KR100561165B1 - Prefabricate stone house - Google Patents

Prefabricate stone house Download PDF

Info

Publication number
KR100561165B1
KR100561165B1 KR1020050019226A KR20050019226A KR100561165B1 KR 100561165 B1 KR100561165 B1 KR 100561165B1 KR 1020050019226 A KR1020050019226 A KR 1020050019226A KR 20050019226 A KR20050019226 A KR 20050019226A KR 100561165 B1 KR100561165 B1 KR 100561165B1
Authority
KR
South Korea
Prior art keywords
wall
tin
stone
house
prefabricated
Prior art date
Application number
KR1020050019226A
Other languages
Korean (ko)
Inventor
한광석
Original Assignee
한광석
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한광석 filed Critical 한광석
Application granted granted Critical
Publication of KR100561165B1 publication Critical patent/KR100561165B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/02Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
    • E04B1/04Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements the elements consisting of concrete, e.g. reinforced concrete, or other stone-like material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C1/00Building elements of block or other shape for the construction of parts of buildings
    • E04C1/24Elements for building-up floors, ceilings, roofs, arches, or beams
    • E04C1/34Elements for building-up floors, ceilings, roofs, arches, or beams designed for use as filling elements
    • E04C1/36Elements for building-up floors, ceilings, roofs, arches, or beams designed for use as filling elements between joists or girders

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Building Environments (AREA)

Abstract

본 발명은 석재로 이루어진 내,외벽체를 조립하여 완성되는 석재가옥에 관한 것으로, 더욱 상세하게는 조립식에 의한 작업공정이 매우 간단함은 물론 작업의 연속성을 확보하여 공사기간을 획기적으로 단축할 수 있고, 석재종류의 옵션에 따라 저급형부터 고급형까지 다양한 형태의 맞춤시공이 가능하며, 냉,난방 및 방음, 방풍의 효과가 개선될 수 있도록 하는 조립식 석재가옥에 관한 것이다. The present invention relates to a stone house completed by assembling the inner and outer walls made of stone, and more particularly, the work process by the prefabricated type is very simple, as well as to secure the continuity of the work can significantly shorten the construction period According to the type of stone, various types of customized construction is possible from low grade to high grade, and it is related to prefabricated stone houses to improve the effects of cooling, heating, soundproofing and windproof.

이러한 본 발명은 기초콘크리트의 상부면에 소정간격으로 안치된 주추석의 사이사이에 보강콘크리트가 타설된 기초부와;The present invention includes a base portion in which reinforcement concrete is poured between the main bones placed at predetermined intervals on the upper surface of the foundation concrete;

상기 주추석에 입설되고 양측면에 외벽체가 끼워지는 끼움홈이 형성된 다수의 외벽지주석과;A plurality of outer wall tins which are placed in the main plumb and formed with fitting grooves on which outer wall bodies are fitted;

상기 외벽지주석의 사이사이 끼움홈에 상,하 적층되게 끼움 설치되는 다수의 외벽체와:And a plurality of outer wall body which is installed to be stacked up, down stacked in the fitting groove between the outer wall tin:

상기 외벽지주석 및 내벽지주석의 상단에 밀착상태로 연속적으로 연결 설치되는 다수의 상부보와;A plurality of upper beams continuously connected to the upper end of the outer wall tin and the inner wall tin;

상기 외벽지주석 및 외벽체의 내면에 밀착 고정된 내벽지주석 사이에 연결 설치되어 실내를 다수의 구역으로 구획하는 내벽부를 구비시키므로써 이루어지는 것이다.It is made by providing an inner wall portion that is connected between the outer wall tin and the inner wall tin that is tightly fixed to the inner surface of the outer wall body to divide the interior into a plurality of zones.

Description

조립식 석재가옥{Prefabricate stone house}Prefabricate stone house

도 1은 본 발명의 주추석이 안치된 기초부의 사시도1 is a perspective view of the base portion of the main calculus of the present invention

도 2는 본 발명의 주추석에 외벽지주석이 입설된 상태의 사시도Figure 2 is a perspective view of a state in which the outer wall tin is placed in the headstone of the present invention

도 3은 본 발명의 외벽지주석에 외벽체가 조립되는 상태의 사시도Figure 3 is a perspective view of the outer wall assembly state in the outer wall paper tin of the present invention

도 4는 본 발명의 외벽체 및 외벽지주석에 상부보가 안치되는 상태의 사시도Figure 4 is a perspective view of the upper beam is placed in the outer wall and outer wall tin of the present invention

도 5는 본 발명의 단열재 및 내부벽면이 설치된 상태의 사시도5 is a perspective view of a state in which the heat insulating material and the inner wall surface of the present invention is installed

도 6은 본 발명의 내벽부가 조립되는 상태의 사시도6 is a perspective view of the inner wall of the present invention assembled;

도 7은 본 발명의 상부보에 연결빔이 연결된 상태의 사시도Figure 7 is a perspective view of the connection beam is connected to the upper beam of the present invention

도 8은 본 발명 석재가옥의 설치상태 평단면도Figure 8 is a plan sectional view of the installation state of the stone house of the present invention

도 9는 본 발명 외벽부의 설치상태 평단면도9 is a cross-sectional view of the installation state of the outer wall of the present invention

도 10은 본 발명 외벽의 설치상태 일부절결 분해사시도10 is a partially cutaway exploded perspective view of the installation state of the outer wall of the present invention

도 11은 본 발명 석재가옥의 설치상태 측단면도Figure 11 is a side cross-sectional view of the installation state of the stone house of the present invention

도 12는 본 발명 기밀방지수단의 확대상태 측단면도12 is an enlarged side cross-sectional view of the airtight preventing means of the present invention;

도 13은 본 발명 연결빔의 설치상태 측단면도Figure 13 is a side cross-sectional view of the installation state of the connection beam of the present invention

도 14는 본 발명의 상부보와 외벽지주석의 연결상태 확대단면도Figure 14 is an enlarged cross-sectional view of the connection state of the upper beam and the outer wall tin of the present invention

도 15는 본 발명의 내벽부가 조립되는 상태의 사시도15 is a perspective view of the inner wall of the present invention assembled;

도 16은 본 발명 내벽부의 설치상태 평단면도Figure 16 is a plan sectional view of the installation state of the inner wall of the present invention

도 17은 본 발명 도 16의 A-A선 단면도 17 is a cross-sectional view taken along the line A-A of FIG. 16 of the present invention.

