KR101149564B1 - Operation method and apparatus of emergency generator for reserve power - Google Patents

Operation method and apparatus of emergency generator for reserve power Download PDF

Info

Publication number
KR101149564B1
KR101149564B1 KR1020110105810A KR20110105810A KR101149564B1 KR 101149564 B1 KR101149564 B1 KR 101149564B1 KR 1020110105810 A KR1020110105810 A KR 1020110105810A KR 20110105810 A KR20110105810 A KR 20110105810A KR 101149564 B1 KR101149564 B1 KR 101149564B1
Authority
KR
South Korea
Prior art keywords
power
diesel generator
emergency
emergency diesel
reserve
Prior art date
Application number
KR1020110105810A
Other languages
Korean (ko)
Inventor
김운해
Original Assignee
부경엔지니어링주식회사
김운해
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 부경엔지니어링주식회사, 김운해 filed Critical 부경엔지니어링주식회사
Priority to KR1020110105810A priority Critical patent/KR101149564B1/en
Application granted granted Critical
Publication of KR101149564B1 publication Critical patent/KR101149564B1/en

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/04Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
    • H02J9/06Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems
    • H02J9/08Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems requiring starting of a prime-mover
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R19/00Arrangements for measuring currents or voltages or for indicating presence or sign thereof
    • G01R19/165Indicating that current or voltage is either above or below a predetermined value or within or outside a predetermined range of values
    • G01R19/16533Indicating that current or voltage is either above or below a predetermined value or within or outside a predetermined range of values characterised by the application
    • G01R19/16538Indicating that current or voltage is either above or below a predetermined value or within or outside a predetermined range of values characterised by the application in AC or DC supplies

Abstract

PURPOSE: A method and an apparatus for operating an emergency generator in order to secure the reserve power of a power system are provided to supply emergency power to the power system by operating emergency diesel generators scattered across the whole country. CONSTITUTION: House load(2) is in connection with a power system(1) through a first switch(4). A second switch(5) is installed to be in parallel with the house load at the backend part of the first switch. An emergency diesel generator(3) is in connection with the backend part of the second switch. A power outage monitoring part controls the first switch and the second switch. A remote command transmitting and receiving part operate the switches according to the remote commands of a power exchange(10). A parallel operation commanding part(14) drives a generation adjusting part(13) to control the operation of the emergency diesel generator.

Description

전력계통 예비전력 확보를 위한 비상 발전기 운전방법 및 장치{Operation method and apparatus of emergency generator for reserve power}Operation method and apparatus for emergency generator for securing power system reserve

본 발명은 전력 계통의 예비전력 부족을 해소하기 위한 것으로, 전력계통의 예비전력 부족이 감지되면 전국 아파트단지, 학교, 기타 시설 등에 기 설치되어있는 비상 발전기를 기동시켜 전력계통의 부족전력 확보차원에서의 운전 예비전력 부족 사태를 해소시킬 수 있도록 하는 전력계통 예비전력 확보를 위한 비상 발전기 운전방법 및 장치에 관한 것이다.The present invention is to solve the shortage of the reserve power of the power system, when the lack of reserve power of the power system is detected by starting the emergency generators already installed in apartment complexes, schools, and other facilities nationwide in order to secure the power shortage of the power system The present invention relates to a method and apparatus for operating an emergency generator for securing a power system reserve power to solve a shortage of operation reserve power.

국내에서 2011. 09. 15에 발생된 순환정전사태는 전력계통의 예비전력 부족으로 인하여 발생된 것으로, 이를 해소하기 위해서는 예비전력을 충분히 확보하여야 하나, 예비전력 확충을 위하여 추가적인 발전소의 증설은 물론 다각적인 예비전력 확보방안이 필요하나 본 발명은 화력발전의 경우 운전대기 중인 발전기를 기동시키고자 할 때 충분한 예열시간을 필요로 하기 때문에 급작스러운 예비전력 저하에 대처하기가 곤란한 점을 해결하기위한 발명이다.In Korea, the circular outage occurred on September 15, 2011 due to the lack of reserve power in the power system. To solve this problem, sufficient power reserve must be secured. The present invention is to solve the problem that it is difficult to cope with the sudden decrease of the reserve power, because it requires sufficient preheating time when starting the generator in standby in thermal power generation .

즉, 발전기의 발전전력을 확대시켜 예비전력 부족을 보상하기 위해서는 대용량화력 발전기가 정상출력을 내기까지의 시간이 오래 걸려 효과적으로 사용될 수 없으며, 또한 전력 사용량의 증가로 인하여 실시간적인 운전예비력확보가 필요한 것이 전력계통운영의 특성이므로 예비력 확보는 물론 이러한 기술적 특성을 해소할 수 있는 운전방안이 절실하게 필요한 점이 있다 하겠다.In other words, in order to compensate for the shortage of reserve power by expanding the power generation of the generator, it cannot be effectively used because it takes a long time for the large-capacity power generator to reach the normal output, and it is necessary to secure the real-time operational reserve due to the increase of the power consumption. As it is a characteristic of power system operation, there is a desperate need for not only securing reserve power but also operating methods that can solve these technical characteristics.

