formed on the upper outer surface of the non-woven fabric 30, the drainage material 100 for improving the soft ground.

특히, 본 발명의 연약지반 개량을 위한 배수재 시공방법은 시공현장에서 롤형태로 감겨 있는 상태의 배수재(100)를 가공한 후 시공장비(I)로 시공함으로써 배수재(100)의 시공 효율을 극대화시킨 것이 큰 특징이다. In particular, the drainage construction method for improving the soft ground of the present invention by maximizing the construction efficiency of the drainage 100 by processing with the construction equipment (I) after processing the drainage material 100 in a roll form in the construction site It is a big feature.

즉, 생산공장에서 배수재(100)의 제조부터 가공까지 완료한 후 시공현장으로 운반하여 연약지반 내부에 관입시켜 시공하는 종래의 배수재 시공방법과 달리, 시공현장에서 배수재(100)의 가공 및 시공 작업을 연속적으로 행함으로써 시공의 편의성을 향상시키고 공기를 단축시킨 것이다. That is, unlike the conventional drainage construction method in which the production plant completes the manufacturing process of the drainage 100 and then transports it to the construction site and injects it into the soft ground, the processing and construction work of the drainage 100 at the construction site. By carrying out continuously, the convenience of construction is improved and the air is shortened.

이는 시공현장에서 맨드럴(M)을 연약지반 내부로 관입시켜 맨드럴(M)을 작동시키는 유압장치(H)의 압력 변화를 통해 복토층(A)의 깊이와 개량대상층(B)의 거리 등에 대한 데이터를 획득하고, 상기 획득한 데이터를 이용하여 배수재(100)의 절단 길이와 배수재(100)가 배수재관이나 수평배수재 등에 연결하기 위하여 복토층(A) 상부에 일부 노출되고, 개량 대상층(B)에 일부 깊이까지 관입 가능한 불투과층(40)의 코팅 길이 등의 데이터를 산출하며, 산출된 데이터에 부합되게 시공현장에 비치된 가공장치(P)로 배수재(100)를 가공하고, 가공된 배수재(100)를 시공장비(I)로 연약지반 내부로 관입시켜 시공을 완료하는 방법에 의해 달성된다.This is based on the depth of the cover layer (A) and the distance of the improvement target layer (B) through the pressure change of the hydraulic device (H) that injects the mandrel (M) into the soft ground to operate the mandrel (M) at the construction site. Acquire the data, and using the obtained data, the cut length of the drain material 100 and the drain material 100 are partially exposed on the cover layer A to connect to the drain pipe or the horizontal drain material, and to the improvement target layer B. It calculates the data such as the coating length of the impermeable layer 40 that can penetrate to a certain depth, and processes the drainage material 100 with a processing device (P) provided in the construction site in accordance with the calculated data, and the processed drainage material ( 100) is achieved by injecting the construction equipment (I) into the soft ground to complete the construction.

따라서 시공현장에 비치된 가공장치(P)를 이용하여 롤형태로 감겨 있는 배수재(100)를 가공한 후 바로 연약지반 내부로 관입시켜 시공을 완료할 수 있다. Therefore, after processing the drainage material 100 wound in a roll shape by using the processing device (P) provided in the construction site can be completed by injecting into the soft ground immediately.

이에 따라 시공현장에서 배수재(100)의 절단 길이와 불투과층(40)의 코팅 길이를 결정하기 위한 데이터를 획득 및 산출한 후 그 데이터를 이용하여 생산공장에서 배수재(100)를 가공한 다음 다시 시공현장으로 운반하여 배수재(100)를 시공함으로 인해 시공 편의성이 저하되고 공기도 연장되는 종래의 문제점이 완전히 해소된다. Accordingly, after acquiring and calculating data for determining the cutting length of the drain material 100 and the coating length of the impermeable layer 40 at the construction site, the drain material 100 is processed in the production plant using the data and then again. By carrying the construction to the construction site by the drainage 100, the convenience of construction is lowered and the conventional problem of extending the air is completely solved.

상기와 같은 특성을 가지는 본 발명의 배수재 시공방법을 각각의 단계별로 보다 상세하게 설명하면 다음과 같다. When explaining the drainage construction method of the present invention having the characteristics as described above in more detail in each step as follows.

우선, 배수재(100)를 시공하기에 앞서 무거운 중량의 시공장비(I)가 안전하게 이동할 수 있도록 연약지반 상부에는 상기 시공장비(I)로부터 가해지는 하중에 충분히 견디도록 표층처리가 선행되어야 한다. First, prior to the construction of the drainage 100, the surface of the soft ground must be preceded to sufficiently withstand the load applied from the construction equipment I so that the heavy construction equipment I can safely move.

즉, 연약지반의 개량대상층(B) 상부에 매트(D)를 격자형태로 설치하고, 상기 매트(D) 상부에 양질의 토사를 포설하여 복토층(A)을 형성한다. 그러면 연약지반의 개량대상층(B) 내부에 많은 간극수가 존재하더라도 상기 매트(D)와 복토층(A)에 의해 안정화되어 시공장비(I)의 하중에 의한 침하 현상을 막을 수 있다. That is, the mat (D) is installed in a lattice form on the upper part of the improvement target layer (B) of the soft ground, and a high-quality soil is disposed on the mat (D) to form a cover layer (A). Then, even if a large number of pore water in the improvement target layer (B) of the soft ground stabilized by the mat (D) and the cover layer (A) can prevent the settlement phenomenon by the load of the construction equipment (I).

상기와 같이 연약지반의 표층처리를 행한 후에는 연약지반의 지층 분석을 실시한다. 이는 배수재(100)의 절단 길이와 불투과층(40)의 코팅 길이를 결정하는 데이터가 되는 복토층(A)의 깊이와 개량대상층(B)의 깊이 등을 파악하기 위함이다. As described above, after the surface treatment of the soft ground is carried out, the geological analysis of the soft ground is performed. This is to determine the depth of the cover layer (A) and the depth of the improvement target layer (B), which are data for determining the cutting length of the drainage material 100 and the coating length of the impermeable layer 40.

이러한 지층 분석은 시공장비(I)에 설치된 맨드럴(M)을 연약지반으로 관입시킨 후 인발하는 과정을 통하여 간단하게 이루어지는데, 맨드럴(M)이 연약지반으로 관입되는 과정에서 맨드럴(M)을 가동시키는 유압장치(H)의 압력 변화를 통해 간단하게 분석 처리된다. This stratum analysis is performed simply by injecting the mandrel (M) installed in the construction equipment (I) into the soft ground and drawing it out. The mandrel (M) is introduced into the soft ground. It is simply analyzed through the pressure change of the hydraulic device (H) that activates.

즉, 맨드럴(M)이 복토층(A)으로 관입될 때는 유압장치(H)의 압력은 일정하게 유지되다가, 복토층(A)과 매트(D)를 통과하여 개량대상층(B)으로 관입되는 순간에는 유압장치(H)의 압력이 하강된다. 그리고 맨드럴(M)이 개량대상층(B)을 통과하여 하부지지층(C)으로 관입되려는 순간에는 다시 유압장치(H)의 가동 압력은 복토층(A)으로 관입될 때의 압력보다 더욱 높게 상승된다. That is, when the mandrel (M) is introduced into the cover layer (A), the pressure of the hydraulic device (H) is kept constant, while passing through the cover layer (A) and the mat (D) into the improvement target layer (B) The pressure of the hydraulic device (H) is lowered. At the moment when the mandrel M tries to penetrate the lower support layer C through the improvement target layer B, the operating pressure of the hydraulic device H is increased higher than the pressure when the mandrel M is introduced into the cover layer A. .

따라서 시간에 따른 유압장치(H)의 압력 변화를 유압장치(H)와 연결된 감지부에서 감지한 후 그 감지신호를 감지부와 연결된 연산부로 전송한다. 그러면 연산부는 감지부의 감지신호와 맨드럴(M)의 관입 속도를 이용하여 복토층(A)의 깊이와 개량대상층(B)의 깊이에 데이터를 산출한다. Therefore, after detecting the pressure change of the hydraulic device (H) over time by the sensing unit connected to the hydraulic device (H) and transmits the detection signal to the calculation unit connected to the sensing unit. Then, the calculating unit calculates data in the depth of the cover layer (A) and the depth of the improvement target layer (B) by using the detection signal of the detector and the penetration speed of the mandrel (M).

