KR100496619B1 - beam for cut-off wall construction method - Google Patents

beam for cut-off wall construction method Download PDF

Info

Publication number
KR100496619B1
KR100496619B1 KR10-2002-0062019A KR20020062019A KR100496619B1 KR 100496619 B1 KR100496619 B1 KR 100496619B1 KR 20020062019 A KR20020062019 A KR 20020062019A KR 100496619 B1 KR100496619 B1 KR 100496619B1
Authority
KR
South Korea
Prior art keywords
impermeable material
body portion
order wall
wall
connection
Prior art date
Application number
KR10-2002-0062019A
Other languages
Korean (ko)
Other versions
KR20040033118A (en
Inventor
임성철
Original Assignee
임성철
김명률
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 임성철, 김명률 filed Critical 임성철
Priority to KR10-2002-0062019A priority Critical patent/KR100496619B1/en
Publication of KR20040033118A publication Critical patent/KR20040033118A/en
Application granted granted Critical
Publication of KR100496619B1 publication Critical patent/KR100496619B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/14Sealing joints between adjacent sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2450/00Gaskets
    • E02D2450/10Membranes
    • E02D2450/105Membranes impermeable
    • E02D2450/106Membranes impermeable for liquids

Abstract

본 발명의 목적은 하천제방 또는 개착식 굴토공사 시 지하수의 침투를 차단하고, 쓰레기 매립장 또는 폐기물 처리장의 오염물질인 침출수의 유출을 차단하는 차수벽을 설치하는 차수벽 시공방법과 이 방법에 사용되는 빔을 제공하는 데 있다.An object of the present invention is to provide a water barrier wall construction method and a beam used in the method to block the infiltration of groundwater during the river dike or landfill pit construction, and to install a water barrier wall to block the outflow of leachate, which is a pollutant in a landfill or waste treatment plant. To provide.

본 발명의 차수벽 시공방법은, 차수벽을 설치할 위치에 연결 접속부와 주입 파이프가 구비된 빔을 항타기로 소정의 심도(深度)까지 타입(打入)하는 타입공정(A), 이 타입공정에 의하여 타입된 빔을 인발기로 인발(引拔)함과 동시에 지중에 형성된 빔 형상의 공간에 그라우팅 펌프로 불투수성재료를 주입하는 인발/주입공정(B)으로 구성되고; 이 차수벽 시공방법에 사용되는 빔은, 단면 I형상을 가지고 길이 방향으로 신장 형성되는 바디부(15), 이 바디부의 양단 외측에 길이 방향으로 형성되어 인접 위치에 타입되는 다른 빔과 연결시키도록 암, 수로 형성되는 연결 접속부(17), 이 바디부의 양단 내측 모서리 전후에 길이 방향으로 설치되어 불투수성재료의 주입을 안내하는 주입 파이프(19), 이 주입 파이프로 주입되는 불투수성재료에 의한 차수벽의 두께를 증대시키도록 바디부의 하단에 구비된 웹부(21)로 구성되어 있다.The order wall construction method of this invention is a type process (A) which types the beam provided with the connection connection part and the injection pipe in the position to install a order wall to a predetermined depth with a navigator, The type by this type process A drawing / injection process (B) for drawing a beam into a drawing machine and simultaneously injecting an impermeable material into a beam-shaped space formed in the ground with a grouting pump; The beam used in this order wall construction method is a body portion 15 having a cross-sectional I shape and extending in the longitudinal direction, and formed so as to be connected to other beams which are formed in the longitudinal direction on both ends of the body portion and are located in adjacent positions. The connection connecting portion 17 formed by the water, the injection pipe 19 is installed in the longitudinal direction before and after the inner corners of both ends of the body portion to guide the injection of the impermeable material, the thickness of the order wall by the impermeable material injected into the injection pipe It is composed of a web portion 21 provided at the bottom of the body portion to increase.

Description

차수벽 시공방법에 사용되는 빔{beam for cut-off wall construction method}Beam for cut-off wall construction method

본 발명은 차수벽 시공방법과 이 방법에 사용되는 빔에 관한 것으로서, 보다 상세하게는 하천제방 및 지하 대수층(자갈 모래 층)의 침윤선을 차단하거나 쓰레기 매립장 및 폐기물 처리장의 침출수를 차단하는 차수벽을 설치하는 차수벽 시공방법과 이 방법에 사용되는 빔에 관한 것이다.The present invention relates to a method for constructing a barrier wall and a beam used in the method, and more particularly, to install a barrier wall for blocking the infiltration line of the river bank and the underground aquifer (gravel sand layer) or the leachate of the landfill and waste treatment plant. It relates to a method for constructing a barrier wall and a beam used in the method.

