KR101072401B1 - Constructing lining simultaneously with excavating tunnel, and lining constructing method using thereof - Google Patents

Constructing lining simultaneously with excavating tunnel, and lining constructing method using thereof Download PDF

Info

Publication number
KR101072401B1
KR101072401B1 KR1020110056877A KR20110056877A KR101072401B1 KR 101072401 B1 KR101072401 B1 KR 101072401B1 KR 1020110056877 A KR1020110056877 A KR 1020110056877A KR 20110056877 A KR20110056877 A KR 20110056877A KR 101072401 B1 KR101072401 B1 KR 101072401B1
Authority
KR
South Korea
Prior art keywords
lining
tunnel
precast
frame
construction
Prior art date
Application number
KR1020110056877A
Other languages
Korean (ko)
Inventor
장진헌
권기익
전성근
정연현
정수헌
김성운
김영진
서경원
백기현
김웅구
Original Assignee
(주)대우건설
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)대우건설 filed Critical (주)대우건설
Priority to KR1020110056877A priority Critical patent/KR101072401B1/en
Application granted granted Critical
Publication of KR101072401B1 publication Critical patent/KR101072401B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs

Abstract

본 발명은 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치 및 이를 이용한 라이닝 축조 방법에 관한 것으로서, 특히 굴착된 터널에 설치되고, 내부에 공사 장비의 이동이 가능하도록 공간부가 설치되는 프레임부과; 굴착된 터널 하단 양측에 설치된 기초부를 따라 상기 프레임부를 이동시키고, 프리캐스트 라이닝이 거치되는 이동부; 및 상기 이동부에 거치된 상기 프리캐스트 라이닝을 상기 터널의 굴착면으로 이동시켜 상기 프리캐스트 라이닝을 축조하는 축조부로 이루어지는 것을 특징으로 한다.
상기와 같은 본 발명에 따르면 프레임부의 외측에 프리캐스트 라이닝을 적재한 후 프레임부를 터널을 따라 이동시킨 다음 해당 위치에서 적재부를 이용하여 프리캐스트 라이닝을 굴착면에 축조하고, 프레임부 내부를 통해 굴착 장비의 이동이 가능하도록 함으로써 굴착 작업과 라이닝 축조 작업이 동시에 진행되도록 하여 상대적으로 공사 기간을 단축시킬 수 있다.
The present invention relates to a lining construction device and a lining construction method using the same, which can be parallel to the tunnel excavation work, in particular installed in the excavated tunnel, the frame portion is installed in the space to enable the movement of construction equipment therein; A moving part which moves the frame part along the base parts installed at both sides of the bottom of the excavated tunnel, and is precast lining-mounted; And a construction unit for constructing the precast lining by moving the precast lining mounted on the moving unit to the excavation surface of the tunnel.
According to the present invention as described above, after loading the precast lining on the outside of the frame portion to move the frame portion along the tunnel and then construct the precast lining on the excavation surface using the loading portion at the corresponding position, the excavation equipment through the inside of the frame portion By enabling the movement of the excavation work and lining construction work proceeds at the same time can be relatively shortened construction period.

Description

터널 굴착 작업의 병행이 가능한 라이닝 축조 장치 및 이를 이용한 라이닝 축조 방법{CONSTRUCTING LINING SIMULTANEOUSLY WITH EXCAVATING TUNNEL, AND LINING CONSTRUCTING METHOD USING THEREOF}CONSTRUCTING LINING SIMULTANEOUSLY WITH EXCAVATING TUNNEL, AND LINING CONSTRUCTING METHOD USING THEREOF}

본 발명은 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치 및 이를 이용한 라이닝 축조 방법에 관한 것으로서, 상세하게는 프레임부의 외측에 프리캐스트 라이닝을 적재한 후 프레임부를 터널을 따라 이동시킨 다음 해당 위치에서 적재부를 이용하여 프리캐스트 라이닝을 굴착면에 축조하고, 프레임부 내부를 통해 굴착 장비의 이동이 가능하도록 하는 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치 및 이를 이용한 라이닝 축조 방법에 관한 것이다.The present invention relates to a lining construction device and a lining construction method using the same that can be parallel to the tunnel excavation work, and in detail, after loading the precast lining on the outside of the frame portion moving the frame portion along the tunnel and then the loading portion in the corresponding position The present invention relates to a lining construction device and a lining construction method using parallel tunnel excavation work for constructing a precast lining on an excavation surface and allowing movement of the excavation equipment through the inside of the frame part.

일반적으로 터널을 시공함에 있어서, 지반을 굴착한 후 굴착면에 보강용 숏크리트를 뿜어 붙여 1차 라이닝을 시공한다. 숏크리트에 의한 1차 라이닝이 완료된 후 굴착 지반면이 안정되면 상기 1차 라이닝의 외측면에 부직포, 방수 시트 등을 부착하고, 라이닝용 거푸집을 설치한 후, 상기 거푸집 내측에 콘크리트를 주입, 양생시켜 약 30 내지 40 ㎝ 두께의 콘크리트로 이루어진 2차 라이닝을 시공하게 된다.In general, in the construction of a tunnel, after the ground is excavated, reinforcing shotcrete is sprayed on the excavation surface to construct the primary lining. When the excavation ground is stabilized after the primary lining by shotcrete is completed, nonwoven fabric, waterproof sheet, etc. are attached to the outer surface of the primary lining, and after the lining formwork is installed, concrete is injected into the formwork and cured. Secondary lining made of concrete with a thickness of 30 to 40 cm.

그런데 이와 같이 현장 타설 콘크리트를 이용하여 2차 라이닝을 시공하는 경우, 콘크리트의 주입 타설하기 위하여 터널 공사 현장으로 콘크리트를 운반하여야 하는데, 터널 공사 현장은 대부분은 산악지역에 위치하고 있어, 설계 배합강도에 맞추어 콘크리트를 생산한 후 이를 레미콘 차량을 이용하여 터널 공사 현장으로 이송하는데 상당한 시간이 소요되므로, 그에 따라 콘크리트의 품질이 저하되고 콘크리트의 균일한 품질을 유지하기 어렵다는 단점이 있다.However, in the case of constructing secondary lining using the site-pouring concrete in this way, the concrete must be transported to the tunnel construction site in order to inject and place the concrete. The tunnel construction sites are mostly located in the mountainous area, After producing concrete, it takes considerable time to transfer it to the tunnel construction site using ready-mixed concrete vehicles. Therefore, the quality of concrete is deteriorated and it is difficult to maintain uniform quality of concrete.

또한 현장에서 2차 라이닝용 콘크리트를 타설하기 위해서는 거푸집을 설치하여야 하므로 거푸집의 운반, 조립 및 안전관리에 많은 시간과 노력, 그리고 비용이 소요될 뿐만 아니라, 콘크리트의 양생을 위한 시간을 확보하여야만 하므로 공기가 지연되어 전체 터널 시공에 소요되는 기간과 비용이 증가하게 되는 한계가 있다.In addition, in order to pour concrete for secondary lining in the field, since the formwork must be installed, it takes much time, effort, and cost to transport, assemble, and manage the formwork, as well as to secure time for curing concrete. There is a limit that the delay and the time required for the entire tunnel construction increases.

특히, 터널 굴착시에 터널 단면보다 더 크게 과다 굴착하게 되거나 또는 여굴이 발생하게 되는 경우에는 이를 메우기 위하여 많은 양의 콘크리트가 사용되어야 하므로, 2차 라이닝에 소요되는 콘크리트의 사용량이 증가하게 되고 그에 따른 재료의 낭비, 재료비의 증가 등의 문제가 발생하게 된다.In particular, when the tunnel is excavated more than the tunnel cross section or over excavation occurs, a large amount of concrete must be used to fill it, so the amount of concrete used for the secondary lining is increased and accordingly Problems such as waste of material and increase of material cost occur.

상기 현장 타설 콘크리트에 의하여 터널 라이닝을 시공하는 종래 기술이 가지는 여러 가지 문제점과 한계를 극복하기 위하여 개발된 것으로서, 공장에서 사전 제작된 프리캐스트 라이닝을 순차적으로 축조하는 방법이 개발되었다.It was developed to overcome various problems and limitations of the prior art of constructing the tunnel lining by the cast-in-place concrete, a method of sequentially building a precast lining pre-fabricated in the factory.

그러나, 이러한 프리캐스트 라이닝을 축조하는 방법은 세그먼트 형태로 제작된 프리캐스트 라이닝을 지게차와 같은 대형 장비를 굴착 공간에서 이동시키면서 축조하기 때문에 터널의 굴착에 필요한 장비(버럭 운반 차량 등)와의 간섭이 발생하여 굴착과 라이닝 축조를 동시에 진행하지 못하고, 이로 인해 공사 기간이 증대되는 문제점이 있다.However, the method of constructing such precast lining is constructed while the precast lining manufactured in the form of segment is constructed while moving large equipment such as a forklift truck in the excavation space, so that interference with equipment necessary for excavation of the tunnel (such as a bucket transport vehicle) occurs. Therefore, the excavation and lining construction can not be carried out at the same time, thereby increasing the construction period.

본 발명은 상기와 같은 문제점을 해결하기 위한 것으로, 프레임부의 외측에 프리캐스트 라이닝을 적재한 후 프레임부를 터널을 따라 이동시킨 다음 해당 위치에서 적재부를 이용하여 프리캐스트 라이닝을 굴착면에 축조하고, 프레임부 내부를 통해 굴착 장비의 이동이 가능하도록 함으로써 굴착 작업과 라이닝 축조 작업이 동시에 진행되도록 하여 상대적으로 공사 기간을 단축시키고, 공사 금액을 절감하도록 하는 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치 및 이를 이용한 라이닝 축조 방법을 제공하는데 그 목적이 있다.The present invention is to solve the above problems, and after loading the precast lining on the outside of the frame portion, the frame portion is moved along the tunnel and the precast lining on the excavation surface using the loading portion at the corresponding position, the frame Lining construction device capable of parallel drilling excavation work to reduce the construction period and reduce construction cost by allowing excavation work and lining construction work to proceed at the same time by allowing the movement of the excavation equipment through the inside of the part and using the same The purpose is to provide a lining construction method.

상기와 같은 목적을 달성하기 위한 본 발명의 특징은,Features of the present invention for achieving the above object,

굴착된 터널에 설치되고, 내부에 공사 장비의 이동이 가능하도록 공간부가 설치되는 프레임부과; 굴착된 터널 하단 양측에 설치된 기초부를 따라 상기 프레임부를 이동시키고, 프리캐스트 라이닝이 거치되는 이동부; 및 상기 이동부에 거치된 상기 프리캐스트 라이닝을 상기 터널의 굴착면으로 이동시켜 상기 프리캐스트 라이닝을 축조하는 축조부로 이루어지는 것을 특징으로 한다.A frame part installed in the excavated tunnel and having a space part installed therein to allow movement of construction equipment therein; A moving part which moves the frame part along the base parts installed at both sides of the bottom of the excavated tunnel, and is precast lining-mounted; And a construction unit for constructing the precast lining by moving the precast lining mounted on the moving unit to the excavation surface of the tunnel.

여기에서, 상기 프레임부는 상호 대응되도록 이격되고, 상기 터널의 길이 방향으로 복수개가 설치되는 수직 프레임과; 상기 공간부를 형성하도록 상기 수직 프레임과 이웃하는 수직 프레임을 상호 연결하는 수평 프레임; 및 상기 수직 프레임의 상하단과 이웃하는 수직 프레임의 상하단을 상호 연결시키는 종방향 프레임으로 이루어진다.Here, the frame portion is spaced to correspond to each other, the vertical frame is provided with a plurality in the longitudinal direction of the tunnel; A horizontal frame interconnecting the vertical frame and a neighboring vertical frame to form the space portion; And a longitudinal frame interconnecting the upper and lower ends of the vertical frame and the upper and lower ends of neighboring vertical frames.

여기에서, 상기 수직 프레임은 상기 터널의 바닥면에 고정되도록 저면에 각각 고정잭이 구비된다.Here, the vertical frame is provided with a fixed jack on the bottom so as to be fixed to the bottom surface of the tunnel.

여기에서 또, 상기 이동부는 각각의 상기 기초부에 설치되되, 상기 터널의 외측까지 연장되는 제 1레일과; 저면에 상기 제 1레일을 따라 이동되는 복수의 제 1휠이 구비되고, 상기 프레임부중 수직 프레임의 하단에서 직각으로 설치되는 제 1프레임과; 상기 제 1프레임의 상면에 설치되는 제 2레일과; 저면에 상기 제 2레일을 따라 이동되는 복수의 제 2휠이 구비되는 이동 플레이트; 및 상기 이동 플레이트의 일측면과 상기 프레임부의 수직 프레임 사이에 설치되어 상기 이동 플레이트를 좌우로 이동시키는 제 1길이 가변 수단으로 이루어진다.Here, the moving unit is provided in each of the base portion, the first rail extending to the outside of the tunnel; A first frame having a plurality of first wheels moved along the first rail on a bottom surface thereof, the first frame being installed at a right angle from a lower end of a vertical frame of the frame part; A second rail installed on an upper surface of the first frame; A moving plate having a plurality of second wheels moved along the second rail at a bottom thereof; And a first length variable means installed between one side of the movable plate and the vertical frame of the frame part to move the movable plate to the left and right.

여기에서 또, 상기 제 1프레임의 제 1휠은 동력 수단에 의해 회전된다.Here, again, the first wheel of the first frame is rotated by the power means.

여기에서 또, 상기 축조부는 상기 이동부의 이동 플레이트 상면에서 고정 결합되는 하단 붐과; 하단이 상기 하단 붐과 힌지 결합되며, 상단이 상기 프리캐스트 라이닝에 고정되어 상기 프리캐스트 라이닝을 이동시켜 상기 터널의 굴착면에 축조하는 상단 붐과; 상기 하단 붐과 상단 붐 사이에 힌지에 의해 결합되는 제 2길이 가변 수단; 및 상기 프레임부중 수평 프레임의 상부에서 하단이 힌지 결합되고, 상단이 상기 프리캐스트 라이닝과 결합되어 상기 프리캐스트 라이닝을 외측으로 이동시키는 제 3길이 가변 수단으로 이루어진다.Here, the shaft portion and the lower boom is fixedly coupled on the upper surface of the moving plate of the moving part; A lower boom hinged to the lower end, and an upper boom fixed to the precast lining to move the precast lining to build on the excavation surface of the tunnel; Second length variable means coupled by a hinge between the lower boom and the upper boom; And a third length varying means hingedly coupled to a lower end of an upper part of a horizontal frame of the frame part, and an upper end thereof coupled to the precast lining to move the precast lining outward.

여기에서 또, 상기 프리캐스트 라이닝은 상기 터널 상에서 상기 이동부에 거치후 이동되도록 상기 터널의 반단면 크기보다 작게 형성된다.Here, the precast lining is formed smaller than the size of the half-section of the tunnel so as to move after passing through the moving portion on the tunnel.

여기에서 또, 상기 프리캐스트 라이닝은 상기 굴착면 양측에 각각 축조한 후 이들 사이에 라이닝을 현장 타설하거나 또는 별도로 제작된 프리캐스트 상부 라이닝을 축조한다.Here, the precast lining is constructed on both sides of the excavation surface, and then casts the lining between them or builds a separately manufactured precast upper lining.

여기에서 또, 상기 프리캐스트 라이닝은 라이닝이 현장 타설되는 경우 이들 사이에 강관을 설치하여 상기 프리캐스트 라이닝을 고정 후 철근을 배근하고, 거푸집을 설치한 다음 콘크리트를 타설한다.
Here, when the precast lining is placed in the field, the steel pipes are installed between them to fix the precast lining and then reinforce the reinforcing bar, install the formwork, and then cast concrete.

본 발명의 다른 특징은,According to another aspect of the present invention,

상기의 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치를 이용한 라이닝 축조 방법에 있어서, 터널을 굴착하는 제 1공정과; 굴착이 기준 위치까지 진행되면 굴착된 터널 하단 양측에 기초부를 설치하는 제 2공정과; 상기 기초부의 상면에 이동부의 제 1레일을 설치하되, 상기 제 1레일을 상기 터널의 외측까지 연장 설치하는 제 3공정과; 터널의 외측인 상기 제 1레일 상에 프레임부를 설치하고, 상기 프레임부에 프리캐스트 라이닝을 거치한 다음, 축조 위치로 이동시키는 제 4공정과; 축조부를 통해 상기 프리캐스트 라이닝을 상기 터널의 굴착면에 축조하는 제 5공정과; 상기 프리캐스트 라이닝을 상기 굴착면 양측에 각각 축조한 후 이들 사이에 상부 라이닝을 현장 타설하거나 또는 별도로 제작된 프리캐스트 상부 라이닝을 축조하는 제 6공정과; 상기 프레임부를 터널 외부로 배출하는 제 7공정; 및 상기 제 1~7공정을 반복하여 굴착과 함께 상기 프리캐스트 라이닝을 축조하는 것을 특징으로 한다.A lining construction method using a lining construction apparatus capable of parallel tunnel excavation work, comprising: a first step of excavating a tunnel; A second step of installing foundations on both sides of the bottom of the excavated tunnel when the excavation proceeds to the reference position; A third step of installing a first rail of a moving part on an upper surface of the foundation part, and extending the first rail to an outer side of the tunnel; A fourth step of installing a frame portion on the first rail that is outside the tunnel, placing a precast lining on the frame portion, and then moving the frame portion to a construction position; A fifth step of constructing the precast lining on the excavation surface of the tunnel through a construction unit; A sixth step of constructing the precast linings on both sides of the excavation surface, and then placing the upper linings between them or constructing a separately manufactured precast upper lining; A seventh step of discharging the frame unit out of the tunnel; And repeating the first to seventh steps to build the precast lining with excavation.

상기와 같이 구성되는 본 발명인 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치 및 이를 이용한 라이닝 축조 방법에 따르면, 프레임부의 외측에 프리캐스트 라이닝을 적재한 후 프레임부를 터널을 따라 이동시킨 다음 해당 위치에서 적재부를 이용하여 프리캐스트 라이닝을 굴착면에 축조하고, 프레임부 내부를 통해 굴착 장비의 이동이 가능하도록 함으로써 굴착 작업과 라이닝 축조 작업이 동시에 진행되도록 하여 상대적으로 공사 기간을 단축시킬 수 있는 이점이 있다.According to the lining construction device and the lining construction method using the same according to the present invention the tunnel excavation work is configured as described above, after loading the precast lining on the outside of the frame portion to move the frame portion along the tunnel and then the loading portion at the corresponding position By using the precast lining on the excavation surface, and by allowing the movement of the excavation equipment through the inside of the frame portion, there is an advantage that can be relatively shortened construction period by performing the excavation work and lining construction work at the same time.

