KR100736383B1 - Reinforcing bar and slab construction method - Google Patents

Reinforcing bar and slab construction method Download PDF

Info

Publication number
KR100736383B1
KR100736383B1 KR1020060003529A KR20060003529A KR100736383B1 KR 100736383 B1 KR100736383 B1 KR 100736383B1 KR 1020060003529 A KR1020060003529 A KR 1020060003529A KR 20060003529 A KR20060003529 A KR 20060003529A KR 100736383 B1 KR100736383 B1 KR 100736383B1
Authority
KR
South Korea
Prior art keywords
bar
main
bars
muscle
short side
Prior art date
Application number
KR1020060003529A
Other languages
Korean (ko)
Inventor
김두희
Original Assignee
김두희
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김두희 filed Critical 김두희
Priority to KR1020060003529A priority Critical patent/KR100736383B1/en
Application granted granted Critical
Publication of KR100736383B1 publication Critical patent/KR100736383B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/36Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
    • E04B5/38Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/36Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
    • E04B5/38Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element
    • E04B5/40Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element with metal form-slabs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

A bar arrangement and a slab construction method using the bar arrangement are provided to reduce the quantity of reinforcing bars required for slab construction by arranging reinforcing bars at the optimum on a truss form regardless of skillfulness and to shorten a period of construction by performing a slab form assembly work and a bar arrangement work for slab construction at the same time. The bar arrangement comprises a column strip reinforcing bar member(10) composed of support bars(13) arranged on column strip upper and lower bars(11,12) at regular intervals to connect the column strip upper and lower bars and projected to the appointed height from the column strip lower bars, a middle strip reinforcing bar member composed of middle strip lower bars(22) having the same length as the column strip upper and lower bars, middle strip upper bars(21) arranged on two upper sides of the middle strip lower bar parallel to each other, support bars(23) connected to the middle strip upper and lower bars and projected to the appointed height from the middle strip lower bar and backing bars(24) installed on the middle strip lower bar at regular intervals and projected downward, short edge lower bars(30) connected at right angles to the column strip lower bar and the middle strip lower bar, long edge lower bars(31) connected at right angles to the short edge lower bars, short edge lower joint bars connected to a short edge lower bar(30a) of the whole section of the column strip and an edge lower bar(30c) of the center of the middle strip, long edge lower joint bars connected to the column strip and middle strip lower bars and the long edge lower bar, long edge upper joint bars connected to the column strip and middle strip upper bars, short edge upper spread bars connected at right angles to the column strip and middle strip upper bars, and long edge upper spread bars arranged on the short edge lower bars and connected to the short edge upper spread bars.

Description

철근 배근체와 이를 이용한 슬래브 시공 방법{omitted}Reinforcing bar body and slab construction method using the same

도 1은 본 발명에 사용될 수 있는 슬래브 트러스 거푸집을 보인 도면1 shows a slab truss formwork that can be used in the present invention.

도 2a,b,c는 본 발명에 있어 인양전 슬래브 철근 배근체가 조립되는 과정을 설명하기 위한 도면Figure 2a, b, c is a view for explaining the process of assembling the slab reinforcement before lifting in the present invention

도 3은 본 발명에 있어서 단변 하부근이 설치되는 상태를 보인 도면Figure 3 is a view showing a state in which the short side lower muscles are installed in the present invention

도 4는 본 발명의 철근 배근체가 인양되는 상태를 보인 도면Figure 4 is a view showing a state in which the reinforcement is lifting the body of the present invention

도 5a,b,c,d는 본 발명에 있어 인양후 슬래브 철근 배근체가 조립되는 과정을 설명하기 위한 도면Figure 5a, b, c, d is a view for explaining the process of assembling the slab reinforcement body after lifting in the present invention

도 6은 본 발명에 있어서 단변 상부 전개근이 설치되는 상태를 보인 도면6 is a view showing a state in which the short side upper deployment muscle is installed in the present invention;

도 7은 본 발명의 시공 방법에 있어서 각 단계별 작업 위치를 예시하기 위한 설명하기 위한 건물 도면Figure 7 is a building diagram for explaining the work position for each step in the construction method of the present invention

도 8은 본 발명이 적용되는 건물의 구조 평면도8 is a structural plan view of a building to which the present invention is applied

도 9a.b는 본 발명에 있어 보와 슬래브의 철근 이음 상태를 도면Figure 9a.b is a view showing a reinforced state of the beam and the slab in the present invention

도 10은 본 발명의 주열대 및 주간대 받침 수단에 나사공을 형성한 상태를 보인 도면10 is a view showing a state in which a screw hole is formed in the support unit for the main column and the day stand of the present invention;

도 11은 본 발명에 있어서 가설재를 이용하여 거푸집을 두개 이상 인양 하는 상태를 보인 도면11 is a view showing a state of lifting two or more formwork using a temporary material in the present invention.