일반적으로 하천제방이나 하천 및 바다에 인접하고 투수계수가 높은 대수층으로 형성된 지층의 개착식(open cut) 굴토공사에는 침투수를 차단하는 차수벽의 설치 공사가 수반된다. 하천제방의 경우에는 주로 점토 심벽이 영구 차수벽을 형성하게 되고, 굴토공사의 경우에는 지하수 침투의 차단을 위하여 시트파일(Sheet Pile), 그라우팅 공법, 강제분사교반공법 및 SCW(Soil Cement Wall)에 의하여 연속적으로 차수벽을 형성하게 된다.In general, the open cut pit excavation works formed of aquifers adjacent to river embankments, rivers and seas and having a high permeability coefficient involves installation of a barrier wall to block infiltration water. In the case of river embankment, the main wall of clay is formed permanent permanent wall, and in the case of gulceum construction, it is used by sheet pile, grouting method, forced spray stirring method and SCW (Soil Cement Wall) to block groundwater infiltration. Successively, the order walls are formed.

또한, 쓰레기 매립장 및 폐기물 처리장의 경우에는 침출수에 의한 오염물질의 확산을 방지하도록 대상 부지 외곽에 침출수 차수벽이 설치되어 있다. 이 경우 차수벽은 시트파일, 그라우팅 공법, 슬러리 벽(Slurry Wall, Diaphragm Wall) 및 심층혼합공법을 이용한 SCW에 의하여 형성된다.In the case of a landfill and a waste disposal plant, a leachate order wall is provided outside the target site to prevent the spread of pollutants by leachate. In this case, the order wall is formed by SCW using a sheet pile, grouting method, slurry wall (Slurry Wall, Diaphragm Wall) and deep mixing method.

그러나, 시트파일을 사용하여 차수벽을 설치할 경우에는 인접한 시트파일을 연결하는 연결 접속부 사이로 침투수 및 침출수의 유출을 방지하기 위하여 연결 접속부에 불투수성 팽창막을 부착하여야 하는 불편이 있다.However, in the case of installing the order wall using the sheet pile, it is inconvenient to attach an impermeable expansion membrane to the connecting joint in order to prevent the outflow of permeate and leachate between the connecting joints connecting the adjacent sheet piles.

그라우팅 공법 및 강제분사교반공법으로 차수벽을 설치할 경우에는 차수벽의 균일한 두께확보를 어렵게 하고, 천공 구멍 사이에 불연속면을 발생시킬 가능성이 높다.In the case of installing the order wall by the grouting method and the forced spray stirring method, it is difficult to secure the uniform thickness of the order wall and there is a high possibility of generating discontinuous surfaces between the perforations.

심층혼합공법을 이용한 SCW의 경우에는 원형의 파일을 중첩시킴으로서 연속된 차수벽을 형성할 수 있으나 시공심도가 깊어 수직도의 유지가 용이하지 않을 때에는 하단부에서 파일이 서로 중첩되지 않는 단점이 있다.In the case of the SCW using the deep mixing method, the continuous piles can be formed by superimposing circular piles, but when the construction depth is deep and the maintenance of the vertical degree is not easy, the piles do not overlap each other.

슬러리 벽의 경우에는 가장 확실한 연속 차수벽을 형성할 수 있지만 시공장비의 규모로 인하여 사용상 많은 제약이 따르고, 하천제방의 시공 중에는 경사면 활동이 파괴되며, 장비가 고가인 단점이 있다.In the case of slurry walls, the most reliable continuous order walls can be formed, but due to the size of construction equipment, there are many limitations in use, the slope activity is destroyed during construction of river banks, and the equipment is expensive.

따라서, 본 발명은 상기와 같은 단점들을 해소하고, 하천제방 또는 개착식 굴토공사 시 지하수의 침투를 차단하고, 쓰레기 매립장 또는 폐기물 처리장의 오염물질인 침출수의 유출을 차단하는 차수벽을 설치하는 차수벽 시공방법과 이 방법에 사용되는 빔을 제공하는 데 그 목적이 있다.Accordingly, the present invention solves the above drawbacks, and the water barrier wall construction method for installing a water barrier wall to block the infiltration of groundwater during the river bank or reclamation excavation, and to block the outflow of leachate that is a pollutant in the landfill or waste treatment plant And to provide a beam used in this method.