도 18은 본 발명 내,외벽지주석의 결합상태 확대단면도18 is an enlarged cross-sectional view of the combined state of the inner and outer wall tin of the present invention;

도 19는 본 발명 받침석의 설치상태 확대도19 is an enlarged view of the installation state of the present invention pedestal

[도면의 주요부분에 대한 부호의 설명][Explanation of symbols on the main parts of the drawings]

1: 석재가옥 10: 기초부1: stone house 10: foundation

12: 주추석 20: 외벽지주석12: mainstream 20: outer wall

21: 끼움홈 30: 외벽체21: fitting groove 30: outer wall

32: 수지폼 40: 기밀방지수단32: resin foam 40: airtight prevention means

41: 완충패드 42: 기밀방지부재41: buffer pad 42: airtight member

50: 외벽부 53: 단열재50: outer wall portion 53: heat insulating material

54: 내부벽면 60: 상부보54: inner wall 60: upper beam

70: 내벽부 71: 내벽지주석70: inner wall 71: inner wall tin

72: 받침석 75: 내벽체 72: pedestal 75: inner wall

78: 연결플레이트 80: 연결빔78: connecting plate 80: connecting beam

본 발명은 석재로 이루어진 내,외벽체를 조립하여 완성되는 석재가옥에 관한 것으로, 더욱 상세하게는 조립식에 의한 작업공정이 매우 간단함은 물론 작업의 연속성을 확보하여 공사기간을 획기적으로 단축할 수 있고, 석재종류의 옵션에 따라 저급형부터 고급형까지 다양한 형태의 맞춤시공이 가능하며, 냉,난방 및 방음, 방풍의 효과가 개선될 수 있도록 하는 조립식 석재가옥에 관한 것이다.The present invention relates to a stone house completed by assembling the inner and outer walls made of stone, and more particularly, the work process by the prefabricated type is very simple, as well as to secure the continuity of the work can significantly shorten the construction period According to the type of stone, various types of customized construction is possible from low grade to high grade, and it is related to prefabricated stone houses to improve the effects of cooling, heating, soundproofing and windproof.

일반적으로 석재는 외관이 장중하고 미려할 뿐만 아니라 마모 및 풍화에도 강하며, 에너지의 효율성이 뛰어나 냉,난방의 효과가 뛰어나고, 장마철 수분을 끌어당기는 흡착력에 의해 쾌적함을 유지하는 동시에 살균작용 및 방음이 뛰어난 특성을 갖는 반면 가공이 어려운 단점을 지니고 있다.In general, the stone is not only beautiful and beautiful in appearance, but also strong in abrasion and weathering. It has excellent energy efficiency and excellent cooling and heating effects, and maintains comfort by adsorption power that draws moisture during the rainy season. It has excellent characteristics but difficult processing.

이러한 가공상의 어려움에도 불구하고 근래에는 가공기계의 발달에 따라 석재의 이용은 점진적으로 증가하고 있는 추세이며, 이러한 추세는 건축구조물에 집중되고 있다.In spite of the difficulty in processing, in recent years, the use of stone is gradually increasing with the development of processing machines, and this trend is concentrated on building structures.

그러나 상기 석재를 전체적으로 이용한 건축구조물로는 시체를 화장하여 유골을 그릇에 담아 안치해 두는 납골묘와 같은 비거주용에 제한적으로 사용될 뿐 실상 인간이 거주하는 주택이나 가옥 등을 전체적으로 석재를 이용하여 시공하는 일은 거의 전무하며, 이러한 시공방법 및 시공구조에 대해서도 명확하게 제시되지 못하고 있는 실정이다. However, the building structure using the stone as a whole is limited to non-residential use such as the ossuary which cremates the body and puts the ashes in a bowl. Actually, the construction of the houses or houses where humans reside by using the stone as a whole Almost none, these construction methods and construction structures are not clearly presented.

다만 일반적인 콘크리트가옥의 내,외벽이나 바닥면에 판상의 석재를 조금씩 붙여 시공하는 정도에 불과한 것이었다.However, it was only the construction of attaching plate-like stone little by little to the inner, outer wall or floor of a concrete house.

즉 종래에는 상기한 석재의 뛰어난 특성에도 불구하고 체계화되지 못한 시공방법 및 시공구조의 현실에 의해 대부분 콘크리트를 이용한 건축물이 주종을 이루고 있는 것이었다.In other words, in the past, despite the excellent characteristics of the above-mentioned stone, most of the buildings using concrete are mainly made by the reality of unstructured construction methods and construction structures.

상기한 종래의 콘크리트를 이용한 시공은 기초콘크리트의 타설 내,외벽철 근의 결속작업내,외벽 거푸집설치 콘크리트의 타설 후 양생 거푸집의 해체 슬라브거푸집설치콘크리트의 타설 후 양생슬라브거푸집의 해체 내,외벽미장 내부배관, 배선 및 미장완료의 작업공정을 통해 이루어지는 것이었다Using a conventional concrete above construction are casting of the foundation concrete My, the binding operation of the outer wall of the iron muscle installed inside, the outer wall formwork after pouring of the concrete after dismantling casting of slab formwork installation concrete curing mold curing slab dismantling the mold was made through the operation of the process within the outer wall plastering internal piping, wiring and plastering complete

그러나 상기 콘크리트를 이용한 시공방법은 작업공정이 매우 복잡할 뿐만 아니라 콘크리트가 양생되는 동안에 일시적으로 작업이 중단되는 등의 작업에 따른 연속성이 없어 일반적인 가옥을 시공하는 경우에도 약 3개월정도가 소요되는 문제점이 야기되며, 이러한 공사기간의 지연은 건축비의 과도한 상승 및 경쟁력의 저하로 직결되어 부실공사의 빌미를 제공하는 것이었다.However, the construction method using the concrete is not only very complicated work process, but also takes about 3 months when constructing a general house because there is no continuity due to the work being temporarily suspended while the concrete is being cured. This delay was caused by excessive increase in construction cost and deterioration of competitiveness, thus providing a virtue for poor construction.