[도면의 주요 부분에 대한 부호의 설명][Description of Symbols for Main Parts of Drawing]

10 : 주열대 철근 부재 11 : 주열대 상부근10: main column reinforcing bar member 11: upper row of main column

12 : 주열대 하부근 13,23 : 지지 철근12: subtropical lower bar 13,23: support bar

20 : 주간대 철근 부재 21 : 주간대 상부근20: the main bar reinforcing member 21: the upper bar reinforcement

22 : 주간대 하부근 24 : 받침 철근22: the lower bar of the day stand 24: the reinforcing bar

30 : 단변 하부근 31 : 장변 하부근30: short side lower muscle 31: long side lower muscle

32 : 단변 하부 이음근 33 : 장변 하부 이음근32: short side lower joint 33: long side lower joint

34 : 장변 상부 이음근 36 : 단변 상부 전개근34: long side upper muscle 36: short side upper deployment muscle

37 : 장변 상부 전개근 40 : 보 철근 배근체37: long side upper muscle 40: prosthetic reinforcement

본 발명은 철근 배근체와 이를 이용한 슬래브 시공 방법에 관한 것으로 더욱 상세히는 운반 및 시공 편의성을 고려하여 설계되어 공장에서 대부분의 구조물이 제작되는 트러스 거푸집 위에 철근을 숙련도와 관계없이 최적의 상태로 배근할 수 있도록 한 슬래브 시공 방법에 관한 것이다.The present invention relates to a reinforcing bar reinforcement and a slab construction method using the same in more detail is designed in consideration of the transport and construction convenience to reinforce the reinforcing bar in the optimal state irrespective of skill on the truss formwork most of the structure is manufactured in the factory It is about a slab construction method.

일반적으로 슬래브를 시공하는 방식은 거푸집을 설치한 후 그 위에 철근을 배근할 수 밖에 없기 때문에 공사기간이 길어지게 되고, 철근의 배근 상태가 경험에 의존하기 때문에 현장 여건과 작업자에 따라 달라지게 될 뿐만 아니라 최적상태의 배근과 비교해 보면 철근이 과다하게 사용되는 문제점이 있었다.In general, the method of constructing the slab will be longer depending on the site conditions and workers because the construction period will be longer because the reinforcing bars are forced to be placed on top of the formwork after installing the formwork. But there is a problem that the rebar is excessively used compared to the optimal reinforcement.

종래에는 거푸집에 철근을 배근한 상태의 데크 방식이 알려져 있으나 이것은 거푸집과 철근이 일체화 되어있기 때문에 공장에서 현장까지 운반하여 인양하는데 어려움이 있으며, 철근 및 거푸집을 현장에 따라 호환성 있게 제작할 수 없을 뿐만 아니라 최적상태의 배근과 비교해 보면 철근이 40~60% 정도 과다하게 사용되는 문제점 역시 해결되지 못하고 있다.Conventionally, the deck method of reinforcing the reinforcement in the formwork is known, but since the formwork and the reinforcing bar is integrated, it is difficult to lift and carry from the factory to the site, and not only can not be manufactured to be compatible with the reinforcement and formwork according to the site Compared with the optimal reinforcement bar, the problem that the rebar is used excessively by 40 to 60% has not been solved.

본원출원인은 운반 및 시공 편의성을 감안한 설계에 따라 공장에서 제작되는 트러스 구조물과 현장에서 조립되는 부분을 나눔으로써 유니트화 한 입체 트러스 거푸집을 10-2005-0130274로 선출원 하였으며, 이와같이 유니트화 된 거푸집을 이용한다면 철근을 숙련도와 관계없이 최적의 상태로 배근할 수 있을 것이라는 점에 착안하여 본 발명을 안출하게 되었다.The applicant filed a 10-2005-0130274 unitized three-dimensional truss formwork by dividing the truss structure manufactured at the factory and the parts assembled at the site according to the design considering transportation and construction convenience. The present invention has been devised in view of the fact that the reinforcing bar can be arranged in an optimal state regardless of skill level.

본 발명이 이루고자 하는 기술적 과제는 유니트화 된 거푸집 위에 숙련도와 관계없이 철근을 최적의 상태로 배근할 수 있도록 한 철근 배근체와 이를 이용한 슬래브 시공방법을 제공하기 위한 것이다.The technical problem to be achieved by the present invention is to provide a reinforcing bar reinforcement body and a slab construction method using the same to reinforce the reinforcing bar in the optimal state irrespective of skill on the united formwork.

본 발명이 이루고자 하는 다른 기술적 과제는 고임재 작업이 필요 없을 뿐만 아니라 슬래브 거푸집 조립 작업과 슬래브의 철근 배근 작업이 동시에 이루어질 수 있도록 함으로써 공사 기간을 단축할 수 있도록 하기 위한 것이다.Another technical problem to be achieved by the present invention is to reduce the construction period by not only the high-bearing material work is required, but also the slab formwork and the slab reinforcement work can be performed at the same time.

