KR100615567B1 - A construction method of a floor and a wall for yellow soil room - Google Patents
A construction method of a floor and a wall for yellow soil room Download PDFInfo
- Publication number
- KR100615567B1 KR100615567B1 KR1020040085220A KR20040085220A KR100615567B1 KR 100615567 B1 KR100615567 B1 KR 100615567B1 KR 1020040085220 A KR1020040085220 A KR 1020040085220A KR 20040085220 A KR20040085220 A KR 20040085220A KR 100615567 B1 KR100615567 B1 KR 100615567B1
- Authority
- KR
- South Korea
- Prior art keywords
- ocher
- floor
- wall
- construction
- gravel
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/02—Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
- E04B1/12—Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements the elements consisting of other material
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/70—Drying or keeping dry, e.g. by air vents
- E04B1/7069—Drying or keeping dry, e.g. by air vents by ventilating
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/84—Walls made by casting, pouring, or tamping in situ
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C2/00—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
- E04C2/02—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
- E04C2/26—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials composed of materials covered by two or more of groups E04C2/04, E04C2/08, E04C2/10 or of materials covered by one of these groups with a material not specified in one of the groups
- E04C2/284—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials composed of materials covered by two or more of groups E04C2/04, E04C2/08, E04C2/10 or of materials covered by one of these groups with a material not specified in one of the groups at least one of the materials being insulating
Abstract
본 발명은 황토방 바닥 및 벽면 시공방법에 관한 것으로, 콘크리트 바닥(1) 상부면에 수맥을 차단하기 위하여 수맥차단층(2)이 형성되고, 상기 수맥차단층(2)의 상부면에 게르마늄 자갈과 옥돌 자갈 및 황토 자갈을 도포하며, 상기 자갈층(3)의 상부면에 바닥 가열을 위한 보일러 엑셀파이프(4)를 설치하고, 상기 보일러 엑셀파이프(4) 사이에 옥돌가루와 황토모래를 투입하여 보일러 엑셀파이프(4)를 덮어준 상태에서 그 상부면에 알루미늄 시트 및 부직포(5)를 각각 부착설치하며, 상기 바닥기초 면에 황토판(6)을 다수 올려 고정설치하고, 상기 황토판(6)의 상부면에 부직포(5)와 천연장판(7)을 깔아 시공한 후 천연페인트 또는 수용성왁스를 이용하여 바닥을 마감함으로써 황토방의 바닥을 시공하는 한편, 나무를 일정한 두께와 크기로 절단한 후 격자형의 목재 프레임(8)을 제작하여 콘크리트 벽체(9)에 고정설치하고, 상기 목재 프레임(8)에 황토판(6)을 다수 부착설치하여 황토방의 벽면을 시공하는 것으로서, 상기 황토방의 바닥과 벽면이 황토판으로 시공됨으로써 그 시공성과 경제성 및 작업성 등을 향상시킬 수 있고, 상기 황토판이 콘크리트 바닥과 벽체에 일정 간격을 두고 설치되기 때문에 콘크리트의 독성을 차단할 수 있다.The present invention relates to an ocher floor and wall construction method, the water vein blocking layer (2) is formed to block the vein on the concrete floor (1), the upper surface of the water vein blocking layer (2) and the germanium gravel and Apply jade gravel and ocher gravel, and install a boiler excel pipe (4) for heating the floor on the upper surface of the gravel layer (3), and put jade stone and ocher sand between the boiler excel pipe (4) The aluminum pipe and the nonwoven fabric 5 are attached to the upper surface of the state in which the Excel pipe 4 is covered, and a plurality of ocher plates 6 are fixedly mounted on the bottom foundation surface, and the ocher plate 6 is installed. Lay the nonwoven fabric (5) and the natural sheet (7) on the upper surface of the floor, and then finish the floor by using natural paint or water-soluble wax. The neck of a brother The frame 8 is manufactured and fixed to the concrete wall 9, and a plurality of ocher plates 6 are attached to the wood frame 8 to install the wall surface of the ocher room, and the bottom and the wall surface of the ocher room are ocher. The construction of the plate can improve the workability, economical efficiency and workability, etc., and since the ocher plate is installed at a certain interval on the concrete floor and the wall can block the toxicity of the concrete.