또한 작업의 연속성 부재에 따라 현장에서 작업인부들의 작업이 불균형적으로 이루어지므로써 작업인부에게는 생계의 위협을 초래하며, 시공사는 인력수급에 어려움을 가중시켜 원활한 시공이 이루어질 수 없는 문제점이 야기되고 있는 실정이다.In addition, due to the lack of continuity of work, the workmen's work is disproportionately performed in the field, which creates a threat of livelihoods to the workers. It is true.

본 발명은 일반화된 종래의 콘크리트가옥을 대체하기 위한 석재가옥을 조립식으로 간단하게 시공할 수 있도록 하는 것이다.The present invention is to make it easy to build a prefabricated stone house to replace the conventional concrete house generalized.

이러한 본 발명은 기초콘크리트 상부에 주추석을 안치시켜 견고한 기초부를 형성하도록 하고, 상기 주추석에 입설되는 요철형의 외벽지주석 사이사이에 다수의 외벽체를 끼움 조립할 수 있도록 하며, 상기 외벽지주석 및 내벽지주석의 상단에 다수의 상부보를 설치하도록 하는 한편, 상기 외벽체의 내측으로 보조지주석(73)을 확보한 채 단열재 및 내부벽면을 설치하여 완전한 외벽부를 이루도록 하고, 상기 외벽지주석 및 외벽체의 내면에 밀착된 내벽지주석 사이에 다수의 내벽체를 연속적으로 연결하여 실내를 다수의 공간으로 구획할 수 있도록 하며, 상기 상부보의 상단에 연결빔을 일체로 설치하여 외벽체 및 내벽부의 견고한 고정상태를 유지할 수 있도록 하는 간단한 조립구성으로 이루어짐을 핵심적인 기술적과제로 하는 것이다.The present invention is to place the main chuseok on the top of the base concrete to form a solid foundation, to enable the assembly of a plurality of outer wall between the uneven outer wall tin of the uneven type, the outer wall tin and While installing a plurality of upper beams on the upper end of the inner wall tin, while installing the insulating tin and the inner wall surface while securing the auxiliary tin 73 inside the outer wall body to form a complete outer wall portion, the outer wall tin and outer wall of the By connecting a plurality of inner walls continuously between inner wall tins in close contact with the inner surface, the interior can be partitioned into a plurality of spaces, and the connection beams are integrally installed on the upper end of the upper beam to secure a fixed state of the outer wall and the inner wall. The key technical task is to consist of a simple assembly configuration that can be maintained.

이러한 본 발명에 의하면 상기 기초부를 포함하여 내,외벽체를 완성한 후 최종적으로 상부에 지붕을 올리는 간단한 방법으로 석재가옥을 단기간에 시공할 수 있게 된다.According to the present invention it is possible to construct a stone house in a short time by a simple method of finally raising the roof at the top after completing the inner and outer walls, including the base portion.

본 발명의 목적을 효과적으로 달성하기 위한 바람직한 실시예의 구성에 대해 설명하기로 한다.The configuration of the preferred embodiment for effectively achieving the object of the present invention will be described.

본 발명은 종래에 관행적으로 실시된 콘크리트를 이용한 가옥의 형태를 탈피하여 전체적으로 석재로 이루어진 외벽지주석(20) 및 내,외벽체(75)(30)를 이용하여 간단하고 신속하게 석재가옥을 조립 구성하므로써 공기를 단축함은 물론 작업의 연속성을 유지하여 효율적인 작업 및 인력수급의 용이함을 제공하며, 석재의 특성에 따른 각종 효과를 제공할 수 있음을 발명의 특징적인 요지로 한다.The present invention simply and quickly assemble a stone house using the outer wall tin 20 and the inner and outer walls 75, 30 made of stone as a whole to escape the shape of the house using the conventionally practiced concrete. It is a characteristic gist of the present invention that shortening the air and consequently maintaining the continuity of the work to provide efficient work and ease of manpower supply, and can provide various effects according to the characteristics of the stone.

상기한 특징적인 요지를 달성하고자 하는 본 발명의 전체적인 구성은 도 1 내지 도 7에 따른 순서도와 같이 기초콘크리트(11)의 상부면에 다수의 주추석(12)이 안치된 기초부(10)와, 상기 주추석(12)에 입설되는 다수의 외벽지주석(20)과, 상기 외벽지주석(20)의 사이사이에 적층상태로 끼움 설치되는 다수의 외벽체(30)와, 상기 외벽지주석(20) 및 내벽지주석(71)의 상단에 밀착상태로 연속적으로 연결 설치되는 다수의 상부보(60)와, 상기 외벽지주석(20) 및 외벽체(30)에 밀착된 내벽지주석(71) 사이에 연속적으로 연결되어 실내를 다수의 구역으로 구획하는 내벽부(70)로 구성됨을 알 수 있다.The overall configuration of the present invention to achieve the above-mentioned characteristic gist is a base portion 10 having a plurality of main bone 12 placed on the upper surface of the base concrete 11, as shown in the flow chart according to Figs. And a plurality of outer wall tins 20 installed in the main stem 12 and a plurality of outer wall bodies 30 installed in a stacked state between the outer wall tins 20 and the outer wall tins ( 20) and a plurality of upper beams 60 continuously connected to the upper end of the inner wall tin 71 and the inner wall tin 71 in close contact with the outer wall tin 20 and the outer wall body 30. It can be seen that it is composed of the inner wall portion 70 which is continuously connected between and partitions the room into a plurality of zones.

