KR101042945B1 - Tendon Anchoring Apparatus and Connecting Structure for Precast Concrete Box Culvert - Google Patents

Tendon Anchoring Apparatus and Connecting Structure for Precast Concrete Box Culvert Download PDF

Info

Publication number
KR101042945B1
KR101042945B1 KR1020090041879A KR20090041879A KR101042945B1 KR 101042945 B1 KR101042945 B1 KR 101042945B1 KR 1020090041879 A KR1020090041879 A KR 1020090041879A KR 20090041879 A KR20090041879 A KR 20090041879A KR 101042945 B1 KR101042945 B1 KR 101042945B1
Authority
KR
South Korea
Prior art keywords
wedge
steel wire
hole
culvert
end point
Prior art date
Application number
KR1020090041879A
Other languages
Korean (ko)
Other versions
KR20100122799A (en
Inventor
이상철
Original Assignee
이상철
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이상철 filed Critical 이상철
Priority to KR1020090041879A priority Critical patent/KR101042945B1/en
Publication of KR20100122799A publication Critical patent/KR20100122799A/en
Application granted granted Critical
Publication of KR101042945B1 publication Critical patent/KR101042945B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F5/00Draining the sub-base, i.e. subgrade or ground-work, e.g. embankment of roads or of the ballastway of railways or draining-off road surface or ballastway drainage by trenches, culverts, or conduits or other specially adapted means
    • E01F5/005Culverts ; Head-structures for culverts, or for drainage-conduit outlets in slopes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions
    • E04C5/12Anchoring devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Sewage (AREA)

Abstract

하나의 웨지콘몸체에 강선의 종점정착을 위한 종점웨지와 시점정착을 위한 시점웨지가 병렬로 배치된 2단 일체형 양방향 강선정착장치를 이용하여 PC 암거군과 또 다른 PC 암거군을 연결함에 있어 양쪽으로 긴장하는 강선의 긴장방향이 웨지콘몸체의 중심선에 최대한 근접하도록 하여 서로 반대방향으로 작용하는 강선의 긴장력에 의해 웨지콘몸체에 편하중 및 회전하중이 작용하는 것을 최소화함으로써, 웨지콘몸체가 긴장방향으로 돌출되는 현상을 방지할 수 있으며, 하나의 PC 암거군과 또 다른 PC 암거군 간에 작용하는 강선의 긴장방향을 최대한 동일 선상으로 유지하여 밀착력을 강화시킬 수 있는 2단 일체형 양방향 강선정착장치 및 이를 이용한 프리캐스트 콘크리트 박스 암거 연결구조를 개시한다.When connecting the PC culvert group and another PC culvert group by using the two-stage integrated bi-directional wire fixing apparatus in which the end wedge for the end point of the steel wire and the end wedge for the point fixing are arranged in parallel in one wedge cone body As the tension direction of the steel wire which is tensioned as close as possible to the center line of the wedge cone body is minimized, the wedge cone body is tensioned by minimizing the acting load and rotational load on the wedge cone body by the tension force of the steel wires which act in opposite directions. Two-stage integrated bi-directional wire fixing device that can prevent the phenomenon of protruding in the direction, and can strengthen the adhesion by maintaining the tension direction of the steel wire acting between one PC culvert group and another PC culvert group in the same line as possible; Disclosed is a precast concrete box culvert connection structure using the same.

본 발명은, 점차 단면이 확대되는 종점웨지홀을 제1 중심축선에 형성한 종점정착구멍과, 상기 종점웨지홀에 대하여 반대방향으로 점차 단면이 확대되는 시점웨지홀을 제2 중심축선에 형성한 시점정착구멍이 병렬로 배치된 웨지콘몸체와, 상기 종점웨지홀에 설치된 종점웨지와, 상기 시점웨지홀에 설치된 시점웨지를 구비하되, 상기 시점정착구멍의 제2 중심축선은 웨지콘몸체의 중심선과 평행하게 형성되고, 상기 종점정착구멍의 제1 중심축선은 한쪽이 웨지콘몸체의 중심선과의 간격이 점차 근접하도록 시점정착구멍의 2 중심축선에 대하여 경사지게 형성한 것이다.The present invention provides an end point fixing hole in which an end point wedge hole whose cross section is gradually enlarged is formed in the first center axis line, and a start point wedge hole in which the cross section is gradually enlarged in a direction opposite to the end point wedge hole is formed in the second center axis line. And a wedge-con body in which the viewpoint fixing holes are arranged in parallel, an endpoint wedge provided in the endpoint wedge, and a viewpoint wedge provided in the viewpoint wedge hole, wherein the second central axis of the viewpoint fixing hole is a centerline of the wedge cone body. The first center axis of the end point fixing hole is formed to be inclined with respect to the two center axis lines of the start point fixing hole so that one side is gradually close to the center line of the wedge cone body.

Description

2단 일체형 양방향 강선정착장치 및 이를 이용한 프리캐스트 콘크리트 박스 암거 연결구조{Tendon Anchoring Apparatus and Connecting Structure for Precast Concrete Box Culvert}Two-stage one-way bidirectional steel wire fixing device and precast concrete box culvert connection structure using it {Tendon Anchoring Apparatus and Connecting Structure for Precast Concrete Box Culvert}

본 발명은 지하에 매설되어 상하수도, 전력구, 통신구, 공동구 등의 시설물로 사용되는 조립식 PC 암거를 강선으로 강하게 밀착시켜 조립하기 위한 2단 일체형 양방향 강선정착장치 및 이를 이용한 프리캐스트 콘크리트 박스 암거(이하, PC 암거라 칭한다.) 연결구조에 관한 것이다.The present invention is a two-stage integrated bi-directional steel wire fixing device and a precast concrete box culvert using the same to assemble a prefabricated PC culvert used in facilities such as water and sewage, electric power, communication, co-communication strongly buried in steel wire Hereinafter, referred to as PC culvert.) Relates to a connection structure.

일반적으로 조립식 PC 암거는 상호 간의 연결강도(밀착력)가 매우 약하기 때문에, 지반이 연약하여 부분 침하 및 지진 등으로 인해 상하,좌우 및 회전 하중이 가해지는 경우, 조립된 PC 암거 사이의 연결부위가 벌어져 수밀성을 저하시키는 등, 기능을 수행함에 있어 악영향을 주는 문제가 있으며, 이를 위해 강선과 강선정착장치를 이용하여 PC 암거의 연결부위를 강하게 밀착시키는 연결구조가 많이 알려져 있다.In general, the assembled PC culverts have very weak connection strengths (adhesive forces), so that when the ground is soft and subjected to up, down, left and right rotational loads due to partial settlement and earthquakes, the connection areas between the assembled PC culverts are opened. There is a problem that adversely affects the performance of the function, such as lowering the watertightness, and for this purpose, a connection structure for strongly contacting the connection portion of the PC culvert using a steel wire and a wire fixing device is known.

예를 들면, 대한민국 등록특허 10-0692913호에는, 상기한 강선과 강선정착장치를 이용한 PC 암거 연결구조가 개시되어 있다.For example, Korean Patent No. 10-0692913 discloses a PC culvert connection structure using the steel wire and the steel wire fixing device.

도 1a 내지 도 1e는 강선과 강선정착장치를 이용하여 다수개의 PC 암거를 연결하는 과정을 설명하기 위한 것으로, 먼저, 도 1a 및 도 1b에 도시된 바와 같이, 연결하고자 하는 제1 내지 제3 PC 암거(201,202,203)를 위치시킨 다음, 강선통과공(112)을 통하여 강선(11)을 삽입한다.1A to 1E illustrate a process of connecting a plurality of PC culverts using a steel wire and a steel wire fixing device. First, as shown in FIGS. 1A and 1B, first to third PCs to be connected Positioning the culverts (201, 202, 203), the steel wire 11 is inserted through the steel wire through hole (112).

강선(11)의 시점 끝단(도면의 좌측 끝단)은 제1 PC 암거(201)의 시점면에 정착되는데, 제1 PC 암거(201)의 단면에 형성된 오목부(110)에 시점강선정착장치(600)의 웨지콘부재(602)를 위치시키고, 강선(11)의 시점 끝단부에 웨지(603)를 물린 후, 강선(11)을 당김(도 1b의 화살표 b방향)으로써 웨지(603)가 강선(11)을 물은 채로 웨지콘부재(602)의 웨지홀로 삽입되어 강선(11)이 정착되도록 한다.The viewpoint end (left end of the figure) of the steel wire 11 is fixed to the viewpoint surface of the 1st PC culvert 201, and the viewpoint steel wire fixing apparatus was formed in the recessed part 110 formed in the cross section of the 1st PC culvert 201. The wedge cone member 602 of 600 is positioned, the wedge 603 is bitten at the end point of the steel wire 11, and the wedge 603 is pulled by pulling the steel wire 11 (in the direction of arrow b in FIG. 1B). The steel wire 11 is inserted into the wedge hole of the wedge cone member 602 while biting the steel wire 11 to fix the steel wire 11.

