KR100485194B1 - Interception device of pollution matter and construction method of it - Google Patents

Interception device of pollution matter and construction method of it Download PDF

Info

Publication number
KR100485194B1
KR100485194B1 KR10-2002-0004303A KR20020004303A KR100485194B1 KR 100485194 B1 KR100485194 B1 KR 100485194B1 KR 20020004303 A KR20020004303 A KR 20020004303A KR 100485194 B1 KR100485194 B1 KR 100485194B1
Authority
KR
South Korea
Prior art keywords
film
plot
anchor block
prevention device
pollution prevention
Prior art date
Application number
KR10-2002-0004303A
Other languages
Korean (ko)
Other versions
KR20030063939A (en
Inventor
김현철
Original Assignee
김현철
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김현철 filed Critical 김현철
Priority to KR10-2002-0004303A priority Critical patent/KR100485194B1/en
Publication of KR20030063939A publication Critical patent/KR20030063939A/en
Application granted granted Critical
Publication of KR100485194B1 publication Critical patent/KR100485194B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B15/00Cleaning or keeping clear the surface of open water; Apparatus therefor
    • E02B15/04Devices for cleaning or keeping clear the surface of open water from oil or like floating materials by separating or removing these materials
    • E02B15/08Devices for reducing the polluted area with or without additional devices for removing the material
    • E02B15/085Details of connectors
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63CLAUNCHING, HAULING-OUT, OR DRY-DOCKING OF VESSELS; LIFE-SAVING IN WATER; EQUIPMENT FOR DWELLING OR WORKING UNDER WATER; MEANS FOR SALVAGING OR SEARCHING FOR UNDERWATER OBJECTS
    • B63C9/00Life-saving in water
    • B63C9/21Boats, rafts, buoys or the like, characterised by signalling means, e.g. lights, reflectors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B15/00Cleaning or keeping clear the surface of open water; Apparatus therefor
    • E02B15/04Devices for cleaning or keeping clear the surface of open water from oil or like floating materials by separating or removing these materials
    • E02B15/08Devices for reducing the polluted area with or without additional devices for removing the material
    • E02B15/0857Buoyancy material
    • E02B15/0885Foam
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/02Stream regulation, e.g. breaking up subaqueous rock, cleaning the beds of waterways, directing the water flow
    • E02B3/023Removing sediments

Abstract

본 발명은 오탁방지장치의 시공방법에 관한 것으로, 보다 상세하게는 하천, 해안 또는 해저에서의 매립준설공사시 발생되는 오탁수가 주변의 하천수나 해수로 확산되는 것을 차단하는 오탁방지장치의 설치 및 해체가 용이하고, 심야에도 오탁방지장치의 영역을 식별할 수 있는 오탁방지장치의 시공방법에 관한 것이다.The present invention relates to a construction method of a pollution prevention device, and more particularly, the installation and dismantling of a pollution prevention device that prevents the contamination of water generated during landfill dredging in rivers, coasts or seabeds to the surrounding streams or seawater The present invention relates to a construction method of a pollution prevention device that can be easily identified and can identify the area of the pollution prevention device even in the middle of the night.

본 발명의 목적은 오탁방지장치의 결합구조가 간단하여 설치 및 해체가 용이하여 시공시간 및 비용이 절감되고, 오탁방지막의 부구인 플롯(float)에 조명수단을 설치하여 야간에도 식별이 가능토록 함으로써 오탁방지장치의 영역을 표시하는 경계선의 기능과 조업선박을 안내하는 기능을 행할 수 있을 뿐만 아니라, 플롯(float)을 재활용하여 사용함으로써 산업폐기물을 감소시킬 수 있으며, 오탁방지장치를 인공어초형 앵커블록으로 해저에 고정함으로써 어류자원을 보호하고 증식시킬 수 있는 오탁방지장치 및 그 시공방법을 제공함에 있다.The object of the present invention is to simplify the installation and disassembly of the contaminant prevention device to facilitate the installation and dismantling, and to reduce the construction time and cost, by installing a lighting means in the float (float) of the contaminant prevention film to enable identification at night Not only can it function as a boundary line to mark the area of the pollution prevention device and guide the operation vessel, it can reduce the industrial waste by recycling the float, and the pollution prevention device can be used as the artificial reef type anchor block. The present invention provides a pollution prevention device and a construction method thereof that can protect and multiply fish resources by fixing them to the seabed.

상기의 목적을 달성하기 위한 본 발명의 구성은, 해안 또는 해저에서의 매립준설공사시 발생되는 오탁수가 주변의 하천수나 해수로 확산되는 것을 차단하는 오탁방지장치를 설치함에 있어서, 상기 오탁방지장치의 설치될 범위를 설정하여 막체를 재단하고 다수개의 보강벨트(2,4,7)를 재봉하여 오탁방지막(1)을 제작하고, 내부에 램프(27)가 장착되게 원형체의 플롯(10)을 사출성형하는 오탁방지막 및 플롯제작단계와; 현장으로 운반된 상기 오탁방지막(1)의 상부보강벨트(2)에 상기 플롯(10)의 체결편(15)과 보강플레이트(17)를 각각 대응되게 위치하여 결합/고정하고, 상기 플롯(10)의 양측에 형성된 로프체결고리(13)에 플롯연결로프로(12)상호 연결한 후, 상기 상부보강벨트(2)의 제2체결홈(2a)에 고정하는 플롯결합단계와; 상기 오탁방지막(1)에 연결될 앵커블록을 무세골재 콘크리트를 사용하여 플랑크톤의 자유로운 이동 및 부착 어패류의 서식공간을 형성할 수 있도록 인공어초형 앵커블록(30)으로 양생하는 앵커블록 제작단계와; 상기 오탁방지막(1)이 설치된 영역을 야간에도 식별가능하도록 상기 플롯(10)에 전구(25)가 내장된 중공형의 전구보호관(26)을 설치하고, 상기 램프(27)를 커넥터(28)로 연결하여 타이머(21)와 조도감지센서(22)에 의해 외부의 전원(20)에 인가하도록 설치하는 조명수단의 설치단계와; 상기 조명수단이 설치된 오탁방지막(1)과 상기 인공어초형 앵커블록(30)을 해안의 공사현장으로 인양한 후, 길이조절용 클립(37)과 와이어로프(38)로 상호 연결하여 상기 인공어초형 앵커블록(30)을 해저에 설치하는 자재인양 및 조립단계로 이루어지는 것을 특징으로 한다.The construction of the present invention for achieving the above object, in the installation of a pollution prevention device for preventing the contamination of the water generated during the landfill dredging work in the coast or seabed to the surrounding river or sea water, Set the range to be installed to cut the membrane and sew a plurality of reinforcing belts (2, 4, 7) to produce a stain prevention film (1), and to eject the plot (10) of the circular body so that the lamp 27 is mounted therein Shaping prevention film and plotting step of forming; The fastening pieces 15 and the reinforcing plate 17 of the plot 10 are respectively located on the upper reinforcing belts 2 of the anti-fouling film 1 transported to the site to be coupled / fixed, respectively, and the plot 10 After connecting the rope connection ring (13) formed on both sides of the cross-connected connection rope (12), and the second coupling groove (2a) of the upper reinforcing belt (2); Anchor block manufacturing step of curing the anchor block to be connected to the antifouling film (1) to artificial reef-type anchor block 30 to form a space for free movement of the plankton and attached seafood using the fine aggregate concrete; A hollow bulb protection tube 26 having a light bulb 25 embedded therein is installed on the plot 10 so that the area where the antifouling film 1 is installed can be identified even at night, and the lamp 27 is connected to the connector 28. An installation step of the lighting means installed to be applied to the external power source 20 by the timer 21 and the illumination sensor 22; After lifting the pollution prevention film (1) and the artificial reef type anchor block 30 is installed to the coastal construction site, the artificial reef type anchor block by interconnecting with the length adjustment clip 37 and the wire rope 38 (30) is characterized in that it consists of the material lifting and assembly step of installing on the seabed.

Description

오탁방지장치의 시공방법{Interception device of pollution matter and construction method of it}Interception device of pollution matter and construction method of it}

본 발명은 오탁방지장치의 시공방법에 관한 것으로, 보다 상세하게는 하천, 해안 또는 해저에서의 매립준설공사시 발생되는 오탁수가 주변의 하천수나 해수로 확산되는 것을 차단하는 오탁방지장치의 설치 및 해체가 용이하고, 제품의 내구성이 뛰어나며 심야에도 오탁방지장치의 영역을 식별할 수 있는 오탁방지장치의 시공방법에 관한 것이다.The present invention relates to a construction method of a pollution prevention device, and more particularly, the installation and dismantling of a pollution prevention device that prevents the contamination of water generated during landfill dredging in rivers, coasts or seabeds to the surrounding streams or seawater The present invention relates to a construction method of an anti-fouling device that is easy to use, has excellent durability, and can identify an area of an anti-fouling device even at night.

일반적으로, 하천, 해안 또는 해저에서 준설공사, 축조공사 또는 간척공사를 할 때는 토사 또는 부유물질이 함유된 오탁수가 발생되어 공사장 인근의 수중으로 확산되므로 공사지역의 생태계에 영향을 줌은 물론이고, 주변 어장을 황폐화 시키거나 수자원을 황폐하시키므로 오탁수가 주변의 하천수나 해수로 확산되지 않고 일정한 구역내에 격리되도록 하기 위하여 공사장 주위에 오탁방지장치를 설치하고 있다.In general, when dredging, construction, or reclamation work in rivers, coasts or seabeds, soil water or soil containing suspended solids is generated and diffused into the water near the construction site, thus affecting the ecosystem of the construction area. As it destroys the surrounding fisheries or wastes the water resources, pollution prevention devices are installed around the construction site so that the polluted water does not spread to the surrounding rivers or seawater, but is segregated within a certain area.

상기 오탁방지장치는 토사와 같은 해상 부유물을 격리하는 막체등으로 제작된 오탁방지막의 상단에 플롯(float)을 부착하고 오탁방지막의 하단을 해저면에 고정시키게 되었다.The antifouling device is attached to the float (top) of the top of the antifouling film made of a membrane to isolate the sea floating, such as earth and sand and fixed to the bottom of the antifouling film.

이러한 오탁방지장치에 사용되는 오탁방지막은 공사 현장의 자연환경 조건에 따라 높이, 길이 등의 규격을 조절하는 것은 물론이고, 오탁 방지막을 구성하는 막체의 재질을 선택 사용하여야 한다.The antifouling film used in the antifouling device should not only adjust the standard such as height and length according to the natural environment conditions of the construction site, but also select and use the material of the membrane constituting the antifouling film.

예를들면, 강이나 바다에서 공사가 진행되는 경우에는 비중이 1.1 이상이고 내수성이 강한 폴리프로필렌 막체를 오탁방지막으로 사용하는바, 물의 유속, 풍향, 조류의 방향등을 고려하여 오탁방지막을 지지하는 보조 수단을 부설하여야 한다.For example, when construction is underway in a river or sea, a polypropylene membrane having a specific gravity of 1.1 or more and having a high water resistance is used as an antifouling membrane. The antifouling membrane is supported in consideration of water flow rate, wind direction, and algae direction. Auxiliary means should be provided.

즉, 조류의 흐름이 빠르지 않고 방향이 일정하며, 바람의 영향을 받지 아니하는 공사 현장에는 오탁방지막에 플롯(float)만을 부착하여 설치할 수 있으나, 파도가 심하고 조류의 속도가 빠르며 조류의 방향의 수시로 변하고 바람의 영향을 크게 받는 해안공사현장, 예를들면 외항에 설치하는 오탁방지막은 압력을 견딜 수 있도록 설계되어야 한다.In other words, the flow of algae is not fast, the direction is constant, and construction sites that are not affected by wind can be installed by attaching only floats to the antifouling film, but the waves are severe, the speed of algae is high, and the direction of algae Coastal construction sites that are changed and greatly influenced by wind, for example, antifouling films installed in the outer port, should be designed to withstand the pressure.

예를들면, 대한민국 서해안 영종도에 건설하는 수도권 공항건설 공사장 주변의 해역에서는 유속의 51.7∼226.6cm/s이고, 조량은 137.8×106∼1207.3×106m3이며, 조향은 31°∼278°로 나타나므로 이 지역에 2.2m×20m의 포지 150개를 연결하여 오탁방지막을 설치하는 경우, 오탁방지막이 받는 최대 압력은 426.94MPa, 즉 426.94×106N/m2으로 나타나게 된다.For example, in the area around the airport construction site in Yeongjong Island, west coast of Korea, the flow rate is 51.7 ~ 226.6cm / s, the volume is 137.8 × 106 ~ 1207.3 × 106m3, and the steering is 31 ° ~ 278 °. In the case of installing an antifouling film by connecting 150 forge of 2.2m × 20m in this area, the maximum pressure of the antifouling film is 426.94MPa, that is, 426.94 × 10 6 N / m 2 .

따라서, 이러한 지역에 설치되는 오탁방지막은 최소한 전술한 압력에 유지될 수 있도록 제작되어야 한다.Therefore, the antifouling film installed in such an area should be manufactured so that it can be maintained at least at the above-mentioned pressure.

그러나, 태풍과 같은 최악의 해상 조건에서는 전술한 압력보다 더 큰 압력을 받게되므로 실제적으로 이러한 기상조건하에서는 오탁방지막에 부이만 부착된 오탁 방지장치로는 전술한 큰 압력에 견딜수 없게 된다.However, in the worst sea conditions such as typhoons, the pressure is greater than the above-mentioned pressure, and therefore, under such weather conditions, the stain protection device attached only to the anti-fouling film cannot withstand the above-mentioned large pressure.

특히, 해안 공사에서는 오탁방지막을 설치하는 길이가 수km 정도로 길어질수도 있는바, 이와같은 긴 단일 오탁방지막을 제작하는 것은 실제적으로 불가능하므로 수십개 내지 수백개의 오탁방지막을 연결하여 사용하여야 한다.In particular, in coastal construction, the length of the antifouling film may be set to be several kilometers long, so it is practically impossible to manufacture such a long single antifouling film. Therefore, dozens to hundreds of antifouling films should be used in connection.

상기와 같, 종래의 오탁방지막은 상단부의 플롯(float)을 고정하게 되는데, 이 경우 폴리프로필렌수지의 막체에 볼트와 너트를 고정하는 것으로, 그 결합강도가 낮아 오탁방지막에 가해지는 압력이 크면 오탁방지막을 서로 연결하는 플롯(float)이 파손될 수도 있고, 그 시공과정이 복잡한 문제점이 있었다.As described above, the conventional antifouling film is to fix the float (float) of the upper end, in this case by fixing the bolt and nut to the membrane of the polypropylene resin, when the pressure applied to the antifouling film is low, the stain is high Plots connecting the barrier films to each other may be broken, and the construction process has a complicated problem.

그리고, 오탁방지막을 해저에 고정하는 앵커블록은 콘크리트로 제작하여 사용하므로, 장시간 해저에 방치하게 되면 생태계를 파괴할 수 있어, 이를 다시 제거제거해야 하는 후처리 작업이 불편한 단점이 있었다.In addition, since the anchor block fixing the antifouling film on the sea floor is made of concrete and used, the ecosystem may be destroyed when left on the sea floor for a long time.

또한, 상기 오탁방지막에는 별도의 표시수단이 없어 야간에는 오탁방지막의 설치영역을 식별하기가 어려웠으며, 이로 인해 불측의 사고로 어선이나 조업선박에 걸려 상기 오탁방지막이 손상될 위험이 있을 뿐만 아니라, 소형 어선이 좌초될 수 있는 문제점이 있었다.In addition, there is no separate display means on the antifouling film, so it was difficult to identify the installation area of the antifouling film at night. As a result, there is a risk of damaging the antifouling film by being caught on a fishing boat or a fishing vessel due to an accident. There was a problem that a fishing boat could be stranded.

본 발명은 상기한 제반 문제점을 해결하기 위해 안출된 것으로서, 본 발명의 목적은 하천, 해안 또는 해저에서의 매립준설공사시 발생되는 오탁수가 주변의 하천수나 해수로 확산되는 것을 차단하는 오탁방지장치의 설치 및 해체가 용이하고, 제품의 내구성이 뛰어나며 심야에도 오탁방지장치의 영역을 식별할 수 있는 오탁방지장치의 시공방법을 제공하는데 있다.상기 목적을 달성하기 위한 본 발명은, 해안 또는 해저에서의 매립준설공사시 발생되는 오탁수가 주변의 하천수나 해수로 확산되는 것을 차단하는 오탁방지장치의 시공방법에 있어서, 상기 오탁방지막(1)의 가장자리에는 토목섬유로 접어서 중첩되게 봉착한 보강벨트를 재봉하고, 상기 오탁방지막(1) 내측의 가로방향에 다수개의 수평보강벨트(B1)와 세로방향에 수직보강벨트(B2)를 각각 재봉하여 상기 오탁방지막(1)을 제작하고 상기 보강벨트 중 상부보강벨트(2)를 다시 중첩되게 접은 후, 직경 10mm의 보강로프(3)를 삽입하여 재봉하고 양측 가장자리에 형성된 측면보강벨트(4)는 상기 오탁방지막(1)을 다수개로 횡방향으로 연결이 용이하도록 재봉하며 내부에 램프(27)가 장착되게 원형체의 플롯(10)을 사출성형하는 오탁방지막 및 플롯제작단계와; 현장으로 운반된 상기 오탁방지막(1)의 상부보강벨트(2)에 상기 플롯(10)의 체결편(15)과 보강플레이트(17)를 각각 대응되게 위치하여 결합/고정하고, 상기 플롯(10)의 양측에 형성된 로프체결고리(13)에 플롯연결로프로(12)상호 연결한 후, 상기 상부보강벨트(2)의 제2체결홈(2a)에 고정하는 플롯결합단계와; 상기 오탁방지막(1)에 연결될 앵커블록을 무세골재 콘크리트를 사용하여 플랑크톤의 자유로운 이동 및 부착 어패류의 서식공간을 형성할 수 있도록 인공어초형 앵커블록(30)으로 양생하는 앵커블록 제작단계와; 상기 오탁방지막(1)이 설치된 영역을 야간에도 식별가능하도록 상기 플롯(10)에 전구(25)가 내장된 중공형의 전구보호관(26)을 설치하고, 상기 램프(27)를 커넥터(28)로 연결하여 타이머(21)와 조도감지센서(22)에 의해 외부의 전원(20)에 인가하도록 설치하는 조명수단의 설치단계와; 상기 조명수단이 설치된 오탁방지막(1)과 상기 인공어초형 앵커블록(30)을 해안의 공사현장으로 인양한 후, 길이조절용 클립(37)과 와이어로프(38)로 상호 연결하여 상기 인공어초형 앵커블록(30)을 해저에 설치하는 자재인양 및 조립단계로 이루어지는 것을 특징으로 한다.The present invention has been made to solve the above-mentioned problems, an object of the present invention is to provide a pollution prevention device for preventing the contamination of the filthy water generated during the landfill dredging work in the river, coast or seabed to the surrounding stream or seawater It is an object of the present invention to provide a construction method of an antifouling device that is easy to install and dismantle, which is excellent in durability, and which can identify a region of an antifouling device even in the middle of the night. In the construction method of the pollution prevention device to block the spreading of the polluted water generated during the landfill dredging to the surrounding river or sea water, the reinforcing belt is sewn and folded to overlap the edge of the fouling prevention film (1) by overlapping with geotextiles Reattach the plurality of horizontal reinforcing belts B1 in the horizontal direction of the inside of the antifouling film 1 and the vertical reinforcing belts B2 in the vertical direction, respectively. After manufacturing the fouling prevention film (1) and folding the upper reinforcing belt (2) of the reinforcing belt to overlap again, inserting a reinforcing rope (3) of diameter 10mm to sew and side reinforcing belt (4) formed on both edges The anti-fouling film and the plot production step of sewing to facilitate the connection of the anti-fouling film (1) in the lateral direction to a plurality of injection molding the plot 10 of the circular body so that the lamp 27 is mounted therein; The fastening pieces 15 and the reinforcing plate 17 of the plot 10 are respectively located on the upper reinforcing belts 2 of the anti-fouling film 1 transported to the site to be coupled / fixed, respectively, and the plot 10 After connecting the rope connection ring (13) formed on both sides of the cross-connected connection rope (12), and the second coupling groove (2a) of the upper reinforcing belt (2); Anchor block manufacturing step of curing the anchor block to be connected to the antifouling film (1) to artificial reef-type anchor block 30 to form a space for free movement of the plankton and attached seafood using the fine aggregate concrete; A hollow bulb protection tube 26 having a light bulb 25 embedded therein is installed on the plot 10 so that the area where the antifouling film 1 is installed can be identified even at night, and the lamp 27 is connected to the connector 28. An installation step of the lighting means installed to be applied to the external power source 20 by the timer 21 and the illumination sensor 22; After lifting the pollution prevention film (1) and the artificial reef type anchor block 30 is installed to the coastal construction site, the artificial reef type anchor block by interconnecting with the length adjustment clip 37 and the wire rope 38 (30) is characterized in that it consists of the material lifting and assembly step of installing on the seabed.

이하, 본 발명의 바람직한 실시 예에 대해 첨부된 도면을 참조하여 상세하게 설명하기로 한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명에 따른 오탁방지장치의 설치공정도이고, 도 2는 본 발명에 따른 오탁방지장치의 설치상태를 도시한 측면도이고, 도 3은 본 발명에 따른 오탁방지막의 정면도이고, 도 4는 도 3의 부분확대단면도이고, 도 5는 도 3의 "A"부분의 확대단면도이고, 도 6은 본 발명에 따른 오탁방지막의 분리상태를 도시한 부분확대사시도이고, 도 7은 도 6의 "B"부분의 확대사시도이고, 도 8은 본 발명에 따른 플롯의 정면도이고, 도 9는 본 발명에 따른 플롯의 측면도이고, 도 10a는 본 발명에 따른 인공어초형 앵커블록을 도시한 사시도이고, 도 10b는 본 발명에 따른 인공어초형 앵커블록의 다른 실시예를 도시한 사시도이고, 도 10c는 도 10b의 결합상태를 도시한 사시도이고, 도 11은 본 발명에 따른 조명수단의 회로도이다.1 is an installation process of the pollution prevention apparatus according to the present invention, Figure 2 is a side view showing the installation state of the pollution prevention apparatus according to the present invention, Figure 3 is a front view of the pollution prevention film according to the invention, Figure 4 3 is an enlarged cross-sectional view of a portion “A” of FIG. 3, FIG. 6 is a partially enlarged perspective view showing a separation state of an antifouling film according to the present invention, and FIG. Is an enlarged perspective view of the portion B ″, FIG. 8 is a front view of the plot according to the present invention, FIG. 9 is a side view of the plot according to the present invention, and FIG. 10a is a perspective view showing an artificial reef type anchor block according to the present invention, FIG. 10b is a perspective view showing another embodiment of the artificial reef-type anchor block according to the present invention, Figure 10c is a perspective view showing a coupling state of Figure 10b, Figure 11 is a circuit diagram of the lighting means according to the present invention.

상기 도 1에 도시한 바와 같이, 본 발명의 오탁방지장치의 시공방법은 오탁방지장치의 설치될 범위를 설정하여 막체를 재단하고 다수개의 보강벨트(2,4,7)를 재봉하여 오탁방지막(1)을 제작하고, 내부에 램프(27)가 장착되게 원형체의 플롯(10)을 사출성형하는 오탁방지막 및 플롯제작단계와; 현장으로 운반된 상기 오탁방지막(1)의 상부보강벨트(2)에 상기 플롯(float,10)의 체결편(15)과 보강플레이트(17)를 각각 대응되게 위치하여 결합/고정하고, 상기 플롯(10)의 양측에 형성된 로프체결고리(13)에 플롯연결로프로(12)상호 연결한 후, 상기 상부보강벨트(2)의 제2체결홈(2a)에 고정하는 플롯결합단계와; 상기 오탁방지막(1)에 연결될 앵커블록을 무세골재 콘크리트를 사용하여 플랑크톤의 자유로운 이동 및 부착 어패류의 서식공간을 형성할 수 있도록 인공어초형 앵커블록(30)으로 양생하는 앵커블록 제작단계와; 상기 오탁방지막(1)이 설치된 영역을 야간에도 식별가능하도록 상기 플롯(10)에 전구(25)가 내장된 중공형의 전구보호관(26)을 설치하고, 상기 램프(27)를 커넥터(28)로 연결하여 타이머(21)와 조도감지센서(22)에 의해 외부의 전원(20)에 인가하도록 설치하는 조명수단의 설치단계와; 상기 조명수단이 설치된 오탁방지막(1)과 상기 인공어초형 앵커블록(30)을 해안의 공사현장으로 인양한 후, 길이조절용 클립(clip,37)과 와이어로프(38)로 상호 연결하여 상기 인공어초형 앵커블록(30)을 해저에 설치하는 자재인양 및 조립단계로 이루어진다.As shown in FIG. 1, the construction method of the pollution prevention apparatus of the present invention sets a range to be installed of the pollution prevention apparatus to cut the membrane body and sew a plurality of reinforcing belts 2, 4, and 7 to prevent contamination. 1) fabrication, anti-fouling film and plot production step of injection molding the plot 10 of the circular body so that the lamp 27 is mounted therein; Coupling pieces 15 and reinforcing plate 17 of the plot (10) on the upper reinforcing belt (2) of the anti-fouling film (1) transported to the site, respectively corresponding to the coupling / fixing, the plot Connecting the rope connection loops 13 formed on both sides of the cross-connection to the rope connection loops 12, and then fixing the second fastening grooves 2a of the upper reinforcing belts 2; Anchor block manufacturing step of curing the anchor block to be connected to the antifouling film (1) to artificial reef-type anchor block 30 to form a space for free movement of the plankton and attached seafood using the fine aggregate concrete; A hollow bulb protection tube 26 having a light bulb 25 embedded therein is installed on the plot 10 so that the area where the antifouling film 1 is installed can be identified even at night, and the lamp 27 is connected to the connector 28. An installation step of the lighting means installed to be applied to the external power source 20 by the timer 21 and the illumination sensor 22; After lifting the pollution prevention film (1) and the artificial reef type anchor block 30 is installed to the coastal construction site, the artificial reef type by interconnecting with a length adjusting clip (clip 37) and a wire rope (38) The anchor block 30 is made of a material lifting and assembly step of installing on the seabed.

상기와 같이 이루어진 오탁방지장치의 시공방법을 각 공정으로 분류하여 설명하면 다음과 같다.When explaining the construction method of the pollution prevention device made as described above classified into each process as follows.

오탁방지막 및 플롯 제작단계Anti-fouling film and plot manufacturing step

해안 매립지 등의 항만공사시 발생되는 오탁물을 차단하기 위해 오탁방지장치를 설치하기 위해서, 먼저 시공해야 할 범위를 조사하여 현장의 크기에 맞게 상기 오탁방지막(1)을 재단하고 재봉하게 된다.In order to install a pollution prevention device to block the contamination generated during port construction such as coastal landfills, the pollution prevention membrane 1 is cut and sewn to fit the size of the site by first examining the range to be constructed.

상기 오탁방지막(1)의 가장자리에는 토목섬유로 접어서 중첩되게 봉착한 보강벨트를 재봉하고, 상기 오탁방지막(1) 내측의 가로방향에 다수개의 수평보강벨트(B1)와 세로방향에 수직보강벨트(B2)를 각각 재봉하여 상기 오탁방지막(1)에 강도를 부여하게 된다.The reinforcing belt is sewn on the edge of the anti-fouling film (1) folded and sealed with geosynthetic fibers, a plurality of horizontal reinforcing belt (B1) in the horizontal direction of the inside of the anti-fouling film (1) and vertical reinforcing belt ( Each of B2) is sewn to give strength to the fouling prevention film 1.

그리고, 상기 보강벨트 중 상부보강벨트(2)를 다시 중첩되게 접은 후, 직경 10mm의 보강로프(3)를 삽입하여 재봉함으로써 플롯(10)을 상기 상부보강벨트(2)에 결합시 막체의 처짐현상을 방지하며, 양측 가장자리에 형성된 측면보강벨트(4)는 상기 오탁방지막(1)을 다수개로 횡방향으로 연결이 용이하도록 재봉되어 있다.Then, after folding the upper reinforcing belt (2) of the reinforcing belt to overlap again, by inserting and sewing a reinforcing rope (3) of diameter 10mm, sagging of the membrane when coupling the plot 10 to the upper reinforcing belt (2). To prevent the phenomenon, the side reinforcing belt (4) formed on both side edges are sewn to facilitate the connection of the anti-fouling film (1) in the transverse direction.

상기 상부보강벨트(2)에는 다수개의 제2체결홈(2a)을, 양측의 측면보강벨트(4)에는 인접 오탁방지막(1)과 연결하기 위해 아이렛(eyelet) 형상으로 다수개의 제1연결공(5)을, 그리고 하부보강벨트(7)에는 다수개의 제2연결공(5)을 각각 형성하게 된다.The second reinforcing belt (2) in the upper reinforcing belt (2), the side reinforcing belt (4) on both sides of the plurality of first connection holes in the eyelet (eyelet) shape to connect with the adjacent anti-fouling film (1) (5) and the lower reinforcing belt (7) is to form a plurality of second connecting holes (5), respectively.

또한, 상기 하부보강벨트(7)에는 중량감 있는 다수개의 체인(9c)이 결합되어 상기 오탁방지막(1)을 해안에 설치시 상기 체인(9c)에 자중에 의해 막체가 평평하게 유지할 수 있게 된다.In addition, the lower reinforcing belt (7) is coupled to a plurality of chains of heavy weight (9c) it is possible to keep the membrane flat by the weight on the chain (9c) when the fouling prevention film (1) is installed on the shore.

상기 오탁방지막(1)의 상부보강벨트(2)에 결합되는 부구용 플롯(float,10)은 합성수지재로 구비되며, 이는 소모성이 아니라 재활용이 가능하여 오탁방지막(1)의 설치시마다 재 사용할 수 있게 된다.The float plot (10) coupled to the upper reinforcing belt (2) of the antifouling film (1) is provided with a synthetic resin material, which is not consumable but can be recycled and reused every time the antifouling film (1) is installed. Will be.

상기 플롯(10)은 도8 및 도 9와 같이 내부가 비어있는 원형체로 형성된 플롯본체(11)와, 상기 플롯본체(11)를 플롯연결로프(12)로 상호 연결할 수 있도록 양측에 일정길이로 돌출된 로프체결고리(13)와, 상기 플롯본체(11) 상부에 고리형상으로 돌출된 고정구(14)와, 상기 플롯본체(11) 하부에 일정길이로 연장됨과 아울러 다수개의 제1체결홈(15a)을 갖는 체결편(15)이 형성되도록 성형하게 된다.8 and 9, the plot 10 has a predetermined length on both sides to interconnect the plot main body 11 with the plot connecting rope 12. A protruding rope fastening ring 13, a fixture 14 protruding in an annular shape on the top of the plot body 11, and a plurality of first fastening grooves extending in a predetermined length below the plot body 11. It is molded so that the fastening piece 15 having 15a) is formed.

여기서, 상기 플롯(10) 내부에는 조명수단 중에 하나인 램프(27)가 장착하게 되는데, 상기 램프(27)로 부터 연결된 플러그(28a)가 상기 플롯본체(11) 상부의 내측에 구비된 전선삽입관(19)을 통해 외부로 인출되도록 구비되어 있다.Here, the lamp 10, which is one of the lighting means, is mounted inside the plot 10, and a plug 28a connected from the lamp 27 is provided inside the upper part of the plot body 11. It is provided to be drawn out through the tube 19.

상기와 같이 플롯(10)이 성형되면, 상기 플롯(10)을 포함하여 상기 오탁방지막(1) 및 연결부품들을 현장으로 운반하게 된다.When the plot 10 is formed as described above, the fouling prevention film 1 and the connecting parts are transported to the site including the plot 10.

플롯결합단계Plot combining step

현장으로 운반된 상기 플롯(float,10)을 상기 상부보강벨트(2)에 연결/고정하게 되는데 도 6과 같이, 먼저 상기 상부보강벨트(2)의 제2체결홈(2a)의 후면부에 상기 플롯(10)의 제1체결홈(15a)이 일치되도록 위치하고, 이어서 다수개의 제3체결홈(17a)이 형성된 금속성의 보강플레이트(17)를 상기 보강벨트의 전면부에 위치하여 볼트(18a)와 너트(18b)로 상기 제1/2/3체결홈(15a,2a,17a)을 체결함으로써 상기 플롯(10)을 상기 상부보강벨트(2)에 결합하게 된다.The float (10) transported to the site is connected to / fixed to the upper reinforcing belt (2), as shown in Figure 6, first to the rear of the second fastening groove (2a) of the upper reinforcing belt (2) The first fastening groove 15a of the plot 10 is positioned to coincide, and then a metal reinforcing plate 17 having a plurality of third fastening grooves 17a is positioned at the front of the reinforcing belt so that the bolt 18a is located. And the first and third fastening grooves 15a, 2a, and 17a with the nut 18b to couple the plot 10 to the upper reinforcing belt 2.

즉, 섬유재질로 이루어진 상기 상부보강벨트(2)를 중심으로 상기 금속성의 보강플레이트(17)와 상기 합성수지제로 된 상기 플롯(10)의 체결편(15)을 각각 대응되게 위치하여 상기 볼트(18a)와 너트(18b)를 체결함으로써, 체결강도가 상승되어 상기 플롯(10)을 견고하게 결합/고정할 수 있게 된다.That is, the bolts 18a are positioned to correspond to the fastening pieces 15 of the metallic reinforcement plate 17 and the plot 10 made of the synthetic resin, respectively, based on the upper reinforcing belt 2 made of a fiber material. ) And the nut 18b, the fastening strength is increased, it is possible to firmly couple / fix the plot 10.

이어서, 상기 플롯(10)의 양측에 돌출 형성된 로프체결고리(13)에 플롯연결로프(12)로 상호 연결하고 상기 상부보강벨트(2)의 제2체결홈(2a)에 고정함으로써, 인접되어 있는 상기 플롯(10)간의 연결을 도모함과 아울러, 상기 오탁방지막(1)에 부력을 부여하게 된다.Subsequently, the rope fastening rings 13 protruding from both sides of the plot 10 are connected to each other by a plot connecting rope 12 and fixed to the second fastening grooves 2a of the upper reinforcing belt 2 to thereby be adjacent to each other. In addition to promoting the connection between the plot 10, and to provide a buoyancy to the antifouling film (1).

앵커블록 제작단계Anchor block production stage

상기 플롯결합작업과 동시에 인공어초형 앵커블록(30)을 현장에서 직접 제작하게 되는데, 본 발명의 일실시예로서 도 10a과 같이 물, 시멘트, 굵은골재로 구성된 무세골재 콘크리트로 육교형으로 양생하게 된다.Simultaneously with the above plot combining operation, the artificial reef type anchor block 30 is directly manufactured in the field. As an embodiment of the present invention, as shown in FIG. 10A, the structure is cured in an overpass type with a fine aggregate concrete composed of water, cement, and coarse aggregate. .

상기 무세골재 콘크리트는 일반적인 콘크리트에서 충진재로 작용하는 모래가 함유되지 않는 것으로, 양호한 공극율을 갖는다.The fine aggregate concrete does not contain sand, which acts as a filler in general concrete, and has good porosity.

즉, 무세골재 콘크리트는 시멘트 페이스트가 피복된 굵은 골재만으로 콘크리트를 형성하여 큰 공극을 발생시킨 것으로 일반적인 콘크리트에 비해 강도는 떨어지지만 공극율이 매우 향상된다.That is, the fine aggregate concrete is to form a concrete only by the coarse aggregate coated with cement paste to generate a large gap, the strength is lower than the general concrete, but the void ratio is very improved.

이와 같이, 무세골재 콘크리트는 양호한 공극율을 가지기 때문에 상기 인공어초형 앵커블록(30) 벽면 내부를 통한 플랑크톤의 자유로운 이동 및 부착 어패류의 서식이 양호해 생산성이 높은 어장을 형성할 수 있다.As such, since the fine aggregate concrete has a good porosity, the free movement of plankton through the inside of the wall of the artificial reef type anchor block 30 and the habitat of attached fish and shellfish can be formed to form a high-productive fishery.

상기 무세골재 콘크리트를 양생하여 제작된 상기 인공어초형 앵커블록(30)의 다른 실시예로서, 도 10b와 같이 내부가 비어 있는 육면체 형상으로 이루어진 앵커블록본체(31)와, 상기 앵커블록본체(31)의 사방면 중앙부에 소정크기로 형성된 조류환구멍(32)과, 상기 조류환구멍(32)이 형성된 사방주벽에 다수개의 인공어초형 앵커블록(30)을 서로 결합할 수 있도록 형성된 다수개의 결합홀(33)과, 상기 앵커블록본체(31) 상부의 가장자리에 샤클(shackle)형상의 연결구(9a)로 연결할 수 있도록 소정길이로 돌출된 앵커블록고리(35)로 구성된다.As another embodiment of the artificial reef-type anchor block 30 is produced by curing the non-aggregate concrete, as shown in Figure 10b the anchor block body 31 made of a hollow hexahedron shape, and the anchor block body 31 A plurality of coupling holes formed to couple the plurality of artificial reef type anchor blocks 30 to each other in the circumferential wall formed with a predetermined size in the central portion of the bird ring hole 32 is formed on the four sides ( 33) and an anchor block ring 35 protruding to a predetermined length so as to be connected to the edge of the upper portion of the anchor block body 31 by a shackle-shaped connector 9a.

또한, 상기 앵커블록본체(31)의 저부에 요철형상으로 일정길이로 돌출되어 해저에 용이하게 고정될 수 있도록 스파이크(spike,36)를 형성하는 것이 바람직 할 것이다.In addition, it is desirable to form a spike (36) so that the bottom of the anchor block body 31 protrudes in a predetermined length in an uneven shape to be easily fixed to the seabed.

조명수단의 설치단계Installation stage of the luminaire

상기 오탁방지막(1)의 설치된 영역을 야간에도 식별이 가능하도록 하고 조업선박을 안내하는 기능을 행할 수 있도록 상기 플롯(10)에 조명수단을 설치하게 된다.Illumination means are installed on the plot 10 to enable the installed area of the antifouling film 1 to be distinguishable even at night and to guide the operating vessel.

먼저, 상기 다수개의 플롯본체(11) 상부의 고정구(14)에 전선(23)이 내장된 전선관(24)을 끼운다.First, the conduit tube 24 having the wire 23 is inserted into the fixture 14 on the plurality of plot bodies 11.

상기 전선(23)은 외부의 전원(20)에 의해 연결되어 있고, 상기 전선관(24)에는 일정간격으로 인출홈이 형성되어 있으며, 도 7에 도시한 바와같이, 인출홈(24a)을 통해 상기 전선(23)으로 부터 연장된 소켓(28b)이 상기 전선관(24) 저부로 돌출되어 있다.The wire 23 is connected by an external power source 20, the conduit tube 24 is formed with a drawing groove at a predetermined interval, as shown in Figure 7, through the drawing groove 24a A socket 28b extending from the electric wire 23 protrudes into the bottom of the conduit 24.

상기 소켓(28b)과 상기 플롯본체(11) 내부의 램프(27)로 부터 인출된 플러그(28a)를 상기 소켓(28b)에 접속시킴으로써 외부의 전원(20)과 연결되어진다.The socket 28b and the plug 28a drawn out from the lamp 27 inside the plot body 11 are connected to the external power source 20 by connecting to the socket 28b.

여기서, 인출홈(24a)은 해수가 침투되지 않도록 실리콘 등으로 밀봉되고, 상기 플러그(28a)와 소켓(28b)으로 구성된 커넥터(28)에는 타원형의 케이스 형상으로 된 커버(29)를 씌움으로써 해수가 침투되는 것을 방지하는 것이 바람직할 것이다.Here, the extraction groove 24a is sealed with silicon or the like so that the seawater does not penetrate, and the connector 28 composed of the plug 28a and the socket 28b is covered with an oval case-shaped cover 29 to cover the seawater. It would be desirable to prevent the infiltration.

이어서, 상기 플롯본체(11) 상부의 고정구(14)에 또 다른 조명수단인 상기 전원(20)과 상기 전선(23)에 의해 연결된 다수개의 전구(25)가 내장된 중공형의 전구보호관(26)을 끼우게 된다.Subsequently, a hollow bulb protecting tube 26 in which a plurality of bulbs 25 connected by the power source 20 and the electric wires 23, which are other lighting means, are fixed to the fixture 14 on the upper portion of the plot body 11. ) Is fitted.

여기서, 상기 전선관(24) 및 전구보호관(26)은 신축성을 갖는 소재로 이루어져 파도에 의해 상기 플롯(10)이 유동되어도 충격을 흡수함과 아울러 해수의 침투를 방지하여 내부의 상기 전선(23)과 전구(25)를 보호할 수 있게 된다.Here, the conduit 24 and the bulb protection tube 26 is made of an elastic material to absorb shock even when the plot 10 is flowed by waves and to prevent the penetration of seawater, thereby preventing the penetration of the wire 23 therein. And the bulb 25 can be protected.

상기 전원(20)으로 부터 인가되는 전원전압을 상기 조명수단에 일정시간 간격으로 공급/차단할 수 있도록 타이머(21)가 구비되어 있다.The timer 21 is provided to supply / block the power supply voltage applied from the power supply 20 at regular intervals.

또한, 상기 타이머(21) 외에 상기 전원(20)으로 부터 인가되는 전원전압이 검출된 조도값에 의해 상기 전구(25)와 램프(26)로 공급/차단될 수 있도록 조도감지센서(22)에 의해 제어할 수 있을 것이다.In addition, in addition to the timer 21, a power supply voltage applied from the power supply 20 may be supplied to / off the light bulb 25 and the lamp 26 by the detected illuminance value. Will be controlled by

즉, 상기 타이머(21)에 의해 입력된 시간에 상기 전구(25)와 램프(27)가 1차적으로 on/off되며, 상기 조도감지센서(22)에 의해 검출된 조도량에 의해 2차적으로 on/off 시킬 수 있도록 구성되어 있다.That is, at the time input by the timer 21, the bulb 25 and the lamp 27 are primarily turned on and off, and secondly by the illuminance detected by the illuminance sensor 22. It is configured to be turned on / off.

상기 조명수단은 먼저 상기 전선관(24)에 내장된 전구(25)에 상기 전원(20)을 인가하여 야간에 상기 오탁방지막(1)의 영역을 표시하게 되며, 불측의 사고로 상기 전구(25)가 작동되지 않으면, 상기 램프(27)에 전원(20)을 인가함으로써 이를 대체하여 사용하는 것이 바람직할 것이다.The lighting means first applies the power source 20 to the light bulb 25 embedded in the conduit 24 to display the area of the antifouling film 1 at night, and the light bulb 25 in an unintended accident. If is not operated, it may be preferable to use it by applying the power source 20 to the lamp 27.

자재인양 및 조립단계Material lifting and assembly stage

조명수단이 설치된 상기 플롯(10)이 오탁방지막(1)에 결합된 상태로 적재하고, 연결부품 및 인공어초형 앵커블록(30)도 함께 적재하여 바지선으로 해안의 공사현장으로 인양하게 된다.The plot 10 installed with the lighting means is loaded in a state in which it is coupled to the anti-fouling film 1, and the connecting parts and the artificial reef type anchor block 30 are also loaded together to be lifted to the construction site of the coast by a barge.

인양된 상기 오탁방지막(1)을 설치수역에 맞게 여러개를 횡방향으로 연결하여 일체형으로 형성하게 되는데, 상기 상부보강벨트(2)의 제2체결홈(2a)에서 샤클(shackle) 등의 연결구(9a) 및 금구(9b)를 사용하여 인접한 오탁방지막과 연결하며, 상기 측면보강벨트(4)의 제1연결공(5)에 각각 연결로프(8)로 삽입하여 결합하는 방법으로 다수개의 오탁방지막(1)을 연결하게 된다.The lifted anti-fouling film 1 is connected to each other in the transverse direction so as to be integrally formed so as to be integrally formed, and a connector such as a shackle in the second fastening groove 2a of the upper reinforcing belt 2 9a) and brackets (9b) are connected to the adjacent anti-fouling film, and a plurality of anti-fouling films by inserting into the first connection hole (5) of the side reinforcing belt (4), respectively, by coupling as a connecting rope (8). (1) will be connected.

이어서, 상기 인공어초형 앵커블록(30)을 상기 오탁방지막(1)에 연결하는 작업은 먼저, 상기 앵커블록고리(35)와 샤클(shackle)형상의 연결구(9a)를 체결하고, 여기에 길이조절용 클립(clip,37)과 와이어로프(38)의 일측을 연결한다.Subsequently, the operation of connecting the artificial reef type anchor block 30 to the fouling prevention film 1 is performed by first coupling the anchor block ring 35 with the shackle-shaped connector 9a and adjusting the length therefor. The clip (37) and one side of the wire rope (38) are connected.

그리고, 상기 와이어로프(38)의 타측을 상기 하부보강벨트(7)의 제2결공(8)에 고정된 금구(9b)에 샤클(shackle) 등의 연결구(9a)로 연결하여 상기 오탁방지막(1)과 인공어초형 앵커블록(30)을 연결한다.The other side of the wire rope 38 is connected to a metal fitting 9b fixed to the second hole 8 of the lower reinforcing belt 7 by a connector 9a such as a shackle. 1) and the artificial reef type anchor block 30 is connected.

이와 동일한 방법으로, 상기 인공어초형 앵커블록(30) 2개를 상기 상부보강벨트(2)의 제2체결홈(2a)에 연결한다.In the same manner, the two artificial reef type anchor blocks 30 are connected to the second fastening groove 2a of the upper reinforcing belt 2.

상기와 같이 인공어초형 앵커블록(30) 3개를 1조로 하여 상기 오탁방지막(1)이 설치되는 횡방향으로 일정간격을 두고 연결한다.As described above, three artificial reef type anchor blocks 30 are connected to each other at a predetermined interval in the transverse direction in which the fouling prevention film 1 is installed.

상기 오탁방지막(1)에 연결된 인공어초형 앵커블록(30)을 해저에 투하하여 잠수인력을 통해 해저에 고정하게 된다.The artificial reef type anchor block 30 connected to the fouling prevention film 1 is dropped on the seabed and fixed to the seabed through a diving force.

이때, 상기 인공어초형 앵커블록(30)의 저부에 형성된 스파이크(spike,36)에 의해 용이하게 해저에 고정할 수 있으며, 고정한 후에는 상기 오탁방지막(1)이 처짐이 없이 수면에서 평행하도록 상기 클립(clip,37)을 통해 길이를 조절한다.In this case, the spikes (36) formed on the bottom of the artificial reef type anchor block 30 can be easily fixed to the seabed, and after fixing the clip so that the fouling prevention film (1) parallel to the water surface without sag Use (clip, 37) to adjust the length.

상기 하부보강벨트(7)에 연결되는 인공어초형 앵커블록(30)은 서브앵커블록이며, 상기 오탁방지막(1)과 수직하게 연결되고, 상기 상부보강벨트(2)에 연결되는 2개의 인공어초형 앵커블록(10)은 메인앵커블록으로 상기 상부보강벨트(2)로 부터 양측으로 일정간격이 이격되게 설치되어 상기 오탁방지막(1)을 지지하게 된다.The artificial reef type anchor block 30 connected to the lower reinforcing belt 7 is a sub-anchor block, and two artificial reef type anchors connected to the anti-fouling film 1 vertically and connected to the upper reinforcing belt 2. Block 10 is a main anchor block is installed at both sides from the upper reinforcing belt (2) spaced apart from each other to support the anti-fouling film (1).

또한, 상기 하부보강벨트(7)에 연결된 체인(9c)의 자중에 의해 상기 오탁방지막(1)이 평평하게 유지될 수 있어 오탁물을 효과적으로 차단할 수 있다.In addition, the antifouling film 1 may be kept flat by the weight of the chain 9c connected to the lower reinforcing belt 7 to effectively block the dirt.

여기서, 상기 인공어초형 앵커블록(30)은 1개를 설치하거나, 필요에 따라 다수개를 적재하여 해저에 설치할 수 있는데 도 10c와 같이, 다수개를 적재하는 경우에는 상기 스파이크(spike,36)가 형성된 인공어초형 앵커블록(30)을 최하부에 설치하고, 상기 스파이크(spike,36)가 형성되지 않은 인공어초형 앵커블록(30)을 그 상부에 적절하게 적재함으로써, 어패류의 서식공간을 확대함과 아울러 상기 오탁방지막(1)을 견고하게 고정할 수 있을 것이다.Here, the artificial reef type anchor block 30 may be installed one, or may be installed in the seabed by loading a plurality if necessary, as shown in Figure 10c, the spike (spike, 36) when loading a plurality By installing the formed artificial reef type anchor block 30 at the bottom and appropriately loading the artificial reef type anchor block 30, in which the spike 36 is not formed, expands the habitat space of fish and shellfish The fouling prevention film 1 may be firmly fixed.

상기한 바와 같은 시공방법으로 오탁방지막(1)의 설치가 끝나게 되면, 상기 플롯(10)에 설치된 조명수단을 상기 전원(20)에 인가하여 작동여부를 점검하고, 연결부분을 점검함으로써 본 발명의 오탁방지장치의 설치작업이 완료된다.When the installation of the anti-fouling film 1 by the construction method as described above is finished, by applying the lighting means installed on the plot 10 to the power source 20 to check whether the operation, the connection part of the present invention The installation of the antifouling device is completed.

상술한 바와 같이 본 발명에 의하면, 오탁방지장치의 설치 및 해체가 용이하며, 특히 플롯을 보강플레이트를 대고 오탁방지막에 볼트와 너트로 용이하게 결합함으로써, 결합강도가 우수할 뿐만 아니라 시공시간이 적게 소요되는 장점이 있다.As described above, according to the present invention, it is easy to install and dismantle the contamination prevention device, and in particular, by easily attaching the plot to the contamination prevention membrane with the reinforcing plate by bolts and nuts, the bonding strength is excellent and the construction time is short. There is an advantage.

그리고, 오탁방지막의 부구인 플롯(float)에 조명수단을 설치하여 야간에도 식별이 가능토록 함으로써 오탁방지장치의 영역을 표시하는 경계선의 기능과 조업선박을 안내하는 기능을 행할 수 있을 뿐만 아니라, 플롯(float)을 재활용하여 반영구적으로 사용함으로써 산업폐기물을 감소시킬 수 있는 효과가 있다.In addition, by installing a lighting means on a float, which is a part of the anti-fouling film, it is possible to identify at night, thereby not only functioning as a boundary line for displaying the area of the anti-fouling device and guiding operating ships, but also a plot. By recycling the floats semi-permanently, it is possible to reduce industrial waste.

또한, 플롯이나 조명수단이 파도에 의해 부분적으로 파손되거나 단락된 경우, 파손된 구성요소를 용이하게 교체하여 사용할 수 있어 장치의 수명이 오래 지속될 뿐만 아니라 사용신뢰성을 향상시킬 수 있는 장점이 있다.In addition, when the plot or the luminaire is partially broken or shorted by the waves, the broken component can be easily replaced and used, so that the life of the device is long lasting and the reliability of use can be improved.

아울러, 오탁방지장치를 인공어초형 앵커블록의 스파이크에 의해 해저에 견고하게 고정함으로써 막체의 처짐현상을 방지할 수 있으며, 앵커블록을 인공어초형으로 구비하여 오탁방지장치의 해체시, 이를 제거시키지 않고 반영구적으로 보전함으로써, 어류자원의 서식공간을 제공함과 아울러 보호 및 증식시킬 수 있는 효과가 있다.In addition, it is possible to prevent the deflection of the membrane body by fixing the fouling prevention device firmly to the seabed by the spikes of the artificial reef-type anchor block, semi-permanent without dismantling the fouling prevention device equipped with the artificial block type By preserving the fish, it provides the habitat of fish resources, and also protects and multiplies.

도 1은 본 발명에 따른 오탁방지장치의 설치공정도,1 is a installation process of the contamination prevention apparatus according to the present invention,

도 2는 본 발명에 따른 오탁방지장치의 설치상태를 도시한 측면도,Figure 2 is a side view showing the installation state of the pollution prevention apparatus according to the present invention,

도 3은 본 발명에 따른 오탁방지막의 정면도,3 is a front view of an antifouling film according to the present invention;

도 4는 도 3의 부분확대단면도,4 is a partially enlarged cross-sectional view of FIG. 3;

도 5는 도 3의 "A"부분의 확대단면도,5 is an enlarged cross-sectional view of the portion "A" of FIG.

도 6은 본 발명에 따른 오탁방지막의 분리상태를 도시한 부분확대사시도,Figure 6 is a partially enlarged perspective view showing the separation state of the antifouling film according to the present invention,

도 7은 도 6의 "B"부분의 분리상태를 도시한 확대사시도,FIG. 7 is an enlarged perspective view illustrating a separated state of part “B” of FIG. 6;

도 8은 본 발명에 따른 플롯의 정면도,8 is a front view of a plot according to the present invention,

도 9는 본 발명에 따른 플롯의 측면도,9 is a side view of a plot according to the present invention,

도 10a는 본 발명에 따른 인공어초형 앵커블록을 도시한 사시도,10A is a perspective view of an artificial reef type anchor block according to the present invention;

도 10b는 본 발명에 따른 인공어초형 앵커블록의 다른 실시예를 도시한 사시도,10b is a perspective view showing another embodiment of an artificial reef type anchor block according to the present invention;

도 10c는 도 10b의 결합상태를 도시한 사시도,FIG. 10c is a perspective view illustrating a coupled state of FIG. 10b; FIG.

도 11은 본 발명에 따른 조명수단의 회로도.11 is a circuit diagram of a luminaire according to the invention.

< 도면의 주요부분에 대한 부호의 설명 ><Description of Symbols for Major Parts of Drawings>

1 : 오탁방지막 2 : 상부보강벨트1: Stain prevention film 2: Upper reinforcement belt

2a : 제2체결홈 3 : 보강로프2a: 2nd fastening groove 3: reinforcement rope

4 : 측면보강벨트 5 : 제1연결공4: side reinforcement belt 5: the first connection hole

6 : 연결로프 7 : 하부보강벨트6: connection rope 7: lower reinforcement belt

9a : 연결구 9b : 금구9a: Connector 9b: Bracket

9c : 체인 10 : 플롯(float)9c: chain 10: plot

11 : 플롯본체 12 : 플롯연결로프11: plot body 12: plot connection rope

13 : 로프체결고리 14 : 고정구13: rope fastening ring 14: fixture

15 : 체결편 15a : 제1체결홈15: fastening piece 15a: first fastening groove

17 : 보강플레이트 17a : 제3체결홈17: reinforcing plate 17a: third fastening groove

18a : 볼트 18b : 너트18a: Bolt 18b: Nut

19 : 전선삽입관 20 : 전원19: wire insertion tube 20: power supply

21 : 타이머 22 : 조도감지센서21: Timer 22: Ambient Light Sensor

23 : 전선 24 : 전선관23: wire 24: conduit

25 : 전구 26 : 전구보호관25: bulb 26: bulb protector

27 : 램프 28 : 커넥터27 lamp 28 connector

28a : 플러그 28b : 소켓28a: plug 28b: socket

29 : 커버 30 : 인공어초형 앵커블록29 cover 30 artificial reef anchor block

31 : 앵커블록본체 32 : 조류환구멍31: anchor block body 32: bird ring hole

33 : 결합홀 35 : 앵커블록고리33: coupling hole 35: anchor block ring

36 : 스파이크(spike) 37 : 클립(clip)36: spike 37: clip

38 : 와이어로프38: wire rope

Claims (2)

해안 또는 해저에서의 매립준설공사시 발생되는 오탁수가 주변의 하천수나 해수로 확산되는 것을 차단하는 오탁방지장치의 시공방법에 있어서,In the construction method of the fouling prevention device to block the spreading of the polluted water generated during the landfill dredging work on the shore or seabed to the surrounding river or sea water, 상기 오탁방지막(1)의 가장자리에는 토목섬유로 접어서 중첩되게 봉착한 보강벨트를 재봉하고, 상기 오탁방지막(1) 내측의 가로방향에 다수개의 수평보강벨트(B1)와 세로방향에 수직보강벨트(B2)를 각각 재봉하여 상기 오탁방지막(1)을 제작하고 상기 보강벨트 중 상부보강벨트(2)를 다시 중첩되게 접은 후, 직경 10mm의 보강로프(3)를 삽입하여 재봉하고 양측 가장자리에 형성된 측면보강벨트(4)는 상기 오탁방지막(1)을 다수개로 횡방향으로 연결이 용이하도록 재봉하며 내부에 램프(27)가 장착되게 원형체의 플롯(10)을 사출성형하는 오탁방지막 및 플롯제작단계와;The reinforcing belt is sewn on the edge of the anti-fouling film (1) folded and sealed with geosynthetic fibers, a plurality of horizontal reinforcing belt (B1) in the horizontal direction of the inside of the anti-fouling film (1) and vertical reinforcing belt ( B2) to sew each of the anti-fouling film (1) to produce and folded the upper reinforcing belt (2) of the reinforcement belt to overlap again, and then sewing by inserting a reinforcing rope (3) of diameter 10mm and formed on both side edges The reinforcing belt (4) is sewage prevention film and plot production step of injection molding the plot (10) of the circular body so that the plurality of the antifouling film (1) for easy connection in the transverse direction and the lamp 27 is mounted therein; ; 현장으로 운반된 상기 오탁방지막(1)의 상부보강벨트(2)에 상기 플롯(10)의 체결편(15)과 보강플레이트(17)를 각각 대응되게 위치하여 결합/고정하고, 상기 플롯(10)의 양측에 형성된 로프체결고리(13)에 플롯연결로프로(12)상호 연결한 후, 상기 상부보강벨트(2)의 제2체결홈(2a)에 고정하는 플롯결합단계와;The fastening pieces 15 and the reinforcing plate 17 of the plot 10 are respectively located on the upper reinforcing belts 2 of the anti-fouling film 1 transported to the site to be coupled / fixed, respectively, and the plot 10 After connecting the rope connection ring (13) formed on both sides of the cross-connected connection rope (12), and the second coupling groove (2a) of the upper reinforcing belt (2); 상기 오탁방지막(1)에 연결될 앵커블록을 무세골재 콘크리트를 사용하여 플랑크톤의 자유로운 이동 및 부착 어패류의 서식공간을 형성할 수 있도록 인공어초형 앵커블록(30)으로 양생하는 앵커블록 제작단계와;Anchor block manufacturing step of curing the anchor block to be connected to the antifouling film (1) to artificial reef-type anchor block 30 to form a space for free movement of the plankton and attached seafood using the fine aggregate concrete; 상기 오탁방지막(1)이 설치된 영역을 야간에도 식별가능하도록 상기 플롯(10)에 전구(25)가 내장된 중공형의 전구보호관(26)을 설치하고, 상기 램프(27)를 커넥터(28)로 연결하여 타이머(21)와 조도감지센서(22)에 의해 외부의 전원(20)에 인가하도록 설치하는 조명수단의 설치단계와;A hollow bulb protection tube 26 having a light bulb 25 embedded therein is installed on the plot 10 so that the area where the antifouling film 1 is installed can be identified even at night, and the lamp 27 is connected to the connector 28. An installation step of the lighting means installed to be applied to the external power source 20 by the timer 21 and the illumination sensor 22; 상기 조명수단이 설치된 오탁방지막(1)과 상기 인공어초형 앵커블록(30)을 해안의 공사현장으로 인양한 후, 길이조절용 클립(37)과 와이어로프(38)로 상호 연결하여 상기 인공어초형 앵커블록(30)을 해저에 설치하는 자재인양 및 조립단계로 이루어지는 것을 특징으로 하는 오탁방지장치의 시공방법.After lifting the pollution prevention film (1) and the artificial reef type anchor block 30 is installed to the coastal construction site, the artificial reef type anchor block by interconnecting with the length adjustment clip 37 and the wire rope 38 Construction method of the pollution prevention device, characterized in that consisting of the material lifting and assembling step to install the (30) on the seabed. 삭제delete
KR10-2002-0004303A 2002-01-24 2002-01-24 Interception device of pollution matter and construction method of it KR100485194B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2002-0004303A KR100485194B1 (en) 2002-01-24 2002-01-24 Interception device of pollution matter and construction method of it

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2002-0004303A KR100485194B1 (en) 2002-01-24 2002-01-24 Interception device of pollution matter and construction method of it

Publications (2)

Publication Number Publication Date
KR20030063939A KR20030063939A (en) 2003-07-31
KR100485194B1 true KR100485194B1 (en) 2005-04-22

Family

ID=32219278

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2002-0004303A KR100485194B1 (en) 2002-01-24 2002-01-24 Interception device of pollution matter and construction method of it

Country Status (1)

Country Link
KR (1) KR100485194B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100667614B1 (en) * 2006-10-18 2007-01-11 (주)케이지엔지니어링 Institution structure of silt protector of intake tower for tap piped water
KR101030258B1 (en) * 2010-05-17 2011-04-22 창신개발(주) Silt protector equipped with anchor
KR20190073239A (en) 2018-04-18 2019-06-26 현대건설주식회사 Silt curtain for water quality management of water intake facility adjacent thereto and method for constructing the same

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100501808B1 (en) * 2004-06-16 2005-07-20 주식회사 건일엔지니어링 An anchor for a silt protector
KR101030259B1 (en) * 2011-01-24 2011-04-22 창신개발(주) Anchor for establishing silt protector
CN111827209A (en) * 2020-07-27 2020-10-27 中国电建集团成都勘测设计研究院有限公司 Float stopping facility and construction method thereof
KR102576073B1 (en) * 2023-01-11 2023-09-06 양병선 Easy to Install and Collect Silt Protector and It's Construction Method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR950031849U (en) * 1994-05-30 1995-12-14 유도실업 주식회사 Haitai farming buoy with warning light
KR980000116U (en) * 1997-12-15 1998-03-30 허재광 Rich man
JPH1084814A (en) * 1996-09-19 1998-04-07 Hakko Denki Kk Float
KR19990005357U (en) * 1997-07-12 1999-02-18 성기팔 Fish farm
KR100225025B1 (en) * 1996-12-09 1999-10-15 김승취 Oil fence
KR20000007004A (en) * 1999-11-13 2000-02-07 이근희 Construction method of water head hole having moving channel of amphibia and for protecting fish of middle/small river and shore
KR200232407Y1 (en) * 2001-02-15 2001-09-29 원 회 양 Cellular block covering breakwater which have function of fishing reef

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR950031849U (en) * 1994-05-30 1995-12-14 유도실업 주식회사 Haitai farming buoy with warning light
JPH1084814A (en) * 1996-09-19 1998-04-07 Hakko Denki Kk Float
KR100225025B1 (en) * 1996-12-09 1999-10-15 김승취 Oil fence
KR19990005357U (en) * 1997-07-12 1999-02-18 성기팔 Fish farm
KR980000116U (en) * 1997-12-15 1998-03-30 허재광 Rich man
KR20000007004A (en) * 1999-11-13 2000-02-07 이근희 Construction method of water head hole having moving channel of amphibia and for protecting fish of middle/small river and shore
KR200232407Y1 (en) * 2001-02-15 2001-09-29 원 회 양 Cellular block covering breakwater which have function of fishing reef

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100667614B1 (en) * 2006-10-18 2007-01-11 (주)케이지엔지니어링 Institution structure of silt protector of intake tower for tap piped water
KR101030258B1 (en) * 2010-05-17 2011-04-22 창신개발(주) Silt protector equipped with anchor
KR20190073239A (en) 2018-04-18 2019-06-26 현대건설주식회사 Silt curtain for water quality management of water intake facility adjacent thereto and method for constructing the same

Also Published As

Publication number Publication date
KR20030063939A (en) 2003-07-31

Similar Documents

Publication Publication Date Title
CN109906292B (en) System for installing anti-scour material on self-floating marine foundation and related method and use of such system
JP3983675B2 (en) Permanent / semi-permanent breakwater structure and coastal and land regeneration methods
KR101272903B1 (en) Silt prevent the spread of temporary for harbor renovation and, marine dredging and reclamation
KR100485194B1 (en) Interception device of pollution matter and construction method of it
US5944443A (en) Adjustable porous groynes and method for shoreline reclamation
AU2002256111B2 (en) Adjustable porous structures and method for shoreline and land mass reclamation
US6722817B2 (en) Adjustable porous structures and method for shoreline and land mass reclamation
KR101393721B1 (en) Water purification device that is concealed by water plant island
CN1406303A (en) Method for soil erosion control works or shore protection works and structure for soil protection or shore protection
KR101912576B1 (en) A Silt Protector Device For Water Ancheor Stone bag
KR100633018B1 (en) Silt protector
KR101930491B1 (en) Apparatus for defending against underwater
KR100677898B1 (en) Anchors for establishment of silt barrier, and establishment method of silt barrier using the same
KR101251602B1 (en) Pollution protection fence fix device by rock sack
KR101718213B1 (en) Silt protector apparatus and anchor manufacturing and installation method of this same
KR100225025B1 (en) Oil fence
KR200423737Y1 (en) water dirt and oil-fence structure
CN211898581U (en) Erosion protection device for offshore wind power pile foundation
KR102576073B1 (en) Easy to Install and Collect Silt Protector and It&#39;s Construction Method
KR102580666B1 (en) Eco-Friendly preventing contamination Using Wooden Pile Anchors
JP7345701B1 (en) How to remove the scour prevention unit
KR100530616B1 (en) Concrete cover mounting structure for safeguard of sea bottom cable
KR19980044955A (en) Fouling prevention device
KR200393313Y1 (en) Installation structure of float fence using anchors
KR102606363B1 (en) Silt prevent the spread of temporary for harbor renovation and, marine dredging and reclamation

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130514

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20140415

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20150708

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20160404

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20170411

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20180416

Year of fee payment: 14

LAPS Lapse due to unpaid annual fee