이 차수벽 시공방법은, 차수벽을 설치할 위치에 연결 접속부와 주입 파이프가 구비된 빔을 항타기로 소정의 심도(深度)까지 타입(打入)하는 타입공정, 이 타입공정에 의하여 타입된 빔을 인발기로 인발(引拔)함과 동시에 지중에 형성된 빔 형상의 공간에 그라우팅 펌프로 불투수성재료를 주입하는 인발/주입공정으로 구성되어 있다.This order wall construction method is a type process in which a beam provided with a connecting connection portion and an injection pipe is installed to a predetermined depth by driving a rider at a position where the order wall is to be installed. At the same time as drawing, it is composed of drawing / injection process that injects impermeable material into the beam-shaped space formed in the ground with a grouting pump.

이 타입공정과 인발/주입공정은 10~20m 거리를 유지하면서 차수벽의 양측에서 각각 진행되어, 빔 타입 시 발생되는 진동이 기 주입된 불투수성재료에 의하여 형성된 차수벽으로 전달되는 것을 최소화한다.This type process and the drawing / injection process are respectively carried out on both sides of the order wall while maintaining a distance of 10 to 20 m, thereby minimizing the transmission of vibration generated in the beam type to the order wall formed by the impermeable material pre-injected.

타입공정은 주입 파이프를 워터 제트 펌프에 연결하여 빔이 타입되는 지중에 압력수를 순환시켜 밀실(密室)한 모래자갈 층을 흩어 빔의 타입을 보다 용이하게 한다.The type process connects an injection pipe to a water jet pump to circulate the pressure water in the ground where the beam is typed, dispersing the tight sand gravel layer to make the beam easier.

인발/주입공정은 빔의 상단에 장착된 진동헤머로 진동을 가하면서 빔을 인발시켜 지중에 형성된 빔 형상 공간에 주입되는 불투수성재료를 보다 밀실하게 한다.The drawing / injection process draws the beam while vibrating with a vibration hammer mounted on the top of the beam, thereby making the impermeable material injected into the beam shape space formed in the ground more tight.

불투수성재료는 투수계수가 1×10-7cm/sec 이하인 시멘트와 벤토나이트 혼합물, 시멘트와 벤토나이트 및 이멀션아스팔트 혼합물로 이루어져 있다.The water impermeable material is composed of a cement and bentonite mixture, a cement and bentonite mixture, and an emulsion asphalt mixture having a permeability coefficient of 1 × 10 −7 cm / sec or less.

이 차수벽 시공방법에 사용되는 빔은,The beam used for this order wall construction method is

단면 I형상을 가지고 길이 방향으로 신장 형성되는 바디부,A body portion elongated in the longitudinal direction with a section I shape,

이 바디부의 양단 외측에 길이 방향으로 형성되어 인접 위치에 타입되는 다른 아이 빔과 연결시키도록 암, 수로 형성되는 연결 접속부,A connecting connection part formed of a female and a male so as to be connected to other eye beams which are formed in the longitudinal direction on both ends of the body part and are adjacent to each other;

이 바디부의 양단 내측 모서리 전후에 길이 방향으로 설치되어 불투수성재료의 주입을 안내하는 주입 파이프,An injection pipe installed in the longitudinal direction before and after inner edges of both ends of the body part to guide injection of an impermeable material

이 주입 파이프로 주입되는 불투수성재료에 의한 차수벽의 두께를 증대시키도록 바디부의 하단에 구비된 웹부로 구성되어 있다.It is comprised by the web part provided in the lower end of a body part so that the thickness of the order wall by the impermeable material injected into this injection pipe may be increased.

본 발명의 이점과 장점은 이하의 바람직한 실시 예를 첨부한 도면에 의거하여 상세히 설명함으로서 보다 명확하게 될 것이다.Advantages and advantages of the present invention will be more apparent from the following detailed description based on the accompanying drawings.

도 1은 본 발명에 따른 차수벽 시공방법의 공정도로서, 차수벽(W)을 설치할 위치의 지중(G)으로 빔(1)을 타입하는 타입공정(A)과, 타입된 빔(1)을 인발하면서 불투수성재료를 주입하는 인발/주입공정(B)이 진행되고 있는 것을 보여주고 있다. 이 불투수성재료가 최종적으로 차수벽(W)을 형성하게 된다. 여기서 빔(1)은 아이 빔 또는 에치 빔으로 구성될 수 있다.1 is a process diagram of a method for constructing a barrier wall according to the present invention, while drawing a type process A and a type beam 1 to type the beam 1 into the ground G at the position where the barrier wall W is to be installed. It shows that the drawing / injection process (B) for injecting an impermeable material is in progress. This water impermeable material finally forms the order wall W. FIG. The beam 1 may be configured as an eye beam or an etch beam.

타입공정(A)은 지중(G)에 차수벽(W)을 형성하기 위하여 항타기(3)로 빔(1)을 연속적으로 타입한다. 도 2에 도시된 바와 같이, 빔(1)은 먼저 타입되어 있는 다른 빔(1a)과 상호 연결되면서 지중(G)으로 타입된다. 이 빔(1)은 차수 효과를 얻고자 하는 지중(G)의 심도까지 타입되어야 한다.The type process A successively types the beam 1 with the driving machine 3 to form the order wall W in the ground G. As shown in FIG. As shown in FIG. 2, the beam 1 is typed into the ground G while interconnected with another beam 1a that is first typed. This beam 1 must be typed up to the depth of the ground G where the order effect is to be obtained.

또한, 타입공정(A)은 항타기(3)의 작동으로만 빔(1)을 소정의 심도로 지중(G)에 타입할 수 있으나, 빔(1)이 타입되는 지중(G)에 워터 제트 펌프(5)로 압력수를 순환시키면서 빔(1)을 타입할 수도 있다.In addition, the type process (A) can type the beam (1) in the ground (G) to a predetermined depth only by the operation of the driving machine (3), but the water jet pump in the ground (G) in which the beam (1) is typed The beam 1 may be typed while circulating the pressure water at (5).

이 워터 제트 펌프(5)에서 공급되는 압력수는 빔(1)의 일측을 통하여 빔(1)의 하단에 밀실하게 되어 있는 모래자갈 층(11)으로 공급되어 모래자갈 층(7)을 흩어 줌으로서 빔(1) 선단의 타입 저항을 저감시키게 된다.The pressure water supplied from the water jet pump 5 is supplied through the one side of the beam 1 to the sand gravel layer 11 which is kept close to the bottom of the beam 1 to disperse the sand gravel layer 7. As a result, the type resistance at the tip of the beam 1 is reduced.

인발/주입공정(B)은 상기 타입공정(A)에 이어서 진행되는 공정으로서, 지중(G)에 타입된 빔(1)을 인발기(9)로 인발하여 빔(1)이 위치하던 지중(G)에 빔 형상의 공간(11)을 형성하고, 이 공간(11)에 불투수성재료(13)를 주입하게 된다.The drawing / injection process (B) is a process that proceeds following the type process (A), and the beam 1 typed on the ground G is drawn to the drawer 9 to make the ground where the beam 1 is located ( A beam-shaped space 11 is formed in G), and the impermeable material 13 is injected into this space 11.

또한, 인발/주입공정(B)은 인발기(9)로 빔(1)을 단순히 인발할 수도 있으나, 빔(1)의 상단에 진동헤머(미도시)를 구비하고, 이 진동헤머의 진동을 빔(1)에 가하면서 인발할 수도 있다.In addition, the drawing / injection process (B) may simply draw the beam (1) with the drawer (9), but is provided with a vibration hammer (not shown) on the top of the beam (1), and the vibration of the vibration hammer It can also draw while applying to the beam (1).

이 진동헤머에서 빔(1)으로 전달되는 진동은 지중(G)에 형성된 빔 형상 공간(11)에 주입되는 불투수성재료(13)로 전달되어 불투수성재료(13)를 밀실하게 하여 최종적으로 차수벽(W)의 강도를 증가시키게 된다.The vibration transmitted from the vibration hammer to the beam 1 is transmitted to the water-impermeable material 13 injected into the beam-shaped space 11 formed in the ground G to close the water-impermeable material 13 to finally seal the order wall W. ) Will increase the strength.

결국, 타입공정(A)에 의하여 빔(1)을 지중에 타입한 후, 인발/주입공정(B)에서 빔(1)을 지중(G)으로부터 인발하면서 빔(1)이 인발된 자리에 불투수성재료(13)를 충진함으로서, 지중(G)에는 도 3에 도시된 바와 같은 차수벽(W)이 형성된다.As a result, after the beam 1 is typed into the ground by the type process A, the water impermeable to the spot where the beam 1 is drawn while drawing the beam 1 from the ground G in the drawing / injection process B is performed. By filling the material 13, the ground wall G is formed with the order wall W as shown in FIG.

이 차수벽(W)을 형성하는 불투수성재료(13)는 시멘트와 벤토나이트 혼합물, 시멘트와 벤토나이트 및 이멀션아스팔트 혼합물로 이루어질 수 있다. 이 불투수성재료(13)의 투수계수는 1×10-7cm/sec 이하이다. 투수계수가 이 수치를 초과하게 되면 차수벽(W)의 차수효과가 떨어진다.The impermeable material 13 forming this order wall W may be made of a cement and bentonite mixture, a cement and bentonite and an emulsion asphalt mixture. The water permeability coefficient of this water impermeable material 13 is 1x10 <-7> cm / sec or less. If the permeability coefficient exceeds this value, the order effect of the order wall (W) is reduced.

또한, 공정 초기에는 타입공정(A)만 진행되고, 이 타입공정(A)이 일정 시간 진행되면 타입공정(A)과 인발/주입공정(B)이 동시에 진행되며, 공정 후기에는 인발/주입공정(B)만 진행됨으로서, 지중(G)에 차수벽(W)이 형성된다.In addition, only the type process (A) is carried out at the beginning of the process, and if this type process (A) proceeds for a predetermined time, the type process (A) and the drawing / injection process (B) are simultaneously performed, and at the end of the process, the drawing / injection process is performed. As only (B) is advanced, the order wall W is formed in the ground G. As shown in FIG.

이와 같이 타입공정(A)과 인발/주입공정(B)이 동시에 진행되면 작업효율은 향상되지만, 빔(1) 타입의 진동이 이미 시공되어 있는 차수벽(W)으로 전달되는 것을 최소화해야 한다.Thus, if the type process (A) and the drawing / injection process (B) proceeds at the same time work efficiency is improved, but the transmission of the beam (1) type to the ordered wall (W) that is already constructed should be minimized.

이를 위하여 타입공정(A)과 인발/주입공정(B)은 도 1에 도시된 바와 같이 10~20m 거리(l)를 유지하면서 진행된다. 이 거리(l)가 10m 미만이면 타발공정(A)의 진동이 기 주입된 불투수성재료(13)에 의하여 형성된 차수벽(W)으로 전달되어 차수벽(W)의 차수 성능을 저하시키게 되고, 이 거리(l)가 20m 초과이면 타발공정(A) 시작 후 인발/주입공정(B)을 시작하기까지 소요 시간을 너무 길게 하여 작업효율을 저하시키게 된다.To this end, the type process (A) and the drawing / injection process (B) are performed while maintaining a distance of 10 to 20 m as shown in FIG. 1. If the distance l is less than 10 m, the vibration of the punching step A is transmitted to the order wall W formed by the impermeable material 13 injected therein, thereby lowering the order performance of the order wall W. If l) is more than 20m, it takes too long to start the drawing / injection process (B) after starting the punching process (A), thereby reducing work efficiency.

도 4는 상기와 같은 차수벽 시공방법에 사용되는 빔의 사시도로서, 바디부(15), 연결 접속부(17), 주입 파이프(19), 그리고 웹부(21)로 구성되어 있다.4 is a perspective view of a beam used in the above-described order wall construction method, which is composed of a body portion 15, a connection connecting portion 17, an injection pipe 19, and a web portion 21.

바디부(15)는 I형상의 단면을 가지고 길이 방향으로 신장 형성되어 있다. 이 바디부(15)는 항타기(3)의 타격력과 인발기(9)의 인발력에 변형되지 않고 안정된 상태를 유지할 수 있는 내구성을 가져야 한다. 이 바디부(15)의 길이는 시공될 차수벽(W)의 심도에 따라 적절하게 설정된다.The body portion 15 has an I-shaped cross section and is elongated in the longitudinal direction. This body portion 15 should have a durability that can maintain a stable state without being deformed by the blow force of the driving machine 3 and the pull force of the drawer 9. The length of the body portion 15 is appropriately set according to the depth of the order wall W to be constructed.

연결 접속부(17)는 지중(G)에 차수벽(W)을 시공하기 위하여 여러 개의 아이 빔(1, 1a)을 연속적으로 타입 설치할 때 이웃하는 빔(1, 1a)을 상호 일체로 연결시켜 준다. 따라서 이 연결 접속부(17)는 바디부(15)의 양단 외측에 각각 길이 방향으로 형성되어 있다. 일측에는 암 연결 접속부(17a)가, 다른 일측에는 수 연결 접속부(17b)가 각각 형성되어 있다. 즉 도 2에서와 같이, 빔(1)의 암 연결 접속부(17a)는 이웃한 빔(1a)의 수 연결부(17a)에 결합되어 있다.The connection connecting portion 17 connects the neighboring beams 1 and 1a integrally with each other when successively installing the plurality of eye beams 1 and 1a in order to construct the order wall W in the ground G. Therefore, this connection connection part 17 is formed in the longitudinal direction in the both ends outer side of the body part 15, respectively. The female connection connection part 17a is formed in one side, and the male connection connection part 17b is formed in the other side, respectively. That is, as shown in FIG. 2, the female connecting portion 17a of the beam 1 is coupled to the male connecting portion 17a of the neighboring beam 1a.

주입 파이프(19)는 타입된 아이 빔(1)의 인발에 따라 불투수성재료(13)의 주입을 안내할 수 있도록 구성되어 있다. 또한 이 주입 파이프(19)는 상기한 바와 같이 워터 제트 펌프(5)에 연결하여 빔(1)이 타입되는 지중(G)에 압력수를 순환시킬 수도 있도록 바디부(15)의 양단 내측 모서리 전후에 길이 방향으로 설치되어 있다.The injection pipe 19 is configured to guide the injection of the impermeable material 13 in accordance with the drawing of the typed eye beam 1. In addition, the injection pipe 19 is connected to the water jet pump 5 as described above, and before and after the inner edges of both ends of the body portion 15 so as to circulate the pressure water in the ground G where the beam 1 is typed. Is installed in the longitudinal direction.

바디부(15)에 연결 접속부(17) 및 주입 파이프(19)를 구비한 빔(1)은 그 일측 선단에 웹부(21)를 구비하고 있다. 이 웹부(21)는 항타기(1)의 타격력에 의하여 바디부(15)가 지중(G)으로 원활히 타입되도록 도 5에 도시된 바와 같이 그 하단과 상단 및 측단이 경사지게 형성되어 있다.The beam 1 having the connecting portion 17 and the injection pipe 19 in the body portion 15 has a web portion 21 at one end thereof. As shown in FIG. 5, the web portion 21 is formed to be inclined at a lower end, an upper end, and a side end so that the body 15 is smoothly typed into the ground G by the striking force of the driving machine 1.

또한, 이 웹부(21)는 빔(1)의 타입 평면을 결정하여 주입 파이프(19)로 주입되는 불투수성재료(13)에 의한 차수벽(W)의 두께를 결정하게 된다. 즉 이 웹부(21)의 평단면적을 크게 하면 차수벽(W)의 두께가 두꺼워지고, 반대로 웹부(21)의 평단면적을 작게 하면 차수벽(W)의 두께가 얇아진다.In addition, the web portion 21 determines the type plane of the beam 1 to determine the thickness of the order wall W by the impermeable material 13 injected into the injection pipe 19. That is, when the flat cross-sectional area of the web portion 21 is increased, the thickness of the order wall W becomes thick. On the contrary, when the flat cross-sectional area of the web portion 21 is reduced, the thickness of the order wall W becomes thin.

도 6은 본 발명에 따른 다른 실시 예인 빔의 연결 상태 평면도로서, 도 2 내지 도 5의 연결 접속부(17)와 다른 연결 접속부(23)를 예시하고 있다.FIG. 6 is a plan view illustrating a connection state of a beam according to another embodiment of the present invention, and illustrates a connection connection unit 23 different from the connection connection unit 17 of FIGS. 2 to 5.

즉, 도 2 내지 도 5의 빔(1) 연결 접속부(17)는 원형의 암, 수 연결 접속부(17a, 17b)로 구성되어 있는 데, 도 6의 연결 접속부(23)는 사각형의 암, 수 연결 접속부(23a, 23b)로 구성되어 있다.That is, the beam 1 connection connecting portion 17 of FIGS. 2 to 5 is composed of a circular female and male connection connecting portions 17a and 17b. The connection connecting portion 23 of FIG. It is comprised by the connection connection part 23a, 23b.

따라서, 원형의 연결 접속부(17)를 가지는 도 2 내지 도 5의 빔(1)은 곡선으로 형성되는 차수벽(W)의 설치에 용이하게 사용될 수 있고, 사각형의 연결 접속부(23)를 가지는 도 6의 빔(1)은 직선으로 형성되는 차수벽(W)의 설치에 용이하게 사용될 수 있다.Accordingly, the beam 1 of FIGS. 2 to 5 having a circular connecting connection 17 can be easily used for installation of the ordered wall W formed in a curved shape, and FIG. 6 having a rectangular connecting connection 23. The beam 1 of can be easily used for installation of the order wall W formed in a straight line.

그리고, 이러한 연결 접속부(17, 23)는 원형 및 사각형뿐만 아니라 다양한 모양으로 형성될 수 있다.In addition, the connection connectors 17 and 23 may be formed in various shapes as well as circular and rectangular.

이 연결 접속부(17, 23)가 원형 또는 사각형과 같이 중공 구조의 폐쇄 단면을 형성하는 경우에는 빔(1)의 인발 전에 압력수를 순환시켜 연결 접속부(17) 주위의 토립자를 제거하여 차수벽(W)의 연속성을 확보할 수 있게 한다.When the connection connecting portions 17 and 23 form a closed cross section of a hollow structure, such as a circle or a square, the pressure water is circulated before the drawing of the beam 1 to remove the torticles around the connection connecting portion 17 to reduce the order wall W. To ensure continuity.

이 차수벽 시공방법은 상기와 같은 빔을 사용하는 타입공정과 인발/주입공정으로 이루어지며, 타입공정에서 연결 접속부와 주입 파이프를 구비한 빔을 소정의 심도까지 타입하고, 인발/주입공정에서 타입된 빔을 인발과 동시에 지중에 형성된 빔 형상의 공간에 불투수성재료를 주입하여 차수벽을 시공함으로서, 시트파일을 사용할 때 연결 접속부에 불투수성 팽창막을 부착하여야 하는 불편을 제거할 수 있고, 그라우팅 공법 및 강제분사교반공법에서 야기되는 차수벽의 균일한 두께확보에 대한 어려움 및 천공 구멍 사이에 불연속면을 발생시킬 가능성을 제거할 수 있으며, 심층혼합공법을 이용한 SCW의 경우에서 발생되는 깊은 시공심도에서 수직도의 유지가 어려워 하단부에서 파일이 서로 비중첩되는 현상을 방지할 수 있고, 슬러리 벽의 경우 시공장비의 규모로 인하여 받게 되는 사용상 제약 및 하천제방의 시공 중에 발생되는 경사면 활동 파괴를 방지할 수 있다.This order wall construction method consists of a type process using a beam as described above and a draw / injection process. In the type process, a beam having a connection connection part and an injection pipe is typed to a predetermined depth, By drawing the beam and injecting the impermeable material into the beam-shaped space formed in the ground at the same time, constructing the barrier wall, it is possible to eliminate the inconvenience of attaching the impermeable expansion membrane to the connecting connection when using the sheet pile, grouting method and forced spray bridge Difficulties in securing the uniform thickness of the order wall caused by the semi-construction method and the possibility of generating discontinuities between the perforations can be eliminated, and it is difficult to maintain the verticality at the deep construction depth generated in the case of SCW using the deep mixing method. In the lower part, the piles can be prevented from overlapping each other. It is possible to prevent the destruction of slope activities that occur during the construction of a pharmaceutical factory in use and rivers are subjected due to the scale of non-banks.

도 1은 본 발명에 따른 차수벽 시공방법의 공정도.1 is a process chart of the order wall construction method according to the present invention.

도 2는 본 발명에 따른 빔의 연결 상태 평면도.Figure 2 is a plan view of the connection state of the beam according to the present invention.

도 3은 본 발명으로 시공된 차수벽의 평면도.Figure 3 is a plan view of the order wall constructed with the present invention.

도 4는 본 발명의 차수벽 시공방법에 사용되는 빔의 사시도.Figure 4 is a perspective view of the beam used in the order wall construction method of the present invention.

도 5는 도 4의 A-A선에 따른 단면도.5 is a cross-sectional view taken along the line A-A of FIG.

도 6은 본 발명에 따른 다른 실시 예인 빔의 연결 상태 평면도.Figure 6 is a plan view of the connection state of another embodiment according to the present invention.

*도면의 주요 부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *

1 : 빔 3 : 항타기1: beam 3: driving

5 : 워터 제트 펌프 7 : 모래자갈 층5: water jet pump 7: sand gravel layer

9 : 인발기 11 : 빔 형상의 공간9: drawer 11: beam-shaped space

13 : 불투수성재료 15 : 바디부13: impermeable material 15: body part

17, 23 : 연결 접속부 17a, 23a : 암 연결 접속부17, 23 connection connection part 17a, 23a: female connection connection part

17b, 23b : 수 연결 접속부 19 : 주입 파이프17b, 23b: male connection connection 19: injection pipe

21 : 웹부 G : 지중21: Web Part G: Underground

W : 차수벽W: Order wall

Claims (6)

단면 I형상을 가지고 길이 방향으로 신장 형성되는 바디부(15)와;A body portion 15 having a cross-sectional I shape and extending in the longitudinal direction; 상기 바디부(15)의 양단 외측에 길이 방향으로 형성되어 인접 위치에 타입되는 다른 빔과 연결시키도록 중공 구조의 폐쇄단면을 갖는 암수로 형성되는 연결 접속부(17)와;A connection connecting portion (17) formed in a lengthwise direction on both ends of the body portion (15) and formed of a male and female having a closed cross section of a hollow structure so as to connect with other beams of a type adjacent to each other; 상기 바디부(15)의 양단 내측 모서리 전후에 길이 방향으로 설치되어 불투수성재료의 주입을 안내하는 주입 파이프(19) 및;An injection pipe 19 installed in a longitudinal direction before and after inner edges of both ends of the body part 15 to guide injection of an impermeable material; 상기 주입 파이프(19)로 주입되는 불투수성재료에 의한 차수벽의 두께를 증대시키도록 상기 바디부(15)의 하단에 구비된 웹부(21)를 포함하는 차수벽 시공방법에 사용되는 빔.And a web portion (21) provided at the lower end of the body portion (15) to increase the thickness of the order wall by the impermeable material injected into the injection pipe (19). 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete
KR10-2002-0062019A 2002-10-11 2002-10-11 beam for cut-off wall construction method KR100496619B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2002-0062019A KR100496619B1 (en) 2002-10-11 2002-10-11 beam for cut-off wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2002-0062019A KR100496619B1 (en) 2002-10-11 2002-10-11 beam for cut-off wall construction method

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR20-2002-0030394U Division KR200300969Y1 (en) 2002-10-11 2002-10-11 cut-off wall construction beam

Publications (2)

Publication Number Publication Date
KR20040033118A KR20040033118A (en) 2004-04-21
KR100496619B1 true KR100496619B1 (en) 2005-06-28

Family

ID=37332657

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2002-0062019A KR100496619B1 (en) 2002-10-11 2002-10-11 beam for cut-off wall construction method

Country Status (1)

Country Link
KR (1) KR100496619B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102184081B1 (en) 2020-05-20 2020-11-27 강창구 Construction method for perforating goround bore using inverse casing
KR102233572B1 (en) 2020-05-20 2021-03-29 강창구 Inverse casing for perforating ground bore and inverse casing manufacturing method thereof

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101135652B1 (en) * 2008-08-19 2012-04-13 김일 Pulling method of pile
CN106759264A (en) * 2016-11-16 2017-05-31 新疆兵团水利水电工程集团有限公司 One kind grouting pipe network and its construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62163533U (en) * 1986-04-09 1987-10-17
US4877357A (en) * 1987-12-10 1989-10-31 Funderingstechnieken Verstraeten B.V. Method and apparatus for making a slurry trench or wall in the soil

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62163533U (en) * 1986-04-09 1987-10-17
US4877357A (en) * 1987-12-10 1989-10-31 Funderingstechnieken Verstraeten B.V. Method and apparatus for making a slurry trench or wall in the soil

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102184081B1 (en) 2020-05-20 2020-11-27 강창구 Construction method for perforating goround bore using inverse casing
KR102233572B1 (en) 2020-05-20 2021-03-29 강창구 Inverse casing for perforating ground bore and inverse casing manufacturing method thereof

Also Published As

Publication number Publication date
KR20040033118A (en) 2004-04-21

Similar Documents

Publication Publication Date Title
KR20100068597A (en) A shoring method using arch plate pile and h-pile
KR100832490B1 (en) A foundation method of continuous and cut off wall by overlap casing
CN102359112A (en) Method for bracing foundation pit by using steel box piles
KR101065017B1 (en) A shoring method using arch plate pile and H-Pile
US10669687B1 (en) Systems and methods for constructing retaining wall structure and well point in granular soils under groundwater level
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
CN111236387A (en) Construction method for connecting newly-built sewage pipe with existing sewage pipe
KR100496619B1 (en) beam for cut-off wall construction method
KR200300969Y1 (en) cut-off wall construction beam
JP4088871B2 (en) Impermeable wall structure and impermeable wall structure using the impermeable wall
US5490743A (en) System for installing material in the ground
CN105714832A (en) Deep-foundation-pit large-sized precast building envelope and construction method
KR100507983B1 (en) Method for piling sheet in the base rock
CN215715515U (en) Municipal pipe network construction supporting integrated structure under unfavorable geological conditions
KR102325623B1 (en) Construction method of retaining wall
CN205502021U (en) UH goes along with sb. to guard him stagnant water structure
JP4888293B2 (en) Earth retaining wall made of parent pile sheet pile, water stop structure of earth retaining wall made of parent pile side sheet pile, construction method of earth retaining wall made of parent pile side sheet pile, and retaining wall of earth retaining wall made of parent pile side sheet pile Water method
CN211690401U (en) Impervious wall structure and ecological seepage-control solid bed system
RU2209268C1 (en) Process of development of foundation pit
WO2009139510A1 (en) Construction method for continuous cut-off wall using overlap casing
JP4905296B2 (en) Method for constructing retaining wall and retaining wall
JP2004162325A (en) Impervious construction method for controlling revetment
KR200297427Y1 (en) Retaining Pile for Retaining Wall Engineer
KR100538739B1 (en) Pile for sheet-pile wall and construction method using that
CN115233719B (en) Large-area foundation reinforcement method and system

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20090430

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee