KR100789252B1 - Base for project management support and control system and method - Google Patents

Base for project management support and control system and method Download PDF

Info

Publication number
KR100789252B1
KR100789252B1 KR1020070040676A KR20070040676A KR100789252B1 KR 100789252 B1 KR100789252 B1 KR 100789252B1 KR 1020070040676 A KR1020070040676 A KR 1020070040676A KR 20070040676 A KR20070040676 A KR 20070040676A KR 100789252 B1 KR100789252 B1 KR 100789252B1
Authority
KR
South Korea
Prior art keywords
ready
module
information
process management
management
Prior art date
Application number
KR1020070040676A
Other languages
Korean (ko)
Inventor
안재홍
김홍기
Original Assignee
주식회사 유미드시스템
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 유미드시스템 filed Critical 주식회사 유미드시스템
Priority to KR1020070040676A priority Critical patent/KR100789252B1/en
Application granted granted Critical
Publication of KR100789252B1 publication Critical patent/KR100789252B1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/087Inventory or stock management, e.g. order filling, procurement or balancing against orders
    • G06Q10/0875Itemisation or classification of parts, supplies or services, e.g. bill of materials

Abstract

A system and a method for making a basis for project management and processing a claim in connection with the project management are provided to journalize/manage resources such as expenses and schedules by calculating/verifying quantity of each part and adjusting the expenses of each part based on an estimate. A quantity calculating module(100) registers a construction site, inputs data for calculating the quantity, and calculates the quantity classified into each process class by collecting the inputted data, and using location information, the process class, and process information of each item. A detail managing module(200) makes details by reading the quantity, and manages construction details by fixing the expenses based on cost/unit cost after generating a process classification system, activity, and the resources of each activity based on the quantity information. A claim detail calculating module is linked with a process management linking module, and calculates the claim processed by the schedule, the process item of each activity, or each object.

Description

공정관리의 기반을 마련하고, 공정관리와 연계한 기성처리 시스템 및 방법{Base for Project management support and control system and method}Establish a foundation for process management and establish a ready-made treatment system and method in connection with process management {Base for Project management support and control system and method}

도 1은 본 발명의 공정관리의 기반을 마련하고, 공정관리와 연계한 기성처리 방법을 도시한 도면.1 is a view showing a ready-made processing method in connection with the process management, providing the basis of the process management of the present invention.

도 2는 본 발명의 공정관리의 기반을 마련하는 시스템을 도시한 도면.2 is a diagram illustrating a system for laying the foundation for process management of the present invention.

도 3은 기성내역모듈에서 수량산출정보가 연계된 내역관리모듈의 객체를 이용하여 기성내역의 처리와 공정관리를 위한 기성데이터 정보를 공정관리와 연동하여 사용하는 과정의 시스템 및 방법을 도시한 도면.FIG. 3 is a diagram illustrating a system and method of a process of using ready-made data information for process and ready-to-use process in connection with process management by using an object of a history management module linked to quantity calculation information in a ready-made history module. .

도 4는 수량산출정보에 의하여 액티비티를 자동으로 생성하여 마련된 공정관리에서 처리된 기성이나 각 액티비티별 공종항목에 의한 기성을 기성내역모듈과의 연동 과정을 도시한 도면.FIG. 4 is a diagram illustrating a process of linking a ready-made module based on a ready-made item processed by a process management prepared by an activity by automatically generating an activity based on quantity calculation information and a ready-made module according to each activity.

본 발명은 수량산출과정에서 위치정보를 이용하여 공종, 시설, 공간, 부위정보를 포함한 수량산출정보를 자동으로 생성하고, 상기 수량산출정보를 이용하여 건 물과 같은 모습의 객체를 자동으로 구성하여 시설, 공간, 부위별 공사비를 파악할 수 있도록 하여 효과적인 예산의 편성을 유도하고, 상기 수량산출정보를 이용하여 공정관리의 중요요소인 액티비티와 액티비티별 내역에 의한 비용을 자동으로 산출하여 공정관리의 기반을 구성하며, 작성된 공정관리와 시설 공간 부위로 구성된 객체를 이용한 기성관리를 상호 연계하여 투명한 예산집행관리 방법을 제공하는 공정관리의 기반을 마련하고, 공정관리와 연계한 기성처리 시스템 및 방법에 관한 것이다.The present invention automatically generates quantity calculation information including work type, facility, space, and site information by using location information in the quantity calculation process, and automatically constructs an object like a building by using the quantity calculation information. Understand the construction cost by facility, space, and part to induce effective budget formation, and use the quantity calculation information to automatically calculate the cost based on activities and details by activity, which are important elements of process management. It is related to the ready-made processing system and method that establishes the basis of the process management that provides transparent budget execution management method by interconnecting the created process management and the ready-made management using objects composed of the part of facility space. .

일반적으로 수량의 산출은 해당 공사에 대한 수량을 집계하여 공사비 내역서의 수량을 산출하는 흐름을 가지고 있다. 이러한 산출과정에서 발생하는 데이터는 시설 공간 부위에 따른 상세한 수량산출정보는 아니며, 산출된 수량에 대한 과학적이고 합리적인 검증방법이 없어 발주처와 시공사 간에 산출된 공사비 내역수량에 대한 논쟁의 소지가 많은 상황이다.In general, the calculation of quantity has the flow of calculating the quantity of the construction cost statement by counting the quantity of the relevant construction. The data generated in this process is not detailed quantity calculation information for each part of the facility space, and there is a lot of controversy about the amount of construction cost calculated between the client and the contractor because there is no scientific and reasonable verification method for the calculated quantity. .

즉, 종래에는 단순한 공사비 내역수량만으로 작성된 내역을 바탕으로 건설시공관리를 하게 되는데 상기 내역수량은 공사비 각각의 전체수량이기 때문에, 각 위치별 수량을 포함하지 않고 있다. 그러므로 이것을 바탕으로 시공관리를 하기 위하여 공정관리를 위한 공정표를 작성할 때 공정관리의 중요 요소인 액티비티를 일일이 만들어 입력해야하는 불편이 따르며, 상기 액티비티별 비용을 만들기 위해서는 수량산출한 결과를 바탕으로 물량분개라는 과정을 추가적으로 수행해야 하는 번거로움이 따른다.That is, in the related art, the construction and construction management is performed based on the details created by the simple construction cost breakdown quantity, but the breakdown quantity is the total quantity of each construction cost, and thus does not include the quantity for each location. Therefore, it is inconvenient to input and create activities, which are important elements of process management, in order to prepare the process table for process management based on this, and in order to create the costs for each activity, This can be a hassle to perform.

또한, 종래에는 기성을 처리하는 별도의 기술이 존재하는 것이 아니고 현장 의 관리자가 기성을 청구하기 위하여 현장의 각 시설 공간 부위별로 기성량을 체크하여 기성내역에 입력하는 주먹구구식 방식이 사용되어 왔다. 이는 기성량의 투명성 확보에 커다란 문제점을 가지고 있다.In addition, conventionally, there is no separate technology for processing ready-made, and the old-fashioned method of checking the ready-made amount for each facility space part of the site and inputting it to the ready-made details in order to request for ready-made. This has a big problem in securing the transparency of the ready-made amount.

즉, 종래에는 시시각각 변하는 국내외 경제상황과 급변하는 건설기술에 따른 현장의 변화에 효과적으로 예산을 편성하고, 투명한 예산 집행할 수 있는 방안 마련이 어렵고 그에 대한 시스템이 없다는 구조적인 문제점을 가지고 있었다.In other words, the prior art had a structural problem that it is difficult to prepare a way to effectively budget and to implement a transparent budget in accordance with the domestic and international economic situation and the rapidly changing construction technology.

상기와 같은 문제점을 해결하기 위하여 안출된 본 발명은 건설시공시 공정관리에 있어서, 부정확한 수량산출부분을 수량산출정보를 이용하여 시설 공간 부위별로 수량산출에 대한 합리적이고 과학적인 검증을 할 수 있도록 하고, 시설, 공간, 부위별로 투입되는 공사비를 추출하여 예산에 따른 공사비 조정을 할 수 있도록 하며, 이 정보를 이용하여 비용과 일정의 통합관리인 공정관리의 기반인 자원을 분개하여 관리하는 것을 목적으로 한다.The present invention devised to solve the above problems in the process management during construction and construction, so that the rational and scientific verification of the quantity calculation for each facility space part using the quantity calculation information inaccurate quantity calculation part The purpose of this study is to extract the cost of construction by facility, space, and part, and to adjust the cost of construction according to the budget, and to use this information to responsibly manage the resources that are the basis of process management, the integrated management of costs and schedules. do.

또한, 본 발명은 작업분류체계별 액티비티별 비용을 자동으로 추출하여 합리적인 시공관리를 유도하며, 예산집행에 있어서 객체를 이용한 기성처리와 공정관리를 연계 처리함으로써, 기성 처리방법을 보다 효과적으로 운영하며, 투명하고 합리적인 기성처리를 할 수 있도록 하는 것을 목적으로 한다.In addition, the present invention automatically extracts the cost of each activity according to the WBS to induce rational construction management, and in the budget execution by linking the off-the-shelf processing and process management using the object, to operate the off-the-shelf processing method more effectively, The purpose is to enable transparent and reasonable ready-made treatment.

상기 목적을 달성하기 위하여 안출된 본 발명은 (A) 수량을 산출하는 물량산출정보화 단계; (B) 건물의 도형과 공간 부위 객체를 이용하여 수량산출의 정확성을 검증하기 위하여 위치 정보를 이용한 수량산출정보를 생성하는 단계; (C) 상기 수량산출정보를 이용하여 공사비 내역서를 관리하는 단계; (D) 상기 공사비 내역서를 바탕으로 작업분류체계 및 액티비티를 자동으로 추출하는 단계; (E) 상기 추출된 액티비티별 자원을 추출하고 자동으로 공사비를 연산하는 단계; (F) 공정관리의 액티비티를 선후 연관관계를 자동으로 작성하여 공정관리를 수행하는 단계; (G) 액티비티별 기성을 기성내역으로 구성하여 공정관리를 수행하는 단계; (H) 상기 (C)단계를 통해서 시설물의 도형과 객체를 이용하여 기성데이터정보를 획득하는 단계; 및 (I) 상기 공정관리와 상호 연동하여 객체를 이용하여 기성을 관리하는 단계를 포함하는 공정관리의 기반을 마련하고, 공정관리와 연계한 기성처리 방법을 제공한다.The present invention devised to achieve the above object is (A) quantity calculation information calculating step; (B) generating quantity calculation information using location information to verify the accuracy of the quantity calculation using the figure of the building and the spatial part object; (C) managing the construction cost statement using the quantity calculation information; (D) automatically extracting a work breakdown structure and activities on the basis of the construction cost statement; (E) extracting the extracted resources for each activity and automatically calculates the construction cost; (F) performing the process management by automatically creating a relationship after the process management activities; (G) performing process management by constructing ready-made activities for each activity as ready-made details; (H) acquiring ready data information using the figure and the object of the facility through the step (C); And (I) provides a ready-made process method in connection with the process management, providing a basis for process management, including the step of managing the ready-to-use using the object in conjunction with the process management.

또한, 본 발명은 공사 현장을 등록하고 물량을 산출하기 위한 자료를 입력하며, 입력된 산출자료를 집계하여 산출시 입력하는 위치정보와 건설공사작업분류 및 산출된 항목의 공종정보를 이용하여 작업분류 체계화된 수량산출정보를 생성하는 수량산출모듈; 상기 수량산출정보를 전자적으로 읽어 들여 내역을 작성하고, 단가 적용 및 일위대가 적용을 통하여 공사비를 확정하여 공사 내역을 관리하는 내역관리모듈; 및 공정관리연계모듈과 상호 연동하며, 공정관리에서 일정에 의하여 처리된 기성이나 각 엑티비티별 공종항목에 의한 기성을 산출하는 기성내역모듈을 포함하는 공정관리의 기반을 마련하고, 공정관리와 연계한 기성처리 시스템을 제공한 다.In addition, the present invention registers the construction site and inputs the data for calculating the quantity, the work classification by using the location information and the construction work classification and the type information of the calculated items inputted when calculating the input calculation data A quantity calculation module for generating systematic quantity calculation information; A history management module that reads the quantity calculation information electronically to create a detail, and manages the construction details by determining a construction cost by applying a unit price and a first member price; And interworking with the process management linkage module, lay the foundation for process management including a ready-made module that processes the process according to schedule in the process management or the work item by industry item, and establishes the basis for process management Provide a treatment system.

바람직하게는, 상기 내역관리모듈은 공종별 공종항목의 수량과 단가를 입력하여 공사비 내역을 공종별로 구성하고, 2차원 건물 형태의 객체를 공간 부위별로 세분화하여 상기 수량 및 단가 자료와 연계하여 처리할 수 있다.Preferably, the breakdown management module inputs the quantity and unit price of the type of work item for each type of construction to configure the construction cost breakdown by type of work, and subdivided the two-dimensional building type object by space parts to be processed in connection with the quantity and unit price data. have.

또한, 상기 내역관리모듈은 포함된 수량산출정보를 이용하여 공정관리에 필요한 요소인 작업분류체계, 액티비티 그리고 각 액티비티별 자원을 자동으로 생성하여 금액을 자동 연산할 수 있다.In addition, the history management module may automatically calculate the amount of money by automatically generating a work classification system, activities and resources for each activity, which are elements necessary for process management, using the included quantity calculation information.

본 발명과 본 발명의 동작성의 이점 및 본 발명의 실시에 의하여 달성되는 목적을 충분히 이해하기 위해서는 본 발명의 바람직한 실시예를 예시하는 첨부 도면 및 첨부 도면에 기재된 내용을 참조하여야만 한다.In order to fully understand the present invention, the advantages of the operability of the present invention, and the objects achieved by the practice of the present invention, reference should be made to the accompanying drawings which illustrate preferred embodiments of the present invention and the contents described in the accompanying drawings.

이하, 첨부된 도면을 참조하여 본 발명의 바람직한 실시예를 설명함으로써, 본 발명을 상세히 설명한다. 각 도면에 제시된 동일한 참조부호는 동일한 부재를 나타낸다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings. Like reference numerals in the drawings denote like elements.

도 1은 본 발명의 공정관리의 기반을 마련하고, 공정관리와 연계한 기성처리 방법을 도시한 도면이다.1 is a view showing a ready-made processing method in connection with the process management, providing the basis of the process management of the present invention.

도 1을 참조하면, 물량산출과정에서부터 수량을 산출하는 물량산출정보화 단계(S100), 건물의 도형과 공간 부위 객체를 이용하여 수량산출의 정확성을 검증하기 위하여 위치 정보를 이용한 수량산출정보를 생성하는 단계(S110), 상기 수량산 출정보를 이용하여 공사비 내역서를 관리하는 단계(S120), 상기 공사비 내역서를 바탕으로 작업분류체계 및 액티비티를 자동으로 추출하고, 선후 공정관계를 자동으로 연계하는 단계(S130), 상기 추출된 액티비티별 자원을 추출하고 자동으로 비용을 연산하는 단계(S140), 공정관리에서 일정으로 처리한 액티비티별 기성을 기성내역으로 구성하여 공정관리를 수행하는 단계(S150)를 포함한다.Referring to Figure 1, the quantity calculation information step of calculating the quantity from the quantity calculation process (S100), to generate the quantity calculation information using the location information to verify the accuracy of the quantity calculation using the figure of the building and the spatial part object Step (S110), the step of managing the construction cost statement using the quantity calculation information (S120), automatically extracting the work breakdown structure and activities based on the construction cost statement, and automatically linking the post-process process relationship ( S130), extracting the extracted resources for each activity and automatically calculating the cost (S140), and the process of the process by configuring the ready-made activity for each activity processed as a schedule in the process management (S150) (S150) do.

또한, 상기 공사비 내역서 관리 단계(S120)를 통해서 시설물의 도형과 객체를 이용하여 수량산출정보를 획득하는 단계(S160), 객체를 이용하여 기성을 관리하는 단계(S170)를 포함하며, 상기 S150 단계와 S170 단계 사이는 객체를 이용한 기성처리와 공정관리의 정보를 교환할 수 있어 EVM을 구현할 수 있으며, 공정관리에서 일정을 이용하여 기성 처리한 것을 기성내역시스템의 객체로 기성현황을 파악할 수 있다.In addition, obtaining the quantity calculation information using the figures and objects of the facility through the construction cost history management step (S120) (S160), and managing the ready-to-use by using the object (S170), the step S150 Between step S170 and EVM can be implemented by exchanging the information of the process and process management using the object, the process of the process using the schedule in the process management can grasp the current status as the object of the ready-made history system.

본 발명은 시공사가 건설현장의 시공관리를 위하여, 비용과 일정의 통합관리인 공정관리를 수작업과정 없이 자동으로 처리할 수 있도록 처리하는 시스템으로서, 적산과정에서 위치정보를 이용하여 자동으로 작업분류체계에 의하여 세분화한 집계를 생성한다. 이를 수량산출정보라 한다. 이 수량산출정보를 바탕으로 내역 시스템으로 연계하여 내역을 자동으로 작성한다.The present invention is a system that allows the contractor to automatically process the process management, which is an integrated manager of cost and schedule, without the manual process for the construction management of the construction site, using the position information in the integration process automatically to the work classification system To generate granular aggregates. This is called quantity calculation information. Based on this quantity calculation information, the details are automatically created by linking to the details system.

내역서에서는 적산과정에서 입력한 현장개요부분을 해석하여 건물모양을 자동으로 생성하며, 건물을 구성하는 시설, 공간, 부위를 객체로 구성하여, 그림으로 표현하고, 시설 공간 부위로 구분된 각 객체에 해당하는 수량과 비용을 자동으로 연계처리한다.In the statement of interpretation, the site outline entered during the integration process is automatically generated to create a building shape, and the facilities, spaces, and parts that make up the building are represented by objects, represented by a picture, and applied to each object divided into facility space parts. Automatically link the corresponding quantity and cost.

상기 수량산출정보를 포함하는 내역서에서, 수량산출정보를 이용하여 공정관리에 필요한 작업분류체계와 액티비티를 자동으로 생성하고, 각 액티비티별로 자원 및 비용을 자동으로 연산 및 분개 처리함으로써 공정관리의 기반을 제공한다.In the statement including the quantity calculation information, the work classification system and activities required for the process management are automatically generated using the quantity calculation information, and the resources and costs are automatically calculated and processed for each activity to provide the basis for the process management. to provide.

내역을 바탕으로 하는 기성내역은 자동으로 구성된 객체를 이용하여 기성을 처리한다. 이를 통하여 각 시설별 공간별 부위별로 기성을 처리함으로써 기성 처리에 정확성을 기할 수 있어 예산집행의 투명성을 확보할 수 있다.Ready-made history based on the history is handled by using automatically configured objects. Through this process, it is possible to secure the transparency of budget execution by processing the ready-made by the parts of the space by each facility, thereby ensuring the accuracy of the ready-made processing.

또 하나의 방법은 공정관리에서 일정별 또는 공사 진척에 따른 기성율을 각 액티비티에 반영한 기성율을 기성 내역에서 읽어들여 기성내역을 만들며 어느 시설 공간 부위에서 기성이 발생하였는지 파악할 수 있도록 할 수 있다.Another method is to read the ready-made rate, which reflects the ready-made rate according to schedule or construction progress in each activity, to make ready-made breakdowns and to identify which area of the facility space has occurred.

도 2는 본 발명의 공정관리의 기반을 마련하는 시스템을 도시한 도면이다.2 is a diagram illustrating a system for providing a basis for process management of the present invention.

도 2를 참조하면, 본 발명의 공정관리의 기반을 마련하고, 공정관리와 연계한 기성처리 시스템은 수량산출정보를 생성하는 수량산출모듈(100), 상기 생성된 수량산출정보를 이용하여 공사 내역을 관리하는 내역관리모듈(200)을 포함한다.Referring to Figure 2, providing a basis for the process management of the present invention, the ready-made processing system associated with the process management is a quantity calculation module 100 for generating quantity calculation information, the construction details by using the generated quantity calculation information It includes a history management module 200 to manage.

보다 상세히, 상기 수량산출모듈(100)에서는 공사 현장을 등록하고 물량을 산출하기 위한 자료를 입력한다. 물량을 산출하여 집계를 하기 위한 산출자료의 입력은 산출하고자 하는 대상물의 성격에 따라 산출하는 형태가 다르다. 이는 산출자체와 작업관리의 성격이 다르기 때문이다. 작업 관리는 공정과는 관계가 있으나 물량산출은 공정과는 관계가 없고 단지 공사비를 산출하기 위하여 공종별로 산출하기 때문이다.In more detail, the quantity calculation module 100 registers the construction site and inputs the data for calculating the quantity. The input of the calculation data for calculating the quantity by counting differs depending on the characteristics of the object to be calculated. This is because the production itself and the nature of work management are different. This is because work management is related to the process but quantity calculation is not related to the process and is calculated by the type of work only to calculate the construction cost.

예를 들면, 어느 한부분에 방수, 미장, 수장공사에 해당하는 공종항목이 있는 경우에, 산출은 그 부위의 면적을 이용하여 공종항목에 대한 물량만을 산출한다. 그러나 공정은 그것이 어느 시설물의 어느 공간의 어느 부위의 공종항목이며, 방수공종이 끝나고 미장을 하며 미장공종이 끝나야 수장공종을 시공한다는 등의 순서가 있는 작업관리의 개념이다.For example, in a case where there is a work item corresponding to waterproofing, plastering, or repair work, the calculation calculates only the quantity for the work item using the area of the part. However, the process is a concept of work management, in which it is a work item in a certain part of a space of a facility, the construction work is performed after the waterproof work is finished, and the construction work is completed only after the finishing work is completed.

본 발명은 수량을 산출하는 과정은 그대로 유지하면서, 산출시 입력하는 위치정보와 건설공사작업분류 그리고 산출된 항목의 공종정보를 이용하여 수량산출정보를 자동으로 생성한다.The present invention automatically generates the quantity calculation information by using the position information, the construction work classification, and the type information of the calculated items input while calculating, while maintaining the process of calculating the quantity.

즉, 입력된 자료를 이용하여 계산 처리시 집계하는 과정에서(산출을 위하여 입력한 정보를 이용하여) 작업분류체계화된 수량산출정보를 생성한다.That is, in the process of counting (using the information inputted for calculation) using the input data, the WBS structured quantity calculation information is generated.

상기 내역관리모듈(200)에서는 공사현장을 등록하고 상기 수량산출모듈(100)에서 자동으로 생성한 수량산출정보를 전자적으로 읽어들여 내역을 작성하고, 단가 적용 및 일위대가 적용을 통하여 공사비를 확정한다.The breakdown management module 200 registers a construction site and reads the quantity calculation information generated automatically by the quantity calculation module 100 electronically to create a breakdown, and establishes a construction cost by applying a unit price and a first-class unit. do.

내역관리모듈(200)의 성격은 공종별 공종항목의 수량과 단가를 입력하여 공사비 내역을 공종별로 구성(작성)하는 것이다.The nature of the breakdown management module 200 is to configure (create) the construction cost breakdown by type by inputting the quantity and unit price of the work item for each work type.

본 발명은 단지 공종항목의 수량만을 만들어 주는 것이 아니고 각 공종항목별로 작업분류체계화된 정보를 자동으로 연계하고, 상기 연계된 정보는 다시 2차원 건물 형태의 객체에 공간 부위별로 세분화되어 정보 자료를 연계한다. 즉, 상기 내역관리모듈(200)은 수량산출정보를 활용하여 객체를 생성하고, 작업분류체계 및 액티비티를 생성한다. 보다 상세히, 객체 생성을 위하여 2차원의 시설 공간 부위를 생성하고, 수량 및 단가를 곱해 상기 시설 공간 부위별 금액을 확인할 수 있다. 또한, 작업분류체계 및 액티비티를 생성하기 위하여 산출모듈별, 시설별, 공간별, 부위정보를 획득하고, 액티비티를 생성하고, 선후 공정관계를 자동으로 연계하는 단계 및 자원 생성 단계를 거쳐 비용을 자동으로 연산할 수 있다.The present invention does not only create the quantity of the work item, but automatically links the work breakdown structured information for each work item, and the linked information is further subdivided into the two-dimensional building type object by the spatial part to link the information data. do. That is, the history management module 200 creates an object using quantity calculation information, and generates a work breakdown structure and activities. In more detail, a two-dimensional facility space part may be generated to generate an object, and the amount of each facility space part may be confirmed by multiplying the quantity and unit price. In addition, in order to create a work breakdown structure and activities, the cost is automatically obtained through the steps of acquiring calculation module, facility, space, and site information, generating activities, and automatically linking post-process relationships with resources. Can be calculated.

상기 연계된 정보를 이용하면 어느 위치에 무엇을 얼마나 시공(작업)하여야 하는지 보다 쉽게 파악할 수 있다.By using the linked information, it is easier to know what and how much to construct (work) at which position.

수량산출정보의 구성은 시설물인 동, 공간을 표현하는 층, 그리고 산출 및 집계부위로 1차 기본적인 분류를 하고, 시설물의 용도에 따라 2차적인 분류를 한다. 예를 들어, 아파트의 경우 평형, 세대종류, 그리고 호실로 구분하고, 일반건물인 경우 이러한 분류를 하지 않는다. 3차 분류는 작업관리를 위한 분류로 공간인 방, 그리고 부위로 구분한다.The quantity calculation information is composed of the basic basic classification of the facility, the space representing the space, and the calculation and aggregation areas, and the secondary classification according to the purpose of the facility. For example, apartments are divided into equilibrium, household type, and room, and in general buildings, these classifications are not. The tertiary classification is a classification for work management, which is divided into a room and a space.

골조공사인 경우 일반 건물인 경우는 각 층별로 하위분류에 부재별로 분류하여 산출하고 수량산출정보를 구성한다. 아파트인 경우는 먼저 2 단계 분류인 평형, 세대로 구분 후 부재별로 분류하여 산출하고 수량산출정보를 구성한다.In the case of framing construction, in case of general building, it is calculated by classifying each member in subdivision by each floor and compiling quantity calculation information. In the case of apartments, it is divided into equilibrium and household, which are two stages, and then classified and calculated by members.

예를 들어, 창호공사인 경우 일반 건물인 경우는 각 창호별로 하위분류에 창호 산출과정에서 발생하는 항목을 창호철물 유리 도장 유리코킹 및 창호코킹과 사춤몰탈로 구분하여 산출하고, 수량산출정보를 구성한다. 아파트인 경우는 먼저 2단계 분류인 평형, 세대, 호실을 구분한 후 각 창호별로 하위분류에 창호 산출과정에서 발생하는 항목을 창호철물 유리 도장 유리코킹 및 창호코킹과 사춤몰탈로 구분하여 산출하고 수량산출정보를 구성한다. For example, in the case of windows and doors construction, in case of general building, the items generated in the process of calculating windows are divided into windows and doors, glass coating, window and caulking, and private mortar. do. In case of apartments, first, two levels of equilibrium, household, and room are classified, and the items generated in the process of calculating the doors are divided into windows and doors, glass coating, window caulking, and private mortar. Construct output information.

또한, 내부공사인 경우 일반 건물인 경우는 각 창호별로 하위분류에 내부 산출과정에서 발생하는 항목을 바닥, 천정, 몰딩, 커텐박스, 벽, 걸레받이, 조적으로 구분하여 산출하고 수량산출정보를 구성한다. 아파트인 경우는 먼저 2단계 분류인 평형, 세대, 호실을 구분한 후 각 각 방별로 하위분류에 내부 산출과정에서 발생하는 항목을 바닥, 천정, 몰딩, 커텐박스, 벽, 걸레받이, 조적으로 구분하여 산출하고 수량산출정보를 구성한다.In case of internal construction, in case of general building, the items generated in the internal calculation process are classified into floors, ceilings, moldings, curtain boxes, walls, mopboards, and masonry in sub-categories for each window and constitute quantity calculation information. do. In case of apartment, first, classify the 2nd level equilibrium, household, and room, and then classify items generated in the internal calculation process into the floor, ceiling, molding, curtain box, wall, cloth tray, and masonry. And calculate the quantity calculation information.

또한, 계단공사인 경우 시설물 용도의 구분이 없으므로 2단계의 분류는 계단실명으로 하고, 각 계단실별 하위분류를 계단바닥, 계단벽, 계단천정으로 구분하고 각 산출과정에서 발생하는 항목에 대하여 세분화된 분류를 이용하여 산출하고 수량산출정보를 구성한다.In the case of stair construction, there is no classification of facility use, so the classification of step 2 is called stair room name, and the sub-classification for each stair room is divided into stair floor, stair wall, and stair ceiling. Calculate using classification and organize quantity calculation information.

그 외 외부 부대 가설 토공사 등의 경우 시설물 용도의 구분이 없으므로 2단계의 분류는 그 산출대로 분류하고, 하위분류를 사용자가 입력한 산출모듈명 단위로 구분하고 각 산출과정에서 발생하는 항목에 대하여 세분화된 분류를 이용하여 산출하고 수량산출정보를 구성한다.In the case of other external temporary works, there is no classification of facility use, so the classification of the second stage is classified according to the calculation, subdivision by the unit of calculation module name input by the user, and subdivided into items generated in each calculation process. The calculated classification is used to construct the quantity calculation information.

상기 객체는 수량산출모듈의 공사 등록개요를 이용하여 건물의 형태와 같은 형상을 2차원으로 표현하고 각각의 공간과 부위를 객체화하여 수량산출정보와 연계처리함으로써 각 공간 부위 등 객체별로 단가와 수량으로 표현된 공종항목별 금액과 합계금액을 파악할 수 있다. 상기 객체는 건물의 어느 부위에 시공되는 각각의 수량과 그 공사비용을 파악할 수 있어 공사수량 및 공사금액에 정확성을 기할 수 있다.The object expresses the shape, such as the shape of the building, in two dimensions by using the construction registration overview of the quantity calculation module, and objectizes each space and part to associate with the quantity calculation information to generate unit price and quantity for each object such as each space part. The amount and total amount of each expressed industrial item can be identified. The object can grasp each quantity to be constructed in any part of the building and its construction cost can be accurate to the construction quantity and construction cost.

상기 수량산출정보를 이용하여 객체를 자동으로 구성하며, 이는 상기 수량산출모듈(100)에서 입력한 건물의 층의 정보를 이용하여 건물을 도형화한 것이며, 공간객체는 층으로 구성하고, 각층을 바닥, 벽, 천정, 조적, 창호로 구분하여 부위로 세분화한 뒤 부위객체에 정보를 연계하여 부위객체별로 공종별 항목을 참조할 수 있도록 하여 수량과 단가로 객체별 공사비를 파악할 수 있다. 아파트의 경우에는 각 층의 평형별, 세대별, 호실별 부위객체를 구성하여 정보를 연계처리한다.The object is automatically constructed using the quantity calculation information, which is a graphic representation of the building using the information of the floor of the building input by the quantity calculation module 100, and the spatial object is composed of floors, After subdividing into floors, walls, ceilings, masonry, and windows, it is possible to identify the construction cost of each object by quantity and unit price by linking the information to the site objects so that the items can be referred to by sector. In the case of apartments, information is linked by constructing sub-objects of each floor by balance, generation, and room.

상기 내역관리모듈(200)에 포함된 수량산출정보를 이용하여 공정관리에 필요한 요소인 작업분류체계, 액티비티 그리고 각 액티비티별 자원을 자동으로 생성하여 금액을 자동 연산한다.Using the quantity calculation information included in the history management module 200, the work classification system, the activities and the resources for each activity are automatically generated by automatically calculating the necessary amount for the process management.

건설공사관리의 가장 핵심적인 공정관리는 비용과 일정의 통합관리로써 비용부분에 대한 처리를 물량산출과정에서부터 물량산출정보화를 하여 수량산출의 정확성을 검증할 수 있도록 한다. 이 자동생성된 물량산출정보를 기반으로 공정관리의 액티비티별 비용을 자동으로 생성하며, 투입되는 자원을 일위대가에 의하여 자동으로 생성한다.The most important process control of construction management is integrated management of cost and schedule so that the process of cost part can be processed from quantity calculation process to quantity calculation information to verify the accuracy of quantity calculation. Based on the automatically generated quantity calculation information, the cost of each process management activity is automatically generated, and the input resources are automatically generated by the first cost.

각 액티비티는 수량산출정보를 구성할 때의 3단계를 이용하여 작업분류체계와 공종을 이용하여 액티비티명을 구성하고 각 부위의 공종항목을 연계하여 액티비티별 공종과 그 공종의 수량 단가정보를 이용하여 금액을 자동으로 추출할 수 있다. 액티비티는 산출된 위치정보인 공간 부위 정보와 공종항목의 공종정보를 이용하여 액티비티명을 구성한다.Each activity is composed of activity classification system and work type using three steps when composing quantity calculation information, and uses the work type system and work type to link the work items of each part to use the work type and quantity unit price information of the work type. The amount can be extracted automatically. The activity constructs the activity name by using the spatial location information, which is the calculated positional information, and the type information of the type.

공정관리에서 액티비티의 구성은 관리자의 관리관점에 따라 작성이 됨으로 액티비티를 가장 작은 단위로 구성하며, 이를 병합하여 액티비티를 구성할 수도 있다.In process management, the activities are organized according to the manager's management viewpoint, so the activities are organized in the smallest units, and the activities can be organized by merging them.

즉 구조체에 대한 작업관리는 형틀을 설치하고, 철근을 조립한 뒤 콘크리트를 타설을 하는 것으로 구성하였으나 이를 하나의 골조공사로 병합할 수 있도록 하여 하나의 액티비티로 작성할 수 있고, 그에 속하는 공종항목을 모두 모아 한 액티비티의 금액을 추출할 수도 있다.In other words, the work management for the structure consists of installing the mold, assembling the reinforcing bars, and then placing the concrete, but it can be merged into one framework so that it can be created as one activity and all the work items belong to it. You can also extract the amount of one activity.

도 3은 기성내역모듈에서 수량산출정보가 연계된 내역관리모듈의 객체를 이용하여 기성내역의 처리와 공정관리를 위한 기성데이터 정보를 공정관리와 연동하여 사용하는 과정의 시스템 및 방법을 도시한 도면이다.FIG. 3 is a diagram illustrating a system and method of a process of using ready-made data information for process and ready-to-use process in connection with process management by using an object of a history management module linked to quantity calculation information in a ready-made history module. to be.

도 3을 참조하면, 기성 처리에 있어서 객체를 사용함으로써 기성량에 대한 근거가 자동으로 작성될 수 있도록 하여, 기성의 투명성을 확보하고 그로 인하여 예산집행의 투명성을 제고한다.Referring to Fig. 3, by using the object in the ready processing, the basis for the ready amount can be automatically generated, thereby ensuring the transparency of the ready and thereby improving the transparency of budget execution.

객체를 이용한 기성의 처리는 어느 층의 어느 부위에 대한 공종별 기성을 처리할 수 있도록 한다. 기성처리방법은 층별, 바닥, 벽 천정, 조적 창호별, 공종별 항목에 대한 기성율로 기성을 처리할 수 있을 뿐만 아니라, 항목별 기성량을 입력하여 기성을 처리할 수도 있다.The ready-made treatment using objects makes it possible to process the ready-made ready-made for any part of a layer. The ready-made treatment method can not only handle the ready-made by the rate of ready-made for the items of each floor, floor, wall ceiling, masonry windows, types of work, but also can be processed by inputting the amount of ready-made by item.

공종별로 기성 수량을 입력하는 경우 동일한 공간인 같은 방의 같은 부위에 같은 수량을 갖는 객체에 대하여 기성을 처리하게 됨으로써 종래의 기성 처리방법 보다 신속하고 정확한 기성처리가 가능하다. 상기 처리된 기성량은 공종별로 연산 처리되어 기성내역을 자동으로 작성할 수 있게 되며, 각 공종항목별로 기성근거를 유지할 수 있도록 하여, 기성의 투명성을 확보할 수 있고 예산 집행의 신뢰성을 높일 수 있다.In case of inputting the ready-made quantity for each type of object, it is possible to process the ready-made for the object having the same quantity in the same part of the same room which is the same space. The ready-made amount is processed for each type of work can be automatically generated ready-made history, it is possible to maintain the established basis for each type of item, it is possible to secure the transparency of the ready and increase the reliability of budget execution.

각 층별 바닥, 벽, 천정, 조적, 창호 외의 부위로 표현할 수 없는 것은 객체 구성시 별도로 부대공사 등을 처리할 수 있도록 객체별 정보를 연계하여 처리할 수 있다. 즉 객체를 이용하여 처리한 기성을 바탕으로 신속하고 정확하며 투명한 예산집행을 할 수 있으며, 기성내역을 자동으로 작성할 수 있다.What can not be expressed in parts other than floors, walls, ceilings, masonry, windows, etc. for each floor can be processed by linking object-specific information so that additional work can be handled separately when constructing objects. In other words, it is possible to execute the budget quickly, accurately and transparently based on the ready-made objects, and to automatically prepare the ready-made details.

그리고 동시에 상기 기성내역모듈(300)에서 액티비티로 연계된 정보를 이용하여 공정관리연계모듈(400)에서의 작업분류체계(WBS)를 거쳐 공정관리(500)에서 액티비티별 기성이 자동으로 처리되어 이미 수량산출정보에 의하여 작성된 공정관리에서 계획 공정대비 기성에 의한 실제 공사진척을 손쉽게 파악할 수 있다.At the same time, the activity by activity is automatically processed in the process management 500 through the WBS in the process management linkage module 400 by using the information linked to the activity in the ready-made history module 300. In the process control created by the quantity calculation information, it is possible to easily grasp the actual public photograph by the ready-made process.

도 4는 수량산출정보에 의하여 액티비티를 자동으로 생성하여 마련된 공정관리에서 처리된 기성이나 각 액티비티별 공종항목에 의한 기성을 기성내역모듈과의 연동 과정을 도시한 도면이다.4 is a diagram illustrating an interlocking process with a ready-made module processed by a process management prepared by automatically generating an activity based on quantity calculation information or a ready-made by an industrial item for each activity.

상기 공정관리(500)에서의 액티비티별로 작성된 기성 데이터는 공정관리연계모듈(400)에서의 작업분류체계(WBS)를 거쳐 기성내역모듈(300)에서 액티비티별 기성을 적용받는다. 이후 객체에 의한 기성 처리가 가능해지고, 기성 내역을 통해 투명한 기성근거를 얻을 수 있다.The ready-made data for each activity in the process management 500 is subjected to the activity for each activity in the ready-made history module 300 via the WBS in the process management linkage module 400. After that, the ready-made processing by the object becomes possible, and the ready-made details can obtain a transparent ready-made basis.

즉, 액티비티별로 작성된 기성 데이터는 기성내역관리에서 읽어들여 작성된 객체의 공간 부위별 정보와 연계되어 객체에 의한 기성현황을 파악할 수 있도록 표현된다. 또한, 상기 데이터를 가시 공종별 기성내역으로 연계처리하여 각 공종항목별 그에 대한 근거를 제시할 수 있다.That is, the ready-made data prepared for each activity is expressed in order to grasp the ready-made status by the object in association with the information of the spatial part of the object which is read in the ready-made history management. In addition, the data may be linked to the ready-made history for each visible type to provide a basis for each item.

본 발명은 도면에 도시된 일 실시예를 참고로 설명되었으나, 이는 예시적인 것에 불과하며, 본 기술 분야의 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 타 실시예가 가능하다는 점을 이해할 것이다. 따라서, 본 발명의 진정한 기술적 보호 범위는 첨부된 등록청구범위의 기술적 사상에 의해 정해져야 할 것이다.Although the present invention has been described with reference to one embodiment shown in the drawings, this is merely exemplary, and those skilled in the art will understand that various modifications and equivalent other embodiments are possible therefrom. . Therefore, the true technical protection scope of the present invention will be defined by the technical spirit of the appended claims.

본 발명은 건설시공시 공정관리에 있어서, 부정확한 수량산출부분을 수량산출정보를 이용하여 시설 공간 부위별로 수량산출에 대한 합리적이고 과학적인 검증을 할 수 있도록 하고, 시설, 공간, 부위별로 투입되는 공사비를 추출하여 예산에 따른 공사비 조정을 할 수 있도록 하며, 이 정보를 이용하여 비용과 일정의 통합관리인 공정관리의 기반인 자원을 분개하여 관리할 수 있다.The present invention allows the rational and scientific verification of the quantity calculation for each part of the facility space by using the quantity calculation information in the inaccurate quantity calculation in the process of construction and construction, and inputted by facility, space, and part The cost of the project can be extracted and adjusted according to the budget, and this information can be used to responsibly manage the resources that are the basis of process management, which is the integrated management of costs and schedules.

또한, 본 발명은 작업분류체계별 액티비티별 비용을 자동으로 추출하여 합리적인 시공관리를 유도하며, 예산집행에 있어서 객체를 이용한 기성처리와 공정관리를 연계 처리함으로써, 기성 처리방법을 보다 효과적으로 운영하며, 투명하고 합리적인 기성처리를 할 수 있도록 하는 것을 목적으로 한다.In addition, the present invention automatically extracts the cost of each activity according to the WBS to induce rational construction management, and in the budget execution by linking the off-the-shelf processing and process management using the object, to operate the off-the-shelf processing method more effectively, The purpose is to enable transparent and reasonable ready-made treatment.

Claims (4)

(A) 수량산출 모듈에서 건물의 공간 부위별 객체마다 위치 정보에 따른 산출 공종 항목에 대한 수량산출정보를 생성하는 단계;(A) generating the quantity calculation information for the calculated work item according to the location information for each object of each space part of the building in the quantity calculation module; (B) 내역관리 모듈에서 상기 산출된 수량산출정보를 이용하여 상기 객체에 해당하는 수량과 비용을 관리하는 공사비 정보를 생성하는 단계;(B) generating construction cost information for managing the quantity and cost corresponding to the object by using the calculated quantity calculation information in the history management module; (C) 내역관리 모듈에서 상기 공사비 정보를 바탕으로 작업분류체계 및 액티비티를 생성하는 단계;(C) generating a work breakdown structure and activities based on the construction cost information in the history management module; (D) 공정관리 모듈에서 상기 생성된 액티비티별 요구되는 자원을 추출하고, 공사비를 연산하는 단계;(D) extracting the required resources for each of the generated activities in the process management module, and calculating the construction cost; (E) 공정관리 모듈에서 상기 (C) 단계를 통하여 생성된 액티비티와 상기 (D) 단계를 통하여 추출된 액티비티별 요구되는 자원의 비용을 연계하여 공정관리와 상호 연동하는 단계;(E) interoperating with the process management by linking the costs generated by the activity (C) and the resources required for each activity extracted through the step (D) in the process management module; (F) 기성내역 모듈에서 상기 내역관리 모듈을 통하여 생성된 공사비 내역서를 기초로 객체 마다의 수량산출정보를 획득하는 단계;(F) acquiring quantity calculation information for each object on the basis of the construction cost statement generated by the details management module in the ready history module; (G) 기성내역 모듈에서 상기 (F) 단계를 통하여 산출된 상기 객체 마다의 수량산출정보를 이용하여 객체 마다의 기성내역을 획득하는 단계; 및(G) acquiring the ready history for each object by using the quantity calculation information for each object calculated through the step (F) in the ready history module; And (H) 공정관리 연계 모듈에서, 상기 공정관리 모듈과, 기성내역 모듈을 상호 연동시켜 객체를 이용하여 액티비티별 기성을 관리하는 단계를 포함하는 공정관리의 기반을 마련하고, 공정관리와 연계한 기성처리 방법.(H) In the process management linkage module, the process management module and the ready-made history module interoperate with each other to establish a basis for process management, including the step of managing the activity for each activity using the object, and the ready-made process linked with the process management Way. 공사 현장을 등록하고 물량을 산출하기 위한 자료를 입력하며, 입력된 산출자료를 집계하여 산출시 입력하는 위치정보와 건설공사작업분류 및 산출된 항목의 공종정보를 이용하여 작업분류 체계화된 수량산출정보를 생성하는 수량산출모듈;Register the construction site and input the data to calculate the quantity, and calculate the work classification system by using the location information, the construction work classification and the work information of the calculated items Quantity calculation module for generating a; 상기 수량산출정보를 전자적으로 읽어 들여 내역을 작성하고, 상기 수량산출정보를 이용하여 공정관리에 필요한 요소인 작업분류체계, 액티비티 그리고 각 액티비티별 자원을 생성하여 단가 적용 및 일위대가 적용을 통하여 공사비를 확정하여 공사 내역을 관리하는 내역관리모듈; 및Read the quantity calculation information electronically to create a breakdown, and use the quantity calculation information to generate work breakdown structure, activities and resources for each activity, which are necessary elements for process management, and apply the cost by applying unit price and first cost Confirmation management module for managing the construction details to determine; And 공정관리연계모듈과 상호 연동하며, 공정관리에서 일정에 의하여 처리된 기성이나 각 엑티비티별 공종항목에 의한 기성 또는 각 객체별 기성을 산출하는 기성내역모듈을 포함하는 공정관리의 기반을 마련하고, 공정관리와 연계한 기성처리 시스템.Interoperate with the process management linkage module, and provide the basis for process management, which includes the ready-made module processed by schedule in the process management, the ready-made by the industry item for each activity, or the ready-made module for each object. Ready-made treatment system linked with management. 제 2항에 있어서,The method of claim 2, 상기 내역관리모듈은 공종별 공종항목의 수량과 단가를 입력하여 공사비 내역을 공종별로 구성하고, 2차원 건물 형태의 객체를 공간 부위별로 세분화하여 상기 수량 및 단가 자료와 연계하여 처리하는 공정관리의 기반을 마련하고, 공정관리와 연계한 기성처리 시스템.The breakdown management module inputs the quantity and unit price of the work item by construction type to construct the construction cost breakdown by type of construction, and subdivids the object of the 2D building type by the spatial part and processes the linkage with the quantity and unit price data. Ready-made processing system in connection with process management. 삭제delete
KR1020070040676A 2007-04-26 2007-04-26 Base for project management support and control system and method KR100789252B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020070040676A KR100789252B1 (en) 2007-04-26 2007-04-26 Base for project management support and control system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020070040676A KR100789252B1 (en) 2007-04-26 2007-04-26 Base for project management support and control system and method

Publications (1)

Publication Number Publication Date
KR100789252B1 true KR100789252B1 (en) 2008-01-02

Family

ID=39216001

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020070040676A KR100789252B1 (en) 2007-04-26 2007-04-26 Base for project management support and control system and method

Country Status (1)

Country Link
KR (1) KR100789252B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101081880B1 (en) 2010-02-12 2011-11-09 이기상 Construction Cost Information Processing System Including Small Space or Element Information and the Method on it

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020008644A (en) * 2000-07-24 2002-01-31 홍명희 The construction management system and the service method using the system
KR20070004162A (en) * 2005-07-04 2007-01-09 심영호 Project management information system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020008644A (en) * 2000-07-24 2002-01-31 홍명희 The construction management system and the service method using the system
KR20070004162A (en) * 2005-07-04 2007-01-09 심영호 Project management information system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101081880B1 (en) 2010-02-12 2011-11-09 이기상 Construction Cost Information Processing System Including Small Space or Element Information and the Method on it

Similar Documents

Publication Publication Date Title
Monteiro et al. A survey on modeling guidelines for quantity takeoff-oriented BIM-based design
US10891405B2 (en) Method, computer program product and apparatus for providing a building options configurator
Gourlis et al. Building Information Modelling for analysis of energy efficient industrial buildings–A case study
Leite et al. Analysis of modeling effort and impact of different levels of detail in building information models
Nath et al. Productivity improvement of precast shop drawings generation through BIM-based process re-engineering
Ballard et al. The St. Olaf College Fieldhouse Project: a case study in designing to target cost
Kim et al. A discrepancy analysis of BIM-based quantity take-off for building interior components
Elnabawi Building information modeling-based building energy modeling: investigation of interoperability and simulation results
Khosakitchalert et al. Automated modification of compound elements for accurate BIM-based quantity takeoff
KR101592762B1 (en) Automatic quantity calculation method for calculating rough estimate using BIM in construction design stage and information classification system
Jiang Developments in cost estimating and scheduling in BIM technology
Kumar Interoperability between building information models (BIM) and energy analysis programs
Cha et al. A case study of time/cost analysis for aged-housing renovation using a pre-made BIM database structure
Prada-Hernández et al. Interoperability of building energy modeling (BEM) with building information modeling (BIM)
Huhnt et al. Data management for animation of construction processes
Whang et al. Building information modeling (BIM) for project value: Quantity take-off of building frame approach
JP6429380B2 (en) Building planning and design system and method
Mohammadiziazi et al. Developing a framework for urban building life cycle energy map with a focus on rapid visual inspection and image processing
KR100789252B1 (en) Base for project management support and control system and method
Bhuskade Building information modeling (BIM)
Grzyl et al. Building information modeling in small and middle sized buildings–case study
Collins Incorporating BIM into architectural precast concrete fabrication
Berdeja Conflict analyses in a BIM based design
Ho Song et al. Empirical determination of the smallest batch sizes for daily planning
KR101976514B1 (en) Providing method of building cost estimate

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
G170 Publication of correction
FPAY Annual fee payment

Payment date: 20121128

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20131223

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20141219

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20161227

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20180621

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20181221

Year of fee payment: 12

R401 Registration of restoration