KR100505127B1 - Segmental Block-faced Retaining Wall System - Google Patents
Segmental Block-faced Retaining Wall System Download PDFInfo
- Publication number
- KR100505127B1 KR100505127B1 KR10-2003-0063959A KR20030063959A KR100505127B1 KR 100505127 B1 KR100505127 B1 KR 100505127B1 KR 20030063959 A KR20030063959 A KR 20030063959A KR 100505127 B1 KR100505127 B1 KR 100505127B1
- Authority
- KR
- South Korea
- Prior art keywords
- retaining wall
- shaped
- wall block
- geogrid
- soil
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0258—Retaining or protecting walls characterised by constructional features
- E02D29/0266—Retaining or protecting walls characterised by constructional features made up of preformed elements
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0084—Geogrids
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/20—Miscellaneous comprising details of connection between elements
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Retaining Walls (AREA)
Abstract
본 발명은 토압으로 인한 비탈면 붕괴를 막고, 옹벽의 기울기에 따라 실시간적으로 적층되는 옹벽블럭의 경사각을 용이하게 조정할 수 있도록 한 보강토 옹벽용 조립체에 관한 것으로, 이러한 본 발명은 그 상부 상면에 사각형 결합홈 및 저면에 사각형 결합홈을 복수개 구비하여 도로변 비탈면, 제방, 하안, 단지 조경벽면 등 토목공사에 의하여 형성되는 절개지의 경사면이나 법면을 지탱하고 토사가 붕괴되는 것을 막는 "요"자형 옹벽블럭과, 복수개의 가로바와 세로바를 연결하여 타원형 체결공을 형성하여 적층되는 "요"자형 옹벽블럭 사이 사이에 설치되어 흙과의 마찰력, 인발저항력, 전단응력을 발생시키는 지오그리드(Geogrid)를 구비한 보강토 옹벽용 조립체에 있어서, 상기 "요"자형 옹벽블럭의 사각형 결합홈에 삽입 고정되도록 사각형 기둥이 형성되고, 상기 사각형 기둥의 양측 상면 가장자리에 일정길이 수직 상방으로 지오그리드의 체결공의 일측에 완전히 삽입 밀착되되 그 저면 가장자리 양측에는 실시간적으로 적층되는 "요"자형 옹벽블럭의 경사각을 다르게 조절할 수 있도록 길이가 다른 제1조절턱 및 제2조절턱을 구비하여 상기 지오그리드와 흙과의 마찰력, 인발저항력, 전단응력을 현격하게 증가시키는 밀착부가 형성된 "Y"자형 인터록킹 플레이트와; 상기 "Y"자형 인터록킹 플레이트의 밀착부와 체결됨과 아울러 상기 "요"자형 옹벽블럭에 적층되는 "요"자형 옹벽블럭의 저면에 형성된 사각형 결합홈에 삽입 고정되어 상기 "요"자형 옹벽블럭들을 연결 고정시켜주되 그 양측에는 실시간적으로 적층되는 "요"자형 옹벽블럭의 경사각을 다르게 조절할 수 있도록 길이가 다른 제1조절부 및 제2조절부가 형성된 "n"자형 앵글 캡으로 구성된다.The present invention relates to a reinforcement soil retaining wall assembly that prevents the slope collapse due to earth pressure and to easily adjust the inclination angle of the retaining wall blocks stacked in real time according to the slope of the retaining wall. “Y” shaped retaining wall blocks for supporting slopes or slopes of cutouts formed by civil works such as roadside slopes, banks, riverbanks, landscaping walls, and preventing soil from collapse Reinforced soil retaining wall with geogrid which is installed between the “yo” shaped retaining wall blocks that are stacked by connecting a plurality of horizontal bars and vertical bars to form an elliptical fastening hole, and generates friction, pull resistance and shear stress with soil. In the assembly, the rectangular pillar is shaped to be inserted into the rectangular coupling groove of the "yo" retaining wall block It is formed so as to be completely inserted close to one side of the fastening hole of the geogrid in a vertical length up to both sides of the upper edge of the rectangular column, but to adjust the inclination angle of the "yo" -shaped retaining wall blocks stacked in real time on both sides of the bottom edge. A “Y” shaped interlocking plate having a first adjusting jaw and a second adjusting jaw having different lengths, and having a close contact portion for remarkably increasing friction, pull resistance and shear stress between the geogrid and the soil; The "yo" -shaped retaining wall blocks are fastened to the close contact portion of the "Y" -shaped interlocking plate and inserted into a rectangular coupling groove formed in the bottom surface of the "yo" -shaped retaining wall block stacked on the "yo" -shaped retaining wall block. It is fixed to the connection on both sides of the "y" shaped retaining wall is stacked in real time so that the angle of inclination of the first adjustment portion and the second adjustment portion of the "n" shaped angle cap is formed so as to adjust differently.
Description
본 발명은 보강토 옹벽에 관한 것으로, 보다 상세하게는 토압으로 인한 비탈면 붕괴를 막고, 옹벽의 기울기(예를들어, 옹벽블럭을 설치하고자하는 비탈면의 경사각)에 따라 실시간적으로 적층되는 옹벽블럭의 경사각을 용이하게 조정할 수 있도록 한 보강토 옹벽용 조립체에 관한 것이다.The present invention relates to a reinforced soil retaining wall, and more particularly, to prevent slope collapse due to earth pressure, and inclination angle of retaining wall blocks stacked in real time according to the slope of the retaining wall (for example, the slope angle of the slope to which the retaining wall is to be installed). It relates to a reinforcement earth retaining wall assembly that can be easily adjusted.
일반적으로, 보강토 옹벽(擁壁)은 토압력(土壓力)에 저항하여 흙이 무너지지 못하게 만든 벽체(壁體)로써, 지표지반(地表地盤)의 안정된 경사를 그것보다 가파른 경사로 하였을 경우에 일어나는 지반 붕괴를 막기 위해 다수개의 보강토 옹벽용 조립체가 결합된 구조물이다.Generally, reinforcement soil retaining wall is a wall that prevents soil from collapsing due to soil pressure, and it is the ground that occurs when the slope of the ground becomes steeper than that. It is a structure in which a plurality of reinforcement retaining wall assemblies are combined to prevent collapse.
도 1은 일반적인 보강토 옹벽용 조립체를 나타낸 도면이다.1 is a view showing the assembly for a general reinforced earth retaining wall.
도 1에 도시된 바와 같이, 일반적인 보강토 옹벽용 조립체는 그 상부에 타원형 관통공(10-1)과 제1 및 제2원형 결합홈(10-3)(10-4)을 복수개 구비하여 도로변 비탈면, 제방, 하안, 단지 조경벽면 등 토목공사에 의하여 형성되는 절개지의 경사면이나 법면을 지탱하고 토사가 붕괴되는 것을 막는 "요"자형 옹벽블럭(10)과, 상기 "요"자형 옹벽블럭(10)의 제1결합홈(10-3) 또는 제2결합홈(10-4)에 삽입 고정됨과 아울러 후술할 지오그리드(30)의 체결공(30-1) 일측에 삽입 통과되어 상기 지오그리드(30)의 흙과의 마찰력, 인발저항력, 전단응력을 증가시키는 봉형상의 연결핀(20)과, 복수개의 가로바(30-3)와 세로바(30-5)를 연결하여 타원형 체결공(30-1)을 형성하고 상기 체결공(30-1)으로 연결핀(20)을 삽입 밀착시켜 흙과의 마찰력, 인발저항력, 전단응력을 발생시키는 지오그리드(Geogrid)(30)로 구성된다.As shown in FIG. 1, a general reinforcement soil retaining wall assembly includes a plurality of elliptical through holes 10-1 and first and second circular coupling grooves 10-3 and 10-4 on the upper side thereof. And a "yo" -shaped retaining wall block (10) for supporting a slope or a normal surface of an incision formed by a civil works such as a dike, a riverbank, a landscaping wall, and preventing soil from being collapsed, and the "yo" -shaped retaining wall block (10). It is inserted into and fixed in the first coupling groove (10-3) or the second coupling groove (10-4) of the geogrid 30 of the geogrid 30 to be described later is passed through one side of the geogrid (30) Rod-shaped connecting pin 20 to increase frictional force, pull resistance, and shear stress with soil, and connects a plurality of horizontal bars 30-3 and vertical bars 30-5 to form an elliptical fastening hole 30-1. Geogrid for forming a friction force with the soil, pull-out resistance, shear stress by forming a close contact with the connecting pin 20 to the fastening hole (30-1) ( Geogrid).
