KR100968518B1 - Construction method of reinforced green retaining wall - Google Patents

Construction method of reinforced green retaining wall Download PDF

Info

Publication number
KR100968518B1
KR100968518B1 KR1020100007894A KR20100007894A KR100968518B1 KR 100968518 B1 KR100968518 B1 KR 100968518B1 KR 1020100007894 A KR1020100007894 A KR 1020100007894A KR 20100007894 A KR20100007894 A KR 20100007894A KR 100968518 B1 KR100968518 B1 KR 100968518B1
Authority
KR
South Korea
Prior art keywords
pillar
retaining wall
slope
reinforced concrete
anchor
Prior art date
Application number
KR1020100007894A
Other languages
Korean (ko)
Inventor
이순호
Original Assignee
주식회사 경호엔지니어링 종합건축사사무소
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 경호엔지니어링 종합건축사사무소 filed Critical 주식회사 경호엔지니어링 종합건축사사무소
Priority to KR1020100007894A priority Critical patent/KR100968518B1/en
Application granted granted Critical
Publication of KR100968518B1 publication Critical patent/KR100968518B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0208Gabions
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01CPLANTING; SOWING; FERTILISING
    • A01C1/00Apparatus, or methods of use thereof, for testing or treating seed, roots, or the like, prior to sowing or planting
    • A01C1/04Arranging seed on carriers, e.g. on tapes, on cords ; Carrier compositions
    • A01C1/044Sheets, multiple sheets or mats
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0266Retaining or protecting walls characterised by constructional features made up of preformed elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/13Geometrical or physical properties having at least a mesh portion
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Abstract

PURPOSE: A construction method for a reinforced vegetative retaining wall is provided to form a vegetative space over the entire or part of the front side of a retaining wall and secure structural stability. CONSTITUTION: A construction method for a reinforced vegetative retaining wall is as follows. A column form is installed on the front side of a slope(S) and column bars(11) are arranged and column concrete(12) is placed so that reinforced concrete columns(10) are installed at regular intervals along the slope. A vegetative mat(31) and a guard net(32) are fixed to an anchor(20) and vegetation soil(41) is filled and compacted between the slope and the vegetative mat.

Description

강화 녹화옹벽 시공방법{Construction method of reinforced green retaining wall}Construction method of reinforced green retaining wall

본 발명은 깎기 또는 쌓기 비탈면이나 호안 비탈면에 시공되는 옹벽에 관한 것으로서, 비탈면에 철근콘크리트기둥을 시공하고 철근콘크리트기둥 사이를 식생공간으로 구성한 옹벽의 바람직한 시공방법에 관한 것이다.
The present invention relates to a retaining wall that is constructed on a cutting or stacking slope or a lakeside slope, and relates to a preferable method for constructing a retaining wall constructed of vegetation space between a reinforced concrete column and a reinforced concrete column.

둑, 호안(護岸), 깎기(절토), 쌓기(성토) 등의 비탈면(법면)의 붕괴를 방지하기 위해 비탈면 보호공사를 실시한다. 비탈면 보호공사에는 비탈면의 경사도에 따라 다양한 방법이 있다.A slope protection work is carried out to prevent the collapse of slopes such as banks, banks, cuts, and piles. There are various methods of slope protection, depending on the slope of the slope.

급경사의 깎기 비탈면의 경우에는 소일네일, 어스앵커, 락볼트 등의 비탈면 보강공으로 비탈면을 안정화시킨 후에 격자블록으로 보호하거나 씨앗뿜어붙이기 등으로 보호한다. 격자블록 보호방식은 비탈면 보호효과에서 우수하다는 장점이 있으나, 블록이 커서 시공이 어렵고 급비탈면에 시공하기 때문에 블록 내 공간에 복토 후 식재할 경우 대부분 유실되는 문제가 있다. 씨앗뿜어붙이기 방식은 유기질토와 안정액, 씨앗을 혼합하여 비탈면에 취부하는 방식으로 전면을 녹화할 수 있다는 장점이 있으나, 호우시 쉽게 유실될 뿐만 아니라 갈라짐 현상이 심하고 용수가 많은 곳은 적용하기 곤란하다는 단점이 있다.For steep slopes, the slopes are stabilized with slope slope reinforcements such as nail nails, earth anchors, and rock bolts, and then protected with a grid block or seed spraying. Lattice block protection method has the advantage of excellent slope protection effect, but because the block is large construction is difficult to install on the steep slope, there is a problem that is mostly lost when planting in the space in the block after cover. The seed spraying method has the advantage of recording the whole surface by mixing organic soil, stabilizer, and seed on the slope, but it is not only easy to be lost during heavy rain, but also has severe cracking and water. There are disadvantages.

기울기가 약간 급한 쌓기 비탈면의 경우에는 통상 블록쌓기, 돌쌓기 또는 보강토옹벽으로 시공하나, 이들 방법들은 공사비가 비싸고 녹화가 어렵다는 문제가 있다.Stacking slopes with a slight slope are usually constructed with block stacking, stone stacking or reinforcement soil walls, but these methods are expensive and difficult to green.

경사가 급한 비탈면을 지닌 저수호안, 수충부, 만곡부의 호안 비탈면의 경우에는 식생블록이나 돌망태옹벽으로 시공한다. 식생블록 시공방식은 홍수시 이탈 및 단차발생이 심하여 이를 방지하고자 중량이 무거운 것을 사용해야 하기 때문에 고가의 자재와 고가의 장비를 이용해야 하는 등 공사비가 비싸다는 단점이 있다. 돌망태옹벽 시공방식은 채움돌 사이의 연결구조가 취약하고 국부적인 배부름 현상이 발생하기 쉽다는 단점이 있다.
Reservoir slopes with sloping slopes, ridges, and curved slopes should be constructed with vegetation blocks or gabion retaining walls. The vegetation block construction method has a disadvantage in that the construction cost is high, such as the use of expensive materials and expensive equipment, because heavy weight should be used in order to prevent the departure and step difference during flooding. The gabion retaining wall construction method has a disadvantage in that the connection structure between the filling stones is vulnerable, and local filling phenomenon is likely to occur.

본 발명은 상기한 종래 비탈면 보호공사의 문제를 개선하고자 개발된 것으로서 다음과 같은 기술적 과제를 갖는다.The present invention has been developed in order to improve the problems of the above-described conventional slope protection work has the following technical problems.

첫째, 본 발명은 전면 전체 또는 일부를 식생공간으로 구현하면서도 구조적으로 안정적인 비탈면 보호공사 방법을 제공하고자 한다.First, the present invention is to provide a method for structurally stable slope protection work while implementing the entire or part of the front surface as vegetation space.

둘째, 깎기 또는 쌓기 비탈면은 물론 호안 비탈면 등 다양한 비탈면에 범용적으로 적용할 수 있는 비탈면 보호공사 방법을 제공하고자 한다.Second, to provide a slope protection construction method that can be applied to a variety of slopes, such as shaved or stacked slopes, as well as shore slopes.

셋째, 비탈면의 굴곡구간에 유연하게 대응할 수 있는 비탈면 보호공사 방법을 제공하고자 한다.Third, to provide a slope protection method that can flexibly respond to the bent section of the slope.

넷째, 거푸집 설치 및 콘크리트 공사를 간단하게 진행할 수 있는 비탈면 보호공사 방법을 제공하고자 한다.
Fourth, to provide a slope protection work method that can easily proceed with the formwork and concrete construction.

상기한 기술적 과제를 해결하기 위해 본 발명은, 안정화된 비탈면 전면에 기둥거푸집을 설치하고 기둥철근을 배근하고 기둥콘크리트를 타설하는 과정을 통해 철근콘크리트기둥을 비탈면을 따라 띄엄띄엄 시공하되 기둥거푸집 전면을 관통 돌출하도록 앵커를 설치하여 앵커가 철근콘크리트기둥 전면에 돌출 정착하도록 시공하는 제1단계; 철근콘크리트기둥 전면에서 철근콘크리트기둥 사이를 연결하도록 배치되는 식생매트와 식생매트를 덮는 보호철망을 앵커에 고정 설치하고 비탈면과 식생매트 사이에 식생토를 다짐하면서 채우는 제2단계; 그리고, 옹벽 높이로 상기 제2단계를 반복 실시하는 제3단계;를 포함하여 이루어지는 것을 특징으로 하는 강화 녹화옹벽 시공방법을 제공한다.
In order to solve the above technical problem, the present invention, while installing the pillar formwork on the stabilized slope front and reinforces the column reinforcement and placing the pillar concrete through the process of spacing the reinforced concrete pillar along the slope surface, the pillar form the front A first step of installing the anchor to protrude through and constructing the anchor to protrude and fix the front of the reinforced concrete pillar; A second step of fixing the vegetation mat disposed on the front of the reinforced concrete column and securing the vegetation mat covering the vegetation mat and fixing the vegetation soil between the inclined surface and the vegetation mat; And, a third step of repeating the second step at the height of the retaining wall; provides a reinforced green retaining wall construction method comprising a.

삭제delete

삭제delete

본 발명에 따르면 다음과 같은 효과를 기대할 수 있다.According to the present invention, the following effects can be expected.

첫째, 비탈면에 철근콘크리트기둥을 시공하고 철근콘크리트기둥 사이를 식생공간으로 구성하기 때문에 친환경적이면서 구조적으로 안정적인 녹화옹벽을 시공할 수 있다. First, since reinforced concrete pillars are installed on slopes and vegetation spaces are constructed between reinforced concrete pillars, eco-friendly and structurally stable retaining walls can be constructed.

둘째, 자력으로 안정화되거나 각종 비탈면 보강공(소일네일, 어스앵커, 락볼트 등)으로 안정화된 상태의 비탈면에 적용하기 때문에, 깎기 또는 쌓기 비탈면은 물론 호안 비탈면에도 유리하게 적용하면서 녹화옹벽을 시공할 수 있다. 특히 비탈면 보강공이 시공된 비탈면에 적용할 경우 비탈면 보강공의 두부를 옹벽 구체의 일부인 철근콘크리트기둥에 매입 시공하기 때문에 비탈면 보강공과 옹벽 구체의 일체성을 강화하면서 비탈면 보호효과를 강화할 수 있다. Second, since it is applied to slopes stabilized by magnetic force or stabilized with various slope reinforcement holes (soil nails, earth anchors, rock bolts, etc.), the greening retaining wall can be advantageously applied to not only cutting or stacking slopes but also lake slopes. Can be. In particular, when slope slope reinforcement is applied to the slopes on which the slope slope reinforcement is applied, the head of the slope slope reinforcement is buried in the reinforced concrete column, which is part of the retaining wall sphere, thereby enhancing slope integrity while strengthening the integrity of the slope slope reinforcing hole and the retaining wall sphere.

셋째, 철근콘크리트기둥을 띄엄띄엄 시공하기 때문에 비탈면의 굴곡 구간은 철근콘크리트기둥을 시공하지 않고 식생공간으로 구성할 수 있으며, 이에 따라 식생공간은 비교적 형상 변경이 자유로운 식생매트, 보호철망, 식생토로 구현함으로써 비탈면의 굴곡 구간에 유연하게 대응하면서 녹화옹벽을 시공할 수 있다. 나아가 띄엄띄엄 시공된 철근콘크리트기둥의 유지보수가 간단하다.Third, because the reinforced concrete pillars are sparsely constructed, the curved section of the slope can be configured as a vegetation space without constructing the reinforced concrete pillars. Accordingly, the vegetation space can be realized as a vegetation mat, a protective wire mesh, or a vegetation soil that can be relatively freely changed. Thus, the green retaining wall can be constructed while flexibly responding to the curved section of the slope. Furthermore, maintenance of sparsely constructed reinforced concrete columns is simple.

넷째, 비탈면에 철근콘크리트기둥을 시공하기 위해 조립식의 기둥거푸집을 제안하기 때문에 철근콘크리트공사를 간단하게 진행하면서 녹화옹벽을 시공할 수 있다.
Fourth, because the prefabricated pillar formwork is proposed to construct reinforced concrete pillars on the slope, it is possible to construct greening retaining walls while simplifying the reinforced concrete construction.

도 1은 본 발명에 따른 강화 녹화옹벽의 다양한 실시예를 도시한다.
도 2a 내지 도 2c는 본 발명에 따른 강화 녹화옹벽 시공방법을 나타내는 시공순서도이다.
도 3은 본 발명에 따른 강화 녹화옹벽 시공방법에서 채움돌과 식생토를 단계별로 시공하는 과정을 도시한다.
도 4는 본 발명에 따른 강화 녹화옹벽 시공방법에 이용되는 기둥거푸집의 제1실시예를 도시한다.
도 5는 본 발명에 따른 강화 녹화옹벽 시공방법에서 도 4의 기둥거푸집을 이용하여 철근콘크리트기둥을 시공하는 과정을 도시한다.
도 6은 본 발명에 따른 강화 녹화옹벽 시공방법에 이용되는 기둥거푸집의 제2실시예를 도시한다.
도 7은 본 발명에 따른 강화 녹화옹의 시공방법에서 도 6의 기둥거푸집을 이용하여 철근콘크리트기둥을 시공하는 과정을 도시한다.
1 illustrates various embodiments of a reinforced green retaining wall according to the present invention.
2A to 2C are construction sequence diagrams illustrating a method for constructing a reinforced green retaining wall according to the present invention.
Figure 3 shows the process of constructing the filling stone and vegetation soil step by step in the reinforced green retaining wall construction method according to the present invention.
Figure 4 shows a first embodiment of the column formwork used in the reinforced green retaining wall construction method according to the present invention.
5 is a view illustrating a process of constructing a reinforced concrete column using the pillar formwork of FIG. 4 in the reinforced green retaining wall construction method according to the present invention.
Figure 6 shows a second embodiment of the column formwork used in the reinforced green retaining wall construction method according to the present invention.
7 is a view illustrating a process of constructing a reinforced concrete column using the pillar formwork of FIG. 6 in the construction method of reinforcement greening according to the present invention.

이하, 첨부한 도면 및 바람직한 실시예에 따라 본 발명을 상세히 설명한다.
Hereinafter, the present invention will be described in detail with reference to the accompanying drawings and preferred embodiments.

도 1은 본 발명에 따른 강화 녹화옹벽의 다양한 실시예를 도시한다. 본 발명에 따른 강화 녹화옹벽은 깎기 또는 쌓기 비탈면(S)이나 호안 비탈면(S)에 옹벽을 시공함에 있어 철근콘크리트기둥(10)을 시공하고 철근콘크리트기둥(10) 사이를 식생공간으로 구성한다는데 기술적 특징이 있다. 이와 같은 기술적 특징을 구현하기 위해 본 발명은 철근콘크리트기둥(10), 앵커(20), 식생매트(31), 보호철망(32), 식생토(41)를 필수적인 구성으로 포함하는 한편, 보강그리드(42), 돌망태(33), 채움돌(43)을 선택적인 구성으로 포함한다.
1 illustrates various embodiments of a reinforced green retaining wall according to the present invention. Reinforced greening retaining wall according to the present invention constructs the reinforced concrete column (10) in the construction of the retaining wall on the cutting or stacking slope (S) or rake slope (S) and constitutes the vegetation space between the reinforced concrete pillars (10) There are technical features. In order to implement such technical features, the present invention includes a reinforced concrete column 10, an anchor 20, a vegetation mat 31, a protective wire mesh 32, and a vegetation soil 41 as essential components, and a reinforcing grid. (42), the gabion 33, and the filling stone 43 is included in an optional configuration.

철근콘크리트기둥(10)은 안정화된 비탈면(S)을 따라 시공되는 한편 좌우로 비탈면(S)을 따라 띄엄띄엄 시공되는 구성이다. 본 발명에서 안정화된 비탈면(S)이란 안식각 이하의 경사도를 가지거나 소일네일, 어스앵커, 락볼트 등의 비탈면 보강공(S4)으로 보강됨에 따라 안정화된 지반을 의미하며, 본 발명에서 안정화된 비탈면(S)은 직접적인 지반 표면(S1)이 될 수 있는 것은 물론 지반 표면(S1)에 부직포(S2)나 배수판(S3) 등이 처리된 상태가 될 수 있으며, 특히 소일네일에 의한 비탈면 보강공(S4)으로 보강된 경우에는 숏크리트(S41)로 표면 처리된 상태가 된다.Reinforced concrete column 10 is constructed along the stabilized slope (S) while being spaced along the slope (S) from side to side. Slope stabilized in the present invention (S) means the ground stabilized by having an inclination of less than the angle of repose or reinforced with a slope reinforcing hole (S4), such as a small nail, earth anchor, rock bolt, stabilized slope in the present invention (S) may be a direct ground surface (S1), as well as a non-woven fabric (S2), drain plate (S3), etc. are treated on the ground surface (S1), in particular slope slope reinforcement hole by a small nail ( When it is reinforced with S4), it will be in the state surface-treated with shotcrete S41.

도 1(a)에서는 철근콘크리트기둥(10)이 숏크리트(S41)로 표면 처리된 비탈면(S)에 시공된 것을 확인할 수 있고, 도 1(b)에서는 철근콘크리트기둥(10)이 부직포(S2)와 배수판(S3)이 처리된 비탈면(S)에 시공된 것을 확인할 수 있으며, 도 1(c)에서는 철근콘크리트기둥(10)이 어떠한 것도 처리되지 아니한 상태의 비탈면(S)에 시공된 것을 확인할 수 있다. 나아가 도 1(a)(b)(c)에서는 철근콘크리트기둥(10)이 비탈면 보강공(S4)으로 보강된 비탈면(S)에 시공된 것을 확인할 수 있는데, 이 경우 철근콘크리트기둥(10)은 그 내부에 비탈면 보강공(S4)의 돌출 두부가 매입되도록 시공된다. 비탈면 보강공(S4)의 돌출 두부가 철근콘크리트기둥(10)에 매입됨에 따라 철근콘크리트기둥(10)은 지압판으로 역할할 것으로 기대된다. 즉 비탈면 보강공(S4)의 돌출 두부와 철근콘크리트기둥(10)이 일체화되기 때문에 지반 내부에서 비탈면 보강공(S4)에 인장력이 작용할 때 그 인장력이 철근콘크리트기둥(10)으로 전달되면서 비탈면(S)을 누르는 지압력으로 전환되는 것이다.In Figure 1 (a) it can be seen that the reinforced concrete pillar 10 was constructed on the slope surface (S) surface-treated with the shot concrete (S41), in Figure 1 (b) the reinforced concrete pillar (10) is a nonwoven fabric (S2) And it can be confirmed that the drainage plate (S3) has been constructed on the treated slope surface (S), in Figure 1 (c) can be confirmed that the reinforced concrete column 10 was constructed on the slope surface (S) of the state that is not treated anything. have. Furthermore, in Figure 1 (a) (b) (c) it can be confirmed that the reinforced concrete column 10 was constructed on the slope surface (S) reinforced by the slope surface reinforcing hole (S4), in this case the reinforced concrete column (10) The projecting head of the slope reinforcing hole (S4) is built in the interior. As the projecting head of the slope-surface reinforcing hole (S4) is embedded in the reinforced concrete column 10, the reinforced concrete column 10 is expected to serve as a pressure plate. That is, because the projecting head of the slope reinforcing hole (S4) and the reinforced concrete pillar (10) is integrated, when the tensile force acts on the slope reinforcing hole (S4) in the ground, the tensile force is transmitted to the reinforced concrete pillar (10) and slopes (S). It is converted to the pressure by pressing).

철근콘크리트기둥(10)은 도 1에서와 같이 전면으로 갈수록 점점 폭이 좁아지는 사다리꼴 단면 형상이 바람직한데, 이는 철근콘크리트기둥(10)의 전면 노출을 최소화하여 옹벽 전면의 녹화면적을 최대화하기 위함이다. 나아가 철근콘크리트기둥(10)은 도 1(c)에서와 같이 전면에 길이방향을 따라 연속하는 연속홈(13)이 형성되도록 시공할 수 있는데, 이는 앵커(20)의 외부 돌출을 최소화하기 위함이다.
Reinforced concrete column 10 is preferably a trapezoidal cross-sectional shape that becomes narrower toward the front as shown in Figure 1, to minimize the front exposure of the reinforced concrete column 10 to maximize the greening area of the retaining wall front . Furthermore, the reinforced concrete column 10 may be constructed such that continuous grooves 13 are formed in the front in the longitudinal direction as shown in FIG. 1 (c), which is to minimize the external protrusion of the anchor 20. .

앵커(20)는 철근콘크리트기둥(10) 전면에 돌출되게 정착 설치되는 구성이다. 앵커(20)는 시공 완료된 철근콘크리트기둥(10)에 천공하여 정착 설치하는 것도 가능하고 철근콘크리트기둥(10) 시공과정에서 기둥콘크리트(12)에 매입시키면서 정착 설치하는 것도 가능하다. 특히 철근콘크리트기둥(10) 시공과정에서 앵커(20)를 기둥콘크리트(12)에 매입시키는 경우라면, 앵커(20)는 철근콘크리트기둥의 기둥철근(11)을 배근하기 위한 철근스페이서(RS)와 일체화된 형태로 마련할 수 있다(도 4 참조). 도 1(c)에서와 같이 철근콘크리트기둥(10) 전면에 연속홈(13)이 형성된 경우라면 앵커(20)는 연속홈(13)에 위치하면서 주변의 기둥콘크리트(12) 부분보다 돌출하지 않게 정착 설치되도록 한다.Anchor 20 is configured to be fixed to protrude in front of the reinforced concrete pillar (10). Anchor 20 can be installed by drilling the perforated reinforced concrete pillar (10) completed, and can also be installed while fixing to the pillar concrete 12 during the reinforced concrete pillar (10) construction process. Particularly, in the case of purchasing the anchor 20 to the pillar concrete 12 during the construction of the reinforced concrete column 10, the anchor 20 may include a reinforcement spacer RS for reinforcing the column reinforcement 11 of the reinforced concrete column. It may be provided in an integrated form (see FIG. 4). If the continuous groove 13 is formed on the front of the reinforced concrete pillar 10, as shown in Figure 1 (c) anchor 20 is located in the continuous groove 13 so as not to protrude from the portion of the surrounding pillar concrete 12 Make sure to settle down.

도 1에서는 볼트와 너트 및 와셔의 조립으로 구성된 앵커(20)를 확인할 수 있는데, 이러한 앵커(20)는 보호철망(32) 내지 돌망태(33)를 조립식으로 용이하게 고정 설치하기 위해 제안된 예이다. 도 1(a)(c)에서는 정착볼트(21)와 고정너트(22) 및 고정와셔(23)로 구성된 앵커(20)를 확인할 수 있고, 도 1(b)에서는 조절너트(24)를 더 포함하여 구성된 앵커(20)를 확인할 수 있다. 앵커(20)에서 고정와셔(23)는 이웃하는 앵커 상호 간을 동시에 연결할 수 있도록 장방형 판재로 준비할 수 있다(도 2b 참조). 특히 도 1(c)에서와 같이 정착볼트(21)와 고정너트(22)의 조립이 연속홈(13) 내부에서 이루어진다면 정착볼트(21)가 노출되지 않아 미관상 유리할 뿐만 아니라 옹벽 주변 보행자의 통행시 보행자의 스침에 의한 위험을 차단할 수 있을 것이다.
In Figure 1 it can be seen that the anchor 20 consisting of the assembly of bolts, nuts and washers, this anchor 20 is an example proposed to easily install the protective wire mesh 32 to the gabion 33 in a prefabricated manner. . In Figure 1 (a) (c) it can be seen the anchor 20 consisting of the fixing bolt 21, the fixing nut 22 and the fixing washer 23, in Figure 1 (b) further the adjustment nut 24 You can check the anchor 20 configured to include. Fixing washer 23 in the anchor 20 can be prepared in a rectangular plate so as to connect the adjacent anchors at the same time (see Figure 2b). In particular, when the fixing bolt 21 and the fixing nut 22 are assembled in the continuous groove 13 as shown in FIG. 1 (c), the fixing bolt 21 is not exposed, so it is not only aesthetically advantageous but also the passage of pedestrians around the retaining wall. City pedestrians can be prevented by the danger of grazing.

식생매트(31)는 철근콘크리트기둥(10) 전면에서 철근콘크리트기둥(10) 사이를 연결하도록 배치되는 한편 앵커(20)에 구속 설치되는 구성이다. 식생매트(31)는 식물의 활착을 유도하기 위한 구성이 된다. 본 발명에서 식생매트(31)는 통상 녹화공법에 적용하는 초본류의 씨앗이 심어진 형태의 것은 물론 잔디매트도 포함한다.The vegetation mat 31 is arranged to connect between the reinforced concrete pillars 10 in front of the reinforced concrete pillars 10 while being restrained and installed in the anchor 20. The vegetation mat 31 is configured to induce the sticking of the plant. In the present invention, the vegetation mat 31 includes a grass mat as well as a planted form of a herbaceous seed, which is usually applied to a greening method.

식생매트(31)는 도 1(a)(c)에서와 같이 철근콘크리트기둥(10) 전면에 밀착하게 설치하는 것은 물론, 도 1(b)에서와 같이 정착볼트(21)의 길이를 적절히 조절하고 아울러 조절너트(24)를 적절히 이용하면서 철근콘크리트기둥(10) 전면에서부터 소정 거리 이격하게 설치할 수도 있다.
Vegetation mat 31 is installed in close contact with the front of the reinforced concrete pillar 10, as shown in Figure 1 (a) (c), as well as appropriately adjust the length of the fixing bolt 21 as shown in Figure 1 (b) In addition, it may be installed at a predetermined distance from the front of the reinforced concrete pillar 10 while using the adjustment nut 24 appropriately.

보호철망(32)은 식생매트(31)를 덮으면서 앵커(20)에 고정 설치되는 구성으로, 식생매트(31)를 보호하는 한편 옹벽 전면을 구성하는 구성이 된다. 오랜 시간이 지나 식물 활착이 활발해지면 식생매트(31)가 부식되거나 분해되므로 이를 감안하면 보호철망(32)은 실질적으로 옹벽의 형태를 유지시키는 구성이 된다고도 할 수 있다. The protective wire mesh 32 is fixed to the anchor 20 while covering the vegetation mat 31 and protects the vegetation mat 31 and constitutes a retaining wall front surface. After a long time, the vigor of the plant activity is corroded or decomposed vegetation mat 31 is considered in consideration of this can be said that the protective wire mesh 32 substantially maintains the shape of the retaining wall.

보호철망(32)은 식생매트(31)와 함께 식생공간을 형성하게 되는데, 식생공간에 식생토(41)가 채워지면 보호철망(32)에 식생토(41)에 의한 토압이 작용하기 때문에 보호철망(32)은 식생토(41)에 의한 토압을 견딜 수 있는 충분한 강성을 가지는 자재로 준비할 필요가 있다. 아울러 옹벽의 전면을 구성하면서 항시 외기에 노출되기 때문에 보호철망(32)은 내식성이 우수한 자재로 준비할 필요가 있다. 그러한 자재에는 익스펜디드 메탈(expanded metal)이 있다.The protective wire mesh 32 forms a vegetation space together with the vegetation mat 31, and when the vegetation soil 41 is filled in the vegetation space, the earth pressure by the vegetation soil 41 acts on the protective wire mesh 32. The wire net 32 needs to be prepared from a material having sufficient rigidity to withstand the earth pressure by the vegetation soil 41. In addition, since the front surface of the retaining wall is always exposed to the outside air, the protective wire mesh 32 needs to be made of a material having excellent corrosion resistance. Such materials include expanded metals.

도 1(a)(b)에서와 같이 철근콘크리트기둥(10) 전면이 평평하게 형성되는 경우라면 보호철망(32) 또한 평평하게 마련하면 될 것이나, 도 1(c)에서와 같이 철근콘크리트기둥(10) 전면에 연속홈(13)이 형성되는 경우라면 보호철망(32)은 연속홈(13)에 끼워져 앵커(20)에 고정되도록 적절히 절곡시켜 마련해야 할 것이다.
If the front of the reinforced concrete pillar 10 as shown in Figure 1 (a) (b) is to be formed flat, the protective wire mesh 32 may also be provided flat, as shown in Figure 1 (c) reinforced concrete pillar ( 10) If the continuous groove 13 is formed on the front surface of the protective wire mesh 32 will be provided by properly bending to be fixed to the anchor 20 is fitted into the continuous groove (13).

식생토(41)는 식생매트(31)와 보호철망(32)에 의해 형성된 식생공간에 채워지는 구성으로, 식물 생장의 기반이 되는 구성이 된다. 즉, 비탈면(S)과 식생매트(31) 사이에 채워지는 것이다. Vegetation soil 41 is a configuration that is filled in the vegetation space formed by the vegetation mat 31 and the protective wire mesh 32, it is a configuration that is the basis of plant growth. That is, it is filled between the slope (S) and the vegetation mat (31).

식생토(41)가 채워지면 곧 녹화옹벽으로 완성된다. 도 1(a)(c)는 철근콘크리트기둥(10) 사이에 식생토(41)가 채워짐에 따라 철근콘크리트기둥(10) 전면이 노출되는 녹화옹벽으로 완성되고 있고, 도 1(b)는 철근콘크리트기둥(10)이 완전히 매입되도록 식생토(41)가 채워짐에 따라 옹벽 전면이 식생환경으로 조성된 녹화옹벽으로 완성되고 있다. As soon as the vegetation soil 41 is filled, it is completed as a green retaining wall. 1 (a) (c) is completed with a green retaining wall exposed to the front of the reinforced concrete column 10 as the vegetation soil 41 is filled between the reinforced concrete pillars 10, Figure 1 (b) As the vegetation soil 41 is filled so that the concrete pillar 10 is completely embedded, the retaining wall is completed with a green retaining wall formed as a vegetation environment.

본 발명에 따른 녹화옹벽에서 보호철망(32)이 앵커(20)에 의해 철근콘크리트기둥(10)에 연결 결속되기 때문에, 식생토(41)에 의한 토압은 보호철망(32)을 통해 최종적으로 철근콘크리트기둥(10)에 전달되어 안정화된 상태로 유지된다. 다만 식생토(41)에 의한 토압이 보호철망(32)으로 전달되는 것을 최소화하는 것이 녹화옹벽의 구조적인 안정성과 효율적인 구조설계를 위해 바람직할 것이므로, 본 발명에서는 도 1(b)에서와 같이 식생토(30)의 채움 면적이 넓은 경우에는 보강그리드(42)를 적절히 이용할 것을 제안한다.Since the protective wire mesh 32 in the green retaining wall according to the present invention is connected to the reinforced concrete pillar 10 by the anchor 20, the earth pressure by the vegetation soil 41 is finally reinforced through the protective wire mesh 32. Transmitted to the concrete pillar 10 is maintained in a stabilized state. However, minimizing the transmission of earth pressure by the vegetation soil 41 to the protective wire mesh 32 will be preferable for structural stability and efficient structural design of the greening retaining wall. In the present invention, the vegetation as shown in FIG. When the filling area of the toe 30 is large, it is proposed to use the reinforcing grid 42 appropriately.

보강그리드(42)는 식생토(41) 내부에 수평으로 매설되는 구성으로, 식생토(41)를 층간 구분하는 구성이라고 할 수 있다. 보강그리드(42)가 설치됨에 따라 식생토(41)에 의한 횡방향의 변형은 보강그리드(42)와 토사입자의 마찰력과, 인장력을 받는 보강그리드(42)의 구속에 의해 억제된다. 보강그리드(42)는 보호철망(32)에 연결하면서 설치될 수도 있는데, 이 경우 보강그리드(42)가 보호철망(32)을 붙잡는 형태가 되기 때문에 보호철망(32)의 배부름 현상을 유리하게 억제할 수 있다(도 3(c) 참조).
The reinforcing grid 42 is a structure that is horizontally embedded in the vegetation soil 41, it can be said to be a configuration for separating the vegetation soil 41 between the layers. As the reinforcing grid 42 is installed, the deformation in the lateral direction due to the vegetation soil 41 is suppressed by the friction of the reinforcing grid 42 and the earth and sand particles and the restraint of the reinforcing grid 42 which receives the tensile force. The reinforcing grid 42 may be installed while connecting to the protective wire mesh 32. In this case, since the reinforcing grid 42 is formed to hold the protective wire mesh 32, the filling phenomenon of the protective wire mesh 32 is advantageous. It can suppress (refer FIG. 3 (c)).

한편 호안 비탈면(S)과 같은 경우에는 수위변경에 따라 옹벽 하부가 물에 잠기게 되기도 하는데, 이를 고려하여 본 발명에서는 옹벽을 상부옹벽과 하부옹벽 2단으로 구분할 것을 제안한다. 상부옹벽은 앞서 살펴본 식생매트(31), 보호철망(32), 식생토(41)로 구성하여 실질적인 녹화옹벽으로 완성하고, 하부옹벽은 돌망태(33)와 채움돌(43)로 구성하여 유수를 정화시키고 물고기 서식공간으로 제공한다(도 2c, 도 3(a) 참조).On the other hand, in the case of the lakeside slope (S), the lower part of the retaining wall may be submerged according to the water level change. The upper retaining wall is composed of the vegetation mat 31, the protective wire mesh 32, and the vegetation soil 41 as described above, and is completed as the actual green retaining wall, and the lower retaining wall is composed of the gabion 33 and the filling stone 43 It is clarified and provided to the fish habitat (see Figures 2c, 3a).

돌망태(33)는 철근콘크리트기둥(10) 상호 간을 연결하면서 앵커(20)에 고정 설치되는 구성으로, 앞서 살펴본 식생매트(31)와 보호철망(32)을 대체하는 구성이 된다. 채움돌(43)은 비탈면(S)과 돌망태(33) 사이에 채워지는 구성으로, 앞서 살펴본 식생토(41)를 대체하는 구성이 된다.
Gabion 33 is a structure that is fixed to the anchor 20 while connecting the reinforced concrete pillars 10, it is configured to replace the vegetation mat 31 and the protective wire mesh 32 described above. Filling stone 43 is a configuration that is filled between the slope (S) and the gabion 33, it becomes a configuration to replace the vegetation soil 41 described above.

도 2a 내지 도 2d는 본 발명에 따른 강화 녹화옹벽의 시공방법을 나타내는 시공순서도이고, 도 3은 채움돌(43)과 식생토(41)를 단계별로 시공하는 과정을 나타낸다. 이들 도면을 참고하여 본 발명에 따른 강화 녹화옹벽의 시공방법을 단계적으로 살펴본다.2a to 2d is a construction sequence diagram showing the construction method of the reinforced green retaining wall according to the present invention, Figure 3 shows the process of constructing the filling stone 43 and the vegetation soil 41 step by step. The construction method of the reinforced green retaining wall according to the present invention will be described step by step with reference to these drawings.

(1)제1단계-철근콘크리트기둥과 앵커 시공단계(도 2a 및 도 2b)(1) the first step-reinforced concrete column and anchor construction step (Fig. 2a and 2b)

안정화된 비탈면(S) 전면에 기둥거푸집(100)을 설치하고 기둥철근(11)을 배근하고 기둥콘크리트(12)를 타설하는 과정을 통해 철근콘크리트기둥(10)을 비탈면(S)을 따라 띄엄띄엄 시공한다. 이때 기둥거푸집(100) 전면을 관통 돌출하도록 앵커(20)를 설치하여 앵커(20)가 철근콘크리트기둥(10) 전면에 돌출 정착하도록 시공한다(도 2b). 기둥거푸집(100)에 의한 철근콘크리트기둥(10)의 시공방법에 대해서는 도 4 내지 도 7에서 자세히 설명한다.The reinforcement concrete pillars 10 are spaced along the slopes S by installing pillar formwork 100 on the stabilized slope surface S, laying the pillar reinforcement 11 and placing the pillar concrete 12. Construct. At this time, the anchor 20 is installed so as to protrude through the front of the pillar formwork 100 is constructed so that the anchor 20 protrudes and fixed to the front of the reinforced concrete pillar (10) (Fig. 2b). The construction method of the reinforced concrete column 10 by the pillar formwork 100 will be described in detail with reference to FIGS.

안정화된 비탈면(S)은 앞서 살펴본 바와 같다. 도 2a에서는 지반 표면(S1)에 부직포(S2)나 배수판(S3) 등을 처리하는 한편 비탈면 보강공(S4)으로 보강하여 안정화시킨 상태와 비탈면(S) 하부에 기초(F)를 시공한 상태를 확인할 수 있다. 지반조건에 따라 부직포(S2), 배수판(S3), 기초(F)를 생략할 수 있는 것은 물론, 나아가 숏크리트(S41)로 표면 처리할 수도 있다.Stabilized slope (S) is as described above. In FIG. 2A, the nonwoven fabric S2, the drainage plate S3, and the like are treated on the ground surface S1 while being stabilized by sloped reinforcing holes S4 and the foundation F is installed on the lower surface of the slope S. You can check. Depending on the ground conditions, the nonwoven fabric S2, the drainage plate S3, and the foundation F can be omitted, as well as surface treatment with shotcrete S41.

도 2b에서는 기초(F) 위 배수판(S3) 전면으로 비탈면 보강공(S4)이 시공된 위치에 철근콘크리트기둥(10)을 시공하고 있다. 철근콘크리트기둥(10)은 시공할 옹벽의 구조계산에 따라 배치간격과 단면을 결정하도록 한다. 다만 철근콘크리트기둥(10)의 시공성을 고려한다면 철근콘크리트기둥(10)은 비탈면(S)에서 굴곡 구간(비탈면이 휘어지는 유선 구간 등)에 위치하지 않도록 배치 설계하는 것이 바람직하다.In FIG. 2B, the reinforced concrete column 10 is constructed at the position where the slope-surface reinforcing hole S4 is constructed on the front surface of the drain plate S3 on the foundation F. As shown in FIG. Reinforced concrete column 10 is to determine the placement interval and cross section according to the structural calculation of the retaining wall to be constructed. However, considering the constructability of the reinforced concrete column 10, the reinforced concrete column 10 is preferably arranged so as not to be located in the bent section (such as the curved section bent slope surface) in the slope (S).

(2)제2단계-녹화단계(도 2c 및 도 3 참조)(2) 2nd step-recording step (refer to FIG. 2C and FIG. 3)

철근콘크리트기둥(10) 전면에서 철근콘크리트기둥(10) 사이를 연결하도록 배치되는 식생매트(31)와 식생매트(31)와 식생매트(31)를 덮는 보호철망(32)을 앵커(20)에 고정 설치하고 비탈면(S)과 식생매트(31) 사이에 식생토(41)를 다짐하면서 채운다(도 2c). 상부옹벽과 하부옹벽을 구분하는 경우에는 도 3에서와 같이 소정 높이까지 돌망태(33)를 설치하고 채움돌(43)을 채우는 과정을 진행한 후에 그 위로 녹화단계를 실시하도록 한다.The vegetation mat 31 and vegetation mat 31 and vegetation mat 31 covering the vegetation mat 31 and the vegetation mat 31 arranged to connect between the reinforced concrete pillars 10 at the front of the reinforced concrete pillar 10 are anchored to the anchor 20. Fixed installation and filling the vegetation soil 41 between the slope (S) and the vegetation mat 31 while filling (Fig. 2c). In the case of distinguishing the upper retaining wall and the lower retaining wall, the gabion 33 is installed to a predetermined height as shown in FIG.

본 단계는 도 3에서와 같이 보강그리드(42)를 더 설치하면서 진행할 수 있다. 이 경우에는 식생토(41)를 1차 채움하여 다짐하는 단계(도 3(b)); 식생토(41) 위에 보강그리드(42)를 수평으로 포설하는 단계(도 3(c)); 보강그리드(42) 위에 식생토(41)를 2차 채움하여 다짐하는 단계(도 3(d));로 세분하여 진행하면 된다. 식생매트(31)와 보호철망(32)의 단위 높이에 따라 다짐작업과 보강그리드(42) 설치작업을 반복 실시할 수 있음은 물론이다.This step may proceed while installing the reinforcing grid 42 as shown in FIG. In this case, the first step is to fill the vegetation soil 41 (Fig. 3 (b)); Laying horizontally the reinforcing grid 42 on the vegetation soil 41 (FIG. 3 (c)); Secondly filling the vegetation soil 41 on the reinforcing grid 42 and compacting (FIG. 3 (d)); Of course, according to the unit height of the vegetation mat 31 and the protective wire mesh 32, the compacting operation and the installation of the reinforcing grid 42 can be repeatedly performed.

(3)제3단계-반복단계(도 2d 참조)(3) Step 3-Repeating Steps (see FIG. 2D)

녹화단계(제2단계)를 시공할 옹벽 높이로 상향하여 반복 실시한다. 즉, 옹벽 전 구간에 걸쳐 제1단의 녹화과정(식생매트와 보호철망 설치, 식생토 채움)을 실시하고, 제1단 위로 제2단의 녹화과정을 반복 실시하는 것이다. 이로써 도 2d에서와 같이 전면 전체 또는 일부가 식생공간으로 구현된 녹화옹벽이 완성된다.
The greening step (second step) is repeated to the height of the retaining wall to be constructed. In other words, the greening process of the first stage (vegetation mat and protective wire mesh installation and vegetation soil filling) is performed over the entire retaining wall, and the second stage is repeated to the first stage. As a result, as shown in FIG. 2D, a greening retaining wall having a whole or part of the front surface of the vegetation space is completed.

도 4 내지 도 7은 철근콘크리트기둥(10)을 용이하게 시공하기 위해 본 발명에서 제안하는 기둥거푸집(100)과 그 기둥거푸집(100)을 이용하여 철근콘크리트기둥(10)을 시공하는 과정을 나타낸다. 본 발명은 기둥거푸집(100)에 대해 두 가지 실시예를 제안한다.  4 to 7 illustrate a process of constructing the reinforced concrete pillar 10 using the pillar formwork 100 and the pillar formwork 100 proposed in the present invention in order to easily construct the reinforced concrete pillar 10. . The present invention proposes two embodiments for the column formwork 100.

도 4는 기둥거푸집(100)의 제1실시예로서 후면평판(110a)과 조립틀(120)로 구성된 예이다. 후면평판(110a)은 철근콘크리트기둥(10)의 후면을 형성하는 부분으로, 비탈면(S) 전면에 놓이도록 설치되는 구성이며, 비탈면에 배수판이 설치되는 경우에는 배수판이 후면평판(110a)을 대신할 수 있다. 조립틀(120)은 철근콘크리트기둥(10)의 후면 이외의 다른 면을 형성하는 부분으로, 상기 후면평판(110a)에 제1결속구(130)에 의해 조립식으로 고정 설치되는 한편 횡방향으로 분할된 둘 이상의 구성각편(120a, 120b)이 제2결속구(140)에 의해 조립 구성되는 구성이다. 도 4에서 보는 바와 같이 조립틀의 각 구성각편(120a, 120b)은 철근콘크리트기둥(10)의 표면을 형성시키기 위한 면형성부(121)와 구성각편의 상호 조립과 구성각편(120a. 120b)의 후면평판(110a)에의 조립을 위한 결속날개(122, 123)로 구성하면 되며, 결속날개(122, 123)에는 제1,2결속구의 체결을 위한 통공(122a, 123a)을 적절히 마련하면 된다. 이와 같은 제1실시예에 따른 기둥거푸집(100)은 콘크리트 타설에 따른 부력을 후면평판(110a)과 조립틀(120)의 결속력으로 지지하는 방식이 되는데, 후면평판(110a)을 생략하는 것도 고려할 수 있다. 다만 후면평판(110a)을 생략한다면 조립틀(120)은 앵커를 이용하여 비탈면(S)에 확고하게 정착 설치해야 할 것이며, 그래야 조립틀(120)이 받는 부력을 안전하게 비탈면(S)으로 전달하여 조립틀(120)의 설치안정성을 확보할 수 있다. 4 is an example consisting of a rear plate 110a and an assembly frame 120 as a first embodiment of the pillar formwork 100. The rear plate 110a is a portion that forms the rear side of the reinforced concrete column 10, and is installed to be placed on the front side of the slope (S). When the drain plate is installed on the slope, the drain plate replaces the rear plate 110a. can do. The assembly frame 120 is a part forming a surface other than the rear surface of the reinforced concrete column 10, and is fixedly installed by the first binding hole 130 on the rear plate 110a while being split in the horizontal direction. The two or more configuration pieces 120a and 120b are assembled by the second binding port 140. As shown in FIG. 4, each of the component pieces 120a and 120b of the assembly frame includes the surface forming portion 121 and the component assembly pieces 120a and 120b for forming the surface of the reinforced concrete column 10. The coupling blades 122, 123 for assembling the rear flat plate 110a of the, and the coupling wings 122, 123 may be provided with the through holes (122a, 123a) for fastening the first and second binding holes as appropriate. . The pillar formwork 100 according to the first embodiment is a method of supporting the buoyancy according to the concrete placing by the binding force of the rear plate 110a and the assembly frame 120, it is also considered to omit the rear plate 110a. Can be. However, if the rear plate 110a is omitted, the assembly frame 120 should be firmly fixed to the slope surface S using an anchor so that the buoyancy received by the assembly frame 120 is safely transferred to the slope surface S. Installation stability of the assembly frame 120 can be secured.

제1실시예에 따른 기둥거푸집(100)은 조립틀(120)이 받는 부력을 후면평판(110a)이 지지하는 구조가 되며, 특히 후면평판(110a)은 콘크리트에 함유된 시멘트페이스트가 지반 내부로 스며들지 않고 그대로 콘크리트 경화에 작용하게 하여 철근콘크리트기둥(10)이 설계강도로 시공할 수 있게 하는 역할도 한다. 조립틀(120)은 시공할 철근콘크리트기둥(10) 단면에 부합하게 마련하면 되며, 도 4에서는 두 개의 구성각편(120a, 120b)으로 구성되는 한편 하나의 구성각편(120a)이 철근콘크리트기둥(10) 전면에 연속홈(13)을 형성하기 위한 형태로 이루어진 조립틀(120)을 확인할 수 있다. 또한 도 4에서는 고정못(나사도 가능함)으로 마련한 제1결속구(130), 볼트와 너트로 마련한 제2결속구(140)를 확인할 수 있다. The pillar formwork 100 according to the first embodiment has a structure in which the rear plate 110a supports the buoyancy received by the assembly frame 120, and in particular, the rear plate 110a has a cement paste contained in concrete into the ground. It also acts on the concrete hardening as it does not penetrate, so that the reinforced concrete column 10 can be constructed with design strength. The assembly frame 120 may be provided so as to correspond to the cross-section of the reinforced concrete pillar 10 to be constructed, and in FIG. 4, two component angle pieces 120a and 120b are formed, while one component angle piece 120a is a reinforced concrete column ( 10) It can be seen that the assembly frame 120 made of a form for forming the continuous groove 13 on the front. In addition, in FIG. 4, the first binding holes 130 provided with fixing nails (screws may be used) and the second binding holes 140 provided with bolts and nuts can be confirmed.

도 5는 도 4의 기둥거푸집(100)을 이용하여 철근콘크리트기둥(10)을 시공하는 방법을 보여주는데, 이에 따라 철근콘크리트기둥(10)을 시공하는 방법을 살펴본다. 먼저 후면평판(110a)을 설치하고 조립틀(120)의 일부 구성각편(120a)을 설치하면서 기둥거푸집(100)을 설치한다(도 5(a)). 이어 조립틀(120)의 나머지 구성각편(120b)을 조립한 다음(도 5(b)), 기둥거푸집(100) 내부에 기둥콘크리트(12)를 타설한다(도 5(c)). 기둥거푸집(100)에서 후면평판(110a)은 비탈면(S)에 나사못 등으로 고정 설치하는 것은 물론 별도 고정하지 않은 채 그대로 설치하는 것도 가능하며, 후면평판(110a)의 고정 여부는 비탈면의 경사도에 따라 기둥거푸집(100)의 설치안정성을 고려하여 결정하면 된다. 기둥거푸집(100) 설치 과정 중에 기둥거푸집(100) 내부에 기둥철근(11)을 배근하는 과정을 포함하는 것은 물론이다. 기둥콘크리트(12)는 비탈면(S) 상부에서 펌프로 흘려 내려주는 방식으로 타설하면 되며, 아울러 나무망치 등으로 조립틀(120)을 두드려 다짐작업을 진행할 수도 있다. 기둥콘크리트(12)는 하부평판과 조립틀(120) 사이에 채워지며, 이에 따라 기둥콘크리트(12)에 함유된 시멘트페이스트는 비탈면(S)으로 유출되지 않은 채 그대로 기둥콘크리트(12) 경화에 작용한다. 기둥콘크리트(12)가 양생된 후에는 기둥거푸집(100)에서 조립틀(120)을 탈형 제거하도록 하며, 이로써 철근콘크리트기둥(10)이 완성된다(도 5(d)). 도 5(d)에서 보는 바와 같이 기둥거푸집(100)에서 후면평판(110a)은 제거되지 않고 영구적으로 존치된다. 5 shows a method of constructing the reinforced concrete pillar 10 using the pillar formwork 100 of FIG. 4, and thus looks at a method of constructing the reinforced concrete pillar 10. First, the rear plate 110a is installed and the pillar formwork 100 is installed while installing some constituent pieces 120a of the assembly frame 120 (FIG. 5 (a)). Then, assembling the remaining component pieces 120b of the assembly frame 120 (FIG. 5 (b)), the pillar concrete 12 is poured into the pillar formwork 100 (FIG. 5 (c)). In the column formwork 100, the rear flat plate 110a may be fixedly installed on the inclined surface S with screws or the like, and may be installed as it is without fixing the rear flat plate 110a. According to the installation stability of the column formwork 100 may be determined. Of course, including the process of reinforcing the column reinforcement 11 in the pillar formwork 100 during the pillar formwork 100 installation process. The pillar concrete 12 may be poured in such a manner as to flow down from the upper surface of the slope (S) by a pump, and may also be compacted by tapping the assembly frame 120 using a wooden hammer or the like. The pillar concrete 12 is filled between the lower plate and the assembly frame 120, and thus the cement paste contained in the pillar concrete 12 acts on the curing of the pillar concrete 12 without being spilled onto the slope (S). do. After the pillar concrete 12 is cured, the mold 100 is demolded and removed from the pillar formwork 100, thereby completing the reinforced concrete pillar 10 (FIG. 5 (d)). As shown in Figure 5 (d) in the column formwork 100, the back plate 110a is not removed and is permanently present.

한편, 도 5(a)에서는 앵커(20)가 조립틀(120)에 고정 설치된 것을 확인할 수 있는데, 이는 앵커(20)를 철근콘크리트기둥(10)에 일체로 정착시키기 위함이다. 앵커(20)는 기둥거푸집의 조립틀(120) 전면을 관통 돌출하도록 조립틀(120)에 고정 설치된다. 도 5(a)에서는 정착볼트(21)를 한 쌍의 너트를 적절히 이용하여 설치한 앵커를 확인할 수 있으며, 아울러 기둥철근(11)의 배근을 고려하여 기둥철근(11)을 배근하기 위한 철근스페이서(25)가 앵커의 정착볼트(21)와 일체로 제작 준비된 것을 확인할 수 있다.
On the other hand, in Figure 5 (a) it can be seen that the anchor 20 is fixed to the assembly frame 120, this is to anchor the anchor 20 integrally to the reinforced concrete pillar (10). The anchor 20 is fixed to the assembly frame 120 so as to project through the front of the assembly frame 120 of the column formwork. In Figure 5 (a) can be confirmed anchor anchoring the fixing bolt 21 using a pair of nuts properly, and in addition to the reinforcement spacer for reinforcing the column reinforcement 11 in consideration of the reinforcement of the column reinforcement (11) It can be seen that 25 is manufactured integrally with the anchoring bolt 21 of the anchor.

도 6은 기둥거푸집(100)의 제2실시예로서 후면각재(110b)와 조립틀(120)로 구성된 예이며, 도 7은 도 6의 기둥거푸집(100)을 이용하여 철근콘크리트기둥(10)을 시공하는 방법을 보여준다. 제2실시예에 따른 기둥거푸집은 전체적으로 앞서 살펴본 제1실시예에 따른 기둥거푸집과 동일하고, 다만 후면평판(110a) 대신에 후면각재(110b)가 이용된다는 점에서 차이가 있다. 즉 비탈면(S) 전면에 후면평판(110a)을 설치하는 대신에, 후면각재(110b) 한 쌍을 철근콘크리트기둥(10)의 후면 너비 간격으로 이격하게 비탈면(S) 전면에 고정 설치하는 것이다. 이러한 후면각재(110b) 한 쌍은 후면평판(110a)과 달리 비탈면에 직접 고정 설치되는데, 왜냐하면 후면평판(110a)과는 달리 후면각재(110b)는 조립틀(120)이 받는 콘크리트 부력을 안정적으로 지지하지 못하기 때문이다.FIG. 6 is an example of a backside shell 110b and an assembly frame 120 as a second embodiment of the pillar formwork 100. FIG. 7 illustrates a reinforced concrete column 10 using the pillar formwork 100 of FIG. Demonstrate how to construct. The pillar formwork according to the second embodiment is the same as the pillar formwork according to the first embodiment described above as a whole, except that the rear shell material 110b is used instead of the rear plate 110a. That is, instead of installing the rear flat plate (110a) in front of the slope (S), a pair of rear lumber (110b) is to be fixed to the slope surface (S) front spaced apart at the rear width interval of the reinforced concrete pillar (10). Unlike the rear flat plate 110a, a pair of such back lumber 110b is directly fixed to the slope, because unlike the rear flat plate 110a, the rear lumber 110b stably supports the concrete buoyancy received by the assembly frame 120. Because I do not support.

제2실시예에 따른 기둥거푸집(100)은 소일네일에 의해 보강하면서 숏크리트(S41)로 표면 처리된 비탈면(S)에 유리하게 적용할 수 있다. 숏크리트(S41)가 경화하기 전에 후면각재(110b)를 숏크리트(S41) 표면에 설치하여 고정할 수 있기 때문이다. 제1실시예와 비교할 때 제2실시예는 철근콘크리트기둥(10)의 후면을 직접적으로 형성하지 않는다는 점에서만 차이가 있을 뿐이므로, 전반적으로 앞서 살펴본 제1실시예의 기둥거푸집과 동일한 방법으로 철근콘크리트기둥(10)을 시공하게 된다.The pillar formwork 100 according to the second embodiment may be advantageously applied to the inclined surface S surface-treated with the shotcrete S41 while being reinforced by a small nail. This is because the back corner material 110b may be installed and fixed on the surface of the shotcrete S41 before the shotcrete S41 is cured. Compared with the first embodiment, the second embodiment differs only in that it does not directly form the rear surface of the reinforced concrete pillar 10, and thus, the reinforced concrete in the same manner as the pillar formwork of the first embodiment described above as a whole. The pillar 10 will be constructed.

한편, 도 7(a)에서는 비탈면 보강공(S4)에 기둥철근(11)이 긴결 설치된 것을 확인할 수 있다. 보는 바와 같이 비탈면 보강공(S4)의 돌출 두부에 철근정착판(S42)을 연결 설치한 후 철근정착판(S42)에 주철근(11a)을 기대게 배근하고 띠철근(11b)으로 둘러 감는 방식으로 기둥철근(11)을 배근하고 있다. 이러한 배근으로 비탈면 보강공(S4)의 철근콘크리트기둥(10)에 대한 정착능력을 향상시킬 수 있다.
On the other hand, in Figure 7 (a) it can be confirmed that the column reinforcing bar 11 is installed in the slope slope reinforcing hole (S4). As shown, after connecting the rebar fixing plate S42 to the protruding head of the slope-surface reinforcing hole S4, the reinforcing bar 11a is leaned on the rebar fixing plate S42 and wound around the band reinforcing bars 11b. The column reinforcement 11 is arranged. Such reinforcement can improve the fixing ability for the reinforced concrete pillar 10 of the slope surface reinforcing hole (S4).

이상에서 본 발명은 구체적인 실시예를 참조하여 상세히 설명되었으나, 실시예는 본 발명을 예시하기 위한 것일 뿐이므로, 본 발명의 기술적 사상을 벗어나지 않는 범위 내에서 치환, 부가 및 변형된 실시 형태들 역시 아래에 첨부한 특허청구범위에 의하여 정하여지는 본 발명의 보호범위에 속한다고 할 것이다.
The present invention has been described in detail above with reference to specific embodiments, but the embodiments are only for illustrating the present invention, and thus the embodiments substituted, added, and modified within the scope without departing from the spirit of the present invention are also described below. It will be said to belong to the protection scope of the present invention as defined by the claims appended hereto.

10: 철근콘크리트기둥
11: 기둥철근
12: 기둥콘크리트
13: 연속홈
20: 앵커
21: 정착볼트
22: 고정너트
23: 고정와셔
24: 조절너트
25: 철근스페이서
31: 식생매트
32: 보호철망
33: 돌망태
41: 식생토
42: 보강그리드
43: 채움돌
100: 기둥거푸집
110aa: 후면평판
110b: 후면각재
120: 조립틀
120a, 120b: 구성각편
130, 140: 결속구
F: 기초
S: 비탈면
S1: 지반 표면
S2: 부직포
S3: 배수판
S4: 비탈면 보강공
S41: 숏크리트
S42: 철근정착판
10: reinforced concrete column
11: column rebar
12: pillar concrete
13: continuous groove
20: anchor
21: fixing bolt
22: fixing nut
23: fixed washer
24: Adjustment nut
25: Rebar spacer
31: vegetation mat
32: protective wire mesh
33: Gabion
41: vegetation soil
42: reinforcing grid
43: Filling Stone
100: pillar formwork
110aa: rear flat
110b: back angle
120: assembly frame
120a, 120b: Configuration
130, 140: Binding
F: base
S: slope
S1: ground surface
S2: Nonwoven
S3: drain plate
S4: slope reinforcement
S41: shotcrete
S42: Rebar fixing plate

Claims (10)

깎기 또는 쌓기 비탈면(S)이나 호안 비탈면(S)에 옹벽을 시공함에 있어,
안정화된 비탈면(S) 전면에 기둥거푸집(100)을 설치하고 기둥철근(11)을 배근하고 기둥콘크리트(12)를 타설하는 과정을 통해 철근콘크리트기둥(10)을 비탈면(S)을 따라 띄엄띄엄 시공하되, 기둥거푸집(100) 전면을 관통 돌출하도록 앵커(20)를 설치하여 앵커(20)가 철근콘크리트기둥(10) 전면에 돌출 정착하도록 시공하는 제1단계;
철근콘크리트기둥(10) 전면에서 철근콘크리트기둥(10) 사이를 연결하도록 배치되는 식생매트(31)와 식생매트(31)를 덮는 보호철망(32)을 앵커(20)에 고정 설치하고, 비탈면(S)과 식생매트(31) 사이에 식생토(41)를 다짐하면서 채우는 제2단계; 그리고,
옹벽 높이로 상기 제2단계를 반복 실시하는 제3단계;를 포함하여 이루어지되,
상기 제1단계의 기둥거푸집(100)은,
철근콘크리트기둥(10)의 후면을 형성하는 부분으로, 비탈면(S) 전면에 놓이도록 설치되는 후면평판(110a);
철근콘크리트기둥(10)의 후면 이외의 다른 면을 형성하는 부분으로, 상기 후면평판(110a)에 제1결속구(130)에 의해 조립식으로 고정 설치되는 한편 횡방향으로 분할된 둘 이상의 구성각편(120a, 120b)이 제2결속구(140)에 의해 조립 구성되는 조립틀(120);을 포함하여 구성된 것이며,
상기 제1단계는,
후면평판(110a)을 설치하고 조립틀(120)의 일부 구성각편(120a)을 설치하면서 기둥거푸집(100)을 설치하는 제1A단계;
조립틀(120)의 나머지 구성각편(120b)을 조립하는 제1B단계;
기둥거푸집(100) 내부에 기둥콘크리트(12)를 타설하는 제1C단계;
로 이루어지되, 상기 제1A단계 또는 제1B단계는 기둥거푸집(100) 내부에 기둥철근(11)을 배근하고 기둥거푸집의 조립틀(120) 전면을 관통 돌출하도록 앵커(20)를 조립틀(120)에 고정 설치하는 과정을 포함하면서 진행하는 것을 특징으로 하는 강화 녹화옹벽 시공방법.
In constructing the retaining wall on the cutting or stacking slope (S) or the rake slope (S),
The reinforcement concrete pillars 10 are spaced along the slopes S by installing pillar formwork 100 on the stabilized slope surface S, laying the pillar reinforcement 11 and placing the pillar concrete 12. To construct, the first step of installing the anchor 20 so as to protrude through the front of the pillar formwork 100, the anchor 20 protrudes and fixed to the front of the reinforced concrete pillar (10);
The vegetation mat 31 and the protective wire mesh 32 covering the vegetation mat 31 disposed to connect between the reinforced concrete pillars 10 at the front of the reinforced concrete pillar 10 are fixedly installed on the anchor 20 and sloped ( A second step of filling the vegetation soil 41 between S) and the vegetation mat 31; And,
A third step of repeating the second step at the height of the retaining wall;
The pillar formwork 100 of the first step,
A part forming the rear surface of the reinforced concrete column 10, the rear plate 110a being installed to be placed on the front surface of the slope (S);
Two or more components each of which forms a surface other than the rear surface of the reinforced concrete column 10, which is prefabricated and fixed by the first binding hole 130 on the rear plate 110a, and is divided in the transverse direction ( 120a, 120b is configured to include; assembly frame 120 is assembled by the second binding port 140, including,
The first step,
A first step of installing the column formwork 100 while installing the rear flat plate 110a and installing each component 120a of the assembly frame 120;
Step 1B of assembling the remaining component pieces (120b) of the assembly frame 120;
1C step of pouring pillar concrete 12 into the pillar formwork 100;
Wherein, step 1A or step 1B is a step of placing the anchor reinforcing the reinforcing bar 11 in the pillar formwork 100 and through the assembly frame 120 of the pillar formwork through the assembly frame 120 Reinforcing green retaining wall construction method characterized in that proceeding while including a fixed installation process.
깎기 또는 쌓기 비탈면(S)이나 호안 비탈면(S)에 옹벽을 시공함에 있어,
안정화된 비탈면(S) 전면에 기둥거푸집(100)을 설치하고 기둥철근(11)을 배근하고 기둥콘크리트(12)를 타설하는 과정을 통해 철근콘크리트기둥(10)을 비탈면(S)을 따라 띄엄띄엄 시공하되, 기둥거푸집(100) 전면을 관통 돌출하도록 앵커(20)를 설치하여 앵커(20)가 철근콘크리트기둥(10) 전면에 돌출 정착하도록 시공하는 제1단계;
철근콘크리트기둥(10) 전면에서 철근콘크리트기둥(10) 사이를 연결하도록 배치되는 식생매트(31)와 식생매트(31)를 덮는 보호철망(32)을 앵커(20)에 고정 설치하고, 비탈면(S)과 식생매트(31) 사이에 식생토(41)를 다짐하면서 채우는 제2단계; 그리고,
옹벽 높이로 상기 제2단계를 반복 실시하는 제3단계;를 포함하여 이루어지되,
상기 제1단계의 기둥거푸집(100)은,
철근콘크리트기둥(10)의 후면 너비 간격으로 이격하게 비탈면(S) 전면에 고정 설치되는 한 쌍의 후면각재(110b);
철근콘크리트기둥(10)의 측면과 전면을 형성하기 위한 부분으로, 상기 한 쌍의 후면각재(110b)에 제1결속구(130)에 의해 조립식으로 고정 설치되는 한편 횡방향으로 분할된 둘 이상의 구성각편(120a, 120b)이 제2결속구(140)에 의해 조립 구성되는 조립틀(120);을 포함하여 구성된 것이며,
상기 제1단계는,
후면각재(110b)를 고정 설치하고 조립틀(120)의 일부 구성각편(120a)을 설치하면서 기둥거푸집(100)을 설치하는 제1A단계;
조립틀(120)의 나머지 구성각편(120b)을 조립하는 제1B단계;
기둥거푸집(100) 내부에 기둥콘크리트(12)를 타설하는 제1C단계;
로 이루어지되, 상기 제1A단계 또는 제1B단계는 기둥거푸집(100) 내부에 기둥철근(11)을 배근하고 기둥거푸집의 조립틀(120) 전면을 관통 돌출하도록 앵커(20)를 조립틀(120)에 고정 설치하는 과정을 포함하면서 진행하는 것을 특징으로 하는 강화 녹화옹벽 시공방법.
In constructing the retaining wall on the cutting or stacking slope (S) or the rake slope (S),
The reinforcement concrete pillars 10 are spaced along the slopes S by installing pillar formwork 100 on the stabilized slope surface S, laying the pillar reinforcement 11 and placing the pillar concrete 12. To construct, the first step of installing the anchor 20 so as to protrude through the front of the pillar formwork 100, the anchor 20 protrudes and fixed to the front of the reinforced concrete pillar (10);
The vegetation mat 31 and the protective wire mesh 32 covering the vegetation mat 31 disposed to connect between the reinforced concrete pillars 10 at the front of the reinforced concrete pillar 10 are fixedly installed on the anchor 20 and sloped ( A second step of filling the vegetation soil 41 between S) and the vegetation mat 31; And,
A third step of repeating the second step at the height of the retaining wall;
The pillar formwork 100 of the first step,
A pair of rear shell materials 110b fixedly installed on the front surface of the inclined surface S at intervals of the rear width of the reinforced concrete column 10;
A portion for forming the side and the front surface of the reinforced concrete pillar 10, two or more components that are fixed in the prefabricated by the first binding holes 130 to the pair of rear shell member 110b and divided in the transverse direction It is configured to include; each piece (120a, 120b) is assembled frame 120 is assembled by the second binding port 140,
The first step,
1A step of installing the pillar formwork 100 while fixing and installing the rear angler 110b and installing some component angle pieces 120a of the assembly frame 120;
Step 1B of assembling the remaining component pieces (120b) of the assembly frame 120;
1C step of pouring pillar concrete 12 into the pillar formwork 100;
Wherein, step 1A or step 1B is a step of placing the anchor reinforcing the reinforcing bar 11 in the pillar formwork 100 and through the assembly frame 120 of the pillar formwork through the assembly frame 120 Reinforcing green retaining wall construction method characterized in that proceeding while including a fixed installation process.
제2항에서,
상기 제1단계 앞서 숏크리트로 마무리하면서 소일네일에 의한 비탈면 보강공(S4)으로 비탈면(S)을 안정화시키는 단계;가 더 포함되며,
상기 제1A단계는 후면각재(110b)를 경화하기 전의 숏크리트 표면에 설치하면서 이루어지는 것을 특징으로 하는 강화 녹화옹벽 시공방법.
In claim 2,
Stabilizing the inclined surface (S) by the slope surface reinforcing hole (S4) by the small nail while finishing with the shotcrete prior to the first step;
The step 1A is reinforced green retaining wall construction method characterized in that the installation is made on the shotcrete surface before curing the back shell (110b).
제1항 내지 제3항 중 어느 한 항에서,
상기 제2단계는,
식생토(41)를 1차 채움하여 다짐하는 제2A단계;
식생토(41) 위에 보강그리드(42)를 수평으로 포설하는 제2B단계;
보강그리드(42) 위에 식생토(41)를 2차 채움하여 다짐하는 제2C단계;
로 이루어지는 것을 특징으로 하는 강화 녹화옹벽 시공방법.
The method according to any one of claims 1 to 3,
The second step,
Step 2A of first filling the vegetation soil 41 to compact;
A second step B of horizontally laying the reinforcing grid 42 on the vegetation soil 41;
A second step C2 of filling vegetation soil 41 on the reinforcing grid 42 to be compacted;
Reinforced greening retaining wall construction method comprising the.
제1항 내지 제3항 중 어느 한 항에서,
상기 제1단계와 제2단계 사이에, 철근콘크리트기둥(10) 전면에서 돌망태로 철근콘크리트기둥(10) 사이를 연결하도록 배치한 돌망태를 앵커에 고정 설치하고 비탈면(S)과 돌망태 사이에 채움돌을 채우는 하부옹벽 시공단계;가 더 포함되며,
상기 제2단계는, 상기 하부옹벽 시공단계를 통해 시공된 하부옹벽 위로 실시하여 상부옹벽을 시공하는 과정으로 이루어지는 것을 특징으로 하는 강화 녹화옹벽 시공방법.
The method according to any one of claims 1 to 3,
Between the first step and the second step, the gabions arranged to connect between the reinforced concrete pillars 10 from the front of the reinforced concrete pillars 10 to the gabions fixedly installed in the anchor and the filling stone between the slope (S) and the gabion Filling the lower retaining wall construction step; further includes,
The second step is a reinforced green retaining wall construction method comprising the step of constructing the upper retaining wall by performing over the lower retaining wall constructed through the lower retaining wall construction step.
삭제delete 삭제delete 삭제delete 삭제delete 삭제delete
KR1020100007894A 2010-01-28 2010-01-28 Construction method of reinforced green retaining wall KR100968518B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100007894A KR100968518B1 (en) 2010-01-28 2010-01-28 Construction method of reinforced green retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100007894A KR100968518B1 (en) 2010-01-28 2010-01-28 Construction method of reinforced green retaining wall

Publications (1)

Publication Number Publication Date
KR100968518B1 true KR100968518B1 (en) 2010-07-08

Family

ID=42645275

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100007894A KR100968518B1 (en) 2010-01-28 2010-01-28 Construction method of reinforced green retaining wall

Country Status (1)

Country Link
KR (1) KR100968518B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102542373B1 (en) 2023-03-14 2023-06-13 에스와이건설 주식회사 Plant planting structure utilizing plants planting soil bag

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09189028A (en) * 1995-11-08 1997-07-22 Shimizu Corp Slope face protective work and its work execution method
JPH10183649A (en) * 1996-12-21 1998-07-14 Takaaki Endo Construction method for retaining wall for greening
KR100306045B1 (en) * 1999-03-31 2001-10-29 이영렬 Shore protection construction material for vegetation and construction method by using the same

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09189028A (en) * 1995-11-08 1997-07-22 Shimizu Corp Slope face protective work and its work execution method
JPH10183649A (en) * 1996-12-21 1998-07-14 Takaaki Endo Construction method for retaining wall for greening
KR100306045B1 (en) * 1999-03-31 2001-10-29 이영렬 Shore protection construction material for vegetation and construction method by using the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102542373B1 (en) 2023-03-14 2023-06-13 에스와이건설 주식회사 Plant planting structure utilizing plants planting soil bag

Similar Documents

Publication Publication Date Title
KR100813236B1 (en) The structure for a slope reinforcement and eco slope reinforcement method
KR100737768B1 (en) Environmental vegetation mat pannels
KR100793985B1 (en) Method and structure of slope reinforce
KR101077949B1 (en) Block for reinforcement and construction method
JP2017155574A (en) Construction method of retaining wall
KR100764019B1 (en) Vertational soil slope structure and method
KR100763443B1 (en) Retaining wall having eco-blocks and constructing method thereof
KR101963362B1 (en) Reinforced gabion retaining wall capable of completely drainage and construction method thereof
KR100968518B1 (en) Construction method of reinforced green retaining wall
KR102116085B1 (en) A Eco-friendly retain wall structure
KR100665338B1 (en) Latticed assembly of retaing wall with soil nailing and anchor
KR20060108900A (en) Slope-protect weight block for prevent degradation
KR101342130B1 (en) Eco greening and reinforcing facilities for slope of road
KR101501733B1 (en) The eco-friendly precast l type retaining wall fixed with an anchor
JP2001172936A (en) Ground face protection structure and construction method therefor
KR101334749B1 (en) Vegetation block in tiers for retaining wall and method for construction of retaining wall using the same
KR20090035951A (en) Retaining wall for easy drainage and it's construction work method thereof
JP3643114B2 (en) Concrete building block retaining wall and method for constructing concrete building block retaining wall
KR102064538B1 (en) Reinforced gabion retaining wall and construction method thereof
KR102064537B1 (en) Reinforced gabion retaining wall and construction method thereof
JP2006083697A (en) Reinforced earth structure and wall surface block
KR200387012Y1 (en) Retaining wall having a fuction of landscape architecture
JP2547946B2 (en) Reinforced soil structure
JP7109840B1 (en) Embankment reinforced wall and construction method of embankment reinforced wall
KR200424468Y1 (en) latticed assembly of retaing wall with soil nailing

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130516

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20140513

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20150528

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20160520

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20170519

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20180518

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20190522

Year of fee payment: 10