한편 전국의 아파트, 종교시설, 학교, 병원, 대형건물, 공장 등에는 정전 시 비상발전을 위하여 통상 디젤유를 원료로 사용하는 비상용디젤발전기를 구비하고 있으나, 비상용디젤발전기는 순수하게 설치된 목적에 따라 해당 건물의 정전이 진행된 경우만 이를 감지하여 즉각 기동함으로써 정전에 대비하게 된다.Meanwhile, apartments, religious facilities, schools, hospitals, large buildings, and factories all over the country have emergency diesel generators that use diesel oil as raw materials for emergency power generation during power outages. Only when the power failure of the building is in progress, it detects it immediately and prepares for power failure.

즉, 도 1에 도시된 바와 같이 전력계통(1)을 통하여 공급되는 전력은 소내부하(2)로 공급되게 되고, 상기 소내부하(2)에는 전력계통(1)으로부터 공급되는 전력과는 별도로 정전시에만 비상용디젤발전기(3)를 구동시켜 발전시킨 전력이 공급될 수 있도록 하고 있으며, 상기 상용전력과 비상전력은 스위치(4)(5)의 절환에 의해 공급이 선택되게 되고, 이때 스위치(4)(5)는 정전을 감지한 정전감지부(6)에 의해 작동되며, 상기 정전감지부(6)에서는 비상용디젤발전기(3)의 구동을 제어하는 한편 차단기투입이 이루어지도록 한다.That is, as shown in FIG. 1, the power supplied through the power system 1 is supplied to the small load 2, and the small load 2 is separately interrupted from the power supplied from the power system 1. Only when the emergency diesel generator 3 is driven so that the generated power can be supplied. The commercial power and the emergency power are supplied by switching of the switches 4 and 5, and at this time, the switch 4 (5) is operated by the electrostatic detection unit (6) detecting the power failure, the electrostatic detection unit (6) controls the operation of the emergency diesel generator (3) while the breaker input is made.

여기서 정전감지부(6)는 전력계통(1)의 정전이 감지되면 이를 감지하여 비상용디젤발전기(3)를 구동시켜 발전이 이루어지게 하는 한편 스위치(4)(5)를 절환시켜 비상전력의 차단기 투입이 이루어지도록 하고, 전력계통(1)의 정전이 복귀도면 정전감지부(6)에서는 스위치(4)(5)를 절환시켜 비상전력의 공급을 차단하는 한편 비상용디젤발전기(3)의 구동을 중단시키도록 한다.Here, the power failure detecting unit 6 detects a power failure of the power system 1 and drives the emergency diesel generator 3 to generate power, while switching the switches 4 and 5 to switch off the emergency power. When the power failure of the power system 1 is returned, the outage detection unit 6 switches the switches 4 and 5 to cut off the supply of emergency power while driving the emergency diesel generator 3. Stop it.

본 발명은 전력계통의 예비전력 부족을 해소하기 위하여 순환정전과 같은 사태가 발생하지 않도록 하는 것으로, 기존의 비상용디젤발전기가 특정 건물이나 장소의 정전 시에만 작동되어 비상전력을 공급함으로써 전력계통의 예비전력 부족을 해소하는 데는 전혀 도움이 되지 않았던 문제를 해결하기 위한 것으로, 전력계통의 예비전력 부족이 감지되면 전국에 산재한 비상용디젤발전기를 기동시켜 전력계통에 비상전력을 공급함으로써 예비전력 부족을 해소시키도록 하는 것이다.The present invention is to prevent a situation such as a cyclic outage in order to solve the shortage of the reserve power of the power system, the existing emergency diesel generator is operated only when a power failure of a specific building or place to supply emergency power to reserve the power system It is to solve the problem that did not help to solve the power shortage at all.If the shortage of the power system is detected, the emergency diesel generators scattered throughout the country are started to supply the emergency power to the power system. It is to be.

