KR100949937B1 - Epoxy injection equipment to both direction movement worktable of crack repair-reinforcement for concret structure - Google Patents

Epoxy injection equipment to both direction movement worktable of crack repair-reinforcement for concret structure Download PDF

Info

Publication number
KR100949937B1
KR100949937B1 KR1020090072446A KR20090072446A KR100949937B1 KR 100949937 B1 KR100949937 B1 KR 100949937B1 KR 1020090072446 A KR1020090072446 A KR 1020090072446A KR 20090072446 A KR20090072446 A KR 20090072446A KR 100949937 B1 KR100949937 B1 KR 100949937B1
Authority
KR
South Korea
Prior art keywords
epoxy
coupled
rail
piston
unit
Prior art date
Application number
KR1020090072446A
Other languages
Korean (ko)
Inventor
김종만
Original Assignee
한세이엔씨(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한세이엔씨(주) filed Critical 한세이엔씨(주)
Priority to KR1020090072446A priority Critical patent/KR100949937B1/en
Application granted granted Critical
Publication of KR100949937B1 publication Critical patent/KR100949937B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0203Arrangements for filling cracks or cavities in building constructions
    • E04G23/0211Arrangements for filling cracks or cavities in building constructions using injection
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05CAPPARATUS FOR APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05C17/00Hand tools or apparatus using hand held tools, for applying liquids or other fluent materials to, for spreading applied liquids or other fluent materials on, or for partially removing applied liquids or other fluent materials from, surfaces
    • B05C17/005Hand tools or apparatus using hand held tools, for applying liquids or other fluent materials to, for spreading applied liquids or other fluent materials on, or for partially removing applied liquids or other fluent materials from, surfaces for discharging material from a reservoir or container located in or on the hand tool through an outlet orifice by pressure without using surface contacting members like pads or brushes

Abstract

PURPOSE: An epoxy injection device with a movable worktable for repairing and reinforcing a concrete structure is provided to automatically inject epoxy into a cracked part and repair and reinforce the cracked part at heights. CONSTITUTION: An epoxy injection device with a movable worktable for repairing and reinforcing a concrete structure comprises a support(10), a moving plate(40), a worktable(20), an epoxy supply part(30), and a transfer device. A supporter(14) coupled with a wheel(16) is installed on the lower side of the support. The moving plate is transferred in the traverse direction through a rail(60). The worktable is installed on the upper part of a lift(43) installed on the moving plate. An epoxy injection part connects to the epoxy supply part. The epoxy injection part injects the epoxy into a cracked part. The transfer device transfers the supporter.

Description

콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치{Epoxy injection equipment to both direction movement worktable of crack repair-reinforcement for concret structure}Epoxy injection equipment to both direction movement worktable of crack repair-reinforcement for concret structure}

본 발명은 콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치에 관한것으로 상세하게는 바퀴가 결합된 지지대가 하측면에 설치되어지는 받침판과, 상기 받침판의 상측에 설치되는 레일을 통해 횡방향으로 이송되어지는 이송판과, 이송판 상측에 설치되는 리프트부의 상측에 설치되는 작업대와, 군열 및 파손부에 에폭시를 주입하는 에폭시 주입부가 연결된 에폭시 공급부와, 상기 지지대의 바퀴를 가이드하는 레일과, 상기 지지대를 이송시키는 이송장치를 포함하여 구성되는 것을 특징으로 하는 콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치에 관한 것이다.The present invention relates to an epoxy injection device having a bi-directional movable workbench for reinforcement of cracks in concrete structures, and in particular, a support plate with wheels coupled thereto is provided on a lower side of the support plate, and a rail installed on an upper side of the support plate. A rail for guiding the wheels of the support plate; And it relates to an epoxy injection device having a bi-directional movable workbench for reinforcing the cracks of the concrete structure, characterized in that it comprises a transfer device for transporting the support.

종래에 터널의 내부벽면 공사에 있어서는 별도의 장치가 없이 이동식 대차등으로 작업원이 이동하면서 부직포와 방수쉬트 설치 및 설치전 면정리, 터널 라이닝 작업후의 그라우칭작업, 터널내 조명시설 설치 및 환기용 제트휀 설치, 터널완성 후 내부의 도장 및 타일붙임, 터널의 정기적인 청소 및 유지관리 보수를 하였으나, 이는 터널내부에 설치하려는 재료 및 작업용구의 무게로 인해 천정부분이나 높은 벽면 작업시 핸들링에 불편함이 있으며 작업자의 추락등의 위험 요인과 작업원의 불안정한 자세로 인하여 작업상의 어려움이 있다. 따라서 작업자는 작업환경이 나빠서 쉽게 피로를 느끼고 추락의 위험부담이 커서 작업능률이 떨어지며 이로 인한 작업속도의 지연등의 문제점이 있다.Conventionally, in the construction of the inner wall of a tunnel, there is no separate device, and the worker moves on a mobile cart, and the nonwoven fabric and the waterproof sheet are installed and cleaned before installation, the grouting work after the tunnel lining work, and the lighting facility is installed and ventilated. After the installation of the jet, the interior painting and tile installation after the completion of the tunnel, the regular cleaning and maintenance of the tunnel, but due to the weight of the materials and work tools to be installed inside the tunnel, There are inconveniences and difficulties in work due to risk factors such as falling of the worker and unstable posture of the worker. Therefore, the worker feels tired easily due to the bad working environment, and the risk of falling is large so that the work efficiency is reduced, resulting in a delay in work speed.

상기의 문제를 해결하기 위하여 차량의 통행이 가능하도록 받침판과 지지대 간에 아무런 지지부를 설치하지 않고, 리프트부와 높낮이 조절부를 통해 보수장치의 높이를 조절하여 높은 곳의 균열부도 보수 및 보강 할 수 있으며, 에폭시 주입부가 자동으로 에폭시를 균열부에 주입하므로 인력을 소비하지 않아도 되는 콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치를 제공하는데 그 목적이 있다.In order to solve the above problem, without any support between the support plate and the support to allow the traffic of the vehicle, it is possible to repair and reinforce the crack in the high place by adjusting the height of the repair device through the lift part and the height adjustment part, It is an object of the present invention to provide an epoxy injection device having a bi-directional movable workbench for reinforcing cracks in concrete structures that do not consume manpower because the epoxy injection unit automatically injects epoxy into the cracks.

상기의 과제를 해결하기 위한 본 발명은 콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치에 관한것으로서 바퀴가 결합된 지지대가 하측면에 설치되어지는 받침판과, 상기 받침판의 상측에 설치되는 레일을 통해 횡방향으로 이송되어지는 이송판과, 이송판 상측에 설치되는 리프트부의 상측에 설치되는 작업대와, 군열 및 파손부에 에폭시를 주입하는 에폭시 주입부가 연결된 에폭시 공급부와, 상기 지지대의 바퀴를 가이드하는 레일과, 상기 지지대를 이송시키는 이송장치를 포함하여 구성되어진다.The present invention for solving the above problems relates to an epoxy injection device having a bi-directional movable workbench for reinforcement of cracks in a concrete structure, and a support plate on which wheels are coupled is installed on a lower side, and installed on an upper side of the support plate. A transfer plate conveyed in the transverse direction through the rail, a workbench installed above the lift unit installed above the transfer plate, an epoxy supply unit connected to an epoxy injection unit for injecting epoxy into the group line and the damaged part, and wheels of the support plate It is configured to include a rail for guiding the transfer device for transferring the support.

본 발명은 차량의 통행이 가능하도록 받침판과 지지대 간에 아무런 지지부를 설치하지 않고, 리프트부와 높낮이 조절부를 통해 보수장치의 높이를 조절하여 높은 곳의 균열부도 보수 및 보강 할 수 있으며, 에폭시 주입부가 자동으로 에폭시를 균열부에 주입하므로 인력을 소비하지 않아도 되는 효과가 있다.The present invention can repair and reinforce the cracks of high places by adjusting the height of the repair device through the lift portion and the height adjustment unit without installing any support portion between the support plate and the support to allow the passage of the vehicle, and the epoxy injection portion is automatically By injecting the epoxy into the cracks there is an effect that does not have to consume manpower.

본 발명은 터널 또는 콘크리트 구조물의 균열부 보수 보강을 위한 보수장치에 있어서, 터널의 양측차선 외측 바닥에 차선을 따라 설치되어지는 레일(60)과; 상기 레일(60)을 따라 이동되는 바퀴(16)가 하단에 결합되고 터널벽측 양측에 작업발판(15)이 형성되는 지지대(14)가 하측에 다수 결합되어지며, 상측면에 레일(6)의 횡방향으로 이송레일(11)이 설치되고, 상기 이송레일(11) 상에 설치되는 이동판(40)을 이송레일(11)을 따라 이송시키는 횡방향 이송장치(12)가 설치되는 받침대(10)와; 상기 받침대(10)의 상측면에 설치된 이송레일(11)을 따라 이동되는 바퀴가 결합되어지고, 상측면에 유압모터(42)의 유압으로 상하강 되어지는 리프트부(43)가 설치되며, 상기 횡방향 이송장치(12)에 연결되는 와이어로 이송되어지는 이동판(40)과; 상기 이송레일(11) 상에 설치되는 이동판(40)의 상측에 형성되는 리프트부(43)의 상측에 결합되어지고, 상측면 테두리에 사용자의 안전을 위한 보호대(21)가 결합되어지며, 에폭시 주입부(70)가 연결되어 에폭시를 공급하는 에폭시 공급부(30)가 설치되는 작업대(20)와; 상기 지지대(14)의 전측 또는 후측에 케이블이 연결되어 레일(60)을 따라 지지대(14)가 이동되어지도록 터널의 입구 또는 출구에 설치되어지는 이송장지(90);를 포함하여 구성되어진다.The present invention provides a repair device for repairing a crack or reinforcing a crack of a tunnel or concrete structure, comprising: a rail 60 installed along a lane at an outer bottom of both lanes of the tunnel; The wheel 16 moving along the rail 60 is coupled to the lower end and the support 14 is formed on the lower side of the tunnel wall is formed on both sides of the tunnel 15 is coupled to the lower side, the upper side of the rail (6) Pedestal 10 is provided with a transport rail 11 in the transverse direction, the transverse conveying device 12 for transporting the moving plate 40 installed on the conveying rail 11 along the conveying rail 11 )Wow; Wheels that are moved along the transport rails 11 installed on the upper side of the pedestal 10 is coupled, and the upper portion is provided with a lift unit 43 for lifting up and down by hydraulic pressure of the hydraulic motor 42, A moving plate 40 which is conveyed by a wire connected to the transverse conveying apparatus 12; Is coupled to the upper side of the lift portion 43 formed on the upper side of the moving plate 40 installed on the conveying rail 11, the guard 21 for the safety of the user is coupled to the upper side edge, A work bench 20 to which an epoxy injecting unit 70 is connected and an epoxy supply unit 30 for supplying epoxy is installed; It is configured to include; a transport medium 90 is installed at the inlet or outlet of the tunnel so that the cable is connected to the front or rear of the support 14 to move the support 14 along the rail 60.

이러한 상기 에폭시 주입부(70)는 일측에 토출부(71)가 형성되어지고, 타측이 절개되어지는 실린더부(76)의 타측에 삽입되어지며, 실린더부(76) 내부에 주입되는 에폭시를 토출부(71) 측으로 토출시키도록 피스톤부가 삽입되어지며, 상기 피스톤부는 실린더부(76)의 내부에 삽입되어지는 피스톤(72)과, 상기 피스톤(72)의 중심에 형성되는 홀에 삽입되어 피스톤(72)의 홀을 개폐하는 벨브(73)와, 상기 피 스톤(72)의 타측면에 결합되어 실린더부(76)의 타측면에 결합되는 덮개부(74)에 지지되어지는 탄성부(75)와, 상기 피스톤(72)의 홀에 연결되어 에폭시 공급부(30)에서 에폭시가 공급되어지는 공급관(31)과, 상기 공급관(31)이 관통되어지며, 상기 실린더부(76)의 타측에 결합되어지는 덮개부(74)로 구성되며, 상기 토출부(71)에는 중단부가 접시형태로 형성되어 다수의 실링홀(81)이 형성되는 접시판(84)과, 벽면에 삽입되어 에폭시를 주입하도록 다수의 홀(82)이 형성된 분사구(83)로 구성되는 분사부(80)가 결합되어지는 것을 포함하여 구성되어진다.The epoxy injection portion 70 is discharge portion 71 is formed on one side, the other side is inserted into the other side of the cylinder portion 76 is cut, discharge the epoxy injected into the cylinder portion 76 A piston part is inserted to discharge to the part 71 side, and the piston part is inserted into a piston 72 inserted into the cylinder part 76 and a hole formed in the center of the piston 72 so that the piston ( An elastic portion 75 supported by a valve 73 for opening and closing a hole of the 72 and a lid portion 74 coupled to the other side of the piston 72 and coupled to the other side of the cylinder portion 76. And a supply pipe 31 connected to the hole of the piston 72 to which epoxy is supplied from the epoxy supply part 30, and the supply pipe 31 penetrated and coupled to the other side of the cylinder part 76. It consists of a cover portion 74, the discharge portion 71 has a stop portion formed in the form of a plate a plurality of seals Including the plate portion 84 is formed, the hole 81 is formed, and the injection portion 80 composed of the injection hole 83 is formed in a plurality of holes 82 is inserted into the wall surface to inject the epoxy is coupled It is done.

그리고, 상기 지지대(14)와 바퀴 간에는 상기 지지대(14)의 높낮이를 조절할 수 있도록 높낮이 조절부(50)가 형성되어진다.And, the height adjustment unit 50 is formed between the support 14 and the wheel to adjust the height of the support (14).

즉, 본 발명을 좀더 상세하게 설명하면 다음과 같다.That is, the present invention will be described in more detail as follows.

터널의 양측 차선 외측 지면에 차선을 따라 레일(60)이 설치되어지고, 상측면에 상기 레일(60)의 횡방향으로 이송레일(11)과 횡방향 이송장치(12)가 설치되며, 하측에는 하단에 바퀴가 형성된 다수개의 지지대(14)가 결합되고, 상기 레일(60)상에 위치하여 레일(60)을 따라 이동어지는 받침대(10)와, 상기 받침대(10)의 상측면에 형성된 이송레일(11) 상에 설치되어 이송레일(11)을 따라 이동되며, 유압모터(42)로 동작되는 유압실린더(41)를 통해 상하강 되어지는 리프트부(43)가 설치되고, 횡방향 이송장치(12)와 와이어로 연결되어 횡방향 이송장치(12)의 작동으로 이송레일(11)상에서 이송되어지는 이동판(40)과, 사람이 보수 및 보강 작업을 할 수 있으며 에폭시 주입부(70)가 연결되는 에폭시 공급부(30)가 설치되고, 테두리에 안전사고를 방지하는 보호대(21)가 결합되며, 상기 리프트부(43)의 상측에 설치되는 작업대(20)와, 상기 지지대(14)와 케이블로 연결되어 지지대(14)를 레일(60)을 따라 이송시키는 이송장치(90)가 터널의 입구 또는 출구에 설치되어지는 것을 포함하여 구성되어진다.Rails 60 are installed along the lanes on both sides of the lane outer surface of the tunnel, and a conveying rail 11 and a transverse conveying device 12 are installed in the transverse direction of the rails 60 on the upper side thereof. A plurality of supports 14 having wheels formed at the bottom thereof are coupled to each other, the pedestal 10 being positioned on the rail 60 and moving along the rail 60, and a conveying rail formed at an upper side of the pedestal 10. It is installed on the (11) is moved along the conveying rail (11), the lifting unit 43 which is moved up and down through the hydraulic cylinder (41) operated by the hydraulic motor 42 is installed, the transverse conveying device ( 12) and the moving plate 40 to be transferred on the conveying rail 11 by the operation of the lateral conveying device 12 is connected to the wire, the person can repair and reinforcement work and the epoxy injection unit 70 Epoxy supply unit 30 to be connected is installed, the guard 21 to prevent safety accidents are coupled to the rim The work table 20 installed on the upper side of the lift unit 43 and the transfer device 90 connected to the support 14 and the cable to transfer the support 14 along the rail 60 have an entrance to the tunnel. Or it is comprised including what is installed in an exit.

상기 지지대(14)와 바퀴 간에는 높낮이 조절부(50)가 형성되어 받침대(10)의 높낮이를 조절할 수 있고, 전후방에 위치한 지지대(14) 간에는 접혀지는 작업발판(15)이 설치되어 측 벽면의 보수 및 보강 작업을 할 수 있도록 한다.The height adjustment unit 50 is formed between the support 14 and the wheels to adjust the height of the pedestal 10, and the work footrest 15 is installed between the support 14 located in the front and rear is installed to repair the side wall And reinforcement work.

상기 이송장치(90)를 통해 지지대(14)는 터널 또는 콘크리트 구조물의 길이방향으로 설치된 레일(60)을 따라 전후 방향으로 이동되어지고, 상기 횡방향 이송장치(12)를 통해 상기 이동판(40)이 이송레일(11)을 따라 횡방향으로 이송되어진다.The support 14 is moved in the front-rear direction along the rail 60 installed in the longitudinal direction of the tunnel or the concrete structure through the transfer device 90, and the moving plate 40 through the lateral transfer device 12. ) Is transported in the transverse direction along the transport rail (11).

그리고, 상기 에폭시 주입부(70)는 실린더부(76)와 덮개부(74)가 결합된 피스톤부 및 분사부(80)로 구성되어진다.In addition, the epoxy injection portion 70 is composed of a piston portion and the injection portion 80 is coupled to the cylinder portion 76 and the cover portion 74.

상기의 실린더부(76)는 일측에 토출부(71)가 형성되고, 원통형의 형상으로 형성되어지며, 타측에 덮개부(74)가 결합되는 나사산이 형성되어진다.The cylinder portion 76 is the discharge portion 71 is formed on one side, is formed in a cylindrical shape, the other side is formed with a screw thread to which the cover portion 74 is coupled.

상기 피스톤부는 중심에 홀이 형성되어 홀을 개폐하는 벨브(73)가 결합된 피스톤(72)과, 상기 피스톤(72)의 타측면에 탄성부(75)가 결합되며, 피스톤(72)의 타측면 홀에 에폭시 공급부(30)와 연결된 에폭시를 공급하는 공급관(31)이 결합되어지고, 상기 공급관(31)이 관통되어지며 탄성부(75)의 타단이 결합되어 상기 실린더부(76)의 나사산에 회전으로 결합되어지는 덮개부(74)로 구성되어진다.The piston portion has a hole formed in the center of the piston 72 is coupled to the valve 73 for opening and closing the hole, the elastic portion 75 is coupled to the other side of the piston 72, the other of the piston 72 A supply pipe 31 for supplying an epoxy connected to the epoxy supply unit 30 to the side hole is coupled, the supply pipe 31 is penetrated, and the other end of the elastic unit 75 is coupled to the thread of the cylinder unit 76. It consists of a cover portion 74 which is coupled to the rotation.

상기 분사부(80)는 중단부가 접시형태로 형성되어 다수의 실링홀(81)이 형성되는 접시판(84)과, 벽면에 삽입되어 에폭시를 주입하도록 다수의 홀(82)이 형성된 분사구(83)와, 상기 토출부(71)와 결합되어지는 결합부로 구성되어진다.The injection unit 80 has a stop plate formed in the shape of a plate, and a plurality of plate plates 84 having a plurality of sealing holes 81 formed therein, and a plurality of holes 82 formed to be inserted into a wall to inject epoxy. ) And a coupling part to be coupled to the discharge part 71.

이러한 상기 에폭시 주입부(70)를 이용하여 보수 및 보강을 하는 방법은 분사부(80)를 벽면에 삽입홀을 형성하여 미리 삽입하고, 실링홀(81)을 통해 접착제로 분사부(80)를 벽면에 고정시킨뒤 실린더부(76)의 토출부(71)와 결합부를 결합시킨다.In the repair and reinforcement method using the epoxy injection unit 70, the injection unit 80 is inserted in advance by forming an insertion hole in the wall, and the injection unit 80 is formed of an adhesive through the sealing hole 81. After fixing to the wall surface coupled to the discharge portion 71 and the coupling portion of the cylinder portion 76.

그런뒤 상기 피스톤부의 피스톤(72) 타측에 덮개부(74)를 관통하는 공급관(31)의 끝단을 결합하고, 상기 덮개부(74)를 실린더부(76)와 결합시킨뒤 토출부(71)에 주입부(70)의 결합부를 결합한다.Then, the end of the supply pipe 31 passing through the cover portion 74 is coupled to the other side of the piston 72 of the piston portion, and the cover portion 74 is coupled with the cylinder portion 76 and then the discharge portion 71. Combine the coupling of the injection unit 70 to.

그리고, 에폭시를 에폭시 공급부(30)에서 공급관(31)을 통해 실린더부(76) 내부로 주입하면 벨브(73)가 열리며 피스톤(72) 일측과 실린더부(76)의 내부측 간의 공간에 주입되어지고, 이로인해 피스톤(72)이 타측으로 이동되어 에폭시가 실린더부(76)의 내부에 저장되어진다.Then, when epoxy is injected into the cylinder portion 76 through the supply pipe 31 from the epoxy supply portion 30, the valve 73 is opened and injected into the space between one side of the piston 72 and the inner side of the cylinder portion 76. This causes the piston 72 to move to the other side so that the epoxy is stored in the cylinder portion 76.

그런뒤 상기 공급관(31)을 덮개부(74) 외측에서 절단하면 상기 벨브(73)가 피스톤(72)을 미는 탄성부(75)의 힘으로 인해 닫히게되고, 탄성부(75)의 압력으로 분사부(80)를 통해 벽면의 내부로 주입되어진다.Then, when the supply pipe 31 is cut outside the cover portion 74, the valve 73 is closed due to the force of the elastic portion 75 that pushes the piston 72, and the pressure is reduced by the pressure of the elastic portion 75. It is injected into the wall through the sand 80.

에폭시 주입이 완료된 에폭시 주입부(70)는 벽면에서 제거를 하게되는데 분사부(80)의 분사구(83)는 에폭시와 함께 경화 되므로 분사구(83)를 절단하여 접시판(84) 후측을 분리하게 된다.Epoxy injection is completed, the epoxy injection portion 70 is removed from the wall surface, since the injection port 83 of the injection unit 80 is cured together with the epoxy to cut the injection port 83 to separate the rear plate plate 84 .

이러한 본 발명은 상기 받침대(10)의 하측에 아무런 장애물이 설치되지 않아 보강 및 보수작업을 하더라도 차량이 진행 할 수 있도록 구성되어 도로 혼잡등의 혼란을 방지하게된다.The present invention is configured so that the vehicle can proceed even if the reinforcement and repair work is not installed because no obstacle is installed on the lower side of the pedestal 10 to prevent confusion such as road congestion.

도 1은 본 발명에 따른 콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치가 터널에 설치되어진 것을 나타낸 구성도,1 is a block diagram showing that the epoxy injection device having a bi-directional movable workbench for reinforcement of cracks in a concrete structure according to the present invention is installed in the tunnel,

도 2는 본 발명에 따른 콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치의 전체 구성사시도,Figure 2 is an overall configuration perspective view of the epoxy injection device having a bi-directional movable workbench for reinforcement of cracks in concrete structures according to the present invention,

도 3은 본 발명에 따른 콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치의 리프트부가 동작되어지는 것을 나타낸 도면,Figure 3 is a view showing that the lift portion of the epoxy injection device having a bi-directional movable workbench for reinforcing the cracks of the concrete structure according to the present invention,

도 4는 본 발명에 따른 콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치의 에폭시 주입부가 벽면에 삽입되어진 것을 나타낸 도면,Figure 4 is a view showing that the epoxy injection portion of the epoxy injection device having a bi-directional movable workbench for reinforcement of the crack cracking concrete structure according to the present invention,

도 5는 본 발명에 따른 콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치의 에폭시 주입부를 나타낸 사시도,Figure 5 is a perspective view showing the epoxy injection portion of the epoxy injection device having a bi-directional movable workbench for reinforcement of cracks concrete structure according to the invention,

도 6은 본 발명에 따른 콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치의 에폭시 주입부를 투시한 투시도,Figure 6 is a perspective view through the epoxy injection portion of the epoxy injection device having a bi-directional movable workbench for reinforcement of cracks in the concrete structure according to the present invention,

도 7은 본 발명에 따른 콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치의 에폭시 주입부를 분해한 사시도,Figure 7 is an exploded perspective view of the epoxy injection portion of the epoxy injection device having a bi-directional movable workbench for reinforcing the cracks of the concrete structure according to the present invention,

도 8은 본 발명에 따른 콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치의 에폭시 주입부를 벽면에 삽입하여 균열부를 보수 및 복강 하는 방법을 나타낸 순서도.8 is a flow chart illustrating a method for repairing and reinforcing cracks by inserting an epoxy injection part of an epoxy injection device having a bidirectional movable work bench for repairing and strengthening a crack of a concrete structure according to the present invention.

<도면의 주요 부분에 대한 부호 설명><Description of the symbols for the main parts of the drawings>

10 : 받침판 20 : 작업대10: support plate 20: worktable

30 : 에폭시 공급부 40 : 이동판30: epoxy supply part 40: moving plate

50 : 높낮이 조절부 60 : 레일50: height adjustment unit 60: rail

70 : 에폭시 주입부 80 : 분사부70: epoxy injection portion 80: injection portion

Claims (3)

터널 또는 콘크리트 구조물의 균열부 보수 보강을 위한 보수장치에 있어서,In the repair device for repairing cracks of tunnels or concrete structures, 터널의 양측차선 외측 바닥에 차선을 따라 설치되어지는 레일(60)과;Rail 60 is installed along the lane on the outer bottom of both lanes of the tunnel; 상기 레일(60)을 따라 이동되는 바퀴(16)가 하단에 결합되고 터널벽측 양측에 작업발판(15)이 형성되는 지지대(14)가 하측에 다수 결합되어지며, 상측면에 레일(6)의 횡방향으로 이송레일(11)이 설치되고, 상기 이송레일(11) 상에 설치되는 이동판(40)을 이송레일(11)을 따라 이송시키는 횡방향 이송장치(12)가 설치되는 받침대(10)와;The wheel 16 moving along the rail 60 is coupled to the lower end and the support 14 is formed on the lower side of the tunnel wall is formed on both sides of the tunnel 15 is coupled to the lower side, the upper side of the rail (6) Pedestal 10 is provided with a transport rail 11 in the transverse direction, the transverse conveying device 12 for transporting the moving plate 40 installed on the conveying rail 11 along the conveying rail 11 )Wow; 상기 받침대(10)의 상측면에 설치된 이송레일(11)을 따라 이동되는 바퀴가 결합되어지고, 상측면에 유압모터(42)의 유압으로 상하강 되어지는 리프트부(43)가 설치되며, 상기 횡방향 이송장치(12)에 연결되는 와이어로 이송되어지는 이동판(40)과;Wheels that are moved along the transport rails 11 installed on the upper side of the pedestal 10 is coupled, and the upper portion is provided with a lift unit 43 for lifting up and down by hydraulic pressure of the hydraulic motor 42, A moving plate 40 which is conveyed by a wire connected to the transverse conveying apparatus 12; 상기 이송레일(11) 상에 설치되는 이동판(40)의 상측에 형성되는 리프트부(43)의 상측에 결합되어지고, 상측면 테두리에 사용자의 안전을 위한 보호대(21)가 결합되어지며, 에폭시 주입부(70)가 연결되어 에폭시를 공급하는 에폭시 공급부(30)가 설치되는 작업대(20)와;Is coupled to the upper side of the lift portion 43 formed on the upper side of the moving plate 40 installed on the conveying rail 11, the guard 21 for the safety of the user is coupled to the upper side edge, A work bench 20 to which an epoxy injecting unit 70 is connected and an epoxy supply unit 30 for supplying epoxy is installed; 상기 지지대(14)의 전측 또는 후측에 케이블이 연결되어 레일(60)을 따라 지지대(14)가 이동되어지도록 터널의 입구 또는 출구에 설치되어지는 이송장지(90);를 포함하여 구성되어지는 것을 특징으로 하는 콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치.It is configured to include; a transport medium 90 is installed at the inlet or outlet of the tunnel so that the cable is connected to the front or rear side of the support 14 to move the support 14 along the rail 60; Epoxy injection device with bi-directional mobile workbench for reinforcing cracks in concrete structures. 제 1항에 있어서,The method of claim 1, 상기 에폭시 주입부(70)는 일측에 토출부(71)가 형성되어지고, 타측이 절개되어지는 실린더부(76)의 타측에 삽입되어지며, 실린더부(76) 내부에 주입되는 에폭시를 토출부(71) 측으로 토출시키도록 피스톤부가 삽입되어지며, The epoxy injection portion 70 has a discharge portion 71 is formed on one side, the other side is inserted into the other side of the cylinder portion 76 is cut, the epoxy injected into the cylinder portion 76 discharge portion Piston part is inserted to discharge to the (71) side, 상기 피스톤부는 실린더부(76)의 내부에 삽입되어지는 피스톤(72)과, 상기 피스톤(72)의 중심에 형성되는 홀에 삽입되어 피스톤(72)의 홀을 개폐하는 벨브(73)와, 상기 피스톤(72)의 타측면에 결합되어 실린더부(76)의 타측면에 결합되는 덮개부(74)에 지지되어지는 탄성부(75)와, 상기 피스톤(72)의 홀에 연결되어 에폭시 공급부(30)에서 에폭시가 공급되어지는 공급관(31)과, 상기 공급관(31)이 관통되어지며, 상기 실린더부(76)의 타측에 결합되어지는 덮개부(74)로 구성되며, The piston portion is inserted into the cylinder 72, the piston 72, the valve 73 is inserted into the hole formed in the center of the piston 72 to open and close the hole of the piston 72, and An elastic supply unit 75 coupled to the other side of the piston 72 and supported by the cover unit 74 coupled to the other side of the cylinder unit 76, and an epoxy supply unit connected to the hole of the piston 72. 30 is provided with a supply pipe 31 through which the epoxy is supplied, the supply pipe 31 is penetrated, and the cover portion 74 coupled to the other side of the cylinder portion 76, 상기 토출부(71)에는 중단부가 접시형태로 형성되어 다수의 실링홀(81)이 형성되는 접시판(84)과, 벽면에 삽입되어 에폭시를 주입하도록 다수의 홀(82)이 형성된 분사구(83)로 구성되는 분사부(80)가 결합되어지는 것을 포함하여 구성되는 것을 특징으로 하는 콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치.The discharge part 71 has a stop plate formed in the shape of a plate and a plate plate 84 having a plurality of sealing holes 81, and a plurality of holes 82 formed in the wall surface so as to inject epoxy into the injection hole 83. Epoxy injection device having a bi-directional movable workbench for repairing and reinforcing the cracks of the concrete structure, characterized in that comprising the injection unit 80 is configured to be coupled. 제1항에 있어서,The method of claim 1, 상기 지지대(14)와 바퀴 간에는 상기 지지대(14)의 높낮이를 조절할 수 있도록 높낮이 조절부(50)가 형성되어지는 것을 특징으로 하는 콘크리트 구조물 균열부 보수보강을 위한 양방향 이동식 작업대를 가진 에폭시 주입장치.Epoxy injection device having a bi-directional movable workbench for repairing and reinforcing the crack of the concrete structure, characterized in that the height adjustment unit 50 is formed between the support 14 and the wheel to adjust the height of the support (14).
KR1020090072446A 2009-08-06 2009-08-06 Epoxy injection equipment to both direction movement worktable of crack repair-reinforcement for concret structure KR100949937B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090072446A KR100949937B1 (en) 2009-08-06 2009-08-06 Epoxy injection equipment to both direction movement worktable of crack repair-reinforcement for concret structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090072446A KR100949937B1 (en) 2009-08-06 2009-08-06 Epoxy injection equipment to both direction movement worktable of crack repair-reinforcement for concret structure

Publications (1)

Publication Number Publication Date
KR100949937B1 true KR100949937B1 (en) 2010-03-30

Family

ID=42183891

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090072446A KR100949937B1 (en) 2009-08-06 2009-08-06 Epoxy injection equipment to both direction movement worktable of crack repair-reinforcement for concret structure

Country Status (1)

Country Link
KR (1) KR100949937B1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101262736B1 (en) 2013-02-07 2013-05-09 케이에스엠기술 주식회사 A operating car for a constucting tunnel or safety diagnosis
KR101287462B1 (en) * 2013-02-07 2013-07-19 케이에스엠기술 주식회사 A operating car having a upper part can move vertical direction for a constucting tunnel or safety diagnosis
KR101446965B1 (en) * 2013-07-29 2014-10-07 강영기 Concrete vomiter
KR101725392B1 (en) * 2016-03-30 2017-04-11 최관희 Multi-packer for repairing crack or backside water barrier and method for repairing concrete structure using thereof
KR101731475B1 (en) 2015-05-19 2017-05-02 에스큐엔지니어링(주) Apparatus for track type conveyance vehicle
CN113494194A (en) * 2021-09-02 2021-10-12 深圳市鑫麟钰鼎科技有限公司 Screen remote control manipulator is inlayed in outer wall crack
KR102537663B1 (en) 2021-12-31 2023-05-30 조영수 Method of repair cracks in concrete structures using epoxy resin

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0616366A (en) * 1992-07-02 1994-01-25 Koa:Kk Outer wall installation by shiftable lifter and device therefor
KR20080053442A (en) * 2008-05-12 2008-06-13 임영호 Lining con'c
KR20080063224A (en) * 2006-12-29 2008-07-03 김민하 Portable worktable
KR100904293B1 (en) 2009-03-13 2009-06-25 용화산업 주식회사 Potable worktable enbling the adjustment of the height and width

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0616366A (en) * 1992-07-02 1994-01-25 Koa:Kk Outer wall installation by shiftable lifter and device therefor
KR20080063224A (en) * 2006-12-29 2008-07-03 김민하 Portable worktable
KR20080053442A (en) * 2008-05-12 2008-06-13 임영호 Lining con'c
KR100904293B1 (en) 2009-03-13 2009-06-25 용화산업 주식회사 Potable worktable enbling the adjustment of the height and width

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101262736B1 (en) 2013-02-07 2013-05-09 케이에스엠기술 주식회사 A operating car for a constucting tunnel or safety diagnosis
KR101287462B1 (en) * 2013-02-07 2013-07-19 케이에스엠기술 주식회사 A operating car having a upper part can move vertical direction for a constucting tunnel or safety diagnosis
KR101446965B1 (en) * 2013-07-29 2014-10-07 강영기 Concrete vomiter
KR101731475B1 (en) 2015-05-19 2017-05-02 에스큐엔지니어링(주) Apparatus for track type conveyance vehicle
KR101725392B1 (en) * 2016-03-30 2017-04-11 최관희 Multi-packer for repairing crack or backside water barrier and method for repairing concrete structure using thereof
CN113494194A (en) * 2021-09-02 2021-10-12 深圳市鑫麟钰鼎科技有限公司 Screen remote control manipulator is inlayed in outer wall crack
CN113494194B (en) * 2021-09-02 2022-06-21 深圳市鑫麟钰鼎科技有限公司 Screen remote control manipulator is inlayed in outer wall crack
KR102537663B1 (en) 2021-12-31 2023-05-30 조영수 Method of repair cracks in concrete structures using epoxy resin

Similar Documents

Publication Publication Date Title
KR100949937B1 (en) Epoxy injection equipment to both direction movement worktable of crack repair-reinforcement for concret structure
CN103437782B (en) Hydraulic pressure automatic moving type steel form carrier and construction method thereof
CN109469300A (en) A kind of device of automatic tiling
CN211314235U (en) Tunnel inverted arch and filling concrete paver
CN204436416U (en) Lay chassis
CN112878714B (en) Automatic brick laying machine for building engineering
CN105736012B (en) A kind of tunnel lining concrete grouting device
CN210919080U (en) Tunnel pipe wall crack filling device
CN208416552U (en) Shield formula TBM beans gravel backfills fast switching system
CN203921709U (en) The blockage-clearing device of V flute profile disjunctor ferro-concrete feed bin
JP2010261192A (en) Tamping device for track
CN115853518A (en) Shield construction method using subway crossover arrangement
CN204851281U (en) Device is confirmed to tunnel construction lining cutting volume
CN104963702A (en) Tunnel construction lining quantity confirming device and construction method thereof
CN106121680B (en) Wet shotcreting lining cutting boom truck
CN115262497A (en) Underwater concrete repairing method for trash rack gate slot of hydropower station
CN204851283U (en) Device is confirmed to tunnel construction lining cutting volume
CN104963701A (en) Tunnel construction lining quantity confirming device and construction method thereof
CN203877256U (en) Blockage removal device for cylindrical flat-bottom reinforced concrete bin
CN106481349A (en) Tunnel lining concrete grouting device and its construction method
CN104368574A (en) Pneumatic pipe clearing machine
CN205100039U (en) Novel track concrete placement machine
CN204703171U (en) A kind of concrete transfer system and there is the concrete transport vehicle of this transfer system
CN204208862U (en) Pneumatic pipeline dredging machine
CN211692501U (en) Tunnel inverted arch and filling concrete sliding die

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
N231 Notification of change of applicant
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
N231 Notification of change of applicant
N231 Notification of change of applicant
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130322

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20140321

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20160420

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20170321

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20180322

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20190320

Year of fee payment: 10