도 2 및 도 3은 도 1의 보강토 옹벽용 조립체를 이용하여 옹벽을 설치한 상태를 나타낸 도면이다.2 and 3 are views showing a state in which the retaining wall is installed using the reinforcement soil retaining wall assembly of FIG.
도 2 및 도 3에 도시된 바와 같이, 배수성이 좋은 기초 저면에 "요"자형 옹벽블럭(10)을 위치시켜 첫째층을 쌓는다.As shown in Figs. 2 and 3, the first layer is stacked by placing the "yo" retaining wall block 10 on the bottom of the foundation having good drainage.
그리고, "요"자형 옹벽블럭(10)에 형성된 제1원형 결합홈(10-3) 또는 제2원형 결합홈(10-4)으로 일정길이 봉형상의 연결핀(20)을 삽입 고정시킨다.Then, the rod-shaped connecting pin 20 is fixedly inserted into the first circular coupling groove 10-3 or the second circular coupling groove 10-4 formed in the “yo” -shaped retaining wall block 10.
그런후에, 상기 연결핀(20)을 지오그리드(30)의 체결공(30-1)으로 삽입 밀착시킨다.Thereafter, the connecting pin 20 is inserted into close contact with the fastening hole (30-1) of the geogrid (30).
한편, 첫째층의 "요"자형 옹벽블럭(10) 상면에 둘째층의 "요"자형 옹벽블럭(10)을 쌓는다.On the other hand, the "yo" shaped retaining wall block 10 of the second layer is stacked on the upper surface of the "yo" shaped retaining wall block 10 of the first layer.
이때, 상기 제1원형 결합홈(10-3) 또는 제2원형 결합홈(10-4)에 삽입 고정된 연결핀(20)을 둘째층의 "요"자형 옹벽블럭(10) 저면에 형성된 관통공으로 삽입시킨다.At this time, the connecting pin 20 inserted into the first circular coupling groove 10-3 or the second circular coupling groove 10-4 is formed on the bottom surface of the “yo” shaped retaining wall block 10 of the second layer. Insert into ball.
그리고, 상기와 같은 방식으로, 셋째층, 넷째층, 다섯째층, ····등의 "요"자형 옹벽블럭(10)을 순차적으로 쌓는다.Then, in the same manner as described above, the "yo" -shaped retaining wall blocks 10 such as the third layer, the fourth layer, the fifth layer, ..., etc. are sequentially stacked.
다른 한편, 지오그리드(30)를 일정간격의 층 사이에 위치시킨다.On the other hand, the geogrid 30 is positioned between the layers at regular intervals.
그런후에, 옹벽으로 형성된 "요"자형 옹벽블럭(10)의 후단부로 흙을 채운다.Then, the soil is filled with the rear end of the "yo" shaped retaining wall block 10 formed of the retaining wall.
그러나, 이와 같이 구성된 종래의 보강토 옹벽용 조립체는 첫째층의 "요"자형 옹벽블럭의 제1원형 결합홈에 연결핀이 삽입될 경우 또는 제2원형 결합홈에 연결핀이 삽입될 경우에 따라, 첫째층의 "요"자형 옹벽블럭의 상면에 순서적으로 위치되는 둘째층, 셋째층, 넷째층, 다섯째층, ····N층 "요"자형 옹벽블럭의 경사면 각도가 두가지로 나타나는 바, 다양한 경사면을 갖는 옹벽을 설치할 수 없는 문제점이 있었다.However, according to the conventional reinforcement earth retaining wall assembly configured as described above, when the connecting pin is inserted into the first circular coupling groove of the "yo" -shaped retaining wall block of the first layer or when the connecting pin is inserted into the second circular coupling groove, 2nd, 3rd, 4th, 5th, ... N layer "Y" shaped retaining wall blocks have two inclination angles, which are sequentially placed on the upper surface of the "yo" retaining wall block of the first layer. There was a problem in that it is not possible to install retaining walls having various slopes.
따라서, 종래의 보강토 옹벽용 조립체로 옹벽을 쌓을 경우, 쌓고자 하는 지역의 조건에 따라(부지 면적의 넓고, 좁음에 따라) 옹벽 경사면의 각도가 단지 2가지로 제한 됨으로, 옹벽 경사 각도를 설정함에 있어 융통성이 극히 제한적 이라는 문제점이 있었다.Therefore, when the retaining wall is stacked with the conventional reinforcement earth retaining wall assembly, the retaining wall inclination angle is limited to only two according to the conditions of the area to be stacked (according to the wide and narrow area of the site). There was a problem that flexibility is extremely limited.
또한, 도 4에 도시된 바와 같이, 옹벽의 뒷채움토(보강토)와의 마찰력, 인발저항력, 전단응력을 증가시키기 위해, 연결핀을 지오그리드의 체결공으로 삽입시키지만, 상기 연결핀이 체결공의 일측 가로바와 세로바에 밀착되지 않아 옹벽의 뒷채움토와의 마찰력, 인발저항력, 전단응력이 현격하게 증가되지 못하는 문제점이 있었다.In addition, as shown in Figure 4, in order to increase the frictional force, pullout resistance, and shear stress with the backfilling soil (reinforced soil) of the retaining wall, the connecting pin is inserted into the fastening hole of the geogrid, but the connecting pin is connected to one side bar of the fastening hole There was a problem that the friction, pullout resistance, and shear stress with the backfill soil of the retaining wall did not increase significantly because they did not adhere to the vertical bars.
이로 인해, 보강토에 의해 옹벽이 자주 무너져 내리는 문제점이 있었다.For this reason, there is a problem that the retaining wall is often collapsed by the reinforcement soil.
특히, "요"자형 옹벽블럭에 손잡이가 설치되지 않아 사용자가 상기 "요"자형 옹벽블럭을 운반할 경우, 힘이 아주 많이 소비되는 문제점이 있었다.In particular, the handle is not installed on the "yo" retaining wall block, so that when the user carries the "yo" retaining wall block, there is a problem that a very large amount of power is consumed.
따라서, 본 발명은 상기한 종래 기술에 따른 제반 문제점을 해결하기 위하여 제안된 것으로서, 본 발명의 목적은 토압으로 인한 비탈면 붕괴를 막고, 옹벽의 기울기에 따라 실시간적으로 적층되는 옹벽블럭의 경사각을 용이하게 조정할 수 있도록 한 보강토 옹벽용 조립체를 제공하는데 있다.Accordingly, the present invention has been proposed to solve the above problems according to the prior art, the object of the present invention is to prevent the slope of the slope due to earth pressure, and easy to incline the angle of the retaining wall blocks are stacked in real time according to the slope of the retaining wall To provide a reinforcement earth retaining wall assembly that can be adjusted.
상기한 목적을 달성하기 위한 본 발명에 따른 보강토 옹벽용 조립체의 특징은,그 상부 상면에 사각형 결합홈(100-1) 및 저면에 사각형 결합홈을 복수개 구비하여 도로변 비탈면, 제방, 하안, 단지 조경벽면 등 토목공사에 의하여 형성되는 절개지의 경사면이나 법면을 지탱하고 토사가 붕괴되는 것을 막는 "요"자형 옹벽블럭(100)과, 복수개의 가로바(120-3)와 세로바(120-5)를 연결하여 타원형 체결공(120-1)을 형성하여 적층되는 "요"자형 옹벽블럭(100) 사이 사이에 설치되어 흙과의 마찰력, 인발저항력, 전단응력을 발생시키는 지오그리드(Geogrid)(120)를 구비한 보강토 옹벽용 조립체에 있어서,상기 "요"자형 옹벽블럭(100)의 사각형 결합홈(100-1)에 삽입 고정되도록 사각형 기둥(110-3)이 형성되고, 상기 사각형 기둥(110-3)의 양측 상면 가장자리에 일정길이 수직 상방으로 지오그리드(120)의 체결공(120-1)의 일측에 완전히 삽입 밀착되되 그 저면 가장자리 양측에는 실시간적으로 적층되는 "요"자형 옹벽블럭(100)의 경사각을 다르게 조절할 수 있도록 길이가 다른 제1조절턱(110-7) 및 제2조절턱(110-9)을 구비하여 상기 지오그리드(120)와 흙과의 마찰력, 인발저항력, 전단응력을 현격하게 증가시키는 밀착부(110-1)가 형성된 "Y"자형 인터록킹 플레이트(Inter Locking plate)(110)와; Features of the assembly for reinforcement soil retaining wall according to the present invention for achieving the above object, roadside slope, embankment, riverbank, only landscaping by having a plurality of rectangular coupling groove (100-1) and a plurality of rectangular coupling groove on the bottom of the upper surface A “yo” shaped retaining wall block 100 supporting the inclined or normal surface of the incision formed by civil works such as a wall and preventing soil from collapse, a plurality of horizontal bars 120-3 and vertical bars 120-5 Geogrid 120 is installed between the "yo" shaped retaining wall block 100 to be stacked by forming an elliptical fastening hole (120-1) by connecting to generate a frictional force, pullout resistance, shear stress with the soil (120) In the assembly for reinforcement soil retaining wall having a rectangular pillar 110-3 is formed to be inserted and fixed to the rectangular coupling groove (100-1) of the "yo" -shaped retaining wall block 100, the rectangular pillar 110- 3) constant length vertical upward on the upper edge of both sides It is inserted into close contact with one side of the fastening hole (120-1) of the log grid 120, but the length of the different length so as to adjust the inclination angle of the "yo" -shaped retaining wall block 100 is stacked in real time on both sides of the bottom edge A close contact portion 110-1 having a first adjustment jaw 110-7 and a second adjustment jaw 110-9 to significantly increase frictional force, pullout resistance, and shear stress between the geogrid 120 and soil is provided. A formed “Y” shaped inter locking plate 110;
상기 "Y"자형 인터록킹 플레이트(110)의 밀착부(110-1)와 체결됨과 아울러 상기 "요"자형 옹벽블럭(100)에 적층되는 "요"자형 옹벽블럭(100)의 저면에 형성된 사각형 결합홈에 삽입 고정되어 상기 "요"자형 옹벽블럭들을 연결 고정시켜주되 그 양측에는 실시간적으로 적층되는 "요"자형 옹벽블럭(100)의 경사각을 다르게 조절할 수 있도록 길이가 다른 제1조절부(130-7) 및 제2조절부(130-9)가 형성된 "n"자형 앵글 캡(130)으로 구성된다. The square formed on the bottom surface of the "yo" -shaped retaining wall block 100 which is fastened to the close contact portion 110-1 of the "Y" -shaped interlocking plate 110 and laminated on the "yo" -shaped retaining wall block 100. The first adjustment part having a different length so as to adjust the inclination angle of the "yo" -shaped retaining wall blocks 100 stacked in real time on both sides thereof is fixed to the coupling groove and fixed to the "yo" -shaped retaining wall blocks. 130-7) and the second adjustment portion 130-9 is formed of the "n" shaped angle cap 130 .
삭제delete
삭제delete
삭제delete
이하, 본 발명에 따른 보강토 옹벽용 조립체의 바람직한 실시 예를 첨부한 도면을 참조하여 설명하면 다음과 같다.Hereinafter, with reference to the accompanying drawings a preferred embodiment of the reinforcement earth retaining wall assembly according to the present invention.
도 5는 본 발명에 따른 보강토 옹벽용 조립체를 나타낸 도면이다.5 is a view showing the assembly for the reinforcement earth retaining wall according to the present invention.
도 5에 도시된 바와 같이, 본 발명에 따른 보강토 옹벽용 조립체는 그 상부 상면에 사각형 결합홈(100-1) 및 저면에 사각형 결합홈(도시는 생략함)을 복수개 구비하여 도로변 비탈면, 제방, 하안, 단지 조경벽면 등 토목공사에 의하여 형성되는 절개지의 경사면이나 법면을 지탱하고 토사가 붕괴되는 것을 막는 "요"자형 옹벽블럭(100)과, "요"자형 옹벽블럭(100)의 경사각을 실시간적으로 다르게 조절할 수 있도록 그 상부에 일정간격을 두고 수직하게 형성된 밀착부(110-1)를 구비함과 아울러 상기 "요"자형 옹벽블럭(100)의 사각형 결합홈(100-1)에 삽입 고정되고 그 밀착부(110-1)가 후술할 지오그리드(120)의 체결공(120-1)의 일측에 삽입 밀착되어 상기 지오그리드(120)의 흙과의 마찰력, 인발저항력, 전단응력을 현격하게 증가시키는 "Y"자형 인터록킹 플레이트(Inter Locking plate)(110)와, 복수개의 가로바(120-3)와 세로바(120-5)를 연결하여 타원형 체결공(120-1)을 형성하고 상기 체결공(120-1)으로 "Y"자형 인터록킹 플레이트(110)을 삽입 밀착시켜 흙과의 마찰력, 인발저항력, 전단응력을 발생시키는 지오그리드(Geogrid)(120)와, 상기 "Y"자형 인터록킹 플레이트(110)의 밀착부(110-1)와 체결됨과 아울러 상기 "요"자형 옹벽블럭(100)에 적층되는 "요"자형 옹벽블럭(100)의 저면에 형성된 사각형 결합홈에 삽입 고정되어 실시간적으로 적층되는 상기 "요"자형 옹벽블럭(100)의 경사각을 다르게 조절할 수 있도록 한 "n"자형 앵글 캡(Angle Cap)(130)으로 구성된다.As shown in Figure 5, the reinforcement earth retaining wall assembly according to the present invention is provided with a plurality of rectangular coupling groove (100-1) and a rectangular coupling groove (not shown) in the upper upper surface slope side, embankment, The inclination angle of the "yo" -shaped retaining wall block 100 and the "yo" -shaped retaining wall block 100 that support the slope or the slope of the cutout formed by the civil works such as the riverbank and the landscaping wall surface and prevent the soil from being collapsed are real-time. It is provided with a close contact portion (110-1) formed vertically at a predetermined interval on the upper portion so as to be differently adjusted, and fixedly inserted into the rectangular coupling groove (100-1) of the "yo" -shaped retaining wall block 100. And the close contact portion 110-1 is inserted into and close to one side of the fastening hole 120-1 of the geogrid 120 to be described later, and the frictional force with the soil of the geogrid 120, the pullout resistance, and the shear stress are significantly increased. "Y" shaped interlocking plate (Inter Lo cking plate) 110, the plurality of horizontal bars (120-3) and the vertical bar (120-5) is connected to form an elliptical fastening hole (120-1) and "Y" as the fastening hole (120-1) Geogrid 120 that inserts and closes the “shaped interlocking plate 110” and generates friction, pull resistance, and shear stress with the soil, and the contact portion 110 of the “Y” shaped interlocking plate 110. -1) and the "yo" shaped to be laminated in real time by being fixed in a rectangular coupling groove formed in the bottom surface of the "yo" shaped retaining wall block 100 which is fastened to the "yo" shaped retaining wall block 100. It is composed of an "n" shaped angle cap (Angle Cap) 130 to adjust the inclination angle of the retaining wall block 100 differently.
그리고, 상기 "요"자형 옹벽블럭(100)의 저면에는 도 6에 도시된 바와 같이, "n"자형 앵글 캡(130)이 삽입 고정시킬 수 있도록 사각형 결합홈(100-5)이 형성되며, 옹벽블럭의 용이하게 움직일 수 있도록 손잡이(100-7)가 형성된다.Then, the bottom surface of the "yo" -shaped retaining wall block 100, as shown in Figure 6, the "n" shaped angle cap 130 is formed so that the square coupling groove (100-5), The handle 100-7 is formed to easily move the retaining wall block.
또한, 상기 "Y"자형 인터록킹 플레이트(110)는 도 7a 및 도 7b에 도시된 바와 같이, "요"자형 옹벽블럭(100)의 사각형 결합홈(100-1)에 삽입 고정되도록 사각형 기둥(110-3)이 형성되며, 상기 사각형 기둥(110-3)의 양측 상면 가장자리에 일정길이 수직 상방으로 지오그리드(120)의 체결공(120-1)의 일측에 완전히 삽입 밀착되어 상기 지오그리드(120)의 흙과의 마찰력, 인발저항력, 전단응력을 현격하게 증가시키는 밀착부(110-1)가 형성된다.In addition, the "Y" -shaped interlocking plate 110, as shown in Figures 7a and 7b, the rectangular pillar (to be inserted into the rectangular coupling groove (100-1) of the "yo" -shaped retaining wall block 100 is fixed ( 110-3 is formed, the geogrid 120 is completely inserted into one side of the fastening hole (120-1) of the geogrid 120 in a vertical vertical length to the upper edge of both sides of the rectangular column (110-3) A close contact portion 110-1 is formed to significantly increase the frictional force, pull resistance, and shear stress with the soil.
그리고, 상기 밀착부(110-1)의 상부에는 "n"자형 앵글 캡(130)과 체결 고정이 용이하도록 계단부(110-5)가 형성된다.In addition, a step portion 110-5 is formed at an upper portion of the contact portion 110-1 to facilitate fastening and fixing with the “n” shaped angle cap 130.
특히, 도 7c에 도시된 바와 같이, 상기 사각형 기둥(110-3)의 상면에 위치되는 밀착부(110-1)의 가장자리 양측에는 실시간적으로 적층되는 "요"자형 옹벽블럭(100)의 경사각을 다르게 조절하는 제1조절턱(110-7) 및 제2조절턱(110-9)이 형성된다.In particular, as shown in Figure 7c, the inclination angle of the "yo" -shaped retaining wall block 100 is stacked in real time on both sides of the edge of the contact portion 110-1 located on the upper surface of the rectangular column (110-3) The first adjusting jaw (110-7) and the second adjusting jaw (110-9) to control the different is formed.
여기서, 상기 제2조절턱(110-9)의 길이는 도 7d에 도시된 바와 같이, 제1조절턱(110-7)의 길이 보다 길다. 즉, P2의 길이는 P1의 길이 보다 길다.Here, the length of the second adjustment jaw (110-9) is longer than the length of the first adjustment jaw (110-7), as shown in Figure 7d. That is, the length of P2 is longer than the length of P1.
그리고, 상기 밀착부(110-1)의 외면 일측은 지오그리드(120)의 체결공(120-1)의 일측에 삽입 밀착되도록 라운더져 있다.In addition, one side of the outer surface of the close contact portion 110-1 is rounded to be in close contact with one side of the fastening hole 120-1 of the geogrid 120.
한편, 상기 "n"자형 앵글 캡(130)은 도 8에 도시된 바와 같이, 밀착부(110-1)의 계단부(110-5)와 체결 고정이 용이하도록 계단부(130-1)를 갖는 수납부(130-3)가 형성된다.On the other hand, the "n" shaped angle cap 130 as shown in Figure 8, the step portion 130-1 to facilitate fastening and fixing the step portion (110-5) of the close contact portion (110-1). The accommodating part 130-3 which has is formed.
또한, 상기 "n"자형 앵글 캡(130)의 양측에는 실시간적으로 적층되는 "요"자형 옹벽블럭(100)의 경사각을 다르게 조절하는 제1조절부(130-7) 및 제2조절부(130-9)가 형성된다.In addition, on both sides of the "n" shaped angle cap 130, the first adjusting unit 130-7 and the second adjusting unit for differently adjusting the inclination angle of the "yo" shaped retaining wall block 100 is stacked in real time ( 130-9).
여기서, 상기 제2조절부(130-9)의 길이는 제1조절부(130-7)의 길이 보다 길다. 즉, C2의 길이는 C1의 길이 보다 길다.Here, the length of the second control unit 130-9 is longer than the length of the first control unit 130-7. That is, the length of C2 is longer than the length of C1.
이와 같이 구성된 보강토 옹벽용 조립체를 이용하여 옹벽을 설치하는 과정을 살펴보면 다음과 같다.Looking at the process of installing the retaining wall using the reinforcement earth retaining wall assembly configured as described above are as follows.
도 9a는 본 발명에 따른 보강토 옹벽용 조립체를 이용하여 옹벽을 설치한 제1 실시예의 상태를 나타낸 도면이다.9A is a view showing a state of a first embodiment in which a retaining wall is installed by using the reinforcement earth retaining wall assembly according to the present invention.
도 9a에 도시된 바와 같이, 배수성이 좋은 기초 저면에 "요"자형 옹벽블럭(100)을 위치시켜 첫째층을 쌓는다.As shown in FIG. 9A, the first layer is stacked by placing the “yo” retaining wall block 100 on the bottom of the foundation having good drainage.
그리고, "요"자형 옹벽블럭(100)에 형성된 사각형 결합홈(100-1)으로 일정길이 "Y"자형 인터록킹 플레이트(110)의 사각형 기둥(110-3)을 삽입 고정시킨다.Then, the square pillars 110-3 of the “Y” shaped interlocking plate 110 are inserted and fixed into the rectangular coupling groove 100-1 formed in the “yo” shaped retaining wall block 100.
이때, "Y"자형 인터록킹 플레이트(110)에 형성된 밀착부(110-1)의 제1조절턱(110-7)을 도 9b에 도시된 바와 같이, 상기 사각형 결합홈(100-1)의 후벽 상면에 위치되도록 한다. 여기서, 제1조절턱(110-7)의 길이는 P1이다.At this time, the first adjustment jaw (110-7) of the close contact portion 110-1 formed on the "Y" shaped interlocking plate 110, as shown in Figure 9b, of the rectangular coupling groove (100-1) Position it on the top of the rear wall. Here, the length of the first adjustment jaw (110-7) is P1.
이에 따라, 축조의 각도는 0.4도 이다. Accordingly, the angle of construction is 0.4 degrees.
그런후에, 지오그리드(30)의 타원형 체결공(30-1)으로 상기 "Y"자형 인터록킹 플레이트(110)의 밀착부(110-1)를 삽입시킨다.Then, the close contact portion 110-1 of the “Y” shaped interlocking plate 110 is inserted into the elliptical fastening hole 30-1 of the geogrid 30.
이때, 상기 밀착부(110-1)가 타원형 체결공(30-1)을 이루는 가로바(120-3)와 세로바(120-5)와 완전히 밀착되도록 한다.At this time, the close contact portion 110-1 is in close contact with the horizontal bar 120-3 and the vertical bar 120-5 forming the elliptical fastening hole 30-1.
이에 따라, 지오그리드(30)와 흙과의 마찰력, 인발저항력, 전단응력을 현격하게 향상된다.Accordingly, the friction between the geogrid 30 and the soil, the pullout resistance, the shear stress is significantly improved.
그리고, 첫째층의 "요"자형 옹벽블럭(100) 상면에 둘째층의 "요"자형 옹벽블럭(100)을 쌓는다.Then, the "yo" shaped retaining wall block 100 of the second layer is stacked on the upper surface of the "yo" shaped retaining wall block 100 of the first layer.
이때, 둘째층의 "요"자형 옹벽블럭(10)의 저면에 형성된 사각형 결합홈(100-4)에, 상기 "Y"자형 인터록킹 플레이트(110)의 밀착부(110-1)가 삽입되도록 한다.At this time, the contact portion 110-1 of the "Y" shaped interlocking plate 110 is inserted into the rectangular coupling groove 100-4 formed in the bottom surface of the "yo" shaped retaining wall block 10 of the second layer. do.
그리고, 상기와 같은 방식으로, 셋째층, 넷째층, 다섯째층, ····등의 "요"자형 옹벽블럭(100)을 순차적으로 쌓는다.Then, in the same manner as described above, the "yo" -shaped retaining wall blocks 100 such as the third layer, the fourth layer, the fifth layer, ..., etc. are sequentially stacked.
따라서, 옹벽의 경사각은 0.4도 이다.Therefore, the inclination angle of the retaining wall is 0.4 degrees.
그런후에, 옹벽으로 형성된 "요"자형 옹벽블럭(100)의 후단부로 흙을 채운다.Then, the soil is filled with the rear end of the "yo" shaped retaining wall block 100 formed by the retaining wall.
도 10a는 본 발명에 따른 보강토 옹벽용 조립체를 이용하여 옹벽을 설치한 제2 실시예의 상태를 나타낸 도면이다.10A is a view illustrating a state of a second embodiment in which a retaining wall is installed by using the reinforcement earth retaining wall assembly according to the present invention.
도 10a에 도시된 바와 같이, 배수성이 좋은 기초 저면에 "요"자형 옹벽블럭(100)을 위치시켜 첫째층을 쌓는다.As shown in FIG. 10A, the first layer is stacked by placing the “yo” retaining wall block 100 on the bottom of the foundation having good drainage.
그리고, "요"자형 옹벽블럭(100)에 형성된 사각형 결합홈(100-1)으로 일정길이 "Y"자형 인터록킹 플레이트(110)의 사각형 기둥(110-3)을 삽입 고정시킨다.Then, the square pillars 110-3 of the “Y” shaped interlocking plate 110 are inserted and fixed into the rectangular coupling groove 100-1 formed in the “yo” shaped retaining wall block 100.
이때, "Y"자형 인터록킹 플레이트(110)에 형성된 밀착부(110-1)의 제2조절턱(110-9)을 도 10b에 도시된 바와 같이, 상기 사각형 결합홈(100-1)의 후벽 상면에 위치되도록 한다. 여기서, 제2조절턱(110-9)의 길이는 P2이다.At this time, the second adjustment jaw (110-9) of the close contact portion 110-1 formed on the "Y" shaped interlocking plate 110, as shown in Figure 10b, of the rectangular coupling groove (100-1) Position it on the top of the rear wall. Here, the length of the second adjustment jaw (110-9) is P2.
이에 따라, 축조의 각도는 1.4도 이다. Accordingly, the angle of construction is 1.4 degrees.
그런후에, 지오그리드(30)의 타원형 체결공(30-1)으로 상기 "Y"자형 인터록킹 플레이트(110)의 밀착부(110-1)를 삽입시킨다.Then, the close contact portion 110-1 of the “Y” shaped interlocking plate 110 is inserted into the elliptical fastening hole 30-1 of the geogrid 30.
이때, 상기 밀착부(110-1)가 타원형 체결공(30-1)을 이루어는 가로바(120-3)와 세로바(120-5)와 완전히 밀착되도록 한다.At this time, the close contact portion 110-1 is in close contact with the horizontal bar (120-3) and the vertical bar (120-5) to form an elliptical fastening hole (30-1).
이에 따라, 지오그리드(30)와 흙과의 마찰력, 인발저항력, 전단응력을 현격하게 향상된다.Accordingly, the friction between the geogrid 30 and the soil, the pullout resistance, the shear stress is significantly improved.
그리고, 첫째층의 "요"자형 옹벽블럭(100) 상면에 둘째층의 "요"자형 옹벽블럭(100)을 쌓는다.Then, the "yo" shaped retaining wall block 100 of the second layer is stacked on the upper surface of the "yo" shaped retaining wall block 100 of the first layer.
이때, 둘째층의 "요"자형 옹벽블럭(10)의 저면에 형성된 사각형 결합홈(100-4)에, 상기 "Y"자형 인터록킹 플레이트(110)의 밀착부(110-1)가 삽입되도록 한다.At this time, the contact portion 110-1 of the "Y" shaped interlocking plate 110 is inserted into the rectangular coupling groove 100-4 formed in the bottom surface of the "yo" shaped retaining wall block 10 of the second layer. do.
그리고, 상기와 같은 방식으로, 셋째층, 넷째층, 다섯째층, ····등의 "요"자형 옹벽블럭(100)을 순차적으로 쌓는다.Then, in the same manner as described above, the "yo" -shaped retaining wall blocks 100 such as the third layer, the fourth layer, the fifth layer, ..., etc. are sequentially stacked.
따라서, 옹벽의 경사각은 1.4도 이다.Therefore, the inclination angle of the retaining wall is 1.4 degrees.
그런후에, 옹벽으로 형성된 "요"자형 옹벽블럭(100)의 후단부로 흙을 채운다.Then, the soil is filled with the rear end of the "yo" shaped retaining wall block 100 formed by the retaining wall.
도 11a는 본 발명에 따른 보강토 옹벽용 조립체를 이용하여 옹벽을 설치한 제3 실시예의 상태를 나타낸 도면이다.11A is a view showing a state of a third embodiment in which the retaining wall is installed by using the reinforcement earth retaining wall assembly according to the present invention.
도 11a에 도시된 바와 같이, 배수성이 좋은 기초 저면에 "요"자형 옹벽블럭(100)을 위치시켜 첫째층을 쌓는다.As shown in FIG. 11A, the first layer is stacked by placing the “yo” retaining wall block 100 on the bottom of the foundation having good drainage.
그리고, "요"자형 옹벽블럭(100)에 형성된 사각형 결합홈(100-1)으로 일정길이 "Y"자형 인터록킹 플레이트(110)의 사각형 기둥(110-3)을 삽입 고정시킨다.Then, the square pillars 110-3 of the “Y” shaped interlocking plate 110 are inserted and fixed into the rectangular coupling groove 100-1 formed in the “yo” shaped retaining wall block 100.
이때, "Y"자형 인터록킹 플레이트(110)에 형성된 밀착부(110-1)의 제1조절턱(110-7)을 도 11b에 도시된 바와 같이, 상기 사각형 결합홈(100-1)의 후벽 상면에 위치되도록 한다. 여기서, 제1조절턱(110-7)의 길이는 P1이다.At this time, the first adjustment jaw (110-7) of the close contact portion 110-1 formed on the "Y" shaped interlocking plate 110, as shown in Figure 11b, of the rectangular coupling groove (100-1) Position it on the top of the rear wall. Here, the length of the first adjustment jaw (110-7) is P1.
이에 따라, 축조의 각도는 0.4도 이다. Accordingly, the angle of construction is 0.4 degrees.
그런후에, 지오그리드(30)의 타원형 체결공(30-1)으로 상기 "Y"자형 인터록킹 플레이트(110)의 밀착부(110-1)를 삽입시킨다.Then, the close contact portion 110-1 of the “Y” shaped interlocking plate 110 is inserted into the elliptical fastening hole 30-1 of the geogrid 30.
이때, 상기 밀착부(110-1)가 타원형 체결공(30-1)을 이루어는 가로바(120-3)와 세로바(120-5)와 완전히 밀착되도록 한다.At this time, the close contact portion 110-1 is in close contact with the horizontal bar (120-3) and the vertical bar (120-5) to form an elliptical fastening hole (30-1).
이에 따라, 지오그리드(30)와 흙과의 마찰력, 인발저항력, 전단응력을 현격하게 향상된다.Accordingly, the friction between the geogrid 30 and the soil, the pullout resistance, the shear stress is significantly improved.
그리고, 상기 밀착부(110-1)의 계단부(110-5)에 "n"자형 앵글 캡(130)을 위치시킨다.Then, the "n" shaped angle cap 130 is positioned on the stepped portion 110-5 of the close contact portion 110-1.
이때, 상기 밀착부(110-1)의 계단부(110-5)와 "n"자형 앵글 캡(130)의 계단부(130-1)가 체결되도록 한다.At this time, the step part 110-5 of the close contact part 110-1 and the step part 130-1 of the "n" shaped angle cap 130 are fastened.
이에 따라, "n"자형 앵글 캡(130)에 형성된 제1조절부(130-7)가 도 11b에 도시된 바와 같이, 상기 사각형 결합홈(100-1)의 후벽 상면에 위치된다.Accordingly, the first adjusting part 130-7 formed in the "n" shaped angle cap 130 is located on the rear wall upper surface of the rectangular coupling groove 100-1, as shown in FIG. 11B.
여기서, 제1조절부(130-7)의 길이는 C1이고, 축조의 각도는 2.4도 이다.Here, the length of the first adjustment unit 130-7 is C1, the angle of construction is 2.4 degrees.
그런후에, 첫째층의 "요"자형 옹벽블럭(100) 상면에 둘째층의 "요"자형 옹벽블럭(100)을 쌓는다.Then, the "yo" shaped retaining wall block 100 of the second layer is stacked on the upper surface of the "yo" shaped retaining wall block 100 of the first layer.
이때, 둘째층의 "요"자형 옹벽블럭(10)의 저면에 형성된 사각형 결합홈(100-4)에, 상기 "n"자형 앵글 캡(130)이 삽입되도록 한다.At this time, the "n" shaped angle cap 130 is inserted into the rectangular coupling groove 100-4 formed in the bottom surface of the "yo" shaped retaining wall block 10 of the second layer.
그리고, 상기와 같은 방식으로, 셋째층, 넷째층, 다섯째층, ····등의 "요"자형 옹벽블럭(100)을 순차적으로 쌓는다.Then, in the same manner as described above, the "yo" -shaped retaining wall blocks 100 such as the third layer, the fourth layer, the fifth layer, ..., etc. are sequentially stacked.
따라서, 옹벽의 경사각은 2.8도 이다.Therefore, the inclination angle of the retaining wall is 2.8 degrees.
그런후에, 옹벽으로 형성된 "요"자형 옹벽블럭(100)의 후단부로 흙을 채운다.Then, the soil is filled with the rear end of the "yo" shaped retaining wall block 100 formed by the retaining wall.
도 12a는 본 발명에 따른 보강토 옹벽용 조립체를 이용하여 옹벽을 설치한 제4 실시예의 상태를 나타낸 도면이다.12A is a view showing a state of a fourth embodiment in which the retaining wall is installed by using the reinforcement earth retaining wall assembly according to the present invention.
도 12a에 도시된 바와 같이, 배수성이 좋은 기초 저면에 "요"자형 옹벽블럭(100)을 위치시켜 첫째층을 쌓는다.As shown in FIG. 12A, the first layer is stacked by placing the “yo” retaining wall block 100 on the bottom of the foundation having good drainage.
그리고, "요"자형 옹벽블럭(100)에 형성된 사각형 결합홈(100-1)으로 일정길이 "Y"자형 인터록킹 플레이트(110)의 사각형 기둥(110-3)을 삽입 고정시킨다.Then, the square pillars 110-3 of the “Y” shaped interlocking plate 110 are inserted and fixed into the rectangular coupling groove 100-1 formed in the “yo” shaped retaining wall block 100.
이때, "Y"자형 인터록킹 플레이트(110)에 형성된 밀착부(110-1)의 제2조절턱(110-9)을 도 12b에 도시된 바와 같이, 상기 사각형 결합홈(100-1)의 후벽 상면에 위치되도록 한다. 여기서, 제2조절턱(110-9)의 길이는 P2이다.At this time, the second adjustment jaw (110-9) of the close contact portion (110-1) formed in the "Y" shaped interlocking plate 110, as shown in Figure 12b, of the rectangular coupling groove (100-1) Position it on the top of the rear wall. Here, the length of the second adjustment jaw (110-9) is P2.
이에 따라, 축조의 각도는 1.4도 이다. Accordingly, the angle of construction is 1.4 degrees.
그런후에, 지오그리드(30)의 타원형 체결공(30-1)으로 상기 "Y"자형 인터록킹 플레이트(110)의 밀착부(110-1)를 삽입시킨다.Then, the close contact portion 110-1 of the “Y” shaped interlocking plate 110 is inserted into the elliptical fastening hole 30-1 of the geogrid 30.
이때, 상기 밀착부(110-1)가 타원형 체결공(30-1)을 이루어는 가로바(120-3)와 세로바(120-5)와 완전히 밀착되도록 한다.At this time, the close contact portion 110-1 is in close contact with the horizontal bar (120-3) and the vertical bar (120-5) to form an elliptical fastening hole (30-1).
이에 따라, 지오그리드(30)와 흙과의 마찰력, 인발저항력, 전단응력을 현격하게 향상된다.Accordingly, the friction between the geogrid 30 and the soil, the pullout resistance, the shear stress is significantly improved.
그리고, 상기 밀착부(110-1)의 계단부(110-5)에 "n"자형 앵글 캡(130)을 위치시킨다.Then, the "n" shaped angle cap 130 is positioned on the stepped portion 110-5 of the close contact portion 110-1.
이때, 상기 밀착부(110-1)의 계단부(110-5)와 "n"자형 앵글 캡(130)의 계단부(130-1)가 체결되도록 한다.At this time, the step part 110-5 of the close contact part 110-1 and the step part 130-1 of the "n" shaped angle cap 130 are fastened.
이에 따라, "n"자형 앵글 캡(130)에 형성된 제1조절부(130-7)가 도 12b에 도시된 바와 같이, 상기 사각형 결합홈(100-1)의 후벽 상면에 위치된다.Accordingly, the first adjusting portion 130-7 formed in the "n" shaped angle cap 130 is positioned on the rear wall upper surface of the rectangular coupling groove 100-1 as shown in FIG. 12B.
여기서, 제2조절부(130-7)의 길이는 C1이고, 축조의 각도는 2.4도 이다.Here, the length of the second adjustment unit 130-7 is C1, the angle of construction is 2.4 degrees.
그런후에, 첫째층의 "요"자형 옹벽블럭(100) 상면에 둘째층의 "요"자형 옹벽블럭(100)을 쌓는다.Then, the "yo" shaped retaining wall block 100 of the second layer is stacked on the upper surface of the "yo" shaped retaining wall block 100 of the first layer.
이때, 둘째층의 "요"자형 옹벽블럭(10)의 저면에 형성된 사각형 결합홈(100-4)에, 상기 "n"자형 앵글 캡(130)이 삽입되도록 한다.At this time, the "n" shaped angle cap 130 is inserted into the rectangular coupling groove 100-4 formed in the bottom surface of the "yo" shaped retaining wall block 10 of the second layer.
그리고, 상기와 같은 방식으로, 셋째층, 넷째층, 다섯째층, ····등의 "요"자형 옹벽블럭(100)을 순차적으로 쌓는다.Then, in the same manner as described above, the "yo" -shaped retaining wall blocks 100 such as the third layer, the fourth layer, the fifth layer, ..., etc. are sequentially stacked.
따라서, 옹벽의 경사각은 3.8도 이다.Therefore, the inclination angle of the retaining wall is 3.8 degrees.
그런후에, 옹벽으로 형성된 "요"자형 옹벽블럭(100)의 후단부로 흙을 채운다.Then, the soil is filled with the rear end of the "yo" shaped retaining wall block 100 formed by the retaining wall.
도 13a는 본 발명에 따른 보강토 옹벽용 조립체를 이용하여 옹벽을 설치한 제5 실시예의 상태를 나타낸 도면이다.Figure 13a is a view showing a state of a fifth embodiment in which the retaining wall is installed by using the reinforcement earth retaining wall assembly according to the present invention.
도 13a에 도시된 바와 같이, 배수성이 좋은 기초 저면에 "요"자형 옹벽블럭(100)을 위치시켜 첫째층을 쌓는다.As shown in FIG. 13A, the first layer is stacked by placing the “yo” retaining wall block 100 on the bottom of the foundation having good drainage.
그리고, "요"자형 옹벽블럭(100)에 형성된 사각형 결합홈(100-1)으로 일정길이 "Y"자형 인터록킹 플레이트(110)의 사각형 기둥(110-3)을 삽입 고정시킨다.Then, the square pillars 110-3 of the “Y” shaped interlocking plate 110 are inserted and fixed into the rectangular coupling groove 100-1 formed in the “yo” shaped retaining wall block 100.
이때, "Y"자형 인터록킹 플레이트(110)에 형성된 밀착부(110-1)의 제1조절턱(110-7)을 도 11b에 도시된 바와 같이, 상기 사각형 결합홈(100-1)의 후벽 상면에 위치되도록 한다. 여기서, 제1조절턱(110-7)의 길이는 P1이다.At this time, the first adjustment jaw (110-7) of the close contact portion 110-1 formed on the "Y" shaped interlocking plate 110, as shown in Figure 11b, of the rectangular coupling groove (100-1) Position it on the top of the rear wall. Here, the length of the first adjustment jaw (110-7) is P1.
이에 따라, 축조의 각도는 0.4도 이다. Accordingly, the angle of construction is 0.4 degrees.
그런후에, 지오그리드(30)의 타원형 체결공(30-1)으로 상기 "Y"자형 인터록킹 플레이트(110)의 밀착부(110-1)를 삽입시킨다.Then, the close contact portion 110-1 of the “Y” shaped interlocking plate 110 is inserted into the elliptical fastening hole 30-1 of the geogrid 30.
이때, 상기 밀착부(110-1)가 타원형 체결공(30-1)을 이루어는 가로바(120-3)와 세로바(120-5)와 완전히 밀착되도록 한다.At this time, the close contact portion 110-1 is in close contact with the horizontal bar (120-3) and the vertical bar (120-5) to form an elliptical fastening hole (30-1).
이에 따라, 지오그리드(30)와 흙과의 마찰력, 인발저항력, 전단응력을 현격하게 향상된다.Accordingly, the friction between the geogrid 30 and the soil, the pullout resistance, the shear stress is significantly improved.
그리고, 상기 밀착부(110-1)의 계단부(110-5)에 "n"자형 앵글 캡(130)을 위치시킨다.Then, the "n" shaped angle cap 130 is positioned on the stepped portion 110-5 of the close contact portion 110-1.
이때, 상기 밀착부(110-1)의 계단부(110-5)와 "n"자형 앵글 캡(130)의 계단부(130-1)가 체결되도록 한다.At this time, the step part 110-5 of the close contact part 110-1 and the step part 130-1 of the "n" shaped angle cap 130 are fastened.
이에 따라, "n"자형 앵글 캡(130)에 형성된 제2조절부(130-9)가 도 13b에 도시된 바와 같이, 상기 사각형 결합홈(100-1)의 후벽 상면에 위치된다.Accordingly, as shown in FIG. 13B, the second adjusting part 130-9 formed in the “n” shaped angle cap 130 is positioned on the rear wall upper surface of the rectangular coupling groove 100-1.
여기서, 제2조절부(130-9)의 길이는 C2이고, 축조의 각도는 5.8도 이다.Here, the length of the second adjustment unit 130-9 is C2, the angle of construction is 5.8 degrees.
그런후에, 첫째층의 "요"자형 옹벽블럭(100) 상면에 둘째층의 "요"자형 옹벽블럭(100)을 쌓는다.Then, the "yo" shaped retaining wall block 100 of the second layer is stacked on the upper surface of the "yo" shaped retaining wall block 100 of the first layer.
이때, 둘째층의 "요"자형 옹벽블럭(10)의 저면에 형성된 사각형 결합홈(100-4)에, 상기 "n"자형 앵글 캡(130)이 삽입되도록 한다.At this time, the "n" shaped angle cap 130 is inserted into the rectangular coupling groove 100-4 formed in the bottom surface of the "yo" shaped retaining wall block 10 of the second layer.
그리고, 상기와 같은 방식으로, 셋째층, 넷째층, 다섯째층, ····등의 "요"자형 옹벽블럭(100)을 순차적으로 쌓는다.Then, in the same manner as described above, the "yo" -shaped retaining wall blocks 100 such as the third layer, the fourth layer, the fifth layer, ..., etc. are sequentially stacked.
따라서, 옹벽의 경사각은 6.2도 이다.Therefore, the inclination angle of the retaining wall is 6.2 degrees.
그런후에, 옹벽으로 형성된 "요"자형 옹벽블럭(100)의 후단부로 흙을 채운다.Then, the soil is filled with the rear end of the "yo" shaped retaining wall block 100 formed by the retaining wall.
도 14a는 본 발명에 따른 보강토 옹벽용 조립체를 이용하여 옹벽을 설치한 제6 실시예의 상태를 나타낸 도면이다.14A is a view showing a state of a sixth embodiment in which the retaining wall is installed using the reinforcement earth retaining wall assembly according to the present invention.
도 14a에 도시된 바와 같이, 배수성이 좋은 기초 저면에 "요"자형 옹벽블럭(100)을 위치시켜 첫째층을 쌓는다.As shown in FIG. 14A, the first layer is stacked by placing the “yo” retaining wall block 100 on the bottom of the foundation having good drainage.
그리고, "요"자형 옹벽블럭(100)에 형성된 사각형 결합홈(100-1)으로 일정길이 "Y"자형 인터록킹 플레이트(110)의 사각형 기둥(110-3)을 삽입 고정시킨다.Then, the square pillars 110-3 of the “Y” shaped interlocking plate 110 are inserted and fixed into the rectangular coupling groove 100-1 formed in the “yo” shaped retaining wall block 100.
이때, "Y"자형 인터록킹 플레이트(110)에 형성된 밀착부(110-1)의 제2조절턱(110-9)을 도 12b에 도시된 바와 같이, 상기 사각형 결합홈(100-1)의 후벽 상면에 위치되도록 한다. 여기서, 제2조절턱(110-9)의 길이는 P2이다.At this time, the second adjustment jaw (110-9) of the close contact portion (110-1) formed in the "Y" shaped interlocking plate 110, as shown in Figure 12b, of the rectangular coupling groove (100-1) Position it on the top of the rear wall. Here, the length of the second adjustment jaw (110-9) is P2.
이에 따라, 축조의 각도는 1.4도 이다. Accordingly, the angle of construction is 1.4 degrees.
그런후에, 지오그리드(30)의 타원형 체결공(30-1)으로 상기 "Y"자형 인터록킹 플레이트(110)의 밀착부(110-1)를 삽입시킨다.Then, the close contact portion 110-1 of the “Y” shaped interlocking plate 110 is inserted into the elliptical fastening hole 30-1 of the geogrid 30.
이때, 상기 밀착부(110-1)가 타원형 체결공(30-1)을 이루어는 가로바(120-3)와 세로바(120-5)와 완전히 밀착되도록 한다.At this time, the close contact portion 110-1 is in close contact with the horizontal bar (120-3) and the vertical bar (120-5) to form an elliptical fastening hole (30-1).
이에 따라, 지오그리드(30)와 흙과의 마찰력, 인발저항력, 전단응력을 현격하게 향상된다.Accordingly, the friction between the geogrid 30 and the soil, the pullout resistance, the shear stress is significantly improved.
그리고, 상기 밀착부(110-1)의 계단부(110-5)에 "n"자형 앵글 캡(130)을 위치시킨다.Then, the "n" shaped angle cap 130 is positioned on the stepped portion 110-5 of the close contact portion 110-1.
이때, 상기 밀착부(110-1)의 계단부(110-5)와 "n"자형 앵글 캡(130)의 계단부(130-1)가 체결되도록 한다.At this time, the step part 110-5 of the close contact part 110-1 and the step part 130-1 of the "n" shaped angle cap 130 are fastened.
이에 따라, "n"자형 앵글 캡(130)에 형성된 제2조절부(130-9)가 도 14b에 도시된 바와 같이, 상기 사각형 결합홈(100-1)의 후벽 상면에 위치된다.Accordingly, as shown in FIG. 14B, the second adjusting part 130-9 formed in the “n” shaped angle cap 130 is positioned on the rear wall upper surface of the rectangular coupling groove 100-1.
여기서, 제2조절부(130-9)의 길이는 C2이고, 축조의 각도는 5.8도 이다.Here, the length of the second adjustment unit 130-9 is C2, the angle of construction is 5.8 degrees.
그런후에, 첫째층의 "요"자형 옹벽블럭(100) 상면에 둘째층의 "요"자형 옹벽블럭(100)을 쌓는다.Then, the "yo" shaped retaining wall block 100 of the second layer is stacked on the upper surface of the "yo" shaped retaining wall block 100 of the first layer.
이때, 둘째층의 "요"자형 옹벽블럭(100)의 저면에 형성된 사각형 결합홈(100-4)에, 상기 "n"자형 앵글 캡(130)이 삽입되도록 한다.At this time, the "n" shaped angle cap 130 is inserted into the rectangular coupling groove 100-4 formed in the bottom surface of the "yo" shaped retaining wall block 100 of the second layer.
그리고, 상기와 같은 방식으로, 셋째층, 넷째층, 다섯째층, ····등의 "요"자형 옹벽블럭(100)을 순차적으로 쌓는다.Then, in the same manner as described above, the "yo" -shaped retaining wall blocks 100 such as the third layer, the fourth layer, the fifth layer, ..., etc. are sequentially stacked.
따라서, 옹벽의 경사각은 7.2도 이다.Therefore, the inclination angle of the retaining wall is 7.2 degrees.
그런후에, 옹벽으로 형성된 "요"자형 옹벽블럭(100)의 후단부로 흙을 채운다.Then, the soil is filled with the rear end of the "yo" shaped retaining wall block 100 formed by the retaining wall.
이상과 같이 본 발명은 지오그리드의 체결공에 완전히 삽입 밀착되는 "Y"자형 인터록킹 플레이트를 구비함으로써, 지오그리드와 흙과의 마찰력, 인발저항력, 전단응력을 현격하게 향상시킬 수 있는 효과가 있다.As described above, the present invention is provided with a "마찰" shaped interlocking plate that is completely inserted into and close to the fastening hole of the geogrid, thereby significantly improving the frictional force, pullout resistance, and shear stress between the geogrid and the soil.
특히, 지오그리드의 체결공에 "Y"자형 인터록킹 플레이트의 밀착부가 복수개 설치되는 바, 밀착부에 미치는 응력이 분산됨으로써 더욱 안전한 옹벽을 설치할 수 있는 효과가 있다.In particular, a plurality of contact portions of the "Y" -shaped interlocking plate are installed in the fastening hole of the geogrid, so that the stress on the contact portion is dispersed, thereby providing a safer retaining wall.
또한, 본 발명은 "Y"자형 인터록킹 플레이트와 "n"자형 앵글 캡을 결합하여 사용할 경우, 옹벽의 경사각을 다양하게 이용할 수 있는 효과가 있다.In addition, the present invention has the effect of using a variety of inclination angle of the retaining wall when used in combination with the "캡" shaped interlocking plate and the "n" shaped angle cap.
특히, 좁은 지역의 절개지의 경사면에 옹벽을 설치할 수 있는 효과가 있다.In particular, there is an effect that the retaining wall can be installed on the inclined surface of the incision in the narrow area.
도 1은 일반적인 보강토 옹벽용 조립체를 나타낸 도면,1 is a view showing the assembly for a general reinforced earth retaining wall,
도 2 및 도 3은 도 1의 보강토 옹벽용 조립체를 이용하여 옹벽을 설치한 상태를 나타낸 도면,2 and 3 is a view showing a state in which the retaining wall is installed using the reinforcement earth retaining wall assembly of Figure 1,
도 4는 도 1의 연결핀과 지오그리드의 설치 상태를 나타낸 도면,4 is a view showing the installation state of the connecting pin and the geogrid of FIG.
도 5는 본 발명에 따른 보강토 옹벽용 조립체를 나타낸 도면,5 is a view showing an assembly for a reinforced soil retaining wall according to the present invention,
도 6은 도 5의 "요"자형 옹벽블럭의 저면을 나타낸 도면,6 is a view showing the bottom surface of the "yo" retaining wall block of FIG.
도 7a는 도 5의 "Y"자형 인터록킹 플레이트를 확대한 도면,FIG. 7A is an enlarged view of the “Y” shaped interlocking plate of FIG. 5;
도 7b는 도 5의 "Y"자형 인터록킹 플레이트의 정면도,FIG. 7B is a front view of the “Y” shaped interlocking plate of FIG. 5, FIG.
도 7c는 도 5의 "Y"자형 인터록킹 플레이트의 측면도,FIG. 7C is a side view of the “Y” shaped interlocking plate of FIG. 5, FIG.
도 7d는 도 5의 "Y"자형 인터록킹 플레이트의 평면도,FIG. 7D is a plan view of the “Y” shaped interlocking plate of FIG. 5, FIG.
도 8은 도 5의 앵글 캡을 확대한 도면,8 is an enlarged view of the angle cap of FIG. 5;
도 9a는 본 발명에 따른 보강토 옹벽용 조립체를 이용하여 옹벽을 설치한 제1 실시예의 상태를 나타낸 도면,Figure 9a is a view showing a state of the first embodiment in which the retaining wall is installed using the reinforcement earth retaining wall assembly according to the present invention,
도 9b는 도 9a의 요부 확대 단면도,9B is an enlarged cross-sectional view of the main portion of FIG. 9A;
도 10a는 본 발명에 따른 보강토 옹벽용 조립체를 이용하여 옹벽을 설치한 제2 실시예의 상태를 나타낸 도면,10A is a view showing a state of a second embodiment in which a retaining wall is installed using the reinforcement earth retaining wall assembly according to the present invention;
도 10b는 도 10a의 요부 확대 단면도,10B is an enlarged cross-sectional view of the main portion of FIG. 10A;
도 11a는 본 발명에 따른 보강토 옹벽용 조립체를 이용하여 옹벽을 설치한 제3 실시예의 상태를 나타낸 도면,11A is a view showing a state of a third embodiment in which the retaining wall is installed by using the reinforcement earth retaining wall assembly according to the present invention;
도 11b는 도 11a의 요부 확대 단면도,11B is an enlarged cross-sectional view of the main portion of FIG. 11A;
도 12a는 본 발명에 따른 보강토 옹벽용 조립체를 이용하여 옹벽을 설치한 제4 실시예의 상태를 나타낸 도면,12A is a view showing a state of a fourth embodiment in which the retaining wall is installed by using the reinforcement earth retaining wall assembly according to the present invention;
도 12b는 도 12a의 요부 확대 단면도,12B is an enlarged cross-sectional view of the main portion of FIG. 12A;
도 13a는 본 발명에 따른 보강토 옹벽용 조립체를 이용하여 옹벽을 설치한 제5 실시예의 상태를 나타낸 도면,13A is a view showing a state of a fifth embodiment in which the retaining wall is installed by using the reinforcement earth retaining wall assembly according to the present invention;
도 13b는 도 13a의 요부 확대 단면도,13B is an enlarged cross-sectional view of the main portion of FIG. 13A;
도 14a는 본 발명에 따른 보강토 옹벽용 조립체를 이용하여 옹벽을 설치한 제6 실시예의 상태를 나타낸 도면,14A is a view showing a state of a sixth embodiment in which the retaining wall is installed by using the reinforcement earth retaining wall assembly according to the present invention;
도 14b는 도 14a의 요부 확대 단면도이다.14B is an enlarged cross-sectional view of the main portion of FIG. 14A.
<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>
100 : "요"자형 옹벽블럭100: "Y" shaped retaining wall block
100-1 : 사각형 결합홈100-1: square coupling groove
110 : "Y"자형 인터록킹 플레이트(Inter Locking plate)110: "Y" shaped interlocking plate
110-1 : 밀착부110-1: tight contact
120 : 지오그리드(Geogrid)120: Geogrid
130 : "n"자형 앵글 캡130: "n" shaped angle cap
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2003-0063959A KR100505127B1 (en) | 2003-09-16 | 2003-09-16 | Segmental Block-faced Retaining Wall System |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2003-0063959A KR100505127B1 (en) | 2003-09-16 | 2003-09-16 | Segmental Block-faced Retaining Wall System |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20050027625A KR20050027625A (en) | 2005-03-21 |
KR100505127B1 true KR100505127B1 (en) | 2005-07-29 |
Family
ID=37384853
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR10-2003-0063959A KR100505127B1 (en) | 2003-09-16 | 2003-09-16 | Segmental Block-faced Retaining Wall System |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100505127B1 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100988940B1 (en) | 2009-09-21 | 2010-10-20 | 동양건설(주) | An engineering method for reinforce the slope with porus vegetation block |
KR101141894B1 (en) * | 2011-09-21 | 2012-05-03 | 김수득 | Seashore wave dissipating block and the structure thereof |
KR200463213Y1 (en) | 2012-07-03 | 2012-10-24 | 주식회사동림이엔지 | Fixing pin for plantable retaining wall constructing block |
EP3118377A1 (en) | 2015-07-17 | 2017-01-18 | Eco-Top Co., Ltd. | Prefabricated retaining wall block and method for constructing retaining wall |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20090104213A (en) * | 2008-03-31 | 2009-10-06 | 김성민 | Ply-angle adjustable, plantable retaining wall block assembly of reinforced earth |
KR101006543B1 (en) * | 2008-04-04 | 2011-01-07 | 강구종 | Geogrid structure of retaining wall block made reinforced earth and method constructing the retaining wall |
KR100903057B1 (en) * | 2008-06-24 | 2009-06-18 | 주식회사 행림종합 건축사사무소 | A hexagon block and that of construction method |
CN114199200A (en) * | 2021-11-18 | 2022-03-18 | 佛山市川东磁电股份有限公司 | Building gradient monitoring devices |
CN114722566B (en) * | 2022-03-02 | 2023-07-28 | 中铁二院工程集团有限责任公司 | Stability processing method based on reservoir bank landslide partition |
CN115958436B (en) * | 2022-12-26 | 2024-05-10 | 山东大学 | Device and method for determining right angle cutting and observing cutting process |
-
2003
- 2003-09-16 KR KR10-2003-0063959A patent/KR100505127B1/en not_active IP Right Cessation
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100988940B1 (en) | 2009-09-21 | 2010-10-20 | 동양건설(주) | An engineering method for reinforce the slope with porus vegetation block |
KR101141894B1 (en) * | 2011-09-21 | 2012-05-03 | 김수득 | Seashore wave dissipating block and the structure thereof |
KR200463213Y1 (en) | 2012-07-03 | 2012-10-24 | 주식회사동림이엔지 | Fixing pin for plantable retaining wall constructing block |
EP3118377A1 (en) | 2015-07-17 | 2017-01-18 | Eco-Top Co., Ltd. | Prefabricated retaining wall block and method for constructing retaining wall |
KR20170009571A (en) | 2015-07-17 | 2017-01-25 | 주식회사 에코탑 | Bricks for wall and wall construction method with the bircks |
Also Published As
Publication number | Publication date |
---|---|
KR20050027625A (en) | 2005-03-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7997830B2 (en) | Barrier wall made of sheet-pile components | |
US6416260B1 (en) | Self-connecting, reinforced retaining wall and masonry units therefor | |
KR101103142B1 (en) | Retaining wall structure and construction method of the retaining wall structure | |
KR100505127B1 (en) | Segmental Block-faced Retaining Wall System | |
KR100789210B1 (en) | Land-side protection wall using composite pile connected two piles in a body | |
KR100878716B1 (en) | Coupling Block for Revetment Construction with Vegetation | |
KR102490872B1 (en) | Reinforced earth retaining wall and construction method using tensile force of steel rod piles | |
KR100789209B1 (en) | Land-side protection wall using composite pile connected two piles in a body | |
WO2009082672A1 (en) | Sand and soil internal reinforcement system | |
US20060096180A1 (en) | Retaining wall block and grid system | |
KR100636085B1 (en) | Assembly type retaining wall structure | |
KR200387146Y1 (en) | Coupling Block for Revetment Construction | |
KR200369476Y1 (en) | Segmental Block-faced Retaining Wall System | |
KR200369479Y1 (en) | The land-side protection wall panel | |
KR100724781B1 (en) | A sheathing board | |
KR100680246B1 (en) | Afforestation retaining-wall | |
KR200421809Y1 (en) | A sheathing board | |
KR20090028184A (en) | A retaining wall for using a steel stiffener | |
KR102285192B1 (en) | A Eco-friendly retain wall structure | |
KR102337526B1 (en) | Grid panel type reinforced wall with filier and its construction method | |
KR102511386B1 (en) | Connecting structure of reinforced wall using reinforced block and constructing method thereof | |
JP2957995B1 (en) | Retaining wall backfill frame | |
KR200409796Y1 (en) | Afforestation retaining-wall | |
KR100770559B1 (en) | Retaining wall building fabric | |
GB2454488A (en) | Block panel modules and a tieback wall constructed therefrom |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
A302 | Request for accelerated examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20090722 Year of fee payment: 5 |
|
LAPS | Lapse due to unpaid annual fee |