본 발명은 특정 건물별로 구비된 비상용디젤발전기를 이용하여 전력계통의 예비전력 부족을 해소하기 위한 것으로, 전력망을 총괄하는 전력거래소와 무선 통신으로 원격지령을 송신하고 수신하는 원격지령 송수신부를 구비하고, 상기 원격지령 송수신부와 통신을 하며 비상용디젤발전기의 기동과 출력을 조절하는 발전 조절부를 구비하며, 상기 발전 조절부의 제어에 따라 비상용디젤발전기의 병렬운전을 제어하는 병렬운전 지령부를 구비함으로써 이루어지는 것으로, 비상용디젤발전기를 정전시에만 구동시키는 기존의 운전방식에서 벗어나 전력계통의 예비전력이 부족할 때 비상용디젤발전기를 기동시켜 전력계통에 동기투여 함으로서 예비전력 부족을 간단히 해결할 수 있도록 하는 것이다.The present invention is to solve the lack of the reserve power of the power system by using an emergency diesel generator provided for each specific building, and has a remote command transceiver for transmitting and receiving a remote command by wireless communication with the power exchange that oversees the electric power grid, Comprising a communication with the remote command transmission and reception unit and having a power generation control unit for controlling the start and output of the emergency diesel generator, and comprises a parallel operation command unit for controlling the parallel operation of the emergency diesel generator under the control of the power generation control unit, It is to deviate the shortage of reserve power by activating the emergency diesel generator in synchronization with the power system when the reserve power of the power system is insufficient.

본 발명은 특정 건물별로 구비되어 전력계통의 정전이 감지된 경우 기동하게 되는 비상용디젤발전기를 전력계통의 예비전력이 부족할 때 전력거래소의 명령에 따라 비상용디젤발전기를 구동시켜 주파수와 전압을 조정한 후 전력계통에 동기투입 함으로써 예비전력 부족을 간단히 해결할 수 있는 효과가 있다.The present invention is provided by a specific building to start the emergency diesel generator to be activated when the power system is detected when the power system lacks the reserve power of the power system to operate the emergency diesel generator according to the power exchange command after adjusting the frequency and voltage Synchronous input to the power system can easily solve the shortage of reserve power.

즉, 정전 시에만 기동되어 평상시 사용하지 않는 비상용디젤발전기를 정전은 되지 않았으나 전력계통의 예비전력이 부족할 때 전력거래소에서 강제로 비상용디젤발전기를 기동시켜 예비전력의 부족을 간단히 해소시키는 것으로, 신설발전소의 건설 등과 같은 많은 비용과 기간을 필요로 하지 않고도 간단히 예비전력을 보충할 수 있는 효과가 있다.In other words, emergency diesel generators that are started only during a power outage and are not normally used, but do not have a power outage, but when the reserve system lacks the power system, the power exchange forcibly starts the emergency diesel generator to simply eliminate the lack of reserve power. There is an effect that can simply replenish the reserve power without requiring a large cost and period such as the construction of.

도 1은 기존의 전력계통도
도 2는 본 발명의 전력계통도
1 is a conventional power system diagram
2 is a power system diagram of the present invention

본 발명은 기존 전력계통에 비상용디젤발전기를 이용하여 정전 시 비상용 발전전력을 투입하는 일반적인 구성에서, 정전이 발생하지 않았음에도 전력계통의 예비전력이 부족할 경우 강제로 비상용디젤발전기를 기동시켜 전력계통에 동기 투입함으로써, 간단히 예비전력 부족 현상을 해소시키는 것으로, 국가 전력망을 총괄하는 전력거래소에서 강제로 비상용디젤발전기를 구동시키는 것이다. The present invention is a general configuration for injecting emergency power generation in the event of a power failure by using an emergency diesel generator in the existing power system, if the power reserve is not enough even if there is no power failure to start the emergency diesel generator forcibly to the power system By synchronously eliminating the shortage of reserve power, the emergency diesel generators are forcibly driven by a power exchange that oversees the national grid.

이를 위하여 본 발명은 전력거래소와 인터넷이나 CDMA 통신망을 이용하여 원격지령을 송신하고 수신하는 원격지령 송. 수신 부를 구비하고, 상기 원격지령 송수신부와 통신을 하며 전력거래소의 명령에 따라 비상용디젤발전기의 기동과 출력을 조절하는 발전 조절부를 구비하며, 상기 발전 조절부의 제어에 따라 비상용디젤발전기의 병렬운전을 제어하는 병렬운전 지령부를 구비하게 된다.To this end, the present invention transmits and receives a remote command using a power exchange and the Internet or a CDMA communication network. And a power generation control unit for communicating with the remote command transmission and reception unit and controlling the start and output of the emergency diesel generator according to the power exchange command. The parallel operation command part to control is provided.

전력거래소는 전력계통의 예비전력이 부족할 경우 통신망을 통하여 강제로 비상용디젤발전기 구동 명령을 내리게 되고, 이를 원격지령 송수신부에서 수신하여 발전 조절부에서 비상용디젤발전기의 기동을 기동시켜 주파수와 전압을 조절한 후 동기를 맞추어 전력계통으로 공급하도록 하며, 이때 전력계통으로 공급되는 전력량과 전압 등을 체크하여 전력거래소로 통보함으로써 전력거래소에서 예비전력을 산출할 수 있도록 하는 한편 비상용디젤발전기의 구동에 따른 보상이 이루어지도록 한다.The power exchange issues an emergency diesel generator driving command through the communication network when the reserve power of the power system is insufficient, receives it from the remote command transmitter and receiver and starts the emergency diesel generator in the power generation control section to adjust the frequency and voltage. After that, it is supplied to the power system in synchronization, and at this time, the power exchange checks the amount and voltage supplied to the power system and informs the power exchange so that the power exchange can calculate the reserve power and compensates the operation of the emergency diesel generator. Let this be done.

