KR100382320B1 - Bridge construction apparatus - Google Patents

Bridge construction apparatus Download PDF

Info

Publication number
KR100382320B1
KR100382320B1 KR10-2000-0039151A KR20000039151A KR100382320B1 KR 100382320 B1 KR100382320 B1 KR 100382320B1 KR 20000039151 A KR20000039151 A KR 20000039151A KR 100382320 B1 KR100382320 B1 KR 100382320B1
Authority
KR
South Korea
Prior art keywords
truss
cross beam
bridge
central
segment
Prior art date
Application number
KR10-2000-0039151A
Other languages
Korean (ko)
Other versions
KR20020005157A (en
Inventor
김영홍
도하석
이명성
Original Assignee
엘지건설 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 엘지건설 주식회사 filed Critical 엘지건설 주식회사
Priority to KR10-2000-0039151A priority Critical patent/KR100382320B1/en
Publication of KR20020005157A publication Critical patent/KR20020005157A/en
Application granted granted Critical
Publication of KR100382320B1 publication Critical patent/KR100382320B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges

Abstract

본 발명은 PSM공법으로 교량을 건설하는 장치에 관한 것으로서, 후방측 크로스 빔을 상판 세그먼트의 상부에 배치시키는 한편 후방측 크로스 빔의 양단이 상판 세그먼트의 하부에서 사이드 트러스와 결합되고, 전방측 크로스 빔이 센트럴 트러스에 거치됨과 동시에 상면에 하중 분산 부재를 설치하는 구조를 채택하여 구조적 안정성을 확보함과 동시에 작업 지연에 따른 비용문제를 동시에 해결하는 효과가 있다.The present invention relates to an apparatus for constructing a bridge by the PSM method, wherein a rear cross beam is disposed on an upper portion of a top segment, while both ends of the rear cross beam are coupled with a side truss at the bottom of the upper segment, and a front cross beam. It is mounted on the central truss and at the same time adopts a structure to install a load distribution member on the upper surface to ensure structural stability and solve the cost problem due to work delay.

Description

교량 건설장치{BRIDGE CONSTRUCTION APPARATUS}Bridge construction device {BRIDGE CONSTRUCTION APPARATUS}

본 발명은 교량 건설장치에 관한 것으로서, 특히 PSM(Precast Segmental Method)공법의 상·하부 타입 각각의 장단점을 상호 보완하여 하부 구조물인 교각의 안전성을 확보하고 원가를 절감하면서 공기를 단축할 수 있는 교량 건설장치에 관한 것이다.The present invention relates to a bridge construction device, and in particular, to complement the strengths and weaknesses of the upper and lower types of the PSM (Precast Segmental Method) method mutually to secure the safety of the bridge pier, the bridge structure that can shorten the air while reducing costs It relates to a construction device.

PSM공법이란 일정한 길이로 분할된 교량 상부 구조물인 상판 세그먼트(Segment)를 제작장에서 균일한 품질로 정밀 제작한 후 가설장소에서 각종의 가설장비를 사용하여 가설 트러스 상에 정렬시킨 후 접합, 인장시켜 교량을 완성해 나가는 공법이다.The PSM method is to precisely manufacture the top plate segment, which is the upper structure of the bridge divided into a certain length, with uniform quality at the manufacturing site, and then align it on the temporary truss using various construction equipment at the construction site, then join and tension it. It is a construction method to complete the bridge.

이러한 PSM공법의 특징은 취급이 편리한 치수, 경량의 세그먼트로 분할하여 시공할 수 있으므로 대형구조물, 복잡한 형상의 구조물도 비교적 용이하게 시공할 수 있고, 상판 세그먼트가 일정한 장소에서 제작되므로 콘크리트의 품질관리가 용이할 뿐만 아니라 상판 세그먼트를 연속적으로 제작하므로 인력관리 및 거푸집 전용이 가능하며, 상판 세그먼트 제작을 하부공사와 병행해서 실시할 수 있으므로 현장 타설 방식에 비해서 공기를 단축할 수 있다.The characteristics of the PSM method can be divided into easy-to-handle dimensions and lightweight segments, so that large structures and complex shaped structures can be constructed relatively easily. Not only is it easy to manufacture the top plate segment continuously, it is possible to manpower management and formwork only, and the top plate segment can be carried out in parallel with the lower construction, it is possible to shorten the air compared to the field casting method.

또한, 상부구조 가설시 콘크리트는 상당한 재령에 도달해 있기 때문에 가설후에 발생하는 크리프(creep), 건조수축 등에 의한 소성변형이 적게 발생하여 프리스트레스(Prestress)의 감소량 등이 작아져 유리하다.In addition, since the concrete reaches a significant age during the construction of the superstructure, less plastic deformation occurs due to creep, dry shrinkage, etc. occurring after the construction, and thus, the amount of reduction in prestress is reduced, which is advantageous.

상판 세그먼트 제작방법에는 세그먼트를 개별적으로 제작하여 이음부를 0.15~1.0m 범위로 이음 콘크리트가 완전히 경화한 후 프리스트레싱하여 접합하도록 하는 와이드 조인트 방식(Wide Joing Type)과, 바로 전에 생산된 세그먼트면을 그대로 거푸집면(Counter Mould)으로 이용하여 다음 세그먼트를 타설하므로써 접합면에서 완벽한 결합이 이루어질 수 있도록 하는 매취 캐스트 조인트 방식(Match-Cast Joint Type)이 있으며, 매취 캐스트 조인트 방식에는 롱 라인(Long Line) 공법과 쇼 라인(Short Line) 공법이 있다.The upper plate segment manufacturing method is a wide jointing type (Wide Joing Type), in which the segments are manufactured separately, and the joints are fully hardened in the range of 0.15 to 1.0m, and then prestressed to join the joints. There is a Match-Cast Joint Type that allows perfect joining at the joint surface by casting the next segment by using the Counter Mold.The Mast Cast Joint Method uses the Long Line method and There is a short line method.