본 발명의 기술적 과제는 동일한 길이로 평행한 주열대 상,하부근에 일정한 간격으로 배열되어 상기 주열대 상,하부근을 연결하는 동시에 주열대 하부근으로부터 일정 높이만큼 돌출된 지지 철근으로 이루어진 주열대 철근 부재; 상기 주열대 상,하부근과 동일한 길이를 갖는 주간대 하부근과, 상기 주간대 하부근의 양측 상부에 평행하게 배열되는 주간대 상부근과, 상기 주간대 상,하부근에 연결하는 동시에 주간대 하부근으로부터 일정 높이만큼 돌출된 지지 철근과, 상기 주간대 하부근에 일정한 간격으로 두고 하부로 돌출되게 설치된 받침 철근으로 이루어진 주간대 철근 부재; 바닥에 놓여진 상태에서 설계에 따라 배열된 상기 주열대 하부근과 주간대 하부근에 직교하는 상태로 연결되는 단변 하부근; 상기 단변 하부근에 직교하는 상태로 연결되는 장변 하부근; 상기 단변 하부근중 주열대 전구간 단변 하부근과 주간대 전구간 단변 하부근에 연결되는 단변 하부 이음근; 상기 주열대 및 주간대 하부근과 장변 하부근에 연결되는 장변 하부 이음근; 상기 주열대 및 주간대 상부근에 연결되는 장변 상부 이음근; 상기 주열대 및 주간대 상부근에 직교하는 상태로 연결되는 단변 상부 전개근; 상기 단변 하부근 위에 배열된 상태에서 상기 단변 상부 전개근에 연결되는 장변 상부 전개근;을 포함하는 철근 배근체에 의하여 달성되어진다.The technical problem of the present invention is arranged at regular intervals on the upper and lower roots of the parallel column in the same length at the same time to connect the upper and lower roots of the main column and at the same time the main column made of a support bar protruding by a certain height from the lower root of the main column Rebar member; The main stem lower muscle having the same length as the upper and lower roots of the main row, and the upper root of the main bench arranged parallel to the upper sides of the lower root of the main bench, and the upper stem at the same time to the upper and lower roots A main bar reinforcing member consisting of a support bar protruding from a lower bar by a predetermined height and a supporting bar protruding downwardly at regular intervals from the lower bar of the bar; A short side lower muscle connected in a state orthogonal to the lower main root and the lower main muscle arranged in accordance with the design in a state placed on the floor; A long side lower muscle connected in a state orthogonal to the short side lower muscle; A short side lower joint connected to the short side lower root of the short side muscle of the short side muscle and the short side lower muscle of the whole day zone; A long side lower joint connected to the lower main muscle and the long side lower muscle of the main tropics and the main body; A long side upper joint connected to the upper row of the main row and the main row; A short side upper deploying muscle connected in a state orthogonal to the upper row of the main row and the main row; It is achieved by the reinforcement body comprising a; long side upper deployment muscles connected to the short side upper deployment muscles in a state arranged on the short side lower muscles.

본 발명의 기술적 과제는 슬래브 시공에 소요되는 철근을 가공하는 공장 가공 단계; 거푸집 합판 위에 단변 하부근을 배열하는 인양전 제 1 단계; 주열대 철근 부재와 주간대 철근 부재를 상기 단변 하부근에 직교하는 방향으로 배열한 상태에서 단변 하부근을 들어올려 상기 주열대 및 주간대 하부 철근에 연결하는 인양전 제 2 단계; 장변 하부근을 상기 단변 하부근에 직교하는 상태로 연결하여 인양전 철근 배근체를 완성하는 제 3 단계; 상기 인양전 철근 배근체를 인양하여 거푸집을 설치하는 제 4 단계; 단변 하부 이음근을 상기 단변 하부근에 연결하는 제 5 단계; 장변 하부 이음근을 상기 주열대 및 주간대 하부근과 장변 하부근에 연결하는 제 6 단계; 상기 단변 하부근 위에 장변 상부 전개근을 배열하는 제 7 단계; 단변 상부 전개근을 상기 주열대 및 주간대 상부근에 직교하는 상태로 연결하는 제 8 단계; 상기 장변 상부 전개근을 들어올려 상기 단변 상부 전개근에 연결하는 제 9 단계;로 이루어진 철근 배근체를 이용한 슬래브 시공방법에 의하여 달성되어진다.Technical problem of the present invention is a factory processing step of processing the rebar required for the slab construction; A first step of lifting before arranging the short side root muscles on the formwork plywood; Lifting second step of lifting the short side lower bar in a state in which the main bar reinforcing bar member and the day bar rebar member are arranged in a direction orthogonal to the short side lower bar; A third step of connecting the long side lower muscles in a state orthogonal to the short side lower muscles to complete the reinforcing reinforcement body before lifting; A fourth step of installing formwork by lifting the reinforcement bar before lifting; A fifth step of connecting the short side lower muscle to the short side lower muscle; A sixth step of connecting the lower side of the long side joint with the lower side and the lower side of the main bar; A seventh step of arranging a long side upper deployment muscle above the short side bottom muscle; An eighth step of connecting the short-sided upper deployment muscle in a state orthogonal to the upper row of the main heating zone and the daytime standby zone; It is achieved by the slab construction method using a reinforcing bar reinforcement consisting of; a ninth step of lifting the long side upper deployment muscle to connect to the short side upper deployment muscle.

본 발명의 바람직한 실시예를 첨부된 도면에 의거 상세히 설명하면 다음과 같다.Preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명에 사용될 수 있도록 유니트화 한 선출원 10-2005-0130274의 슬래브 트러스 거푸집을 보인 도면이다. 1 is a view showing the slab truss formwork of prior application 10-2005-0130274 unitized for use in the present invention.

이것은 도시된 바와 같이 메인 트러스(1)와 서브 트러스(2)로 이루어져 건물 설계에 맞춰 현장에서 간편하게 조립될 수 있도록 한 슬래브 거푸집으로 본 발명은 부위별 철근 제작 작업이 공장에서 이루어지기 때문에 이와같이 유니트화 된 거푸집과 함께 사용될 때 그 효용성이 배가될 수 있음은 물론이다.This is a slab formwork made of a main truss (1) and a sub truss (2) as shown in the drawing so that the assembly can be easily assembled in the field according to the building design. Of course, the utility can be doubled when used with the old formwork.

본 발명의 슬래브 철근 배근체는, 동일한 길이로 평행한 주열대 상,하부근(11)(12)에 일정한 간격으로 배열되어 상기 주열대 상,하부근(11)(12)을 연결하는 동시에 주열대 하부근(12)으로부터 일정 높이만큼 돌출된 지지 철근(13)으로 이루어진 주열대 철근 부재(10); 상기 주열대 상,하부근(11)(12)과 동일한 길이를 갖는 주간대 하부근(22)과, 상기 주간대 하부근(22)의 양측 상부에 평행하게 배열되는 주간대 상부근(21)과, 상기 주간대 상,하부근(21)(22)에 연결하는 동시에 주간대 하부근(22)으로부터 일정 높이만큼 돌출된 지지 철근(23)과, 상기 주간대 하부근(22)에 일정한 간격으로 두고 하부로 돌출되게 설치된 받침 철근(24)으로 이루어진 주간대 철근 부재(20); 바닥에 놓여진 상태에서 설계에 따라 배열된 상기 주열대 하부근(12)과 주간대 하부근(22)에 직교하는 상태로 연결되는 단변 하부근(30); 상기 단변 하부근(30) 위에 직교하는 상태로 연결되는 장변 하부근(31); 상기 단변 하부근(30)중 주열대 전구간 단변 하부근(30a)과 주간대 중앙부 단부 하부근(30c)에 연결되는 단변 하부 이음근(32); 상기 주열대 및 주간대 하부근(12)(22)과 장변 하부근(31)에 연결되는 장변 하부 이음근(33); 상기 주열대 및 주간대 상부근(11)(21)에 연결되는 장변 상부 이음근(34); 상기 주열대 및 주간대 상부근(11)(21)에 직교하는 상태로 연결되는 단변 상부 전개근(36); 상기 단변 하부근(30) 위에 배열된 상태에서 상기 단변 상부 전개근(36)에 연결되는 장변 상부 전개근(37);으로 구성된다.The slab reinforcement of the present invention is arranged at regular intervals on the upper and lower roots 11 and 12 in parallel with the same length to connect the upper and lower roots 11 and 12 at the same time. A main tropical reinforcing bar member 10 including a support bar 13 protruding from the tropical lower bar 12 by a predetermined height; Day table lower root 22 having the same length as the upper and lower roots 11 and 12 of the main row, and the upper table root 21 of the main stand parallel to the upper side of both sides of the lower table root 22 And, connected to the upper and lower roots 21, 22 of the day bar, and at the same time protruding from the lower bar 22, the support reinforcing bar 23 and a constant distance to the lower bar 22, Reinforcing bar member consisting of a reinforcing bar (24) installed to protrude to the lower side to be set to; A short side lower muscle 30 connected in a state orthogonal to the lower main muscle root 12 and the lower main muscle root 22 arranged according to a design in a state placed on a floor; A long side lower muscle 31 connected in a state orthogonal to the short side lower muscle 30; Short side lower root joint 32 is connected to the short side lower root 30a of the main hot zone of the short side lower root 30 and the lower end 30g of the central portion of the day band; A long side lower joint (33) connected to the lower main muscles (12) and (22) and the lower side of the long side (31); A long side upper joint muscle 34 connected to the upper and lower muscle roots 11 and 21. A short side upper deploying muscle 36 connected in a state orthogonal to the upper and lower stems 11 and 21 of the main heating zone; And a long side upper deployment muscle 37 connected to the short side upper deployment muscle 36 in a state arranged on the short side lower muscle 30.

상기 주열대 및 주간대 철근 부재(10)(20)는 주열대 하부근(12)의 하부로 돌출된 지지 철근(13)과 받침 철근(24)를 제거하면 벽체의 철근 구조물로 사용될 수 있다.The main stool and daytime reinforcing bar members 10 and 20 may be used as a reinforcing bar structure when the support bar 13 and the supporting bar 24 protruding to the lower part of the lower bar 12 are removed.

상기 단변 하부근(30)은 주열대 하부근(12) 전구간에 설치되는 주열대 전구간 단변 하부근(30a), 상기 주간대 하부근(22) 전구간에만 연결되는 주간대 전구간 단변 하부근(30b)과, 상기 주열대 전구간 단변 하부근(30a)과 길이가 동일하면서 주간대 상부근(21)사이에 설치되는 주간대 중앙부 단변 하부근(30c)으로 이루어진다.The short side lower root 30 is a short side lower root 30a of the main heating zone, which is installed in the entire zone of the main heating zone lower root 12, and the daytime lower whole muscle short side lower root 30b is connected only to the entire day zone lower root 22. And, the length is the same as the short side lower root (30a) of the main hot zone whole zone, and is made up of the day center central short side lower root (30c) installed between the upper stem 21.

상기 장변 하부근(31)은 주열대 전구간 장변 하부근(31a)과 주간대 중앙부 장변 하부근(31b)으로 이루어진다.The long side lower muscle 31 is composed of the long side lower muscle 31a of the main tropics, and the long side lower muscle 31b of the day zone.

상기 단변 상부 전개근(36)은 주간대 단변 전개근(36a)과 중앙부위가 이어지는 주열대 전구간 단변 전개근(36b)으로 이루어진다.The short side upper deployment muscle 36 is composed of a main zone short side deployment muscle 36a and a main tropical zone short-side deployment muscle 36b to which the central portion extends.

상기 장변 상부 전개근(37)은 주간대 장변 전개근(37a), 중앙부위가 이어지는 주열대 전구간 장변 전개근(37b)으로 이루어진다.The long side upper deployment muscle 37 is composed of a main zone long side deployment muscle 37a, a main tropics all long side deployment muscle (37b) that continues the central portion.

이와같이 철근 배근체를 구성하는 주열대 철근 부재(10), 주간대 철근 부재(20), 하부근(30)(31), 이음근(32)(33)(34), 전개근(36)(37)은 설계 소요량만큼 공장에서 각각 제작되어(공장 가공 단계) 현장으로 운반되고 현장에서는 도 2a,b,c에 도시된 순서대로 연결 조립되어 인양전 철근 배근체를 제작한다.Thus, the main heating rod reinforcing member (10), the reinforcing bar reinforcing member (20), the lower bar (30), 31, the joint bar (32) (33) (34), the expanding bar (36) ( 37) are manufactured in the factory as much as the design requirements (factory processing step) and transported to the site, and the site is connected and assembled in the order shown in Figs.

