KR100647488B1 - Caisson for Pier Construction and Construction Method of Underwater Structure - Google Patents
Caisson for Pier Construction and Construction Method of Underwater Structure Download PDFInfo
- Publication number
- KR100647488B1 KR100647488B1 KR1020030053439A KR20030053439A KR100647488B1 KR 100647488 B1 KR100647488 B1 KR 100647488B1 KR 1020030053439 A KR1020030053439 A KR 1020030053439A KR 20030053439 A KR20030053439 A KR 20030053439A KR 100647488 B1 KR100647488 B1 KR 100647488B1
- Authority
- KR
- South Korea
- Prior art keywords
- caisson
- pier
- water
- ground
- installing
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
- Foundations (AREA)
Abstract
본 발명은 수밀케이션을 하상에 설치하고 그 내부의 물을 배수한 건식 상태에서 교각의 기초나 교각을 시공하는 교각시공용 케이슨 및 이를 이용한 수중 구조물의 시공방법을 개시한다.The present invention discloses a bridge construction caisson for constructing a foundation or bridge piers in a dry state in which a water milling application is installed on a lower side and water is drained therein, and a construction method of an underwater structure using the same.
이러한 본 발명의 목적은 하상 구조물의 사공시 최소면적만을 굴착하여 시공할 수 있도록 함으로써, 공기가 단축되고 하상 자연환경의 손상을 최소화함에 있다.The purpose of the present invention is to excavate only the minimum area during the construction of the riverbed structure, to shorten the air and to minimize damage to the riverbed natural environment.
이를 위하여 본 발명은 내부에 부력탱크를 갖는 복수개의 패널이 결합되며 최 하측에 위치되는 패널의 하단에 수밀수단이 구비된 공지의 케이슨에 있어서, 최 하측에 설치되는 패널의 하단에 경사면을 형성함과 아울러 수밀튜브가 설치되는 요입부를 형성하여 됨을 특징으로 한다.To this end, the present invention is a plurality of panels having a buoyancy tank therein is combined in the well-known caisson provided with a watertight means at the bottom of the panel located on the bottom, to form an inclined surface on the bottom of the panel installed on the bottom And it is characterized in that to form a recess in which the water-tight tube is installed.
또한, 케이슨을 하상에 설치하고, 그 내부의 물을 배수한 후 건식상태에서 교각기초나 교각을 시공하는 공지의 방법에 있어서, 하상의 토사층을 평탄하게 하고 육상에서 조립된 케이슨을 교각기초 또는 교각을 시공하고자 하는 하상의 토사층에 침하시키는 공정과, 케이슨 내부의 토사층을 제거하여 케이슨이 지반에 이르도록 한 후 케이슨이 닿는 지반에 복수개의 파일을 설치하는 공정과, 복수개의 파일이 시공된 지반에 레벨링콘크리트를 타설 양생하는 공정과, 요입부에 수밀튜브를 설치하고 보호판을 하강시킨 후 수밀튜브에 물 또는 공기를 주입 팽창시켜 외수유입을 차단시키는 공정과, 케이슨 내부의 물을 배수하는 공정과, 교각기초의 하단에 돌기부(key)가 형성되도록 케이슨 내부의 지반을 굴착하고 굴착된 지반에 교각기초와 교각을 시공하는 공정과, 케이슨의 내부 하측에 세굴방지공을 설치한 후 케이슨을 철거하는 공정과, 교각기초 주변에 토사층을 원상복구하는 공정으로 됨을 특징으로 한다.In addition, in the known method of installing a caisson on a bed, draining the water therein, and constructing a foundation or a pier in a dry state, the soil layer of the bed is flattened, and the caisson assembled on land is based on a pier. The process of submerging the soil layer of the lower layer to be constructed, the process of installing a plurality of piles on the ground where the caissons touch after removing the soil layer inside the caisson to reach the ground, Process of pouring leveling concrete, installing watertight tube at the inlet, lowering the protective plate, and injecting and expanding water or air into the watertight tube to block external water inflow; and draining the water inside the caisson; Excavate the ground inside the caisson to form a key at the bottom of the pier foundation, and construct the pier foundation and pier on the excavated ground. After installing the scour prevention hole to the process and, inside the lower side of the caisson it is characterized in that the step of clean up step, tosacheung around the pier foundation for dismantling the caisson.