황토방, 황토판, 바닥, 벽면Ocher, ocher, floor, wall
Description
도 1은 본 발명에 따른 황토방 바닥의 시공순서를 나타낸 흐름도,1 is a flow chart showing the construction sequence of the bottom of the loess according to the invention,
도 2는 본 발명에 따른 황토방 벽면의 시공순서를 나타낸 흐름도,Figure 2 is a flow chart showing the construction sequence of the ocher wall in accordance with the present invention,
도 3은 본 발명에 따른 황토방 바닥의 시공상태를 나타낸 상태도,Figure 3 is a state diagram showing the construction state of the bottom of the loess according to the invention,
도 4는 본 발명에 따른 황토방 벽면의 시공상태를 나타낸 사시도이다.Figure 4 is a perspective view showing the construction state of the ocher wall surface according to the present invention.
* 도면의 주요 부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings
1 : 콘크리트 바닥 2 : 수맥차단층1: concrete floor 2: water vein blocking layer
3 : 자갈층 4 : 보일러 엑셀파이프3: gravel layer 4: boiler excel pipe
5 : 부직포 6 : 황토판5: nonwoven fabric 6: ocher plate
7 : 천연장판 8 : 목재 프레임7: natural sheet 8: wood frame
9 : 콘크리트 벽체9: concrete wall
본 발명은 황토를 이용한 황토방에 관한 것으로, 특히 황토방을 이루는 바닥과 벽면을 일정 규격을 갖는 황토패널로 간편하게 시공함으로써 이용자의 건강증진 을 도모함과 더불어 시공상의 편의를 줄 수 있도록 한 황토방 바닥 및 벽면 시공방법에 관한 것이다.The present invention relates to an ocher room using ocher, and in particular, an ocher room floor and wall construction to facilitate the construction of the user and to provide convenience for construction by easily constructing the floor and wall forming the ocher room with an ocher panel having a predetermined standard. It is about a method.
일반적으로 현재 시공되고 있는 주택의 바닥이나 벽면은 대부분 콘크리트로 이루어지는 바, 상기 콘크리트로 이루어진 주택의 바닥 기초와 벽면에 시멘트를 이용하여 미장을 하게 되는 것이다.In general, the floor or wall surface of the house currently being constructed is mostly made of concrete, so that the plaster is used to cement the floor base and wall of the house made of concrete.
그런데, 상기 콘크리트와 시멘트의 경우 인체에 해로울 뿐만아니라 건강증진에 악영향을 끼치게 되고, 아울러 주거용 주택의 건축에만 사용할 수 밖에 없으므로 사용 목적상 한계가 있는 것이다.By the way, the concrete and cement is not only harmful to the human body, but also adversely affect health promotion, and also has a limitation in use because it can only be used for construction of residential houses.
한편, 근래에는 흙집, 특히 황토방은 황토에서 발산되는 원적외선이 인체의 신진대사, 혈액순환 등을 촉진시킨다는 것에 기인한 것으로, 통상 바닥재와 벽체를 황토로 형성하고, 또한 이들 내부에 히팅수단을 구비하여 히팅수단의 열기에 의해 사용자가 황토방 내에서 충분히 땀을 배출시킬 수 있도록 한 것이다.On the other hand, in recent years, the earth house, especially the ocher room, is due to the fact that far infrared rays emitted from the ocher promote metabolism, blood circulation, etc. of the human body, and usually form flooring and walls with ocher, and also have heating means therein. The heat of the heating means is to allow the user to discharge the sweat sufficiently in the ocher.