그런 다음 산출부는 상기 데이터를 산출부와 연결된 제어부로 전송하고, 제어부는 산출부의 데이터와 부합되게 배수재(100)의 절단 길이와 불투과층(40)의 코팅 길이를 결정한다. Then, the calculation unit transmits the data to the control unit connected to the calculation unit, and the control unit determines the cutting length of the drainage material 100 and the coating length of the impermeable layer 40 in accordance with the data of the calculation unit.

이때 배수재(100)의 절단 길이는 복토층(A)과 개량대상층(B)을 합한 깊이보다 긴 길이가 되어야 한다. At this time, the cutting length of the drainage material 100 should be longer than the depth of the combined cover layer (A) and the improvement target layer (B).

이는 배수재(100)의 상단은 배수재관이나 수평배수재 등에 연결하기 위하여 복토층(A)의 외부로 일정길이 노출되고, 배수재(100)의 하단은 하부지지층(C)에 존재하는 지하수가 배수재(100)로 흡출되면서 연약지반 내부에 존재하는 간극수가 제대로 흡출되지 않는 폐단을 막기 위해, 개량대상층(B)의 하부지지층(C) 깊이보다 얕게 관입되고, 배수재(100)의 하단에는 맨드럴(M)과 연결되는 정착구(S)가 설치되는 길이(약 0.5m)를 감안하여 절단한다.This is the upper end of the drainage 100 is exposed to a certain length to the outside of the cover layer (A) in order to connect to the drainage pipe or horizontal drainage, etc., the bottom of the drainage 100 is the groundwater existing in the lower support layer (C) drainage 100 In order to prevent the end of the gap that is present in the soft ground while being sucked into the poor ground, the depth is lower than the depth of the lower support layer (C) of the improvement target layer (B), the mandrel (M) and the bottom of the drainage material 100 It cuts in consideration of the length (about 0.5m) is installed fixing unit (S).

그리고 불투과층(40)의 코팅 길이는 불투과층(40)이 형성된 배수재(100)가 배수재관이나 수평배수재 등에 연결하기 위한 복토층(A) 상부 노출길이(약0.5m)와 불투과층(40)이 복토층(A)을 통과하여 개량대상층에 일부(약 1.0m)가 관입되도록 복토층(A)의 깊이보다 긴 길이가 함께 고려되어야 한다. And the coating length of the impermeable layer 40 is the cover layer (A) upper exposure length (about 0.5m) and the impermeable layer (10) for connecting the drainage material 100 formed with the impermeable layer 40 to a drainage pipe or a horizontal drainage material ( The length longer than the depth of the cover layer A must be considered together so that 40 (40) passes through the cover layer A and penetrates a part (about 1.0 m) into the layer to be improved.

이는 배수재(100)의 불투과층(40)이 복토층(A) 하부 개량대상층(B)에 일부가 관입되지 않으면 진공압이 개량대상층(B)으로 제대로 작용하지 않고 흡출된 간극수는 복토층(A)으로 개량대상층(B)으로 유출되기 때문이다. This means that if the impermeable layer 40 of the drainage material 100 does not penetrate into the cover layer A under the improvement target layer B, the vacuum pressure does not function properly as the improvement target layer B, and the gap water extracted is covered with the cover layer A. This is because it flows out into the improvement target layer (B).

상기와 같이 배수재(100)의 절단 길이와 불투과층(40)의 코팅 길이에 대한 데이터가 결정되면, 제어부는 상기 데이터를 시공현장에 비치된 가공장치(P)로 전송한다. When the data on the cutting length of the drainage material 100 and the coating length of the impermeable layer 40 is determined as described above, the control unit transmits the data to the processing device P provided at the construction site.

그러면 가공장치(P)는 롤형태의 배수재(100)를 배수재관이나 수평배수재 등에 연결하기 위한 복토층(A) 상부 노출길이(약0.5m)와 불투과층(40)이 복토층(A)을 통과하여 개량대상층 관입(약 1.0m)에 필요한 길이 등을 고려한 코팅 길이로 불투과층(40)을 상단에 형성시킨 다음 불투과층(40) 길이, 개량대상층(B) 심도 및 정착구(S) 설치길이 등을 고려한 절단 길이로 절단하는 가공을 행한다. Then, the processing apparatus (P) has a top cover length (about 0.5 m) of the cover layer (A) and an impermeable layer (40) passing through the cover layer (A) to connect the roll-shaped drain material 100 to the drain pipe or horizontal drain material. To form the impermeable layer 40 at the top with a coating length in consideration of the length required for penetration of the object to be improved (about 1.0 m), and then install the length of the impermeable layer 40, the depth of the object to be improved (B) and the anchorage (S). The process which cut | disconnects at the cutting length which considered length etc. is performed.