이에 따라 본 발명은 케이슨의 설치 및 구조물의 시공시 토사층과 지반의 최소면적만을 굴착하고, 케이슨 이외의 다른 시설물을 설치할 필요가 없으므로, 공기가 대폭적으로 단축되고 비용이 절감되며, 하상의 자연환경에 손상이 최소화되는 등의 유용한 효과가 있다.
Accordingly, the present invention excavates only the minimum area of the soil layer and the ground when installing the caisson and constructs the structure, and does not need to install other facilities other than the caisson, so that the air is greatly shortened and the cost is reduced, There are useful effects, such as minimizing damage.
Description
도 1은 종래 교각시공용 케이슨을 이용한 교각의 시공과정을 도시한 설명도.1 is an explanatory diagram showing a construction process of a pier using a conventional caisson for pier construction.
도 2는 본 발명에 의한 교각시공용 케이슨을 도시한 구성도.Figure 2 is a block diagram showing a caisson for bridge construction according to the present invention.
도 3은 본 발명에 의한 교각시공용 케이슨의 요부 사시도.Figure 3 is a perspective view of the main portion of the caisson for pier construction according to the present invention.
도 4 a) 내지 g)는 본 발명에 의한 교각시공용 키이슨을 이용한 수중고각의 시공 공정을 도시한 설명도.
Figure 4a) to g) is an explanatory view showing the construction process of the underwater height using the piercing kinson according to the present invention.
*도면의 주요 부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *
10 : 케이슨 11 : 패널 12 : 부력탱크10: caisson 11: panel 12: buoyancy tank
13 : 경사면 14 : 요입부 15 : 리브13
16 : 보호판 17 : 장공 18 : 볼트16: shield 17: long 18: bolt
19 : 수밀튜브 20 : 교각기초 21 : 교각19: watertight tube 20: bridge foundation 21: bridge
22 : 토사층 23 : 지반 24 : 파일22: soil layer 23: ground 24: file
25 : 레벨링콘크리트 26 : 세굴방지공 27 : 돌기부
25 leveling
본 발명은 교각시공용 케이슨 및 이를 이용한 수중 구조물의 시공방법에 관한 것으로, 특히 수밀케이션을 하상에 설치하고 그 내부의 물을 배수한 건식 상태에서 교각의 기초나 교각을 시공하는 교각시공용 케이슨 및 이를 이용한 수중 구조물의 시공방법에 관한 것이다.The present invention relates to a pier construction caisson and a method of construction of an underwater structure using the same, in particular, pier construction caisson for installing the foundation or piers in the dry state in which the water installation is installed on the bottom and drained the water therein and It relates to a construction method of the underwater structure using the same.
주지하는 바와 같이 하상에 시공되는 교량은 하상 지반에 시공된 교각기초에 교각이 시공되고, 상기 교각에 교량의 상부구조를 시공하여 되는 것이며, 교각기초는 지반에 따라 말뚝기초 또는 직접기초로 시공되는 것으로, 이러한 교각기초의 공사방법은 대부분의 작업이 수중에서 이루어지므로 공사가 어렵고 정밀한 시공이 곤란하며 공기가 오래 걸린다는 단점이 있다.As is well known, the bridges constructed on the riverbed are constructed by the piers on the bridge foundations constructed on the river bed, and the superstructures of the bridges are constructed on the bridges, and the bridge foundations are constructed on the basis of piles or direct foundations. As such, the construction method of the bridge foundation has the disadvantage that the construction is difficult, precise construction is difficult and takes a long time because most of the work is done underwater.
이러한 문제로 인하여 본 출원인이 수중에 조립식 구조물을 설치하고 그 내부를 건식상태로 한 후 교각기초 및 교각을 시공 또는 보수 보강할 수 있는 케이슨과 이를 이용한 시공방법을 특허등록 제0366252호(명칭; 교각보수용 케이션) 및 특허등록 제0368604호(명칭; 교각보수용 수밀케이션) 외 다수의 발명으로 제안한바 있으며, 이를 첨부한 도면 도 1로 도시하였다.Due to these problems, the applicant has installed a prefabricated structure in the water, and the interior of the building is in a dry state, and the caisson and construction method using the same can be constructed or repaired and reinforced foundations and piers. Repair applications) and patent registration No. 0368604 (name; watertight repair for pier) has been proposed as a number of invention, it is shown in Figure 1 attached.