이하, 상기 개략적인 구성으로 이루어진 본 발명을 실시 가능하도록 좀 더 상게하게 설명하기로 한다.Hereinafter, the present invention having the above-described schematic configuration will be described in more detail.

우선적으로 본 발명 석재가옥(1)의 토대를 이루는 기초부(10)는 외벽지주석(20) 및 외벽체(30), 내벽부(70)를 설치할 수 있도록 기본적으로 기초콘크리트(11)가 타설되고, 이 기초콘크리트(11)의 테두리부 및 실내를 적정영역(방, 욕실 등)으로 구획하고자 하는 위치에 소정간격으로 외벽지주석(20) 및 내벽지주석(71)을 받쳐주기 위한 다수의 주추석(12)이 일체로 안치되며, 상기 주추석(12)의 사이사이에는 보강콘크리트(13)가 주추석(12)과 동일한 수평면을 이루도록 일체로 타설된다.Basically, the foundation part 10 which forms the foundation of the stone house 1 of the present invention is basically the foundation concrete 11 is placed so that the outer wall tin 20, the outer wall body 30, and the inner wall part 70 can be installed. In addition, a plurality of notes for supporting the outer wall tin 20 and the inner wall tin 71 at predetermined intervals at positions where the edge portion and the interior of the basic concrete 11 are to be partitioned into appropriate areas (rooms, bathrooms, etc.). Chuseok 12 is integrally placed, the reinforcement concrete 13 is integrally placed so as to form the same horizontal plane as the main chuseok 12 between the main chuseok 12.

이러한 기초부(10)는 상부면이 전체적으로 반드시 수평상태를 유지하여야만 외벽체(30) 및 내벽부(70)의 시공시 일체의 오차도 허용하지 않는 정확도를 유지할 수 있게 된다.The base portion 10 can maintain the accuracy that does not allow any error in the construction of the outer wall 30 and the inner wall portion 70 only when the upper surface must be entirely horizontal.

상기한 주추석(12)의 상부에는 본 발명의 골조를 이루는 다수의 외벽지주석(20)이 각각 입설되고, 상기 외벽지주석(20)의 양면에는 외벽체(30)를 조립하기 위한 끼움홈(21)이 각각 형성된다.A plurality of outer wall tin 20 constituting the framework of the present invention is placed in the upper portion of the main stem 12, respectively, and fitting grooves for assembling the outer wall body 30 on both sides of the outer wall tin 20 ( 21) are formed respectively.

이때 기초부(10)의 사방 모서리부에 배치되는 외벽지주석(20)은 인접된 양면에 각각 외벽체(30)가 조립되도록 인접된 양면부에 끼움홈(21)이 형성되는 반면, 상기 모서리부의 외벽지주석(20) 사이사이에 배치되는 다른 외벽지주석(20)은 대응 하는 양면에 각각 외벽체(30)가 조립되도록 양측면부에 끼움홈(21)이 대응되게 형성되는 점이 다소 상이하다.At this time, the outer wall tin 20 is disposed on the four corners of the base portion 10, while the fitting groove 21 is formed in the adjacent both sides so that the outer wall body 30 is assembled on each of the adjacent both sides, the corner portion The other outer wall tin 20 disposed between the outer wall tin 20 is slightly different in that the fitting grooves 21 are formed to correspond to both side portions so that the outer wall body 30 is assembled on the corresponding both surfaces.

상기한 외벽지주석(20)의 사이사이 끼움홈(21)에 끼움 설치되는 다수의 외벽체(30)는 석재로 구성될 수 있으며, 상기 끼움홈(21)에 끼워짐에 있어 양단부가 끼움홈(21)에 완전하게 밀착상태로 끼워지지 않고 도 9와 같이 양단부와 끼움홈(21)의 사이에 일정공간을 확보하도록 끼워진 후 상기 외벽지주석(20)과 외벽체(30)의 내면 사이에는 각각 앵글과 같은 종류의 보강부재(31)가 연결 설치되어 견고함을 유지한다.A plurality of outer wall body 30 that is installed between the fitting groove 21 between the outer wall tin 20 may be composed of a stone, both ends in the fitting groove 21 is fitted into the fitting groove ( 21) is not fitted in close contact with each other, as shown in Fig. 9 and is fitted to secure a predetermined space between the both ends and the fitting groove 21, the angle between the outer wall tin 20 and the inner surface of the outer wall body 30, respectively Reinforcement member 31 of the same type is connected to maintain the firmness.

그리고, 상기 일정공간에는 기밀을 방지함은 물론 지진 등과 같은 외부요인의 발생시 유동발생을 억제하여 석재간의 충돌로 인한 파손을 방지하기 위한 목적으로 수지폼(32)이 채워져 일정한 텐션을 유지할 수 있게 된다.In addition, the predetermined space can be maintained to maintain a constant tension by filling the resin foam 32 for the purpose of preventing leakage due to the collision between stones by preventing the flow of the occurrence of external factors such as earthquake, as well as preventing airtightness. .

또한 상기 외벽체(30)는 상,하 다단으로 상부보(60)의 저면에 밀착될 때 까지 적층되는 것으로, 적층시 외벽체(30)간의 마찰 및 충격으로 인한 파손을 방지하도록 외벽체(30)의 사이사이에는 기밀방지수단(40)이 설치된다.In addition, the outer wall body 30 is stacked until the upper wall 60 in close contact with the bottom of the upper beam 60 in multiple stages, between the outer wall body 30 to prevent damage due to friction and impact between the outer wall body 30 during the stacking Between the airtight prevention means 40 is installed.