그런 다음 도 2와 같이 가공된 배수재(100)를 맨드럴(M)의 내부에 설치되어 윈치(W)에 의해 맨드럴(M)의 내부에서 승하강되는 와이어(R)에 결속시킨 후 윈치(W)를 작동시켜 맨드럴(M)의 상단 일정높이까지 인발한다. Then, the drainage 100 processed as shown in FIG. 2 is installed inside the mandrel M, and is bound to the wire R which is lifted up and down inside the mandrel M by the winch W and then the winch ( Activate W) to draw up to a certain height at the top of the mandrel (M).

이때 배수재(100)를 와이어(W)에 결속시켜 맨드럴(M)의 내부를 통해 그 하부에서 그 상단의 일정높이까지 인발하는 것은 바람에 배수재(100)가 엉키는 것을 막기 위한 것이다. At this time, binding the drainage 100 to the wire (W) to draw through the inside of the mandrel (M) from the bottom to a certain height of the upper end to prevent the drainage 100 is tangled in the wind.

그리고 일정높이까지 인발된 배수재(100)의 하단에 보호비닐(50)을 씌운 후 맨드럴(M)에 고정된 정착구(S)에 연결 고정시킨다. 그런 다음 시공장비(I)의 유압장치(H)를 작동시켜 맨드럴(M)을 연약지반 내부로 관입시킴으로써 도 3과 같이 배수재(100)의 시공이 완료된다. And after covering the protective vinyl 50 to the lower end of the drainage material 100 drawn up to a certain height and fixed to the anchorage (S) fixed to the mandrel (M). Then, by operating the hydraulic device (H) of the construction equipment (I) by injecting the mandrel (M) into the soft ground, the construction of the drainage 100 is completed as shown in FIG.

여기서 배수재(100)의 하단에 보호비닐(50)을 씌우는 것은, 배수재(100)의 절단 길이 혹은 시공 깊이가 실제 지층과 맞지 않아 배수재(100)의 하단이 하부지지층(C)에 이르더라도 하부지지층(C)에 존재하는 지하수나 공기의 유입을 차단하여 간극수의 흡출이 원활하도록 하기 위함이다. In this case, the protective vinyl 50 is applied to the lower end of the drainage material 100 even if the cutting length or the construction depth of the drainage material 100 does not match the actual strata, so that the lower support layer C reaches the lower support layer C. This is to block the inflow of groundwater or air present in (C) to facilitate the outflow of gap water.

이때 연약지반의 지층 분석은 하나의 배수재(100)를 시공할 때마다 매번 행하지는 않는다. 왜냐하면 보통 연약지반의 지층 분포가 급격하게 변화되지 않아 변화량이 크지 않거나 일정하기 때문이다. At this time, the geological analysis of the soft ground is not performed every time one construction of the drainage 100. This is because the distribution of strata in soft ground is not changed drastically, so the amount of change is not large or constant.

즉, 연약지반 전체를 복수의 구역으로 분할한 후 분할된 각 구역마다 한 번씩 연약지반의 지층 분석을 행하면 된다. 그러면 맨드럴(M)을 통해 배수재(100)를 연약지반 내부로 관입하는 작업을 연속적으로 행할 수 있다. In other words, the entire soft ground may be divided into a plurality of zones, and then the geological analysis of the soft ground may be performed once for each divided zone. Then, through the mandrel (M) can be continuously performed to inject the drain material 100 into the soft ground.

이와 같이 본 발명은 시공현장에서 가공장치(P)로 배수재(100)를 가공한 후 바로 맨드럴(M)로 연약지반 내부에 관입하여 시공을 완료함으로써, 배수재(100)의 시공성을 향상시켜 배수재(100)의 시공 효율을 더욱 높이고 공기를 크게 단축시킬 수 있다.
As described above, the present invention processes the drainage material 100 with the processing device P at the construction site and immediately penetrates into the soft ground with the mandrel M to complete the construction, thereby improving the workability of the drainage material 100 and draining the water. It is possible to further increase the construction efficiency of the 100 and to significantly shorten the air.

10: 배수통로 20: 골조
30: 부직포 40: 불투과층
50: 보호비닐 100: 배수재
A: 복토층 B: 개량대상층 C: 하부지지층 D: 매트
P: 가공장치 I: 시공장비
H: 유압장치 M: 맨드럴
W: 윈치 R: 와이어
S: 정착구
10: drainage channel 20: frame
30: nonwoven fabric 40: impermeable layer
50: protective vinyl 100: drainage
A: cover layer B: improvement target layer C: lower support layer D: mat
P: Processing Equipment I: Construction Equipment
H: Hydraulic M: Mandrel
W: winch R: wire
S: anchorage

Claims (1)

시공장비(I)에 설치된 맨드럴(M)을 연약지반 내부로 관입시켜 맨드럴(M)의 관입 속도와 맨드럴(M)을 가동시키는 유압장치(H)의 시간에 따른 압력 변화를 통해 복토층(A)의 깊이와 개량대상층(B)의 깊이를 획득하는 단계; 배수재(100)를 배수재관 이나 수평배수재 등에 연결하기 위한 복토층(A) 상부 노출길이와, 복토층(A)의 깊이와, 복토층(A)을 통과하여 개량대상층(B)의 일정 깊이까지의 관입에 필요한 길이의 합으로 불투과층(40)의 코팅 길이를 산출하는 단계; 상기 불투과층(40) 길이와, 개량대상층(B)의 깊이 및 정착구(S)의 설치 길이를 고려하여 배수재(100)의 절단 길이를 산출하는 단계; 가공장치(P)를 사용하여 롤형태로 감겨 있는 코팅 안 된 배수재(100)에 상기 단계에서 산출한 불투과층(40)의 코팅 길이만큼 불투과층(40)을 코팅으로 형성시키고, 형성된 불투과층(40)을 포함하여 상기 단계에서 산출한 절단 길이만큼 절단하여 가공하는 단계; 가공된 배수재(100)의 상단을 윈치(W)에 의해 작동되는 와이어(R)에 결속시켜 맨드럴(M)의 상부로 인발시키는 단계; 맨드럴(M)의 상부로 인발된 배수재(100)의 하단에 일정길이의 보호비닐(50)을 씌운 후 맨드럴(M)에 고정된 정착구(S)를 연결하는 단계; 유압장치(H)를 통해 맨드럴(M)을 가동하여 맨드럴(M)을 연약지반 내부로 관입시켜 배수재(100)의 시공을 완료하는 단계;를 포함하여 구성됨을 특징으로 한 연약지반 개량을 위한 배수재 시공방법.
Penetrating the mandrel (M) installed in the construction equipment (I) into the soft ground through the change of the penetration rate of the mandrel (M) and the pressure of the hydraulic device (H) to operate the mandrel (M) over time Obtaining a depth of (A) and a depth of the improvement target layer (B); For the penetration of the cover layer (A) upper exposure length, the depth of the cover layer (A), and the cover layer (A) to a certain depth of the improvement target layer (B) for connecting the drain material 100 to the drain pipe or horizontal drain material Calculating the coating length of the impermeable layer 40 as the sum of the required lengths; Calculating a cutting length of the drainage material 100 in consideration of the length of the impermeable layer 40, the depth of the improvement target layer B, and the installation length of the fixing unit S; The impermeable layer 40 is formed as a coating on the uncoated drainage material 100 wound in the form of a roll using the processing device P as long as the coating length of the impermeable layer 40 calculated in the above step. Cutting by processing the cutting length including the transmission layer 40 calculated in the above step; Binding the upper end of the processed drainage 100 to the wire R operated by the winch W to draw the upper portion of the mandrel M; Attaching a fixing device S fixed to the mandrel M by covering a predetermined length of the protective vinyl 50 at a lower end of the drain material 100 drawn to the upper part of the mandrel M; The operation of the mandrel (M) through the hydraulic device (H) to inject the mandrel (M) into the soft ground to complete the construction of the drainage 100; the soft ground improvement characterized in that it comprises a Drainage construction method.
KR1020110039289A 2011-04-27 2011-04-27 Construction method of drain apparatus KR101248825B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110039289A KR101248825B1 (en) 2011-04-27 2011-04-27 Construction method of drain apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110039289A KR101248825B1 (en) 2011-04-27 2011-04-27 Construction method of drain apparatus

Publications (2)

Publication Number Publication Date
KR20120121460A KR20120121460A (en) 2012-11-06
KR101248825B1 true KR101248825B1 (en) 2013-04-01

Family

ID=47507898

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110039289A KR101248825B1 (en) 2011-04-27 2011-04-27 Construction method of drain apparatus

Country Status (1)

Country Link
KR (1) KR101248825B1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104762951B (en) * 2014-12-30 2016-08-17 华北水利水电工程集团有限公司 Secondary directly discharging type vacuum prepressing processes the construction method of new hydraulically filled sludge epeirogenetic
CN107190728B (en) * 2017-06-26 2022-10-18 中交一航局第三工程有限公司 Drainage plate setting device and method
CN113668499B (en) * 2021-09-08 2023-01-17 天津大学 Vacuum preloading drainage system and drainage method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09184129A (en) * 1995-12-28 1997-07-15 Daito Kogyo Kk Mandrel for drain material placement
KR100650435B1 (en) 2006-09-04 2006-11-30 (주)수림건설 Plastic board drain apparatus multi-drain casing with improvement soft ground
JP2007016386A (en) 2005-07-05 2007-01-25 Toa Harbor Works Co Ltd Construction method for improving soft ground
KR100913547B1 (en) 2008-09-12 2009-08-24 박정준 A drain board laying device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09184129A (en) * 1995-12-28 1997-07-15 Daito Kogyo Kk Mandrel for drain material placement
JP2007016386A (en) 2005-07-05 2007-01-25 Toa Harbor Works Co Ltd Construction method for improving soft ground
KR100650435B1 (en) 2006-09-04 2006-11-30 (주)수림건설 Plastic board drain apparatus multi-drain casing with improvement soft ground
KR100913547B1 (en) 2008-09-12 2009-08-24 박정준 A drain board laying device

Also Published As

Publication number Publication date
KR20120121460A (en) 2012-11-06

Similar Documents

Publication Publication Date Title
KR101458814B1 (en) A liquid collection process with liquid guiding holes for in-situ leaching an ore body to extract rare earth
KR101248825B1 (en) Construction method of drain apparatus
CN109236328A (en) The reinforcement means of shallow embedding mountain tunnel suitable for rich water soft layer
KR101407350B1 (en) A liquid collection process with secondary channels for in-situ leaching an ore body to extract rare earth
CN106149673B (en) Collapsible loess deep is soaked heavy-tamping method in advance
JP2013117167A (en) Freshwater storage system
US7736091B2 (en) Method and device for inserting a drainage wick
KR101219690B1 (en) apparatus and method of constructing draining subsurface water
CN209891205U (en) Outer infiltration of foundation ditch lateral wall is dredged and is arranged structure
KR101188733B1 (en) Permeability rock stagnant water grouting method for bulk injection type
JP4532337B2 (en) Propile pile sheet pile method capable of treating underground water
CN105926396B (en) A kind of town road subgrade drainage structure and its construction method
CN210269304U (en) Soil moisture layering collection device
JP6448133B2 (en) Vacuum consolidation method and vacuum consolidation system
CN108265698A (en) A kind of ecological treatment method of landfill discarded slurry
KR101239675B1 (en) Construction method of drain apparatus for suction drain method
CN106245661B (en) The method of buried pipe and its embedded buried pipe
KR101440250B1 (en) Vertical drainage material construction method for riprap layer
CN104895045B (en) Method for embedding horizontal drainage channel in soft soil foundation and device thereof
KR101293778B1 (en) apparatus and method of constructing draining subsurface water
CN210104710U (en) Weak soil foundation drainage well reinforced structure
CN211006700U (en) Foundation ditch flowing water lateral wall drainage protects structure
CN108035370A (en) A kind of well-point pipe and the foundation ditch construction method using the well-point pipe
CN108532710A (en) Construction landscape rainwater recycle utilizes facility and its construction method
KR20010038244A (en) Engineering methods to improve subsurface of soft ground

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160307

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170307

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20180307

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20190307

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20200309

Year of fee payment: 8