가설방법에는 FCM방법(Free Cantilever Method), SPAN BY SPAN방법 및 프로그레시브 방법(Progressive Method) 등 여러방법이 있으나 본 발명에서 언급하고자 하는 방법은 SPAN BY SPAN방법으로서, 가동식 가설 트러스를 교각과 교각 사이에 설치하고 미리 제작된 프리캐스트 세그먼트를 그 위에 정렬한 후 스트레싱을 가하여 인접 지간과 연결하는 방법이다.There are several methods of hypothesis such as FCM method, SPAN BY SPAN method and progressive method, but the method to be mentioned in the present invention is a SPAN BY SPAN method, a movable hypothetical truss between the piers and piers This is done by installing and arranging precast segments on the prefabricated segments and applying stressing to connect them to adjacent spaces.

도 1에서는 종래 PSM공법 중 상부 타입을 개략적으로 도시하고 있다.1 schematically shows an upper type of a conventional PSM method.

상부 타입 PSM공법은 인접한 두 교각(2)(2')에 하부 빔(4)(4')을 설치하고, 그 하부 빔(4)(4')을 가로질러 가설 트러스(6)를 설치하며, 가설 트러스(6)에 설치된 크레인(8)으로 상판 세그먼트(S)를 이어나가는 방식으로 교량을 건설한다.The upper type PSM method installs the lower beams 4 and 4 'in two adjacent piers 2 and 2' and installs a temporary truss 6 across the lower beams 4 and 4 '. The bridge is constructed in such a way that the upper plate segment S is connected to the crane 8 installed on the temporary truss 6.

도 2 내지 도 4는 종래 PSM공법 중 하부 타입을 개략적으로 도시한 도면들이다.2 to 4 are schematic views showing the lower type of the conventional PSM method.

하부 타입 PSM공법은 각 교각(10)(10')의 측면에 브라켓(12)(12')을 설치한 후 교각(10)과 교각(10') 사이에 가설 트러스(14)를 설치하며, 운반된 상판 세그먼트(S)를 크레인(16)으로 들어 올려 연속으로 이어나가 교량을 건설한다. 상판 세그먼트(S)의 접합은 에폭시를 사용하고 접합면의 인장응력에 대한 저항을 높인 상태에서 상판 세그먼트(S)의 중심을 관통한 강선을 스트레싱하여 상판 세그먼트(S)의 정렬을 종료한다.The lower type PSM method installs brackets 12 and 12 'on the side of each pier 10, 10' and then installs a temporary truss 14 between the pier 10 and the pier 10 '. The conveyed upper plate segment S is lifted up by the crane 16 and continues in succession to construct a bridge. Joining of the upper plate segment (S) terminates the alignment of the upper plate segment (S) by using a epoxy and by stretching a steel wire passing through the center of the upper plate segment (S) while increasing the resistance to the tensile stress of the bonding surface.

도 4에서 도시한 바와 같이 크로스 빔(18)은 교각(10) 위에서 힌지 고정되어 회전 개폐되어지며, 가설 트러스(14)의 이동시 고정 브라켓(20)을 해체한 후 크로스 빔(18)을 개방 회전시킨 후 가설 트러스(14)를 전진시키게 된다.As shown in FIG. 4, the cross beam 18 is hinged on the pier 10 to be rotated and opened and closed, and when the temporary truss 14 is moved, the cross beam 18 is opened to rotate after dismantling the fixing bracket 20. After making the hypothesis truss 14 is advanced.

그러나, 전술한 상부 타입의 PSM공법의 경우에는 가설장비가 상판 세그먼트의 위에 설치되어 세그먼트가 매달린 채 이동하므로 바람의 영향을 많이 받는 곳에서는 작업이 불안정하고 이에 따른 공기 지연이 우려된다. 또한 가설장비의 이동이 완성된 상판 위에서 이루어짐에 따라 상부에 하중이 집중되는 문제점이 있다.However, in the case of the PSM method of the upper type described above, since the temporary equipment is installed on the upper plate segment and the segment is suspended, the work is unstable in the place affected by the wind and there is concern about air delay. In addition, there is a problem that the load is concentrated on the upper part as the temporary equipment is made on the completed top plate.

한편, 하부 타입의 PSM공법의 경우에는 센트럴 트러스와 사이드 트러스 및 상판 세그먼트의 하중이 브라켓을 통해 교각 외부에 집중됨으로써 교각 안전성이 위협받게 되며, 또한 고공에서 브라켓을 설치/제거하기 위해서는 대형 장비 및 해상의 경우에는 선박이 요구되어 건설비용이 상승할 뿐만 아니라 이러한 관련작업으로 인한 공기가 지연되는 문제점이 있다.On the other hand, in the case of the lower PSM method, the load of the central truss, side truss and top segment is concentrated outside the pier through the bracket, and the pier safety is threatened. In the case of the vessel is required to not only increase the construction cost, but also has a problem that the air delay due to such related work.

이와 같은 문제점들을 해결하기 위해 안출된 본 발명은 하부 구조물인 교각의 안전성을 확보하고 원가를 절감하면서 공기를 단축할 수 있는 교량 건설장치를 제공하는 것이 목적이다.The present invention devised to solve such problems is an object of the present invention to provide a bridge construction apparatus that can shorten the air while ensuring the safety of the lower bridge pier and cost.