강선(11)의 종점 끝단(도면의 우측 끝단)은 제3 PC 암거(203)의 종점면으로 노출된다. 제3 PC 암거(203)의 종점면에 형성된 오목부(110)에는 양방향 강선정착장치(100)가 설치되는데, 구체적으로 양방향 강선정착장치(100)의 종점정착용 웨지콘부재(102) 및 웨지(103)가 사용되고, 제3 PC 암거(203)의 종점면으로 노출되는 강선(11)은 상기 웨지(103)에 물린다.The end end (right end of the figure) of the steel wire 11 is exposed to the end face of the third PC culvert 203. The concave portion 110 formed on the end surface of the third PC culvert 203 is provided with a two-way steel wire fixing device 100, specifically, the wedge-con member 102 and the wedge for the end point fixing of the two-way steel wire fixing device 100 103 is used, and the steel wire 11 exposed to the end face of the third PC culvert 203 is bitten by the wedge 103.

이어서 웨지(103)에 물린 강선(11)을 유압식 긴장장치(400)로 긴장함으로써 웨지(103)가 웨지콘부재(102)의 웨지홀(104)에 삽입되어 강선(11)이 정착되도록 한다. 즉, 유압식 긴장장치(400)가 강선(11)을 도 1b의 화살표 b방향으로 당겼다 놓게 되면, 강선(11)의 긴장에 의한 반발력으로 웨지(103)가 강선(11)을 물은 채로 웨지콘부재(102)의 웨지홀로 밀착되고, 강선(11)이 수축하면서 웨지(103)를 화살표 a방향으로 더욱 당기게 되므로, 강선(11)은 강하게 정착되어 제1 내지 제3 PC 암 거(201,202,203)는 강선(11)의 수축력에 의해 강하게 밀착된 상태로 연결된다.Subsequently, the steel wire 11 bitten by the wedge 103 is tensioned by the hydraulic tension device 400 so that the wedge 103 is inserted into the wedge hole 104 of the wedge cone member 102 so that the steel wire 11 is fixed. That is, when the hydraulic tension device 400 pulls and releases the steel wire 11 in the direction of the arrow b of FIG. 1B, the wedge 103 receives the steel wire 11 with the wedge 103 with the repulsive force caused by the tension of the steel wire 11. Since the steel wire 11 is brought into close contact with the wedge hole of the member 102 and the steel wire 11 contracts, the wedge 103 is further pulled in the direction of the arrow a, so the steel wire 11 is firmly fixed so that the first to third PC culverts 201, 202, 203 It is connected in a state of being strongly in contact by the contracting force of the steel wire (11).

이어서 도 1c에 도시된 바와 같이 강선(11)의 종점 끝단을 절단하고, 강선(11)이 정착되어 있는 웨지콘부재(102)에 커플링부재(101)의 일측을 나사결합하여 일체화시키고, 도 1d에 도시된 바와 같이 커플링부재(101)의 타측에 마찬가지로 시점정착용 웨지콘부재(102')를 나사결합하여 일체화시킨다.Subsequently, as shown in FIG. 1C, the end of the end point of the steel wire 11 is cut, and one side of the coupling member 101 is integrated with the wedge-con member 102 on which the steel wire 11 is fixed. As shown in 1d, the wedge-cone member 102 'for fixing the viewpoint is similarly screwed to the other side of the coupling member 101 to be integrated.

그 후 연이어 연결할 제4 내지 제6 PC 암거(204,205,206)를 제3 PC 암거(203)에 후속하여 위치시키고, 상기 제4 내지 제6 PC 암거(204,205,206)의 강선통과공(112')을 통하여 강선(11')을 삽입한다.Subsequently, the fourth to sixth PC culverts 204, 205, and 206 to be connected successively are positioned after the third PC culvert 203, and the steel wires pass through the steel wire through holes 112 'of the fourth to sixth PC culverts 204, 205, and 206. Insert (11 ').

강선통과공(112')으로 삽입하여 제4 PC암거(204)의 시점면으로 돌출되는 강선(11')의 시점 끝단은, 제3 PC 암거(203)에 이미 설치되어 있는 양방향 강선정착장치(100)의 시점정착용 웨지콘부재(102')의 웨지홀(104')로 삽입하여, 웨지(103')에 물린다.The end of the steel wire 11 'inserted into the steel wire passing hole 112' and projecting to the viewpoint surface of the fourth PC culvert 204 is a bidirectional steel wire fixing device that is already installed in the third PC culvert 203 ( It inserts into the wedge hole 104 'of the wedge-cone member 102' of the viewpoint fixing of 100, and is bitten by the wedge 103 '.

새로이 삽입된 강선(11')의 종점 끝단, 즉 제6 PC 암거(206)의 종점면 외부로 돌출되는 강선(11')을 앞서 설명한 바와 같이, 유압식 긴장장치(400)로 긴장하게 되면, 도 1e에 도시된 바와 같이, 강선(11')이 화살표 b방향으로 당겨지면서 제4 PC암거(204)의 시점면에 설치되어 있는 시점정착용 웨지콘부재(102')에 강선(11')이 정착된다. 이와 같이 양방향 강선 정착장치(100)를 이용함으로써 PC 암거를 연속적으로 연결할 수 있다. When the end of the newly inserted steel wire 11 ', that is, the steel wire 11' protruding out of the end surface of the sixth PC culvert 206, as described above, the tension with the hydraulic tension device 400, FIG. As shown in 1e, the steel wire 11 'is pulled in the direction of the arrow b while the steel wire 11' is attached to the wedge-cone member 102 'installed at the viewpoint of the fourth PC culvert 204. Settles down. As such, by using the bidirectional steel wire fixing device 100, the PC culvert can be continuously connected.

그러나 상기한 바와 같이 양방향 강선정착장치(100)를 이용한 PC 암거 연결구조는, 시점정착용의 웨지콘부재(102) 및 웨지(103)와 종점정착용의 웨지콘부 재(102') 및 웨지(103')가 직렬로 배치되어 있기 때문에, 강선(W1)의 종점 끝단을 종점정착용의 웨지콘부재(102) 및 웨지(103)에 정착시킨 후 절단하고, 커프링부재(101)를 통해 종점정착용 웨지콘부재(102)와 시점정착용 웨지콘부재(102')를 결합한 후, 강선(W2)의 시점 끝단을 시점정착용 웨지콘부재(102') 및 웨지(103')에 정착시켜야 하므로, 강선을 정착하여 PC 암거를 연결하는 공정이 매우 복잡하다는 단점이 있었다.However, as described above, the PC culvert connection structure using the bidirectional steel wire fixing device 100 includes a wedge-con member 102 and a wedge 103 for fixing a viewpoint and a wedge-con member 102 'and a wedge (for endpoint fixing). 103 ') is arranged in series, the terminal end of the steel wire W1 is fixed to the wedge-con member 102 and the wedge 103 for end point fixing, and cut | disconnected, and the end point through the cuffing member 101 After combining the fixing wedge-con member 102 and the viewpoint fixing wedge-con member 102 ', the end of the viewpoint of the steel wire W2 must be fixed to the viewpoint fixing wedge-con member 102' and the wedge 103 '. Therefore, there was a disadvantage that the process of connecting the PC culvert by fixing the steel wire is very complicated.

상기한 문제를 해결하기 위하여, 예를 들면 대한민국 등록특허 10-0872197호에는 도 2에 도시된 바와 같이, 하나의 웨지콘부재(301)에 웨지홀(302a,302b)을 각각 형성한 종점정착구멍과 시점정착구멍을 평행하게 배치하고, 상기 종점정착구멍과 시점정착구멍의 웨지홀(302a,302b)에 웨지(303a,303b)를 각각 설치함으로써 PC 암거의 조립 공수를 현저히 줄일 수 있는 조립식 PC 암거용 2단 일체형 양방향 강선정착장치(300)가 개시되어 있다.In order to solve the above problem, for example, the Republic of Korea Patent No. 10-0872197, as shown in Figure 2, the end point fixing holes each formed with wedge holes 302a, 302b in one wedge cone member 301 And erecting holes in parallel, and the wedges 303a and 303b are provided in the wedge holes 302a and 302b of the end point fixing holes and the point fixing holes, respectively. Disclosed is a two-stage integrated bidirectional steel wire fixing device for use.

즉, 2단 일체형 양방향 강선정착장치(300)와 서로 다른 위치에 제1 및 제2 강선삽입관통공(320,420)을 각각 형성한 2종류의 PC 암거군(310,410)을 이용하여 PC 암거를 조립한 것으로, PC 암거군(310)은 강선(W1)을 제1 강선삽입관통공(320)에 삽입한 후, 강선(W1)의 종점 끝단을 강선정착장치(300)의 종점정착용 웨지(303a)에 정착시키고, PC 암거군(410)은 강선(W2)을 제2 강선삽입관통공(420)에 삽입하여 연결하되, 강선(W2)의 시점 끝단을 강선정착장치(300)의 시점정착용 웨지(303b)에 정착시키도록 되어 있다.That is, the PC culvert is assembled using two types of two-piece bidirectional wire fixing device 300 and two kinds of PC culvert groups 310 and 410 each having first and second steel wire insertion holes 320 and 420 formed at different positions. As the PC culvert group 310 inserts the steel wire W1 into the first steel wire insertion hole 320, the terminal end of the steel wire W1 is fixed to the terminal fixing wedge 303a of the steel wire fixing device 300. To settle in, the PC culvert group 410 is connected to the steel wire (W2) by inserting the second steel wire insertion hole 420, the end of the steel wire (W2) of the steel wire fixing device 300 for fixing the wedge It is supposed to be fixed at 303b.

