KR100793944B1 - Method for installation of measuring device of a preceding subsidence of the front of a tunnel - Google Patents

Method for installation of measuring device of a preceding subsidence of the front of a tunnel Download PDF

Info

Publication number
KR100793944B1
KR100793944B1 KR1020070033205A KR20070033205A KR100793944B1 KR 100793944 B1 KR100793944 B1 KR 100793944B1 KR 1020070033205 A KR1020070033205 A KR 1020070033205A KR 20070033205 A KR20070033205 A KR 20070033205A KR 100793944 B1 KR100793944 B1 KR 100793944B1
Authority
KR
South Korea
Prior art keywords
measuring device
measuring
wire
tunnel
excavation
Prior art date
Application number
KR1020070033205A
Other languages
Korean (ko)
Inventor
노원석
김완종
권형석
Original Assignee
주식회사 이제이텍
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 이제이텍 filed Critical 주식회사 이제이텍
Priority to KR1020070033205A priority Critical patent/KR100793944B1/en
Application granted granted Critical
Publication of KR100793944B1 publication Critical patent/KR100793944B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Soil Sciences (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

A method for installing a preceding subsidence measuring device of the front of a tunnel is provided to minimize damage of measuring parts and to insert and remove the measuring parts easily by excavating an excavation predicted part and inserting the device on the excavated part. Temporary excavation is carried out around the excavation predicted part(S101). A hardening material is injected in the original ground in the excavated hole(S102). The excavation is carried out in the excavation predicted part after the excavation predicted part is hardened(S103,S104). The excavation is carried out in the excavation predicted part and a preceding subsidence measuring device is inserted in the excavated part(S105).

Description

터널 막장 전방의 선행침하 측정장치의 설치방법{Method for installation of measuring device of a preceding subsidence of the front of a tunnel} Method for installation of measuring device of a preceding subsidence of the front of a tunnel}

도 1은 일반적인 터널 막장 전방의 선행침하 측정을 설명하기 위한 구성도, 1 is a configuration diagram for explaining the pre-sedimentation measurement in front of the general tunnel face,

도 2는 일반적인 터널 막장 전방의 선행침하 측정장치를 설명하기 위한 구성도, Figure 2 is a block diagram for explaining a preliminary settlement measurement device in front of a general tunnel face,

도 3은 본 발명의 일실시예에 따른 터널 막장 전방의 선행침하 측정장치의 설치방법을 나타내는 순서도,Figure 3 is a flow chart showing a method of installing a pre-settling measurement device in front of the tunnel face in accordance with an embodiment of the present invention,

도 4a는 도 3의 단계 101을 나타내는 도면, 도 4b는 도 3의 단계 105를 나타내는 도면,4A is a diagram showing step 101 of FIG. 3, FIG. 4B is a diagram showing step 105 of FIG.

도 5는 본 발명에 따른 선행침하 측정장치를 막장의 선행에 삽입한 상태도,5 is a state in which the pre-settling measuring device according to the present invention is inserted in the front of the film,

도 6은 본 발명의 일 실시예에 따른 선행침하 측정장치의 삽입상태에 따른 단면도,6 is a cross-sectional view according to the insertion state of the pre-settling measuring apparatus according to an embodiment of the present invention,

도 7은 도 6의 하우징헤드의 부분확대도,7 is an enlarged partial view of the housing head of FIG. 6;

도 8은 도 7의 A-A'의 단면도,8 is a cross-sectional view taken along line AA ′ of FIG. 7;

도 9는 본 발명의 일실시예에 따른 선행침하 측정장치의 제거상태에 따른 단면도, 9 is a cross-sectional view of the removal state of the pre-settling measurement apparatus according to an embodiment of the present invention,

도 10은 도 9의 하우징헤드 부분확대도. FIG. 10 is an enlarged view of the housing head of FIG. 9; FIG.

* 도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings

10 : 선행침하 측정장치 11a, 11b, 11c : 측정부 10: presedimentation measuring device 11a, 11b, 11c: measuring unit

12 : 연결부 13a, 13b : 와이어12: connection part 13a, 13b: wire

14a, 14b, 14c : 와이어고정부 15a, 15b, 15c : 이동휠14a, 14b, 14c: wire fixing part 15a, 15b, 15c: moving wheel

16 : 이동휠가이드부 20 : 하우징헤드16: moving wheel guide portion 20: housing head

21 : 하우징몸체 22 : 제 1와이어이동구21 housing body 22: the first wire movement port

23 : 제 2와이어이동구 24 : 풀리 23: 2nd wire movement port 24: pulley

31, 32 : 임의의 천공할 부분 40: 천공 예정 부분31, 32: Random part to be drilled 40: Drilling part

본 발명은 터널 굴착에 따른 막장 전방의 침하상태를 안전적으로 측정하기 위한 터널 막장 전방의 선행침하 측정장치의 설치방법에 관한 것이다. The present invention relates to a method for installing a preliminary settlement measurement device in front of the tunnel face for safely measuring the settlement state of the front face of the tunnel.

최근 사회 간접자본시설 확충을 위하여 터널이 활발하게 시공되고 있으며, 터널시공에 따라서 과거의 기술과 다른 많은 새로운 공법들에 의한 시공이 이루어지고 있다.Recently, tunnels have been actively constructed to expand social indirect capital facilities, and according to the tunnel construction, construction by the past technology and many other new construction methods is being performed.

그러나, 이러한 터널시공에는 어떠한 공법을 적용하든 여러 가지 불확실한 요소들이 많이 존재하게 되는데 그중에서 지질적인 불확실성이 가장 중요한 문제 중의 하나라고 볼 수 있으며, 그 중에서도 터널굴착에 따른 막장전방지질의 연약한층(파쇄대 혹은 공동 외)의 존재 혹은 지반자체의 문제로 터널의 붕락 및 붕괴와 같은 사고로 직면할 수 있다.However, there are many uncertainty factors in this tunnel construction regardless of which method is applied. Among them, geological uncertainty is one of the most important problems, and among them, the weak layer of the membrane-preventing material due to tunnel excavation. Or other problems such as the collapse or collapse of a tunnel due to the presence of the ground or the ground itself.

이에 터널굴착에 따른 터널전방지반의 침하정도를 선형적으로 관리함으로써, 파쇄대 구간 혹은 공동, 지반불량구간의 존재 여부를 사전에 인지하여 터널굴착에 의한 막장전방 지반변화에 따른 터널의 거동 양상을 사전에 예측하고 이에 대한 대책을 수립할 수 있는 기본 데이터를 수집할 필요성이 제시되었다.Therefore, by linearly managing the settlement of the pre-tunnel prevention zone due to tunnel excavation, the presence of fracture zone, cavity, and ground fault zone is recognized in advance, and the behavior of the tunnel according to the change in front of the ground due to tunnel excavation is preliminary. The necessity of collecting basic data to anticipate and develop countermeasures is presented.

이러한 막장 전방의 선행침하를 측정하기 위한 시스템이 대한민국 등록특허 제 10-567810호에 개시되어 있다. 하기의 도 1 및 도 2를 참고하여 설명한다. A system for measuring such a preliminary settlement in front of the membrane is disclosed in Korean Patent Registration No. 10-567810. A description with reference to FIGS. 1 and 2 below.

도 1 에 도시된 터널 막장전방 선행침하 측정 시스템은 터널 막장전방 선행침하를 측정하기 위하여 터널 막장(400)으로부터 일정 거리(20-25m 락볼트의 일반적인 천공심도 4m 감안) 전방의 천장(410)에 천장(410)과 일정 각도(약 10도, 천공기의 천공특성상)로 구멍을 뚫어 측정 장치(100)를 삽입하게 된다. 이때, 측정장치(100)의 길이는 막장의 특성에 따라 다양하게 설정될 수 있으나, 일반적으로 수 미터(센서길이가 각 0.5 ~ 3m 단위로 연결되어져 있음)에 해당하는 길이를 갖고 있다. 측정장치(100)에는 데이터로거(200)와 메인단말기(300)가 연결되어 있다. 데이터로거(200)는 메인단말기(300)로 유무선통신을 통해 제어신호를 전송받아 측정장치(100)로 침하정보 요청신호를 전송할 뿐만 아니라, 측정장치(100)로부터 침하정보를 수신받아 메인단말기(300)로 전송한다. The tunnel-head-front preliminary measurement system shown in FIG. The measuring device 100 is inserted into the ceiling 410 by drilling a hole at a predetermined angle (about 10 degrees, due to the punching characteristics of the punching machine). At this time, the length of the measuring device 100 can be set in various ways depending on the characteristics of the membrane, but generally has a length corresponding to a few meters (the sensor length is connected in units of 0.5 ~ 3m each). The data logger 200 and the main terminal 300 are connected to the measuring device 100. The data logger 200 receives the control signal through the wired / wireless communication to the main terminal 300 and transmits the settlement information request signal to the measurement device 100, and receives the settlement information from the measurement device 100. 300).

한편, 도 1의 측정 장치(100)는 도 2에 도시된 바와 같다. Meanwhile, the measuring apparatus 100 of FIG. 1 is as shown in FIG. 2.

도 2를 참고하면, 측정장치(100)는 경사 센서가 탑재되어 있어 터널 막장전방의 선행침하를 측정하기 위한 측정부(120), 막장 전방의 천장(410)에 뚫린 구멍으로 삽입되어 다수의 측정부(120)의 이동을 가이드하기 위한 케이스(110), 각 측정부를 연결시켜 주기 위한 연결부(130) 및 원하는 길이만큼 측정부를 삽입한 후에 케이스의 입구를 밀봉하므로써, 상기 측정부가 빠져나오는 것을 방지하기 위한 밀폐부(미도시)를 포함하여 구성되어 있다.Referring to FIG. 2, the measuring device 100 is equipped with an inclination sensor so that the measurement unit 120 for measuring the pre-settlement of the tunnel curtain front is inserted into a hole drilled in the ceiling 410 in front of the curtain curtain. The case 110 for guiding the movement of the unit 120, the connection unit 130 for connecting each measurement unit, and by inserting the measurement unit to the desired length after sealing the inlet of the case, to prevent the measurement unit from coming out It is configured to include a seal (not shown) for.

이때, 케이스(110)는 직경이 약 수밀리미터(천공직경에 따라서 틀리며, 일반적으로는 외경 75 ~ 85mm의 ABS 합성수지원형 파이프 사용)로써, 막장전방의 침하에 따라 굴곡될 수 있도록 플라스틱 또는 연한 재질의 합성수지로 재작되는 것이 바람직하다.At this time, the case 110 is about several millimeters in diameter (depending on the diameter of the perforation, generally using an ABS synthetic water support pipe having an outer diameter of 75 to 85 mm), and made of plastic or soft material so that it can be bent according to the settlement of the membrane front. It is preferable to be made of synthetic resin.

또한, 측정부(120)는 직경이 케이스(110)의 직경보다 작도록 구성됨으로써, 케이스(110) 내부에서의 이동이 용이 할 뿐만 아니라, 막장전방의 침하요인 외의 원인에 의해 흔들리지 않게 되어 있다. 또한, 측정부(120)의 일측면에 롤러 형태의 볼(160)이 달려있는 형태로 구성될 수도 있다.In addition, the measuring unit 120 is configured to have a diameter smaller than the diameter of the case 110, so that the inside of the case 110 is not only easy to move, but also shaken by a cause other than the settlement factor in front of the membrane. In addition, the ball 160 in the form of a roller may be formed on one side of the measuring unit 120.

이때, 측정부(120) 각각은 약 0.5m ~ 3m 간격으로 연결부(130)에 의해 연결되어 있으며, 연결부(130)는 각 측정부(120)로부터 나오는 감지 신호를 그 앞단의 측정부로 전송함으로써, 최종적으로 데이터로거(200)로 전송하는 기능을 수행한다. 또한, 연결부(130)는 각 측정부(120)간의 간격을 고정시키기 위하여 스테인레스 재질로 구성되어 있으며, 그 내부에 통신선로뿐만 아니라 전원공급선도 포함 하고 있다.At this time, each of the measuring unit 120 is connected by the connecting unit 130 at intervals of about 0.5m ~ 3m, the connecting unit 130 by transmitting the detection signal from each measuring unit 120 to the measuring unit of the front end, Finally, the data logger 200 is transmitted. In addition, the connection unit 130 is made of a stainless material to fix the interval between each measurement unit 120, and includes a power supply line as well as a communication line therein.

이러한, 측정장치(100)는 천장(410)과 일정 각도로 구멍을 뚫어 삽입하여 전방 선행침하를 측정하고 측정이 끝나고 막장이 이동하면 측정장치(100)를 제거하여 이동된 막장의 천장과 일정 각도로 구멍을 뚫어 다시 삽입하여 측정하고 제거하기를 반복해야한다. This, measuring device 100 is inserted into the ceiling 410 by drilling a hole at a predetermined angle to measure the front subsidence, and when the end of the measurement is finished, the measuring device 100 is removed by removing the measuring device 100 and the ceiling of the moving film It should be repeated by making holes and reinserting them to measure and remove.

그러나 상기와 같은 종래의 터널 막장 전방의 선행침하 측정방식에서는 천장(410)과 일정 각도로 구멍을 뚫어야 하는데, 상기 뚫는 과정에서 천공 홀이 붕괴되어 공벽형성이 이루어지지 않는 문제점이 있었다. 또한, 소정 기간 후, 상기 천공된 홀이 붕괴되어 천공 내에 삽입된 측정장치가 손상되는 문제점이 발생되었다. 이로 인해 선행침하 측정과정에서 반복되어야하는 측정부의 삽입과 제거공정에 차질을 가져오게 되었다.However, in the conventional settlement measurement method in front of the tunnel face as described above, a hole must be drilled at a predetermined angle with the ceiling 410. There is a problem in that the drilling hole is collapsed and the void wall is not formed in the drilling process. In addition, after a predetermined period of time, a problem arises in that the perforated hole collapses and the measuring device inserted in the perforation is damaged. As a result, the insertion and removal process of the measuring part, which has to be repeated in the previous settlement measurement, has been disrupted.

본 발명은 상기와 같은 문제점을 해결하기 위해 안출된 것으로, 그 목적은 천장에 천공하기 전에 천공하고자 하는 천공 예정 부분을 고결하게 한 후에 천공이 이루어지도록 하는 터널 막장 전방의 선행침하 측정장치의 설치방법을 제공하는 데 있다. The present invention has been made to solve the above problems, the purpose of the installation method of the pre-sedimentation measuring device in front of the tunnel membrane to ensure that the puncture is made after the portion to be punctured to puncture before puncturing the ceiling To provide.

이와 같은 목적을 달성하기 위한 본 발명에 따른 터널 막장 전방의 선행침하 측정장치의 설치방법은, 천공하고자 하는 천공 예정 부분의 주위에 임의의 천공을 실시하는 단계; 상기 임의로 천공된 홀 내의 원 지반에 경화재를 투입하는 단계; 천공 예정 부분까지 경화가 이루어지면 그 천공 예정 부분에 천공을 실시하는 단계; 및 상기 천공 예정 부분에 천공을 실시한 후, 그 천공된 부분에 선행침하 측정장치를 삽입하는 단계를 포함한다.According to the present invention, there is provided a method of installing a preliminary settlement measuring device in front of a tunnel face, to achieve the above object, comprising: performing an arbitrary puncturing around a part to be punctured; Injecting a hardener into the original ground in the optionally drilled hole; Performing perforation on the perforated part when curing is performed to the perforated part; And after performing the puncture on the portion to be punctured, comprising the step of inserting the pre-settling measuring device in the punctured portion.

상기 임의의 천공 형성은 상기 천공 예정 부분과 평행하게 동일한 경사, 동일한 폭으로 이루어지는 것이 바람직하다.It is preferable that the said arbitrary punching formation is made with the same inclination and the same width parallel to the said plan part to be drilled.

상기 임의로 천공된 홀 내의 원 지반에 경화재를 투입하는 단계는, 임의로 천공된 홀에 시멘트 맥상 그라우팅 작업을 실시하는 것을 나타냄을 특징으로 한다.Injecting the hardening material into the original ground in the optionally perforated hole, characterized in that the cement vein grouting operation to the optionally perforated hole.

이하, 첨부한 도면을 참조하여 본 발명의 바람직한 실시예를 상세히 기술하기로 한다. Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 3은 본 발명의 일실시예에 따른 터널 막장 전방의 선행침하 측정장치의 설치방법을 나타내는 순서도이고, 도 4a는 도 3의 단계 101을 나타내는 도면이며, 도 4b는 도 3의 단계 105를 나타내는 도면이다.3 is a flowchart illustrating a method of installing a preliminary settlement measuring apparatus in front of a tunnel face in accordance with an embodiment of the present invention, FIG. 4A is a diagram illustrating step 101 of FIG. 3, and FIG. 4B is a diagram illustrating step 105 of FIG. 3. Drawing.

도면을 참조하여 본 발명의 일실시예에 따른 터널 막장 전방의 선행침하 측정장치의 설치방법을 설명하면, 먼저 천공하고자 하는 천공 예정 부분의 주위에 임의의 천공을 실시한다.(S101) 도 4a에서, 점선으로 표기된 부분(40)이 천공 예정 부분이고, 실선으로 된 부분(31)(32)이 임의의 천공 부분을 나타낸다. 본 발명에서는 상기와 같이, 천공 예정 부분의 주위(둘레)(31)(32)에 하나 이상의 임의 천공을 실시한다.Referring to the installation method of the pre-sedimentation measuring device in front of the tunnel face in accordance with an embodiment of the present invention with reference to the drawings, first the arbitrary puncture is to be carried out around the portion to be punctured (S101) in Figure 4a The portion 40 indicated by the dotted line is the portion to be drilled, and the solid portions 31 and 32 represent an arbitrary portion of the drill. In the present invention, as described above, one or more arbitrary punctures are performed around the perimeter (circumference) 31 and 32 of the portion to be punctured.

그런 후, 본 발명에서는 임의로 천공된 홀 내의 원지반에 경화재를 투입한다.(S102) 즉, 임의로 천공된 홀에 시멘트 맥상 그라우팅 등과 같은 작업을 실시한다. Then, in the present invention, a hardening material is introduced into the base in the hole arbitrarily drilled (S102). That is, an operation such as cement grout grouting is optionally performed in the perforated hole.

시멘트 맥상 그라우팅은 일례로 다음과 같은 공정을 거쳐 이루어진다. 즉, 1)시멘트와 물을 376: 376 비율로 혼합하고, 2)조강제(예: 규산 등)와 물을 200: 300 비율로 혼합한 후, 3)상기 두 혼합물을 다시 혼합하여 천공 내로 투입한다. Cement vein grouting is performed by the following process, for example. That is, 1) cement and water are mixed at a ratio of 376: 376, 2) crude steel (eg, silicic acid, etc.) and water are mixed at a ratio of 200: 300, and 3) the two mixtures are mixed again and introduced into the perforation. do.

상기 단계 102처럼 임의로 천공된 홀 내의 원 지반에 경화재를 투입하면, 시간경과에 따라 도 4b와 같이 천공된 홀이 메워질뿐만 아니라 원 지반이 경화되는데, 그 경화가 천공 예정 부분(40)까지 이루어지게 된다.(S103)When the hardening material is put into the original ground in the hole arbitrarily drilled as in step 102, as the time passes, not only the perforated hole is filled but also the original ground is hardened, as shown in FIG. (S103)

상기와 같이, 천공 예정 부분까지 경화가 이루어지면 본 발명에서는 그 천공 예정 부분에 천공을 실시하고(S104), 그 천공된 부분에 선행침하 측정장치를 삽입한다.(S105)As described above, when the hardening is made to the portion to be drilled, the present invention performs the drilling on the portion to be drilled (S104), and inserts a pre-settling measuring device into the drilled portion. (S105)

단계 105에서 상기 임의의 천공 형성은 상기 천공 예정 부분과 평행하게 동일한 경사, 동일한 폭으로 이루어지는 것이 바람직하다.Preferably, in step 105, the optional perforation is made of the same inclination and the same width in parallel with the part to be drilled.

상기와 같이, 본 발명에서는 천공 예정 부분의 원 지반이 고결하게 경화되어 있으므로 안전하게 천공 예정 부분의 천공이 가능할 뿐만 아니라 추후 천공된 부분이 붕괴되는 사고도 방지할 수 있다. 이로 인해 본 발명에서는 천공 내에 삽입된 측정장치의 손상을 최소화할 수 있을 뿐만 아니라 선행침하 측정과정에서 반복되어야하는 측정부의 삽입과 제거공정을 용이하게 할 수 있다. As described above, in the present invention, since the original ground of the portion to be drilled is solidly hardened, not only the drilling of the portion to be drilled can be performed safely but also an accident in which the drilled portion is collapsed later. As a result, in the present invention, not only damage of the measuring device inserted into the perforation can be minimized, but also easy insertion and removal of the measuring part to be repeated in the preliminary settlement measurement process.

다음으로, 도 5 내지 도 10을 참조하여 단계 105에서 삽입되는 본 발명의 일실시예에 따른 터널 막장 전방의 선행침하 측정장치에 대해 설명하기로 한다. Next, with reference to Figures 5 to 10 will be described for the pre-settling measurement device in front of the tunnel face according to an embodiment of the present invention inserted in step 105.

도 5는 본 발명에 따른 선행침하 측정장치를 막장의 선행에 삽입한 상태도이다. 5 is a state diagram in which the pre-sedimentation measuring device according to the present invention is inserted in advance of the membrane.

도 5를 참고하면, 터널 막장전방 선행침하를 측정하기 위하여 터널 막장의 천장에 천장과 일정 각도로 구멍을 뚫어 측정 장치(10)를 삽입한 상태를 보여준다. 이러한 측정장치(10)를 이하의 도 6 내지 도 10을 참고하여 설명한다. Referring to FIG. 5, the measurement apparatus 10 is inserted by drilling a hole at a predetermined angle with the ceiling in the ceiling of the tunnel curtain to measure the front-side settlement of the tunnel curtain. This measuring device 10 will be described with reference to FIGS. 6 to 10 below.

도 6은 본 발명의 일 실시예에 따른 선행침하 측정장치의 삽입상태에 따른 단면도이다. 6 is a cross-sectional view according to the insertion state of the pre-settling measurement apparatus according to an embodiment of the present invention.

도 6의 선행침하 측정장치(10)는 경사 센서가 탑재되어 있어 터널 막장전방의 선행침하를 측정하기 위한 측정부(11a, 11b, 11c), 막장 전방의 천장(410)에 뚫린 구멍으로 삽입되어 다수의 측정부(11a, 111b, 11c)를 연결하기 위한 연결부(12)와, 측정부(11a, 11b, 11c) 각각에 와이어고정부(14a, 14b, 14c)에 의해 고정된 와이어(13a)와, 각 측정부(11a, 11b, 11c)의 이동을 위한 이동휠(15a, 15b, 15c)을 포함한다. 또한, 이러한 측정장치(10)는 와이어(13a)와 반대편 와이어(13b)에 도르레 작용을 하기 위한 풀리(24)와 풀리(24)를 감싸고 있는 하우징헤드(20)와 와이어(13a)를 이동시키기 위한 제 1와이어이동구(22)와 또 다른 반대편 와이어(13b)를 이동시키기 위한 제 2와이어이동구(23)를 포함한다. 그리고 측정장치(10)는 하우 징헤드(20)와 체결되도록 하며 측정부(11a, 11b, 11c)와 와이어(13a)를 내부에 구성하는 하우징몸체(21)로 구성된다. 여기서 와이어(13b)는 하우징몸체(21)내부에 구성되지 않으며 하우징헤드(20)의 일측에 제 2와이어이동구(23)를 통해 이동하도록 형성된다. 와이어(13a)의 일부는 측정부(11a, 11b, 11c)에 고정되어 측정부(11a, 11b, 11c)가 이동하도록 연결되며 풀리(24)를 지난 와이어(13b)는 제2와이어이동구(23)를 통해 외부로 노출되어 있다. 여기서 와이어(13a, 13b)는 연결된 하나의 와이어임이 자명하지만, 설명의 편의상 풀리(24)를 기준으로 제 1와이어이동구(22)쪽에 노출된 와이어를 13a로 설명하고 제 2와이어이동구(23)쪽에 노출된 와이어를 13b로 설명한다. 여기서 와이어(13a)는 노출되어도 하우징몸체(21)에 의해 보호되며, 와이어(13b)는 외부로 노출되면 땅과 접촉되기 때문에 이를 방지하기 위해 외부에 와이어(13b)를 감싸고 있는 파이프의 내부에 위치시킨다. The preliminary settlement measuring apparatus 10 of FIG. 6 is equipped with an inclination sensor and is inserted into a hole drilled in the measurement units 11a, 11b, and 11c for measuring preliminary settlement in the front of the tunnel curtain, and the ceiling 410 in front of the curtain curtain. A connecting portion 12 for connecting the plurality of measuring portions 11a, 111b, and 11c, and a wire 13a fixed by the wire fixing portions 14a, 14b, and 14c to the measuring portions 11a, 11b, and 11c, respectively. And moving wheels 15a, 15b, and 15c for the movement of each measuring unit 11a, 11b, and 11c. In addition, the measuring device 10 moves the pulley 24 and the housing head 20 and the wire 13a surrounding the pulley 24 and the pulley 24 to pulley the wire 13a and the opposite wire 13b. And a second wire mover 23 for moving the first wire mover 22 and another opposite wire 13b. And the measuring device 10 is coupled to the housing head 20 and is composed of a housing body 21 constituting the measuring portion (11a, 11b, 11c) and the wire (13a) inside. The wire 13b is not configured in the housing body 21 and is formed to move through the second wire moving hole 23 on one side of the housing head 20. A part of the wire 13a is fixed to the measuring units 11a, 11b and 11c so that the measuring units 11a, 11b and 11c are connected to move, and the wire 13b passing through the pulley 24 is the second wire moving hole 23. ) Is exposed to the outside. Here, it is obvious that the wires 13a and 13b are connected one wire, but for convenience of description, the wire exposed to the first wire moving hole 22 side with respect to the pulley 24 is described as 13a and the second wire moving hole 23 side. The exposed wire is described as 13b. Here, the wire 13a is protected by the housing body 21 even when exposed, and the wire 13b is located inside the pipe surrounding the wire 13b to prevent the wire 13b from contacting the ground when exposed to the outside. Let's do it.

작업자는 측정부(11a, 11b, 11c)의 삽입 또는 제거에 따라 참조부호 13a의 와이어와 참조부호 13b의 와이어를 선택적으로 당김으로써 측정부(11a, 11b, 11c)를 막장의 전방에 천장 상부로 용이하게 설치하거나 제거할 수 있다.By selectively pulling the wire 13a and the wire 13b according to the insertion or removal of the measuring portions 11a, 11b, and 11c, the operator moves the measuring portions 11a, 11b, and 11c upwards to the ceiling in front of the curtain. Easy to install or remove

도 6의 측정장치(10)는 하우징헤드(20)의 내부에 마련된 풀리(24)에 의해 도르레 작용을 하는 와이어(13a, 13b)중의 하나를 당김에 의해 측정부(11a, 11b, 11c)가 삽입되거나 제거되는 구성이다. 즉, 터널 막장으로부터 일정거리 전방의 천장에 천장과 일정각도로 구멍을 뚫어 측정장치(10)를 삽입할 때, 와이어(13a, 13b)가 풀리(24)에 의해 연결된 하우징헤드(20)와 하우징몸체(21)를 먼저 삽입하고, 작업자는 와이어(13b)의 줄을 실선화살표(와이어이동방향)로 당기면 도 6에 도 시된 바대로 와이어(13a)에 의해 고정된 측정부(11a, 11b, 11c)가 줄줄이 당겨져 삽입되도록 구성된다. 이때 도 6에 점선화살표(측정부이동방향)와 같이 측정부가 11c, 11b, 11a 순으로 밀려 들어와 순서대로 삽입된다. In the measuring device 10 of FIG. 6, the measuring units 11a, 11b, and 11c are pulled by pulling one of the wires 13a and 13b which act as a pulley by the pulley 24 provided in the housing head 20. It is a component that is inserted or removed. That is, when the measuring device 10 is inserted into the ceiling at a predetermined distance from the tunnel face by the ceiling, the housing head 20 and the housing connected by the pulley 24 are connected to the wires 13a and 13b. The body 21 is inserted first, and the operator pulls the string of the wire 13b in a solid arrow (wire moving direction), and as shown in FIG. 6, the measuring portions 11a, 11b, and 11c fixed by the wire 13a. Is configured to be pulled out and inserted. At this time, as shown by the dotted arrow (measurement moving direction) in Figure 6, the measurement unit is pushed in the order of 11c, 11b, 11a is inserted in order.

이러한 측정부(11c)의 삽입상태를 도 7의 부분 확대도를 참고로 좀 더 상세히 살펴본다. The insertion state of the measuring unit 11c will be described in more detail with reference to the partially enlarged view of FIG. 7.

도 7은 도 6의 하우징헤드의 부분 확대도이다. FIG. 7 is a partially enlarged view of the housing head of FIG. 6.

도 7을 참고하면, 측정장치(10)는 하우징헤드(20)와 측정부(11c)만을 도시하였으며 측정부(11c)가 하우징헤드(20)쪽으로 이동하는 상태를 보여준다. 작업자가 와이어(13b)를 실선화살표(와이어이동방향)로 당기면 측정부(11c)는 당긴 만큼씩 이동(점선표시)하여 점선화살표 방향으로 측정부(11c)가 삽입된다. 이러한 측정부(11c)가 와이어(13a, 13b)에 의해 이동하는 과정을 도 8을 통해 상세히 설명한다. Referring to FIG. 7, the measuring device 10 shows only the housing head 20 and the measuring unit 11c and shows a state in which the measuring unit 11c moves toward the housing head 20. When the worker pulls the wire 13b in a solid arrow (wire moving direction), the measuring unit 11c is moved (dotted line) by the pulling amount so that the measuring unit 11c is inserted in the dotted arrow direction. The process in which the measuring unit 11c moves by the wires 13a and 13b will be described in detail with reference to FIG. 8.

도 8은 도 7의 A-A'의 단면도이다.FIG. 8 is a cross-sectional view taken along line AA ′ of FIG. 7.

도 8을 참고하면, 측정부(11c)의 상하로 이동휠(15c)을 구비하고 이동휠(15c)은 상하대칭과 좌우대칭 중의 어느 하나의 이동휠가이드부(16)에 의해 가이드되도록 구성된다. 이동휠가이드부(16)는 하우징몸체(21)의 내부로 마주보는 면에 상호 대칭되도록 상하대칭과 좌우대칭의 홈형태로 구성된다. 이동휠(15c)을 고정하고 있는 측정부(11c)는 와이어(13a)가 이동과 함께 이동휠가이드부(16)를 따라 가이드되면서 이동한다. 여기서, 복수개의 측정부가 한꺼번에 이동하더라도 이동휠가이드부(16)를 따라 이동하므로 뒤틀어짐 없이 순서대로 삽입 및 제거가 가능함 은 자명하다.Referring to FIG. 8, the moving wheel 15c is provided upward and downward of the measuring unit 11c, and the moving wheel 15c is configured to be guided by any of the moving wheel guide portions 16 of up and down symmetry and left and right symmetry. . The moving wheel guide part 16 is configured in the form of a groove of up and down symmetry and left and right symmetry so as to be mutually symmetrical to the surface facing the inside of the housing body 21. The measuring part 11c holding the moving wheel 15c moves while the wire 13a is guided along the moving wheel guide part 16 with movement. Here, it is apparent that even if the plurality of measuring parts move at once, they move along the moving wheel guide part 16 and thus can be inserted and removed in order without distortion.

도 9는 본 발명의 일실시예에 따른 선행침하 측정장치의 제거상태에 따른 단면도이다. 9 is a cross-sectional view of the removal state of the pre-settling measurement apparatus according to an embodiment of the present invention.

도 9는 도 6에서 설명한 측정장치(10)가 삽입된 상태에서 제거를 위해 이동한 상태를 보여준다. 작업자는 삽입된 측정장치(10)를 제거하기 위해서 와이어(13a)의 줄을 실선화살표(와이어이동방향)로 당기면 도 9에 도시된바 대로 와이어(13a)에 의해 고정된 측정부(11a, 11b, 11c)가 줄줄이 당겨져 제거되도록 구성된다. 이때 도 9에 점선화살표(측정부이동방향)와 같이 측정부가 11a, 11b, 11c 순으로 밀려 나오면서 제거된다. 도 9의 참조부호중 도 6과 동일 참조부호에 대해서는 동일기능을 수행하므로 상세한 설명은 생략한다. FIG. 9 shows a state in which the measuring device 10 described in FIG. 6 is moved for removal in the inserted state. When the operator pulls the string of the wire 13a in a solid arrow (wire moving direction) to remove the inserted measuring device 10, the measuring portions 11a and 11b fixed by the wire 13a as shown in FIG. 11c) is configured such that the file is pulled out and removed. At this time, as shown by the dotted arrow (measurement moving direction) in Figure 9, the measurement unit is removed while being pushed in the order 11a, 11b, 11c. The same reference numerals as those of FIG. 6 in the reference numerals of FIG. 9 perform the same functions, and thus detailed descriptions thereof will be omitted.

이러한 측정부(11c)의 제거상태를 도 10의 부분 확대도를 참고로 좀 더 상세히 살펴본다. The removal state of the measuring unit 11c will be described in more detail with reference to the partially enlarged view of FIG. 10.

도 10은 도 9의 하우징헤드의 부분 확대도이다. 10 is a partially enlarged view of the housing head of FIG. 9.

도 10을 참고하면, 측정장치(10)는 하우징헤드(20)와 측정부(11c)만을 도시하였으며 측정부(11c)가 하우징헤드(20)의 반대쪽으로 이동하는 상태를 보여준다. 작업자가 와이어(13a)를 실선화살표(와이어이동방향)로 당기면 측정부(11c)는 당긴 만큼씩 이동(점선표시)하여 점선화살표방향으로 측정부(11c)가 제거된다. 이러한 측정부(11c)가 와이어(13a, 13b)에 의해 이동하는 과정은 전술한 도 8과 같다.Referring to FIG. 10, the measuring device 10 shows only the housing head 20 and the measuring unit 11c, and shows the state in which the measuring unit 11c moves to the opposite side of the housing head 20. When the worker pulls the wire 13a in a solid arrow (wire moving direction), the measuring unit 11c is moved (dotted line) by the pulling amount so that the measuring unit 11c is removed in the dotted arrow direction. The movement of the measuring unit 11c by the wires 13a and 13b is the same as that of FIG. 8 described above.

상기와 같이, 본 발명의 터널 막장 전방의 선행침하 측정장치의 설치방법은 천공 예정 부분의 원 지반을 고결하게 경화시킴으로써 안전한 천공 예정 부분의 천공이 가능할 뿐만 아니라 추후 천공된 부분이 붕괴되는 사고도 방지할 수 있다. As described above, the installation method of the pre-sedimentation measuring device in front of the tunnel face of the present invention by hardening the original ground of the portion to be drilled securely, not only the drilling of the portion to be drilled is possible, but also prevents the accident of the perforated portion to collapse later. can do.

이로 인해 본 발명에서는 천공 내에 삽입된 측정장치의 손상을 최소화할 수 있을 뿐만 아니라 선행침하 측정과정에서 반복되어야하는 측정부의 삽입과 제거공정을 용이하게 할 수 있다. As a result, in the present invention, not only damage of the measuring device inserted into the perforation can be minimized, but also easy insertion and removal of the measuring part to be repeated in the preliminary settlement measurement process.

Claims (3)

터널 막장전방의 선행침하를 측정하는 선행침하 측정장치의 설치방법에 있어서,In the installation method of the presedimentation measuring apparatus for measuring the preliminary settlement of the tunnel face ahead, 천공하고자 하는 천공 예정 부분의 주위에 임의의 천공을 실시하는 단계;Performing any puncturing around the portion to be punctured to be punctured; 상기 임의로 천공된 홀 내의 원 지반에 경화재를 투입하는 단계;Injecting a hardener into the original ground in the optionally drilled hole; 천공 예정 부분까지 경화가 이루어지면 그 천공 예정 부분에 천공을 실시하는 단계; 및Performing perforation on the perforated part when curing is performed to the perforated part; And 상기 천공 예정 부분에 천공을 실시한 후, 그 천공된 부분에 선행침하 측정장치를 삽입하는 단계를 포함함을 특징으로 하는 터널 막장 전방의 선행침하 측정장치의 설치방법.And a step of inserting a pre-sedimentation measuring device into the perforated portion after performing the perforation on the predetermined part of the perforation. 제 1항에 있어서,The method of claim 1, 상기 임의의 천공 형성은 상기 천공 예정 부분과 평행하게 동일한 경사, 동일한 폭으로 이루어지는 것을 특징으로 하는 터널 막장 전방의 선행침하 측정장치의 설치방법.The arbitrary puncturing is formed in the same slope, the same width parallel to the predetermined portion to be punctured, the installation method of the pre-settling measuring device in front of the tunnel face. 제 1항에 있어서,The method of claim 1, 상기 임의로 천공된 홀 내의 원 지반에 경화재를 투입하는 단계는, 임의로 천공된 홀에 시멘트 맥상 그라우팅 작업을 실시하는 것을 나타냄을 특징으로 하는 터널 막장 전방의 선행침하 측정장치의 설치방법.The step of injecting the hardening material into the original ground in the optionally perforated hole, the installation method of the pre-settling measuring device in front of the tunnel face, characterized in that to perform the cement vein grouting operation to the optionally perforated hole.
KR1020070033205A 2007-04-04 2007-04-04 Method for installation of measuring device of a preceding subsidence of the front of a tunnel KR100793944B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020070033205A KR100793944B1 (en) 2007-04-04 2007-04-04 Method for installation of measuring device of a preceding subsidence of the front of a tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020070033205A KR100793944B1 (en) 2007-04-04 2007-04-04 Method for installation of measuring device of a preceding subsidence of the front of a tunnel

Publications (1)

Publication Number Publication Date
KR100793944B1 true KR100793944B1 (en) 2008-01-16

Family

ID=39218075

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020070033205A KR100793944B1 (en) 2007-04-04 2007-04-04 Method for installation of measuring device of a preceding subsidence of the front of a tunnel

Country Status (1)

Country Link
KR (1) KR100793944B1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04264228A (en) * 1991-02-18 1992-09-21 Shigeki Nagatomo Underground subsidence measuring apparatus
KR100567810B1 (en) 2004-04-26 2006-04-05 (주)지오넷 System For Measuring A Preceding Subsidence Of The Front Of A Tunnel Face And Its Method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04264228A (en) * 1991-02-18 1992-09-21 Shigeki Nagatomo Underground subsidence measuring apparatus
KR100567810B1 (en) 2004-04-26 2006-04-05 (주)지오넷 System For Measuring A Preceding Subsidence Of The Front Of A Tunnel Face And Its Method

Similar Documents

Publication Publication Date Title
CN108678777B (en) Support method for tunnel fault fracture zone section
KR100776304B1 (en) Direct punching simultaneous poruing equipment and grouting construction method
KR200424432Y1 (en) Direct punching simultaneous poruing equipment
KR101665515B1 (en) Direct-boring pipe roof tunnel construction method and structure non-cutting natural ground
CN102536158B (en) Uphole sealing method
JP2010163748A (en) Earth retaining wall load testing method
JP2009174178A (en) Method of constructing underground structure
KR20170102397A (en) The Tunnel construction method to use retangular pipe
JP4682944B2 (en) Composite grout water stop method around mine shaft
KR20090007826A (en) Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
KR100793944B1 (en) Method for installation of measuring device of a preceding subsidence of the front of a tunnel
KR20130089225A (en) Method of construction a shallow tunnel using pre-support beam
KR100958053B1 (en) Water stopping anchoring method using pressing
JP3834571B2 (en) Construction method for underground structures
KR20040110204A (en) Earth anchor including a duplex grouting pipe and the earth anchor construction method using the same
JP2016089528A (en) Shear reinforcement method for concrete structure
JP2006077402A (en) Underground timbering structure and its construction method, and tunnel construction method
KR20120009248A (en) Permeability rock stagnant water grouting method for bulk injection type
JP4228898B2 (en) Construction method of underground cavity
JP2015113572A (en) Method to install precedent underground displacement gage
KR100793941B1 (en) Housing-head of apparatus for measuring a preceding subsidence of the front of a tunnel
JP2007023546A (en) Entrance for arrival of jacking pipe, structure of entrance for arrival, and water cut-off construction method for entrance for arrival
CN106592654A (en) Monitoring method for perpendicularity of steel pipe pile
KR101440963B1 (en) System constructing underground structure by the pulling force of tension member and method constructing underground structure thereby
JP6396710B2 (en) Filling status detector

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130104

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20140103

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20150130

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20160104

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20170102

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20171222

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20191223

Year of fee payment: 13