상술한 목적을 달성하기 위해서 본 발명의 교량 건설장치는 상판 세그먼트의 상면에 배치되는 지지목; 전후방측의 교각과 교각 사이에 설치되는 한편 양측에 상판 세그먼트가 배치되며, 전후진 가능한 이송트러스를 갖는 센트럴 트러스; 센트럴 트러스와 교각 사이에 설치되어 센트럴 트러스를 승하강시키는 유압잭; 센트럴 트러스의 후방측에 좌우측으로 가로질러 설치되어지되 지지목에 얹혀지는 후방측 크로스 빔; 후방측 크로스 빔에 고정 설치되어 상판 세그먼트를 집어서 센트럴 크로스에 정열시키는 크레인; 센트럴 트러스의 전방측에 좌우측으로 가로질러 설치되어지되 상판 세그먼트의 위에 탈착 가능하게 설치되는 전방측 크로스 빔; 전방측 크로스 빔의 상부에 설치되어지되 일측이 사이드 트러스와 전방측 크로스 빔의 연결지점과 상판 세그먼트를 구성하는 두 면의 접합되는 지점에 해당하는 전방측 크로스 빔의 상부에 고정되고 타측이 하나로 모아지게 세워진 다수의 지지대로 구성되는 하중 분산 지지부재; 후방측 크로스 빔과 전방측 크로스 빔의 양단에 전후방측 방향으로 설치되는 사이드 트러스; 및 센트럴 트러스와 사이드 트러스에 설치되어 크레인으로부터 견인된 상판 세그먼트가 센트럴 트러스에 안착되면 전방측으로 이송시키는 이송레일로 구성된다.Bridge construction apparatus of the present invention to achieve the above object is a support wood disposed on the upper surface of the upper segment; A central truss, which is installed between the piers and the piers on the front and rear sides, and has a top plate segment disposed on both sides, and has a transfer truss that can move back and forth; A hydraulic jack installed between the central truss and the pier to raise and lower the central truss; A rear cross beam mounted transversely to the rear side of the central truss and mounted on the support neck; A crane fixed to the rear cross beam to pick up the upper segment and align it to the central cross; A front cross beam installed transversely from left to right on the front side of the central truss and detachably installed on the upper plate segment; It is installed on the upper side of the front cross beam, and one side is fixed to the upper side of the front cross beam corresponding to the junction point of the side truss and the front cross beam and the two sides constituting the top plate segment, and the other side is gathered into one. A load distribution support member composed of a plurality of support stands erected; Side trusses provided at both ends of the rear cross beam and the front cross beam in front and rear directions; And a transfer rail installed in the central truss and the side truss and transported to the front side when the upper plate segment pulled from the crane is seated on the central truss.

여기서, 후방측 크로스 빔의 양 끝부분은 상판 세그먼트의 가장자리를 감싸게 형성되는 한편 양단이 사이드 트러스에 결합되는 것이 바람직하다.Here, it is preferable that both ends of the rear cross beam are formed to surround the edge of the upper plate segment while both ends are coupled to the side truss.

특히, 교량이 좌우측의 어느 한 쪽으로 기울어진 부분을 건설할 경우 사이드 트러스와 교각 사이의 접촉을 방지하기 위해서 사이드 트러스와 교각 사이에 버팀대가 설치되는 것이 바람직하다.In particular, when the bridge is built to one side of the left and right sides, it is preferable that a brace is installed between the side truss and the pier to prevent contact between the side truss and the pier.

아울러, 교량이 전후방측으로 경사지게 건설될 경우 상판 세그먼트가 미끄럼되는 것을 방지하기 위해서 유압잭의 상면에 스톱퍼가 고정되는 것이 바람직하다.In addition, it is preferable that the stopper is fixed to the upper surface of the hydraulic jack in order to prevent the upper plate segment from sliding when the bridge is inclined forward and backward.

도 1은 종래 상부타입의 교량 건설장치의 구성을 개략적으로 도시한 측면도,1 is a side view schematically showing the configuration of a bridge construction apparatus of the conventional upper type,

도 2는 종래 하부타입의 교량 건설장치의 구성을 개략적으로 도시한 측면도,Figure 2 is a side view schematically showing the configuration of a bridge construction apparatus of the conventional lower type,

도 3은 도 2의 구성을 개략적으로 도시한 정면도,3 is a front view schematically showing the configuration of FIG.

도 4는 도 2의 구성 일부를 개략적으로 도시한 평면도.4 is a plan view schematically illustrating a part of the configuration of FIG. 2;

도 5는 본 발명에 관련된 교량 건설장치의 구성을 도시한 측면도,5 is a side view showing the configuration of a bridge construction apparatus according to the present invention;

도 6은 본 발명에 관련된 교량 건설장치의 후방측부분을 개략적으로 도시한 정면도,6 is a front view schematically showing a rear side portion of the bridge construction apparatus according to the present invention;

도 7은 본 발명에 관련된 교량 건설장치의 전방측부분을 개략적으로 도시한 정면도,7 is a front view schematically showing a front side portion of the bridge construction apparatus according to the present invention;

도 8은 본 발명에 관련된 교량 건설장치를 도시한 평면도,8 is a plan view showing a bridge construction apparatus according to the present invention,

도 9는 본 발명에 관련된 교량 건설장치가 다음 경간으로 이동시 전방측 크로스 빔의 상태를 도시한 평면도,9 is a plan view showing the state of the front side cross beam when the bridge construction apparatus according to the present invention moves to the next span,

도 10은 본 발명에 관련된 교량 건설장치가 교량의 경사진 부분에 위치시 사이드 트러스와 교각의 접촉부분을 도시한 도면,10 is a view showing the contact portion of the side truss and the pier when the bridge construction device according to the present invention is located on the inclined portion of the bridge,

도 11은 본 발명에 관련된 상판 세그먼트가 교량의 전후 경사지점에서 미끄럼되는 것을 방지하기 위한 장치를 도시한 도면.FIG. 11 illustrates an apparatus for preventing the top plate segment related to the present invention from slipping at the front and rear slope points of a bridge. FIG.