따라서, 종점정착용 웨지(303a)와 시점정착용 웨지(303b)가 서로 평행하게 일체로 형성됨으로써, 분해 조립할 필요없이 강선을 밀어 넣고 인장 정착하면 되기 때문에 시공이 간편하고 빨라 시공성을 향상시키고, 부품수도 현저히 줄여 경제성을 높일 수 있다.Therefore, the end point fixing wedge 303a and the point fixation wedge 303b are integrally formed in parallel with each other, so that the steel wire can be pushed in and tensioned without disassembly and assembly. The number can be significantly reduced to increase economics.

또한, 하나의 웨지콘부재(301)에 종점정착용과 시점정착용의 웨지(303a,303b)가 평행하게 배치되기 때문에, 수용홈의 깊이는, 종래의 수용홈에 비해서 얕아도 되어 암거 성형이 용이하다.In addition, since the wedges 303a and 303b for the end point fixing and the point fixation are arranged in parallel in one wedge-con member 301, the depth of the accommodating groove may be shallower than that of the conventional accommodating groove, and culvert molding is easy. Do.

그러나, 이러한 2단 일체형 양방향 강선정착장치(300)를 이용한 PC 암거 연결구조는, PC 암거군(310)과 PC 암거군(410)을 연결함에 있어 웨지콘부재(301)를 중심으로 하여 양쪽에서 긴장되는 강선(W1,W2)의 긴장방향이 웨지콘부재(301)의 중심선(X-X)으로부터 멀리 이격된 위치에서 각각의 수평방향(X1-X1과 X2-X2)으로 작용하기 때문에, PC 암거군(410) 끝단에서 시점정착용 웨지(303b)에 물린 강선(W2)을 긴장하면, 종점정착용 웨지(303a)에 물려 서로 반대방향으로 작용하는 강선(W1)의 수축력(도 2의 화살표 a)과 강선(W2)의 긴장력(도 2의 화살표 b)에 의해 편하중 및 회전하중이 작용하여 웨지콘부재(301)가 긴장력을 견디지 못하여 긴장방향으로 돌출되는 현상이 발생하며, 이러한 현상을 방지하기 위해서는 복잡한 구조의 돌출방지구성을 구비해야 하고, PC 암거군(310)과 PC 암거군(420) 간에 동일 선상 긴장력을 받지못하므로 인한 밀착력 약화를 초래하는 문제가 있었다.However, the PC culvert connection structure using the two-stage integrated bi-directional wire fixing device 300, in connecting the PC culvert group 310 and the PC culvert group 410 in both sides of the wedge cone member 301 Since the tension direction of the tensioned steel wires W1 and W2 acts in the respective horizontal directions X1-X1 and X2-X2 at positions spaced apart from the centerline XX of the wedge-con member 301, the PC culvert group When the wire W2 bitten by the point fixation wedge 303b is tensioned at the end, the contracting force of the wire W1 acting in opposite directions by being bitten by the point fixation wedge 303a (arrow a in FIG. 2) Due to the tension force of the steel wire (W2) (arrow b in Fig. 2) the uneven load and rotational load acts so that the wedge-con member 301 does not stand the tension force and protrudes in the tension direction, to prevent this phenomenon In order to be equipped with a complex structure to prevent protrusions, PC culvert group 310 and PC arm It did not receive the same tensile force line between the groups (420), so there is a problem that results from the adhesion is weakened.

또한, 강선(W1)의 종점 끝단부에 유압식 긴장장치를 설치하여 강선을 긴장하여 종점정착용 웨지(303a)에 정착시킨 후에는, PC 암거군(410)측 오목부(401)에 강선(W1)의 종점 끝단부가 접촉하지 않도록 종점 끝단부를 반드시 절단해야 하므로 강선 정착작업이 번거로운 단점이 있고, 강선(W2)을 시점정착용 웨지(303b)에 정착할 때에는 강선(W2)의 시점 끝단이 시점정착용 웨지(303b)를 관통하여 삽입되는 길이가 짧아 강선(W2)의 긴장시 웨지(303b)가 강선(W2)을 견고하게 밀착시키지 못하는 경우, 강선(W2)이 시점정착용 웨지(303b)에 정착되지 않고 그대로 빠져나오게 되므로, 정착작업을 재시도해야 하는 조립공정상의 번거로움이 있었다.Further, after the hydraulic tension device is provided at the end point of the steel wire W1 and the steel wire is tensioned and fixed to the wedge 303a for the end point fixing, the steel wire W1 is formed in the recess 401 on the PC culvert group 410 side. Since the end of the end must be cut so that the end of the end does not come into contact with the steel wire, the steel wire fixing operation is cumbersome, and when the steel wire W2 is fixed to the time fixing wedge 303b, the starting point of the steel wire W2 is fixed to the viewpoint. When the length that is inserted through the dragon wedge 303b is short and the wedge 303b does not firmly adhere to the steel wire W2 when the steel wire W2 is tensioned, the steel wire W2 is attached to the viewpoint fixing wedge 303b. As it is not settled out, it is pulled out as it is, and there is a trouble in the assembly process that requires retrying the settling work.

본 발명은 상기와 같은 종래의 문제점을 해결하기 위한 것으로, 그 목적은 하나의 웨지콘몸체에 강선의 종점정착을 위한 종점웨지와 시점정착을 위한 시점웨지가 병렬로 배치된 2단 일체형 양방향 강선정착장치를 이용하여 PC 암거군과 또 다른 PC 암거군을 연결함에 있어 양쪽으로 긴장하는 강선의 긴장방향이 웨지콘몸체의 중심선에 최대한 근접하도록 하여 서로 반대방향으로 작용하는 강선의 긴장력에 의해 웨지콘몸체에 편하중 및 회전하중이 작용하는 것을 최소화함으로써, 웨지콘몸체가 긴장방향으로 돌출되는 현상을 방지할 수 있으며, 하나의 PC 암거군과 또 다른 PC 암거군 간에 작용하는 강선의 긴장방향을 최대한 동일 선상으로 유지하여 밀착력을 강화시킬 수 있는 2단 일체형 양방향 강선정착장치 및 이를 이용한 프리캐스트 콘크리트 박스 암거 연결구조를 제공하는데 있다.The present invention is to solve the conventional problems as described above, the purpose of which is a two-stage integrated bidirectional steel wire fixed in which the end wedge for the end point fixing of the steel wire and the time point wedge for the point fixation are arranged in one wedge cone body In connecting the PC culvert group with another PC culvert using the device, the tension direction of the wires tensioned on both sides is as close as possible to the center line of the wedge cone body. By minimizing the acting load and rotational load, the wedge-con body can be prevented from protruding in the tension direction, and the tension direction of the steel wire acting between one PC culvert group and another PC culvert group is the same. Two-stage integrated bi-directional steel wire fixing device that can maintain the shipboard and enhance the adhesion, and precast concrete box using the same To provide a culvert connection structure.

또한, 본 발명은, 강선의 종점 끝단부를 긴장하여 종점정착용 웨지에 정착시킨 후에 종점 끝단부를 절단할 필요가 없고, 강선을 시점정착용 웨지에 정착할 때에는 강선의 시점 끝단이 시점정착용 웨지를 관통한 후 충분히 삽입되도록 하여 한 번의 삽입 작업으로 강선의 긴장시 웨지가 강선을 견고하게 밀착시킬 수 있도록 함으로써 조립공정상의 번거로움을 해소할 수 있어 작업성을 향상시킬 수 있는 2단 일체형 양방향 강선정착장치 및 프리캐스트 콘크리트 박스 암거 연결구조를 제공하는데 있다.In addition, in the present invention, the end point of the steel wire is tensioned and fixed to the end point fixing wedge, and thus the end point need not be cut off, and when the steel wire is fixed to the start point fixing wedge, the start point of the steel wire is the start point fixing wedge. Two-stage integrated bi-directional steel wire fixing to improve workability by eliminating the hassle in the assembly process by allowing the wedge to firmly adhere to the steel wire when the wire is tensioned with one insertion work by penetrating and inserting it sufficiently. To provide a device and a precast concrete box culvert connection structure.

상기의 목적을 달성하기 위한 본 발명은, 점차 단면이 확대되는 종점웨지홀을 제1 중심축선에 형성한 종점정착구멍과, 상기 종점웨지홀에 대하여 반대방향으로 점차 단면이 확대되는 시점웨지홀을 제2 중심축선에 형성한 시점정착구멍이 병렬로 배치된 웨지콘몸체와, 상기 종점웨지홀에 설치된 종점웨지와, 상기 시점웨지홀에 설치된 시점웨지를 구비하는 2단 일체형 양방향 강선정착장치에 있어서, 상기 시점정착구멍의 제2 중심축선은 웨지콘몸체의 중심선과 평행하게 형성되고, 상기 종점정착구멍의 제1 중심축선은 한쪽이 웨지콘몸체의 중심선과의 간격이 점차 근접하도록 시점정착구멍의 2 중심축선에 대하여 경사지게 형성되는 2단 일체형 양방향 강선정착장치에 특징이 있다.The present invention for achieving the above object, the end point fixing hole formed in the end point wedge hole is gradually enlarged in the first center axis, and the time point wedge hole is gradually enlarged in the opposite direction with respect to the end point wedge hole In the two-stage integrated bidirectional steel wire fixing device having a wedge cone body formed in parallel with the viewpoint fixing holes formed in the second center axis, an end wedge provided in the end wedge hole, and a viewpoint wedge provided in the viewpoint wedge hole. The second central axis of the viewpoint fixing hole is formed in parallel with the center line of the wedge cone body, and the first central axis of the endpoint fixing hole has one side of the viewpoint fixing hole so that the interval with the center line of the wedge cone body gradually approaches. It is characterized by a two-stage integrated bidirectional steel wire fixing device that is formed to be inclined with respect to two central axes.