상기 기밀방지수단(40)은 중앙 양측에 다수의 완충패드(41)가 설치되고, 상기 완충패드(41)의 양측 길이방향으로 기밀방지부재(42)가 설치되며 이 기밀방지부재(42)의 외측으로 실리콘(43)이 도포되도록 마감처리된다.The airtight prevention means 40 is provided with a plurality of buffer pads 41 on both sides of the center, the airtight member 42 is installed in both longitudinal directions of the buffer pad 41 and the airtight member 42 Finished so that the silicon 43 is applied to the outside.

이때 상기 완충패드(41)는 석재용패드가 적용될 수 있으며 매우 단단하면서도 내구성이 뛰어난 특성을 갖으며, 기밀방지부재(42)는 스치로폴 등과 같이 일정한 쿠션을 구비하는 동시에 방음 및 방풍이 뛰어난 성질을 보유하여 냉,난방의 효 과를 극대화시킨다.At this time, the buffer pad 41 is a stone pad can be applied and has a very hard and durable characteristics, the airtight member 42 has a certain cushioning, such as Schiropol and at the same time excellent soundproofing and windproof To maximize the effect of cooling and heating.

따라서 상기 외벽체(30)간의 이음새부위를 통해서는 어떠한 이물질도 투입될 수 없으며, 뛰어난 방음, 방풍의 효과를 제공한다.Therefore, no foreign matter can be introduced through the joint portion between the outer wall 30, and provides an excellent soundproofing, windproof effect.

상기 외벽체(30)의 적층이 완료되면 외벽지주석(20)의 상단부 중앙에는 다수의 상부보(60)가 상호 밀착상태로 만나도록 연속적으로 연결 설치되고, 상기 상부보(60)의 저면과 외벽지주석(20)의 사이에는 보강부재(31)가 연결 설치되어 견고함을 유지하며, 더욱이 상기 최상측의 외벽체(30)와 밀착되는 상부보(60)의 사이에도 기밀방지수단(40)이 설치된다.When the stacking of the outer wall body 30 is completed, a plurality of upper beams 60 are continuously connected to each other in close contact with each other at the center of the upper end of the outer wall tin 20, and the bottom surface and the outer surface of the upper beams 60. The reinforcing member 31 is connected and installed between the wall tin 20 to maintain the robustness, and moreover, the airtight prevention means 40 is provided between the upper beam 60 in close contact with the outer wall body 30 of the uppermost side. Is installed.

상기와 같이 적층되는 외벽체(30)는 내측으로 배선공사를 위한 일정한 공간을 마련하는 동시에 더욱 뛰어난 방음 및 냉,난방에 역점을 두어 실내측으로 단열재(53) 및 내부벽면(54)이 추가적으로 배치된다.The outer wall body 30 stacked as described above is provided with a predetermined space for the wiring work to the inside and at the same time, the heat insulation material 53 and the inner wall surface 54 is additionally disposed to emphasize the excellent soundproofing and cooling, heating.

즉 도 9 내지 도 10와 같이 외벽체(30)의 내측으로 다수의 보조지주석(51)이 일정간격으로 입설되고, 상기 보조지주석(51)의 사이에는 배선 및 배관이 통과될 수 있는 보조지주석(73)(52)을 마련하는 동시에 단열을 위한 목적으로 각각 단열재(53)가 연결 설치되며, 상기 단열재(53)의 내면에는 외벽지주석(20)의 내면과 동일선상으로 위치되는 동시에 상부보(60)의 저면에 밀착되는 내부벽면(54)이 밀착 설치된다.That is, as shown in FIGS. 9 to 10, a plurality of auxiliary support tins 51 are installed at a predetermined interval inside the outer wall body 30, and auxiliary papers through which wiring and piping can pass between the auxiliary support tins 51. At the same time to provide a tin (73) (52), the heat insulating material 53 is connected and installed for the purpose of thermal insulation, respectively, the inner surface of the heat insulating material 53 is located in the same line as the inner surface of the outer wall tin 20 at the same time The inner wall surface 54 in close contact with the bottom of the beam 60 is provided in close contact.

따라서 상기한 보조지주석(73)(52) 및 단열재(53), 내부벽면(54)의 추가적인 구성을 통해 비로서 열효율이 더욱 개선된 완전한 형태의 외벽부(50)를 형성할 수 있게 된다.Therefore, through the additional configuration of the auxiliary support 73, 52, the heat insulating material 53, the inner wall surface 54, it is possible to form the outer wall portion 50 of the complete form with further improved thermal efficiency.

상기 외벽부(50)가 완성된 후 내부에 설치되어 실내를 다수의 구역으로 구획하는 내벽부(70)는 실내측에 배치되는 다수의 주추석(12)에 각각 전용 내벽지주석(71)이 입설된다.After the outer wall portion 50 is completed, the inner wall portion 70 installed inside and partitioning the interior into a plurality of zones has a dedicated inner wall tin 71 in each of the plurality of headstones 12 disposed on the interior side. It is entered.

이때 상기 내벽지주석(71)은 도 16과 같이 대각선 방향으로 위치하는 각각의 외벽지주석(20)에 밀착된 상태로 입설된 후 소정간격으로 배치된 주추석(12)에 연속적으로 배치되어 내부 공간을 구획할 수 있으며, 또한 상기 구획된 내부 공간을 재차 구획할 경우 내벽지주석(71)은 외벽체(30) 및 마주하는 내벽지주석(71)에 밀착된 상태로 입설될 수 있게 된다. In this case, the inner wall tin 71 is placed in close contact with each outer wall tin 20 positioned in a diagonal direction as shown in FIG. 16, and is continuously disposed in the main bone 12 disposed at predetermined intervals. The space may be partitioned, and when the partitioned inner space is partitioned again, the inner wall tin 71 may be placed in close contact with the outer wall 30 and the inner wall tin 71 facing each other.

그리고 상기 내벽지주석(71)의 사이사이에는 상,하 소정간격으로 받침석(72)이 각각 수평상태로 배치되며, 상기 받침석(72)은 내벽지주석(71)과의 충돌로 인한 파손을 효과적으로 방지하도록 양단부에 완충패드(41)가 끼움 설치됨은 물론 양측 상,하단부와 내벽지주석(71) 사이에는 보강부재(31)가 연결 설치되어 더욱 뛰어난 견고함을 유지하게 된다.And between the inner wall tin 71, the pedestal 72 is disposed in a horizontal state at a predetermined interval up and down, respectively, the pedestal 72 is effectively damaged by the collision with the inner wall tin 71 The shock absorbing pads 41 are fitted to both ends to prevent, of course, the reinforcing member 31 is connected between the upper and lower ends and the inner wall tin 71 to maintain the superior strength.

또한 상기 받침석(72)의 상,하단부에는 각각 다수의 보조지주석(73)이 일정간격으로 설치됨에 따라 보조지주석(73)의 사이에는 자연적으로 배선 및 배관 등이 통과할 수 있는 배선공간(74)을 형성하게 되고, 상기 내벽지주석(71)의 상단에는 외벽지주석(20)과 동일하게 상부보(60)가 연속적으로 연결 설치되며, 이때 보조지주석(73)의 상단부는 상부보(60)의 저면과 상호 밀착된다.In addition, the upper and lower ends of the pedestal 72, respectively, as a plurality of auxiliary support tin 73 is installed at regular intervals between the auxiliary support tin 73, wiring space through which wiring and piping can naturally pass ( 74, and the upper beam 60 is continuously connected to the upper end of the inner wall tin 71 in the same manner as the outer wall tin 20, wherein the upper end of the auxiliary tin 73 is an upper beam It comes in close contact with the bottom of 60.

상기 상부보(60)의 설치가 완료된 후 보조지주석(73)의 내,외측에는 다수의 내벽체(75)가 내벽지주석(71)의 내,외면부와 수평면을 이루도록 일체로 부착되고, 부착방법은 보조지주석(73)에 먼저 석재용본드를 도포한 후 내벽체(75)를 부착할 수 있게 된다.After the installation of the upper beam 60 is completed, a plurality of inner wall bodies 75 are integrally attached to the inner and outer surfaces of the inner wall tin 71 so as to form a horizontal plane with the inner and outer sides of the auxiliary tin 73. The attachment method is to apply the stone bond first to the auxiliary support tin 73, and then to be able to attach the inner wall (75).

한편, 본 발명에서는 상호 마주하는 내,외벽지주석(71)(20)의 밀착부위 상단에 연결요홈(77)이 함몰 형성되고, 상기 연결요홈(77)에는 체결부재(81)를 이용하여 연결플레이트(78)가 일체로 연결되므로써 상기 내,외벽지주석(71)(20) 간의 견고한 결합력을 유지할 수 있게 된다.On the other hand, in the present invention, the connecting groove 77 is formed in the top of the close contact portion of the inner and outer wall tin 71, 20 facing each other, the connection groove 77 is connected using a fastening member 81 Since the plate 78 is integrally connected, it is possible to maintain a firm coupling force between the inner and outer wall tin 71 and 20.

그리고 주추석(12)에는 다수의 주추석고정핀(12a)의 일측이 일체로 삽재되고, 돌출된 타측부위는 내,외벽지주석(71)(20)의 하단부에 일체로 끼움 결합되므로써 내,외벽지주석(71)(20)의 견고한 입설상태를 유지할 수 있게 된다.And one side of the plurality of main pinned pin 12a is inserted integrally in the main head 12, and the other protruding part is integrally fitted to the lower end of the inner, outer wall tin (71) (20) by the inner, It is possible to maintain a solid snowfall state of the outer wall tin (71) (20).

상기와 같이 기초부(10)를 포함하여 외벽체(30) 및 내벽부(70), 상부보(60)의 설치가 완료된 후 상기 상부보(60)의 상단에는 외벽체(30) 및 내벽부(70) 간의 견고한 고정상태를 유지하도록 하는 연결빔(80)이 연설된다.After the installation of the outer wall body 30, the inner wall portion 70, the upper beam 60, including the base portion 10 is completed as described above, the outer wall body 30 and the inner wall portion 70 on the upper end of the upper beam 60 The connecting beam 80 is spoken to maintain a firm fixed state between

이때 상기 연결빔(80)은 통상적인 H형의 빔이 적용될 수 있으며, 별도의 체결부재(81)를 매개로 하여 상부보(60)와 일체로 체결되므로써 외벽체(30)와 내벽부(70)의 견고한 고정상태를 유지할 수 있게 된다.At this time, the connection beam 80 may be applied to the conventional H-shaped beam, the outer wall body 30 and the inner wall portion 70 by being integrally fastened with the upper beam 60 through a separate fastening member 81. It is possible to maintain a firm fixed state.

이와 같이 연결빔(80)을 이용한 고정작업이 완료되면 최종적으로 상부에 지붕을 올리는 방법으로 단시간에 석재가옥을 시공할 수 있게 된다.As such, when the fixing operation using the connecting beam 80 is completed, it is possible to construct the stone house in a short time by raising the roof at the top.

이러한 본 발명은 콘크리트가옥과 같이 콘크리트가 양생되기까지 작업을 중단하는 일이 전혀 없어 작업의 연속성을 유지함은 물론 조립식의 공정을 통해 공기를 획기적으로 단축할 수 있으며, 석재 특유의 효과를 입주자에게 체득할 수 있도 록 한다.In the present invention, there is no interruption of work until concrete is cured like a concrete house, and thus, the continuity of the work can be maintained, and the air can be drastically shortened through a prefabricated process. Do it.

본 발명은 에너지 효율성이 뛰어난 석재로 이루어진 내,외벽체를 간단한 작업공정을 통해 조립식으로 석재가옥을 완성할 수 있는 동시에 작업중단 없는 작업의 연속성을 이루어 공사기간을 획기적으로 단축하여 공사비를 절감함은 물론 인력수급이 매우 용이하여 시공에 따른 경쟁력을 확보할 수 있게 된다.The present invention can achieve a stone house by prefabricating the inner and outer walls made of energy-efficient stone through a simple work process and at the same time by continuity of work without interruption, significantly shortening the construction period to reduce construction costs The supply and demand of manpower is very easy to secure the competitiveness of construction.

또한 기존 콘크리트가옥에 비해 냉,난방의 효과가 뛰어나 벽체의 두께를 줄여 보다 넓은 실내공간을 확보할 수 있음은 물론 석재의 특성으로 인한 방음, 및 방풍의 능력이 뛰어나며, 수분을 끌어당기는 흡착력에 의해 장마철 습기를 제거하여 쾌적하고 청결한 상태의 실내를 유지할 수 있게 된다.In addition, it has better cooling and heating effect than existing concrete houses, so it is possible to secure a wider indoor space by reducing the thickness of the wall, as well as the soundproofing and windproof ability due to the characteristics of the stone. By removing the humidity during the rainy season, you can maintain a pleasant and clean room.

더욱이 다양한 석재종류의 옵션에 따라 저급형을 비롯하여 고급형까지 보다 다양한 형태로 소비자의 선택에 알맞는 맞춤시공을 할 수 있는 효과를 제공하게 된다.Furthermore, according to various stone type options, it is possible to provide customized construction suitable for consumer's choice in various forms from low-end to high-end type.

Claims (10)

기초콘크리트(11)의 상부면에 소정간격으로 안치된 주추석(12)의 사이사이에 보강콘크리트(13)가 타설된 기초부(10)와;A base portion 10 on which reinforcement concrete 13 is poured between the main bone 12 placed at a predetermined interval on the upper surface of the foundation concrete 11; 상기 주추석(12)에 입설되고 양측면에 외벽체(30)가 끼워지는 끼움홈(21)이 형성된 다수의 외벽지주석(20)과;A plurality of outer wall tins 20 which are inserted into the main plumes 12 and have fitting grooves 21 formed on both sides of the outer wall bodies 30; 상기 외벽지주석(20)의 사이사이 끼움홈(21)에 상,하 적층되게 끼움 설치되는 다수의 외벽체(30)와:And a plurality of outer wall body 30 is installed to be stacked up, down stacked in the fitting groove 21 between the outer wall tin 20: 상기 외벽지주석(20) 및 내벽지주석(71)의 상단에 밀착상태로 연속적으로 연결 설치되는 다수의 상부보(60)와;A plurality of upper beams 60 which are continuously connected in close contact with the upper ends of the outer wall tin 20 and the inner wall tin 71; 상기 외벽지주석(20) 및 외벽체(30)의 내면에 밀착 고정된 내벽지주석(71) 사이에 연결 설치되어 실내를 다수의 구역으로 구획하는 내벽부(70)로 이루어진 것을 특징으로 하는 조립식 석재가옥.Prefabricated stone, characterized in that consisting of the inner wall portion 70 is installed between the outer wall tin 20 and the inner wall tin 71 is tightly fixed to the inner surface of the outer wall body 30 to partition the interior into a plurality of zones. premises. 청구항 1에 있어서,The method according to claim 1, 외벽체(30)의 내측으로 다수의 보조지주석(51)이 일정간격으로 입설되고, 상기 보조지주석(51)의 사이사이에는 보조지주석(73)(52)이 형성되도록 단열재(53)가 연결 설치되며, 상기 단열재(53)의 내면에는 내부벽면(54)이 외벽지주석(20)의 내면과 동일면을 이루는 동시에 상부보(60)의 저면에 밀착 설치되어 완전한 외벽부(50)를 형성하는 것을 특징으로 하는 조립식 석재가옥.Insulating material 53 is formed so that a plurality of auxiliary support tin 51 is placed in the inner wall of the outer wall 30 at regular intervals, and the auxiliary support tin 73, 52 is formed between the auxiliary support tin 51. The inner wall surface 54 is installed on the inner surface of the heat insulating material 53 to be the same surface as the inner surface of the outer wall tin 20, and is installed in close contact with the bottom surface of the upper beam 60 to form a complete outer wall portion 50. Prefab stone house, characterized in that. 청구항 1 또는 청구항 2에 있어서,The method according to claim 1 or 2, 상,하로 적층되는 다수의 외벽체(30) 사이에는 중앙 양측으로 다수의 완충패드(41)가 배치되고, 상기 완충패드(41)의 양측 길이방향으로 기밀방지부재(42)가 설치되며, 상기 기밀방지부재(42)의 외측으로 실리콘(43)이 도포되어 마감처리된 기밀방지수단(40)을 추가적으로 포함하는 것을 특징으로 하는 조립식 석재가옥.A plurality of buffer pads 41 are disposed at both sides of the center between the plurality of outer wall bodies 30 stacked up and down, and an airtight prevention member 42 is installed in both longitudinal directions of the buffer pad 41. Prefabricated stone house, characterized in that it further comprises an airtight prevention means 40, the silicone 43 is applied to the outside of the prevention member (42). 청구항 2에 있어서,The method according to claim 2, 다수의 외벽체(30)는 양단부와 끼움홈(21)의 사이에 일정공간이 확보되고, 이 일정공간에는 기밀 및 유동방지, 쿠션을 위한 수지폼(32)이 채움 설치되는 것을 특징으로 하는 조립식 석재가옥.A plurality of outer wall body 30 is a predetermined space is secured between both ends and the fitting groove 21, the predetermined space is a prefabricated stone, characterized in that the resin foam 32 for filling the airtightness and flow prevention, cushioning is installed premises. 청구항 1 또는 청구항 2에 있어서,The method according to claim 1 or 2, 내벽부(70)는 실내측 주추석(12)에 다수의 내벽지주석(71)이 입설되고, 상기 내벽지주석(71)의 사이에는 상,하 다수의 받침석(72)이 수평 설치되며, 상기 받침석(72)의 상,하단부에는 배선공간(74)을 형성하도록 다수의 보조지주석(73)이 일정간격으로 설치되는 한편, 상기 보조지주석(73)의 내,외측에는 다수의 내벽체(75)가 일체로 부착된 것을 특징으로 하는 조립식 석재가옥.The inner wall portion 70 has a plurality of inner wall tin 71 is placed in the interior side plume 12, a plurality of upper and lower pedestals 72 are horizontally installed between the inner wall tin 71, On the upper and lower ends of the pedestal 72, a plurality of auxiliary tin 73 is installed at regular intervals to form a wiring space 74, while a plurality of inner walls inside and outside the auxiliary tin 73. Prefabricated stone house, characterized in that (75) is integrally attached. 청구항 5에 있어서,The method according to claim 5, 받침석(72)의 양단에는 다수의 완충패드(41)가 끼움 설치된 것을 특징으로 하는 조립식 석재가옥.Prefabricated stone house, characterized in that a plurality of cushioning pads 41 are fitted to both ends of the pedestal 72. 청구항 5에 있어서,The method according to claim 5, 내,외벽지주석(71)(20)의 밀착부위 상단에는 연결요홈(77)이 형성되고, 상기 연결요홈(77)에는 연결플레이트(78)가 체결부재(81)를 매개로 일체로 삽입 설치된 것을 특징으로 하는 조립식 석재가옥. Connection grooves 77 are formed at the upper end of the contact portion of the inner and outer wall tins 71 and 20, and the connection grooves 78 are integrally installed by the coupling member 81 in the connection grooves 77. Prefab stone house, characterized in that. 청구항 5에 있어서,The method according to claim 5, 내,외벽지주석(71)(20)의 하단부는 주추석(12)에 고정된 주추석고정핀(12a)의 일측에 끼움 결합되는 것을 특징으로 하는 조립식 석재가옥.Prefabricated stone house, characterized in that the lower end of the inner wall outer tin (71) (20) is fitted to one side of the pinned pinned pin 12a fixed to the main spindle 12. 청구항 1 또는 청구항 2에 있어서,The method according to claim 1 or 2, 상부보(60)의 상단에는 외벽체(30) 및 내벽부(70)의 견고한 고정상태를 유지하도록 연결빔(80)이 체결부재(81)를 매개로 일체화 연결되는 것을 특징으로 하는 조립식 석재가옥.Prefabricated stone houses, characterized in that the connection beam 80 is integrally connected through the fastening member 81 to maintain a firm fixed state of the outer wall body 30 and the inner wall portion 70 on the upper end of the upper beam (60). 청구항 1 또는 청구항 2에 있어서,The method according to claim 1 or 2, 외벽체(30)의 내면과 외벽지주석(20)의 사이와, 내벽지주석(71)과 받침석(72)의 사이, 상기 내,외벽지주석(71)(20)과 상부보(60)의 저면 사이에는 각각 견 고한 연결상태를 유지하기 위한 보강부재(31)가 연결 설치된 것을 특징으로 하는 조립식 석재가옥. Between the inner surface of the outer wall body 30 and the outer wall tin 20, and between the inner wall tin 71 and the pedestal 72, the inner and outer wall tins 71, 20 and the upper beam 60 Prefabricated stone houses, characterized in that the reinforcing member 31 is connected between the bottom to maintain a solid connection state, respectively.
KR1020050019226A 2004-12-01 2005-03-08 Prefabricate stone house KR100561165B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020040099880 2004-12-01
KR1020040099880 2004-12-01

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR20-2005-0006232U Division KR200384762Y1 (en) 2004-12-01 2005-03-08 Prefabricate stone house

Publications (1)

Publication Number Publication Date
KR100561165B1 true KR100561165B1 (en) 2006-03-20

Family

ID=37179695

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050019226A KR100561165B1 (en) 2004-12-01 2005-03-08 Prefabricate stone house

Country Status (1)

Country Link
KR (1) KR100561165B1 (en)

Similar Documents

Publication Publication Date Title
KR101209662B1 (en) Steel frame for curved form construction of free from architecture building and method using it
KR101184277B1 (en) Steel frame for free form concrete structure construction and method using it
JP6336682B2 (en) Building blocks for wall structures
KR200431410Y1 (en) Assembling structure of panel for inter layer noise proofing
KR102416023B1 (en) Floor impact sound blocking panel and slab structure for blocking inter-floor impact sound and slab construction method
KR102248291B1 (en) Double Floor Structure and Methods for Protecting against Interfacial Noise in Building
KR200384762Y1 (en) Prefabricate stone house
JP2002339451A (en) Precast concrete slab, its manufacturing method, precast concrete slab for balcony, and outer thermal insulating structure
KR100561165B1 (en) Prefabricate stone house
KR20090046140A (en) Prefabricated korean-style house made of unit structure
KR20010091455A (en) Connecting Structure And Construction Method For Wall Concrete Panel
KR200377470Y1 (en) Prefabricate stone house
EA012427B1 (en) Insulating form for concrete walls
KR100485585B1 (en) Fabricated structure and section steel for the same
KR100622018B1 (en) Method for constructing building, and building constructed thereof
JP2006322205A (en) Wall type wooden building
JP4412731B2 (en) Floating floor construction method and floating floor structure
KR20130024101A (en) Method for constructing cubic construction
GB2079813A (en) Prefabricated building block and a building composed of such blocks
KR100704342B1 (en) Hollow concrete device and multi-layer structure using the same
KR100444155B1 (en) a sectional sphere architecture and building method
KR101776783B1 (en) Integrated module block for Building Construction
KR200382523Y1 (en) Structure of drainage trench for inducing infiltrated water and dew in structure's outside wall
CN217325952U (en) Partition wall pipeline integrated structure
KR100540643B1 (en) Wall of building

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20121224

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20140214

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20150129

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20160108

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20180124

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20190117

Year of fee payment: 14

FPAY Annual fee payment

Payment date: 20191230

Year of fee payment: 15