<< 도면의 주요 부분에 대한 부호의 설명 >><< Explanation of symbols for main part of drawing >>

S..상판 세그먼트S..Top Segment

50, 50'..교각 100..센트럴 트러스50, 50 '.. Pier 100 .. Central truss

101..이송 트러스 102..사이드 트러스101..Transfer Truss 102..Side Truss

104..후방측 크로스 빔 106..크레인104. Rear cross beam 106. Crane

108..이송 레일 110..유압 잭108. Transfer rail 110. Hydraulic jack

112..전방측 크로스 빔 114..고정구112. Front cross beam 114. Fixture

116..하중 분산 부재 118..지지목116. Load distribution members

120..버팀대 122..스톱퍼120. Brace 122. Stopper

이하 첨부된 도면에 의거하여 본 발명의 바람직한 실시예에 따른 교량 건설장치를 상세히 설명한다.Hereinafter, a bridge construction apparatus according to a preferred embodiment of the present invention will be described in detail with reference to the accompanying drawings.

본 발명의 설명에 들어가기에 앞서 상판 세그먼트의 제작과정을 소개하면, 세그먼트는 교량의 경간 전체를 일괄 제작하는 롱 라인(Long Line) 방식과 이전에 제작된 세그먼트를 고정 거푸집으로 하여 동일 장소에서 하나씩 제작하는 본 발명에서 사용되는 쇼 라인(Short Line) 방식의 두가지가 있다.Prior to the description of the present invention, the manufacturing process of the top plate segment is introduced, and the segments are manufactured in one place at the same place by using the Long Line method for collectively manufacturing the entire span of the bridge and the previously manufactured segments as fixed molds. There are two types of short line methods used in the present invention.

제작 과정은 먼저 철근 가공장, 철근제작장, 세그먼트 제작장에서 콘크리트 타설 및 양생까지 일련의 과정을 반복하는데, 철근절단 및 가공 후에 철근조립용 지지대인 지그 위에서 철근 조립 및 시드 파이프(Sheath Pipe)를 설치하고, 바닥거푸집과 바깥측 거푸집을 설치한 후에 이미 조립된 철근 케이지(cage)를 운반 설치하며, 내부 틀을 설치한다.The fabrication process is a series of processes from rebar processing, rebar fabrication, segment manufacturing to concrete placement and curing. After rebar cutting and processing, the rebar assembly and seed pipe are installed on the jig. After installing the floor formwork and the outer formwork, transport and install the already assembled rebar cage, and install the inner frame.

이어서, 콘크리트를 철근 케이지와 내부 틀 사이에 타설 시킨 후 양생 및 내부 틀을 해체하여 완성한다.Subsequently, the concrete is poured between the reinforcing cage and the inner frame and then cured and dismantled.

이러한 세그먼트는 중심에 채널을 갖는 대략 '' 모양으로 형성되며, 2열 종방향으로 후술하는 센트럴 트러스와 사이드 트러스의 사이에 배치된다.These segments are roughly ' It is formed in a shape, and is disposed between the central truss and the side truss described later in the two-row longitudinal direction.

도 5는 본 발명에 관련된 교량 건설장치의 구성을 도시한 측면도이고, 도 6은 교량 건설장치의 후방측부분을 개략적으로 도시한 정면도이고, 도 7은 교량 건설장치의 전방측부분을 개략적으로 도시한 정면도이고, 도 8은 교량 건설장치를 도시한 평면도이며, 도 9는 교량 건설장치가 다음 경간으로 이동시 전방측 크로스 빔의 상태를 도시한 평면도이다.Figure 5 is a side view showing the configuration of the bridge construction apparatus according to the present invention, Figure 6 is a front view schematically showing a rear side portion of the bridge construction apparatus, Figure 7 schematically shows a front side portion of the bridge construction apparatus. 8 is a plan view illustrating a bridge construction apparatus, and FIG. 9 is a plan view illustrating a state of the front side cross beam when the bridge construction apparatus moves to the next span.

도 5 내지 도 8에 도시된 바와 같이, 본 발명의 교량 건설장치는 경간(교각과 교각 사이)에 런칭 트러스(Launching Truss)인 센트럴 트러스(100)와 사이드 트러스(102)를 가설한 후, 후방측 크로스 빔(104)에 설치되는 크레인(106)으로 상판 세그먼트(S)를 센트럴 트러스(100)와 사이드 트러스(102) 사이에 안착시키고 이송레일(108)을 이용하여 전방측을 향해 순차적으로 이송시킬 때 사용되며, 이송된 후 정렬된 상판 세그먼트(S)는 에폭시 수지로 접합시킨 후 강선으로 스트레싱하여 고정시킨다.As shown in Figures 5 to 8, the bridge construction apparatus of the present invention after installing the central truss 100 and the side truss 102, which is a launching truss (Launching Truss) in the span (between pier and piers), the rear The crane 106 installed on the side cross beam 104 seats the upper plate segment S between the central truss 100 and the side truss 102 and sequentially transfers toward the front side using the transfer rail 108. It is used when making, and the upper plate segments (S) aligned after being transferred are bonded by epoxy resin and then stretched and fixed with steel wire.

