KR101031287B1 - Under exterior panel assembly structure for bridge - Google Patents

Under exterior panel assembly structure for bridge Download PDF

Info

Publication number
KR101031287B1
KR101031287B1 KR1020100071851A KR20100071851A KR101031287B1 KR 101031287 B1 KR101031287 B1 KR 101031287B1 KR 1020100071851 A KR1020100071851 A KR 1020100071851A KR 20100071851 A KR20100071851 A KR 20100071851A KR 101031287 B1 KR101031287 B1 KR 101031287B1
Authority
KR
South Korea
Prior art keywords
frame
bridge
exterior
vertical
girder
Prior art date
Application number
KR1020100071851A
Other languages
Korean (ko)
Inventor
이우연
김민선
Original Assignee
김민선
주식회사 디자인그룹오감
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김민선, 주식회사 디자인그룹오감 filed Critical 김민선
Priority to KR1020100071851A priority Critical patent/KR101031287B1/en
Application granted granted Critical
Publication of KR101031287B1 publication Critical patent/KR101031287B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0803Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
    • E04F13/0805Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and the wall
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0803Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
    • E04F13/081Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and covering elements

Abstract

PURPOSE: An exterior panel installation structure for a bridge is provided to facilitate assembly, reduce costs for material and installation, and reduce influence on a bridge. CONSTITUTION: An exterior panel installation structure for a bridge comprises multiple piers, a bridge bearing, multiple girders, an upper slab, and an exterior panel. The multiple piers are installed on the surface. The bridge bearing is installed on the top of the pier. The multiple girders are installed on the top of the bridge bearing at regular intervals. The upper slab is formed on the top of the girder. The exterior panel is assembled on the lower part of the girder by an assembly frame(60) and an exterior member assembling member in order to cover the lower part and side of the girder.

Description

교량용 외장재 설치구조{UNDER EXTERIOR PANEL ASSEMBLY STRUCTURE FOR BRIDGE}Bridge exterior material installation structure {UNDER EXTERIOR PANEL ASSEMBLY STRUCTURE FOR BRIDGE}

본 발명은 교량용 외장재 설치구조에 관한 것으로, 상세하게는 교량 구조물인 거더 하부 영역을 차단하기 위해 외장재에 대한 설치작업이 용이하고, 거더 사이에 온도 변화에 따른 신축이 가능한 구조로 외장재를 설치할 수 있도록 구성한 것이다.The present invention relates to a structure for installing the exterior material for bridges, and in detail, the installation work on the exterior material is easy to block the lower area of the girder, which is the bridge structure, and the exterior material can be installed in a structure that can be stretched and contracted according to the temperature change between the girders. It is configured to be.

일반적으로 도시 내 설치되는 고가도로, 교량 등의 구조물이 설치되며, 이러한 교량 구조물이 도심지 자동차 소통에서 무엇보다도 편리한 시설물로 중요한 역할을 담당해 왔다.In general, structures such as overpasses and bridges installed in cities are installed, and these bridge structures have played an important role as the most convenient facilities in urban automobile communication.

그러나 이러한 교량 구조물은 최근 도심 재개발 및 리모델링 등으로 급속히 변화하는 주변 건축물과 적절한 조화를 이루지 못하고 도시환경 및 지역개발의 저해요인으로 작용함에 따라 철거를 요구하는 민원이 이어지고 있는 실정이다.However, these bridge structures have not been properly harmonized with the rapidly changing surrounding buildings due to urban redevelopment and remodeling, and as a result of the obstacles to urban environment and regional development, civil complaints are demanding removal.

특히 도심지에 위치한 대부분의 교량은 노후 되어 콘크리트 백태, 누수흔적, 기타 얼룩으로 도시경관 이미지를 떨어뜨리며 도로 안전시설 및 각종 배관, 전선 등을 교량 측면 또는 하면 등 외부에 노출되도록 설치함으로 인해 도시 미관을 떨어뜨린다는 지적이 있었다.In particular, most of the bridges in the downtown area are aging, and the image of urban landscape is degraded due to concrete white matter, leakage traces, and other stains. It was pointed out that it was dropped.

한편, 최근에는 이러한 미관 저하의 문제를 개선하기 위해 별도의 외장재패널(막음재)을 교량 구조물의 측면 및 하부에 부착 설치하기 위한 시도가 이루어지고 있다.On the other hand, in recent years, in order to improve the problem of deterioration of aesthetics, attempts have been made to attach and install a separate exterior panel (blocking material) to the side and bottom of the bridge structure.

이러한 종래 교량에 외장재를 설치하기 위한 구조를 첨부된 도면을 참조로 설명하기로 한다.A structure for installing an exterior member on such a conventional bridge will be described with reference to the accompanying drawings.

도 1은 종래 교량용 외장재 설치구조에 따른 교량의 개략적인 단면 구성도이고, 도 2는 도 1의 요부 확대 단면 구성도이고, 도 3은 종래 외장재 설치구조의 다른 실시예를 도시한 단면 구성도이다.1 is a schematic cross-sectional configuration diagram of a bridge according to a conventional bridge mounting structure, Figure 2 is an enlarged cross-sectional configuration of the main portion of Figure 1, Figure 3 is a cross-sectional configuration showing another embodiment of the conventional packaging material mounting structure. to be.

도 1 및 도 2에 도시된 바와 같이, 종래 교량용 외장재 설치구조는 지면에 하부가 설치되는 다수의 교각(100)과; 교각(100) 상부에 구비되는 교량 받침(200)과; 교량 받침(200) 상부에 길이 방향으로 간격이 유지되도록 설치된 다수의 거더(300)와; 거더(300) 상부에 시공되어 차량이 소통하게 되는 상부슬라브(350)와; 상기 거더(300)의 하부 영역에 브라켓(500)과 외장재조립부재(600)로써 조립 유지되어 거더(300)의 하부와 측면을 감싸주게 되는 외장재패널(400)로 이루어진다.As shown in Figure 1 and 2, the conventional bridge exterior mounting structure has a plurality of bridges 100 is installed in the lower portion on the ground; A bridge bearing 200 provided on the pier 100; A plurality of girders 300 installed on the bridge bearing 200 to maintain a distance in the longitudinal direction; An upper slab 350 installed on the girder 300 to communicate with the vehicle; The lower panel of the girder 300 is assembled and maintained with the bracket 500 and the exterior member assembly member 600 to surround the bottom and side of the girder 300.

상기 브라켓(500)은 거더(300) 하부의 확장부에 결합되는 결합부(511)와; 결합부(511)의 상부 양단에 동일한 각도로 경사진 경사결합부(512)와; 결합부(511) 하단에 연장되게 형성된 플랜지부(513)와; 플랜지부(513)와 볼트 및 너트로써 체결 고정되는 수평마감판(514)으로 이루어진다.The bracket 500 includes a coupling part 511 coupled to the extension part of the lower part of the girder 300; An inclined coupling portion 512 inclined at the same angle at both ends of the upper portion of the coupling portion 511; A flange portion 513 formed to extend at the bottom of the coupling portion 511; It consists of a flange 513 and a horizontal finish plate 514 fastened and fixed by a bolt and a nut.

상기 외장재조립부재(600)는 수평마감판(524)에 수직으로 상부가 볼트 및 너트로써 체결 고정된 수직장볼트(610)(611)와; 수직장볼트(610)(611)의 머리부가 삽입 고정되고, 하단에 외장재패널(400)이 연장되게 체결 고정된 지지프레임(620)(621)으로 이루어진다. The exterior material assembly member 600 includes vertical length bolts 610 and 611 fastened and fastened vertically to the horizontal finish plate 524 by bolts and nuts; The heads of the vertical long bolts 610 and 611 are inserted and fixed, and the support frames 620 and 621 are fastened and fixed to extend the exterior panel 400 at the bottom thereof.

이때, 외장재패널(400)은 지지프레임(620)(621) 하부에 볼트로써 체결 고정되고, 이 부위에 코킹(실리콘) 작업을 하면, 볼팅 부위가 은폐된다.At this time, the exterior panel 400 is fastened and fixed to the lower portion of the support frame 620, 621 by a bolt, when the caulking (silicon) work on this portion, the bolting portion is concealed.

따라서, 이와 같이 구성된 구조는 거더 하부 영역에 설치되는 외장재패널을 설치하기 위해 판상의 브라켓을 사용하게 됨에 따라, 조립이 용이하지 않을 뿐만 아니라 자체 중량이 많이 나가 교량에 미치는 영향이 크게 되는 문제점이 발생 되었다.Therefore, the structure configured as described above uses a plate-shaped bracket to install an exterior panel installed in the lower girder, and thus, the assembly is not easy and the weight of the structure is large. It became.

이러한 문제점을 해결하기 위하여 도면에는 도시하지 않았으나, 특허 등록제 10-0764418호(발명의 명칭: 교량의 콘크리트빔 손상 방지형 외장재 설치구조)에는 사각형 단면으로 이루어진 브라켓이 제공되고 있으나, 이는 콘크리트빔(거더)의 확장부에 알맞게 일체로 제작하거나, 구멍을 뚫어 외장재패널을 설치하게 됨에 따라 제작에 따른 가공 및 조립 작업성이 저하되는 문제점이 발생 되었다.In order to solve this problem, although not shown in the drawings, Patent Registration No. 10-0764418 (name of the invention: a concrete beam damage preventing exterior installation structure of the bridge) is provided with a bracket having a rectangular cross section, which is a concrete beam (girder) According to the expansion part of the) to manufacture integrally, or to install the exterior panel by drilling a hole, there is a problem that processing and assembly workability is reduced according to the manufacturing.

한편, 도 3에서와 같이 외장재 프레임(700)은 교각(100) 상부에 구비되는 교량 받침(200) 상부에 길이 방향으로 간격을 두고 설치된 다수의 거더(300) 사이에 설치되어 거더(300)의 연결 부위를 차단하기 위해 사각 파이프(710)를 이용하여 연결하게 된다. Meanwhile, as shown in FIG. 3, the exterior frame 700 is installed between a plurality of girders 300 spaced in the longitudinal direction on an upper portion of the bridge support 200 provided on the pier 100, so that the exterior of the girder 300 is provided. In order to block the connection site is connected using a square pipe 710.

이러한 거더(300)는 온도변화에 따른 교량의 신축에 대한 변위를 고려하여 교각(100)의 상부에 간격을 두고 설치된다.The girder 300 is installed at intervals on the top of the bridge 100 in consideration of the displacement of the bridge in accordance with the temperature change.

상기 거더(300)의 연결 부위에는 사각 파이프(710)에 용접 또는 앵글(730)과 체결나사(740)를 이용하여 연결 방안을 채택하고 있다. 이 경우에 용접부위 부식, 현장작업 어려움 등이 있으며, 앵글 조립시 앵글 자재비 및 작업이 용이하지 않게 되었다. 또한, 교량의 경우 온도신축이 이루어지는데 기존의 프레임들은 별도 신축이음을 둘 방법이 없는 관계로 프레임 변형이 이루어지는 등 구조체에 악영향을 미치게 되었다.The connection part of the girder 300 adopts a connection scheme using a welding or angle 730 and a fastening screw 740 to the square pipe 710. In this case, there is corrosion of the welded part, difficulty in field work, and the angle material cost and the work are not easy when the angle is assembled. In addition, in the case of bridges, temperature stretching occurs. Existing frames have a negative effect on the structure, such as frame deformation, because there is no way to put a separate expansion joint.

본 발명은 이와 같은 종래의 문제점을 해결하기 위하여 안출된 것으로, 본 발명은 교량 구조물인 거더에 조립 프레임의 연결시 프레임에 형성된 볼트머리삽입홈을 통하여 볼트 머리가 삽입되어 볼트 머리가 자유롭게 이동 가능함으로써 필요한 위치에 맞추어 너트를 조이면 조립이 가능하고, 프레임의 연결만으로 거더와 고정이 가능하여 사용되는 부재가 적어 자재, 설치비가 절감되며 무게의 경량으로 인해 교량에 미치는 영향이 적은 데 그 목적이 있다.The present invention has been made to solve such a conventional problem, the present invention is that the bolt head is inserted through the bolt head insertion groove formed in the frame when the assembly frame is connected to the girder bridge structure can be moved freely by the bolt head It is possible to assemble by tightening the nut according to the required position, and it is possible to fix the girder with only the connection of the frame, so there are few members used, which saves material and installation cost, and the light weight makes the bridge less impact.

본 발명의 다른 목적은 교각 상부의 거더 사이를 차단하기 위한 외장재프레임은 재질이 알루미늄으로 가볍고 부식의 우려가 없으며, 알루미늄 프레임 및 슬리이브로 이루어지며 프레임 내부로 슬리이브가 들어감으로써 온도 신축부의 경우 한쪽에 나사 체결하면, 자유로이 온도신축이 가능하고, 또한 부재 연결시 슬리이브를 이용하여 간단히 부재간의 연결이 가능한 데 그 목적이 있다.Another object of the present invention is an outer frame for blocking between the girder of the upper part of the pier is made of aluminum light weight, there is no fear of corrosion, consisting of an aluminum frame and a sleeve, the sleeve is entered into the frame inside the case of temperature expansion and contraction The purpose of this is to freely stretch the temperature by screwing in and to connect the members simply by using the sleeve when connecting the members.

본 발명의 과제의 해결 수단은 지면에 고정되는 교각과; 상기 교각 상부에 설치되는 교량 받침 상부에 길이 방향으로 간격을 두고 설치된 거더와; 상기 거더 상부에 시공되어 차량이 소통하게 되는 상부슬라브와; 상기 거더의 하부 영역에 외장재조립장치로써 조립 유지되는 외장재패널로 이루어진 교량용 외장재 조립구조에 있어서, 상기 외장재조립장치는 거더 하부의 확장부에 결합되는 수직프레임과; 상기 수직프레임의 상부 양단에 경사연결부재로써 동일한 각도로 연결된 경사프레임과; 상기 수직프레임 하부 양단에 수직연결부재로써 수평으로 연결된 수평프레임으로 이루어진 조립 프레임; 및 상기 조립 프레임의 하부에 구비되고, 하부에 외장재패널이 설치되는 외장재조립부재를 포함하는 것을 특징으로 한다.Means for Solving the Problems of the Invention The pier is fixed to the ground; A girder installed at intervals in a longitudinal direction on an upper portion of the bridge bearing installed on the pier; An upper slab installed on the girder to communicate with the vehicle; In a bridge exterior assembly structure consisting of an exterior panel to be assembled and maintained in the lower region of the girder as an exterior assembly device, the exterior assembly device includes a vertical frame coupled to the extension of the lower girder; An inclined frame connected to the upper ends of the vertical frame at the same angle as the inclined connection member; An assembly frame composed of a horizontal frame horizontally connected as a vertical connection member at both ends of the vertical frame; And it is provided on the lower portion of the assembly frame, characterized in that it comprises an outer packaging material assembly member is installed on the lower panel.

본 발명에 따르면, 거더에 조립 프레임 고정설치시 거더에 손상이 발생되지 않도록 연결플레이트를 이용하여 손쉽게 장착이 가능하며, 이 경우 사면에 형성된 홈에 볼트 머리가 이동가능하게 삽입가능하여 필요한 위치에 맞추어 너트를 조이면 조립가능하고, 프레임 연결만으로 거더와 고정이 가능함에 따라 사용되는 부재가 적어 자재, 설치비가 절감되며 경량으로 교량에 미치는 영향이 적은 효과가 제공된다.According to the present invention, when the assembly frame is fixed to the girder can be easily mounted using a connecting plate to prevent damage to the girder, in this case, the bolt head is movable to be inserted into the groove formed on the slope to fit the required position When the nut is tightened, it can be assembled, and it can be fixed with the girder only by connecting the frame, so that the materials used are few, which saves material and installation cost, and provides light weight and low impact on the bridge.

또한, 본 발명의 외장재프레임은 재질이 알루미늄으로 가볍고 부식 우려가 없으며, 알루미늄 프레임 및 슬리이브로 이루어지며 프레임 내부로 슬리이브가 들어감으로써 온도 신축부의 경우 한쪽에 나사 체결하면, 자유롭게 온도신축이 가능하여 프레임의 변형을 방지해 구조체를 보호할 수 있는 효과가 제공된다.In addition, the exterior frame of the present invention is made of aluminum material is light and there is no fear of corrosion, consisting of an aluminum frame and a sleeve, and the sleeve enters into the frame in the case of the temperature expansion and contraction, if screwed to one side, freely stretchable temperature The effect of protecting the structure by preventing the deformation of the frame is provided.

도 1은 종래 외장재 설치구조에 따른 교량의 개략적인 단면 구성도.
도 2는 도 1의 요부 확대 단면 구성도.
도 3은 종래 외장재 설치구조의 다른 실시예를 도시한 단면 구성도.
도 4는 본 발명에 따른 교량용 외장재 설치구조의 제1실시예를 개략적으로 도시한 단면 구성도.
도 5는 도 4의 분해 사시도.
도 6은 본 발명에 따른 교량용 외장재 설치구조의 제1실시예에 대한 동작상태도.
도 7은 본 발명에 따른 교량용 외장재 설치구조의 제1실시예에 대한 다른 실시예를 도시한 구성도.
도 8은 본 발명에 따른 교량용 외장재 설치구조의 제2실시예를 도시한 구성도.
도 9는 도 8의 다른 실시예를 도시한 구성도.
1 is a schematic cross-sectional view of a bridge according to a conventional exterior mounting structure.
Figure 2 is an enlarged cross-sectional configuration of the main portion of FIG.
Figure 3 is a cross-sectional view showing another embodiment of the conventional exterior mounting structure.
Figure 4 is a schematic cross-sectional view showing a first embodiment of the bridge construction material mounting structure according to the present invention.
5 is an exploded perspective view of FIG. 4.
Figure 6 is an operating state of the first embodiment of the bridge construction material mounting structure according to the present invention.
Figure 7 is a block diagram showing another embodiment of the first embodiment of the bridge construction material mounting structure according to the present invention.
Figure 8 is a block diagram showing a second embodiment of the bridge construction material mounting structure according to the present invention.
9 is a block diagram showing another embodiment of FIG.

이하, 첨부된 도면을 참조로 발명을 실시하기 위한 구체적인 내용을 설명하면 다음과 같다.Hereinafter, with reference to the accompanying drawings will be described specific details for carrying out the invention.

도 4는 본 발명에 따른 교량용 외장재 설치구조의 제1실시예를 개략적으로 도시한 단면 구성도이고, 도 5는 도 4의 분해 사시도이고, 도 6은 본 발명에 따른 교량용 외장재 설치구조의 제1실시예에 대한 동작상태도이다.Figure 4 is a cross-sectional configuration diagram schematically showing a first embodiment of the bridge construction material mounting structure according to the present invention, Figure 5 is an exploded perspective view of Figure 4, Figure 6 is a bridge exterior mounting structure according to the invention It is an operation state diagram for the first embodiment.

도 4 내지 도 6에 도시된 바와 같이, 본 발명에 따른 교량용 외장재 설치구조는 지면에 하부가 설치되는 다수의 교각(10)과; 교각(10) 상부에 설치되는 교량 받침(20)과; 교량 받침(20) 상부에 길이 방향으로 간격을 두고 설치된 다수의 거더(30)와; 거더(30) 상부에 시공되어 차량이 소통하게 되는 상부슬라브(35)와; 상기 거더(30)의 하부 영역에 조립 프레임(60)과 외장재조립부재(90)로써 조립 유지되어 거더(30)의 하부와 측면을 감싸주게 되는 외장재패널(40)로 이루어진다.As shown in Figures 4 to 6, the bridge mounting structure according to the present invention includes a plurality of bridges 10, the lower portion is installed on the ground; A bridge bearing 20 installed on the pier 10; A plurality of girders 30 installed at intervals in the longitudinal direction on the bridge bearing 20; An upper slab 35 installed on the girder 30 to communicate with the vehicle; It consists of an exterior panel 40 which is assembled and maintained by the assembly frame 60 and the exterior material assembly member 90 in the lower region of the girder 30 to surround the bottom and the side of the girder 30.