또한 본 발명은 상기 웨지콘몸체는 세로길이가 길고 가로길이가 짧은 직사각형의 단면구조를 가지는 직사각몸체부로 형성되고, 상기 직사각몸체부의 일단면에는 상기 가로길이보다 큰 지름의 원형돌출부를 형성하여 원형돌출부의 양측 가장자리둘레부가 직사각몸체부의 양측면으로부터 돌출하도록 구성한 2단 일체형 양방향 강선정착장치에 특징이 있다.In addition, the wedgecon body is formed of a rectangular body portion having a rectangular cross-sectional structure of a long vertical length and a short horizontal length, a circular protrusion having a diameter larger than the horizontal length formed on one end surface of the rectangular body portion It is characterized by a two-stage integrated bidirectional steel wire fixing device configured to protrude from both sides of the rectangular body portion at both edges of the edge.

또한 본 발명은, 점차 단면이 확대되는 종점웨지홀을 제1 중심축선에 형성한 종점정착구멍과, 상기 종점웨지홀에 대하여 반대방향으로 점차 단면이 확대되는 시점웨지홀을 제2 중심축선에 형성한 시점정착구멍이 병렬로 배치된 웨지콘몸체와, 상기 종점웨지홀에 설치된 종점웨지와, 상기 시점웨지홀에 설치된 시점웨지를 구비하는 2단 일체형 양방향 강선정착장치를 복수개의 PC 암거군의 종점면에 각각 매립하여 한쪽 2단 일체형 양방향 강선정착장치의 시점웨지와 인접한 다른쪽 2단 일체 형 양방향 강선정착장치의 종점웨지를 강선으로 긴장하여 정착함으로써 복수개의 PC 암거군을 상호 밀착시켜 연결하도록 된 프리캐스트 콘크리트 박스 암거 연결구조에 있어서, 상기 2단 일체형 양방향 강선정착장치에 형성한 시점정착구멍의 제2 중심축선은 웨지콘몸체의 중심선과 평행하게 형성하고, 상기 종점정착구멍의 제1 중심축선은 한쪽이 웨지콘몸체의 중심선과의 간격이 점차 근접하도록 경사지게 형성하여, 상기 강선의 시점 끝단은 한쪽 PC 암거군에 매립된 강선정착장치의 시점웨지에 정착하고, 강선의 종점 끝단은 다른쪽 PC 암거군에 매립된 강선정착장치의 종점웨지에 정착함으로써 각 PC 암거군에 매립된 강선정착장치의 웨지콘몸체 양쪽으로 작용하는 강선의 긴장방향이 웨지콘몸체의 중심선에 근접하여 작용하도록 구성한 프리캐스트 콘크리트 박스 암거 연결구조에 특징이 있다.The present invention also provides an end point fixing hole in which an end point wedge hole whose cross section is gradually enlarged is formed in the first center axis line, and a start point wedge hole in which the cross section is gradually enlarged in a direction opposite to the end point wedge hole is formed in the second center axis line. A two-stage integrated bi-directional steel wire fixing device having a wedge cone body having one viewpoint fixing hole disposed in parallel, an endpoint wedge provided in the endpoint wedge hole, and a viewpoint wedge installed in the viewpoint wedge hole, and the endpoint of a plurality of PC culvert groups. It is embedded in the surface of each one of the two-stage one-piece bidirectional steel wire fixing device and the end wedge of the two-stage one-piece bidirectional steel wire fixing device adjacent to each other by tensioning and fixing with a steel wire to connect a plurality of PC culvert groups close to each other. In the precast concrete box culvert connection structure, the second central axis of the viewpoint fixing hole formed in the two-stage integrated bidirectional steel wire fixing device is a wedge. It is formed parallel to the center line of the cone body, the first center axis of the end point fixing hole is formed to be inclined so that one side is gradually closer to the center line of the wedge cone body, the starting point end of the steel wire is embedded in one PC culvert group Settles at the starting wedge of the fixed steel wire fixing device, and the end of the steel wire is fixed to the ending wedge of the steel wire fixing device embedded in the other PC culvert group, thereby acting as both wedge cone bodies of the wire fixing device embedded in each PC culvert group. The precast concrete box culvert connection structure is constructed so that the tension direction of the steel wire acts close to the center line of the wedge body.

상기한 특징적 구성을 가지는 본 발명의 2단 일체형 양방향 강선정착장치 및 이를 이용한 PC 암거 연결구조에 의하면, 2단 일체형 양방향 강선정착장치의 웨지콘몸체에 형성된 시점정착구멍의 중심축선에 대하여 종점정착구멍의 중심축선이 경사지게 형성되어 강선을 긴장하는 방향의 반대방향으로 종점정착구멍과 시점정착구멍의 중심축선 간격이 점차 좁아짐에 따라, PC 암거군과 PC 암거군을 서로 연결할 때, 강선의 종점 끝단은 종점정착구멍의 종점웨지에 정착하고, 강선의 시점 끝단은 시점정착구멍의 시점웨지에 정착하게 되면, 웨지콘몸체에 양쪽으로 작용하는 강선의 긴장방향이 웨지콘몸체의 중심선에 근접하는 경사방향으로 작용하게 되므로, 강선의 긴장방향과 웨지콘몸체의 중심선이 최대한 근접하게 되고, 이로써 웨지콘몸체 에 편하중 및 회전하중이 작용하는 것이 최소화됨으로써, 웨지콘몸체가 긴장방향으로 돌출되는 현상을 방지할 수 있으며, 하나의 PC 암거군과 또 다른 PC 암거군 간에 작용하는 강선의 긴장방향이 최대한 일직선상으로 유지되므로 PC 암거의 밀착력이 강화되는 효과가 있다. According to the two-stage integrated bidirectional steel wire fixing device and the PC culvert connection structure using the same according to the present invention having the above-described configuration, the terminal fixing hole with respect to the center axis of the viewpoint fixing hole formed in the wedge cone body of the two-stage integrated bidirectional steel wire fixing device As the center axis of is formed to be inclined so that the interval between the end point fixing hole and the point fixing hole gradually becomes narrow in the direction opposite to the direction of tensioning the steel wire, when the PC culvert group and the PC culvert group are connected to each other, When settled at the end wedge of the end point fixing hole, and the start end of the steel wire was settled at the end point wedge of the start point fixing hole, the direction of tension of the steel wires acting on both sides of the wedge body is inclined direction close to the center line of the wedge body. Since the tension direction of the steel wire and the center line of the wedge body are as close to each other as possible, this results in a comfortable load on the wedge body. By minimizing the effect of the rotational load, the wedge-con body can be prevented from protruding in the tension direction, and the tension direction of the steel wire acting between one PC culvert group and another PC culvert group is kept as straight as possible. The adhesion of the PC culvert is strengthened.

또한, 본 발명은, 강선의 종점 끝단부에 유압식 긴장장치를 설치하여 강선을 긴장하여 종점웨지에 정착시킨 후에도 강선의 종점 끝단부가 PC 암거의 강선통과구멍에 삽입될 수 있어 종점 끝단부를 절단할 필요가 없고, 강선을 시점웨지에 정착할 때에는 강선의 시점 끝단이 시점웨지를 관통하여 강선통과구멍으로 충분히 삽입됨에 따라, 한 번의 강선 삽입 작업으로 시점웨지에 견고하게 밀착시킬 수 있고, 이로써 조립공정상의 번거로움이 해소되어 작업성이 향상되는 효과가 있다.In addition, the present invention, the end of the wire can be inserted into the wire through hole of the PC culvert even after installing the hydraulic tension device in the end of the steel wire to tension the steel wire to settle in the end wedge need to cut the end of the steel wire When the steel wire is settled in the viewpoint wedge, the end of the steel wire penetrates the viewpoint wedge sufficiently into the line through hole, so that the steel wire can be firmly adhered to the viewpoint wedge by one wire insertion operation. The hassle is eliminated and workability is improved.

이하, 본 발명에 따른 2단 일체형 양방향 강선정착장치 및 이를 이용한 PC 암거 연결구조를 첨부도면에 의거하여 상세하게 설명한다. 도 3 및 도 4는 본 발명의 바람직한 실시예를 나타낸 사시도 및 단면도로서, 도시된 바와 같이 본 발명의 2단 일체형 양방향 강선정착장치(10)는, 하나의 웨지콘몸체(14)에 종점정착구멍(21)과 시점정착구멍(31)을 상,하에 병렬로 형성하고 있다.Hereinafter, a two-stage integrated bidirectional steel wire fixing apparatus and a PC culvert connection structure using the same according to the present invention will be described in detail with reference to the accompanying drawings. 3 and 4 are a perspective view and a cross-sectional view showing a preferred embodiment of the present invention, as shown in the two-stage integrated bidirectional steel wire fixing device 10 of the present invention, the end fixing hole in one wedge cone body 14 21 and the viewpoint fixing hole 31 are formed in parallel up and down.