도 1은 본 발명에 따른 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치의 구성을 나타낸 사시도이다.
도 2는 본 발명에 따른 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치의 구성을 나타낸 측면도이다.
도 3은 본 발명에 따른 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치가 터널에 설치된 모습을 나타낸 정면도이다.
도 4a 및 도 4b는 본 발명에 따른 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치에 의해 프리캐스트 라이닝이 설치된 모습을 나타낸 정면도이다.
도 5a 내지 도 5g는 본 발명에 따른 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치를 이용한 라이닝 축조 방법을 설명하기 위한 공정 설명도이다.
1 is a perspective view showing the configuration of a lining construction device capable of parallel tunnel excavation operation according to the present invention.
Figure 2 is a side view showing the configuration of a lining construction device capable of parallel tunnel excavation operation according to the present invention.
3 is a front view showing a state in which a lining construction device capable of performing a tunnel excavation work according to the present invention is installed in a tunnel.
4A and 4B are front views showing a state in which a precast lining is installed by a lining construction device capable of parallel tunneling work according to the present invention.
5A to 5G are process explanatory diagrams for explaining a lining construction method using a lining construction apparatus capable of parallel tunnel excavation work according to the present invention.

이하, 본 발명에 따른 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치의 구성을 첨부된 도면을 참조하여 상세하게 설명하면 다음과 같다.Hereinafter, with reference to the accompanying drawings the configuration of the lining construction device capable of parallel tunnel excavation work according to the present invention will be described in detail.

하기에서 본 발명을 설명함에 있어, 관련된 공지 기능 또는 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명은 생략할 것이다. 그리고 후술되는 용어들은 본 발명에서의 기능을 고려하여 정의된 용어들로서 이는 사용자, 운용자의 의도 또는 관례 등에 따라 달라질 수 있다. 그러므로 그 정의는 본 명세서 전반에 걸친 내용을 토대로 내려져야 할 것이다.In the following description of the present invention, if it is determined that a detailed description of a related known function or configuration may unnecessarily obscure the subject matter of the present invention, the detailed description thereof will be omitted. The following terms are defined in consideration of the functions of the present invention, and may be changed according to the intentions or customs of the user, the operator, and the like. Therefore, the definition should be based on the contents throughout this specification.

도 1은 본 발명에 따른 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치의 구성을 나타낸 사시도이고, 도 2는 본 발명에 따른 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치의 구성을 나타낸 측면도이며, 도 3은 본 발명에 따른 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치가 터널에 설치된 모습을 나타낸 정면도이며, 도 4a 및 도 4b는 본 발명에 따른 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치에 의해 프리캐스트 라이닝이 설치된 모습을 나타낸 정면도이다.1 is a perspective view showing the configuration of a lining construction device capable of parallel tunnel excavation work according to the present invention, Figure 2 is a side view showing the configuration of a lining construction device capable of parallel tunnel excavation work according to the present invention, Figure 3 Is a front view showing a state in which a lining construction device capable of parallel tunnel excavation work according to the present invention is installed in the tunnel, Figures 4a and 4b is a precast lining by the lining construction device capable of parallel tunnel excavation work according to the present invention This is a front view showing the installed state.

도 1 내지 도 4b를 참조하면, 본 발명에 따른 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치(1)는, 프레임부(100)와, 이동부(200)와, 축조부(300)로 이루어진다.1 to 4B, the lining construction device 1 capable of performing the tunnel excavation work according to the present invention includes a frame portion 100, a moving portion 200, and a construction portion 300. As shown in FIG.

먼저, 프레임부(100)는 수직 프레임(110)과, 수평 프레임(120) 및 종방향 프레임(130)으로 구성된다.First, the frame part 100 includes a vertical frame 110, a horizontal frame 120, and a longitudinal frame 130.

수직 프레임(110)은 H, I 형강으로 이루어져 상호 대응되도록 이격되고, 터널(T)의 길이 방향으로 복수개가 설치된다. 여기에서, 수직 프레임(110)은 터널(T)의 바닥면(I)에 고정되도록 저면에 각각 고정잭(111)이 구비되는 것이 바람직하다. 여기에서 또한, 수직 프레임(110)은 선택에 따라 휠(미도시)이 설치될 수도 있고, 휠이 설치되는 경우 터널(T)의 바닥면(I)에도 레일(미도시)이 설치되는 것이 바람직하다.The vertical frame 110 is made of H, I-shaped steel spaced apart to correspond to each other, a plurality are installed in the longitudinal direction of the tunnel (T). Here, the vertical frame 110 is preferably provided with a fixed jack 111 on the bottom surface so as to be fixed to the bottom surface (I) of the tunnel (T). In this case, the vertical frame 110 may be provided with wheels (not shown) according to selection, and when the wheels are installed, rails (not shown) may also be installed on the bottom surface I of the tunnel T. Do.

수평 프레임(120)은 H, I 형강으로 이루어져 장비나 차량의 이동이 가능한 공간부(140)를 형성하도록 수직 프레임(110)과 이웃하는 수직 프레임(110)의 상단을 상호 연결한다.The horizontal frame 120 is made of H, I-shaped steel to interconnect the top of the vertical frame 110 and the adjacent vertical frame 110 to form a space portion 140 to move the equipment or vehicle.

종방향 프레임(130)은 H, I 형강으로 이루어져 수직 프레임(110)의 상하단과 이웃하는 수직 프레임(110)의 상하단을 상호 연결시킨다.
The longitudinal frame 130 is made of H and I-beams to interconnect the upper and lower ends of the vertical frame 110 and the upper and lower ends of the neighboring vertical frame 110.

그리고, 이동부(200)는 제 1레일(210)과, 제 1프레임(220)과, 제 2레일(230)과, 이동 플레이트(240)와, 제 1길이 가변 수단(250)으로 구성된다.The moving part 200 includes a first rail 210, a first frame 220, a second rail 230, a moving plate 240, and a first length varying means 250. .

제 1레일(210)은 굴착된 터널(T) 하단 양측에 설치된 기초부(B)를 따라 기초부(B)의 상면에 설치된다.The first rail 210 is installed on the upper surface of the foundation portion B along the foundation portion B installed on both sides of the lower end of the tunnel T excavated.

제 1프레임(220)은 H, I 형강으로 이루어져 저면에 제 1레일(210)을 따라 이동되는 복수의 제 1휠(221)이 구비되고, 프레임부(100)의 수직 프레임(110) 하단에서 직각으로 설치되며, 상면에 프리캐스트 라이닝(PCL)이 적재된다. 여기에서, 제 1프레임(220)의 상면 끝단에는 하기에서 설명할 이동 플레이트(240)가 이탈되는 것을 방지하도록 단턱(223)이 설치되는 것이 바람직하다.The first frame 220 is made of H, I-shaped steel is provided with a plurality of first wheels 221 to be moved along the first rail 210 on the bottom, at the bottom of the vertical frame 110 of the frame portion 100 It is installed at a right angle and a precast lining (PCL) is loaded on the top surface. Here, it is preferable that the step 223 is installed at the top end of the first frame 220 to prevent the moving plate 240 to be described later from being separated.

제 2레일(230)은 제 1프레임(220)의 상면에 설치된다.The second rail 230 is installed on the upper surface of the first frame 220.

이동 플레이트(240)는 저면에 제 2레일(230)을 따라 이동되는 복수의 제 2휠(241)이 구비되고, 프리캐스트 라이닝(PCL)을 제 2레일(230) 상에서 외측으로 밀어낸다.The moving plate 240 includes a plurality of second wheels 241 that are moved along the second rail 230 at a bottom thereof, and pushes the precast lining PCL outward on the second rail 230.

제 1길이 가변 수단(250)은 이동 플레이트(240)의 일측면과 프레임부(100)의 수직 프레임(110) 사이에 설치되어 이동 플레이트(240)를 좌우로 이동시킨다. 여기에서, 제 1길이 가변 수단(250)은 유압잭, 하이드로잭, 유압 실린더 등이 적용된다.
The first variable length means 250 is installed between one side of the moving plate 240 and the vertical frame 110 of the frame part 100 to move the moving plate 240 to the left and right. Here, the first variable length means 250 is applied to the hydraulic jack, hydrojack, hydraulic cylinder and the like.

또한, 축조부(300)는 하단 붐(310)과, 상단 붐(320)과, 제 2길이 가변 수단(330)과, 제 3길이 가변 수단(340)으로 이루어진다.In addition, the construction part 300 includes a lower boom 310, an upper boom 320, a second length variable means 330, and a third length variable means 340.

하단 붐(310)은 이동부(200)의 이동 플레이트(240) 상면에서 경사진 형태로 고정 결합된다.The lower boom 310 is fixedly coupled in an inclined form on the upper surface of the moving plate 240 of the moving part 200.

상단 붐(320)은 하단이 하단 붐(310)과 힌지(H) 결합되며, 상단이 프리캐스트 라이닝(PCL)에 고정되어 프리캐스트 라이닝(PCL)을 이동시켜 터널(T)의 굴착면에 축조한다.The upper boom 320 is coupled to the lower boom 310 and the hinge (H), the upper end is fixed to the precast lining (PCL) to move the precast lining (PCL) to build the excavation surface of the tunnel (T) do.

제 2길이 가변 수단(330)은 하단 붐(310)과 상단 붐(320) 사이에서 양단이 각각 힌지(H)에 의해 결합되어 상단 붐(320)을 하단 붐(310)에서 경사 방향으로 이동시킨다. 여기에서, 제 2길이 가변 수단(330)은 유압잭, 하이드로잭, 유압 실린더 등이 적용된다.The second variable length means 330 is coupled between the lower boom 310 and the upper boom 320 by hinges H to move the upper boom 320 in the inclined direction from the lower boom 310. . Here, the second variable length means 330 is applied to the hydraulic jack, hydrojack, hydraulic cylinder and the like.

제 3길이 가변 수단(340)은 프레임부(100)중 수평 프레임(120)의 상부에서 하단이 힌지(H) 결합되고, 상단이 프리캐스트 라이닝(PCL)과 결합되어 프리캐스트 라이닝(PCL)을 외측으로 이동시킨다. 여기에서, 제 3길이 가변 수단(340)은 유압잭, 하이드로잭, 유압 실린더 등이 적용된다.The third variable length means 340 is hinged (H) at the lower end of the upper portion of the horizontal frame 120 of the frame portion 100, the upper end is combined with the precast lining (PCL) to form a precast lining (PCL) Move it outward. Here, the third variable length means 340 is applied to the hydraulic jack, hydrojack, hydraulic cylinder and the like.

한편, 본 발명에 따른 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치(1)에 적용되는 프리캐스트 라이닝(PCL)은 터널(T) 상에서 이동부(200)에 거치후 이동되도록 터널(T)의 반단면 크기보다 작게 형성되고, 상단 붐(320)이 연결 가능하도록 내측면에 별도의 플레이트(미도시)가 고정 설치되는 것이 바람직하고, 도 4a에 도시된 바와 같이 굴착면 양측에 각각 축조한 후 이들 사이에 상부 라이닝(L)을 현장 타설하거나 또는 도 4b에 도시된 바와 같이 별도로 제작된 프리캐스트 상부 라이닝(L)을 축조한다. 이때, 라이닝이 현장 타설되는 경우 이들 사이에 강관(400)을 설치하여 프리캐스트 라이닝(PCL)을 고정 후 철근(미도시)을 배근하고, 거푸집(미도시)을 설치한 다음 콘크리트를 타설하여 양생한다.
On the other hand, the precast lining (PCL) applied to the lining construction device 1 that can be parallel to the tunnel excavation work according to the present invention is mounted on the moving part 200 on the tunnel (T) half of the tunnel (T) Formed smaller than the cross-sectional size, it is preferable that a separate plate (not shown) is fixed to the inner side so that the upper boom 320 is connectable, and after being built on both sides of the excavation surface as shown in Figure 4a Place the upper lining (L) in between, or build a separately manufactured precast upper lining (L) as shown in Figure 4b. At this time, when the lining is cast in place, the steel pipe 400 is installed between them to fix the precast lining (PCL) and then rebar (not shown), install the formwork (not shown), and then cast concrete to cure. do.

이하, 본 발명에 따른 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치를 이용한 라이닝 축조 방법을 첨부된 도면을 참조하여 상세하게 설명하면 다음과 같다.Hereinafter, a lining construction method using a lining construction apparatus capable of parallel drilling excavation operation according to the present invention will be described in detail with reference to the accompanying drawings.

도 5a 내지 도 5g는 본 발명에 따른 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치를 이용한 라이닝 축조 방법을 설명하기 위한 공정 설명도이다.5A to 5G are process explanatory diagrams for explaining a lining construction method using a lining construction apparatus capable of parallel tunnel excavation work according to the present invention.

먼저, 도 5a에 도시된 바와 같이 굴착 장비를 이용하여 터널(T)을 굴착한다(S100).First, as shown in FIG. 5A, the tunnel T is excavated using the excavation equipment (S100).

그리고, 도 5b에 도시된 바와 같이 굴착이 기준 위치(프리캐스트 라이닝의 축조가 가능한 위치)까지 진행되면 굴착된 터널(T) 하단 양측에 기초부(B)를 설치한다(S110).Then, as shown in Figure 5b when the excavation proceeds to the reference position (precast lining can be built position) install the base portion (B) on both sides of the bottom of the excavated tunnel (T) (S110).

그런 다음, 도 5c에 도시된 바와 같이 기초부(B)의 상면에 이동부(200)의 제 1레일(210)을 설치한다(S120).Then, as shown in FIG. 5c, the first rail 210 of the moving part 200 is installed on the upper surface of the base part B (S120).

제 1레일(210)의 설치가 완료되면, 도 5d에 도시된 바와 같이 터널(T)의 외측 제 1레일(210) 상에 프레임부(100)를 조립 설치하고, 프레임부(100)에 프리캐스트 라이닝(PCL)을 거치한 다음, 축조 위치로 이동시킨다(S130). 이때, 프리캐스트 라이닝(PCL)과 축조부(300)의 상단 붐(320)을 상호 연결시킨다. 또한, 제 1프레임(220)의 제 1휠(221)은 동력 수단(미도시)에 의해 회전되는 것이 바람직하고, 별도의 견인 장비로 견인하여 제 1휠(221)을 제 1레일(210) 상에서 이동시킬 수도 있다. 한편, 프레임부(100)의 설치가 완료되면, 공간부(140)를 통해 장비나 차량의 이동이 가능하다.When the installation of the first rail 210 is completed, as shown in FIG. 5D, the frame unit 100 is assembled and installed on the outer first rail 210 of the tunnel T, and the frame unit 100 is free. After passing through the cast lining (PCL), and moves to the building position (S130). At this time, the upper boom 320 of the precast lining (PCL) and the construction unit 300 are interconnected. In addition, the first wheel 221 of the first frame 220 is preferably rotated by a power means (not shown), tow the first wheel 221 by a separate towing equipment to the first rail 210 You can also move it on. On the other hand, when the installation of the frame unit 100 is completed, it is possible to move the equipment or vehicle through the space unit 140.

이어서, 도 5e에 도시된 바와 같이 제 2길이 가변 수단(330)을 동작시켜 상단 붐(320)을 이용하여 프리캐스트 라이닝(PCL)을 제 2프레임(230)에서 승강시키고, 제 1길이 가변 수단(250)을 동작시켜 이동 플레이트(240)로 프리캐스트 라이닝(PCL)을 터널(T)의 굴착면으로 이동시킨 후 상단 붐(320)을 하강시켜 프리캐스트 라이닝(PCL)을 터널(T)의 굴착면에 축조한다(S140).Subsequently, as shown in FIG. 5E, the second length varying means 330 is operated to raise and lower the precast lining PCL in the second frame 230 using the upper boom 320, and the first length varying means. By operating the 250 to move the precast lining (PCL) to the excavation surface of the tunnel (T) with a moving plate 240, the upper boom 320 is lowered to move the precast lining (PCL) of the tunnel (T) Construct on the excavation surface (S140).

그런 다음, 도 5f에 도시된 바와 같이 프리캐스트 라이닝(PCL)을 굴착면 양측에 각각 축조한 후 이들 사이에 상부 라이닝(L)을 현장 타설하거나 또는 별도로 제작된 프리캐스트 상부 라이닝(L)을 축조한다(S150).Then, as shown in FIG. 5F, precast linings PCL are respectively constructed on both sides of the excavation surface, and then the upper linings L are placed between them, or precast upper linings L are separately manufactured. (S150).

상부 라이닝(L)의 축조가 완료되면, 도 5g에 도시된 바와 같이 프레임부(100)를 터널(T) 외부로 배출한다(S160).When the construction of the upper lining (L) is completed, as shown in Figure 5g to discharge the frame portion 100 to the outside of the tunnel (T) (S160).

그리고, 제 1~7공정을 반복하여 굴착과 함께 프리캐스트 라이닝(PCL)을 축조한다.Then, the first to seventh steps are repeated to build a precast lining (PCL) together with the excavation.

본 발명은 다양하게 변형될 수 있고 여러 가지 형태를 취할 수 있으며 상기 발명의 상세한 설명에서는 그에 따른 특별한 실시 예에 대해서만 기술하였다. 하지만 본 발명은 상세한 설명에서 언급되는 특별한 형태로 한정되는 것이 아닌 것으로 이해되어야 하며, 오히려 첨부된 청구범위에 의해 정의되는 본 발명의 정신과 범위 내에 있는 모든 변형물과 균등물 및 대체물을 포함하는 것으로 이해되어야 한다.As those skilled in the art would realize, the described embodiments may be modified in various ways, all without departing from the spirit or scope of the present invention. It is to be understood, however, that the present invention is not limited to the specific forms referred to in the description, but rather includes all modifications, equivalents, and substitutions within the spirit and scope of the invention as defined by the appended claims. Should be.

100 : 프레임부 200 : 이동부
300 : 축조부
100: frame portion 200: moving portion
300: building part

Claims (10)

굴착된 터널에 설치되고, 내부에 공사 장비의 이동이 가능하도록 공간부가 설치되고, 상호 대응되도록 이격되며, 상기 터널의 길이 방향으로 복수개가 설치되는 수직 프레임과, 상기 공간부를 형성하도록 상기 수직 프레임과 이웃하는 수직 프레임을 상호 연결하는 수평 프레임과, 상기 수직 프레임의 상하단과 이웃하는 수직 프레임의 상하단을 상호 연결시키는 종방향 프레임으로 구성되는 프레임부과;
굴착된 터널 하단 양측에 설치된 기초부에 각각 설치되되, 상기 터널의 외측까지 연장되는 제 1레일과, 저면에 상기 제 1레일을 따라 이동되는 복수의 제 1휠이 구비되고, 상기 프레임부중 수직 프레임의 하단에서 직각으로 설치되어 상면에 프리캐스트 라이닝이 적재되는 제 1프레임과, 상기 제 1프레임의 상면에 설치되는 제 2레일과, 저면에 상기 제 2레일을 따라 이동되는 복수의 제 2휠이 구비되는 이동 플레이트와, 상기 이동 플레이트의 상면에 설치되되, 상기 프레임부중 수직 프레임과 대응되는 위치에 설치되어 상기 이동 플레이트를 좌우로 이동시키는 제 1길이 가변 수단으로 구성되는 이동부; 및
상기 이동부에 거치된 상기 프리캐스트 라이닝을 상기 터널의 굴착면으로 이동시켜 상기 프리캐스트 라이닝을 축조하는 축조부로 이루어지는 것을 특징으로 하는 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치.
Installed in the excavated tunnel, the space is installed inside the space to allow the movement of the construction equipment, spaced to correspond to each other, a plurality of vertical frames are installed in the longitudinal direction of the tunnel, and the vertical frame to form the space and A frame unit including a horizontal frame interconnecting adjacent vertical frames, and a vertical frame interconnecting upper and lower ends of the vertical frame and upper and lower ends of the neighboring vertical frames;
It is installed in each of the base portion is installed on both sides of the bottom of the excavated tunnel, the first rail extending to the outside of the tunnel, and a plurality of first wheels are moved along the first rail on the bottom, the vertical frame of the frame portion The first frame is installed at a right angle at the lower end of the precast lining is mounted on the upper surface, the second rail is installed on the upper surface of the first frame, and a plurality of second wheels moved along the second rail on the bottom surface A moving part provided on a moving plate provided on the upper surface of the moving plate, the moving part being provided at a position corresponding to a vertical frame among the frame parts and configured to have a first length variable means for moving the moving plate left and right; And
Lining construction device capable of parallel tunnel excavation work characterized in that it comprises a construction unit for constructing the precast lining by moving the precast lining mounted on the moving part to the excavation surface of the tunnel.
삭제delete 제 1 항에 있어서,
상기 수직 프레임은,
상기 터널의 바닥면에 고정되도록 저면에 각각 고정잭이 구비되는 것을 특징으로 하는 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치.
The method of claim 1,
The vertical frame,
Lining construction device capable of parallel operation of the tunnel excavation work, characterized in that the fixing jack is provided on the bottom surface to be fixed to the bottom surface of the tunnel.
삭제delete 제 1 항에 있어서,
상기 제 1프레임의 제 1휠은,
동력 수단에 의해 회전되는 것을 특징으로 하는 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치.
The method of claim 1,
The first wheel of the first frame,
Lining construction device capable of parallel operation of the tunnel excavation work, characterized in that rotated by the power means.
제 1 항에 있어서,
상기 축조부는,
상기 이동부의 이동 플레이트 상면에서 고정 결합되는 하단 붐과;
하단이 상기 하단 붐과 힌지 결합되며, 상단이 상기 프리캐스트 라이닝에 고정되어 상기 프리캐스트 라이닝을 이동시켜 상기 터널의 굴착면에 축조하는 상단 붐과;
상기 하단 붐과 상단 붐 사이에 힌지에 의해 결합되는 제 2길이 가변 수단; 및
상기 프레임부중 수평 프레임의 상부에서 하단이 힌지 결합되고, 상단이 상기 프리캐스트 라이닝과 결합되어 상기 프리캐스트 라이닝을 외측으로 이동시키는 제 3길이 가변 수단으로 이루어지는 것을 특징으로 하는 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치.
The method of claim 1,
The building unit,
A lower boom fixedly coupled to an upper surface of the movable plate of the movable part;
A lower boom hinged to the lower end, and an upper boom fixed to the precast lining to move the precast lining to build on the excavation surface of the tunnel;
Second length variable means coupled by a hinge between the lower boom and the upper boom; And
The lower end is hinged at the upper part of the horizontal frame of the frame portion, and the upper end is coupled to the precast lining, and the tunnel length can be parallel to the excavation work, characterized in that made of a variable length means for moving the precast lining outward. Lining construction device.
제 1 항에 있어서,
상기 프리캐스트 라이닝은,
상기 터널 상에서 상기 이동부에 거치후 이동되도록 상기 터널의 반단면 크기보다 작게 형성되는 것을 특징으로 하는 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치.
The method of claim 1,
The precast lining,
Lining construction device that can be parallel to the tunnel excavation work, characterized in that formed smaller than the size of the half-section of the tunnel so as to move after mounting on the moving part on the tunnel.
제 7 항에 있어서,
상기 프리캐스트 라이닝은,
상기 굴착면 양측에 각각 축조한 후 이들 사이에 라이닝을 현장 타설하거나 또는 별도로 제작된 프리캐스트 상부 라이닝을 축조하는 것을 특징으로 하는 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치.
The method of claim 7, wherein
The precast lining,
Lining construction apparatus capable of parallel drilling excavation work, characterized in that after the construction on each side of the excavation surface, the lining is placed between them or the precast upper lining is manufactured separately.
제 8 항에 있어서,
상기 프리캐스트 라이닝은,
현장 타설되는 경우 이들 사이에 강관을 설치하여 상기 프리캐스트 라이닝을 고정 후 철근을 배근하고, 거푸집을 설치한 다음 콘크리트를 타설하는 것을 특징으로 하는 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치.
The method of claim 8,
The precast lining,
If the site is cast steel lining between them to fix the precast lining and reinforce the reinforcement, install the formwork and lining construction apparatus that can be parallel to the tunnel excavation work, characterized in that.
제 1 항의 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치를 이용한 라이닝 축조 방법에 있어서,
터널을 굴착하는 제 1공정과;
굴착이 기준 위치까지 진행되면 굴착된 터널 하단 양측에 기초부를 설치하는 제 2공정과;
상기 기초부의 상면에 이동부의 제 1레일을 설치하되, 상기 제 1레일을 상기 터널의 외측까지 연장 설치하는 제 3공정과;
터널의 외측인 상기 제 1레일 상에 프레임부를 설치하고, 상기 프레임부에 프리캐스트 라이닝을 거치한 다음, 축조 위치로 이동시키는 제 4공정과;
축조부를 통해 상기 프리캐스트 라이닝을 상기 터널의 굴착면에 축조하는 제 5공정과;
상기 프리캐스트 라이닝을 상기 굴착면 양측에 각각 축조한 후 이들 사이에 상부 라이닝을 현장 타설하거나 또는 별도로 제작된 프리캐스트 상부 라이닝을 축조하는 제 6공정과;
상기 프레임부를 터널 외부로 배출하는 제 7공정; 및
상기 제 1~7공정을 반복하여 굴착과 함께 상기 프리캐스트 라이닝을 축조하는 것을 특징으로 하는 터널 굴착 작업의 병행이 가능한 라이닝 축조 장치를 이용한 라이닝 축조 방법.
In the lining construction method using a lining construction device capable of parallel to the tunnel excavation work of claim 1,
A first step of digging a tunnel;
A second step of installing foundations on both sides of the bottom of the excavated tunnel when the excavation proceeds to the reference position;
A third step of installing a first rail of a moving part on an upper surface of the foundation part, and extending the first rail to an outer side of the tunnel;
A fourth step of installing a frame portion on the first rail that is outside the tunnel, placing a precast lining on the frame portion, and then moving the frame portion to a construction position;
A fifth step of constructing the precast lining on the excavation surface of the tunnel through a construction unit;
A sixth step of constructing the precast linings on both sides of the excavation surface, and then placing the upper linings between them or constructing a separately manufactured precast upper lining;
A seventh step of discharging the frame unit out of the tunnel; And
A lining construction method using a lining construction device capable of parallel tunnel excavation work, characterized in that the construction of the precast lining with excavation by repeating the first to seventh step.
KR1020110056877A 2011-06-13 2011-06-13 Constructing lining simultaneously with excavating tunnel, and lining constructing method using thereof KR101072401B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110056877A KR101072401B1 (en) 2011-06-13 2011-06-13 Constructing lining simultaneously with excavating tunnel, and lining constructing method using thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110056877A KR101072401B1 (en) 2011-06-13 2011-06-13 Constructing lining simultaneously with excavating tunnel, and lining constructing method using thereof

Publications (1)

Publication Number Publication Date
KR101072401B1 true KR101072401B1 (en) 2011-10-11

Family

ID=45032655

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110056877A KR101072401B1 (en) 2011-06-13 2011-06-13 Constructing lining simultaneously with excavating tunnel, and lining constructing method using thereof

Country Status (1)

Country Link
KR (1) KR101072401B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101227190B1 (en) 2011-10-21 2013-01-28 선산철강공업(주) Steel form for variable tunnel

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100350730B1 (en) 2000-01-28 2002-08-30 (주) 경화엔지니어링 Sprinkler for Curing of Tunnel Lining Concrete
KR100936997B1 (en) * 2008-01-11 2010-01-15 코오롱건설주식회사 Side mold for tunnel lining form
KR101014779B1 (en) 2009-10-14 2011-02-14 (주)이화기공 Construction method by concrete lining in parallel with excavation, working platform for reinforcement and waterproofing work and lining form for pouring lining concrete

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100350730B1 (en) 2000-01-28 2002-08-30 (주) 경화엔지니어링 Sprinkler for Curing of Tunnel Lining Concrete
KR100936997B1 (en) * 2008-01-11 2010-01-15 코오롱건설주식회사 Side mold for tunnel lining form
KR101014779B1 (en) 2009-10-14 2011-02-14 (주)이화기공 Construction method by concrete lining in parallel with excavation, working platform for reinforcement and waterproofing work and lining form for pouring lining concrete

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101227190B1 (en) 2011-10-21 2013-01-28 선산철강공업(주) Steel form for variable tunnel

Similar Documents

Publication Publication Date Title
JP4853429B2 (en) Support structure of lining board, method of supporting lining board
KR101344063B1 (en) The construction method of steel-concrete underpass
CN110656959B (en) Large-section loess tunnel primary support limit-invasion arch-changing construction method
KR101437842B1 (en) Low depth tunnel construction method using variable mould system
KR20160131410A (en) Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method
JP6186267B2 (en) How to build an underground tunnel
KR101696845B1 (en) The Construction Method of Non-excavation tunnel what Steel pipe position can be substitute with PC-upper-slab by Extruding
KR20090114863A (en) Parallelly connected iron tube and construction method for underground structure using the same
JP2020084474A (en) Widening construction method of existing tunnel
CN106939605B (en) Slope protection building block carrying equipment and method
KR101072401B1 (en) Constructing lining simultaneously with excavating tunnel, and lining constructing method using thereof
CN111074893B (en) Construction system and construction method for concrete cushion layer of river dike and dyke
JP7178243B2 (en) Tunnel lining construction method
JP6529378B2 (en) Invert construction method, tunnel construction method and Teruha crane for tunnel
CN110593902B (en) Construction method for filling inverted arch and integrally pouring
KR100815174B1 (en) Pipe Roof Tunnel and Constructing Method thereof
KR101312668B1 (en) Non-excavation type constructed tunnels and conduits using arc-shaped divided segments or rugged panels and its constructing method thereof
KR101427812B1 (en) Open cut method for constructing an underground structure
CN109098720A (en) Precast combined underground structure product and construction method
KR100928566B1 (en) Roof assembly and constructing method thereof
JP7284720B2 (en) steel guide wall
CN110671132B (en) Deep loess tunnel deformation control construction structure and method based on sleeve arch
JP7182176B2 (en) Tunnel lining method
JP6475554B2 (en) Construction method of shaft and construction method of underground storage tank
JP7248236B2 (en) Tunnel repair method and equipment for existing tunnels

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20141016

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20150915

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20161018

Year of fee payment: 6