즉, 상기와 같은 황토방은 그 제작시 바닥 또는 벽면에 온열을 위한 히팅장치를 설치하고, 그 위에 반죽된 황토를 발라줌으로써 황토방의 바닥과 벽면을 황토로 만들어 주는 것이다.In other words, the ocher room as described above is to make the bottom and wall surface of the ocher room by applying a loess for heating on the floor or wall surface when the production, and applying the kneaded ocher on it.
그런데, 상기와 같이 황토를 미장하여 황토방을 제작할 때 황토방이 작은 경우에는 제작시간이나 작업성이 크게 제한되지 않지만 대형의 황토방을 제작하는 경우에는 많은 양의 황토를 미장하여야 하기 때문에 제작시간이 오래 걸림과 더불어 작업성이 저하되는 문제가 있고, 상기 황토를 미장할 때 황토벽의 갈라짐 현상을 극복하기 위하여 황토에 화학적 첨가물을 희석하여 사용하기 때문에 황토의 찜질 효과를 극대화시키기 어렵다는 등의 문제가 있었다.By the way, when manufacturing the ocher room by plastering the ocher as described above, if the ocher room is small, the production time or workability is not greatly limited, but when producing a large ocher room, it takes a long time because the large amount of ocher should be plastered. In addition, there is a problem that the workability is deteriorated, and when the ocher is plastered, it is difficult to maximize the poultice effect of the loess because chemical additives are diluted in the loess to overcome the phenomenon of cracking of the ocher wall.
이에 본 발명은 상기한 바의 문제점을 해소하기 위해 안출된 것으로, 황토방을 이루는 바닥과 벽면을 일정 규격을 갖는 황토패널로 간편하게 시공함으로써 이용자의 건강증진을 도모함과 더불어 시공상의 편의를 줄 수 있도록 한 황토방 바닥 및 벽면 시공방법을 제공함에 그 목적이 있는 것이다.Accordingly, the present invention was devised to solve the above problems, and by simply constructing the floor and wall forming the ocher room with the ocher panel having a certain standard, it is possible to improve the health of the user and provide convenience for construction. It is an object of the present invention to provide an ocher floor and wall construction method.
상기한 바의 목적을 달성하기 위한 본 발명은, 콘크리트 바닥 상부면에 수맥을 차단하기 위하여 알루미늄 시트나 동판을 깔아주게 되는 수맥차단 시공;과, 상기 수맥차단층의 상부면에 원적외선 및 음이온을 발생시키는 게르마늄 자갈과 옥돌 자갈을 75-170mm 두께로 도포함과 아울러 황토 자갈을 25-30mm 두께로 도포하는 자갈도포 시공;과, 상기 자갈층의 상부면에 바닥 가열을 위한 간접 복사열 방식의 보일러 엑셀파이프를 설치하는 보일러 엑셀파이프 시공;과, 상기 보일러 엑셀파이프 사이에 옥돌가루와 황토모래를 투입하여 보일러 엑셀파이프를 덮어준 상태에서 그 상부면에 수맥차단과 습도조절을 위한 알루미늄 시트 및 부직포를 각각 부착설치하는 바닥기초 마감시공;과, 상기 바닥기초 면에 일정규격으로 절단됨과 아울러 20mm 정도의 두께를 갖는 황토판을 다수 올려 고정설치하는 황토판 시공; 및, 상기 황토판의 상부면에 부직포와 천연장판을 깔아 시공한 후, 천연페인트 또는 수용성왁스를 이용하여 바닥을 마감하는 바닥 마감시공;을 거쳐 황토방의 바닥이 시공되는 것이다.The present invention for achieving the above object, the construction of the water vein blocking the aluminum sheet or copper plate in order to block the vein on the concrete floor upper surface; and generating far infrared rays and negative ions on the upper surface of the vein blocking layer Coating gravel and jade gravel to 75-170mm thickness and applying ocher gravel to 25-30mm thickness; and, indirect radiant boiler excel pipe for bottom heating on the top surface of the gravel layer Boiler Excel pipe construction to be installed; and jade powder and ocher sand are put between the boiler Excel pipe and the aluminum sheet and nonwoven fabric for water vein blocking and humidity control are respectively attached and installed on the upper surface of the boiler Excel pipe while covering the boiler Excel pipe. Floor-based finishing construction; And, cut to a certain standard on the bottom surface and having a thickness of about 20mm Ocher plate construction for fixing and installing a number of ocher plates; And, after laying the non-woven fabric and natural sheet on the top surface of the ocher plate, the floor finishing construction to finish the floor using a natural paint or water-soluble wax; through the bottom of the ocher.
그리고, 소나무, 나왕, 향나무 중 하나를 택해 일정한 두께와 크기로 절단한 후 격자형의 목재 프레임을 제작하여 콘크리트 벽체에 고정설치하는 목재 프레임 시공;과, 상기 목재 프레임 사이에 유연성 공기 파이프를 설치하여 황토방 내부의 나쁜 공기를 외부로 배출시킬 수 있도록 한 공기 파이프 시공;과, 상기 목재 프레임이 이루는 공간에 벽면 가열을 위한 간접 복사열 방식의 전기 열선을 설치하는 히팅수단 시공;과, 상기 목재 프레임의 상부면에 수맥차단과 습도조절을 위한 알루미늄 시트 및 부직포를 각각 부착설치하는 벽면기초 마감시공;과, 상기 벽면기초 면에 일정규격으로 절단됨과 아울러 20mm 정도의 두께를 갖는 황토판을 다수 부착설치하는 황토판 시공; 및, 상기 황토판의 상부면에 부직포와 천연벽지를 부착한 후, 천연페인트 또는 수용성왁스를 이용하여 벽면을 마감하는 벽면 마감시공;을 거쳐 황토방의 벽면이 시공되는 것이다.And, by selecting one of the pine, wangwang, juniper and cut to a certain thickness and size, a wooden frame construction to produce a grid-shaped wooden frame and fixed to the concrete wall; And, install a flexible air pipe between the wooden frame Air pipe construction to allow the bad air inside the ocher room to be discharged to the outside; and Heating means for installing an indirect radiant electric heating wire for wall heating in the space formed by the wood frame; And, the top of the wood frame Wall foundation finishing construction for attaching and installing aluminum sheet and non-woven fabric for water vein blocking and humidity control on the surface, and ocher for cutting and installing a number of ocher plates having a thickness of about 20mm and being cut to a certain standard on the wall foundation surface. Plate construction; And, after attaching the non-woven fabric and the natural wallpaper on the upper surface of the ocher plate, the wall surface finishing to finish the wall surface using natural paint or water-soluble wax; through the wall surface of the ocher.
따라서, 상기와 같이 황토방의 바닥과 벽면이 황토판으로 시공됨으로써 그 시공성과 경제성 및 작업성 등을 향상시킬 수 있고, 상기 황토판이 콘크리트 바닥과 벽체에 일정 간격을 두고 설치되기 때문에 콘크리트의 독성을 차단함과 동시에 황토방에서 몸에 이로운 원적외선과 음이온이 다량 방출되며, 이에 따라 황토방 이용자의 건강증진을 도모할 뿐만아니라 황토판을 주택이나 건물에 적용시켜 콘크리트로 인한 새집증후군을 없애줄 수 있는 것이다.Therefore, as described above, the bottom and the wall surface of the ocher room can be improved by constructing the ocher plate to improve its workability, economical efficiency and workability, and block the toxicity of concrete because the ocher is installed at a predetermined interval on the concrete floor and the wall. At the same time, large amounts of far-infrared rays and negative ions that are beneficial to the body are released from the ocher room, thereby promoting the health of the ocher room user and applying ocher plates to houses or buildings to eliminate the sick house syndrome caused by concrete.
이하 본 발명을 첨부된 예시도면을 참조하여 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.
도 1은 본 발명에 따른 황토방 바닥의 시공순서를 도시한 흐름도이고, 도 2는 본 발명에 따른 황토방 벽면의 시공순서를 도시한 흐름도이며, 도 3은 본 발명 에 따른 황토방 바닥의 시공상태를 도시한 상태도이고, 도 4는 본 발명에 따른 황토방 벽면의 시공상태를 도시한 사시도이다.1 is a flow chart showing the construction order of the ocher room floor according to the present invention, Figure 2 is a flow chart showing the construction order of the ocher room wall surface according to the present invention, Figure 3 shows the construction state of the bottom of the ocher room according to the present invention. Figure 4 is a state diagram, Figure 4 is a perspective view showing the construction state of the ocher room wall surface according to the present invention.
상기한 도면들에 의해 황토방의 바닥 및 벽면 시공방법을 설명하면, 콘크리트 바닥(1) 상부면에 수맥을 차단하기 위하여 알루미늄 시트나 동판을 깔아주고, 상기 수맥차단층(2)의 상부면에 원적외선 및 음이온을 발생시키는 게르마늄 자갈과 옥돌 자갈을 75-170mm 두께로 도포함과 아울러 황토 자갈을 25-30mm 두께로 도포하며, 상기 자갈층(3)의 상부면에 바닥 가열을 위한 간접 복사열 방식의 보일러 엑셀파이프(4)를 설치하고, 상기 보일러 엑셀파이프(4) 사이에 옥돌가루와 황토모래를 투입하여 보일러 엑셀파이프(4)를 덮어준 상태에서 그 상부면에 수맥차단과 습도조절을 위한 알루미늄 시트 및 부직포(5)를 각각 부착설치하며, 상기 바닥기초 면에 일정규격으로 절단됨과 아울러 20mm 정도의 두께를 갖는 황토판(6)을 다수 올려 고정설치하고, 상기 황토판(6)의 상부면에 부직포(5)와 천연장판(7)을 깔아 시공한 후 천연페인트 또는 수용성왁스를 이용하여 바닥을 마감함으로써 황토방의 바닥을 시공하는 한편, 소나무, 나왕, 향나무 중 하나를 택해 일정한 두께와 크기로 절단한 후 격자형의 목재 프레임(8)을 제작하여 콘크리트 벽체(9)에 고정설치하고, 상기 목재 프레임(8)에 황토판(6)을 다수 부착설치하여 황토방의 벽면을 시공하는 것이다.Referring to the floor and wall construction method of the ocher room by the above drawings, to cover the vein on the concrete floor (1) to lay the aluminum sheet or copper plate, far infrared rays on the upper surface of the vein blocking layer (2) And coating 75-170mm thick germanium gravel and jade gravel generating anion and applying ocher gravel at a thickness of 25-30mm, and indirect radiant boiler excel for bottom heating on the top surface of the gravel layer (3). An aluminum sheet for installing water pipes and blocking water veins and humidity control on the upper surface of the boiler excel
여기서, 상기 황토방 바닥 및 벽면 시공방법이 갖는 특징은 바닥의 기초와 벽체의 기초를 이루는 콘크리트와 일정간격을 두고 다수 황토판(6)을 설치하여 황토방의 바닥 및 벽면을 이루도록 된 것에 있는 바, 상기 콘크리트와 황토판(6) 사 이에 여러 물체를 채워 시공하기 때문에 콘크리트의 독성을 차단하면서 몸에 이로운 음이온이나 원적외선의 방출량을 극대화시키고, 또한 상기 황토판(6)으로 황토방의 바닥 및 벽면을 간편하게 시공함으로써 그 시공성을 극대화시킬 수 있는 것이다.Here, the features of the ocher floor and the wall surface construction method is to install a plurality of ocher plate (6) at a certain interval with the concrete forming the base of the floor and the wall base to form the bottom and wall surface of the ocher room, It is constructed by filling various objects between concrete and ocher plate (6) to block the toxicity of concrete while maximizing the amount of anion and far infrared rays that are beneficial to the body. Also, the ocher plate (6) allows easy construction of the bottom and wall of ocher room. By doing so, the constructability can be maximized.
즉, 상기 황토방의 바닥 시공방법 및 그 구조는 도 1과 도 3을 통해 단계별로 보다 상세히 설명하면 다음과 같다.That is, the floor construction method and its structure of the ocher room are described in more detail step by step through FIGS. 1 and 3 as follows.
수맥차단 시공; 콘크리트 바닥(1) 상부면에 수맥을 차단하기 위하여 알루미늄 시트나 동판을 깔아주게 되는 과정이다.Water vein blocking construction; It is a process of laying an aluminum sheet or copper plate to block the vein on the upper surface of the concrete floor (1).
자갈도포 시공; 상기 수맥차단층(2)의 상부면에 원적외선 및 음이온을 발생시키는 게르마늄 자갈과 옥돌 자갈을 75-170mm 두께로 도포함과 아울러 황토 자갈을 25-30mm 두께로 도포하는 것으로, 상기 자갈들이 축열작용을 하여 복사열을 냄과 더불어 원적외선 및 음이온을 방사함으로써 새집증후군에서 나타나는 나쁜 화학적 독성을 제거할 수 있는 것이다.Gravel coating construction; By coating germanium gravel and jade gravel to 75-170mm thickness and applying ocher gravel to 25-30mm thickness on the upper surface of the
보일러 엑셀파이프 시공; 상기 자갈층(3)의 상부면에 바닥 가열을 위한 간접 복사열 방식의 보일러 엑셀파이프(4)를 설치하는 것이다.Boiler excel pipe construction; On the upper surface of the gravel layer (3) is to install the boiler excel pipe (4) of indirect radiant heat for heating the floor.
바닥기초 마감시공; 상기 보일러 엑셀파이프(4) 사이에 옥돌가루와 황토모래를 투입하여 보일러 엑셀파이프(4)를 덮어준 상태에서 그 상부면에 수맥차단과 습도조절을 위한 알루미늄 시트 및 부직포(5)를 각각 부착설치하는 것으로, 상기 옥돌가루와 황토모래를 통하여 2차적으로 새집증후군에서 나타나는 포름알데히드를 제거할 수 있는 것이다.Floor foundation finishing; Put jade stone and ocher sand between the boiler excel pipe (4) in the state covered with the boiler excel pipe (4) attached to the aluminum sheet and non-woven fabric (5) for water vein blocking and humidity control respectively installed on the upper surface By doing so, it is possible to remove the formaldehyde secondary to the sick house syndrome through the jade stone and ocher sand.
황토판 시공; 상기 바닥기초 면에 일정규격으로 절단됨과 아울러 20mm 정도의 두께를 갖는 황토판(6)을 다수 올려 고정설치하는 것으로, 콘크리트에서 방출되는 모든 독성물질을 중화시킴과 아울러 방음 효과를 기대할 수 있는 것이다.Ocher plate construction; It is cut to a certain standard on the bottom foundation surface and is fixed by installing a number of
바닥 마감시공; 상기 황토판(6)의 상부면에 부직포(5)와 천연장판(7)을 깔아 시공한 후, 천연페인트 또는 수용성왁스를 이용하여 바닥에 때가 타는 것을 방지하도록 된 것이다.Floor finishing; After laying the
그리고, 상기 황토방의 벽면 시공방법 및 그 구조는 도 2와 도 4를 통해 단계별로 보다 상세히 설명하면 다음과 같다.And, the wall construction method and its structure of the ocher room will be described in more detail step by step through FIGS. 2 and 4 as follows.
목재 프레임 시공; 소나무, 나왕, 향나무 중 하나를 택해 일정한 두께와 크기로 절단한 후 격자형의 목재 프레임(8)을 제작하여 콘크리트 벽체(9)에 고정설치하는 과정이다.Construction of wooden frames; It is a process of selecting one of pine, wangwang, and juniper and cutting it to a certain thickness and size, and then making a
공기 파이프 시공; 상기 목재 프레임(8) 사이에 유연성 공기 파이프를 설치하여 황토방 내부의 나쁜 공기를 외부로 배출시킬 수 있도록 하는 과정이다.Air pipe construction; A process of installing a flexible air pipe between the wood frame (8) to discharge the bad air in the ocher room to the outside.
히팅수단 시공; 상기 목재 프레임(8)이 이루는 공간에 벽면 가열을 위한 간접 복사열 방식의 전기 열선을 설치하는 과정이다.Construction of heating means; It is a process of installing an indirect radiant electric heating wire for wall heating in the space formed by the wooden frame (8).
벽면기초 마감시공; 상기 목재 프레임(8)의 상부면에 수맥차단과 습도조절을 위한 알루미늄 시트 및 부직포를 각각 부착설치하는 과정이다.Wall foundation finishing; The upper surface of the wood frame (8) is a process of attaching and installing the aluminum sheet and non-woven fabric for water vein blocking and humidity control, respectively.
황토판 시공; 상기 벽면기초 면에 일정규격으로 절단됨과 아울러 20mm 정도의 두께를 갖는 황토판(6)을 다수 부착설치하는 과정이다.Ocher plate construction; It is a process of attaching and installing a plurality of
벽면 마감시공; 상기 황토판의 상부면에 부직포와 천연벽지를 부착한 후, 천 연페인트 또는 수용성왁스를 이용하여 벽면을 마감하도록 된 것이다.Wall finishing; After attaching the nonwoven fabric and the natural wall to the upper surface of the ocher plate, it is to finish the wall using a natural paint or water-soluble wax.
그러므로, 상기와 같이 시공되는 황토방의 경우 고압으로 압축된 황토판(6)을 이용하는 바, 황토방을 이루는 바닥과 벽면이 황토판(6)으로 시공됨으로써 황토의 이로운 기운이 사용자에게 직접 전달되고, 상기 황토판(6)이 콘크리트 바닥(1) 또는 벽체(9)와 일정간격을 두고 설치되기 때문에 콘크리트를 통한 이물질이나 독성을 철저히 차단할 수 있고, 상기 황토판(6)과 콘크리트 사이의 공간에 게르마늄자갈, 옥돌자갈, 옥돌가루, 황토모래 등이 채워짐으로써 이들에게서 방사되는 원적외선과 음이온을 통해 콘크리트 독성을 정화함과 아울러 사용자의 건강증진을 도모할 수 있는 것이다.Therefore, in the case of the ocher room being constructed as described above, using the
이상에서 설명한 바와 같이 본 발명에 따른 황토방 바닥 및 벽면 시공방법에 의하면, 황토방의 바닥과 벽면이 황토판으로 시공됨으로써 그 시공성과 경제성 및 작업성 등을 향상시킬 수 있고, 상기 황토판이 콘크리트 바닥과 벽체에 일정 간격을 두고 설치되기 때문에 콘크리트의 독성을 차단함과 동시에 황토방에서 몸에 이로운 원적외선과 음이온이 다량 방출되며, 이에 따라 황토방 이용자의 건강증진을 도모할 뿐만아니라 황토판을 주택이나 건물에 적용시켜 콘크리트로 인한 새집증후군을 없애줄 수 있는 효과가 있는 것이다.As described above, according to the method for constructing the ocher floor and the wall surface according to the present invention, the floor and the wall surface of the ocher room can be constructed with ocher plate to improve its workability, economic efficiency and workability, and the ocher plate is concrete floor and wall. Since it is installed at regular intervals, it blocks the toxicity of concrete and releases a large amount of far-infrared rays and negative ions that are beneficial to the ocher room, thereby promoting the health of the ocher room users and applying ocher plates to houses and buildings. The new house syndrome caused by concrete will eliminate the effects.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020040085220A KR100615567B1 (en) | 2004-10-25 | 2004-10-25 | A construction method of a floor and a wall for yellow soil room |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020040085220A KR100615567B1 (en) | 2004-10-25 | 2004-10-25 | A construction method of a floor and a wall for yellow soil room |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20060036180A KR20060036180A (en) | 2006-04-28 |
KR100615567B1 true KR100615567B1 (en) | 2006-08-25 |
Family
ID=37144446
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020040085220A KR100615567B1 (en) | 2004-10-25 | 2004-10-25 | A construction method of a floor and a wall for yellow soil room |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100615567B1 (en) |
-
2004
- 2004-10-25 KR KR1020040085220A patent/KR100615567B1/en active IP Right Grant
Also Published As
Publication number | Publication date |
---|---|
KR20060036180A (en) | 2006-04-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20160069169A (en) | Hot water panel for heating | |
KR20060134839A (en) | A mud-plastered house | |
KR200416301Y1 (en) | structure for ocher hypocaust Heating using carbon flexible mesh | |
KR102164815B1 (en) | Multipurpose block using skeletal plate | |
CN204850109U (en) | Vibration isolation sound insulation board and vibration isolation sound insulation building structure | |
KR100615567B1 (en) | A construction method of a floor and a wall for yellow soil room | |
KR20100005255A (en) | Method of construction of flat heat ondol system | |
KR101224531B1 (en) | Constructing structure an underfloor-heating room has ondol-floor formation with brick formation and pellet formation | |
KR20100084495A (en) | Constructing method of a hot-floor made of ray clay | |
KR200420635Y1 (en) | construction method for hypocaust Heating using carbon flexible mesh | |
CN204326384U (en) | A kind of gauze wire cloth thin-coat plaster rice straw composite roof board | |
KR100603752B1 (en) | The construction method for a loess structure that use C-type steel, H beam and material wood | |
CN103835418A (en) | Thermal-insulation and moisture-proof bathroom floor | |
CN203684448U (en) | Thermal insulation, breathable and cracking resistant wall | |
TWI711747B (en) | Plastic sheet structure for building | |
CN215212120U (en) | Floor sound insulation structure | |
KR102089748B1 (en) | Building Remodeling Construction Method Using Loess Board, and Remodeled Building Thereof | |
KR100870128B1 (en) | Construction method of house with multi-stories integrated with base, soil floor, soil wall and soil slab | |
KR200367674Y1 (en) | Prefabricated loess panel | |
KR100554106B1 (en) | Far-infrared rays radiant building materials using kaolin and manufacture process thereof | |
KR200481633Y1 (en) | Hwangtobang that use steel-frame structure | |
KR20090126660A (en) | Honey comb plate and the construction method of yellow earth mortar | |
KR101372113B1 (en) | Construction method for reducing noise between floors of building | |
CN205037399U (en) | A mounting panel for ground warms up installation | |
KR100625288B1 (en) | A heating construction method of loess for adiabetic and soundproof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20120731 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20130726 Year of fee payment: 8 |
|
FPAY | Annual fee payment |
Payment date: 20140805 Year of fee payment: 9 |
|
FPAY | Annual fee payment |
Payment date: 20150806 Year of fee payment: 10 |
|
FPAY | Annual fee payment |
Payment date: 20160824 Year of fee payment: 11 |
|
FPAY | Annual fee payment |
Payment date: 20170829 Year of fee payment: 12 |
|
FPAY | Annual fee payment |
Payment date: 20180814 Year of fee payment: 13 |