상기 종점정착구멍(21)에는 도면의 왼쪽으로부터 강선(W1)이 관통하는 관통구멍(22)과, 이 관통구멍(22)의 제1 중심축선(X1-X1)을 중심으로 연이어 형성되어 점차 단면이 확대되는 종점웨지홀(23)이 형성되고, 상기 시점정착구멍(31)은 도면의 우측으로부터 강선(W2)이 관통하는 관통구멍(32)과, 이 관통구멍(32)의 제2 중 심축선(X2-X2)을 중심으로 연이어 형성되어 점차 단면이 확대되는 시점웨지홀(33)과, 상기 시점웨지홀(33)에 연이어 형성된 장착구멍(34)이 형성되어 있다.The end point fixing hole 21 is formed in succession with a through hole 22 through which the steel wire W1 penetrates from the left side of the drawing, and the first center axis line X1-X1 of the through hole 22. The enlarged end point wedge hole 23 is formed, and the viewpoint fixing hole 31 has a through hole 32 through which the steel wire W2 penetrates from the right side of the drawing, and a second center of the through hole 32. The viewpoint wedge hole 33 which is formed successively about the axis X2-X2, and the cross section is gradually expanded, and the mounting hole 34 formed in succession to the said viewpoint wedge hole 33 are formed.

상기 종점웨지홀(23)과 시점웨지홀(33)은 서로 반대방향으로 점차 단면이 확대되도록 형성되어 있으며, 상기 시점정착구멍(31)의 제2 중심축선(X2-X2)은 웨지콘몸체(14)의 중심선(X-X)과 평행하게 형성되고, 상기 종점정착구멍(21)의 제1 중심축선(X1-X1)은 종점웨지홀(32)에서 관통구멍(33)쪽으로 갈수록 웨지콘몸체(14)의 중심선(X-X)과 간격이 점차 근접하도록 시점정착구멍(31)의 제2 중심축선(X2-X2)에 대하여 경사지게 형성되어 있다.The end point wedge hole 23 and the view point wedge hole 33 are formed to gradually expand in cross-section in opposite directions, and the second center axis line X2-X2 of the start point fixing hole 31 is a wedge cone body ( It is formed in parallel with the center line (XX) of the 14, the first center axis (X1-X1) of the end point fixing hole 21 is the wedge cone body 14 toward the through hole 33 from the end point wedge 32 It is formed inclined with respect to the 2nd center axis line X2-X2 of the viewpoint fixing hole 31 so that the space | interval may gradually become close | similar to the center line XX.

또한, 종점정착구멍(21)의 종점웨지홀(22)과 시점정착구멍(31)의 시점웨지홀(32)에는 3분할로 형성되어 고무링(25a,35a)으로 결합된 공지의 종점웨지(25)와 시점웨지(35)가 각각 설치되고, 시점정착구멍(31)의 장착구멍(34)에는 고정링(36)과 시점웨지(35) 사이에 스프링(37)이 탄력설치되어 시점웨지(35)를 항상 시점웨지홀(33)에 밀착시키는 탄성력을 부여하도록 되어 있다.In addition, the end wedge hole 22 of the end point fixing hole 21 and the start point wedge hole 32 of the start point fixing hole 31 are formed in three divisions and are known end wedges coupled to the rubber rings 25a and 35a. 25 and a view point wedge 35 are respectively provided, and a spring 37 is elastically installed between the fixing ring 36 and the view point wedge 35 in the mounting hole 34 of the view point fixing hole 31. The elastic force which always comes into close contact with the viewpoint wedge hole 33 is always provided.

한편, 상기 웨지콘몸체(14)는 세로길이가 길고 가로길이가 짧은 직사각형의 단면구조를 가지는 직사각몸체부(12)로 형성되고, 상기 직사각몸체부(12)의 일단면에는 상기 가로길이보다 큰 지름의 원형돌출부(13)를 형성하여 원형돌출부(13)의 양측 가장자리둘레부가 직사각몸체부(12)의 양측면으로부터 돌출하도록 구성되어 있다.On the other hand, the wedge cone body 14 is formed of a rectangular body portion 12 having a rectangular cross-sectional structure having a long vertical length and a short horizontal length, one end surface of the rectangular body portion 12 is larger than the horizontal length A circular protrusion 13 having a diameter is formed so that both edges of the circular protrusion 13 protrude from both sides of the rectangular body portion 12.

이러한 구성으로 이루어진 2단 일체형 양방향 강선정착장치(10)를 이용한 PC 암거 연결구조를 도 5a 내지 도 5c를 참조하여 설명한다. 먼저 도 5a에 도시된 바 와 같이 연결하고자 하는 PC 암거군은 복수개의 PC 암거, 예를 들면 제1 내지 제3 PC 암거(1A,1B,1C)를 연이어 배치하여 이루어지고, 각 제1 내지 제3 PC 암거(1A,1B,1C)에는 강선이 삽입되는 파이프(2)를 연결방향으로 각각 매립 형성하되, 마지막에 위치하는 제3 PC 암거(1C)의 파이프(2) 종점 끝단에는 본 발명의 강선정착장치(10)를 고정하여 콘크리트 타설 형성시 함께 매립되도록 한다. The PC culvert connection structure using the two-stage integrated bidirectional steel wire fixing device 10 having such a configuration will be described with reference to FIGS. 5A to 5C. First, as shown in FIG. 5A, the PC culvert group to be connected is formed by sequentially arranging a plurality of PC culverts, for example, the first to third PC culverts 1A, 1B, and 1C, and each of the first to third culverts. 3 PC culverts (1A, 1B, 1C) to form a pipe (2) in which the steel wire is inserted in the connecting direction, respectively, the end of the pipe (2) end of the third PC culvert (1C) located at the end of the present invention The steel wire fixing device 10 is fixed to be embedded together when concrete pouring is formed.

이때, 상기 파이프(2)와 강선정착장치(10)의 고정은, 파이프(2)의 안둘레면에 암나사부(2a)를 형성하고, 강선정착장치(10)의 웨지콘몸체(14)에 형성된 원형돌출부(13)에 수나사부(13a)를 형성하여 이들의 나사결합에 의해 이루어지도록 하는 것이 바람직하며, 상기 웨지콘몸체(14)의 원형돌출부(13)는 도 3에서와 같이 직사각몸체부(12)의 양측면으로부터 돌출형성된 것이므로, 제3 PC 암거(1C)의 콘크리트 타설시 강선정착장치(10)와의 결합력을 증대시키고, 매립된 상태에서 웨지콘몸체(14)가 이탈하지 않도록 하는 기능을 수행한다. At this time, the fixing of the pipe 2 and the steel wire fixing device 10, the female threaded portion (2a) is formed on the inner circumferential surface of the pipe (2), to the wedge cone body 14 of the steel wire fixing device 10 It is preferable to form the male screw portion 13a in the formed circular protrusion 13 so as to be made by screwing them, and the circular protrusion 13 of the wedge cone body 14 is a rectangular body portion as shown in FIG. Since it protrudes from both sides of (12), to increase the bonding force with the steel wire fixing device 10 during the concrete placement of the third PC culvert (1C), and prevents the wedge-con body 14 from being detached in the buried state To perform.

상기와 같은 구성의 제1 내지 제3 PC 암거(1A,1B,1C)를 연이어 배치한 PC 암거군(G1)을 시공장소에 위치시킨 다음, 파이프(2)를 통하여 강선(W1)을 삽입하고, 강선(W1)의 시점 끝단(도면의 좌측 끝단)은 제1 PC 암거(1A)의 시점면에 정착되는데, 제1 PC 암거(1A)의 시점면에는 통상의 시점정착장치(10A)를 위치시키고, 강선(W1)의 시점 끝단에 웨지콘부재(11A)와 웨지(12A)를 물린 후, 강선(W1)을 도 5a의 화살표 b방향으로 당김으로써 웨지(12A)가 강선(W1)을 물은 채로 웨지콘부재(11A)의 웨지홀로 삽입되어 강선(W1)이 정착되도록 한다.The PC culvert group G1 having the first to third PC culverts 1A, 1B, and 1C configured as described above in succession is positioned at a city factory, and then the steel wire W1 is inserted through the pipe 2. The viewpoint end (left end of the drawing) of the steel wire W1 is fixed to the viewpoint surface of the first PC culvert 1A, and the normal viewpoint fixation device 10A is positioned on the viewpoint surface of the first PC culvert 1A. The wedge cone member 11A and the wedge 12A are bitten at the end point of the steel wire W1, and the wedge 12A bites the steel wire W1 by pulling the steel wire W1 in the direction of the arrow b of FIG. 5A. It is inserted into the wedge hole of the wedge cone member 11A so as to allow the steel wire W1 to be fixed.

이어서 강선(W1)의 종점 끝단(도면의 우측 끝단)은 강선정착장치(10)의 종점 정착구멍(21)으로 삽입하여 종점웨지(25)에 물리고, 종점웨지(25)에 물린 강선(W1)을 유압식 긴장장치(도시하지 않음)에 의해 화살표 b방향으로 긴장한 후, 긴장을 해제하게 되면, 강선(W1)의 긴장력에 의한 반력으로 종점웨지(25)가 강선(W1)을 물은 채로 웨지콘몸체(14)의 종점웨지홀(23)에 밀착되고, 강선(W1)이 수축하면서 종점웨지(25)를 화살표 a방향으로 더욱 당기게 되므로, 강선(11)은 강하게 정착되어 제1 내지 제3 PC 암거(1A,1B,1C)들은 강선(11)의 수축력에 의해 강하게 밀착된 상태로 연결된다.Subsequently, the terminal end (right end in the drawing) of the steel wire W1 is inserted into the terminal fixing hole 21 of the steel wire fixing device 10 and snapped into the terminal wedge 25, and the steel wire W1 bitten by the terminal wedge 25. When the tension is released in the direction of arrow b by a hydraulic tension device (not shown), and the tension is released, the wedge cone 25 receives the steel wire W1 with the reaction force by the tension force of the steel wire W1. Close to the end wedge hole 23 of the body 14, the steel wire (W1) is contracted further pulls the end wedge 25 in the direction of the arrow a while contracting, the steel wire 11 is firmly fixed to the first to third PC The culverts 1A, 1B and 1C are connected in a state of being strongly in contact with each other by the contracting force of the steel wire 11.