이에 의하면 케이슨(100)은 복수개의 패널(101)을 원통 또는 사각통 형태가 되도록 서로 결합시켜서 되는 것으로, 상기 복수개의 패널(101) 중 최 하단에 위치되는 패널(101)의 하단에 수밀튜브(102)가 설치되고, 아울러 상기 패널(101)에 결 합되어 하방으로 승, 하강되며 수밀튜브(102)를 보호하는 보호판(103)이 형성된 것이며, 이러한 케이슨(100)을 하상에 설치하고, 수밀튜브(102)를 팽창시킴으로써 케이슨(100) 내부로 외수가 유입되는 것을 차단한 후, 상기 케이슨(100) 내부의 물을 배수하여 건식상태가 되도록 한 다음, 작업자가 진입하여 교각(104)을 신설 또는 보수 보강하는 것이다.According to this, the
그러나 이러한 케이슨(100)을 하상에 설치할 경우 상기 케이슨(100)의 안정적으로 설치와 효과적인 차수를 위하여 상기 케이슨(100)을 설치하기 전 별도의 가시설을 설치하여야 되므로 하상의 퇴적층(105)과 지반(106)의 굴착범위가 넓어지게 됨은 물론, 토사의 유실을 방지하기 위한 시설을 설치하여야 되는 등 공기의 지연과 굴착면적의 확장 및 토사유실로 인한 하상의 자연환경이 손상되는 등의 문제가 있다.
However, when the
본 발명의 목적은 상기와 같은 종래의 문제를 감안하여 하상 구조물의 시공시 최소면적만을 굴착하여 시공할 수 있도록 함으로써, 공기가 단축되고 하상 자연환경의 손상을 최소화하는 교각시공용 케이슨 및 이를 이용한 수중 구조물의 시공방법을 제공함에 있다.
The object of the present invention is to allow construction by drilling only the minimum area during construction of the riverbed structure in view of the conventional problems as described above, pier construction caisson and underwater using the same to shorten the air and minimize damage to the riverbed natural environment To provide a construction method of the structure.
이러한 목적을 달성하기 위하여 본 발명은 내부에 부력탱크를 갖는 복수개의 패널이 결합되며 최 하측에 위치되는 패널의 하단에 수밀 수단이 구비된 공지의 케이슨에 있어서, 최 하측에 설치되는 패널의 하단에 경사면을 형성함과 아울러 수밀튜브가 설치되는 요입부가 형성된 교각시공용 케이슨을 제안한다.In order to achieve the above object, the present invention provides a well-known caisson having a watertight means at the bottom of the panel which is coupled to a plurality of panels having a buoyancy tank therein and is located at the bottom of the panel, which is installed at the bottom of the panel. We propose a caisson for pier construction, in which a concave part is formed to form a slope and a watertight tube is installed.
또한, 케이슨을 하상에 설치하고, 그 내부의 물을 배수한 후 건식상태에서 교각기초나 교각을 시공하는 공지의 방법에 있어서, 하상의 토사층을 평탄하게 하고 육상에서 조립된 케이슨을 교각기초 또는 교각을 시공하고자 하는 하상의 토사층에 침하시키는 공정과, 케이슨 내부의 토사층을 제거하여 케이슨이 지반에 이르도록 한 후 케이슨이 닿는 지반에 복수개의 파일을 설치하는 공정과, 복수개의 파일이 시공된 지반에 레벨링콘크리트를 타설 양생하는 공정과, 요입부에 수밀튜브를 설치하고 보호판을 하강시킨 후 수밀튜브에 물 또는 공기를 주입 팽창시켜 외수유입을 차단시키는 공정과, 케이슨 내부의 물을 배수하는 공정과, 교각기초의 하단에 돌기부(key)가 형성되도록 케이슨 내부의 지반을 굴착하고 굴착된 지반에 교각기초와 교각을 시공하는 공정과, 케이슨의 내부 하측에 세굴방지공을 설치하고 케이슨을 철거하는 공정과, 교각기초 주변에 토사층을 원상복구하는 공정으로 됨을 특징으로 한다.In addition, in the known method of installing a caisson on a bed, draining the water therein, and constructing a foundation or a pier in a dry state, the soil layer of the bed is flattened, and the caisson assembled on land is based on a pier. The process of submerging the soil layer of the lower layer to be constructed, the process of installing a plurality of piles on the ground where the caissons touch after removing the soil layer inside the caisson to reach the ground, Process of pouring leveling concrete, installing watertight tube at the inlet, lowering the protective plate, and injecting and expanding water or air into the watertight tube to block external water inflow; and draining the water inside the caisson; Excavate the ground inside the caisson to form a key at the bottom of the pier foundation, and construct the pier foundation and pier on the excavated ground. And in that the process characterized by the step of installing an anti-scour hole in the lower inside of the caisson and a circle and the step of dismantling the caisson, tosacheung around the pier foundation repair.
이에 따라 본 발명은 퇴적층과 지반을 최소면적만 굴착하고, 케이슨 설치를 위한 별도의 가시설이나 토사유실방지를 위한 시설을 설치하지 않아도 되어 공기가 단축되고 비용이 절감되며, 하상의 환경 손상이 최소화된다. Accordingly, the present invention excavates only the minimum area of the sedimentary layer and the ground, and does not need to install a separate temporary facility for caisson installation or a facility for preventing soil loss, which shortens air and reduces costs, and minimizes environmental damage to the riverbed. .
상기와 같은 본 발명의 구성 및 작용을 첨부한 도면에 의거 상세히 설명하면 다음과 같다.Referring to the configuration and operation of the present invention as described above in detail as follows.
도 2는 본 발명에 의한 교각시공용 케이슨을 도시한 구성도이고, 도 3은 본 발명에 의한 교각시공용 케이슨의 요부 사시도이다.Figure 2 is a block diagram showing a caisson for pier construction according to the present invention, Figure 3 is a perspective view of the main portion of the caisson for pier construction according to the present invention.
본 발명은 내부에 부력탱크(12)를 갖는 복수개의 패널(11)을 결합시켜 원통형태 또는 사각형태 등의 케이슨(10)을 조립하는 것으로, 상기 복수개의 패널(11) 중 최 하측에 결합되는 패널(11)의 하단에 쐐기 또는 "V" 형태로 되는 경사면(13)을 형성하고, 상기 경사면(13)의 측부에 수밀튜브(19)가 설치되는 요입부(14)를 형성하며, 패널(11)의 내벽에 수밀튜브(19)를 보호하는 보호판(16)을 설치한다.The present invention is to assemble the
이때, 상기 보호판(16)은 장공(17)이 형성된 것으로, 볼트(18)가 상기 장공(17)에 삽입 관동되어 패널(11)의 내벽에 체결됨으로써 보호판(16)이 패널(11)에 설치되도록 하며, 아울러 상기 경사면(13)의 내부에 보강리브(15)를 형성한다.At this time, the
이와 같이 구성된 케이슨(10)은 하단의 경사면(13)에 의하여 케이슨(10)의 자중 침하가 가능하게 되는 것으로, 이러한 케이슨(10)을 설치하고 수중 구조물을 시공하는 방법을 설명하면 다음과 같다.The
첨부된 도면 도 4 a) 내지 h)는 본 발명에 의한 교각시공용 케이슨을 이용한 수중교각의 시공 공정을 도시한 설명도이다.4a) to (h) are explanatory views showing a construction process of underwater piers using the caisson for piers according to the present invention.
본 발명에 의한 방법은 먼저, 케이슨(10)이 설치될 하상의 토사층(22)을 평탄하게 하고 육상에서 조립된 케이슨(10)을 수상에서 상기 토사층(22) 위에 이르도록 침하시킨 다음, 상기 케이슨(10) 내부의 토사층(22)을 제거하여 케이슨(10)이 지반(23)에 이르도록 한다.The method according to the present invention first flattens the
이때, 상기 케이슨(10)의 하단에 경사면(13)이 형성되었으므로, 케이슨(10) 내부의 토사층(22)만을 제거하더라도 상기 케이슨(10)이 자중에 의하여 침하하게 되는 것이며, 상기 케이슨(10)의 하중이 증가되도록 부력탱크(12) 내부에 물을 주입하여 침하를 촉진시킨다.At this time, since the
아울러 케이슨(10)의 하단이 닿는 지반(23)에 복수개의 파일(24)을 설치한 후, 레벨링콘크리트(25)를 타설 양생하여 파일(24)과 레벨링콘크리트(25)가 견고하게 부착되도록 하고, 이어서 요입부(14)에 수밀튜브(19)를 설치한 후 보호판(16)을 하강시킨 다음, 수밀튜브(19)에 물 또는 공기를 주입 팽창시켜 레벨링콘크리트(25)에 압착시킴으로써 케이슨(10) 내부로 외수가 유입도는 것을 차단시킨다.In addition, after the plurality of
상기 보호판(16)은 패널(11)의 내벽에 체결된 볼트(18)를 풀고 보호판(16)을 하강시킨 후 다시 볼트(18)를 조여 고정시키는 것이며, 상기 보호판(16)은 장공(17)의 길이만큼 승, 하강되는 것이다.The
이와 같이 한 후 펌프를 이용하여 케이슨(10) 내부의 물을 배수하여 건식상태가 되도록 한 다음, 건식상태에서 케이슨(10) 내부의 지반(23)을 굴착하되, 중앙부분을 가장자리 보다 더욱 깊게 굴착하고, 이어서 굴착된 지반(23)에 교각기초(20)와 교각(21)을 시공한다.After doing this, the water inside the
이때, 상기 지반(23)의 깊게 굴착된 중앙부분과 대응되는 교각기초(20)의 하단 중앙에는 돌기부(27)가 형성되고, 이러한 돌기부(27)는 지진에 대한 지지력을 보강하기 위한 것으로, 지진이나 기타 지각변동 등의 현상 발생시 상기 돌기부(27) 에 의하여 교각(21)의 위치가 이동되거나 기울어짐이 방지되는 것이며, 상기 지반(23) 굴착과 교각기초(20) 및 교각(21)의 시공은 케이슨(10)의 내부가 건식상태이므로 작업자가 케이슨(10) 내부에 진입하여 공사를 진행할 수 있는 것이다.In this case, a
아울러 교각기초(20)와 교각(21)의 시공이 완료되면 하상세굴의 방지를 위하여 케이슨(10)의 내부 하측에 연결식 세굴방지공(26)을 설치하고, 부력탱크(12)를 이용 수상에서 케이슨(10)을 들어올려 철거한 후, 교각기초(20) 주변에 토사층(22)을 복구하여 공사를 완료한다.In addition, when the construction of the
즉, 상기 케이슨(10)의 철거는 부력탱크(12)에 주입된 물을 배수하고 공기를 주입하여 부력이 발생하도록 함과 아울러 수상의 고압펌프(27)와 연결되는 노즐(26)을 상기 케이슨(10)의 하측에 설치하고, 상기 고압펌프(26)를 이용하여 노즐(26)에서 물 또는 공기가 분사되도록 함으로써 마찰력이 감소되어 케이슨(10)의 부상이 더욱 촉진되는 것이다.That is, the dismantling of the
이와 같이 본 발명은 케이슨(10) 주변의 퇴적층(22)과 지반(23)을 넓게 굴착하지 않고, 상기 케이슨(10) 내부의 퇴적층(22)과 지반(23) 만을 굴착하여 시공할 수 있으므로, 상기 케이슨(10) 설치를 위한 별도의 가시설이나 토사유실 방지를 위한 시설이 불필요하게 되며, 따라서 공기의 대폭적인 단축과 비용의 절감이 가능하게 되는 것이다.As described above, the present invention can excavate only the
또한, 케이슨(10)의 설치와 해체시 수상에서 균형을 조절할 수 있음과 아울러 자중과 부력을 적절히 이용함으로써, 기울어짐을 방지할 수 있으므로 안정적인 설치와 해체가 가능하게 된다.
In addition, by adjusting the balance in the water during the installation and disassembly of the
아울러 본 발명은 수중 구조물의 신설은 물론, 시공된 기존 구조물의 보수 보강시에도 적용 가능한 것이며, 이러한 보수 보강 공사에 있어서도 대폭적인 공기의 단축과 비용절감이 가능한 것이다.
In addition, the present invention can be applied to the renovation of existing structures, as well as the construction of underwater structures, and in the repair and reinforcement work, it is possible to drastically shorten the air and reduce costs.
상기한 바와 같이 본 발명은 케이슨의 설치 및 구조물의 시공시 토사층과 지반의 최소면적만을 굴착하고, 케이슨 이외의 다른 시설물을 설치할 필요가 없으므로, 공기가 대폭적으로 단축되고 비용이 절감되며, 하상의 자연환경에 손상이 최소화되는 등의 유용한 효과가 있다.
As described above, the present invention excavates only the minimum area of the soil layer and the ground during the installation and construction of the caisson, and does not need to install other facilities other than the caisson, so that the air is drastically shortened and the cost is reduced. There are useful effects, such as minimizing damage to the environment.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020030053439A KR100647488B1 (en) | 2003-08-01 | 2003-08-01 | Caisson for Pier Construction and Construction Method of Underwater Structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020030053439A KR100647488B1 (en) | 2003-08-01 | 2003-08-01 | Caisson for Pier Construction and Construction Method of Underwater Structure |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR20-2003-0026502U Division KR200334754Y1 (en) | 2003-08-18 | 2003-08-18 | Caisson for Pier Construction |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20050019940A KR20050019940A (en) | 2005-03-04 |
KR100647488B1 true KR100647488B1 (en) | 2006-12-04 |
Family
ID=37228923
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020030053439A KR100647488B1 (en) | 2003-08-01 | 2003-08-01 | Caisson for Pier Construction and Construction Method of Underwater Structure |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100647488B1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101278586B1 (en) | 2012-08-08 | 2013-06-25 | 이석찬 | Intake tower renovation process of the work space |
KR101752856B1 (en) * | 2015-09-23 | 2017-07-11 | 삼보이엔씨 주식회사 | Tank structure for allowing dry work and method for installation of the same |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100854338B1 (en) * | 2008-04-02 | 2008-08-26 | 최승희 | Construction structure of open caisson cofferdam using holding type sheet pile |
KR101031571B1 (en) * | 2009-05-28 | 2011-04-27 | 정석으뜸기술(주) | Method for constructing seperating type caisson |
-
2003
- 2003-08-01 KR KR1020030053439A patent/KR100647488B1/en not_active IP Right Cessation
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101278586B1 (en) | 2012-08-08 | 2013-06-25 | 이석찬 | Intake tower renovation process of the work space |
KR101752856B1 (en) * | 2015-09-23 | 2017-07-11 | 삼보이엔씨 주식회사 | Tank structure for allowing dry work and method for installation of the same |
Also Published As
Publication number | Publication date |
---|---|
KR20050019940A (en) | 2005-03-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20020004353A (en) | Reinforcing Construction Method of Foundation for Pier and It's Reinforced Structure Thereof | |
KR20070090733A (en) | Waterproof open caisson assembly and concrete foundation construction method using the same | |
KR100617949B1 (en) | Pile Groups Construction Method of Weak Bedding Bone Using Caission | |
CN110206039B (en) | Construction method of Larsen steel sheet pile in pit under complex geological conditions | |
KR101173029B1 (en) | Under Water Structure Building and Maintenance and Reinforce Method Using Water Tightened Caisson | |
KR20010096389A (en) | Construction Method of Direct Foundation for using Caisson | |
CA2673876A1 (en) | Shoring free excavation and basement construction apparatus and method | |
KR100647488B1 (en) | Caisson for Pier Construction and Construction Method of Underwater Structure | |
CN110080234A (en) | A method of it is excavated in the secondary central island of deep foundation pit of soft soil foundation | |
KR19990078994A (en) | Method to construct a structure on soft soil and the structure thereof | |
KR101117924B1 (en) | Composite type steel temporary construction and construction method thereof | |
KR200334754Y1 (en) | Caisson for Pier Construction | |
KR100609732B1 (en) | Watertight Caisson for Underwater Pier Construction Work and Dry Construction Method of Underwater Pier Foundation Work Using Thereof | |
KR100621410B1 (en) | Dry Construction Method of Underwater Structure Using Watertight Caisson | |
KR100556302B1 (en) | Caisson Installed Support Means and Construction Method of Underwater Structure Using It | |
KR200224758Y1 (en) | Structure of caisson soil protection four concret caisson | |
KR100592397B1 (en) | storey spacing support ssoldier pile soil retaining wall | |
KR200240016Y1 (en) | Structure of reclamation type's for dection soil | |
KR100637899B1 (en) | Pier foundation temporarily structure and method for constructing it | |
KR100493516B1 (en) | Micro pile and assembly foundation reinforcement structure member and its method for pier | |
JP3728659B2 (en) | Basement extension method | |
KR200291370Y1 (en) | Concrete caisson structure for earth and sand guard of pier's basis | |
RU2808966C1 (en) | Method for strengthening bridge supports | |
KR200357965Y1 (en) | Caisson Installed Support Means | |
CN216920366U (en) | One-level ground closes on to construct foundation ditch support of structure and groundwater control structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
N231 | Notification of change of applicant | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
N231 | Notification of change of applicant | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20121113 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20131113 Year of fee payment: 8 |
|
LAPS | Lapse due to unpaid annual fee |