센트럴 트러스(100)는 1 경간인 전후방측의 교각(50)과 교각(50') 사이에 설치되며, 센트럴 트러스(100)의 내부에는 전후진 가능한 이송트러스(101)가 내장되어 1 경간에서의 작업이 종료되면 이송트러스(101)가 인출되어 다음 교각으로 이동후 거치된 상태에서 센트럴 트러스(100)와 사이드 트러스(102)가 다음 경간으로 함께 이송된다. 사이드 트러스(102)는 센트럴 트러스(100)의 양측에 소정 간격을 두고 설치된다.The central truss 100 is installed between the piers 50 and the piers 50 'of the front and back sides, which are one span, and the transfer truss 101 which can move back and forth is built in the central truss 100 so that When the work is finished, the transport truss 101 is drawn out and moved to the next pier, and then the central truss 100 and the side truss 102 are transported together in the next span. The side truss 102 is installed at both sides of the central truss 100 at predetermined intervals.

센트럴 트러스(100)와 사이드 트러스(102)의 상면에는 이송레일(108)이 설치되어 크레인(106)으로부터 견인된 상판 세그먼트(S)가 센트럴 트러스(100)에 안착되면 전방측으로 이송시키게 된다.Transfer rails 108 are installed on the upper surfaces of the central truss 100 and the side truss 102 so that the upper plate segments S pulled from the crane 106 are transferred to the front side when they are seated on the central truss 100.

센트럴 트러스(100)와 교각(50)(50') 사이에는 센트럴 트러스(100)를 승하강시키는 유압잭(110)이 설치되어 상판 세그먼트(S)의 시공이 완료된 후 센트럴 트러스(100)를 하강시켜 다음 교각으로 이송이 가능하게 된다.A hydraulic jack 110 is installed between the central truss 100 and the piers 50 and 50 'to raise and lower the central truss 100, and then the central truss 100 is lowered after the construction of the upper plate segment S is completed. It is possible to transfer to the next pier.

그리고, 교각(50)(50')의 상부인 센트럴 트러스(100)와 사이드 트러스(102)의 전후방측에 각각 전방측 크로스 빔(112)과 후방측 크로스 빔(104)이 설치되는 바, 센트럴 트러스(100)에 대해 직교되는 방향으로 설치된다.In addition, the front cross beam 112 and the rear cross beam 104 are installed at the front and rear sides of the central truss 100 and the side truss 102, which are upper portions of the pier 50, 50 ', It is installed in the direction orthogonal to the truss 100.

전방측 크로스 빔(112)은 센트럴 트러스(100)에 거치된 상태로 사이드 트러스(102)의 전방측 단을 지지하며, 단지 센트럴 트러스(100)와 사이드 트러스(102)가 이동시 도 9에 도시된 바와 같이 전방측 크로스 빔(112)은 완성된 상판 세그먼트(S)의 고정구(114)에 의해 고정된다.The front cross beam 112 supports the front end of the side truss 102 in a state where it is mounted on the central truss 100, and only when the central truss 100 and the side truss 102 move, as shown in FIG. 9. As described above, the front side cross beam 112 is fixed by the fastener 114 of the completed upper plate segment S. As shown in FIG.

전방측 크로스 빔(112)의 상부에는 다수의 지지대(117)로 구성된 하중 분산 지지부재(116)가 설치되어지되 지지대(117)의 일측은 사이드 트러스(102)와 전방측 크로스 빔(112)의 연결지점과 상판 세그먼트(S)를 구성하는 두 면이 접합되는 지점에 해당하는 전방측 크로스 빔(112)의 상부에 고정 지지되고, 지지대(117)의 타측은 하나로 모아져 정면에서 보면 우산살과 유사한 모양으로 제작된다.A load distribution support member 116 composed of a plurality of supports 117 is installed on the upper side of the front cross beam 112, but one side of the support 117 is formed of the side truss 102 and the front side cross beam 112. It is fixedly supported on the upper side of the front cross beam 112 corresponding to the point where the two sides constituting the connecting point and the upper plate segment (S), the other side of the support 117 is gathered into one and looks like an umbrella It is made into a shape.

후방측 크로스 빔(104)은 상판 세그먼트(S)의 상부에 설치되며 후방측 크로스 빔(104)의 양 끝부분은 상판 세그먼트(S)의 측면을 감싸면서 양단은 상판 세그먼트(S)의 하부에 위치된 상태에서 사이드 트러스(102)에 고정된다.The rear side cross beam 104 is installed on the upper plate segment S, and both ends of the rear side cross beam 104 surround the side surface of the upper plate segment S, and both ends are disposed under the upper plate segment S. It is fixed to the side truss 102 in the positioned state.

후방측 크로스 빔(104)과 상판 세그먼트(S)의 상면에는 쇠뭉치로 된 지지목(118)이 배치되어 는 후방측 크로스 빔(104)을 지지하게 되며, 후방측 크로스 빔(104)의 위에는 크레인(106)이 설치되어 상판 세그먼트(S)를 집어서 상기 센트럴 크로스(100)에 정열시킨다.On the upper surface of the rear side cross beam 104 and the upper plate segment (S) is supported a rear side cross beam 104 in which a support neck 118 made of a metal ball is disposed, and a crane on the rear side cross beam 104. A 106 is installed to pick up the top plate segment S and align it to the central cross 100.

한편, 도 10에 도시된 바와 같이 교량의 좌우측 한쪽이 기울어지게 시공되는 경간에서는 교각(50)과 사이드 트러스(102) 사이에 접촉이 발생될 수 있는데, 이로 인하여 교각의 주두부가 손상될 수 있기 때문에 본 발명에서는 교각(50)과 사이드 트러스(102)의 사이에 버팀대(120)가 설치된다.On the other hand, as shown in FIG. 10, in the span in which the left and right sides of the bridge are inclined, contact may occur between the pier 50 and the side truss 102, which may damage the head of the pier. Therefore, in the present invention, the brace 120 is installed between the pier 50 and the side truss 102.

또한, 도 11에 도시된 바와 같이 교량의 전후가 기울어진 경간에서는 센트럴 트러스(100)에 정렬된 상판 세그먼트(S)가 하중에 의해 미끄럼되는 것을 방지하기 위해서 유압잭(110)의 상면에 스톱퍼(122)를 고정시켜 상판 세그먼트(S)의 하면이 스톱퍼와 마찰됨으로써 미끄럼되는 것을 방지하는 것이다.In addition, as shown in FIG. 11, the stopper 122 is disposed on the upper surface of the hydraulic jack 110 in order to prevent the upper plate segment S aligned with the central truss 100 from sliding under load in a span in which the front and rear of the bridge are inclined. ) Is fixed to prevent the lower surface of the upper plate segment S from sliding by friction with the stopper.

이상과 같이 구성된 본 발명에 따른 교량 건설장치의 작동과 함께 효과를 설명한다.The effect together with the operation of the bridge construction apparatus according to the present invention configured as described above will be described.

우선, 교각(50)과 교각(50') 사이에 센트럴 트러스(100)와 사이드 트러스(102)가 안착된 상태에서 세그먼트 제작장으로부터 이송되어 온 상판 세그먼트(S)를 크레인(106)으로 들어 올려 상판 세그먼트(S)의 양측 하면 가장자리가 센트럴 트러스(100)와 사이드 트러스(102)에 안착되도록 배치시킨다.First, the crane plate 106 lifts the upper plate segment S transferred from the segment fabrication shop in the state where the central truss 100 and the side truss 102 are seated between the pier 50 and the pier 50 '. Both bottom surface edges of the upper plate segment S are disposed to be seated on the central truss 100 and the side truss 102.

이때 상판 세그먼트(S)는 이송레일(108)에 의해 전방측 크로스 빔(112) 쪽으로 이송되고, 이어서 다른 상판 세그먼트들도 전술한 방식에 의해 순차적으로 정렬된다.The upper plate segment S is then conveyed toward the front cross beam 112 by the conveying rail 108, and then the other upper plate segments are also sequentially aligned in the manner described above.

그리고, 상판 세그먼트(S)는 에폭시 수지로 접합시켜 접합면의 인장응력에 대한 저항을 높인다.Then, the upper plate segment (S) is bonded by epoxy resin to increase the resistance to the tensile stress of the bonding surface.

이어서, 정렬된 상판 세그먼트(S)의 덕트 내부로 강선을 관통 후 강선의 양단을 고정시킨 후 스트레싱하여 상판 세그먼트(S)를 완전히 정렬시킨다.Subsequently, after passing the steel wire into the duct of the aligned upper plate segment S, both ends of the steel wire are fixed and stretched to completely align the upper plate segment S.

이와같은 작업을 통해 1 경간이 완성되면 도 9에 도시된 바와 같이 전방측 크로스 빔(112)을 고정구(114)에 고정시킨 후 사이드 트러스(102)와 전방측 크로스 빔(112)의 연결부위를 해체시키고, 이송 트러스(101)를 다음 교각으로 전진시켜 그 교각에 고정시킨 후 고정부(114)를 해제한다.When one span is completed through the above operation, the front cross beam 112 is fixed to the fixture 114 as shown in FIG. 9, and then the connection portion between the side truss 102 and the front cross beam 112 is fixed. After dismantling, the transfer truss 101 is advanced to the next pier to be fixed to the pier, and then the fixing part 114 is released.

이어서, 유압잭(110)을 작동시켜 센트럴 트러스(100)를 하강시키고 나서 센트럴 트러스(100)와 사이드 트러스(102)를 이송시키면 전후방측 크로스 빔(104)(112)과 크레인등 나머지가 모두 견인된다.Subsequently, when the central truss 100 is lowered by operating the hydraulic jack 110 and then the central truss 100 and the side truss 102 are transferred, the front and rear cross beams 104 and 112 and the rest of the crane are towed. .

견인이 종료되면 전방측 크로스 빔(112)과 사이드 트러스(102)를 연결시킨다.When the towing is finished, the front cross beam 112 and the side truss 102 are connected.

상술한 바와 같은 작업 과정에서, 전방측 크로스 빔(112)을 완성된 상판 세그먼트(S)에 고정시킴으로써 이송 트러스(101)의 이송시 이송 트러스만 전진하면 되기 때문에 전방측 크로스 빔(112)의 무게로 인한 무게중심의 변화에 따른 전복 위험성은 제거된다.In the above working process, the front cross beam 112 is fixed to the completed upper plate segment S so that only the transport truss needs to be advanced when the transport truss 101 is transported. The risk of overturning due to changes in the center of gravity due to

또한, 본 발명에서 제안한 고정구(114)는 종래의 전방측 크로스 빔(112)과 센트럴 트러스(100) 및 사이드 트러스(102) 사이의 접합 및 해체에 따른 재해 발생 위험성과 장비 투입에 따른 비용이 절감된다.In addition, the fixture 114 proposed in the present invention reduces the risk of disaster occurrence due to the joining and dismantling between the conventional front cross beam 112 and the central truss 100 and the side truss 102 and the cost of equipment input do.

아울러, 후방측 크로스 빔(104)은 상판 세그먼트(S)의 상부에 위치시키고 하중의 받는 후방측 크로스 빔(104)의 양단은 상판 세그먼트(S)의 하부로 위치시킨 후 사이드 트러스(102)에 결합시킴으로써 사이드 트러스(102)의 하중은 교각 중앙 및 상판으로 분산되어 하부 구조물의 안정성을 확보할 수 있다.In addition, the rear cross beam 104 is positioned above the upper plate segment S, and both ends of the rear cross beam 104 under load are positioned under the upper plate segment S, and then the side truss 102 is placed on the side truss 102. By combining, the load of the side truss 102 is distributed to the center of the piers and the top plate to ensure the stability of the lower structure.

나아가, 전방측 크로스 빔(112)도 센트럴 트러스(100)의 상부에 거치시키고 전방측 크로스 빔(112)의 상부에 하중 분산 부재(116)를 설치시킴으로써 사이드 트러스(102)의 하중을 센트럴 트러스(100) 및 교각 중앙부에 집중시켜 구조적 안정성을 확보하였다.Furthermore, the front cross beam 112 is also mounted on the top of the central truss 100 and the load distribution member 116 is installed on the top of the front cross beam 112 to load the central truss 102. 100) and the center of the pier to ensure structural stability.

이상에서 살펴본 바와 같이 본 발명에 따른 바람직한 실시예는 종래의 문제점을 실질적으로 해소하고 있다.As described above, the preferred embodiment of the present invention substantially solves the conventional problems.

즉, 가설장비를 PSM공법의 하부 타입과 유사하게 상판 세그먼트의 상부에 설치하여 상판 세그먼트 정렬 작업시 안정성을 확보하면서도 후방측 크로스 빔의 양단이 상판 세그먼트의 하부에 위치된 상태에서 사이드 트러스와 결합되어 구조적으로도 안정적이다.In other words, similar to the lower type of the PSM method, the temporary equipment is installed on the upper part of the upper segment to ensure stability during the upper segment alignment, while both ends of the rear cross beam are coupled with the side truss while the lower end of the upper cross segment is located at the lower part of the upper segment. It is also structurally stable.

또한, 교각에 브라켓을 설치하지 않기 때문에 브라켓의 설치/제거 작업에 따른 재해 발생의 위험성과 비용 상승 및 교각의 안전성 위협으로부터 해방되는 효과가 있다.In addition, since the bracket is not installed in the pier, there is an effect of being freed from the risk of disaster occurrence due to the installation / removal of the bracket and the increase in cost and the safety threat of the pier.

아울러, 사이드 트러스와 전방측 크로스 빔 사이의 접합 및 해체에 따른 재해 발생 위험성과 장비 투입에 따른 비용이 절감된다.In addition, the risk of disaster caused by joining and dismantling between the side truss and the front cross beam and the cost of equipment input are reduced.

Claims (4)

교각과 교각 사이에 격자 모양의 상판 세그먼트를 연속으로 이어서 교량을 건설하는 PSM공법에 이용되는 교량 건설 장치에 있어서,In the bridge construction apparatus used in the PSM method of constructing a bridge by successively lattice-shaped plate segment between the bridge piers, 상기 상판 세그먼트의 상면에 배치되는 지지목;A support neck disposed on an upper surface of the upper segment; 전후방측의 교각과 교각 사이에 설치되는 한편 양측에 상기 상판 세그먼트가 배치되며, 전후진 가능한 이송트러스를 갖는 센트럴 트러스;A central truss installed between the piers and the piers on the front and rear sides, and having the upper plate segments disposed on both sides, and having a transfer truss that can move back and forth; 상기 센트럴 트러스와 교각 사이에 설치되어 상기 센트럴 트러스를 승하강시키는 유압잭;A hydraulic jack installed between the central truss and the piers to move up and down the central truss; 상기 센트럴 트러스의 후방측에 좌우측으로 가로질러 설치되어지되 상기 지지목에 얹혀지는 후방측 크로스 빔;A rear cross beam which is installed on the rear side of the central truss and crosses the left and right sides and is mounted on the support neck; 상기 후방측 크로스 빔에 고정 설치되어 상기 상판 세그먼트를 집어서 상기 센트럴 크로스에 정열시키는 크레인;A crane fixed to the rear cross beam to pick up the top plate segment and align it to the central cross; 상기 센트럴 트러스의 전방측에 좌우측으로 가로질러 설치되어지되 상기 상판 세그먼트의 위에 탈착 가능하게 설치되는 전방측 크로스 빔;A front cross beam installed transversely from left to right on the front side of the central truss and detachably installed on the upper plate segment; 상기 전방측 크로스 빔의 상부에 설치되어지되 일측이 상기 사이드 트러스와 전방측 크로스 빔의 연결지점과 상판 세그먼트를 구성하는 두 면의 접합되는 지점에 해당하는 상기 전방측 크로스 빔의 상부에 고정되고 타측이 하나로 모아지게 세워진 다수의 지지대로 구성되는 하중 분산 지지부재;It is installed on the upper side of the front side cross beam, and one side is fixed to the upper side of the front side cross beam corresponding to the junction point of the side truss and the front side cross beam and the two surfaces constituting the upper plate segment and the other side. A load distribution support member composed of a plurality of support bars erected together; 상기 후방측 크로스 빔과 상기 전방측 크로스 빔의 양단에 전후방측 방향으로 설치되는 사이드 트러스; 및Side trusses which are installed in both front and rear directions at both ends of the rear cross beam and the front cross beam; And 상기 센트럴 트러스와 상기 사이드 트러스에 설치되어 크레인으로부터 견인된 상기 상판 세그먼트가 상기 센트럴 트러스에 안착되면 전방측으로 이송시키는 이송레일로 구성되는 것을 특징으로 하는 교량 건설장치.Bridge construction apparatus is installed in the central truss and the side truss and comprises a transfer rail for transporting the upper plate segment to the front side when seated on the central truss is pulled from the crane. 제 1 항에 있어서, 상기 후방측 크로스 빔의 양 끝부분은 상기 상판 세그먼트의 가장자리를 감싸게 형성되는 한편 양단이 상기 사이드 트러스에 결합되는 것을 특징으로 하는 교량 건설장치.The bridge construction apparatus according to claim 1, wherein both ends of the rear cross beam are formed to surround an edge of the upper segment, while both ends are coupled to the side truss. 제 1 항 또는 제 2 항 중 어느 한 항에 있어서, 교량이 좌우측의 어느 한 쪽으로 기울어진 부분을 건설할 경우 상기 사이드 트러스와 상기 교각 사이의 접촉을 방지하기 위해서 상기 사이드 트러스와 상기 교각 사이에 버팀대가 설치되는 것을 특징으로 하는 교량 건설장치.The brace according to any one of claims 1 to 3, wherein a brace between the side truss and the pier to prevent contact between the side truss and the pier when the bridge is constructed inclined to either side of the right and left sides. Bridge construction apparatus characterized in that the installation. 제 3 항에 있어서, 교량이 전후방측으로 경사지게 건설될 경우 상기 상판 세그먼트가 미끄럼되는 것을 방지하기 위해서 상기 유압잭의 상면에 스톱퍼가 고정되는 것을 특징으로 하는 교량 건설장치.4. The bridge construction apparatus according to claim 3, wherein a stopper is fixed to an upper surface of the hydraulic jack to prevent the upper segment from sliding when the bridge is inclined forward and backward.
KR10-2000-0039151A 2000-07-08 2000-07-08 Bridge construction apparatus KR100382320B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2000-0039151A KR100382320B1 (en) 2000-07-08 2000-07-08 Bridge construction apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2000-0039151A KR100382320B1 (en) 2000-07-08 2000-07-08 Bridge construction apparatus

Publications (2)

Publication Number Publication Date
KR20020005157A KR20020005157A (en) 2002-01-17
KR100382320B1 true KR100382320B1 (en) 2003-05-01

Family

ID=19677012

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2000-0039151A KR100382320B1 (en) 2000-07-08 2000-07-08 Bridge construction apparatus

Country Status (1)

Country Link
KR (1) KR100382320B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109520838B (en) * 2018-12-25 2023-12-15 西南交通大学 Tensile property test device for shield tunnel bolt joint

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3985480A (en) * 1972-08-18 1976-10-12 Dyckerhoff & Widmann Ag Apparatus for the sectional cantilever construction of bridge girder systems
US5195204A (en) * 1990-07-27 1993-03-23 J. Muller International Construction equipment and method for precast segmental bridges
JPH08165613A (en) * 1994-12-13 1996-06-25 Kajima Corp Erection method of bridge beam
JP2000170122A (en) * 1998-12-08 2000-06-20 Kajima Corp Erection method of concrete girder and its device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3985480A (en) * 1972-08-18 1976-10-12 Dyckerhoff & Widmann Ag Apparatus for the sectional cantilever construction of bridge girder systems
US5195204A (en) * 1990-07-27 1993-03-23 J. Muller International Construction equipment and method for precast segmental bridges
JPH08165613A (en) * 1994-12-13 1996-06-25 Kajima Corp Erection method of bridge beam
JP2000170122A (en) * 1998-12-08 2000-06-20 Kajima Corp Erection method of concrete girder and its device

Also Published As

Publication number Publication date
KR20020005157A (en) 2002-01-17

Similar Documents

Publication Publication Date Title
JP3885584B2 (en) Construction method of composite truss bridge
KR100667921B1 (en) Construction method of pylon using precast concrete beam
KR102009134B1 (en) Construction Method of Long Span Girder Bridge
KR100522170B1 (en) Method of constructing simple and continuous composite bridges
CA2061871C (en) Composite, prestressed structural member and method of forming same
KR20130141276A (en) Incremental launching apparatus for launching concrete slab for composite bridge using form of buried type
JP3635004B2 (en) Bridge cantilever construction method
JP2768283B2 (en) Bridge construction method
CN114197325A (en) Pier shaft construction safety protection platform
KR102227878B1 (en) Construction Method of Long Span Bridge Using PSC Girder
CN110904854B (en) Arch bridge construction method adapting to removal progress
KR100382320B1 (en) Bridge construction apparatus
JPH0643686B2 (en) Construction method of arch bridge by precast members
US5553439A (en) Composite, prestressed structural members and methods of forming same
KR101527752B1 (en) Construction method of prestressed composite girder bridge
KR100374017B1 (en) Continuous Preflex Beam Bridge and Constructing Method thereof
KR100244085B1 (en) Prestressed steel-concrete composite continuous beam and the erection method thereof
JP3877995B2 (en) How to build a string string bridge
KR101791949B1 (en) Spreader beam stabilizer for distributing bearing stress, and method using the same
CN110029729B (en) Splicing joint of prefabricated reinforced concrete main beam and secondary beam and construction method
CN110847355A (en) Novel efficient mounting node assembly integral beam column and production design method thereof
JP4375788B2 (en) Construction method of upper-floor type suspension floor slab bridge
KR101739658B1 (en) steel box girder bridge of wide slab and all slab concrete section used as compression member and slab assemblied with steel box
KR100730018B1 (en) Prestressed steel-concrete composite and method for constructing the same
JPH08135182A (en) Timbering sliding construction method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130417

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20140516

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20151019

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20160411

Year of fee payment: 14

FPAY Annual fee payment

Payment date: 20170411

Year of fee payment: 15

FPAY Annual fee payment

Payment date: 20180403

Year of fee payment: 16

FPAY Annual fee payment

Payment date: 20190401

Year of fee payment: 17