KR100793578B1 - Apparatus for press controlling of hopper of blast furnace - Google Patents

Apparatus for press controlling of hopper of blast furnace Download PDF

Info

Publication number
KR100793578B1
KR100793578B1 KR1020010081889A KR20010081889A KR100793578B1 KR 100793578 B1 KR100793578 B1 KR 100793578B1 KR 1020010081889 A KR1020010081889 A KR 1020010081889A KR 20010081889 A KR20010081889 A KR 20010081889A KR 100793578 B1 KR100793578 B1 KR 100793578B1
Authority
KR
South Korea
Prior art keywords
blast furnace
hopper
pressure
charge
charge hopper
Prior art date
Application number
KR1020010081889A
Other languages
Korean (ko)
Other versions
KR20030052073A (en
Inventor
이동형
정승원
변동욱
Original Assignee
주식회사 포스코
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 포스코 filed Critical 주식회사 포스코
Priority to KR1020010081889A priority Critical patent/KR100793578B1/en
Publication of KR20030052073A publication Critical patent/KR20030052073A/en
Application granted granted Critical
Publication of KR100793578B1 publication Critical patent/KR100793578B1/en

Links

Images

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B7/00Blast furnaces
    • C21B7/18Bell-and-hopper arrangements
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B7/00Blast furnaces
    • C21B7/24Test rods or other checking devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Blast Furnaces (AREA)

Abstract

본 발명은 장입물호퍼 내부의 가압시 질소를 사용하지 않고 장입물호퍼를 가압할 수 있도록 된 고로 장입물호퍼의 가압제어장치를 제공하는 데 목적이 있다.It is an object of the present invention to provide a pressure control device for a blast furnace charge hopper which is capable of pressurizing the charge hopper without using nitrogen when pressurizing the charge hopper.

따라서 본 발명은 고로의 노정에 설치되어 고로에 장입되는 장입물을 일시 저장한 후 장입하도록 설치된 고로 장입물호퍼의 가압제어장치에 있어서, 장입물호퍼의 내부 압력을 검출하는 호퍼압력검출기와 고로 내부의 압력을 검출하는 고로압력검출기로 이루어진 검출부; 호퍼압력검출기와 고로압력검출기로부터 검출된 압력을 비교하는 차압검출기; 장입물호퍼에 유입되는 가스를 가압하는 승압기와 승압기로부터 배출되는 가스의 흐름을 개폐하는 호퍼가압제어밸브를 제어하는 제어부를 포함하는 고로 장입물호퍼의 가압제어장치를 제공한다.Therefore, the present invention is a pressure control device of the blast furnace charge hopper installed in the blast furnace blast furnace to temporarily store the charges charged in the blast furnace and then charged, the hopper pressure detector for detecting the internal pressure of the charge hopper and the inside of the blast furnace Detecting unit consisting of a blast furnace pressure detector for detecting the pressure of the; A differential pressure detector for comparing the pressure detected from the hopper pressure detector with the blast furnace pressure detector; It provides a pressure control device of the blast furnace charge hopper including a control unit for controlling the hopper pressure control valve for opening and closing the flow of the gas discharged from the booster and pressurizing the gas flowing into the charge hopper.

장입물호퍼, 고로, 차압검출기, 승압기Charge Hopper, Blast Furnace, Differential Pressure Detector, Booster

Description

고로 장입물호퍼의 가압 제어장치{APPARATUS FOR PRESS CONTROLLING OF HOPPER OF BLAST FURNACE}Pressure regulating device of blast furnace charge hopper {APPARATUS FOR PRESS CONTROLLING OF HOPPER OF BLAST FURNACE}

도 1은 종래기술에 따른 고로 장입물호퍼의 가압 제어장치가 설치된 고로설비를 개략적으로 나타내는 도면.  1 is a view schematically showing the blast furnace equipment is installed pressure control device of the blast furnace charge hopper according to the prior art.

도 2는 본 발명에 따른 고로 장입물호퍼의 가압 제어장치가 설치된 고로설비를 개략적으로 나타내는 도면.  Figure 2 is a schematic view of the blast furnace equipment installed pressure control device of the blast furnace charge hopper according to the present invention.

<도면의 주요 부분에 대한 부호의 설명 >  <Explanation of symbols for main parts of the drawings>

1 : 고로 2 : 장입물호퍼  1: blast furnace 2: charged hopper

3a : 분배슈트 7 : 승압기  3a: distribution chute 7: booster

9 :노정압 발전기  9: static pressure generator

본 발명은 고로에 연료 및 원료의 장입시 장입물호퍼의 압력을 제어하는 고로 장입물호퍼의 가압 제어장치에 관한 것으로, 더욱 상세하게는 고로에 연료 및 원료의 장입시 질소를 사용하지 않고 반청정 개스를 이용하여 장입물호퍼를 가압하여 고로의 내부압력으로 인한 원료 및 연료의 미장입되는 것을 방지하고,장입노치 에 정확하게 연료 및 원료가 장입되도록 하는 고로 장입물호퍼의 가압 제어장치에 관한 것이다.The present invention relates to a pressure control device of the blast furnace charge hopper for controlling the pressure of the charge hopper when charging the fuel and the raw material into the blast furnace, more specifically, the semi-clean without using nitrogen when charging the fuel and raw material into the blast furnace The present invention relates to a pressure control device for a blast furnace charge hopper which pressurizes a charge hopper using gas to prevent unloading of raw materials and fuel due to internal pressure of the blast furnace, and to accurately load fuel and raw material into the charge notch.

일반적으로 고로에서 원료 및 연료 등의 장입물을 장입하는 고로 장입설비는 장입물을 평량하는 장입물평량호퍼와, 평량된 장입물을 운반하는 벨트컨베이어와 운반된 장입물을 저장한 후 내부를 가압하여 장입물을 고로의 내부에 장입시키는 장입물호퍼로 이루어진다.In general, a blast furnace charging facility that charges charges such as raw materials and fuels in a blast furnace is charged with a charge hopper for weighing charges, a belt conveyor for carrying the weighted charges, and a pressurized inside after storing the transported charges. It consists of a charge hopper to charge the charge into the interior of the blast furnace.

여기서 장입물을 고로에 장입하기 위해 장입물호퍼의 내부를 가압하는 장입물호퍼의 가압장치는 도 1에 도시된 바와 같이 중량검출기(7h)에서 장입물호퍼(2)의 중량을 검출하여 장입완료 여부를 감지하게 되고, 장입완료가 검출되면 고로(1)의 내부에 장입물을 장입하기 위하여 장입물호퍼(2)의 내부를 가압한다.Here, the pressurizing device of the charge hopper for pressurizing the inside of the charge hopper to charge the charge into the blast furnace detects the weight of the charge hopper 2 in the weight detector 7h as shown in FIG. When it is detected, and the charging completion is detected to press the inside of the charge hopper (2) to charge the load into the interior of the blast furnace (1).

또한 장입물호퍼(2)의 내부를 가압한 상태에서 장입물을 고로(1)에 장입한 후, 배압라인에 설치된 가스회수차단밸브(13)를 개방하여 압력을 노정압발전기(9)로 배압시킨다.In addition, after charging the charge into the blast furnace (1) in the state of pressurizing the inside of the charge hopper (2), the gas recovery shut-off valve 13 installed in the back pressure line is opened to back pressure to the notch generator (9). Let's do it.

여기서 저장된 장입물을 고로(1)에 장입하기 위해서는 노정의 장입물호퍼(2)를 하부의 고로(1) 내부의 압력과 일치되도록 가압시켜 장입을 실시해야 한다.In order to charge the stored charge in the blast furnace (1) it is necessary to pressurize the charging hopper (2) of the top to match the pressure inside the blast furnace (1) in the lower portion.

따라서 가압차단밸브(12)를 개방시켜 청정설비의 전단으로부터 반청정가스를 인가하여 장입물호퍼(2)에 가압시켜 압력을 상승시켜 1차 가압을 완료하게 된다.Therefore, by opening the pressure blocking valve 12 to apply a semi-clean gas from the front end of the clean facility to pressurize the charge hopper (2) to increase the pressure to complete the primary pressure.

또한 노정호퍼차압검출기(7a)에서 1차 가압완료를 감지하게 되면 질소(N2)를 2차가압차단밸브(2b)를 개방시켜 2차 가압을 실시하게 된다. In addition, when the primary hopper differential pressure detector 7a detects the completion of the primary pressurization, the secondary pressurization valve 2b is opened with nitrogen (N 2 ) to perform the secondary pressurization.

따라서 2차 가압이 완료되면 장입물호퍼(2) 내부의 장입물을 고로(1)의 내부로 장입시킨다.Therefore, when the secondary pressurization is completed, the contents of the charging hopper 2 are charged into the blast furnace 1.

여기서 장입물호퍼(2) 가압의 제어는 가압차단밸브(12)를 개방하면 청정설비 전단의 반청정된 가스가 장입물호퍼(2) 내부로 회수되어 1차압력이 상승하게 되고, 2차가압차단밸브(2b)가 개방시켜 질소를 인가하므로 목표 압력까지 장입물호퍼(2)의 내부를 가압하게 된다.Here, in the control of the charge of the charge hopper 2, when the pressure shutoff valve 12 is opened, the semi-clean gas at the front of the clean facility is recovered into the charge hopper 2 so that the primary pressure is increased and the secondary pressure is increased. Since the shutoff valve 2b is opened to apply nitrogen, the inside of the charge hopper 2 is pressurized to the target pressure.

이와 같이 가압이 완료되면 장입물호퍼(2)로부터 장입물의 장입이 개시되고, 장입물호퍼(2) 내부의 압력을 유지시키기 위하여 2차가압차단밸브(2b)를 개방된 상태로 유지하여야 질소가스가 계속 필요하며 이로 인해 공장 라인의 질소압력이 저하된다.When the pressurization is completed as described above, charging of the charging material is started from the charging hopper 2, and in order to maintain the pressure in the charging hopper 2, the secondary pressure shut-off valve 2b must be kept open to nitrogen gas. Is still required, which reduces the nitrogen pressure in the plant line.

따라서 질소압력의 저하로 인하여 질소를 사용하는 PCI COAL 취입능력이 정하되고, 질소공장이 과부하를 받게 되고, 노정의 기어박스 질소압력의 저하로 인한 BFG 가스의 역류로 대형 사고를 발생시키는 문제점이 있다..Therefore, there is a problem that the PCI COAL blowing capacity using nitrogen is reduced due to the decrease in nitrogen pressure, the nitrogen plant is overloaded, and a large accident occurs due to the backflow of BFG gas due to the decrease in the gearbox nitrogen pressure of the road. ..

또한 장입물호퍼 내부의 압력이 용광로 내부의 압력에 비해 감소되면 순간적으로 장입물을 투입하지 못하고 홀딩되므로 장입지연이 발생하게 되어 생산성이 떨어지는 문제점이 있다.In addition, when the pressure inside the charge hopper is reduced compared to the pressure inside the furnace, the charge may not be instantaneously held and the charging delay may occur, resulting in a decrease in productivity.

아울러 장입물이 적절한 시기에 투여되지 못하므로 장입노치로 장입물이 정확하게 장입되지 못하여 장입물 분포제어가 불량하여 노황관리에 문제가 발생되고 이로 인한 용선의 품질이 떨어지는 문제점이 있다.In addition, because the charges are not administered at the proper time, the charges are not accurately charged with the charge notch, and the distribution control of the charges is poor.

따라서 본 발명은 종래기술의 문제점을 해결하기 위하여 안출된 것으로, 그 목적은 장입물호퍼 내부의 가압시 질소를 사용하지 않고 장입물호퍼를 가압할 수 있도록 된 고로 장입물호퍼의 가압제어장치를 제공하는 데 있다. Accordingly, the present invention has been made to solve the problems of the prior art, the object of the present invention is to provide a pressure control device of the blast furnace charge hopper that can pressurize the charge hopper without using nitrogen when pressurized inside the charge hopper. There is.

상기한 바와 같은 목적을 달성하기 위하여 본 발명은 고로의 노정에 설치되어 고로에 장입되는 장입물을 일시 저장한 후 장입하도록 설치된 고로 장입물호퍼의 가압제어장치에 있어서, 장입물호퍼의 내부 압력을 검출하는 호퍼압력검출기와 고로 내부의 압력을 검출하는 고로압력검출기로 이루어진 검출부; 호퍼압력검출기와 고로압력검출기로부터 검출된 압력을 비교하는 차압검출기; 장입물호퍼에 유입되는 가스를 가압하는 승압기와 승압기로부터 배출되는 가스의 흐름을 개폐하는 호퍼가압제어밸브를 제어하는 제어부를 포함하는 고로 장입물호퍼의 가압제어장치를 제공한다.In order to achieve the above object, the present invention provides a pressure control device for a blast furnace charge hopper installed in a blast furnace to temporarily charge and store the charges charged in the blast furnace, the internal pressure of the charge hopper A detection unit comprising a hopper pressure detector for detecting and a blast furnace pressure detector for detecting a pressure in the blast furnace; A differential pressure detector for comparing the pressure detected from the hopper pressure detector with the blast furnace pressure detector; It provides a pressure control device of the blast furnace charge hopper including a control unit for controlling the hopper pressure control valve for opening and closing the flow of the gas discharged from the booster and pressurizing the gas flowing into the charge hopper.

여기서 승압기에서 가압되는 가스는 상기 고로에서 배출된 가스를 회수한 회수가스인 것이 바람직하다.The gas pressurized by the booster is preferably a recovery gas obtained by recovering the gas discharged from the blast furnace.

또한 회수가스는 청정설비를 통과하지 않은 반청정가스인 것이 바람직하다.In addition, the recovery gas is preferably a semi-clean gas that does not pass through the clean facility.

이하 본 발명에 따른 고로 장입물호퍼의 가압제어장치를 첨부도면을 참조하여 설명하면 다음과 같다.Hereinafter, the pressure control device of the blast furnace charge hopper according to the present invention will be described with reference to the accompanying drawings.

도 2는 본 발명에 따른 고로 장입물호퍼의 가압 제어장치가 설치된 고로설비를 개략적으로 나타내는 도면이다.Figure 2 is a schematic view of the blast furnace equipment is installed pressure control device of the blast furnace charge hopper according to the present invention.

본 발명에 따른 고로 장입물호퍼의 가압제어장치는 청정설비 전단의 반청정 가스배관에 장입물호퍼(2)가 연통 설치되고, 이 장입물호퍼(2)에 유입되는 가스를 승압하는 승압기(7)가 반청정가스배관에 설치되며, 장입물호퍼(2)와 승압기(7)를 연통시키는 배관에 승압기(7)에서 가압되어 배출되는 가스의 흐름을 개폐시키는 호퍼가압제어밸브(7b)가 설치된다.In the pressure control device of the blast furnace charge hopper according to the present invention, the charge hopper (2) is installed in the semi-clean gas pipe in front of the clean facility, the booster (7) for boosting the gas flowing into the charge hopper (2) ) Is installed in the semi-clean gas pipe, and a hopper pressure control valve 7b is installed in the pipe connecting the charge hopper 2 and the booster 7 to open and close the flow of gas pressurized and discharged from the booster 7. do.

여기서 승압기(7)에서 가압되는 가스는 고로(1)에서 배출되는 배가스를 회수한 회수가스를 사용하는 것이 바람직하다.The gas pressurized by the booster 7 is preferably used to recover the exhaust gas discharged from the blast furnace 1.

아울러 회수가스는 청정설비를 통과하지 않은 반청정가스를 승압기(7)에서 가압 사용하는 것이 더욱 바람직하다.In addition, the recovered gas is more preferably used by pressurizing the semi-clean gas in the booster (7) does not pass through the clean facility.

또한 승압기(7)의 공급 및 배출배관에는 승압기(7)의 고장시 이를 수리하기 위하여 가스차단용밸브(12a)가 설치되는 것이 바람직하다.In addition, it is preferable that the gas shutoff valve 12a is installed in the supply and discharge pipes of the booster 7 in order to repair the failure of the booster 7.

한편 장입물호퍼(2)에는 장입물호퍼(2)의 압력을 감지하는 호퍼압력검출기()와 장입물이 장입되는 분배슈트(3a)에는 고로(1) 내부의 압력을 감지하는 고로압력검출기(1a)가 설치된다.On the other hand, the hopper pressure detector for sensing the pressure of the charge hopper (2) in the charge hopper (2) and the blast furnace pressure detector for detecting the pressure in the blast furnace (1) in the distribution chute (3a) is charged ( 1a) is installed.

한편 고로압력검출기(1a)와 호퍼압력검출기(7c)에서 검출된 압력은 전기 신호로 변환되어 차압검출기(7a)에 전달된다.On the other hand, the pressure detected by the blast furnace pressure detector 1a and the hopper pressure detector 7c is converted into an electrical signal and transmitted to the differential pressure detector 7a.

여기서 장입물호퍼(2)에 장입된 장입물의 무게를 감지하는 중량검출기(7h)가 설치된다.Here, the weight detector 7h for detecting the weight of the charged material in the charge hopper (2) is installed.

또한 중량검출기(7h)에서 검출된 장입물의 중량에 따라 각 노치별로 장입물의 분배량을 결정하는 연산기가 설치된다.In addition, an arithmetic unit for determining the distribution amount of the charges for each notch is installed according to the weight of the charges detected by the weight detector 7h.

한편 이 연산기의 작동에 따라 전자통신제어기와 분배슈트(3a)를 선회 및 경 동시키는 모터를 제어하는 프로세서 컴퓨터가 설치된다.On the other hand, according to the operation of the calculator, a processor computer for controlling the motor for turning and tilting the electronic communication controller and the distribution chute 3a is installed.

또한 제어부가 설치되어 승압기(7)와 호퍼가압제어밸브(7b)를 제어하여 장입물호퍼(2)를 가압시키거나 장입물호퍼(2)의 압력을 배출시킨다.In addition, a control unit is installed to control the booster 7 and the hopper pressure control valve 7b to pressurize the charge hopper 2 or to discharge the pressure of the charge hopper 2.

이하 본 발명에 따른 고로 장입물호퍼의 가압제어장치의 작동은 다음과 같다.Operation of the pressure control device of the blast furnace charge hopper according to the present invention is as follows.

먼저 원료평량기에서 평량된 원료 및 연료 등의 장입물은 벨트콘베어에 의해 노정상부까지 운반되어 장입물호퍼(2)에 수입된다. First, the charged materials, such as raw materials and fuel, weighed in the raw material weighing machine are transported to the top of the road by a belt conveyor and imported into the charged hopper (2).

장입물호퍼(2)에 입조된 장입물은 중량검출기(7h)에서 검출된 신호가 중량하이(High)가 되면 승압기(7)가 기동되고, 호퍼가압제어밸브(7b)가 개방되어 장입물호퍼(2) 내부가 가압되므로 장입물호퍼(2) 내부의 압력이 상승된다.When the load detected by the weight detector 7h becomes high in weight, the booster 7 is started and the hopper pressure control valve 7b is opened to load the charged material into the charged hopper 2. (2) Since the inside is pressurized, the pressure inside the charge hopper 2 is increased.

여기서 통상 고로(1)의 내부압력과 장입물호퍼(2) 내부의 압력차인 호퍼차압은 통상 +0.05kg/cm2로 설정하기 때문에 장입물호퍼(2)의 압력이 상승되어 호퍼차압이 설정치를 벗어나면 호퍼가압차단밸브(7b)가 크로스되어 가압이 중지된다.Here, the hopper differential pressure, which is the difference between the internal pressure of the blast furnace 1 and the internal pressure of the charged hopper 2, is usually set at +0.05 kg / cm 2, so that the pressure of the charged hopper 2 is increased and the hopper differential pressure is out of the set value. Pressurization is stopped because the surface hopper pressure blocking valve 7b is crossed.

또한 차압검출기(7a)에 의해 호퍼차압이 설정치 이내일 경우에는 중량검출기(7h)에서 검출된 신호에 따라 분량에 해당하는 무게의 장입물이 장입될 때까지 분배슈트(3a)를 선회시키게 되며, 중량검출기(7h)에서 감지된 분량의 장입물이 장입 완료가 되면 비로소 다음 지점인 셋팅된 노치(Notch)로 이동하게 된다.In addition, when the hopper differential pressure is within the set value by the differential pressure detector 7a, the dispensing chute 3a is rotated until a charge of a weight corresponding to the quantity is charged according to the signal detected by the weight detector 7h. When the amount of the charge detected by the weight detector 7h is completed, it is moved to the next set point Notch.

물론,장입물호퍼(2)에 기저장된 장입물의 무게는 지속적으로 중량검출기(7h)에서 검지되고 검지된 신호값은 제어부에서 각 노치별로 분배량이 연산된다.Of course, the weight of the charge previously stored in the charge hopper (2) is continuously detected by the weight detector (7h) and the signal value detected is calculated by the control unit for each notch distribution amount.

이와 같이 연산된 각 노치별 분배량에 따라 프로세서 컴퓨터가 전자통신제어 기와 분배슈트를 선회 및 경동시키는 모터를 제어한다.The processor computer controls the electronic communication controller and the motor for turning and tilting the distribution chute according to the distribution amount for each notch calculated as described above.

한편 노정압력이 감소되면 장입물호퍼(2)와 고로(1) 내부의 장입압력이 상승되기 때문에 호퍼가스비상배출밸브(7d)가 개방되어 장입물호퍼(2)의 내부를 배압시킨다.On the other hand, when the top pressure decreases, the charge pressure inside the charge hopper 2 and the blast furnace 1 is increased, so the hopper gas emergency discharge valve 7d is opened to back up the inside of the charge hopper 2.

이 때 장입물호퍼(2)의 가압이 완료되어 장입물호퍼(2) 내부의 장입물을 고로(1)의 내부로 장입중 노정압력이 감소되면, 배압제어밸브(23)를 동작시키고, 동시에 배압차단밸브(21)를 개방시켜 장입물호퍼 내부의 압력을 설정치(통상 +0.05kg/cm2)에 맞도록 제어하면서 서서히 배압을 시킨다.At this time, when pressurization of the charge hopper 2 is completed and charge of the charge inside the charge hopper 2 is reduced into the blast furnace 1, the back pressure control valve 23 is operated, and at the same time, The back pressure shut-off valve 21 is opened to gradually back pressure while controlling the pressure in the charge hopper to match the set value (usually +0.05 kg / cm 2).

한편 장입물호퍼(2) 내부의 장입물이 고로(1) 내부에 장입되면 장입시간이 경과함에 따라 서서히 중량이 감소된다.On the other hand, when the contents of the charging hopper (2) is charged into the blast furnace (1), the weight gradually decreases as the charging time elapses.

따라서 중량검출기(2h)에서 중량로우(Low)신호가 검출되면 가압차단밸브(7b)를 크로스시키고 가스회수차단밸브(13)을 개방하여 장입물호퍼(1) 내부의 압력을 노정압발전기(9) 후단으로 배압시켜 가압용가스를 대기 중으로 배압시키지 않고 회수하여 재사용하게 된다.Therefore, when the low signal is detected in the weight detector 2h, the pressure shutoff valve 7b is crossed and the gas recovery shutoff valve 13 is opened to convert the pressure inside the charge hopper 1 into the stationary pressure generator 9. Back pressure is used to recover and reuse the pressurized gas without back pressure to the atmosphere.

이상에서 설명한 내용과 같이 본 발명에 따른 고로 장입물호퍼의 가압제어장치는 질소 공급없이 장입물을 원활하게 장입할 수 있으므로 질소압력의 저하로 인한 BFG가스의 역류를 방지한다.As described above, the pressure control device of the blast furnace charge hopper according to the present invention can smoothly load the charge without supplying nitrogen, thereby preventing the backflow of the BFG gas due to the decrease in the nitrogen pressure.

또한 장입물을 적기에 투입할 수 있으므로 장입물지연이 발생되지 않아 생산성이 향상된다. In addition, the charge can be added in a timely manner, so no charge delay occurs, productivity is improved.                     

아울러 장입물을 적기에 투입할 수 있으므로 노황관리가 용이하여 용선의 품질이 향상된다.In addition, the charge can be added in a timely manner, easy to manage the yellowing, the quality of the charter.

Claims (3)

고로의 노정에 설치되어 고로에 장입되는 장입물을 일시 저장한 후 장입하도록 설치된 고로 장입물호퍼의 가압제어장치에 있어서,In the pressure control device of the blast furnace charge hopper installed on the top of the blast furnace to temporarily store the charges charged in the blast furnace, and then to charge, 상기 장입물호퍼의 내부 압력을 검출하는 호퍼압력검출기, 상기 고로 내부의 압력을 검출하는 고로압력검출기로 이루어진 검출부;A detection unit comprising a hopper pressure detector for detecting an internal pressure of the charge hopper and a blast furnace pressure detector for detecting a pressure in the blast furnace; 상기 호퍼압력검출기와 상기 고로압력검출기로부터 검출된 압력을 비교하는 차압검지부;A differential pressure detector for comparing the pressure detected from the hopper pressure detector with the blast furnace pressure detector; 상기 장입물호퍼에 유입되는 가스를 가압하는 승압기와 상기 승압기로부터 배출되는 가스의 흐름을 개폐하는 호퍼가압제어밸브를 제어하는 제어부를 포함하는 것을 특징으로 하는 고로 장입물호퍼의 가압 제어장치.And a control unit for controlling a booster for pressurizing the gas flowing into the charge hopper and a hopper pressure control valve for opening and closing the flow of gas discharged from the booster. 제 1 항에 있어서,The method of claim 1, 상기 승압기에서 가압되는 가스는 상기 고로에서 배출된 가스를 회수한 회수가스인 것을 특징으로 하는 고로 장입물호퍼의 가압 제어장치.The gas pressurized by the booster is a pressure control device of the blast furnace charge hopper, characterized in that the recovery gas recovered from the gas discharged from the blast furnace. 제 2 항에 있어서,The method of claim 2, 상기 회수가스는 청정설비를 통과하지 않은 반청정가스인 것을 특징으로 하는 고로 장입물 호퍼의 가압 제어장치.The recovery gas is a pressure control device of the blast furnace charge hopper, characterized in that the semi-clean gas does not pass through the clean facility.
KR1020010081889A 2001-12-20 2001-12-20 Apparatus for press controlling of hopper of blast furnace KR100793578B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020010081889A KR100793578B1 (en) 2001-12-20 2001-12-20 Apparatus for press controlling of hopper of blast furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020010081889A KR100793578B1 (en) 2001-12-20 2001-12-20 Apparatus for press controlling of hopper of blast furnace

Publications (2)

Publication Number Publication Date
KR20030052073A KR20030052073A (en) 2003-06-26
KR100793578B1 true KR100793578B1 (en) 2008-01-14

Family

ID=29576865

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020010081889A KR100793578B1 (en) 2001-12-20 2001-12-20 Apparatus for press controlling of hopper of blast furnace

Country Status (1)

Country Link
KR (1) KR100793578B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101289899B1 (en) 2011-12-23 2013-07-24 주식회사 포스코 Control apparatus for equalizing and increasing a pressure of a blast furnace lower hopper and control method using the same

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102175841B1 (en) * 2018-10-26 2020-11-06 주식회사 포스코 Apparatus and method for controlling pressure of top hopper in blast furnace

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62145120A (en) * 1985-12-19 1987-06-29 Ishikawajima Harima Heavy Ind Co Ltd Method and device for measuring charge quantity of raw material in blast furnace
JPH0892616A (en) * 1994-09-21 1996-04-09 Kawasaki Steel Corp Operation of coke packed bed type smelting reduction furnace
KR19990038977A (en) * 1997-11-08 1999-06-05 이구택 Charge distribution device of blast furnace
KR100398408B1 (en) * 1999-12-28 2003-09-19 주식회사 포스코 Apparatus for controlling pressure in hopper of blast furnace

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62145120A (en) * 1985-12-19 1987-06-29 Ishikawajima Harima Heavy Ind Co Ltd Method and device for measuring charge quantity of raw material in blast furnace
JPH0892616A (en) * 1994-09-21 1996-04-09 Kawasaki Steel Corp Operation of coke packed bed type smelting reduction furnace
KR19990038977A (en) * 1997-11-08 1999-06-05 이구택 Charge distribution device of blast furnace
KR100398408B1 (en) * 1999-12-28 2003-09-19 주식회사 포스코 Apparatus for controlling pressure in hopper of blast furnace

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101289899B1 (en) 2011-12-23 2013-07-24 주식회사 포스코 Control apparatus for equalizing and increasing a pressure of a blast furnace lower hopper and control method using the same

Also Published As

Publication number Publication date
KR20030052073A (en) 2003-06-26

Similar Documents

Publication Publication Date Title
CN103950734A (en) Automatic conveying device and method for raw materials
KR100793578B1 (en) Apparatus for press controlling of hopper of blast furnace
KR100398408B1 (en) Apparatus for controlling pressure in hopper of blast furnace
KR20130052058A (en) Method for parallel injection of feed hoppers in pulverized coal facilities
KR100805052B1 (en) Apparatus for controlling pressure of hopper in blast furnace
JPH0711313A (en) Control method for blowing of pulverized coal
KR100784681B1 (en) An control pressurize using a float nitrogen-gas and method
CN111996318A (en) Reversing device and reversing method for pulverized coal injected into blast furnace
CN206916179U (en) Slag equipment is splashed in a kind of converter automatically
JP3292257B2 (en) Granular material transfer control method
KR100862834B1 (en) Apparatus for controling charging of ore in blast furance
KR101059219B1 (en) Top bunker pressure control
KR100862813B1 (en) Apparatus for injecting dust coal into blast furnace
JP2785093B2 (en) Pressure equalization method in bell blast furnace charging equipment
KR100928985B1 (en) Hopper pressure control device and control method for preventing pulverized coal sticking of pulverized coal transfer hopper
KR100402256B1 (en) How to Prevent Pulverized Coal Stuck in the Feed Tank
CN212669727U (en) Reversing device for pulverized coal injected into blast furnace
KR100979011B1 (en) An apparatus for inserting fine coal into a blast furnace
KR101153589B1 (en) An appratus for controlling feed hopper empty signAn appratus for controlling feed hopper empty signal automatically al automatically
KR100971983B1 (en) Apparatus for controlling the pressure of feed hopper to prevent vent valve from being wearing, and controlling method the same
KR920004983B1 (en) Injecting process for the powder coal into the blast furnace
CN217296381U (en) Pneumatic ash conveying device for conveying coal
KR100605714B1 (en) A method for controlling the feeding time of feed tanks of the 2 way PCI feeding system
KR101279057B1 (en) Recycle device of hot compacted irons comprising fine reduced irons for manufacturing molten irons
JP2001059108A (en) Method for controlling exhaust pressure

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20121231

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20131212

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20150102

Year of fee payment: 8

LAPS Lapse due to unpaid annual fee