상기 조립 프레임(60)은 거더(30) 하부의 확장부에 결합되는 수직프레임(62)과; 수직프레임(62)의 상부 양단에 경사연결부재(70)로써 동일한 각도로 연결된 경사프레임(64)과; 수직프레임(62) 하부 양단에 수직연결부재(80)로써 수평으로 연결된 수평프레임(66)으로 이루어진다. 이때, 수직프레임(62), 경사프레임(64) 및 수평프레임(66)은 볼트 머리부가 삽입되는 볼트머리삽입홈(63)이 연장 형성된 사각파이프 타입으로 이루어진다.The assembly frame 60 and the vertical frame 62 is coupled to the expansion portion of the lower girder 30; An inclined frame 64 connected to the upper ends of the vertical frame 62 at the same angle as the inclined connecting member 70; It consists of a horizontal frame 66 horizontally connected by a vertical connecting member 80 at both ends of the lower vertical frame (62). At this time, the vertical frame 62, the inclined frame 64 and the horizontal frame 66 is made of a square pipe type in which a bolt head insertion groove 63 into which the bolt head is inserted is extended.

상기 경사연결부재(70)는 수직프레임(62)과 경사프레임(64)의 각도와 동일한 각도를 유지하고, 수직프레임(62)과 경사프레임(64)의 전후면에 밀착되며, 경사장공(71)이 형성된 제1,2경사연결편(72)(73)과; 제1,2경사연결편(72)(73)과 동일한 각도를 유지하여 수직프레임(62)과 경사프레임(63)의 우측면에 밀착되고, 경사장공(71)이 형성된 전면연결편(74)과; 수직프레임(62)과 경사프레임(64)의 볼트머리삽입홈(63)에 머리가 삽입되고, 제1,2경사연결편(72)(73) 및 전면연결편(74)의 경사조절공(71)을 통하여 몸체가 삽입되어, 너트(75)로써 체결되어 제1,2경사연결편(72)(73) 및 전면연결편(74)을 고정시키기 위한 체결볼트(76)로 이루어진다.The inclined connection member 70 maintains the same angle as that of the vertical frame 62 and the inclined frame 64, is in close contact with the front and rear surfaces of the vertical frame 62 and the inclined frame 64, the inclined long hole 71 A first and second inclined connecting pieces (72) (73) formed thereon; Maintaining the same angle as the first and second inclined connection pieces 72 and 73 to be in close contact with the right side of the vertical frame 62 and the inclined frame 63, and having a sloped hole 71 formed therein; The head is inserted into the bolt head insertion groove (63) of the vertical frame (62) and the inclined frame (64), and the inclination adjusting hole (71) of the first and second inclined connection pieces (72) and (73) and the front connection piece (74). The body is inserted through, is fastened with a nut 75 is composed of a fastening bolt 76 for fixing the first and second inclined connection piece 72, 73 and the front connection piece (74).

상기 수직연결부재(80)는 수직프레임(62)과 수평프레임(66)의 전후면에 밀착되고, 수직 및 수평의 조절장공(81)이 형성된 "ㄴ"자형의 제1,2수직연결편(82)(83)과; 수직프레임(62)과 수평프레임(66)의 볼트머리삽입홈(63)에 머리가 삽입되고, 제1,2수직연결편(82)(83)의 조절장공(81)을 통하여 몸체가 삽입되며, 너트(85)로써 체결되어 제1,2수직연결편(82)(83)을 고정시키기 위한 체결볼트(86)로 이루어진다.The vertical connecting member 80 is in close contact with the front and rear surfaces of the vertical frame 62 and the horizontal frame 66, the first and second vertical connecting piece 82 of the "b" shaped with the vertical and horizontal adjustment holes 81 are formed. 83; The head is inserted into the bolt head insertion groove 63 of the vertical frame 62 and the horizontal frame 66, and the body is inserted through the adjustment hole 81 of the first and second vertical connecting pieces 82 and 83. It is fastened with a nut 85 is made of a fastening bolt 86 for fixing the first and second vertical connecting pieces (82, 83).

상기 외장재조립부재(90)는 외장재패널(40)과 수평프레임(66)의 볼트머리삽입홈(63)에 수직으로 삽입된 다수의 삽입구(91)와; 볼트머리삽입홈(63)을 관통하여 체결 고정되어 외장재패널(40)을 체결 고정하기 위한 고정스크류(92)로 이루어진다. 이때, 삽입구(91)에는 돌기(91a)가 형성되고, 돌기(91a)에는 커버(93)가 분리 가능하게 결합되어 고정스크류(92)를 은폐시키게 된다. The exterior material assembly member 90 includes a plurality of insertion holes 91 vertically inserted into the exterior panel panel 40 and the bolt head insertion groove 63 of the horizontal frame 66; Fastening and fixing through the bolt head insertion groove 63 is made of a fixing screw 92 for fastening and fixing the exterior panel 40. In this case, the protrusion 91a is formed in the insertion hole 91, and the cover 93 is detachably coupled to the protrusion 91a to conceal the fixing screw 92.

한편, 도 7은 본 발명에 따른 교량용 외장재 설치구조의 제1실시예에 대한 다른 실시예를 도시한 구성도로서, 이는 도 4 내지 도 6에 도시된 교량용 외장재 설치구조의 제1실시예에 대한 외장재조립부재의 다른 실시예를 도시한 것으로, 동일한 구조에 대해서는 동일 번호를 사용하기로 한다.On the other hand, Figure 7 is a configuration diagram showing another embodiment of the first embodiment of the bridge mounting material mounting structure according to the present invention, which is a first embodiment of the bridge mounting material shown in Figures 4 to 6 Another embodiment of the exterior material assembly member for showing the same number will be used for the same structure.

상기 외장재조립부재(90)는 수평프레임(66)의 볼트머리삽입홈(63)에 형성된 나사부(94a)가 형성된 체결구(94)로써 외장재패널(40)을 체결 고정하게 된다. The exterior member assembly member 90 is fastened to the exterior panel 40 by a fastener 94 having a threaded portion 94a formed in the bolt head insertion groove 63 of the horizontal frame 66.

이때, 체결구(94)는 나사부(94a)가 외장재패널(40)을 통과하고 볼트머리삽입홈(63)에 강제로 박혀 고정되어 외장재패널(40)을 조립하게 된다.At this time, the fastener 94 is a screw portion 94a passes through the exterior panel 40 and is forcibly fixed in the bolt head insertion groove 63 to assemble the exterior panel 40.

또한, 도 8은 본 발명에 따른 교량용 외장재 설치구조의 제2실시예를 도시한 구성도이고, 도 9는 도 8의 다른 실시예를 도시한 구성도이다.In addition, Figure 8 is a block diagram showing a second embodiment of the bridge construction material mounting structure according to the present invention, Figure 9 is a block diagram showing another embodiment of FIG.

도 8에 도시된 바와 같이, 본 발명에 따른 교량용 외장재 설치구조는 교각(10) 상부에 구비되는 교량 받침(20) 상부에 길이 방향으로 연결된 다수의 거더(30) 사이에 설치되어, 온도의 변화에 따른 신축이 가능한 구조로 거더(30)의 연결 부위를 차단하기 위한 외장프레임부재(95)에 관한 것이다.As shown in FIG. 8, the bridge exterior installation structure according to the present invention is installed between a plurality of girders 30 connected in a longitudinal direction to an upper portion of a bridge bearing 20 provided on an upper portion of a bridge 10, thereby maintaining a temperature. It relates to an outer frame member 95 for blocking the connection portion of the girder 30 in a structure capable of stretching according to the change.

이때, 거더(30)는 온도에 따른 변화를 고려하여 교각(10) 사이에 길이 방향으로 간격을 유지하여 연결 설치되고, 이 연결부위에 상기 외장재프레임부재(95)를 약 10m 간격으로 설치하여 연결부위를 은폐시키게 된다.At this time, the girder 30 is installed in connection with maintaining the interval in the longitudinal direction between the piers 10 in consideration of the change according to the temperature, and installed by connecting the outer frame member (95) at about 10m intervals in this connection portion It will conceal the site.

상기 외장재프레임부재(95)는 외주면에 볼트머리삽입홈(96a)이 형성되고, 내부에 사각의 끼움공(96b)이 형성된 외장재프레임(96)(97)과; 외장재프레임(96)(97)의 끼움공(96b)에 간격을 유지하여 삽입되어 스크류(98)로써 체결 고정되는 슬리이브(99)로 이루어져 온도의 변화에 따라 신축할 수 있는 공간이 마련된다.The outer frame member (95) is a bolt head insertion groove (96a) is formed on the outer circumferential surface, the outer frame (96, 97) formed with a square fitting hole (96b) therein; It is made of a sleeve 99 is inserted and maintained in the fitting hole (96b) of the exterior frame frame 96, 97 is fastened and fixed by the screw 98 is provided with a space that can be stretched in accordance with the change in temperature.

도 9는 도 8의 다른 실시예로서, 이는 슬리이브(99)를 연통되게 십자형으로 연결하게 되고, 이 십자형의 슬리이브(99)에 외장재프레임(96)(97)을 각각 삽입연결하는 구조로 이루어져 온도의 변화에 따라 신축할 수 있도록 한다.FIG. 9 is another embodiment of FIG. 8, which is connected to the sleeve 99 in a cross shape to communicate with each other, and is configured to insert and connect the exterior frame 96 and 97 to the cross-shaped sleeve 99, respectively. It can be stretched according to the change of temperature.

이와 같이 구성된 본 발명에 따른 교량용 외장재에 대한 조립 상태를 설명하면, 도 4 내지 도 6에서와 같이 교각(10) 상부에 설치된 교량 받침(20) 상부에 길이 방향으로 간격을 유지하여 설치되는 다수의 거더(30)의 하부 영역에 조립 프레임(60)과 외장재조립부재(90)로써 외장재패널(40)을 설치하여 거더(30)의 하부 및 측면을 감싸주게 된다.Referring to the assembly state for the bridge exterior material according to the present invention configured as described above, as shown in Figures 4 to 6, a plurality of installed while maintaining the interval in the longitudinal direction on the bridge support 20 installed on the top of the bridge 10 In the lower region of the girder 30, the exterior panel 40 is installed as the assembly frame 60 and the exterior assembly assembly member 90 to surround the bottom and side surfaces of the girder 30.

이를 개략적으로 설명하면, 조립 프레임(60)을 구성하는 수평프레임(66)에 수직으로 수직연결부재(80)로써 거더(30)의 확장부 폭에 적절하게 수평프레임(66)의 양단에 수직프레임(66)을 체결 고정하게 된다. If this is schematically described, the vertical frame at both ends of the horizontal frame 66 as appropriate for the width of the extension of the girder 30 as a vertical connection member 80 perpendicular to the horizontal frame 66 constituting the assembly frame 60 The 66 is fastened and fixed.

즉, 수평프레임(66) 양단에 거더(30)의 확장부 폭에 적절하게 수평프레임(66)의 수직프레임(62)을 수직으로 일치시킨 다음, 수평프레임(66)과 수직프레임(62)의 볼트머리삽입홈(63)에 체결볼트(86)의 머리부를 순차적으로 삽입시키게 된다.That is, the vertical frame 62 of the horizontal frame 66 vertically matches the width of the girder 30 at both ends of the horizontal frame 66, and then the horizontal frame 66 and the vertical frame 62 The head of the fastening bolt 86 is sequentially inserted into the bolt head insertion groove 63.

그 다음으로 체결볼트(86)를 통하여 "ㄴ"자 형으로 이루어진 제1,2수직연결편(82)(83)의 조절장공(81)을 순차적으로 삽입한 다음, 체결볼트(86)에 너트(85)를 순차적으로 체결하면, 제1,2수직연결편(82)(83)의 전후면에 제1,2수직연결편(82)(83)이 체결 고정된다.Next, through the fastening bolt 86, the insertion holes 81 of the first and second vertical connecting pieces 82 and 83 made of "B" shape are sequentially inserted, and then the nut (to the fastening bolt 86) is inserted. When the 85 is sequentially fastened, the first and second vertical connecting pieces 82 and 83 are fastened and fixed to the front and rear surfaces of the first and second vertical connecting pieces 82 and 83.

이러한 상태에서 수직프레임(62) 상단과 경사프레임(64) 하단을 경사지게 밀착시킨 다음, 수직프레임(62)과 경사프레임(64)의 볼트머리삽입홈(63)을 통하여 체결볼트(76)의 머리부를 순차적으로 끼우고, 제1,2경사연결편(72)(73)의 경사조절공(71)을 순차적으로 삽입하면, 제1,2경사연결편(72)(73)의 경사조절공(71)이 체결볼트(76)에 삽입되어 수직프레임(62)과 경사프레임(64)의 연결부위에 제1,2경사연결편(72)(73)이 밀착된다.In such a state, the top of the vertical frame 62 and the bottom of the inclined frame 64 are inclined in close contact with each other, and then the head of the fastening bolt 76 through the bolt head insertion groove 63 of the vertical frame 62 and the inclined frame 64. Part by inserting sequentially, the inclination adjustment hole 71 of the first and second inclined connection piece 72, 73 sequentially inserted, the inclination control hole 71 of the first and second inclined connection piece 72, 73 The first and second inclined connection pieces 72 and 73 are closely attached to the connection portion of the vertical frame 62 and the inclined frame 64 by being inserted into the fastening bolt 76.

그 다음으로 체결볼트(76)에 너트(75)를 순차적으로 체결하면, 수직프레임(62) 상단과 경사프레임(64) 하단에 제1,2경사연결편(72)(73)이 고정된다.Next, when the nut 75 is sequentially fastened to the fastening bolt 76, the first and second inclined connection pieces 72 and 73 are fixed to the top of the vertical frame 62 and the bottom of the inclined frame 64.

이러한 상태에서 제1,2경사연결편(72)(73) 사이의 수직프레임(62)과 경사프레임(64)의 볼트머리삽입홈(63)에 체결볼트(76)의 머리부를 순차적으로 끼운 다음, 이에 제1,2경사연결편(72)(73)과 동일한 각도를 유지하여 형성된 전면연결편(74)의 경사조절공(71)을 삽입한 다음, 이에 너트(75)를 체결하면, 전면연결편(74)이 체결 고정된다. 따라서, 양단에 거더(30)의 확장부 폭에 적절하게 조립 프레임(60)이 삽입되어 체결 고정된다.In this state, the heads of the fastening bolts 76 are sequentially inserted into the vertical frame 62 between the first and second inclined connection pieces 72 and 73 and the bolt head insertion groove 63 of the inclined frame 64. Insert the inclination adjusting hole 71 of the front connecting piece 74 formed by maintaining the same angle as the first and second inclined connecting pieces 72 and 73, and then tighten the nut 75, the front connecting piece 74 ) Is fastened and fixed. Therefore, the assembly frame 60 is inserted and fastened to both ends of the girder 30 in an appropriate width.

그 다음으로 수평프레임(66)의 볼트머리삽입홈(63)을 통하여 삽입구(91)를 순차적으로 삽입시키면서 외장재패널(40)을 고정한 다음, 이 삽입구(91)를 통하고 볼트머리삽입홈(63)을 관통하여 고정스크류(92)를 체결하여 외장재패널(40)을 고정시키고, 삽입구(91)의 돌기(91a)에 외부에서 커버(93)를 결합시키면, 고정스크류(92)가 은폐되면서 외장재패널(40)이 설치되어 거더(30)의 하부 및 측면을 차단하여 손상을 방지하는 동시에 은폐시키게 된다.Next, the exterior panel 40 is fixed while the insertion holes 91 are sequentially inserted through the bolt head insertion grooves 63 of the horizontal frame 66, and then through the insertion holes 91, the bolt head insertion grooves 63 are inserted. When the fixing screw 92 is fastened to fix the exterior panel 40, and the cover 93 is coupled to the protrusion 91a of the insertion hole 91 from the outside, the fixing screw 92 is concealed and the exterior member is concealed. Panel 40 is installed to block the bottom and side of the girder 30 to prevent damage and at the same time concealed.

한편, 도 7은 교량용 외장재 설치구조의 제1실시예에 대한 다른 실시예를 도시한 구성도로서, 이는 도 4 내지 도 6에 도시된 교량용 외장재 설치구조의 제1실시예에 대한 외장재조립부재의 다른 실시예를 도시한 것이다.On the other hand, Figure 7 is a configuration diagram showing another embodiment of the first embodiment of the bridge construction material mounting structure, which is an assembly of the exterior material for the first embodiment of the bridge mounting material shown in Figures 4 to 6 Another embodiment of the member is shown.

이에 대한 조립상태를 개략적으로 설명하면, 체결구(94)의 나사부(94a)를 통하여 수평프레임(66)의 볼트머리삽입홈(63)에 강제로 박아 체결 고정하여 간편하게 외장재패널(40)을 고정시키게 된다.When the assembly state is briefly described, through the screw portion 94a of the fastener 94, it is forcibly driven into the bolt head insertion groove 63 of the horizontal frame 66 and fastened to fix the exterior panel 40 easily. Let's go.

그리고, 도 8은 본 발명에 따른 교량용 외장재 설치구조의 제2실시예를 도시한 구성도이고, 도 9는 도 8의 다른 실시예를 도시한 구성도이다.8 is a block diagram showing a second embodiment of the bridge construction material mounting structure according to the present invention, Figure 9 is a block diagram showing another embodiment of FIG.

먼저, 도 8에서와 같이 교량용 외장재 설치구조는, 교각(10) 상부에 구비되는 교량 받침(20) 상부에 길이 방향으로 연결된 다수의 거더(30) 사이에 설치되어 거더(30)의 연결 부위를 차단하기 위한 외장프레임부재(95)에 관한 것이다.First, as shown in FIG. 8, the bridge mounting structure for the bridge is installed between a plurality of girders 30 connected in a longitudinal direction to an upper portion of the bridge receiving portion 20 provided on the bridge 10, and thus connecting portions of the girders 30. It relates to an outer frame member 95 for blocking the.

이에 대한 조립과정을 설명하면, 사각파이프로 이루어진 외장재프레임(96)(97)의 끼움공(96b)을 통하여 슬리이브(99)를 간격이 유지되게 삽입하게 된다.Referring to the assembly process for this, the sleeve 99 through the fitting hole (96b) of the exterior frame frame 96, 97 made of a square pipe is inserted to maintain the gap.

그런 다음, 외장재프레임(96)(97) 외주면의 볼트머리삽입홈(96a)을 통하여 스크류(98)를 체결하여 외장재프레임(96)에 삽입된 슬리이브(99)를 고정시키면, 온도의 변화에 따라 신축할 수 있는 공간이 마련된다.Then, by fastening the screw 98 through the bolt head insertion groove 96a of the outer circumferential surface of the outer frame 96, 97, to fix the sleeve 99 inserted into the outer frame 96, the change in temperature Therefore, a space for expansion is provided.

그리고, 도 9는 도 8의 다른 실시예로서, 이는 슬리이브(99)를 연통되게 십자형으로 연결하게 되고, 이 십자형의 슬리이브(99)에 외장재프레임(96)(97)을 삽입하여 연결하는 구조로 이루어져 온도의 변화에 따라 신축할 수 있도록 구성한 것이다.And, Figure 9 is another embodiment of Figure 8, which connects the sleeve 99 in communication with the cross, and inserts and connects the outer frame 96, 97 to the cross sleeve (99) It consists of a structure that can be stretched according to the change of temperature.

10 : 교각 20 : 교량 받침
30 : 거더 35 : 상부슬라브
40 : 외장재패널 60 : 조립 프레임
62 : 수직프레임 64 : 경사프레임
66 : 수평프레임 70 : 경사연결부재
71 : 경사장공 72,73 : 제1,2경사연결편
74 : 전면연결편 75,85 : 너트
76,86 : 체결볼트 80 : 수직연결부재
81 : 조절장공 82,83 : 제1,2수직연결편
90 : 외장재조립부재 91 : 삽입구
91a : 돌기 92 : 고정스크류
93 : 커버 94 : 체결구
94a : 나사부 95 : 외장재프레임부재
96,97 : 외장재프레임 96a : 볼트머리삽입홈
96b : 끼움공 98 : 스크류
99 : 슬리이브
10: pier 20: bridge bearing
30: girder 35: upper slab
40: exterior panel 60: assembly frame
62: vertical frame 64: inclined frame
66: horizontal frame 70: inclined connection member
71: inclined long hole 72,73: 1st, 2nd inclined connection piece
74: front connection piece 75,85: nut
76,86: Fastening bolt 80: Vertical connecting member
81: adjustment hole 82,83: 1st, 2nd vertical connection piece
90: exterior material assembly member 91: insertion hole
91a: protrusion 92: fixing screw
93: cover 94: fastener
94a: thread 95: outer frame member
96,97: Exterior frame 96a: Bolt head insertion groove
96b: insertion hole 98: screw
99: sleeve

Claims (7)

지면에 설치되는 교각(10)과; 상기 교각(10) 상부에 설치되는 교량 받침(20) 상부에 길이 방향으로 간격을 두고 설치된 거더(30)와; 상기 거더(30) 상부에 시공되어 차량이 소통하게 되는 상부슬라브(35)와; 상기 거더(30)의 하부 영역에 조립프레임(60)과 외장재조립부재(90)로써 조립 유지되는 외장재패널(40)로 이루어진 교량용 외장재 설치구조에 있어서,
상기 조립 프레임(60)은
거더(30) 하부의 확장부에 결합되는 수직프레임(62)과;
상기 수직프레임(62)의 상부 양단에 경사연결부재(70)로써 동일한 각도로 연결된 경사프레임(64)과;
상기 수직프레임(62) 하부 양단에 수직연결부재(80)로써 수평으로 연결된 수평프레임(66)으로 구성한 것을 특징으로 하는 교량용 외장재 설치구조.
A piers 10 installed on the ground; A girder 30 provided at intervals in a lengthwise direction on an upper portion of the bridge receiving portion 20 installed on the pier 10; An upper slab 35 installed on the girder 30 to communicate with the vehicle; In the bridge mounting material installation structure consisting of the exterior panel 40, which is assembled and maintained as the assembly frame 60 and the exterior material assembly member 90 in the lower region of the girder 30,
The assembly frame 60 is
A vertical frame 62 coupled to an extension of the lower part of the girder 30;
An inclined frame 64 connected to the upper ends of the vertical frame 62 at the same angle as the inclined connection member 70;
Bridge construction material installation structure, characterized in that consisting of a horizontal frame 66 horizontally connected as a vertical connection member 80 at both ends of the lower vertical frame (62).
제1항에 있어서, 상기 경사연결부재(70)는
상기 수직프레임(62)과 경사프레임(64)과 동일한 각도를 유지하고, 수직프레임(62)과 경사프레임(64)의 전후면에 밀착되며, 경사장공(71)이 형성된 제1,2경사연결편(72)(73)과;
상기 제1,2경사연결편(72)(73)과 동일한 각도를 유지하여 수직프레임(62)과 경사프레임(63)의 우측면에 밀착되고, 경사장공(71)이 형성된 전면연결편(74)과;
상기 수직프레임(62)과 경사프레임(64)의 볼트머리삽입홈(63)에 머리가 삽입되고, 제1,2경사연결편(72)(73)과 전면연결편(74)의 경사조절공(71)을 통하여 몸체가 삽입되어, 너트(75)로써 체결되어 제1,2경사연결편(72)(73)과 제1,2경사연결편(72)(73) 사이에 전면연결편(74)을 고정시키기 위한 체결볼트(76)로 구성된 것을 특징으로 하는 교량용 외장재 설치구조.
According to claim 1, wherein the inclined connecting member 70
Maintaining the same angle as the vertical frame 62 and the inclined frame 64, in close contact with the front and rear surfaces of the vertical frame 62 and the inclined frame 64, the first and second inclined connecting piece 71 is formed (72) (73);
A front connection piece 74 which is in close contact with the right side surfaces of the vertical frame 62 and the inclination frame 63 while maintaining the same angle as the first and second inclined connection pieces 72 and 73, and has an inclined long hole 71 formed therein;
The head is inserted into the bolt head insertion groove (63) of the vertical frame (62) and the inclined frame (64), and the inclination adjusting hole (71) of the first and second inclined connection pieces (72) and (73) and the front connection piece (74). The body is inserted through the nut, and fastened with a nut 75 to fix the front connection piece 74 between the first and second slope connection pieces 72 and 73 and the first and second slope connection pieces 72 and 73. Bridge mounting material installation structure, characterized in that consisting of fastening bolts (76).
제1항에 있어서, 상기 수직연결부재(80)는
상기 수직프레임(62)과 수평프레임(66)의 전후면에 밀착되고, 수직 및 수평의 조절장공(81)이 형성된 "ㄴ"자형의 제1,2수직연결편(82)(83)과;
상기 수직프레임(62)과 수평프레임(66)의 볼트머리삽입홈(63)에 머리가 삽입되고, 제1,2수직연결편(82)(83)의 조절장공(81)을 통하여 몸체가 삽입되어, 너트(85)로써 체결되어 제1,2수직연결편(82)(83)을 고정시키기 위한 체결볼트(86)로 구성된 것을 특징으로 하는 교량용 외장재 설치구조.
The method of claim 1, wherein the vertical connecting member 80
First and second vertical connection pieces 82 and 83 of a “b” shape in close contact with the front and rear surfaces of the vertical frame 62 and the horizontal frame 66 and having vertical and horizontal adjustment holes 81 formed therein;
The head is inserted into the bolt head insertion groove 63 of the vertical frame 62 and the horizontal frame 66, and the body is inserted through the adjustment hole 81 of the first and second vertical connecting pieces 82 and 83. Is fastened with a nut 85, the first and second vertical connecting pieces (82, 83), characterized in that consisting of a fastening bolt 86 for fixing the bridge structure installation structure.
제1항에 있어서, 상기 외장재조립부재(90)는
외장재패널(40)과 수평프레임(66)의 볼트머리삽입홈(63)에 수직으로 삽입된 되고, 돌기(91a)가 형성된 삽입구(91)와;
상기 볼트머리삽입홈(63)을 관통하여 체결 고정되어 외장재패널(40)을 체결 고정하기 위한 고정스크류(92)와;
상기 삽입구(91)의 돌기(91a)에 분리 가능하게 결합되어 고정스크류(92)를 은폐시키기 위한 커버(93)로 구성된 것을 특징으로 하는 교량용 외장재 설치구조.
The method of claim 1, wherein the exterior material assembly member 90
An insertion hole 91 inserted vertically into the bolt head insertion groove 63 of the exterior panel 40 and the horizontal frame 66 and having a protrusion 91a formed thereon;
A fixing screw 92 for fastening and fixing through the bolt head insertion groove 63 to fasten and fix the exterior panel 40;
The outer cover mounting structure for the bridge, characterized in that consisting of a cover (93) for detachably coupled to the projection (91a) of the insertion port (91) for concealing the fixing screw (92).
제4항에 있어서, 상기 외장재조립부재(90)는
상기 수평프레임(66)의 볼트머리삽입홈(63)에 나사부(94a)로써 체결하여 외장재패널(40)을 체결 고정하기 위한 체결구(94)로 구성된 것을 특징으로 하는 교량용 외장재 설치구조.
The method of claim 4, wherein the outer material assembly member 90
Bridge mounting structure for the bridge, characterized in that consisting of a fastener (94) for fastening and fixing the exterior panel 40 by fastening with a screw portion (94a) to the bolt head insertion groove (63) of the horizontal frame (66).
제1항에 있어서, 상기 거더(30) 사이의 연결부위에 온도 변화에 따라 신축 가능하도록 외장재프레임부재(95)를 설치하되,
상기 외장재프레임부재(95)는
외주면에 볼트머리삽입홈(96a)이 형성되고, 내부에 사각의 끼움공(96b)이 형성된 외장재프레임(96)(97)과;
상기 외장재프레임(96)(97)의 끼움공(96b)에 간격을 유지하여 삽입되어 스크류(98)로써 체결 고정되는 슬리이브(99)로 구성된 것을 특징으로 하는 교량용 외장재 설치구조.
According to claim 1, wherein the exterior frame member 95 is installed on the connection between the girders 30 so as to be stretchable according to the temperature change,
The exterior frame member 95 is
A bolt head insertion groove 96a formed on an outer circumferential surface thereof, and exterior frame frames 96 and 97 having a rectangular fitting hole 96b formed therein;
Bridge mounting structure, characterized in that consisting of a sleeve (99) which is inserted and maintained at intervals in the fitting hole (96b) of the exterior frame frame (96) (97) is fastened and fixed by a screw (98).
제6항에 있어서, 상기 외장재프레임부재(95)는
십자형으로 연통되게 연결된 슬리이브(99)에, 상기 외장재프레임(96)(97)의 끼움공(96b)를 교차되게 삽입 연결한 것을 특징으로 하는 교량용 외장재 설치구조.
The method of claim 6, wherein the outer frame member (95)
The bridge mounting structure for the bridge, characterized in that the cross-connected to the sleeve (99) connected in communication, the insertion hole (96b) of the exterior frame frame (96) (97) to cross.
KR1020100071851A 2010-07-26 2010-07-26 Under exterior panel assembly structure for bridge KR101031287B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100071851A KR101031287B1 (en) 2010-07-26 2010-07-26 Under exterior panel assembly structure for bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100071851A KR101031287B1 (en) 2010-07-26 2010-07-26 Under exterior panel assembly structure for bridge

Publications (1)

Publication Number Publication Date
KR101031287B1 true KR101031287B1 (en) 2011-04-29

Family

ID=44050598

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100071851A KR101031287B1 (en) 2010-07-26 2010-07-26 Under exterior panel assembly structure for bridge

Country Status (1)

Country Link
KR (1) KR101031287B1 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000320004A (en) 1999-05-14 2000-11-21 Sekisui Chem Co Ltd Building unit, its manufacture and unit building
KR100373783B1 (en) 2000-11-08 2003-03-04 이상식 A temporary bracket for construction of precast concrete beam bridge and the temporary work method using the same
KR100764418B1 (en) 2007-07-11 2007-10-05 (주) 케이 이엔씨 Under exterior panel set up structure for bridge
KR100891468B1 (en) 2008-11-10 2009-04-01 서현철 Assembling structure of bridge outer wall

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000320004A (en) 1999-05-14 2000-11-21 Sekisui Chem Co Ltd Building unit, its manufacture and unit building
KR100373783B1 (en) 2000-11-08 2003-03-04 이상식 A temporary bracket for construction of precast concrete beam bridge and the temporary work method using the same
KR100764418B1 (en) 2007-07-11 2007-10-05 (주) 케이 이엔씨 Under exterior panel set up structure for bridge
KR100891468B1 (en) 2008-11-10 2009-04-01 서현철 Assembling structure of bridge outer wall

Similar Documents

Publication Publication Date Title
US20170234007A1 (en) Holeless Curtain Wall Mullion Connection
US20110167743A1 (en) Curtain wall system and method of installing the system
KR102021487B1 (en) A Soundproofing panel fixing structure for soundproof tunnel
JP3160565U (en) Installation structure of solar panel mount
KR20200107153A (en) Sound and earthquake proofed tunnel with drain-proof function and construction method of the same
KR101031287B1 (en) Under exterior panel assembly structure for bridge
KR101590093B1 (en) Mounting apparatus for open-joint type finishing panel
KR100891468B1 (en) Assembling structure of bridge outer wall
KR101296429B1 (en) Curtain wall unit unitized aluminum
KR20100040420A (en) Establishment structure of building
KR101567301B1 (en) Footstool Installation Structure
KR100893324B1 (en) A frame structure for wire netting fixed
KR20200093107A (en) A Louver system of RC-type Apartment and its construction method
KR102340863B1 (en) Soundproof tunnel and construction method thereof
KR102633364B1 (en) Full detachable maintenance transparent soundproof wall using load transfer prevention device
KR200404105Y1 (en) A external panel assembly of bridge
CN216475779U (en) Screw and anchor bar combined embedded part system of unit curtain wall
KR102655207B1 (en) Soundproof tunnel with roof panel leak prevention structure
KR102441790B1 (en) membrane breakage preventing Horizontal assembly system and assembly method
JP4679473B2 (en) roof
KR102527150B1 (en) A deck road system with a free planar shape and improved walking environment
KR200211018Y1 (en) Exterior bridge attachment mechanism
JP4456283B2 (en) Mounting structure for pier drain pipe
JP4038086B2 (en) Bracing unit mounting structure
KR100674563B1 (en) A simplicity equipment on the road

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20140228

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20150225

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20160202

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20170412

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20190415

Year of fee payment: 9