도 2a,b,c는 현장에서 조립되는 본 발명의 인양전 철근 배근체를 제작하는 과정을 설명하기 위한 도면이고, 도 5a,b,c,d는 인양하여 거푸집 위에 설치된 인양전 철근 배근체에 이음근과 전개근을 조립하여 슬래브 철근 배근체를 완성하는 과정을 보인 도면이다.Figure 2a, b, c is a view for explaining the process of manufacturing the lifting reinforcement of the present invention assembled on-site, Figure 5a, b, c, d is lifted to the lifting reinforcement installed on the formwork The drawing shows the process of completing the slab reinforcement by assembling the joint and the expansion muscle.

철근 배근체를 조립하기 위해 철근을 연결하는 방식은 결속선을 이용하는 방법이 사용된다.The method of connecting the reinforcing bars to assemble the reinforcing bar is a method using a binding line.

철근 배근체를 제작하기 위해서는 먼저 거푸집(3) 위의 합판(4)에 단변 하부근(30)을 배열하고(도 2a 참조, 인양전 제 1 단계), 주열대 철근 부재(10)와 주간대 철근 부재(20)를 상기 단변 하부근(30)에 직교되도록 배열한다. 이때 주열대 철근 부재(10)와 주간대 철근 부재(20)의 양끝은 공지된 버팀수단을 이용하여 세워진 상태가 유지되도록 한다.In order to manufacture the reinforcing bar reinforcement, first, the short side lower bar 30 is arranged on the plywood 4 on the formwork 3 (see FIG. 2A, the first step before lifting), and the main heating bar reinforcing member 10 and the day bar The rebar member 20 is arranged to be orthogonal to the short side lower muscle 30. At this time, both ends of the main column reinforcing bar member 10 and the main bar reinforcing bar member 20 is maintained using a known prop means.

이 상태에서 상기 단변 하부근(30)을 도 3에 도시된 바와 같이 들어 올려 상기 철근 부재(10)(20)에 조립하면 도 2b와 같이 된다.(인양전 제 2 단계)In this state, the short side lower muscle 30 is lifted as shown in FIG. 3 and assembled to the rebar members 10 and 20, as shown in FIG. 2B. (2nd step before lifting)

상기 단변 하부근(30) 위에 직교하는 상태로 장변 하부근(31)를 배열하고 연결하면 인양전 철근 배근체가 도 2c에 도시된 바와 같이 완성된다.(인양전 제 3 단계)If the long side lower muscle 31 is arranged and connected in a state orthogonal to the short side lower muscle 30, the reinforcement reinforcement before lifting is completed as shown in FIG. 2C.

인양전 철근 배근체의 중량은 현장의 인양 설비에 맞춰 설계시 결정되며, 수평이동은 합판(4) 하부의 거푸집(3)에 바퀴(3b)를 부가하는 것만으로 용이하게 이루어질 수 있다.The weight of the reinforcing bar reinforcement before lifting is determined at the time of design according to the lifting equipment of the site, and the horizontal movement can be easily performed simply by adding the wheels 3b to the formwork 3 under the plywood 4.

이렇게 인양전 철근 배근체가 완성되면 도 4에 도시된 바와 같이 이를 거푸집(3)과 함께 인양한후 설치한다.(제 4 단계)When the reinforcing bar reinforcement is completed before lifting as shown in Figure 4 and installed with the formwork (3) (step 4).

상기 철근 배근체의 인양은 거푸집(3)에 연결 설치된 인양 수단(3a)에 의하여 이루어진다.The lifting of the reinforcement bar is made by lifting means 3a connected to the formwork 3.

단변 하부 이음근(32)을 상기 단변 하부근(30)중 주열대 전구간 단변 하부근(30a)과 주간대 전구간 단변 하부근(30b)에 연결한다.(도 5a 참조, 제 5 단계)The short side lower root joint 32 is connected to the short side lower root 30a of the main hot zone zone and the short side lower root 30b of the main zone zone among the short side lower root muscles 30 (see FIG. 5A and the fifth step).

장변 하부 이음근(33)을 상기 주열대 및 주간대 하부근(12)(22)에 연결한다.(도 5b 참조, 제 6 단계)The long side lower root muscle 33 is connected to the lower row muscles 12 and 22 of the main row (see Fig. 5b, step 6).

상기 단변 하부근(30) 위에 장변 상부 전개근(37)을 배열 하고(제 7 단계), 단변 상부 전개근(36)을 상기 주열대 및 주간대 상부근(11)(21)에 직교하는 상태로 연결한다.(도 5c 참조, 제 8 단계)The long side upper deployment muscle 37 is arranged on the short side lower muscle 30 (seventh step), and the short side upper deployment muscle 36 is orthogonal to the upper and lower zones 11 and 21 of the main heating zone. (See Fig. 5c, step 8).