본 발명은 예비전력 확충을 위하여 발전소의 건설과 같은 시간과 비용이 많이 드는 행위를 하지 않고, 이미 갖추어져 있는 비상용디젤발전기를 활용하여 예비전력 확보에 사용하는 한편 비상용디젤발전기의 구동에 따른 보상이 이루어지도록 한다.The present invention does not take the time and costly acts such as the construction of a power plant to expand the reserve power, and is used to secure the reserve power by using an already equipped emergency diesel generator so that compensation can be achieved by driving the emergency diesel generator. do.

본 발명을 첨부된 실시예 도면에 의거 상세히 설명한다.The present invention will be described in detail with reference to the accompanying drawings.

본 발명에서 전력계통(1)에 스위치(4)를 통하여 소내부하(2)가 연결되는 한편 상기 스위치(4)의 후단으로 소내부하(2)와 병렬로 스위치(5)를 설치하고, 상기 스위치(5)의 후단으로 비상용디젤발전기(3)가 연결되게 하며, 상기 스위치(4)(5)는 전력계통(1)의 정전을 감지하는 정전감지부(6)에 의해 제어되게 하는 일반적인 계통도에서, 전력거래소(10)의 원격명령을 받아 원격지령 송수신부(12)에서 스위치(5)를 작동시키는 한편 발전 조절부(13)를 구동시킴으로써 병렬운전 지령부(14)에서 비상용디젤발전기(3)의 기동을 제어하는 동시에 출력전압을 조절하여 전력계통(1)으로 동기 투입이 이루어지도록 한다.In the present invention, the small load 2 is connected to the power system 1 through the switch 4, while the switch 5 is installed in parallel with the small load 2 at the rear end of the switch 4, and the switch The emergency diesel generator 3 is connected to the rear end of the apparatus 5, and the switches 4 and 5 are controlled by the electrostatic sensing unit 6 which detects the power failure of the power system 1. In response to the remote command of the power exchange 10, the remote command transmission unit 12 operates the switch 5 while driving the power generation control unit 13 in parallel operation command unit 14 in the emergency diesel generator (3) By controlling the start of the control at the same time the output voltage is adjusted so that the synchronous input to the power system (1).

본 발명은 일반적인 비상용디젤발전기(3)를 구비한 계통도에서, 전력거래소(10)의 지령을 통신망(11)을 통하여 전달받는 원격지령 송수신부(12)를 구비하고, 상기 원격지령 송수신부(12)는 스위치(5)를 구동시키는 동시에 발전조절부(13)를 작동시킴으로써 발전조절부(13)에서 병렬운전 지령부(14)에서 비상용디젤발전기(3)를 병렬 운전시키도록 한다.The present invention includes a remote command transceiver 12 for receiving a command of the power exchange 10 through a communication network 11 in a system diagram having a general emergency diesel generator 3, and the remote command transceiver 12 ) Drives the switch 5 and simultaneously operates the power generation control unit 13 so that the emergency diesel generator 3 is operated in parallel in the parallel operation command unit 14 in the power generation control unit 13.

여기서, 병렬운전 지령부(14)는 발전조절부(13)의 제어에 의해 비상용디젤발전기(3)를 작동시키되 병렬 연결된 비상용디젤발전기(3)를 순차적으로 구동되게 하는 한편 동기발전기인 비상용디젤발전기(3)의 발전 전력을 스위치(5)를 통하여 전력계통(1)으로 동기 투입이 이루어질 수 있도록 한다.Here, the parallel operation command unit 14 operates the emergency diesel generator 3 under the control of the power generation control unit 13 to sequentially drive the emergency diesel generator 3 connected in parallel, and the emergency diesel generator as a synchronous generator. Synchronous input of the generated power of (3) to the power system (1) through the switch (5) to be made.

발전 조절부(13)는 원격지령 송수신부(12)에 의해 구동이 제어되며, 병렬운전 지령부(14)를 제어하여 비상용디젤발전기(3)의 구동과 출력 전압 등을 제어하도록 하며, 비상용디젤발전기(3)가 구동되어 발전된 전력을 전력계통(1)으로 투입하는 량을 검출하여 원격지령 송수신부(12)를 통하여 전력거래소(10)로 보내도록 한다.The power generation control unit 13 is controlled by the remote command transmission and reception unit 12, and controls the parallel operation command unit 14 to control the drive and output voltage of the emergency diesel generator 3, emergency diesel The generator 3 is driven to detect the amount of power generated by the power system 1 to be sent to the power exchange 10 through the remote command transmission and reception unit 12.

원격지령 송수신부(12)는 전력거래소(10)와 인터넷이나 CDMA 와 같은 통신망(11)을 이용하여 통신이 이루어지도록 하되 전력거래소(10)로부터 발전신호를 받아 비상 발전이 이루어지도록 하는 한편 비상용디젤발전기(3)의 구동에 따른 보상을 위하여 비상용디젤발전기(3)의 구동시간이나 발전전력을 체크하여 전력거래소(10)로 송신함으로써 차후에 보상이 이루어지도록 한다.The remote command transceiver 12 communicates with the power exchange 10 using a communication network 11 such as the Internet or CDMA, while receiving power generation signals from the power exchange 10 to perform emergency power generation and emergency diesel. In order to compensate for the driving of the generator 3, the driving time or the generated power of the emergency diesel generator 3 is checked and transmitted to the power exchange 10 so that the compensation can be made later.

통신망(11)은 인터넷이나 CDMA망을 이용하고, 전력거래소(10)는 전국의 전력망을 총괄하여 전체 전력망의 예비전력 부족이 감지되면 통신망(11)을 통하여 비상발전을 원하는 지역과 장소를 설정하여 발전 명령을 내리게 된다.The communication network 11 uses the Internet or CDMA network, and the power exchange 10 oversees the nationwide electric power grid, and sets a region and a place for emergency power generation through the communication network 11 when a shortage of reserve power of the entire electric power grid is detected. You will be given a development order.

원격지령 송수신부(12)에는 각각의 IP를 지정하여 전력거래소(10)에서 원하는 지역과 장소를 한정하여 발전이 이루어지게 하거나 특정의 비상용디젤발전기(3)를 지정하여 기동과 정지를 선택할 수 있다.Remote command transmission and reception unit 12 may be assigned to each IP to limit the desired area and place on the power exchange 10 to generate power or to designate a specific emergency diesel generator (3) can select the start and stop. .

본 발명이 원활히 작동하기 위해서는 비상용디젤발전기(3)가 항상 기동이 이루어질 수 있도록 대기 상태를 유지하여야 하며, 비상용디젤발전기(3)는 기동 준비상태에서 소모되는 에너지가 거의 없으므로, 발전소에 장치된 발전기의 운전을 대기할 때 필요한 비용을 크게 줄일 수 있는 한편 비상용디젤발전기(3)의 기동에 준비시간이 걸리지 않으므로, 빠르게 전력계통의 예비전력 부족 현상을 해소할 수 있게 된다.In order for the present invention to operate smoothly, the emergency diesel generator 3 must be kept in a standby state so that it can be started at all times, and the emergency diesel generator 3 has little energy consumed in a ready state for starting, so that the generator installed in the power plant The cost required to wait for the operation can be greatly reduced, and the preparation time for starting the emergency diesel generator 3 does not take time, thereby quickly eliminating the preliminary power shortage phenomenon of the power system.

이러한 본 발명은 평상시 스위치(4)가 온 되고, 스위치(5)가 오프 된 상태에서 전력계통(1)에서 공급되는 전력이 소내부하(2)로 정상 공급되게 한 상태에서 비상용디젤발전기(3)는 기동되지 않고, 디젤을 원료로 하여 발전 대기 상태를 유지하게 되며, 전국의 전력망을 총괄하는 전력거래소(10)에서는 전력계통(1)의 예비전력을 감시하게 된다.The present invention is an emergency diesel generator (3) in the state that the switch (4) is normally on, the power supplied from the power system (1) is normally supplied to the small load (2) while the switch (5) is off Does not start, and maintains a standby state of power generation using diesel as a raw material, and the power exchange 10 which manages the national power grid of the whole country monitors the reserve power of the power system 1.

그리고, 전력거래소(10)는 통신망(11)을 통하여 원격지령 송수신부(12)와 수시로 통신하면서 지령을 내리고, 비상용디젤발전기(3)의 구동 상태를 확인할 수 있도록 한다.In addition, the power exchange 10 communicates with the remote command transmission / reception unit 12 through the communication network 11 at any time to give a command, so that the driving state of the emergency diesel generator 3 can be confirmed.

이 상태에서, 전력계통의 예비전력이 부족하여 이를 보충할 경우가 전력거래소(10)에서 감지되면, 전력거래소(10)에서는 통신망(11)을 통하여 원격지령 송수신부(12)로 발전명령을 내리게 되고, 원격지령 송수신부(12)는 이를 수신하면 스위치(5)를 구동시키는 동시에 발전 조절부(13)로 발전명령을 전달함으로써 발전 조절부(13)에서 병렬운전 지령부(14)를 통하여 비상용디젤발전기(3)를 구동시키도록 하며, 비상용디젤발전기(3)의 기동에 따는 전압과 출력을 조절하여 동기 투입이 이루어지도록 함으로써 전력계통의 예비전력 부족을 방지하도록 한다.In this state, when a case in which the supplementary power of the power system is insufficient and supplements it is detected at the power exchange 10, the power exchange 10 issues a power generation command to the remote command transmission / reception unit 12 through the communication network 11. When the remote command transmission and reception unit 12 receives this, it drives the switch 5 and simultaneously transmits a power generation command to the power generation control unit 13 so that the power generation control unit 13 uses the parallel operation command unit 14 for emergency use. By driving the diesel generator (3), by adjusting the voltage and output according to the start of the emergency diesel generator (3) to prevent the lack of the reserve power of the power system by synchronous input is made.

본 발명의 원격지령 송수신부(12)는 전력거래소(10)의 제어명령을 수신하여 비상용디젤발전기(3)에서 발전시킨 전력이 전력계통으로 동기 투입이 이루어질 수 있도록 하는 한편 동기 투입이 이루어진 전력량과 발전시간 등의 발전정보를 전력거래소(10)로 송신하여 차후에 정산이 이루어질 수 있도록 한다.The remote command transceiver 12 of the present invention receives the control command from the power exchange 10 to allow the power generated by the emergency diesel generator 3 to be synchronized with the power system, and the amount of power that has been synchronized. Power generation information such as power generation time is transmitted to the power exchange 10 so that settlement can be made later.

본 발명의 발전 조절부(13)는 원격지령 송수신부(12)에서 인가되는 제어신호에 의해 비상용디젤발전기(3)의 기동 명령을 전달하는 한편 발전 전압과 전력량을 조절하여 발전이 이루어질 수 있도록 하고, 본 발명의 병렬운전 지령부(14)는 비상용디젤발전기(3)를 병렬 운전을 제어하여 설정 출력을 맞추도록 하고, 비상용디젤발전기(3)의 출력전력은 전력계통에 동기 투입이 이루어지도록 한다.The power generation control unit 13 of the present invention transmits a start command of the emergency diesel generator 3 by a control signal applied from the remote command transmission unit 12, and controls power generation voltage and amount of power so as to generate power. In addition, the parallel operation command unit 14 of the present invention controls the emergency diesel generator 3 in parallel to set a set output, and the output power of the emergency diesel generator 3 is made to be synchronized with the power system. .

본 발명에서 전력계통으로 공급되는 비상용디젤발전기(3)의 전력량은 예비전력으로 활용되게 되므로, 사회적으로 문제가 되는 순환정전을 하지 않고도 전력 예비량을 지킬 수 있으며, 특히, 발전소를 건설하지 않고, 기존에 갖추어져 있는 비상용디젤발전기(3)를 이용하여 예비전력을 확보하는 효과가 있다.Since the amount of power of the emergency diesel generator 3 supplied to the electric power system in the present invention is utilized as a reserve power, it is possible to keep the reserve of power without a socially circulating blackout, in particular, without building a power plant, There is an effect of securing the reserve power by using the conventional emergency diesel generator (3).

한편 비상용디젤발전기(3)의 구동으로 예비전력이 확보되고, 충분한 전력의 공급이 이루어지거나 소비전력이 떨어져 전력계통의 전력이 안전선을 유지하면, 전력거래소(10)에서는 발전 정지명령을 통신망(11)으로 전달함으로써 원격지령 송수신부(12)에서는 비상용디젤발전기(3)의 기동을 중단시키는 동시에 스위치(5)를 차단하여 비상용디젤발전기(3) 쪽에서 발전된 전력이 전력계통(1)으로 투입되는 것을 차단하게 된다.On the other hand, if the reserve power is secured by driving the emergency diesel generator 3, and sufficient power is supplied or power consumption is low, and the power of the power system maintains a safety line, the power exchange 10 issues a power generation stop command to the communication network 11 The remote command transmission / reception unit 12 stops the start of the emergency diesel generator 3 and at the same time cuts off the switch 5 so that the power generated from the emergency diesel generator 3 is supplied to the power system 1. Will be blocked.

1 : 전력계통 2 : 소내부하
3 : 비상용디젤발전기 4.5 : 스위치
10 : 전력거래소 11 : 통신망
12 : 원격지령 송수신부 13 : 발전 조절부
14 : 병렬운전 지령부
1: Power system 2: Internal load
3: emergency diesel generator 4.5: switch
10: power exchange 11: communication network
12: remote command transceiver 13: power generation controller
14: Parallel operation command

Claims (3)

국가 전력망을 감시하여 전력계통의 예비전력이 설정치 이하로 떨어지는 것이 감지되면 전력거래소에서는 통신망을 통하여 원격지로 비상용디젤발전기의 기동명령을 내리고,
전력거래소의 기동명령을 원격지령 송수신부에서 수신하여 비상용디젤발전기의 기동명령을 출력시키는 한편 비상용디젤발전기의 발전 전력이 전력계통으로 공급될 수 있게 하고,
상기 원격지령 송수신부에서 수신된 지령에 따라 비상용디젤발전기를 기동시키는 한편 발전전압과 전력을 조절한 후 전력계통으로 동기 투입이 이루어지게 하며,
상기 비상용디젤발전기에서 전력계통의 예비전력으로 공급되는 전력은 전력거래소에서 체크하여 보상이 이루어지게 하고,
전력계통의 예비전력이 충분히 확보되면 전력거래소에서는 비상용디젤발전기의 기동을 중단시키는 것을 특징으로 하는 예비전력 보상을 위한 비상 발전기 운전방법.
When monitoring the national power grid and detecting that the reserve power of the power system falls below the set value, the power exchange issues an emergency diesel generator start command remotely through the communication network.
Receive the start command of the power exchange from the remote command transmitter and receiver to output the start command of the emergency diesel generator, and to allow the generated power of the emergency diesel generator to be supplied to the power system,
Start the emergency diesel generator according to the command received from the remote command transmitter and receiver, adjust the generation voltage and power, and then perform synchronous input to the power system.
The power supplied to the reserve power of the power system in the emergency diesel generator is checked by the power exchange to be compensated,
Emergency generator operation method for the reserve power compensation, characterized in that the power exchange stops the start of the emergency diesel generator when the reserve power of the power system is secured enough.
비상용디젤발전기(3)를 전력계통의 예비전력 부족시 전력거래소(10)에서 강제로 통신망(11)을 통하여 기동 명령을 내리고, 정전시 사용되는 비상용디젤발전기(3)를 상기 기동명령에 따라 기동시켜 발전이 이루어지게 하되 발전전력을 전력계통의 예비전력으로 동기 투입하며, 비상용디젤발전기(3)의 발전량은 전력거래소(10)에서 체크하여 보상이 이루어지게 하는 것을 특징으로 하는 예비전력 보상을 위한 비상 발전기 운전장치.When the emergency diesel generator 3 is insufficient in reserve power of the power system, the power exchange 10 forcibly issues a start command through the communication network 11 and starts the emergency diesel generator 3 used in case of power failure according to the start command. To generate power, while synchronously inserting the generated power into the reserve power of the power system, and checking the power generation amount of the emergency diesel generator 3 in the power exchange 10 to compensate for the reserve power. Emergency generator drive. 전력계통(1)의 전력이 스위치(4)를 통하여 소내부하(2)로 공급되는 한편 스위치(5)를 통하여 비상용디젤발전기(3)의 발전 전력이 소내부하(2)로 공급되는 장치에 있어서,
국가 전력망을 감시하여 전력계통의 예비전력이 설정치 이하로 떨어지는 것이 감지되면 통신망(11)을 통하여 비상발전 기동명령을 수신하여 발전명령을 출력하는 한편 비상용디젤발전기(3)의 발전 전력을 전력계통(1)으로 동기 투입하는 동시에 투입된 전력량을 전력거래소(10)로 송신하는 원격지령 송수신부(12)를 구비하고,
상기 원격지령 송수신부(12)의 발전명령을 수신하여 비상용디젤발전기(3)를 기동시키는 한편 출력과 전력을 조절하여 발전시키는 발전 조절부(13)를 구비하며,
상기 발전조절부(13)의 기동명령에 따라 비상용디젤발전기(3)를 구동시키되 병렬운전이 이루어지면서 전력계통(1)로 동기 투입이 이루어지게 하는 병렬운전 지령부(14)를 구비함으로써 이루어지는 것을 특징으로 하는 예비전력 보상을 위한 비상 발전기 운전장치.
In the apparatus in which the power of the power system 1 is supplied to the small load 2 through the switch 4, while the generated power of the emergency diesel generator 3 is supplied to the small load 2 through the switch 5, ,
When it is detected that the reserve power of the power system falls below the set value by monitoring the national power grid, the emergency power generation command is received through the communication network 11 to output the power generation command, and the power generation power of the emergency diesel generator 3 is output to the power system ( 1) and a remote command transmission and reception unit 12 for synchronously inputting and transmitting the amount of power input to the power exchange 10,
Receiving the power generation command of the remote command transmission and reception unit 12, the emergency diesel generator (3) is activated, and the power generation control unit 13 for generating power by controlling the output and power,
It is made by driving the emergency diesel generator (3) in accordance with the start command of the power generation control unit (13) while having a parallel operation command unit 14 for synchronous input to the power system (1) while parallel operation is made. Emergency generator operation for the reserve power compensation.
KR1020110105810A 2011-10-17 2011-10-17 Operation method and apparatus of emergency generator for reserve power KR101149564B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110105810A KR101149564B1 (en) 2011-10-17 2011-10-17 Operation method and apparatus of emergency generator for reserve power

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110105810A KR101149564B1 (en) 2011-10-17 2011-10-17 Operation method and apparatus of emergency generator for reserve power

Publications (1)

Publication Number Publication Date
KR101149564B1 true KR101149564B1 (en) 2012-05-29

Family

ID=46272615

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110105810A KR101149564B1 (en) 2011-10-17 2011-10-17 Operation method and apparatus of emergency generator for reserve power

Country Status (1)

Country Link
KR (1) KR101149564B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101521165B1 (en) * 2013-10-24 2015-05-18 모루시스템 주식회사 A Smart Uninterruptible Power Supply Apparatus for City Facilities and Control Method thereof
KR101564510B1 (en) * 2014-04-25 2015-10-30 가천대학교 산학협력단 System and Method for Serving a Frequency Control under Virtual Power Plant
KR101979231B1 (en) * 2018-09-21 2019-05-16 이종석 An emergency generator remote control device for securing reserve power
CN111509837A (en) * 2020-04-28 2020-08-07 合肥康尔信电力系统有限公司 Diesel generating set parallel output double-bus main-standby power supply control technology
KR102247755B1 (en) * 2020-06-08 2021-05-04 모광표 Power management system for reserve power management

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005168096A (en) 2003-11-28 2005-06-23 Soken Engineering:Kk Emergency power generating system
KR100907582B1 (en) 2009-02-04 2009-07-14 이승철 The method of controlling hydrogen fuel at the peak of operating

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005168096A (en) 2003-11-28 2005-06-23 Soken Engineering:Kk Emergency power generating system
KR100907582B1 (en) 2009-02-04 2009-07-14 이승철 The method of controlling hydrogen fuel at the peak of operating

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101521165B1 (en) * 2013-10-24 2015-05-18 모루시스템 주식회사 A Smart Uninterruptible Power Supply Apparatus for City Facilities and Control Method thereof
KR101564510B1 (en) * 2014-04-25 2015-10-30 가천대학교 산학협력단 System and Method for Serving a Frequency Control under Virtual Power Plant
KR101979231B1 (en) * 2018-09-21 2019-05-16 이종석 An emergency generator remote control device for securing reserve power
CN111509837A (en) * 2020-04-28 2020-08-07 合肥康尔信电力系统有限公司 Diesel generating set parallel output double-bus main-standby power supply control technology
KR102247755B1 (en) * 2020-06-08 2021-05-04 모광표 Power management system for reserve power management

Similar Documents

Publication Publication Date Title
KR101149564B1 (en) Operation method and apparatus of emergency generator for reserve power
US11050261B2 (en) Fuel cell system, external management apparatus, fuel cell apparatus, and control method for fuel cell apparatus
JP5935268B2 (en) Power generation control system
WO2014083832A1 (en) Power generation system, and control method for same
WO2011039586A1 (en) Electric power management system
WO2013072771A3 (en) Installation for producing electrical energy provided with means of energy storage and control method of such an installation
WO2013051882A3 (en) Apparatus and method for preventing command conflicts in a smart grid network
CN104778108A (en) Device and method for abnormal power failure circulating testing of server system
CN101369732A (en) Multi-parameter automatic presynchronization control method
MY167882A (en) Energy management system and management apparatus
US20140039700A1 (en) Home electric appliance control apparatus, home electric appliance control system, and home electric appliance control method
GB2494151A (en) Emergency light fittings with remote mains monitoring
CN202077124U (en) Television and standby control circuit thereof
CN104079065A (en) Method for making mobile power generation system be connected into power grid for operation in synchronous grid connection mode
JP2004350429A (en) Distributed power supply system and control program for distributed power supply system
JP2019122063A (en) Smart meter communication device
KR20170084528A (en) System and method for uninterruptible supply
CN103795084A (en) Microgrid one-button smooth switching control method from grid connection to off-grid mode
CN104574806A (en) Laser fence warning prompt method for remote operation of transformer substation
JP2013085412A (en) System interconnection power conditioner
WO2017126047A1 (en) Power conditioner
JP4353115B2 (en) Isolated operation detection device, isolated operation detection method, and grid interconnection system
CN201392465Y (en) Electric control device of gasifier
KR101424500B1 (en) Battery emergency power generator and electric power system having the battery emergency power generator
WO2011052928A3 (en) Standby power cutoff apparatus and control method and power supply

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150518

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20160718

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20170517

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20180711

Year of fee payment: 7