이어서 도 5b에 도시된 바와 같이 PC 암거군(G1)에 연이어 연결할 또 다른 복수개의 제1 내지 제3 PC 암거(1A,1B,1C)를 연이어 배치한 PC 암거군(G2)을 시공장소에 위치시킨 다음, 파이프(2)를 통하여 강선(W2)을 삽입한다. 상기 파이프(2)을 통해 PC 암거군(G2)측 제1 PC 암거(1A)의 시작면으로 돌출한 강선(W2)은, 이미 PC 암거군(G1)측 제3 PC 암거(1C)에 결합되어 있는 강선정착장치(10)의 시점정착구멍(31)을 통해 시점웨지(35)에 삽입한 후, 화살표 b 방향으로 당겨 시점웨지(35)에 물린다.Subsequently, as shown in FIG. 5B, the PC culvert group G2 in which the plurality of first to third PC culverts 1A, 1B, and 1C are successively arranged to be connected to the PC culvert group G1 is located at the city factory. Then, the steel wire (W2) is inserted through the pipe (2). The steel wire W2 protruding to the start surface of the first PC culvert 1A on the PC culvert group G2 side through the pipe 2 is already coupled to the third PC culvert 1C on the PC culvert group G1 side. After insertion into the viewpoint wedge 35 through the viewpoint fixation hole 31 of the steel wire fixing apparatus 10, it pulls in the direction of arrow b, and is bitten by the viewpoint wedge 35. FIG.

이때, 도 4에서와 같이 강선(W2)을 시점웨지(35) 내부(화살표 a 방향)로 삽입할 때에는 시점웨지(35)가 뒤로 밀리지만 스프링(37)의 탄성반발력에 의해 시점웨지(35)는 시점웨지홀(33)에 밀착하려고 하므로, 강선(W2)을 삽입 후 긴장시키기 위해 다시 화살표 b 반대방향으로 당기게 되면, 시점웨지(35)가 시점웨지홀(33)에 스프링력으로 밀착되면서 강선(W2)을 더욱 확실하게 조여 정착시킬 수 있고, 이로써 시점웨지(35)가 뒤로 완전히 밀려 시점웨지홀(33)에 밀착되지 않음에 따라 강 선(W2)의 정착이 이루어지지 않는 문제를 해소할 수 있다. At this time, when inserting the steel wire (W2) into the inside of the viewpoint wedge 35 (arrow a direction) as shown in Figure 4, the viewpoint wedge 35 is pushed back, but the viewpoint wedge 35 by the elastic repulsive force of the spring 37 Is trying to be in close contact with the viewpoint wedge hole 33, when the steel wire (W2) is pulled again in the opposite direction to the arrow b in order to tension, the viewpoint wedge 35 is in close contact with the viewpoint wedge hole 33 with a spring force (W2) can be tightened more securely, thereby eliminating the problem that the steel wire (W2) is not settled as the viewpoint wedge (35) is pushed back completely and does not adhere to the viewpoint wedge hole (33). Can be.

이어서, 강선(W2)의 종점 끝단은 PC 암거군(G2)의 제3 PC 암거(1C)에 매립된 또 다른 강선정착장치(10)의 종점정착구멍(21)을 통해 종점웨지(25)에 물리고, 종점웨지(25)에 물린 강선(W2)을 유압식 긴장장치(도시하지 않음)에 의해 화살표 b방향으로 긴장하게 되면, 도 5c에 도시된 바와 같이 PC 암거군(G2)이 PC 암거군(G1)에 밀착하여 연결되고, 그 후, 긴장을 해제하면, 강선(W2)의 긴장력에 의한 반력으로 PC 암거군(G2)측 강선정착장치(10)의 종점웨지(25)가 강선(W2)을 물은 채로 웨지콘몸체(14)의 종점웨지홀(23)에 밀착되고, 강선(W2)이 수축하면서 종점웨지(25)를 화살표 a 방향으로 더욱 당기게 되므로, 강선(W2)은 강하게 정착되어 PC 암거군(G2)의 PC 암거(1A,1B,1C)들은 강선(W2)의 수축력에 의해 강하게 밀착된 상태로 PC 암거군(G1)에 연결되며, 이러한 연결구조를 반복함으로써 PC 암거군(G2)에 또 다른 PC 암거군을 연이어 연결할 수 있게 된다. Subsequently, the terminal end of the steel wire W2 is connected to the terminal wedge 25 through the terminal fixing hole 21 of another steel wire fixing device 10 embedded in the third PC culvert 1C of the PC culvert group G2. When the bite and the wire w2 bitten by the end wedge 25 are tensioned in the direction of arrow b by a hydraulic tension device (not shown), as shown in FIG. 5C, the PC culvert group G2 is a PC culvert group ( When the tension is released afterward, the end wedge 25 of the steel wire fixing device 10 of the PC culvert group G2 side is subjected to the reaction force by the tension force of the steel wire W2. While keeping close to the end wedge hole 23 of the wedge cone body 14, the steel wire (W2) is contracted, so that the end wedge 25 is further pulled in the direction of the arrow a, the steel wire (W2) is firmly fixed PC culverts 1A, 1B and 1C of the PC culvert group G2 are connected to the PC culvert group G1 in a state of being closely adhered to by the contracting force of the steel wire W2, and by repeating this connection structure, P Another C culvert group can be connected to the C culvert group (G2).

이와 같은 본 발명의 PC 암거 연결구조는, 도 4 및 도 5c에서와 같이 2단 일체형 양방향 강선정착장치(10)의 웨지콘몸체(14)에 형성된 시점정착구멍(31)의 중심축선(X2-X2)에 대하여 종점정착구멍(21)의 중심축선(X1-X1)이 경사지게 형성되어 강선(W1)을 긴장하는 방향의 반대방향으로 종점정착구멍(21)과 시점정착구멍(31)의 중심축선 간격이 점차 좁아지게 형성된 것이므로, PC 암거군(G1)과 PC 암거군(G2)을 강선정착장치(10)로 연결할 때, 강선(W1)의 종점 끝단은 종점정착구멍(21)의 종점웨지(25)에 정착하고, 강선(W2)의 시점 끝단은 시점정착구멍(31)의 시점웨지(35)에 정착하게 되면, 웨지콘몸체(14)에 양쪽으로 작용하는 강선(W1,W2)의 수축 및 긴 장방향이 웨지콘몸체(14)의 중심선(X-X)에 근접하는 경사방향으로 작용하게 된다.As described above, the PC culvert connection structure of the present invention has a central axis X2- of the viewpoint fixing hole 31 formed in the wedge-con body 14 of the two-stage integrated bidirectional steel wire fixing device 10 as shown in FIGS. 4 and 5C. The center axis line X1-X1 of the end point fixing hole 21 is inclined with respect to X2), and the center axis line of the end point fixing hole 21 and the start point fixing hole 31 in the direction opposite to the direction in which the steel wire W1 is tensioned. Since the gap is formed to become narrow gradually, when connecting the PC culvert group (G1) and PC culvert group (G2) with the steel wire fixing device 10, the end of the end of the steel wire (W1) is the end wedge of the terminal fixing hole 21 ( 25), and when the end of the viewpoint of the steel wire W2 is fixed to the viewpoint wedge 35 of the viewpoint fixing hole 31, contraction of the steel wires W1 and W2 acting on both sides of the wedge cone body 14 is performed. And a long longitudinal direction acts in an inclined direction close to the centerline XX of the wedge cone body 14.

따라서, 도 6a에 도시된 바와 같이 본 발명의 강선정착장치(10)를 이용하여 강선(W1,W2,W3)을 반복하여 연결하면, 강선의 긴장방향이 시점 끝단은 강선정착장치(10)의 웨지콘몸체(14)의 중심선(X-X) 하부에서 작용하고 종점 끝단은 강선정착장치(10)의 웨지콘몸체(14)의 상부에서 작용하게 되므로, 전체적으로 웨지콘몸체(14)의 중심선(X-X)을 중심으로 하여 대각선 방향으로 경사지게 작용하게 된다.Therefore, as shown in FIG. 6a, when the steel wires W1, W2, and W3 are repeatedly connected using the steel wire fixing device 10 of the present invention, the tension direction of the steel wire is the end of the steel wire fixing device 10. The center line XX of the wedge cone body 14 and the end of the end acts on the upper portion of the wedge cone body 14 of the steel wire fixing device 10, so that the center line (XX) of the wedge cone body 14 as a whole It is inclined in a diagonal direction with the center.

이로 인해 도 6b에 도시된 바와 같이 강선(11,11',11'')이 웨지콘부재(301)(도 2 참조)의 중심선(X-X)으로부터 간격(g)만큼 이격되어 평행한 방향으로 작용하는 종래의 2단 일체형 양방향 강선정착장치(300)에 비하여 긴장방향이 중심선(X-X)선에 최대한 근접하게 되므로, 웨지콘몸체(14)의 중심선(X-X)을 중심으로 하여 작용하는 편하중 및 회전하중이 최소화됨으로써, 웨지콘몸체(14)가 긴장방향으로 돌출되는 현상을 방지할 수 있고, PC 암거군(G1,G2,G3) 간에 작용하는 강선의 긴장방향이 최대한 일직선상으로 유지되므로 PC 암거의 밀착력이 강화된다. As a result, as shown in FIG. 6B, the steel wires 11, 11 ′, 11 ″ are spaced apart from the center line XX of the wedge cone member 301 (see FIG. 2) by an interval g to act in a parallel direction. Compared to the conventional two-stage integrated bidirectional steel wire fixing device 300, the tension direction is as close to the center line (XX) as possible, so that the load and rotation acting about the center line (XX) of the wedge body 14 By minimizing the load, it is possible to prevent the wedge-con body 14 from protruding in the tension direction, and the tension direction of the steel wire acting between the PC culvert groups G1, G2, and G3 is maintained in a straight line as much as possible. The adhesion of the is strengthened.

또한, 본 발명은, 도 5c에서와 같이 강선(W1)의 종점 끝단부에 유압식 긴장장치를 설치하여 강선(W1)을 긴장하여 종점웨지(25)에 정착시킨 후, 강선(W1)의 종점 끝단부를 다음 PC 암거군(G2)의 제1 PC 암거(1A)의 파이프(2) 내에 삽입시킬 수 있어 강선(W1)의 종점 끝단부를 절단할 필요가 없고, 강선(W2)을 시점웨지(35)에 정착할 때에는 강선(W2)의 시점 끝단이 시점웨지(35) 및 시점정착구멍(31)을 관통하여 PC 암거군(G1)의 제3 PC 암거(1C)의 파이프(2)로 충분히 삽입됨에 따라, 한 번의 강선(W2) 삽입 작업으로 시점웨지(35)에 견고하게 밀착시킬 수 있게 되므로, 강선정착장치를 이용한 PC 암거 조립공정상의 번거로움이 해소되어 작업성이 향상된다.In addition, the present invention, as shown in Figure 5c by installing a hydraulic tensioning device in the end of the end of the steel wire (W1) to tension the steel wire (W1) to be fixed to the end wedge 25, the end of the steel wire (W1) The part can be inserted into the pipe 2 of the first PC culvert 1A of the next PC culvert group G2, so that it is not necessary to cut the end point of the steel wire W1, and the steel wire W2 can be inserted into the viewpoint wedge 35. In the case of fixing to the steel wire W2, the end of the viewpoint of the steel wire W2 penetrates the viewpoint wedge 35 and the viewpoint fixing hole 31, and is fully inserted into the pipe 2 of the 3rd PC culvert 1C of the PC culvert group G1. Accordingly, since the steel wire W2 can be firmly adhered to the viewpoint wedge 35 by a single insertion operation, the troublesomeness of the PC culvert assembly process using the steel wire fixing device is eliminated and the workability is improved.

그리고, 본 발명은 도 5c에서와 같이 PC 암거군(G1)에 PC 암거군(G2)을 밀착시키기 위해 강선(W2)을 화살표 b 방향으로 긴장할 때, 강선정착장치(10)는 파이프(2)와 일체적으로 결합됨과 동시에 파이프(2)와 함께 제3 PC 암거(1C)에 매립된 것이므로, 강선(W2)의 당김력은 PC 암거군(G1)을 밀착시키고 있는 강선(W1)에 전혀 영향을 주지 않게 되고, 제3 PC 암거(1C) 자체를 끌어당기게 된다. 따라서, PC 암거군(G1)측 강선(W1)의 수축력을 그대로 유지한 상태에서 다음 PC 암거군(G2)을 연속하여 연결할 수 있게 되고, 이로써 PC 암거 사이의 밀착력이 약화되는 것이 방지되어 외부에서 힘이 작용하는 경우, PC 암거 사이의 연결부위가 벌어져 수밀성을 저하시키는 등, 기능을 수행함에 있어 악영향을 주는 문제를 해소할 수 있다.And, in the present invention, when the steel wire (W2) in tension in the direction of the arrow b in order to contact the PC culvert group (G2) to the PC culvert group (G1), as shown in Figure 5c, the steel wire fixing device 10 is a pipe (2) And integrally coupled with the pipe 2 and embedded in the third PC culvert 1C together with the pipe 2, the pulling force of the steel wire W2 has no influence on the steel wire W1 that is in close contact with the PC culvert group G1. The third PC culvert 1C itself is attracted. Accordingly, the next PC culvert group G2 can be continuously connected while the contracting force of the PC culvert group G1 side steel wire W1 is maintained as it is, thereby preventing the adhesion between the PC culverts from being weakened from the outside. When the force acts, the connection between the PC culverts can be opened to reduce the watertightness, and the problem of adversely affecting the function can be solved.

또한, 강선정착장치(10)의 웨지콘몸체(14)에 형성된 원형돌출부(13)에 의해서는 제3 PC 암거(1C)와의 결합력을 증대시키게 되므로 강선(W2)을 긴장할 때, 강선정착장치(10)가 제3 PC 암거(1C)로부터 이탈되는 것이 방지되고, 강선정착장치(10)에 작용하는 당김력의 방향에 대하여 제3 PC 암거(1C)와 강선정착장치(10)와의 결합력을 극대화시킬 수 있다.In addition, the circular protrusion 13 formed on the wedge-con body 14 of the steel wire fixing device 10 increases the coupling force with the third PC culvert 1C, so when the steel wire W2 is tensioned, the steel wire fixing device ( 10 is prevented from escaping from the third PC culvert 1C, and the coupling force between the third PC culvert 1C and the steel wire fixing device 10 is maximized with respect to the direction of the pulling force acting on the steel wire fixing device 10. You can.

지금까지 설명된 실시예는 본 발명의 바람직한 실시예를 설명한 것에 불과하고, 본 발명의 권리범위는 설명된 실시예에 한정되는 것은 아니며, 본 발명의 기술적 사상과 특허청구범위 내에서 이 분야의 당업자에 의하여 다양한 변경, 변형 또는 치환이 가능할 것이며, 그와 같은 실시예들은 본 발명의 범위에 속하는 것으로 이해되어야 한다.The embodiments described so far are merely illustrative of the preferred embodiments of the present invention, and the scope of the present invention is not limited to the described embodiments, and those skilled in the art within the technical spirit and claims of the present invention. It will be understood that various changes, modifications, or substitutions may be made thereto, and such embodiments are to be understood as being within the scope of the present invention.

도 1a 내지 도 1e는 종래의 양방향 강선정착장치에 의한 PC 암거 연결과정을 나타낸 단면도.1A to 1E are cross-sectional views showing a PC culvert connection process by a conventional bidirectional steel wire fixing apparatus.

도 2는 종래의 2단 일체형 양방향 강선정착장치에 의한 PC 암거 연결구조를 나타낸 단면구성도.Figure 2 is a cross-sectional view showing a PC culvert connection structure by a conventional two-stage integrated bidirectional steel wire fixing device.

도 3 및 도 4는 본 발명에 따른 2단 일체형 양방향 강선장치를 나타낸 사시도 및 종단면도.3 and 4 are a perspective view and a longitudinal cross-sectional view showing a two-stage integrated bidirectional steel wire device according to the present invention.

도 5a 내지 도 5c는 본 발명에 따른 PC 암거 연결구조를 나타낸 단면구성도.5a to 5c is a cross-sectional view showing a PC culvert connection structure according to the present invention.

도 6a 및 도 6b는 본 발명과 종래기술에 따른 PC 암거 연결구조를 비교하여 설명하기 위한 개략도.6A and 6B are schematic diagrams for explaining and comparing a PC culvert connection structure according to the present invention and the prior art.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

10 : 강선정착장치 12 : 직사각몸체부10: steel wire fixing device 12: rectangular body portion

13 : 원형돌출부 14 : 웨지콘몸체13: circular protrusion 14: wedge cone body

21 : 종점정착구멍 22 : 관통구멍21: end fixing hole 22: through hole

23 : 종점웨지홀 25 : 종점웨지23: end wedge hole 25: end wedge

31 : 시점정착구멍 32 : 관통구멍31: viewpoint fixing hole 32: through hole

33 : 시점웨지홀 35 : 시점웨지33: viewpoint wedge hole 35: viewpoint wedge

Claims (3)

점차 단면이 확대되는 종점웨지홀을 제1 중심축선에 형성한 종점정착구멍과, 상기 종점웨지홀에 대하여 반대방향으로 점차 단면이 확대되는 시점웨지홀을 제2 중심축선에 형성한 시점정착구멍이 병렬로 배치된 웨지콘몸체와, 상기 종점웨지홀에 설치된 종점웨지와, 상기 시점웨지홀에 설치된 시점웨지를 구비하는 2단 일체형 양방향 강선정착장치에 있어서,An end point fixing hole in which an end point wedge hole, the section of which is gradually enlarged, is formed in the first center axis line, and a start point fixing hole in which the end point wedge hole is gradually formed in the opposite direction with respect to the end point wedge hole. In the two-stage integrated bi-directional steel wire fixing device having a wedge cone body disposed in parallel, the end wedge provided in the end wedge hole, and the start wedge provided in the viewpoint wedge hole, 상기 시점정착구멍의 제2 중심축선은 웨지콘몸체의 중심선과 평행하게 형성되고, 상기 종점정착구멍의 제1 중심축선은 한쪽이 웨지콘몸체의 중심선과의 간격이 점차 근접하도록 시점정착구멍의 2 중심축선에 대하여 경사지게 형성됨을 특징으로 하는 2단 일체형 양방향 강선정착장치.The second central axis of the viewpoint fixing hole is formed in parallel with the center line of the wedge cone body, and the first central axis of the endpoint fixing hole has two sides of the viewpoint fixing hole so that the distance from the center line of the wedge cone body gradually approaches. A two-stage integrated bi-directional steel wire fixing device, characterized in that formed inclined with respect to the central axis. 제 1 항에 있어서, 상기 웨지콘몸체는, 세로길이가 길고 가로길이가 짧은 직사각형의 단면구조를 가지는 직사각몸체부로 형성되고, 상기 직사각몸체부의 일단면에는 상기 가로길이보다 큰 지름의 원형돌출부를 형성하여 원형돌출부의 양측 가장자리둘레부가 직사각몸체부의 양측면으로부터 돌출하도록 구성함을 특징으로 하는 2단 일체형 양방향 강선정착장치.The wedge-con body of claim 1, wherein the wedge-con body is formed of a rectangular body portion having a rectangular cross-sectional structure having a long vertical length and a short horizontal length, and a circular protrusion having a diameter larger than the horizontal length is formed at one end surface of the rectangular body portion. Two-stage integrated two-way steel wire fixing device characterized in that the protruding from both sides of the rectangular body portion of the circular protrusions. 점차 단면이 확대되는 종점웨지홀을 제1 중심축선에 형성한 종점정착구멍과, 상기 종점웨지홀에 대하여 반대방향으로 점차 단면이 확대되는 시점웨지홀을 제2 중심축선에 형성한 시점정착구멍이 병렬로 배치된 웨지콘몸체와, 상기 종점웨지홀에 설치된 종점웨지와, 상기 시점웨지홀에 설치된 시점웨지를 구비하는 2단 일체형 양방향 강선정착장치를 복수개의 PC 암거군의 종점면에 각각 매립하여 한쪽 2단 일체형 양방향 강선정착장치의 시점웨지와 인접한 다른쪽 2단 일체형 양방향 강선정착장치의 종점웨지를 강선으로 긴장하여 정착함으로써 복수개의 PC 암거군을 상호 밀착시켜 연결하도록 된 프리캐스트 콘크리트 박스 암거 연결구조에 있어서,An end point fixing hole in which an end point wedge hole, the section of which is gradually enlarged, is formed in the first center axis line, and a start point fixing hole in which the end point wedge hole is gradually formed in the opposite direction with respect to the end point wedge hole. A two-stage integrated bi-directional steel wire fixing device having a wedge cone body disposed in parallel, an end wedge installed in the end wedge hole, and a start wedge installed in the end wedge hole are embedded in the end faces of the plurality of PC culvert groups, respectively. Precast concrete box culvert connection to connect multiple PC culverts in close contact by tensioning and fixing the end wedge of the two-stage one-piece bidirectional wire fixing device adjacent to the two-stage one-piece bidirectional steel fixing device by the tension In structure, 상기 2단 일체형 양방향 강선정착장치에 형성한 시점정착구멍의 제2 중심축선은 웨지콘몸체의 중심선과 평행하게 형성하고, 상기 종점정착구멍의 제1 중심축선은 한쪽이 웨지콘몸체의 중심선과의 간격이 점차 근접하도록 경사지게 형성하여, 상기 강선의 시점 끝단은 한쪽 PC 암거군에 매립된 강선정착장치의 시점웨지에 정착하고, 강선의 종점 끝단은 다른쪽 PC 암거군에 매립된 강선정착장치의 종점웨지에 정착함으로써 각 PC 암거군에 매립된 강선정착장치의 웨지콘몸체 양쪽으로 작용하는 강선의 긴장방향이 웨지콘몸체의 중심선에 근접하여 작용하도록 구성함을 특징으로 하는 프리캐스트 콘크리트 박스 암거 연결구조.The second center axis of the viewpoint fixing hole formed in the two-stage integrated bidirectional steel wire fixing device is formed in parallel with the center line of the wedge cone body, and the first center axis of the end point fixing hole has one side with the center line of the wedge cone body. It is formed to be inclined so that the interval gradually closes, the end point of the steel wire is settled in the time wedge of the steel wire anchoring device embedded in one PC culvert group, the end of the steel wire end point of the steel wire fixing device embedded in the other PC culvert group Precast concrete box culvert connection structure, characterized in that the tension direction of the steel wire acting on both sides of the wedge cone body of the steel wire fixing device embedded in each PC culvert group by acting in the wedge acts close to the center line of the wedge cone body .
KR1020090041879A 2009-05-13 2009-05-13 Tendon Anchoring Apparatus and Connecting Structure for Precast Concrete Box Culvert KR101042945B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090041879A KR101042945B1 (en) 2009-05-13 2009-05-13 Tendon Anchoring Apparatus and Connecting Structure for Precast Concrete Box Culvert

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090041879A KR101042945B1 (en) 2009-05-13 2009-05-13 Tendon Anchoring Apparatus and Connecting Structure for Precast Concrete Box Culvert

Publications (2)

Publication Number Publication Date
KR20100122799A KR20100122799A (en) 2010-11-23
KR101042945B1 true KR101042945B1 (en) 2011-06-20

Family

ID=43407637

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090041879A KR101042945B1 (en) 2009-05-13 2009-05-13 Tendon Anchoring Apparatus and Connecting Structure for Precast Concrete Box Culvert

Country Status (1)

Country Link
KR (1) KR101042945B1 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105781117B (en) * 2014-12-23 2017-09-26 天津宏达生产力促进有限公司 Anti- skewing mechanism for line tensioning of constructing
KR200490659Y1 (en) * 2019-02-28 2019-12-13 주식회사 신우산업 Complex nut for fixing reinforcement bar and bolt
CN111706086B (en) * 2020-06-19 2021-12-17 威胜利工程有限公司 Clamping piece mounting auxiliary
CN113174873A (en) * 2021-04-30 2021-07-27 浙江数智交院科技股份有限公司 Reinforced soil-reinforced concrete composite culvert and forming method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2907740B2 (en) 1994-11-28 1999-06-21 水谷建設工業株式会社 Bevel prestressed box culvert and method of introducing prestress into bevel box culvert
KR100457650B1 (en) 2001-09-10 2004-11-18 강신량 Bidirectional wire tension device
KR100829150B1 (en) 2007-03-28 2008-05-13 이정오 Precast concrete box culvert, structure and method of constructing the same
KR100872197B1 (en) 2007-03-28 2008-12-09 이정오 Prefabricated precast concrete box culvert

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2907740B2 (en) 1994-11-28 1999-06-21 水谷建設工業株式会社 Bevel prestressed box culvert and method of introducing prestress into bevel box culvert
KR100457650B1 (en) 2001-09-10 2004-11-18 강신량 Bidirectional wire tension device
KR100829150B1 (en) 2007-03-28 2008-05-13 이정오 Precast concrete box culvert, structure and method of constructing the same
KR100872197B1 (en) 2007-03-28 2008-12-09 이정오 Prefabricated precast concrete box culvert

Also Published As

Publication number Publication date
KR20100122799A (en) 2010-11-23

Similar Documents

Publication Publication Date Title
KR100692913B1 (en) Tendon anchoring apparatus
KR101042945B1 (en) Tendon Anchoring Apparatus and Connecting Structure for Precast Concrete Box Culvert
KR101713525B1 (en) Chiropractors permanent anchor friction
KR101021184B1 (en) Connecting Structure and Connecting method for Precast Concrete Box Culvert
KR100872197B1 (en) Prefabricated precast concrete box culvert
KR20130017177A (en) Coupler
KR102227527B1 (en) Branch pipe binding device that can guarantee a solid state of connection with the main pipe
KR101021186B1 (en) Tendon Anchoring Apparatus for Precast Concrete Box Culvert
KR101873114B1 (en) Coupler for prestressing strand
KR102002470B1 (en) Protecting plate for underground cable
KR101806326B1 (en) Prefabricated precast concrete culvert with integral anchor embedded
KR100829150B1 (en) Precast concrete box culvert, structure and method of constructing the same
KR20110022124A (en) Connecting structure and connecting method of culvert
KR100635484B1 (en) Unification connect for connecter of manhole etc and pipe
KR100696402B1 (en) Earthquake-resistant type piping connector
JP2004360399A (en) Concrete member
KR101200346B1 (en) Shearing connector
JP2020076303A (en) Sheath coupler, insertion tool for forming sheath end connection, and concrete segment installation method
KR200268501Y1 (en) Dual Directional Prestressed Tendon Anchoring Apparatus
JP6238154B2 (en) Cable laying structure for pipeline facilities and seismic fixing fixtures used therefor
JP4217144B2 (en) Joint structure for butt connection
KR20110033365A (en) Both ends fixed type steel-wire anchoring device and precast concrete structure using the same
KR100957850B1 (en) Connection method for precast concrete member
JP5460954B2 (en) Drainage pipe joint and foundation through piping structure
KR20150131905A (en) Tension for both steel and precast concrete structures and its production and construction methods

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20140616

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20150616

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20160615

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee