KR100873519B1 - Hanger of line post insulator supporting power cable - Google Patents

Hanger of line post insulator supporting power cable Download PDF

Info

Publication number
KR100873519B1
KR100873519B1 KR1020080011408A KR20080011408A KR100873519B1 KR 100873519 B1 KR100873519 B1 KR 100873519B1 KR 1020080011408 A KR1020080011408 A KR 1020080011408A KR 20080011408 A KR20080011408 A KR 20080011408A KR 100873519 B1 KR100873519 B1 KR 100873519B1
Authority
KR
South Korea
Prior art keywords
bar
post insulator
line post
cable
vertical bar
Prior art date
Application number
KR1020080011408A
Other languages
Korean (ko)
Inventor
김재일
Original Assignee
(주)일광종합기술단
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)일광종합기술단 filed Critical (주)일광종합기술단
Priority to KR1020080011408A priority Critical patent/KR100873519B1/en
Application granted granted Critical
Publication of KR100873519B1 publication Critical patent/KR100873519B1/en

Links

Images

Classifications

    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01BCABLES; CONDUCTORS; INSULATORS; SELECTION OF MATERIALS FOR THEIR CONDUCTIVE, INSULATING OR DIELECTRIC PROPERTIES
    • H01B17/00Insulators or insulating bodies characterised by their form
    • H01B17/02Suspension insulators; Strain insulators
    • H01B17/06Fastening of insulator to support, to conductor, or to adjoining insulator
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01BCABLES; CONDUCTORS; INSULATORS; SELECTION OF MATERIALS FOR THEIR CONDUCTIVE, INSULATING OR DIELECTRIC PROPERTIES
    • H01B17/00Insulators or insulating bodies characterised by their form
    • H01B17/14Supporting insulators
    • H01B17/16Fastening of insulators to support, to conductor, or to adjoining insulator
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
    • H02G1/04Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables for mounting or stretching
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G7/00Overhead installations of electric lines or cables
    • H02G7/05Suspension arrangements or devices for electric cables or lines
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G7/00Overhead installations of electric lines or cables
    • H02G7/14Arrangements or devices for damping mechanical oscillations of lines, e.g. for reducing production of sound
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G7/00Overhead installations of electric lines or cables
    • H02G7/20Spatial arrangements or dispositions of lines or cables on poles, posts or towers

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

A hanger of a line post insulator supporting a transmission and distribution cable is provided to prevent separation of the cable from the line post insulator by reducing the vibration through a spring. A hanger(10) of a line post insulator supporting the transmission and distribution cable is formed in the line post insulator(5) installed in a pylon. The transmission and distribution cable(3) is fixed in the hanger of the line post insulator supporting the cable. The hanger of the line post insulator supporting the cable includes a bar body and a supporting unit(20). The bar body is formed on the top of the line post insulator. The length of the bar body is varied to reduce the up and down vibration. The supporting unit is installed on the upper portion of the bar body. The supporting part supports the cable. The bar body includes a top bar(30), a vertical bar(40), a support bar, a receiving unit, a lower bar(60), and an elastic member. The top bar has the regular length. The vertical bar is extended downward in the lower part of the top bar. The vertical bar has the external diameter smaller than the top bar. The support bar has the external diameter bigger than the vertical bar. The support bar is screwed in the lower part of the vertical bar and controls the height. The receiving unit receives a vertical bar and a support bar. The elastic member lifts the vertical bar up.

Description

송배전용 케이블을 지지하는 라인포스트애자의 행거{Hanger of line post insulator supporting Power cable}Hanger of line post insulator supporting Power cable

본 발명은 송배전용 케이블을 지지하는 라인포스트애자의 행거에 관한 것으로서, 더욱 상세하게는 전주 또는 송배전 철탑에 설치된 라인포스트애자에 밴딩와이어에 의해 고정된 송배전케이블이 진동에 의해 풀리는 것을 방지할 수 있는 라인포스트 애자의 행거에 관한 것이다.The present invention relates to a hanger of a line post insulator for supporting a cable for transmission and distribution, and more particularly, a transmission and distribution cable fixed by a banding wire to a line post insulator installed in a telephone pole or a transmission and distribution tower can be prevented from being released by vibration. It's about the hanger of the linepost insulator.

일반적으로 발전소에 발생되는 대전력은 송전탑 등의 송전선로를 통해 고압의 전력으로 각 변전소로 송전된 다음, 변전소에서는 여러 단계의 변압과정을 거쳐 각 가정 또는 건물 등의 수용가에서 사용할 수 있도록 케이블을 이용하여 각 지역으로 공급하게 되는 배전과정을 거치게 된다.In general, the large power generated in the power plant is transmitted to each substation with high voltage power through transmission lines such as power transmission towers, and then the cable is used in the home or building through a multi-stage transformation process at the substation. It goes through the distribution process to supply to each region.

이때, 일반 수용가에 대한 전력공급은 일정간격으로 설치되는 전신주 또는 철탑의 상부 측에 완철과 같은 지지부재에 의해 지지되는 라인포스트 애자(LP insulator)에 절연고정되는 송배전케이블을 통해 이루어지게 된다.At this time, the power supply to the general consumer is made through a transmission and distribution cable is insulated and fixed to the line post insulator (LP insulator) supported by a support member such as a wrought iron on the upper side of the pole or pylon installed at regular intervals.

이 경우 송배전케이블은 라인포스트 애자의 몸체에 밴딩와이어를 권선시켜 고정하는 방법이 주로 사용되고 있다. 밴딩와이어는 송배전케이블과 동일한 재질로 이루어지게 되는데, 주로 알루미늄이나 동선이 사용된다. In this case, the transmission and distribution cable is mainly used to fix the winding wire to the body of the line post insulator. The bending wire is made of the same material as the transmission and distribution cable, and mainly aluminum or copper wire is used.

이러한 밴딩와이어는 송배전케이블을 권선 고정하여 라인포스트 애자로부터 송배전케이블이 이탈되는 것을 방지하는 기능을 갖는다.The bending wire has a function of preventing the transmission and distribution cable from being separated from the line post insulator by winding the transmission and distribution cable.

하지만, 종래의 결속방법은 강풍 등에 의해 발생하는 송배전 케이블의 진동에 의해 밴딩와이어의 권선상태가 풀리는 경우가 발생한다. 이때, 와이어가 풀리는 양은 매우 미미하지만, 여기서 발생한 미세한 틈 사이에 공간 전하가 축적된다. 이로 인해 송배전케이블과 밴딩와이어 사이에 스파크가 발생하고 결과적으로 스파크에 의해 송배전케이블이 단선되는 문제점이 있다.However, in the conventional binding method, the winding state of the banding wire is released due to the vibration of the transmission and distribution cable generated by the strong wind or the like. At this time, the amount of wire unwinding is very small, but the space charge is accumulated between the minute gaps generated here. As a result, spark occurs between the transmission and distribution cable and the bending wire, and as a result, the transmission and distribution cable is disconnected by the spark.

또한, 이러한 현상이 계속되면 결국 와이어가 풀려 케이블이 라인포스트애자로부터 이탈되어 지상으로 추락하여 안전사고의 우려가 높아진다.In addition, if this phenomenon continues, the wire is eventually released and the cable is separated from the line post insulator and falls to the ground, which increases the risk of a safety accident.

그리고 상기와 같은 진동에 의해, 송배전 케이블의 송전효율이 저하될 뿐 아니라, 송배전 케이블을 지지하는 애자나 기타 부분들이 손상될 수 있는 문제점이 있다.And, due to the vibration as described above, there is a problem that not only the transmission efficiency of the transmission and distribution cable is lowered, but also the insulator or other parts supporting the transmission and distribution cable may be damaged.

본 발명은 상기와 같은 문제점을 개선하고자 창출된 것으로서 라인포스트 애자에 고정된 송배전케이블의 상하 진동을 완화할 수 있는 라인포스트애자의 행거를 제공하는 데 그 목적이 있다.An object of the present invention is to provide a hanger of a line post insulator which can mitigate the up and down vibration of the transmission and distribution cable fixed to the line post insulator, which is created to improve the above problems.

상기의 목적을 달성하기 위한 본 발명의 송배전용 케이블을 지지하는 라인포스트애자의 행거는 라인포스트 애자의 상부에 형성되며 상하 진동을 완화할 수 있도록 길이가 가변되는 봉체와; 상기 봉체의 상단에 설치되어 상기 케이블을 지지하는 반호형의 지지부;를 구비하며, 상기 봉체는 일정길이를 가지는 상부봉체와, 상기 상부봉체의 하부에서 하방으로 연장되며 상기 상부봉체의 외경보다 더 적은 외경을 가지는 수직바와, 상기 수직바의 외경보다 더 큰 외경을 가지며 상기 수직바의 하부에 나사결합되어 높낮이 조절이 가능한 지지바와, 상기 수직바 및 상기 지지바를 승강가능하게 수용하는 수용부를 가지며 상단부와 상기 상부봉체의 하단부 사이의 거리가 가변되는 하부봉체와, 상기 수직바를 승강시키는 탄성부재를 구비하는 것을 특징으로 한다.Hanger of the line post insulator for supporting the cable for transmission and distribution of the present invention for achieving the above object is formed on the top of the line post insulator and the length is variable so as to mitigate vertical vibration; A half arc-shaped support part installed at an upper end of the rod to support the cable, wherein the rod has an upper rod having a predetermined length and extends downward from a lower portion of the upper rod and is smaller than an outer diameter of the upper rod. An upper end having a vertical bar having an outer diameter, a support bar having a larger outer diameter than the outer diameter of the vertical bar and screwed to a lower portion of the vertical bar to adjust the height, and a receiving portion to receive the vertical bar and the support bar in a liftable manner; It characterized in that it comprises a lower rod body that the distance between the lower end of the upper rod body is variable, and an elastic member for elevating the vertical bar.

상기 탄성부재는 상기 수직바의 외주면을 감싸며 상기 지지바의 상단에 지지되어 상기 수직바를 하방으로 탄성바이어스시키는 제 1스프링과, 상기 지지바의 하단과 상기 하부봉체의 수용부의 바닥 사이에 설치되어 상기 수직바를 상방으로 탄성바이어스시키는 제 2스프링을 구비하는 것을 특징으로 한다.The elastic member surrounds the outer circumferential surface of the vertical bar and is supported on the upper end of the support bar to be elastically biased to the vertical bar downward, and is installed between the lower end of the support bar and the bottom of the receiving part of the lower rod body. And a second spring for elastically biasing the vertical bar upwards.

상기한 바와 같이 본 발명의 송배전용 케이블을 지지하는 라인포스트애자의 행거는 바람이나 기후의 영향으로 케이블이 상하로 진동하는 경우 행거의 길이를 가변시켜 내부에 장착된 스프링이 힘을 흡수하게 함으로써 진동을 완화하여 밴딩와이어의 권선상태가 풀리는 것을 방지하여 케이블이 라인포스트애자로부터 이탈되어 지상으로 추락하는 것을 방지할 수 있다.As described above, the hanger of the line post insulator supporting the cable for power transmission and distribution of the present invention vibrates by varying the length of the hanger so that the spring mounted therein absorbs the force when the cable vibrates up and down under the influence of wind or weather. By mitigating and preventing the winding state of the bending wire from being loosened, the cable can be prevented from falling from the line post insulator and falling to the ground.

또한, 케이블의 진동을 완화시켜 케이블이나 라인포스트 애자가 손상되는 것을 방지할 수 있다.In addition, vibration of the cable can be alleviated to prevent damage to the cable or linepost insulator.

이하, 첨부된 도면을 참조하면서 본 발명의 송배전용 케이블을 지지하는 라인포스트애자의 행거에 대해서 상세하게 설명한다.Hereinafter, the hanger of the line post insulator which supports the cable for transmission and distribution of this invention is demonstrated in detail, referring an accompanying drawing.

도 1은 본 발명의 일 실시 예에 따른 라인포스트애자의 행거에 케이블이 고정된 상태를 나타내는 사시도이고, 도 2는 도 1의 라인포스트 애자의 행거에 적용되는 봉체의 내부를 나타내는 일부 발췌 사시도이고, 도 3은 도 1의 라인포스트 애자의 행거에 케이블이 고정된 상태를 나타내는 측면도이다.1 is a perspective view showing a state in which a cable is fixed to the hanger of the line post insulator according to an embodiment of the present invention, Figure 2 is a partial perspective view showing the inside of the rod applied to the hanger of the line post insulator of FIG. 3 is a side view illustrating a state in which a cable is fixed to the hanger of the line post insulator of FIG. 1.

도 1 내지 도 3을 참조하면, 본 발명의 라인포스트애자의 행거(10)는 라인포스트 애자(5)의 상부에 형성된다.1 to 3, the hanger 10 of the line post insulator of the present invention is formed on the line post insulator 5.

송배전 케이블(3)과 대지를 절연하기 위한 라인포스트 애자(5)는 전주의 상부측에 완철과 같은 지지부재(미도시)를 통해 설치되는 것으로, 이러한 라인포스트 애자(5)의 상부에는 행거(10)가 형성되고, 행거(10)의 상부에는 케이블(3)이 밴딩 와이어(7)에 의해 고정된다. The line post insulator 5 for insulating the transmission and distribution cable 3 and the ground is installed on the upper side of the pole through a supporting member such as a wrought iron (not shown). 10 is formed, and the cable 3 is fixed to the upper part of the hanger 10 by the bending wire 7.

본 발명의 라인포스트애자의 행거(10)는 크게 송배전 케이블(3)의 상하 진동을 완화할 수 있도록 길이가 가변되는 봉체와, 봉체의 상단에 설치되어 케이블(3)을 지지하는 지지부(20)를 가진다.The hanger 10 of the line post insulator of the present invention has a rod body having a variable length to largely alleviate vertical vibration of the transmission and distribution cable 3, and a support 20 installed at the top of the rod to support the cable 3. Has

지지부(20)는 케이블(3)이 안착되어 케이블(3)의 하부를 지지하는 것으로 반호형의 형상을 가진다. 지지부(20)는 도시된 것 이외도 케이블(3)이 안착되어 지지될 수 있는 구조라면 다양한 형태로 형성될 수 있음은 물론이다.The support part 20 has a half arc shape as the cable 3 is seated to support the lower part of the cable 3. The support unit 20 may be formed in various forms as long as the structure in which the cable 3 is seated and supported in addition to those illustrated.

봉체는 지지부(20)와 라인포스트애자(5) 사이에 형성되는 것으로, 상부에 고정되는 케이블(3)이 상하로 진동할 경우 그 진동을 완화할 수 있도록 상하 길이가 가변되도록 구성된다.The rod is formed between the support portion 20 and the line post insulator 5, and is configured such that the vertical length is variable so that the cable 3 fixed to the upper portion vibrates up and down to alleviate the vibration.

상기의 기능을 갖는 봉체는 일정길이를 가지는 상부봉체(30)와, 상부봉체(30)의 하부에서 하방으로 연장되어 형성되며 상부봉체(30)의 외경보다 더 작은 외경을 가지는 수직바(40)와, 수직바(40)의 하부에 나사결합되어 수직바(40)의 외경보다 더 큰 외경을 가지는 지지바(50)와, 수직바(40) 및 지지바(50)를 내부에 수용하는 수용부(63)가 형성된 하부봉체(60)와, 수직바(40)를 승강시키는 탄성부재로 구성된다.The rod having the above function has an upper rod 30 having a predetermined length, and a vertical bar 40 extending downward from the lower portion of the upper rod 30 and having a smaller outer diameter than the outer diameter of the upper rod 30. And a support bar 50 screwed to the lower portion of the vertical bar 40 and having a larger outer diameter than the outer diameter of the vertical bar 40, and accommodating the vertical bar 40 and the support bar 50 therein. The lower rod 60 formed with the portion 63 and the vertical bar 40 is composed of an elastic member for elevating.

그리고 탄성부재는 수직바(40)의 외주면을 감싸며 지지바(50)의 상단에 지지되어 수직바(40)를 하방으로 탄성바이어스시키는 제 1스프링(71)과, 지지바(50)의 하단과 하부봉체(60)의 수용부(63)의 바닥 사이에 설치되어 수직바(40)를 상방으로 탄성바이어스시키는 제 2스프링(75)으로 구성된다.The elastic member surrounds the outer circumferential surface of the vertical bar 40 and is supported by the upper end of the support bar 50 to elastically bias the vertical bar 40 downward, and the lower end of the support bar 50. It is provided between the bottom of the receiving portion 63 of the lower rod 60 is composed of a second spring 75 to elastically bias the vertical bar 40 upward.

상부봉체(30)는 지지부(20)의 하부에서 수직하방으로 일정 길이 연장되어 형성되며 봉형상을 가진다. 그리고 상부봉체(30)의 하부에는 수직하방으로 일정 길이 수직으로 연장되는 수직바(40)가 형성된다. 그리고 수직바(40)의 하부에는 지지바(50)가 나사결합될 수 있도록 나사산이 형성되고, 지지바(50)의 상부 중앙에는 수직바(40)와 나사결합되는 나사홈이 형성된다.The upper rod 30 is formed by extending a predetermined length vertically downward from the lower portion of the support portion 20 and has a rod shape. And the lower portion of the upper rod 30 is formed with a vertical bar 40 extending vertically vertically down a certain length. In addition, a thread is formed at the lower portion of the vertical bar 40 so that the support bar 50 may be screwed, and a screw groove is formed at the upper center of the support bar 50 to be screwed with the vertical bar 40.

그리고 상기 수직바(40) 및 지지바(50)와 탄성부재를 수용하는 하부봉체(60)는 라인포스트 애자(5)의 상단에 고정결합된다. 하부봉체(60)는 도시되지 않았지만 좌우가 상호 분리 및 결합이 가능하도록 2개로 분리되는 구조를 가질 수 있다.And the lower bar 60 for receiving the vertical bar 40 and the support bar 50 and the elastic member is fixedly coupled to the upper end of the line post insulator (5). Although not shown, the lower rod 60 may have a structure that is separated into two to allow the left and right to separate and combine with each other.

상부봉체(30)의 하부에 형성된 수직바(40)는 가해지는 하중에 의해 하부봉체(60)의 수용부(63)를 따라 상하로 이동하면서 상부봉체(30)와 하부봉체(60)의 간격을 가변시키게 된다. The vertical bar 40 formed on the lower part of the upper bar 30 moves up and down along the receiving portion 63 of the lower bar 60 by a load applied thereto, and a gap between the upper bar 30 and the lower bar 60. Will be changed.

상부봉체(30)나 하부봉체(60)에 힘이 가해지지 않는 경우 제 1 및 제 2스프링(71)(75)의 탄성력이 균형을 이루는 위치의 수용부(63)에 수직바(50)는 정지된 상태로 있는다. 그리고 제 1 및 제 2스프링(71)(75)의 탄성력보다 더 큰 힘이 상부봉체(30)의 상부에서 하방으로 가해지는 경우 상부봉체(30)는 하부봉체(60)에 대하여 하강하게 되고, 힘이 하부봉체(60)의 하부에서 상방으로 가해지는 경우 상봉체(30)는 하부봉체(60)에 대하여 상승하게 된다. When the force is not applied to the upper rod 30 or the lower rod 60, the vertical bar 50 to the receiving portion 63 of the position where the elastic force of the first and second springs 71 and 75 is balanced Stay stationary. And when a force greater than the elastic force of the first and second springs 71 and 75 is applied downward from the upper portion of the upper rod 30, the upper rod 30 is lowered relative to the lower rod 60, When the force is applied upward from the lower portion of the lower rod 60, the upper rod 30 is raised relative to the lower rod (60).

또한, 수직바(50)의 하부에 나사결합되는 지지바(50)를 회전시켜 지지바(50)의 높낮이를 조절함으로써 제 1 및 제 2스프링(71)(75)의 탄성력을 조절할 수 있다.In addition, by adjusting the height of the support bar 50 by rotating the support bar 50 is screwed to the lower portion of the vertical bar 50 it is possible to adjust the elastic force of the first and second springs (71) (75).

한편, 지지바(50)의 외주면에는 상부봉체(30)가 하부봉체(60)에 대하여 회전하는 것을 방지할 수 있도록 회전방지핀(53)이 돌출되어 형성되고, 수용부(63)가 형성된 하부봉체(60)의 내주면에는 회전방지핀(53)이 결합될 수 있도록 회전방지핀(53)의 형상과 대응되는 형상의 회전방지홈이 형성되어 지지바(50)의 상하 슬라이딩이동은 허용하되 자전은 방지한다. On the other hand, the outer circumferential surface of the support bar 50 is formed to protrude the anti-rotation pin 53 to prevent the upper rod 30 to rotate about the lower rod 60, the lower portion formed with the receiving portion 63 The inner circumferential surface of the rod 60 is formed with an anti-rotation groove having a shape corresponding to that of the anti-rotation pin 53 to allow the anti-rotation pin 53 to be coupled thereto, thereby allowing the vertical bar sliding movement of the support bar 50 to rotate. Prevent.

본 발명의 라인포스트 애자의 행거는 케이블(3)이 바람 등에 의해 상하로 진동하는 경우 상부 봉체(30)와 하부 봉체(60)의 간격을 가변시켜 제 1 및 제 2스프링(71)(75)이 진동을 흡수하여 진동을 완화시킴으로써 지지부에 케이블을 고정시키는 밴딩와이어가 풀리는 것을 방지하고, 케이블(3)이나 라인포스트 애자(5)가 손상되는 것을 미연에 방지할 수 있다. The hanger of the line post insulator of the present invention is the first and second springs 71 and 75 by varying the distance between the upper rod 30 and the lower rod 60 when the cable 3 vibrates up and down by wind or the like. By absorbing this vibration to mitigate the vibration, it is possible to prevent the bending wire which fixes the cable to the support portion from loosening, and to prevent the cable 3 and the line post insulator 5 from being damaged.

그리고 상부 및 하부 봉체(30)(60)는 화이버글라스 재질과 수지재인 에폭시 재질을 7;3 혹은 6;4정도로 혼합하여 인발 성형공정을 거쳐 성형함이 바람직하다. 한편, 상부봉체(30) 및 하부봉체(60)의 외주면에 절연관(미도시)이 각각 부착되어 절연기능을 수행할 수 있다. 이러한 절연관의 재질은 절연기능이 우수한 실리콘의 재질로 성형됨이 바람직하다. 또한 절연관은 다양한 성형방법을 통해 봉체(30)(60)에 부착될 수 있으나, 본 발명에서는 인발 성형공정을 거친 봉체(30)(60)를 별도의 사출금형에 투입한 후, 봉체(30)(60)의 외경에 액상의 실리콘을 주입하여 성형하는 사출성형방법을 사용함이 가장 바람직하다. In addition, the upper and lower rods 30 and 60 are preferably formed by mixing a fiberglass material and an epoxy material, which is a resin material, at about 7; 3 or 6; On the other hand, an insulating tube (not shown) is attached to the outer circumferential surfaces of the upper rod 30 and the lower rod 60, respectively, to perform an insulation function. The material of the insulated tube is preferably molded of a material of excellent silicon insulation. In addition, the insulation tube may be attached to the rods 30 and 60 through various molding methods, but in the present invention, after the rods 30 and 60 which have been subjected to the drawing molding process are put into a separate injection mold, the rod 30 It is most preferable to use an injection molding method of injecting a liquid silicone into the outer diameter of the (60).

한편, 본 발명의 진동을 완화하는 라인포스트 애자의 행거(10)는 전주 외에도 송배전철탑에 설치될 수 있음은 물론이다.On the other hand, hanger 10 of the line post insulator to mitigate the vibration of the present invention can be installed in the transmission and distribution tower in addition to the pole.

이상에서 본 발명은 도면에 도시된 일 실시 예를 참고로 설명되었으나 이는 예시적인 것에 불과하며, 당해 기술분야에서 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 실시 예가 가능하다는 점을 이해할 것이다.The present invention has been described above with reference to one embodiment shown in the drawings, but this is merely exemplary, and those skilled in the art will understand that various modifications and equivalent embodiments are possible therefrom. .

따라서 본 발명의 진정한 보호 범위는 첨부된 청구범위에 의해서만 정해져야 할 것이다.Therefore, the true scope of protection of the present invention should be defined only by the appended claims.

도 1은 본 발명의 일 실시 예에 따른 라인포스트 애자의 송배전 케이블 행거에 케이블이 고정된 상태를 나타내는 사시도이고,1 is a perspective view showing a state in which a cable is fixed to a transmission and distribution cable hanger of a line post insulator according to an embodiment of the present invention;

도 2는 도 1의 라인포스트 애자의 행거에 적용되는 봉체의 내부를 나타내는 일부 발췌 사시도이고,FIG. 2 is a partial perspective view showing the inside of a rod applied to the hanger of the linepost insulator of FIG. 1,

도 3은 도 1의 라인포스트 애자의 행거에 케이블이 고정된 상태를 나타내는 측면도이다.3 is a side view illustrating a state in which a cable is fixed to a hanger of the line post insulator of FIG. 1.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

3: 송배전 케이블 5: 라인포스트 애자3: Transmission and Distribution Cable 5: Line Post Insulator

7: 밴딩와이어 20: 지지부7: banding wire 20: support part

30: 상부봉체 40: 수직바 30: upper rod 40: vertical bar

50: 지지바 60: 하부봉체50: support bar 60: lower rod body

71: 제 1스프링 75: 제 2스프링71: first spring 75: second spring

Claims (2)

전신주에 설치되는 라인포스트 애자에 형성되어 송배전 케이블이 고정되는 라인포스트 애자의 행거에 있어서,In the hanger of the line post insulator which is formed in the line post insulator installed in the telephone pole and the transmission and distribution cable is fixed, 상기 라인포스트 애자의 상부에 형성되며 상하 진동을 완화할 수 있도록 길이가 가변되는 봉체와;A bar body formed on an upper portion of the line post insulator and having a variable length to mitigate vertical vibration; 상기 봉체의 상단에 설치되어 상기 케이블을 지지하는 반호형의 지지부;를 구비하며,A semi-arc type support part installed at an upper end of the rod to support the cable; 상기 봉체는 일정길이를 가지는 상부봉체와, 상기 상부봉체의 하부에서 하방으로 연장되며 상기 상부봉체의 외경보다 더 적은 외경을 가지는 수직바와, 상기 수직바의 외경보다 더 큰 외경을 가지며 상기 수직바의 하부에 나사결합되어 높낮이 조절이 가능한 지지바와, 상기 수직바 및 상기 지지바를 승강가능하게 수용하는 수용부를 가지며 상단부와 상기 상부봉체의 하단부 사이의 거리가 가변되는 하부봉체와, 상기 수직바를 승강시키는 탄성부재를 구비하는 것을 특징으로 하는 송배전용 케이블을 지지하는 라인포스트애자의 행거.The rod has an upper rod having a predetermined length, a vertical bar extending downward from the lower portion of the upper rod and having a smaller outer diameter than the outer diameter of the upper rod, and having a larger outer diameter than the outer diameter of the vertical bar. A support bar which is screwed to the lower side and is capable of adjusting the height, a lower bar body having a receiving part for receiving the vertical bar and the support bar to be liftable, and having a variable distance between the upper end and the lower end of the upper bar, and an elastic lifting the vertical bar. A line post insulator hanger for supporting a cable for transmission and distribution, comprising a member. 제 1항에 있어서, 상기 탄성부재는 상기 수직바의 외주면을 감싸며 상기 지지바의 상단에 지지되어 상기 수직바를 하방으로 탄성바이어스시키는 제 1스프링과, 상기 지지바의 하단과 상기 하부봉체의 수용부의 바닥 사이에 설치되어 상기 수직바를 상방으로 탄성바이어스시키는 제 2스프링을 구비하는 것을 특징으로 하는 송배전용 케이블을 지지하는 라인포스트애자의 행거.According to claim 1, wherein the elastic member is wrapped around the outer circumference of the vertical bar is supported on the upper end of the support bar and the first spring to elastically bias the vertical bar downward, the lower end of the support bar and the receiving portion of the lower rod body Hanger of the line post insulator for supporting the cable for transmission and distribution, characterized in that it is provided between the bottom and the second spring to elastically bias the vertical bar upwards.
KR1020080011408A 2008-02-04 2008-02-04 Hanger of line post insulator supporting power cable KR100873519B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080011408A KR100873519B1 (en) 2008-02-04 2008-02-04 Hanger of line post insulator supporting power cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080011408A KR100873519B1 (en) 2008-02-04 2008-02-04 Hanger of line post insulator supporting power cable

Publications (1)

Publication Number Publication Date
KR100873519B1 true KR100873519B1 (en) 2008-12-15

Family

ID=40372459

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080011408A KR100873519B1 (en) 2008-02-04 2008-02-04 Hanger of line post insulator supporting power cable

Country Status (1)

Country Link
KR (1) KR100873519B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101040166B1 (en) 2010-12-20 2011-06-16 김종선 Plate of fixing for high voltage overhead electric line
KR101040173B1 (en) 2010-12-20 2011-06-16 김종선 Insulator for very high voltage distribution line
KR101040169B1 (en) 2010-12-20 2011-06-16 김종선 Distribution board box for very high voltage distribution line
KR101293716B1 (en) * 2013-01-22 2013-08-06 주식회사 이린 Insulator for very high voltage distribution line
CN114024246A (en) * 2021-11-03 2022-02-08 连云港市港圣开关制造有限公司 Method for installing insulator for high-voltage power grid construction

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR19990041303A (en) * 1997-11-21 1999-06-15 양재신 Shock Absorber of Automobile Bumper
KR200270670Y1 (en) * 2001-12-28 2002-04-03 한국전력공사 Device for protecting the jump wire of line post insulator
KR100585820B1 (en) * 2006-04-13 2006-06-07 주식회사 라인엔지니어링 Contract apparatus of cable and insulator using telegraph pole

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR19990041303A (en) * 1997-11-21 1999-06-15 양재신 Shock Absorber of Automobile Bumper
KR200270670Y1 (en) * 2001-12-28 2002-04-03 한국전력공사 Device for protecting the jump wire of line post insulator
KR100585820B1 (en) * 2006-04-13 2006-06-07 주식회사 라인엔지니어링 Contract apparatus of cable and insulator using telegraph pole

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101040166B1 (en) 2010-12-20 2011-06-16 김종선 Plate of fixing for high voltage overhead electric line
KR101040173B1 (en) 2010-12-20 2011-06-16 김종선 Insulator for very high voltage distribution line
KR101040169B1 (en) 2010-12-20 2011-06-16 김종선 Distribution board box for very high voltage distribution line
KR101293716B1 (en) * 2013-01-22 2013-08-06 주식회사 이린 Insulator for very high voltage distribution line
CN114024246A (en) * 2021-11-03 2022-02-08 连云港市港圣开关制造有限公司 Method for installing insulator for high-voltage power grid construction
CN114024246B (en) * 2021-11-03 2023-11-14 连云港市港圣开关制造有限公司 Insulator installation method for high-voltage power grid construction

Similar Documents

Publication Publication Date Title
KR101174356B1 (en) Supporting bar for an over head line
KR100873519B1 (en) Hanger of line post insulator supporting power cable
KR100904199B1 (en) A fixing apparatus of an insulator
KR101746372B1 (en) Fixing device of electric wire for transmission tower
KR101869712B1 (en) Fixing frame of high voltage distribution line
KR100519934B1 (en) suspend insulator for a power-transmission line
KR100794148B1 (en) Device for protecting the jump wire of line post insulator
WO2011026310A1 (en) Composite insulated tower for grid
KR100901721B1 (en) Connection apparatus of light weight buffer metal for high-tension wire
CA3032316C (en) Cross arm and angle tower and tension tower comprising the same
KR100840351B1 (en) Insulator fixation apparatus of over head line to distributing of high voltage
KR102265118B1 (en) Electric pole assembly of distribution line
CN105952235B (en) A kind of abnormal shape cross-arm and power transmission rod
KR100936807B1 (en) Power cable space absorbing the vibration
CN107975287B (en) Composite cross arm and transmission pole
CN205908090U (en) Cross arm and strain insulator tower
KR100873518B1 (en) Power cable supporter of line post insulator
KR101293716B1 (en) Insulator for very high voltage distribution line
CN205544113U (en) Cross arm for transmission tower
CN206785078U (en) One kind transmission of electricity cross-arm
CN105633888A (en) Cross arm for transmission tower
KR101772022B1 (en) Tension relaxation apparatus for transmission and distribution tower of overhead wire
KR100667627B1 (en) Device for protecting the jump wire of line postinsulator
KR101543014B1 (en) Prevent the machine back flashover
KR100865074B1 (en) Power cable space for power transmission tower

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120911

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20130927

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20140922

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20150918

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20160922

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20171023

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20180928

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20190917

Year of fee payment: 12