상기 장변 상부 전개근(37)을 들어 올려 상기 단변 상부 전개근(36)에 도 6에 도시된 바와 같이 연결하여 철근 배근체를 완성한다.(도 5d 참조, 제 9 단계)Lifting the long side upper deployment muscle 37 is connected to the short side upper deployment muscle 36 as shown in Figure 6 to complete the reinforcement bar (see Fig. 5d, 9th step)

도 7은 본 발명의 시공 방법에 있어서 각 단계별 작업 위치를 예시하기 위한 설명하기 위한 건물 도면이다. A 구역은 슬래브 거푸집(3) 및 철근을 조립하는 장소로, B 구역은 보 거푸집 및 철근 배근 장소로, C 구역은 인양후 이음근(32)(33)(34)과 전개근(36)(37)을 조립(제 5~9 단계)하는 장소로, B-1 구역은 B 구역의 바닥 슬래브(5)층의 거푸집을 해체하고 윗층의 인양전 슬래브 철근 배근체를 제작하는 장소로, B-2 및 B-3 구역은 (6)(7)의 보 및 슬래브 거푸집을 해체하고 윗층의 보 및 슬래브 철근 배근체를 제작하는 장소로 사용될 수 있다.7 is a building diagram for explaining for explaining the work position of each step in the construction method of the present invention. Area A is the place to assemble slab formwork (3) and rebar, area B is the beam formwork and reinforcement site, and area C is post-lift joint (32) (33) (34) and flattening muscle (36) ( 37) is the place to assemble (steps 5-9), the B-1 area is to dismantle the formwork of the bottom slab (5) layer of the B zone and to manufacture the reinforcing bar of reinforcement slab before lifting the upper floor. Zones 2 and B-3 may be used as a site for dismantling beams and slab formwork in (6) (7) and for fabricating beams and slab reinforcement in the upper floors.

도 8은 건물의 구조 평면도이고, 도 9a,b는 본 발명에 있어 보와 슬래브의 철근 이음 상태를 예시한 도면으로써, 장변 상하부 이음근(34)(33)이 주열대 및 주간대 상하부근(11)(12)(21)(22) 위 또는 측면으로 연결되어 보 철근 배근체(40)를 지나도록 한 것이다.FIG. 8 is a structural plan view of the building, and FIGS. 9A and 9B illustrate a reinforcing bar joint state of a beam and a slab according to the present invention. 11) (12) (21) (22) is connected to the upper or side to pass through the reinforcement reinforcement (40).

도 10은 주열대 및 주간대 받침 수단인 철근(13)(24)의 하부에 나사공(130)(240)을 형성하여 슬래브 시공후 각종 배관을 설치하는 와이어 등을 결합하는데 사용할 수 있도록 한 것이다.Figure 10 is to form a screw hole 130, 240 in the lower portion of the reinforcing bar 13, 24, which is a means for supporting the main column and the day stand, so that it can be used to combine the wires for installing various pipes after the slab construction. .

도 11은 가설대(50)를 이용하여 인양전 철근 배근체가 설치된 2개 이상의 슬래브 거푸집(3)을 인양하는 상태를 보인 도면이다.FIG. 11 is a view showing a state in which two or more slab formwork 3 installed with a reinforcing bar reinforcement body is lifted using a temporary bench 50.

이와같이 된 본 발명은 철근 배근체를 이루는 모든 철근이 공장에서 제작(가 공,절단)되어 현장으로 운반되고 거푸집 위에 인양전 철근 배근체를 조립하는 작업이 하부층에서 이루어지며 거푸집과 함께 인양되어 설치된후 철근 배근체를 완성하는 방식으로 이루어지는 것으로, 철근 배근체를 조립하는 인양전후 작업과 거푸집 해체 작업이 다른 공간에서 동시에 이루어질 수 있어 공사 기간을 단축할 수 있음은 물론 철근을 배근하는데 따른 숙련도에 관계없이 설계시 고려된 최적의 상태를 갖도록 배근할 수 있어 슬래브 시공에 소요되는 철근량을 절감하는 효과를 갖는 유용한 발명이다.In the present invention, all the reinforcing bars of the reinforcing bar are manufactured (processed and cut) at the factory and transported to the site, and the work of assembling the reinforcing bar before reinforcing on the formwork is carried out at the lower floor and is installed with the formwork after lifting. This is done by completing the reinforcing bar, and the lifting work before and after assembling the reinforcing bar can be done in different spaces at the same time to shorten the construction period and regardless of the proficiency of reinforcing the bar. It is a useful invention having the effect of reducing the amount of rebar required for the construction of the slab can be reinforcement to have the optimum state considered in the design.

이상에서는 본 발명을 첨부 도면과 실시예에 의해 한정하여 설명하였으나 이에 한정되는 것은 아니며, 본 발명의 기술적 사상이 속하는 범위내에서 당해분야에 대하여 통상의 지식을 가진자에 의하여 다양한 변형실시가 가능함은 물론이다.In the above, the present invention has been limited to and described with reference to the accompanying drawings and examples, but is not limited thereto. Various modifications may be made by those skilled in the art within the scope of the technical idea of the present invention. Of course.

Claims (8)

동일한 길이로 평행한 주열대 상,하부근에 일정한 간격으로 배열되어 상기 주열대 상,하부근을 연결하는 동시에 주열대 하부근으로부터 일정 높이만큼 돌출된 지지 철근으로 이루어진 주열대 철근 부재; 상기 주열대 상,하부근과 동일한 길이를 갖는 주간대 하부근과, 상기 주간대 하부근의 양측 상부에 평행하게 배열되는 주간대 상부근과, 상기 주간대 상,하부근에 연결하는 동시에 주간대 하부근으로부터 일정 높이만큼 돌출된 지지 철근과, 상기 주간대 하부근에 일정한 간격으로 두고 하부로 돌출되게 설치된 받침 철근으로 이루어진 주간대 철근 부재; 바닥에 놓여진 상태에서 설계에 따라 배열된 상기 주열대 하부근과 주간대 하부근에 직교하는 상태로 연결되는 단변 하부근; 상기 단변 하부근에 직교하는 상태로 연결되는 장변 하부근; 상기 단변 하부근중 주열대 전구간 단변 하부근과 주간대 전구간 단변 하부근에 연결되는 단변 하부 이음근; 상기 주열대 및 주간대 하부근과 장변 하부근에 연결되는 장변 하부 이음근; 상기 주열대 및 주간대 상부근에 연결되는 장변 상부 이음근; 상기 주열대 및 주간대 상부근에 직교하는 상태로 연결되는 단변 상부 전개근; 상기 단변 하부근 위에 배열된 상태에서 상기 단변 상부 전개근에 연결되는 장변 상부 전개근;을 포함하는 철근 배근체.A main column reinforcing member which is arranged at regular intervals in the upper and lower roots of the main column in parallel with the same length and connects the upper and lower roots of the main column and protrudes a predetermined height from the lower part of the main column; The main stem lower muscle having the same length as the upper and lower roots of the main row, and the upper root of the main bench arranged parallel to the upper sides of the lower root of the main bench, and the upper stem at the same time to the upper and lower roots A main bar reinforcing member consisting of a support bar protruding from a lower bar by a predetermined height and a supporting bar protruding downwardly at regular intervals from the lower bar of the bar; A short side lower muscle connected in a state orthogonal to the lower main root and the lower main muscle arranged in accordance with the design in a state placed on the floor; A long side lower muscle connected in a state orthogonal to the short side lower muscle; A short side lower joint connected to the short side lower root of the short side muscle of the short side muscle and the short side lower muscle of the whole day zone; A long side lower joint connected to the lower main muscle and the long side lower muscle of the main tropics and the main body; A long side upper joint connected to the upper row of the main row and the main row; A short side upper deploying muscle connected in a state orthogonal to the upper row of the main row and the main row; Reinforced body comprising a; long side upper deployment muscles connected to the short side deployment muscles in a state arranged on the short side lower muscles. 청구항 1에 있어서, 상기 장변 상하부 이음근을 주열대 및 주간대 상하부근 위로 연결하여 보 철근 배근체를 지나도록 한 것을 특징으로 하는 철근 배근체. The reinforced reinforcement body of claim 1, wherein the upper and lower joints of the long side are connected to the upper and lower muscles of the parachute and daytime zone so as to pass through the prosthetic reinforcement body. 청구항 1에 있어서, 상기 장변 상하부 이음근을 주열대 및 주간대 상하부근 측면으로 연결하여 보 철근 배근체를 지나도록 한 것을 특징으로 하는 철근 배근체.The reinforced reinforcement body of claim 1, wherein the long side upper and lower joints are connected to the upper and lower sides of the main heating zone and the day and night passage so as to pass through the prosthetic reinforcement body. 청구항 1에 있어서, 주열대 및 주간대 받침 수단인 철근의 하부에 나사공을 형성하여서 된 것을 특징으로 하는 철근 배근체.The reinforced reinforcement body according to claim 1, wherein a screw hole is formed in a lower portion of the reinforcing bar serving as the main support rod and the day support. 슬래브 시공에 소요되는 철근을 가공하는 공장 가공 단계; 거푸집 합판 위에 단변 하부근을 배열하는 인양전 제 1 단계; 주열대 철근 부재와 주간대 철근 부재를 상기 단변 하부근에 직교하는 방향으로 배열한 상태에서 단변 하부근을 들어올려 상기 주열대 및 주간대 하부 철근에 연결하는 인양전 제 2 단계; 장변 하부근을 상기 단변 하부근에 직교하는 상태로 연결하여 인양전 철근 배근체를 완성하는 제 3 단계; 상기 인양전 철근 배근체를 인양하여 거푸집을 설치하는 제 4 단계; 단변 하부 이음근을 상기 단변 하부근에 연결하는 제 5 단계; 장변 하부 이음근을 상기 주열대 및 주간대 하부근과 장변 하부근에 연결하는 제 6 단계; 상기 단변 하부근 위에 장변 상부 전개근을 배열하는 제 7 단계; 단변 상부 전개근을 상기 주열대 및 주간대 상부근에 직교하는 상태로 연결하는 제 8 단계; 상기 장변 상부 전개근을 들어올려 상기 단변 상부 전개근에 연결하는 제 9 단계;로 이루어진 철근 배근체를 이용한 슬래브 시공방법.Factory processing step of processing the rebar required for the slab construction; A first step of lifting before arranging the short side root muscles on the formwork plywood; Lifting second step of lifting the short side lower bar in a state in which the main bar reinforcing bar member and the day bar rebar member are arranged in a direction orthogonal to the short side lower bar; A third step of connecting the long side lower muscles in a state orthogonal to the short side lower muscles to complete the reinforcing reinforcement body before lifting; A fourth step of installing formwork by lifting the reinforcement bar before lifting; A fifth step of connecting the short side lower muscle to the short side lower muscle; A sixth step of connecting the lower side of the long side joint with the lower side and the lower side of the main bar; A seventh step of arranging a long side upper deployment muscle above the short side bottom muscle; An eighth step of connecting the short-sided upper deployment muscle in a state orthogonal to the upper row of the main heating zone and the daytime standby zone; Slab construction method using a reinforcing bar reinforcement consisting of; 청구항 5에 있어서, 상기 인양전 제 1~3 단계, 인양후 제 4~9 단계와 거푸집의 해체 작업이 별도의 구역에서 동시에 이루어지는 것을 특징으로 하는 철근 배근체를 이용한 슬래브 시공 방법.The slab construction method according to claim 5, wherein the first to third stages before the salvage, the fourth to ninth stages after the salvage, and the dismantling of the formwork are simultaneously performed in separate zones. 청구항 5에 있어서, 상기 주열대 철근 부재는, 동일한 길이로 평행한 주열대 상,하부근과; 일정한 간격으로 배열되어 상기 주열대 상,하부근을 연결하는 동시에 주열대 하부근으로부터 일정 높이만큼 돌출된 지지 철근;으로 이루어진 것을 특징으로 하는 철근 배근체를 이용한 슬래브 시공 방법.The method according to claim 5, wherein the main row of reinforcing bar member, the upper and lower root of the main row in parallel with the same length; The slab construction method using a reinforcing bar reinforcement, characterized in that consisting of; the reinforcing bar is arranged at regular intervals to connect the upper and lower roots of the main heating zone and at the same time protruding from the lower end of the main heating rod. 청구항 5에 있어서, 상기 주간대 철근 부재는, 상기 주열대 상,하부근과 동일한 길이를 갖는 주간대 하부근과, 상기 주간대 하부근의 양측 상부에 평행하게 배열되는 주간대 상부근과, 상기 주간대 상,하부근에 연결하는 동시에 주간대 하부근으로부터 일정 높이만큼 돌출된 지지 철근과, 상기 주간대 하부근에 일정한 간격으로 두고 하부로 돌출되게 설치된 받침 철근으로 이루어진 것을 특징으로 하는 철근 배근체를 이용한 슬래브 시공 방법.The method according to claim 5, wherein the reinforcing bar member, the main bar lower bar having the same length as the upper and lower roots of the main row, and the upper bar of the main bar arranged in parallel to the upper side of both sides of the lower bar, Reinforcing bar reinforcement, characterized in that the support bar is connected to the upper and lower muscles at the same time, and the support reinforcement protrudes from the lower base of the day by a certain height, and the supporting reinforcement is installed to protrude downwardly at regular intervals on the lower base Slab construction method using
KR1020060003529A 2006-01-12 2006-01-12 Reinforcing bar and slab construction method KR100736383B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060003529A KR100736383B1 (en) 2006-01-12 2006-01-12 Reinforcing bar and slab construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060003529A KR100736383B1 (en) 2006-01-12 2006-01-12 Reinforcing bar and slab construction method

Publications (1)

Publication Number Publication Date
KR100736383B1 true KR100736383B1 (en) 2007-07-06

Family

ID=38503421

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060003529A KR100736383B1 (en) 2006-01-12 2006-01-12 Reinforcing bar and slab construction method

Country Status (1)

Country Link
KR (1) KR100736383B1 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05118140A (en) * 1991-10-25 1993-05-14 Fudo Constr Co Ltd Floor slab reinforcing bar arranging method
JPH11210228A (en) 1998-01-27 1999-08-03 Kajima Corp Reinforcing bar arrangement method of wall and floor slab
KR20020038423A (en) * 2000-11-17 2002-05-23 이창남 Reinforcing Method of Column Capital of Flat Plate
JP2003027646A (en) 2001-07-19 2003-01-29 Sogiri:Kk Method for arranging slab reinforcements and slab reinforcement unit

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05118140A (en) * 1991-10-25 1993-05-14 Fudo Constr Co Ltd Floor slab reinforcing bar arranging method
JPH11210228A (en) 1998-01-27 1999-08-03 Kajima Corp Reinforcing bar arrangement method of wall and floor slab
KR20020038423A (en) * 2000-11-17 2002-05-23 이창남 Reinforcing Method of Column Capital of Flat Plate
JP2003027646A (en) 2001-07-19 2003-01-29 Sogiri:Kk Method for arranging slab reinforcements and slab reinforcement unit

Similar Documents

Publication Publication Date Title
KR100667921B1 (en) Construction method of pylon using precast concrete beam
KR100971736B1 (en) Shear reinforcement with dual anchorage function each up and down
AU2014224166B2 (en) Dual Mesh Level Reinforcement Bar Chair Assembly
US20130125498A1 (en) Rebar chair
ES2367261T3 (en) SET OF PREFABRICATED COMPONENTS FOR THE FORMATION OF SOIL, SOIL AND WALL Slabs WITH EXPOSED WOOD BEAMS.
TWI656263B (en) Structure of load-bearing columns and factory using the same
US20140173903A1 (en) Prefabricated Structural Concrete Beam and Methods for Use
KR20100031233A (en) Pre-fabrication method of rebar structure for reinforced concrete column
US20020092249A1 (en) Partially prefabricated waffle slab
CN101122151B (en) Bidirectional single-row reinforcement shear wall structure and manufacturing method thereof
KR101551196B1 (en) Method for gong-po installation thereby and structure for gong-po installation of korean-style house
CN111794424A (en) Integral laminated slab honeycomb combination beam and manufacturing method thereof
US20090301011A1 (en) Reinforced concrete ceiling and process for the manufacture thereof
KR100736383B1 (en) Reinforcing bar and slab construction method
CN112982963A (en) Hyperboloid wood grain clear water concrete roof construction supporting template and construction process
US20220356706A1 (en) Reinforcing Steel Skeletal Framework
KR101616483B1 (en) Construction Method Of Underground Parking Lot Using Precast Concrete Beam With Changing Cross Section
EP0128431B1 (en) Space truss of metal
KR101385556B1 (en) Ground structure and the built-up construction method that use precast concrete
JP2017066846A (en) Column-beam frame
KR101763266B1 (en) Manufacturing method for twin wall
CN217150851U (en) Use shaping steel bar truss structure of muscle expansion net as die block board
KR20090053306A (en) Connector for pre- fabricating the reinforced bar and connecting method using the connector
KR100974528B1 (en) 2 way slab using steel beam, construction method for the same
JP3138112U (en) Roof unit structure and connecting hardware used therefor

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20121231

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee