KR100302139B1 - Construction method and pull mechanism of prefabricated reinforced retaining wall - Google Patents

Construction method and pull mechanism of prefabricated reinforced retaining wall Download PDF

Info

Publication number
KR100302139B1
KR100302139B1 KR1019980053770A KR19980053770A KR100302139B1 KR 100302139 B1 KR100302139 B1 KR 100302139B1 KR 1019980053770 A KR1019980053770 A KR 1019980053770A KR 19980053770 A KR19980053770 A KR 19980053770A KR 100302139 B1 KR100302139 B1 KR 100302139B1
Authority
KR
South Korea
Prior art keywords
reinforcement
reinforcing material
retaining wall
fixing
spike
Prior art date
Application number
KR1019980053770A
Other languages
Korean (ko)
Other versions
KR20000038693A (en
Inventor
이정수
Original Assignee
이정수
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이정수 filed Critical 이정수
Priority to KR1019980053770A priority Critical patent/KR100302139B1/en
Publication of KR20000038693A publication Critical patent/KR20000038693A/en
Application granted granted Critical
Publication of KR100302139B1 publication Critical patent/KR100302139B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0283Retaining or protecting walls characterised by constructional features of mixed type
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

본 발명은 조립식 보강토 옹벽의 보강재 시공방법 및 그 기구에 관한 것으로, 옹벽 벽체(20) 내면에 돌출형성된 연결구(30)의 걸림부(35)에서 보강재(10)가 동일한 길이로 중간부에서 접혀져 걸림부(35) 바로 선단에서 볼트(12)와 너트(13)로 구성된 체결수단(11)에 의해 두겹의 보강재(10)가 결속되어져 그 후단에서 당김기구(100)에 의해 양방향으로 일정한 각도가 유지되면서 팽팽히 당겨진 상태에서 상기 당김기구(100)에 의해 물린 보강재(10)의 후단부터 유효거리(L)부까지 보강재(10) 중심부의 고정공(15)에 일정한 간격으로 와셔(19)가 일체로 형성된 고정못(17)을 다수 박아 보강토체(50)에 고정시킨 후에 성토 작업과 다짐작업이 이루어지는 보강재 시공방법과, 스파이크(110)가 부착된 발판(105)과 가이드 부재(120), 이동부재(130) 및 조작핸들(134)로 이루어지는 보강재(10)의 당김기구(100)에 있어서, 상기 이동부재(130)의 선단과 물림턱(132)사이에는 상기 물림턱(132)이 상·하로 회전가능하도록 회동부재(140)가 구비되고, 발판(105) 상부의 가이드부재(120)좌·우측 양단에는 내면에 나사가 형성된 스파이크 고정너트(117)를 발판(105)에 관통되도록 돌출형성시키고, 상단부에 볼트부(119)가 형성되고 하단부에 뽀족한 스파이크(110)가 형성된 보조스파이크(118)를 상기 스파이크 고정너트(117)에 분해 결합되도록 하여 이루어지는 것을 특징으로 하는 보강재 당김기구를 제공하여 조립식 옹벽벽체의 시공을 용이하게 한다.The present invention relates to a reinforcement construction method of the prefabricated reinforcement earth retaining wall and its mechanism, the reinforcement 10 is folded in the middle portion of the retaining portion 35 of the connector 30 protruding to the inner wall of the retaining wall wall 20 in the same length. Two layers of reinforcement 10 are bound by the fastening means 11 consisting of the bolt 12 and the nut 13 at the front end of the part 35 so that a constant angle is maintained in both directions by the pulling mechanism 100 at the rear end thereof. Washer 19 integrally at fixed intervals in the fixing hole 15 in the center of the reinforcing material 10 from the rear end of the reinforcing material 10 bitten by the pull mechanism 100 to the effective distance (L) in the pulled state. After fixing a plurality of fixing nails 17 formed in the reinforcement soil body 50, the reinforcement construction method that the filling work and compaction work is performed, the footrest 105, the guide member 120, the movable member, the spike 110 is attached Reinforcement consisting of 130 and the operation handle 134 In the pull mechanism 100 of (10), the rotating member 140 is provided between the leading end of the movable member 130 and the bite jaw 132 so that the bite jaw 132 can be rotated up and down, At both ends of the left and right sides of the guide member 120 at the upper portion of the foot plate 105, a spike fixing nut 117 having a screw formed on the inner surface thereof is projected to penetrate the foot plate 105, and a bolt portion 119 is formed at an upper end thereof and a lower end portion thereof. By providing a reinforcing material pulling mechanism, characterized in that the secondary spike 118 is formed in the spike 110 is formed in the spike fixing nut 117 to facilitate the construction of the prefabricated retaining wall.

Description

조립식 보강토 옹벽의 보강재 시공방법 및 당김기구Construction method and pull mechanism of prefabricated reinforced retaining wall

본 발명은 조립식 보강토 옹벽의 보강재 시공방법 및 당김기구에 관한 것이다.The present invention relates to a reinforcement construction method and a pull mechanism of the prefabricated reinforced soil retaining wall.

종래의 옹벽지지용 보강재의 실시예로는 지오그리드(geogrid, 또는 tensar-grid)등의 망형 보강재가 있으나, 이는 사용범위가 블록식 옹벽에 국한되어 있었으며, 다른 실시예로는 현재 보편적으로 사용되고 있는 금속재 띠 보강재로서 이는 일정폭과 길이를 갖는 띠형의 철판 표면에 부식을 방지하기 위하여 아연도금을 시행한 것으로서, 이는 인장력에 대한 신뢰성은 높으나 고가이며 금속재이므로 단위중량이 커서 보강재 설치작업시 취급 및 운반이 불편하고, 보강토 옹벽 벽체와의 연결방법 및 연결형태가 다양하지 못하며, 연결부위에 핀이나 볼트로 일일이 결속을 시켜주어야 했었으므로 작업성이 저하되는 단점이 있었다.Examples of the conventional retaining wall support reinforcement is a mesh reinforcement such as geogrid (geogrid, or tensar-grid), but the use range is limited to the block retaining wall, in another embodiment is a metal material that is currently commonly used This is a band reinforcing material, which is galvanized to prevent corrosion on the surface of a band-shaped iron plate having a certain width and length. This is a reliable material for tensile strength but is expensive and is a metallic material, so the unit weight is large, so handling and transporting during reinforcement installation work are easy. It is inconvenient, the connection method and the connection form with the reinforced earth retaining wall wall is not diverse, and had to bind the connection part by pin or bolt one by one, there was a disadvantage that workability is reduced.

또 다른 종래 실시예로는, 로울형 띠 섬유 보강재를 들 수 있는데, 이는 여러 가닥의 폴리에스테르 섬유가 폴리에틸렌으로 피복성형된 것으로, 100∼150m정도의 긴 띠가 두루마리상태로 감겨져 있어 보강재의 설치작업시 보강재를 손으로 당겨서 풀어야 하고 보강재를 보강토체 전방부인 보강토 옹벽 벽체의 연결부와 연속하여 핀으로 지그재그 형태로 결속시키기 위해 보강토체 후방엔 상기 전방부인 옹벽벽체와 평행하게 직경 16㎜, 깊이 45cm이상의 다수의 임시고정핀을 박아 연속하여 임시고정바를 설치해야 하므로 인력 및 자재의 손실이 있었으며, 보강재 연결 후 발생되는 각 접힌 부분들의 느즈러짐을 펴주기 위해 많은 작업인원들이 보강재를 손으로 감싸 잡고 당겨야 했으며, 이때 보강재를 손으로 감싸잡고 당길 수 있는 크기 이상의 보강재의 두께 및 폭증대는 불가능하였다. 이에 따라, 고점착 폴리에틸렌에 유착피복되어 보강재의 인장강도와 마찰력을 결정하는 내부의 섬유질 폴리에스테르의 두께와 양의 증대는 제한을 받을 수 밖에 없으며, 또한 보강재 내부의 섬유질 보호 및 각종 화학적 침해에 의한 부식을 방지하는 피복재인 폴리에틸렌의 두께 및 폭의 증대도 제한을 받게 되었다. 또한, 이와 같은 롤형 띠 섬유 보강재는 상기 보강토체 유효거리부분에서의 보강재 상·하 겹침과 보강토체 전방부인 옹벽벽체에 대하여 설치되는 방향이 일률적이지 못하며, 보강재 이음시 겹이음을 2m이상 확보해주어야 하므로써 옹벽 벽체에 대하여 개별적으로 설치되었을 경우와 비교할 때, 보강재의 길이에 비해 요구되는 인장력과 마찰력의 효과가 감소되므로 불필요한 보강재의 낭비가 뒤따르는 문제점이 있었으며, 보강재 설치시 보강재를 지그재그로 깔아 당기는 작업을 한쪽 방향이나 한 곳에서 밖에 할 수 없는 문제점과 아울러 옹벽 벽체마다 연결된 보강재의 느즈러짐을 펴주기 위한 당김작업시 인력에 의존하여 당겨야 함으로써 발생되는 당김후의 느즈러짐 잔류분과 보강재마다 일정한 장력을 가해 똑같이 당기지 못하므로써 옹벽 벽체의 변형 및 부분적인 뒤틀림이 극심하였다.Another conventional embodiment is a roll-shaped band fiber reinforcement, which is a polyester-like coating of several strands, the long strip of about 100 to 150m is wound in a rolled state to install the reinforcement work To reinforce the stiffeners by hand, and reinforce the stiffeners in a zigzag shape with pins in series with the connecting part of the reinforcement earth retaining wall wall, which is the front part of the reinforcement body, the back of the reinforcement body is 16mm in diameter and 45cm in depth and parallel to the retaining wall wall. There was a loss of manpower and materials because it was necessary to install temporary fixing pins in succession, and many workers had to wrap and pull the stiffeners by hand to smooth the looseness of each folded part after connecting the stiffeners. Two pieces of reinforcement that are larger than the size that can be wrapped and pulled by hand And the explosion was impossible to stand. Accordingly, the increase in the thickness and amount of the internal fibrous polyester that is adhered to the high adhesion polyethylene and determines the tensile strength and the friction of the reinforcement is limited, and also due to the fibrous protection and various chemical infringements in the reinforcement Increasing the thickness and width of polyethylene, a coating that prevents corrosion, is also limited. In addition, such a roll-shaped strip fiber reinforcement is not uniform in the direction of the reinforcement in the effective distance portion of the reinforcement to the reinforcement overlapping and the retaining wall wall, which is the front portion of the reinforcement body, and must be secured more than 2 m when the reinforcement joints Compared to the case of installing the retaining wall wall separately, the effect of the required tensile and frictional forces is reduced compared to the length of the reinforcement, which leads to the waste of unnecessary reinforcement. In addition to the problem of only one direction or one place, the pulling tension caused by the pulling force depends on the manpower during the pulling operation to unwind the reinforcement connected to each retaining wall. Retaining wall The deformation and warping were extremely partial.

한편, 이와같은 종래의 보강토 옹벽설치 작업시 발생되는 단점을 해결하기 위해 본 출원인은 제2도 및 제3도에 도시된 바와 같이, 특허출원 제98-38249호의 '조립식 보강토 옹벽지지장치와 이의 시공방법 및 그 기구' 를 출원함으로써 상기한 종래의 문제점을 다수 해결할 수 있는 작업방법과 그 기구 및 옹벽지지장치를 제공한 바 있었다. 하지만, 본 출원인이 출원한 발명에 개시된 보강재 당김기구는 한 번에 한 개씩의 보강재(10) 당김작업이 이루어지도록 구성되고, 보강재(10)를 무는 물럼턱(132)이 당김기구의 이동부재(130) 전방에 고정 부착되어 실제 사용될 때 지면에 대하여 물림턱(132)이 뜨게 되어 보강재(10) 고정작업시 불편하였으며, 옹벽벽체(20)에 매립된 연결구(30)의 재료 및 가공단가가 다소 상승되는 점과, 또한 옹벽벽체(20)의 연결구(30)에 보강재(10)를 미리 결속·거치하여 성토 및 다짐작업을 실시한 후 당김작업을 하기까지에 있어서 보강재(10)의 접혀지는 부위들의 느즈러짐과 아울러 연결구(30)의 걸림부로부터의 흘러내리는 현상 및 길이방향으로 절반이 접혀서 연결되어지는 양단이 길이방향쪽의 유동성에 의해 양단의 길이변동이 발생되는 단점이 있었으며, 이를 개선하고 보강재(10)의 결속방법과 보강재(10)와 보강토체(50)와의 마찰력을 증대시켜 작업의 능률을 더욱 향상시킬 필요가 있었다.On the other hand, in order to solve the disadvantages that occur during the installation of the conventional reinforcement earth retaining wall, the present applicant, as shown in FIGS. 2 and 3, the 'prefabricated retaining earth retaining wall support device and its construction of Patent Application No. 98-38249 The present invention has provided a working method and a mechanism and a retaining wall supporting apparatus which can solve many of the above-mentioned conventional problems by filing a method and a mechanism thereof. However, the reinforcement pull mechanism disclosed in the present invention filed by the present applicant is configured to pull the reinforcing material 10 one at a time, and the moving member of the pulling mechanism is a bite jaw 132, biting the reinforcing material 10 ( 130) When the fixed attachment to the front is actually used, the sill 132 is floating with respect to the ground, which is inconvenient when fixing the reinforcement 10, and the material and the processing cost of the connector 30 embedded in the retaining wall 20 are somewhat Of the folded portions of the reinforcing material 10 until the pulling point is performed after binding and placing the reinforcing material 10 to the connector 30 of the retaining wall 20 in advance and carrying out the filling and compacting work. In addition to the slack, there is a drawback of the flow from the locking portion of the connector 30 and both ends of the ends being folded in the longitudinal direction and connected to each other by the fluidity in the longitudinal direction. The binding method of the reinforcing material 10 and the friction between the reinforcing material 10 and the reinforcing soil 50 was required to further improve the efficiency of the work.

본 발명은 종래의 제반 문제점을 해결함과 동시에 기 출원된 본 출원인의 발명을 개선하기 위하여 안출된 것으로, 본 발명의 목적은 보강재와 연결구와 결속을 신속 ·간단하게 하고, 옹벽벽체에 일부 매몰되어 내면에 돌출된 연결구에 보강재를 미리 결속시켜 옹벽벽체의 상부에 거치하여 성토 및 다짐작업을 실시한 후 보강재를 펼쳐 당김작업을 하기까지에 있어서 옹벽벽체의 연결구에 결속시나 옹벽벽체 상부에 거치시 보강재의 접혀지는 부위들의 느즈러짐과 아울러 연결구 걸림부로부터의 흘러내리는 현상 및 길이방향으로 절반이 접혀져 이루어진 양단이 길이방향쪽의 유동성에 의해 발생되는 양단의 길이변동과 같은 단점을 배제하여 작업성을 향상시키며, 보강재와 보강토체와의 결속력을 더욱 증대시켜 보강재 설치후 성토작업시 보강재의 유동을 방지하여 옹벽벽체의 뒤틀림이 발생되지 않도록 하는데 있다.The present invention has been made to solve the conventional problems and at the same time to improve the present applicant's present invention, the object of the present invention is to quickly and easily bind to the reinforcing material and the connector, and partially buried in the retaining wall Reinforcement is pre-bonded to the connector projecting on the inner surface, and it is mounted on the top of the retaining wall to carry out the filling and compacting work, and then until the reinforcing material is unfolded and pulled up to the connector of the retaining wall or when the upper part of the retaining wall is attached to the retaining wall. It improves workability by eliminating the disadvantages such as the loosening of the folded parts and the phenomenon of flowing down from the connector catching part and both ends being folded half in the longitudinal direction, such as length fluctuation of both ends caused by the fluidity in the longitudinal direction. To increase the cohesion between the reinforcement and the reinforcement body. Is to prevent the distortion of the retaining wall, the wall is not generated to prevent the copper.

본 발명의 다른 목적은 보강재의 당김작업을 한 번에 두 가닥씩 동시에 할수 있도록 할 뿐만 아니라 보강재의 폭과 두께에 관계없이 당김작업이 가능하고, 지면의 고르기 및 강도에 관계없이 당김작업이 가능한 당김기구를 제공하는데 있다.Another object of the present invention is to pull the reinforcing material at the same time two strands at the same time as well as to pull the work regardless of the width and thickness of the reinforcement, the pull can be pulled regardless of the level and strength of the ground To provide a mechanism.

이와같은 목적을 달성하기 위한 본 발명은 옹벽벽체의 내측면으로 돌출된 다수 연결구의 걸림부에 일정길이로 절단되고 길이방향의 중심부에 고정공이 다수 형성된 띠형 보강재를 각각 개별적으로 결속시키고, 후단에서 당김기구를 사용하여 보강재가 팽팽히 유지되도록 당겨준 상태에서 고정못으로 보강재를 고정시키고 그 위에 보강토체를 깔아 다짐작업을 실시하는 시공방법에 있어서, 상기 보강재는 연결구의 걸림부에서 동일한 길이로 중간부에서 접혀져 걸림부 바로 선단에서 볼트와 너트로 구성된 체결수단에 의해 두겹의 보강재가 결속되는 단계; 상기 결속된 보강재의 후단에서 당김기구에 의해 양방향으로 일정한 각도가 유지되면서 동시에 동일하게 팽팽히 당겨지는 인장단계; 상기 인장된 보강재의 후단부터 상기 보강재가 일정한 간격으로 벌어지기 시작한 유효거리부까지 보강재 중심부의 고정공에 일정한 간격으로 와셔가 일체로 형성된 고정못을 다수 박아 보강토체에 고정시키는 단계; 로 이루어지는 옹벽벽체의 보강재 시공방법을 제공한다.In order to achieve the above object, the present invention is to cut each length of the engaging portion of the connector that protrudes into the inner surface of the retaining wall wall, and to bind each of the band-shaped reinforcement formed with a plurality of fixing holes in the central portion in the longitudinal direction, respectively, and pulled at the rear end. In the construction method of fixing the reinforcement with a fixing nail in the state in which the reinforcement is pulled to maintain the tension using a mechanism, the reinforcing material is laid on the reinforcement soil, and the reinforcing material is the same length at the middle of the engaging portion of the connector at the same length The step of being folded to bind the two layers of reinforcement by a fastening means consisting of a bolt and a nut at the front end of the fastening portion; A tensioning step in which a constant angle is maintained in both directions by a pulling mechanism at the rear end of the bound reinforcing material and pulled at the same time as the tensioning device; Fixing a plurality of fixing nails integrally formed with washers at regular intervals from a rear end of the tensioned reinforcement to an effective distance at which the reinforcement starts to be opened at regular intervals at fixed intervals in the center of the reinforcement; Provided is a method for constructing a reinforcing material for a retaining wall wall.

또한, 상기 보강재가 연결구의 걸림부에서 일차로 감겨져 한 쪽 끝단이 볼트와 너트로 이루어진 체결수단에 의해 결속되는 단계; 상기 결속된 보강재를 연결구의 상단에 위치한 연결핀을 외감하도록 하여 보강재의 다른쪽 끝단을 보강토체 상부에 위치시키는 단계; 상기 보강토체 상부에 위치한 보강재의 후단에서 당김기구에 의해 팽팽히 유지되도록 잡아당긴 후에 와셔가 일체로 형성된 고정못을 보강재의 고정공에 일정간격으로 다수 박아 고정시키는 단계; 로 이루어지는 것을 특징으로 한다.In addition, the reinforcing material is first wound on the engaging portion of the connector is coupled to one end by a fastening means consisting of bolts and nuts; Positioning the other end of the reinforcing material on the reinforcing soil by enclosing the connection pin located at the upper end of the connector with the bound reinforcing material; A plurality of fixing nails fixed at a predetermined interval to the fixing hole of the reinforcing material after pulling the pulled to be maintained by the pulling mechanism at the rear end of the reinforcing material located above the reinforcement body at a predetermined interval; Characterized in that consists of.

또한, 본 발명은 스파이크가 부착된 발판에 설치된 가이드 부재에 전·후로 슬라이드 가능하고 물림턱과 랙기어부가 형성된 이동부재와, 상기 랙기어부상에 결합되도록 하단부에 피니언기어가 결합된 조작핸들과, 이 조작핸들을 전 후로 젖힐때 상기 피니언기어를 타고넘어 다음 기어홈에 걸리거나 피니언기어에 결합되어 피니언기어와 동시에 회전 또는 이탈되어 상기 이동부재를 이동시키는 제 1래칫과 제 2래칫으로 이루어지는 조립식 보강토 옹벽의 보강재 당김기구에 있어서, 상기 이동부재의 선단과 물림턱 사이에는 상기 물림턱이 상·하로 회전가능하도록 회동부재가 구비된 보강재 당김기구를 제공한다.In addition, the present invention is a movable member which is slidable back and forth to the guide member installed on the foot plate attached to the spike, and the bite jaw and the rack gear portion, and the operation handle coupled to the pinion gear at the lower end to be coupled to the rack gear portion, Prefabricated reinforcement earth consisting of a first ratchet and a second ratchet moving the movable member by moving the pinion gear to the next gear groove or being coupled to the pinion gear and being rotated or separated simultaneously with the pinion gear when the operation handle is flipped back and forth. In the reinforcing material pulling mechanism of the retaining wall, there is provided a reinforcing material pulling mechanism provided with a rotating member so that the biting jaw is rotatable up and down between the tip of the moving member and the biting jaw.

제1도는 종래 발명에 따른 보강재 당김기구의 결합사시도.1 is a perspective view of the reinforcement pull mechanism according to the prior invention.

제2도는 종래 발명에 따른 연결구의 사시도.2 is a perspective view of a connector according to the prior invention.

제3도는 종래 발명에 따른 보강재 당김기구의 사용상태 사시도.3 is a perspective view of the state of use of the reinforcing material pulling mechanism according to the prior invention.

제4(a)도, 제4(b)도는 본 발명에 따른 보강재 시공방법에 관한 제 1실시예의 시공상태 평면도 및 일부 확대사시도.4 (a), 4 (b) is a plan view and a partially enlarged perspective view of the construction state of the first embodiment of the reinforcing material construction method according to the present invention.

제5(a)도, 제5(b)도, 제5(c)도는 본 발명에 따른 보강재 시공방법에 관한 제 2실시예의 시공상태 평면도, 일부확대 사시도 및 일부 측단면도.5 (a), 5 (b) and 5 (c) are a plan view, a partially enlarged perspective view and a partial side cross-sectional view of a construction state of a second embodiment of a reinforcement construction method according to the present invention.

제6도는 본 발명의 제 1실시예에 따른 옹벽 시공상태사시도.Figure 6 is a retaining wall construction state perspective view according to a first embodiment of the present invention.

제7도는 본 발명의 제 1실시예에 따른 옹벽설치후 상태를 나타내는 사시도.7 is a perspective view showing a state after installing the retaining wall according to the first embodiment of the present invention.

제8(a)도는 본 발명에 따른 보강재 시공방법에 판한 제 3실시예.8 (a) is a third embodiment of the reinforcement construction method according to the present invention.

제8(b)도는 제8(a)도의 일부확대 사시도.8 (b) is a partially enlarged perspective view of FIG. 8 (a).

제9(a)도는 본 발명에 따른 보강재 시공방법에 관한 제 4실시예.9 (a) is a fourth embodiment of the reinforcing material construction method according to the present invention.

제9(b)도는 제9(a)도의 일부확대 사시도.9 (b) is a partially enlarged perspective view of FIG. 9 (a).

제10도는 본 발명에 따른 보강재 당김기구의 결합사시도이다.10 is a perspective view of the reinforcement pull mechanism according to the present invention.

* 도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings

ℓ: 무효거리 L : 유효거리ℓ: Invalid distance L: Effective distance

r : 보강재 간격 10 : 보강재r: Stiffener spacing 10: Stiffener

11 : 체결수단 12 : 볼트11 fastening means 12 bolt

13 : 너트 15 : 고정공13: nut 15: fixing hole

17 : 고정못 19 : 와셔17: fixing nail 19: washer

20 : 옹벽벽체 30 : 연결구20: retaining wall 30: connector

35 : 걸림부 40 : 연결핀35: engaging portion 40: connecting pin

50 : 보강토체 100 : 당김기구50: reinforced earth 100: pulling mechanism

105 : 발판 110 : 스파이크105: scaffold 110: spike

112 : 미끄럼 방지홈 117 : 스파이크 고정너트112: non-slip groove 117: spike fixing nut

118 : 보조스파이크 119 : 볼트부118: auxiliary spike 119: bolt portion

120 : 가이드부재 130 : 이동부재120: guide member 130: moving member

132 : 물림턱 134 : 조작핸들132: bite jaw 134: operation handle

140 : 회동부재 142 : 새클140: rotating member 142: sackle

146 : 연결로드146: connection rod

이하, 본 발명의 바람직한 실시예들을 첨부된 도면에 의하여 상세히 설명하기로 한다. 제4도 내지 제10도는 본 발명에 따른 보강재의 시공방법에 대한 제 1실시예 내지 제 4실시예와 보강재의 당김기구를 도시하고 있다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. 4 to 10 show the first to fourth embodiments and the pulling mechanism of the reinforcing material for the construction method of the reinforcing material according to the present invention.

본 발명에 적용된 옹벽벽체 지지장치 및 시공방법의 일반적인 내용은 본 출원인이 기 출원한 국내특허출원 제98-38249호의 "조립식 보강토 옹벽 지지장치와 이의 시공방법 및 그 기구" 에 상세히 개시되어 있기 때문에 본 명세서에서는 본 발명의 특징적인 내용만을 설명하기로 한다.The retaining wall support device and construction method applied to the present invention are generally described in detail in "Prefabricated Reinforced Earth Retaining Wall Support Device and Its Construction Method and Apparatus" of Korean Patent Application No. 98-38249 filed by the present applicant. In the specification, only characteristic features of the present invention will be described.

제4(a)도 및 제4(b)도에 도시된 본 발명의 제 1실시예에 따른 옹벽벽체(20)의 보강재 시공방법은 옹벽벽체(20)의 내면에 돌출된 연결구(30)의 걸림부(35)에 보강재(10)가 동일한 길이로 중간부에서 접혀져 2겹으로 하여 보강토체(50) 상부에 위치시키고 보강재(10) 후단에 설치한 당김기구(100)에 의해 보강재(10)가 양방향으로 팽팽히 당겨질 수 있도록 한다. 즉 양단의 보강재(10)가 연결구(30)의 걸림부(35) 바로 전단의 상호 교차부위에서 볼트(12)와 너트(13)로 이루어진 체결수단(11)에 의해 결속되어지되, 결속부의 상·하 보강재(10) 사이에는 걸림부(35)의 직경만큼 간격이 유지되도록하여 당김기구(100)에 의해 당겨지는 후단부위가 일정한 각도로 상태에서 보강재(10)가 느즈러짐 없는 상태가 될 때까지 일정한 장력으로 당긴 후에, 보강재(10) 상방에 형성된 고정공(15)에 고정못(17)을 일정간격으로 다수개 박아서 보강재(10)를 임시 고정시키며, 이때 당김기구(100)에 인접한 후단부를 일차로 고정하고 전단부쪽으로의 고정은 당기 당김기구(100)를 해체한 이후에 이차적으로 고정을 하여도 무관하다.The method of constructing the reinforcement of the retaining wall 20 according to the first embodiment of the present invention shown in FIGS. 4 (a) and 4 (b) shows the connection of the connector 30 protruding to the inner surface of the retaining wall 20. The reinforcing material 10 is folded in the middle part by the same length to the catching part 35 and placed in the upper part of the reinforcing soil 50 with two layers, and the reinforcing material 10 is provided by the pulling mechanism 100 installed at the rear end of the reinforcing material 10. To be pulled tight in both directions. That is, the reinforcing material 10 of both ends is bound by the fastening means 11 consisting of the bolt 12 and the nut 13 at the cross section of the front end of the fastening portion 35 of the connector 30, When the reinforcing material 10 is not loosened in a state where the rear end portion drawn by the pulling mechanism 100 is maintained at a constant angle so that the gap is maintained between the lower reinforcing materials 10 by the diameter of the locking part 35. After pulling to a constant tension until the reinforcement (10) is fixed to the fixing holes (15) formed in the fixing holes (17) at regular intervals to fix the reinforcement (10) temporarily, at this time adjacent to the pulling mechanism (100) The rear end may be fixed primarily and the front end may be fixed secondly after dismantling the pulling mechanism 100.

상기의 고정못(17)으로 보강재(10) 상부를 고정할 때 상기 보강재(10)는 연결구(30)의 걸림부(35)선단에서 체결수단(11)에 의해 고정되므로 보강재(10)의 전방부가 일정거리만큼 겹쳐지게 되는데, 이 겹쳐지는 부위의 보강재(10)상에는 고정못(17)을 박아 고정시킬 필요가 없으며, 상기 보강재(10)가 서로 이격되어 일정한 각이 형성되는 부위까지만 고정못(17)으로 보강재(10)를 고정하며, 상기 고정못(17)은 보강재(10)상에 끼워진 후 보강재(10)의 펄럭임을 방지하기 위해 머리부의 직경이 다소 큰 와셔(19)가 일체로 형성된 것을 사용하는 것이 유리하다.When the upper portion of the reinforcing material 10 is fixed by the fixing nail 17, the reinforcing material 10 is fixed by the fastening means 11 at the tip of the engaging portion 35 of the connector 30, so that the front of the reinforcing material 10 is fixed. Addition overlaps by a certain distance, there is no need to fix the fixing nail 17 on the reinforcement (10) of the overlapping portion, the reinforcement (10) is spaced apart from each other until only a fixed angle is formed (part 17) to fix the reinforcement 10, the fixing nail 17 is formed on the reinforcement 10 after the washer (19) having a somewhat larger diameter of the head unit is integrally formed to prevent the flap of the reinforcement (10) It is advantageous to use one.

상기와 같이 고정못(17)으로 보강재(10)를 고정시킨 후, 당김기구(100)의 물림턱(132)을 해제시키고 다른 보강재(10)측으로 당김기구(100)를 옮긴 상태에서 상기와 같은 방법으로 보강재(10)를 당겨 임시 고정시킨 후에 다음 공정인 보강토체(50)를 깔고 다짐작업을 실시해주면 되기 때문에 보강재(10)의 연결작업을 더욱 신속히 할 수 있을 뿐만 아니라, 보강재(10) 상부에 성토작업시 보강재(10)가 보강토체(50) 상면에 떠서 펄럭이는 것을 방지하고 느즈러짐이 없도록 하여 보강토체(50)와의 마찰력을 더욱 증대시킬 수 있으며, 본 발명에 적용된 연결구(30)는 상기 보강재(10)를 옹벽벽체(20)에 결속시키기 위해 원형단면으로 이루어진 강봉을 폐쇄고리 형태가 되도록 하여 옹벽벽체(20)내부에 매몰된 지지용 철근에 고정한 것으로, 연결구(30)의 단순화를 통해 자재비 및 제작단가를 절감할 수 있다.After fixing the reinforcing material 10 with the fixing nail 17 as described above, in the state of releasing the bite jaw 132 of the pulling mechanism 100 and the pulling mechanism 100 to the other reinforcing material 10 side as described above By pulling the reinforcement 10 in a temporary manner and then temporarily reinforcing the reinforcement soil 50, which is the next process, the compaction work can be performed more quickly, and the upper part of the reinforcement 10 can be connected. When the reinforcing work in the reinforcement work 10 is prevented from floating on the upper surface of the reinforcement soil 50, there is no loosening can further increase the frictional force with the reinforcement soil 50, the connector 30 applied to the present invention In order to bind the reinforcing material 10 to the retaining wall wall 20, the steel bar having a circular cross section is fixed to the supporting steel buried in the retaining wall wall 20 so as to have a closed ring shape, thereby simplifying the connector 30. Material costs and Production cost can be reduced.

한편, 제5(a)도, 제5(b)도, 제5(c)도는 본 발명에 따른 제 2실시예에 의한 보강재 시공상태를 도시하고 있는 것으로, 상기 보강재(10)가 연결구(30)의 걸림부(35)에서 일단 감겨져 한 쪽 끝단이 체결수단(11)에 의해 결속되고, 결속된 보강재(10)를 상기 연결구(30)상단에 위치시킨 연결핀(40)에 외감되도록 하여 보강재(10)의 다른쪽 끝단을 보강토체(50) 상부에 위치시키고, 보강재(10)의 후단에서 당김기구(100)에 의해 팽팽한 상태가 되도록 잡아당긴 후에 와셔(19)가 일체로 형성된 고정못(17)을 보강재(10)의 고정공(15)에 일정간격으로 다수 박아 고정시킨 후에 상기한 제 1실시예와 동일한 방법으로 보강토체(50)를 깔고 다짐작업을 하면 된다. 이와 같이, 연결구(30) 상단에 연결핀(40)을 위치시키고 보강재(10)의 당김작업을 실시하면, 제5(c)도에 도시된 바와 같이 상기 연결핀(40)은 보강재(10)의 인장력에 의해 연결구(30)의 걸림부(35)측에 긴밀히 밀착되어 보강재(10)의 연결구(30)에 대한 결속력을 증대시키며, 보강재(10)의 손실을 최대한 줄일 수 있다.5 (a), 5 (b) and 5 (c) show the construction of the reinforcing material according to the second embodiment according to the present invention, and the reinforcing material 10 is connected to the connector 30. One end is wound at the engaging portion 35 of the) and the one end is bound by the fastening means 11, and the bound reinforcement 10 is wound on the connecting pin 40 positioned at the upper end of the connector 30. The other end of the (10) is placed on the upper reinforcement body 50, and pulled to be in a taut state by the pulling mechanism 100 at the rear end of the reinforcing material 10, the fixing nail formed integrally with the washer ( 17) After fixing a plurality of fixing at a predetermined interval in the fixing hole 15 of the reinforcing material 10, the reinforcing soil 50 may be laid and compacted in the same manner as in the first embodiment. As such, when the connecting pin 40 is placed on the upper end of the connector 30 and a pulling operation of the reinforcing material 10 is performed, as shown in FIG. 5 (c), the connecting pin 40 is the reinforcing material 10. By tight force of the connector 30 is in close contact with the engaging portion 35 side to increase the binding force to the connector 30 of the reinforcing material 10, it is possible to reduce the loss of the reinforcing material 10 as possible.

한편, 제6도는 본 발명의 제 1실시예에 따른 보강재의 설치방법에 의하여 옹벽벽체(20)의 지지작업 상태를 도시하고 있는 것으로, 옹벽벽체(20)에 설치된 연결구(30)에는 옹벽벽체(20)의 설치전이나 설치 후 보강토체(50)를 성토 및 다짐작업하기전에 미리 연결구(30)에 보강재(10)를 절반으로 접은 상태에서 연결구(30)의 걸림부(35)바로 전단에 체결수단(11)을 결속시킨 후에 옹벽벽체(20)상단에 보강재(10)를 올려놓고 보강토체(50)의 성토 및 다짐작업을 하고, 성토 및 다짐작업이 끝난 부위부터 보강재(10)를 보강토체(50)상부에 위치시키고 당김기구(100)의 물림턱(132)에 보강재(10)를 물려 당김작업을 한 후에 와셔(19)가 구비된 고정못(17)으로 보강재(10)고정작업을 하면 된다.On the other hand, Figure 6 shows the support working state of the retaining wall wall 20 by the method of installing the reinforcing material according to the first embodiment of the present invention, the retaining wall 30 is provided in the connector 30 provided in the retaining wall wall (20) Before the installation or compaction work of the reinforcement soil 50 before or after the installation of 20) in the state in which the reinforcing material 10 is folded in half in advance in the connector 30, it is fastened to the front end of the engaging portion 35 of the connector 30 immediately. After binding the means 11, the reinforcing material 10 is placed on the retaining wall 20, and the filling and compacting work of the reinforcing soil 50 is carried out, and the reinforcing material 10 is reinforced from the end of the filling and compacting work. (50) After fixing the reinforcing material 10 to the bite jaw 132 of the pulling mechanism 100, the upper part is fixed to the reinforcing material 10 with a fixing nail (17) provided with a washer (19). Just do it.

또한, 제7도에는 상기한 실시예에 따른 옹벽벽체(20)의 보강재 설치단면을 입체적으로 도시하고 있는 것으로, 두겹에 의해 설치된 보강재(10)의 후단은 옹벽벽체(20)의 저단이나 상단 모두 동일한 보강재간격(r)이 유지되며, 하단부분에서부터 상단부분까지 일정한 기울기로 옹벽벽체(20)를 지지하는 보강재(10)의 선단부분은 보강재(10)의 전 설치길이에 대해 상·하단부가 동일한 비율의 무효거리(ℓ)가 유지되고, 보강재(10)의 후단부는 두겹의 보강재(10)가 펼쳐져서 보강토체(50)와의 마찰력을 발생시키는 유효거리(L) 또한 보강재(10)의 전 길이에 상·하단이 동일한 비율로 설치된다. 상기의 무효거리(ℓ)는 보강재(10)가 상호 겹쳐지고 보강토체(50)와의 마찰력을 발생시키지 않고 단지 옹벽벽체(20)를 연결하는 역할을 하는 것이며, 상기 유효거리(L)는 두겹의 보강재(10)에 의해 증대된 마찰력을 발생시켜 옹벽벽체(20)를 지지하는 것이다.In addition, Fig. 7 shows the reinforcement mounting cross section of the retaining wall 20 according to the above embodiment in three dimensions, and the rear end of the reinforcing material 10 provided by the two layers is both the lower end and the upper end of the retaining wall 20. The same reinforcing material spacing (r) is maintained, the front end portion of the reinforcing material 10 for supporting the retaining wall wall 20 with a constant slope from the lower end portion to the upper end portion is the same as the upper and lower ends with respect to the entire installation length of the reinforcement (10) The effective distance L of the ratio is maintained, and the rear end of the reinforcement 10 has two layers of reinforcement 10 unfolded to generate frictional force with the reinforcement soil 50, and also the full length of the reinforcement 10. The upper and lower ends are installed at the same ratio. The invalid distance ℓ means that the reinforcing material 10 overlaps each other and serves to connect the retaining wall wall 20 without generating friction force with the reinforcing soil 50, and the effective distance L is double. The frictional force increased by the reinforcing material 10 is generated to support the retaining wall wall 20.

한편, 제8(a)도, 제8(b)도 및 제9(a)도, 제9(b)도는 본 발명에 따른 제 3 및 제4실시예를 도시하고 있는 것으로, 상기 옹벽벽체(20) 내부에 형성된 연결구(30)에 연결핀(40)을 개재시켜 보강재(10)를 결속하도록 제8(a)도, 제8(b)도는 연결구(30)의 걸림부(35) 선단에 별도의 체결수단(11)을 구비하지 않고 보강토체(50) 상부에 위치된 보강재(10)를 당김기구(100)에 의해 인장시킬 때 보강재(10)의 인장력에 의해 연결핀(40)이 연결구(30)의 걸림부(35)에 더욱 견고히 밀착되게 하는 것으로, 상기 제5(a)도, 제5(b)도와 동일한 원리를 갖는다. 그리고, 제9(a)도, 제9(b)도에 도시된 보강재 설치방법은 상기 보강재(10)의 중심부를 접어 체결수단(11)으로 접힌선단을 결속하여 상기 체결되어 접힌 두겹의 선단부를 옹벽벽체(20)와 연결구(30)사이에 형성된 구멍위로 삽입시키어 연결핀(40)을 삽입된 접힌 선단부 두겹사이로 끼워 연결구(30) 상부에 걸쳐 결속시키고 상기 결속된 두겹의 보강재(10) 양단의 길이를 동일하게 하여 보강토체(50) 상부에 위치시켜 당김기구(100)에 의해 당겨지는 부위에서는 본 발명의 일실시예와 동일하게 보강재(10)의 양단이 일정한 각도로 벌어지도록 한 상태에서 당겨지도록 한 후에 양단의 보강재(10) 상부에 고정못(17)을 사용하여 일정간격으로 다수 박아 고정시킨 후에 보강토체(50)의 성토작업 및 다짐작업을 하면 된다.8 (a), 8 (b), 9 (a) and 9 (b) show the third and fourth embodiments according to the present invention. 20) 8 (a), 8 (b) is a front end of the engaging portion 35 of the connector 30 to bind the reinforcing material 10 through the connecting pin 40 formed in the connector 30 formed therein. When the reinforcing material 10 positioned above the reinforcement soil 50 is tensioned by the pulling mechanism 100 without a separate fastening means 11, the connecting pin 40 is connected by the tension of the reinforcing material 10. The fifth (a) also has the same principle as that of the fifth (b). In the method of installing the reinforcement shown in FIGS. 9A and 9B, the front end of the reinforcement 10 is folded and the front end of the reinforcement 10 is joined to the fastening means 11. Inserted over the hole formed between the retaining wall wall 20 and the connector 30, the connecting pin 40 is sandwiched between the inserted two ends of the folded end portion to bind over the upper portion of the connector 30 and the two ends of the reinforcement of the two layers of the reinforcement (10) In the same position as the length of the reinforcement soil 50 is pulled by the pull mechanism 100 in the area pulled in a state that both ends of the reinforcement 10 in the same angle as in one embodiment of the present invention After the construction of the reinforcement 10 at the upper end of the reinforcement (10) by using a fixed nail 17 to fix a number of fixed at a predetermined interval, and then the filling and compacting work of the reinforcement body (50).

한편, 제10도에는 본 발명에 따른 보강재(10)의 당김기구(100)를 도시한 결합 사시도로, 주요부로는 발판(105), 가이드 부재(120), 이동부재(130), 회동부재(140), 조작핸들(134)로 구성된 것으로, 세부 구성내용은 상기한 본인의 기 특허출원된 내용과 동일하므로 생략하고, 본 발명의 특징부에 대해서 설명을 하면, 발판(105)의 하면 네 모서리부 하단부에 설치된 스파이크(110)와 더불어 가이드부재(120) 좌·우측 양단에 상기 발판(105)에 관통형성되고 내부에 나사가 형성된 스파이크 고정너트(117)를 돌출형성시키고, 상기 발판(105) 하단으로 상단부에 볼트부(119)가 형성되고 하단부에 스파이크(110)가 형성된 보조스파이크(118)를 나사결합되거나 분해될 수 있도록 한 것으로, 상기 당김기구(100)의 발판(105) 하부에 추가 스파이크(110)가 구비되도록 하여 당김기구(100)가 보강토체(50)에 더욱 견고히 고정·지지되도록 한다.On the other hand, Figure 10 is a perspective view showing a pulling mechanism 100 of the reinforcing member 10 according to the present invention, the main portion is a footrest 105, a guide member 120, a moving member 130, a rotating member ( 140, the operation handle 134, the detailed configuration is omitted because it is the same as the contents of the patent application of the above, and the description of the features of the present invention, four corners of the lower surface of the scaffold 105 Spike fixing nut 117 is formed in the bottom of the guide member 120 and the left and right side of the guide member 120 through the foot plate 105 and a screw formed therein, and the foot plate 105 A bolt 119 is formed at the upper end of the lower part, and the auxiliary spike 118 having the spike 110 formed at the lower end thereof can be screwed or disassembled, and is further added to the bottom of the footrest 105 of the pulling mechanism 100. The pull mechanism 100 is provided so that the spike 110 is provided. It is to be more firmly fixed and supported on the soil body (50).

또한, 이동부재(130)의 선단에는 보강재(10)를 물리는 물림턱(132)을 폭과 너비를 증대하여 보강재(10)의 물림을 더욱 확실히 할 수 있으며, 물림턱(132)이 이동부재(130)와 별도로 핀결합되어 상·하 회전이 가능하도록 구성됨으로써, 보강재(10) 당김작업시 보강토체(50)의 바닥면이 고르지 않거나, 장애물이 있는 경우에도 보강재(10)가 느즈러짐이 없이 당겨질 수 있도록 하며, 이와같이 보강재(10)의 당김작업시 상기 물림턱(132)은 자체의 무게로 보강토체(50) 상면과 맞닿은채로 당김작업이 되기 때문에 보강재(10)의 느즈러짐을 방지한다.In addition, the front end of the movable member 130 to increase the width and width of the bite jaw 132 biting the reinforcing material 10 can be more sure the bite of the reinforcing material 10, the bite jaw 132 is a moving member ( 130 is pin-coupled separately and configured to be rotated up and down, so that the bottom surface of the reinforcement soil 50 is uneven or unobstructed when the reinforcement 10 is pulled, without loosening the reinforcement 10. When the pulling operation of the reinforcing material 10 is pulled in this way, the bite jaw 132 prevents the reinforcing material 10 from being loosened because the pulling work is brought into contact with the upper surface of the reinforcing soil 50 at its own weight.

이상 설명한 바와 같이 본 발명은 보강재를 옹벽벽체에 결속시키는 작업을 빠르고 간편하게 하고, 보강재를 동일한 길이로 중간부를 접어 상기 연결구의 걸림부에 감아 걸림부 전단의 상호 교차부위에서 체결수단에 의해 결속됨으로써 옹벽벽체의 연결구에 결속시나 옹벽벽체 상부에 거치시 접혀지는 부위들의 느즈러짐 및 연결구 걸림부로부터의 흘러내리는 현상을 방지하여 옹벽벽체 후단의 부실하였던 성토 및 다짐과 아울러 길이방향으로 절반이 접혀져 이루어진 양단이 길이방향쪽의 유동에 의해 길이변동과 같은 단점을 배제하여 보다 견고한 작업이 되도록 한다.As described above, the present invention makes the operation of fastening the reinforcing material to the retaining wall wall quickly and easily, and folding the reinforcing material to the same length to wind the engaging part of the connector, thereby binding the retaining wall by the fastening means at the mutually intersecting parts of the retaining wall. Both ends are folded in half along the length of the retaining wall as well as to prevent loosening of the parts that are folded and falling from the connector catching part when binding to the wall connector or mounting on the retaining wall. The flow in the longitudinal direction eliminates the disadvantages such as length fluctuations, making the work more robust.

또한, 본 발명은 보강재를 반으로 접어 보강재의 끝단이 일정한 각도로 벌어지도록 하여 인장함으로써 보강재의 후단폭이 더욱 일정하게 유지되고, 보강재의 상단에 와셔가 일체로 된 고정못을 일정간격으로 다수 박아 밀착친정시킴으로써 보강토체 성토작업시 보강재가 펄럭이지 않고 보강재의 느즈러짐이 발생되지 않아 마찰력을 더욱 증대시켜 옹벽벽체를 견고히 지지하여 보강재의 기능을 최대한 발휘할 수 있으며, 본 발명에 의한 당김기구의 발판 상부의 가이드부재 좌·우측 양단에는 스파이크 고정너트가 발판을 관통되도록 돌출형성시켜 보조스파이크가 발판하부에서 분해·결합되도록 이루어지고, 보강재가 물리는 물림턱의 크기가 크고, 상·하 회전되도록 하여 보강재를 한 번에 여러가닥 물릴 수 있고, 지면이 고르지 않거나 스파이크가 지면에 완전히 박히지 않아도 보강재를 무는 물림턱이 항상 지면에 일치됨으로써 보강재의 인장·밀착·고정작업이 견고하게 이루어져 작업의 효율성이 향상됨으로써 경제적이고 견고한 시공을 보장해 줄 수 있는 효과를 갖는다.In addition, the present invention by folding the reinforcing material in half so that the end of the reinforcing material is stretched at a constant angle, the rear end width of the reinforcing material is maintained more constant, and a plurality of fixed nails in which the washers are integrated on the top of the reinforcing material at regular intervals. By the close affinity, the reinforcement does not flutter during the work of reinforcement soil filling and does not cause the reinforcement of the reinforcement, so that the friction force is further increased to firmly support the retaining wall wall so that the function of the reinforcement can be exhibited to the maximum. Spike fixing nut protrudes from the left and right sides of the guide member of the guide member so as to penetrate the scaffold so that the secondary spike is disassembled and combined at the bottom of the scaffold. Can bite several times at a time, uneven ground or spikes Without fully bakhiji the biting surfaces of the stiffener match is always made up ground jaws being rigidly fixed tension, adhesion, reinforcement work to improve the efficiency of the work being has an effect that can guarantee an economical and robust construction.

Claims (5)

옹벽벽체(20)의 내측면으로 돌출된 다수 연결구(30)의 걸림부(35)에 일정길이로 절단되고 길이방향의 중심부에 고정공(15)이 다수 형성된 띠형 보강재(10)를 각각 개별적으로 결속시키고, 보강재(10) 후단에서 당김기구(100)를 사용하여 보강재(10)가 팽팽히 유지되도록 당겨준 상태에서 고정못(17)으로 보강재(10)를 고정시키고 그 위에 보강토체(50)를 깔아 다짐작업을 실시하는 방법에 있어서, 상기 보강재(10)는 연결구(30)의 걸림부(35)에서 동일한 길이로 중간부에서 접혀져 걸림부(35) 바로 선단에서 볼트(12)와 너트(13)로 구성된 체결수단(11)에 의해 두겹의 보강재(10)가 결속되는 단계; 상기 결속된 보강재(10)의 후단에서 당김기구(100)에 의해 양방향으로 일정한 각도가 유지되면서 동일하게 팽팽히 당겨지는 인장단계; 상기 인장된 보강재(10)의 후단부터 상기 보강재(10)가 일정한 간격으로 벌어지기 시작하는 유효거리(L)부까지 보강재(10) 중심부의 고정공(15)에 일정한 간격으로 와셔(14)가 일체로 형성된 고정못(17)을 다수 박아 보강토체(50)에 고정시키는 단계; 로 이루어지는 것을 특징으로 하는 조립식 보강토 옹벽의 보강재 시공방법.Each of the strip-shaped reinforcement 10 is cut to a predetermined length in the engaging portion 35 of the plurality of connectors 30 protruding to the inner surface of the retaining wall wall 20 and the plurality of fixing holes 15 are formed in the central portion in the longitudinal direction. The reinforcing material 10 is fixed to the reinforcing material 10 by fixing nails 17 in a state in which the reinforcing material 10 is pulled to maintain the tension by using the pulling device 100 at the rear end of the reinforcing material 10 and the reinforcing soil 50 is fixed thereon. In the method of carrying out the compacting work, the reinforcing material 10 is folded in the middle portion with the same length in the locking portion 35 of the connector 30, so that the bolt 12 and the nut 13 at the tip of the locking portion 35 immediately. Binding two layers of reinforcing material by the fastening means (11) consisting of; A tensioning step of pulling the same tension while maintaining a constant angle in both directions by the pulling mechanism 100 at the rear end of the bound reinforcement (10); Washers 14 at regular intervals in the fixing hole 15 in the center of the reinforcing material 10 from the rear end of the tensioned reinforcing material 10 to the effective distance (L) portion in which the reinforcing material 10 begins to be opened at regular intervals. Fixing a plurality of nails 17 integrally formed into the reinforcement soil 50; Reinforcement construction method of prefabricated reinforcement retaining wall, characterized in that consisting of. 옹벽벽체(20)의 내측면으로 돌출된 다수 연결구(30)의 걸림부(35)에 일정길이로 절단되고 길이방향의 중심부에 고정공(15)이 다수 형성된 띠형 보강재(10)를 각각 개별적으로 결속시키고, 보강재(10)후단에서 당김기구(100)를 사용하여 보강재(10)가 팽팽히 유지되도록 당겨준 상태에서 고정못(17)으로 보강재(10)를 고정시키고 그 위에 보강토체(50)를 깔아 다짐작업을 실시하는 방법에 있어서, 상기 보강재(10)가 연결구(30)의 걸림부(35)에서 일차로 감겨져 한 쪽 끝단이 볼트(12)와 너트(13)로 이루어진 체결수단(11)에 의해 결속되는 단계; 상기 결속된 보강재(10)를 연결구(30)의 상단에 위치한 연결핀(40)을 외감하도록 하여 보강재(10)의 다른쪽 끝단을 보강토체(50) 상부에 위치시키는 단계; 상기 보강토체(50) 상부에 위치한 보강재(10)의 후단에서 당김기구(100)에 의해 팽팽히 유지되도록 잠아당긴 후에 와셔(14)가 일체로 형성된 고정못(17)을 보강재(10)의 고정공(15)에 일정간격으로 다수 박아 고정시키는 단계; 로 이루어지는 것을 특징으로 하는 조립식 보강토 옹벽의 보강재 시공방법.Each of the strip-shaped reinforcement 10 is cut to a predetermined length in the engaging portion 35 of the plurality of connectors 30 protruding to the inner surface of the retaining wall wall 20 and the plurality of fixing holes 15 are formed in the central portion in the longitudinal direction. The reinforcing material 10 is fixed to the reinforcing material 10 with the fixing nail 17 in a state in which the reinforcing material 10 is pulled to maintain the tension by using the pulling device 100 at the rear end of the reinforcing material 10 and the reinforcing soil 50 is fixed thereon. In the method for carrying out the compacting work, the reinforcing material 10 is first wound in the locking portion 35 of the connector 30, one end of the fastening means 11 consisting of a bolt 12 and a nut 13 Bound by; Positioning the other end of the reinforcing member 10 on the reinforcing soil body 50 by allowing the bundled reinforcing member 10 to surround the connection pin 40 positioned at the upper end of the connector 30; Fixing nail 17 of the reinforcing material 10 is fixed to the fixing nail 17 formed integrally with the washer 14 after being locked so as to be maintained by the pull mechanism 100 at the rear end of the reinforcing material 10 located above the reinforcement body (50) A plurality of driving at fixed intervals at 15; Reinforcement construction method of prefabricated reinforcement retaining wall, characterized in that consisting of. 스파이크(110)가 부착된 발판(105)에 설치된 가이드부재(120)에 전·후로 슬라이드 가능하고 물림턱(132)과 랙기어부가 형성된 이동부재(130)와, 상기 랙기어부상에 결합되도록 하단부에 피니언기어가 결합된 조작핸들(134)과, 이 조작핸들(134)을 전·후로 젖힐 때 상기 피니언기어를 타고넘어 다음 피어홈에 걸리거나 피니언 기어에 결합되어 피니언기어와 동시에 회전 또는 이탈되어 상기 이동부재(130)를 이동시키는 제 1래칫과 제 2래칫으로 이루어지는 조립식 보강토 옹벽의 지지용 보강재의 당김기구에 있어서, 상기 이동부재(130)의 선단과 물림턱(132)사이에는 상기 물림턱(132)이 상·하로 회전가능하도록 회동부재(140)가 구비된 것을 특징으로 하는 조립식 보강토 옹벽의 보강재 당김기구.A movable member 130 which is slidable back and forth on the guide member 120 installed on the footrest 105 to which the spike 110 is attached and is formed with a chuck 132 and a rack gear portion, and a lower end portion to be coupled to the rack gear portion. When the operation handle 134 is coupled to the pinion gear and the operation handle 134 is flipped forward and backward, the pinion gear is crossed over the pinion gear to be caught in the next pier groove or engaged with the pinion gear to rotate or move simultaneously with the pinion gear. In the pull mechanism of the reinforcement for supporting the prefabricated reinforcement retaining wall consisting of a first ratchet and a second ratchet for moving the movable member 130, the gripping jaw between the tip of the movable member 130 and the bite jaw 132 Reinforcement pull mechanism of the prefabricated reinforcement retaining wall, characterized in that the rotating member 140 is provided so that 132 is rotatable up and down. 제3항에 있어서, 상기 회동부재(130)는 이동부재(130)선단에 형성된 새클(142)과, 이 새클(142)에 끼워질 수 있도록 물림턱(132) 후단에 형성된 연결로드(146)와, 이 연결로드(146)를 상기 새클(142)에 결착시키는 고정핀(144)으로 구성된 것을 특징으로 하는 조립식 보강토 옹벽의 보강재 당김기구.According to claim 3, The rotating member 130 is a sack 142 formed at the front end of the moving member 130, and the connecting rod 146 formed at the rear end of the bite jaw 132 to be fitted to the sack 142 And, the reinforcement pull mechanism of the prefabricated reinforcement retaining wall, characterized in that consisting of the fixing pins (144) for binding the connecting rod (146) to the sackle (142). 제3항에 있어서, 상기 발판(105) 상부의 가이드부재(120) 좌·우측 양단에는 내면에 나사가 형성된 스파이크 고정너트(117)를 발판(105)에 관통되도록 돌출형성시키고, 상기 스파이크 고정너트(117)에는 상단부에 볼트부(119)가 형성되고 하단부에 스파이크(110)가 형성된 보조스파이크(118)가 분리가능하도록 결합되는 것을 특징으로 하는 조립식 보강토 옹벽의 보강재 당김기구.4. The spike fixing nut of claim 3, wherein the spike fixing nut 117 having a screw formed on the inner surface of the guide member 120 on the upper side of the foot plate 105 protrudes to penetrate the foot plate 105. 117 is a bolt portion 119 is formed at the upper end and the reinforcement pull mechanism of the prefabricated reinforcement retaining wall, characterized in that the secondary spike 118 formed with a spike 110 at the lower end is coupled to be detachable.
KR1019980053770A 1998-12-08 1998-12-08 Construction method and pull mechanism of prefabricated reinforced retaining wall KR100302139B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019980053770A KR100302139B1 (en) 1998-12-08 1998-12-08 Construction method and pull mechanism of prefabricated reinforced retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019980053770A KR100302139B1 (en) 1998-12-08 1998-12-08 Construction method and pull mechanism of prefabricated reinforced retaining wall

Publications (2)

Publication Number Publication Date
KR20000038693A KR20000038693A (en) 2000-07-05
KR100302139B1 true KR100302139B1 (en) 2001-10-29

Family

ID=19561904

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019980053770A KR100302139B1 (en) 1998-12-08 1998-12-08 Construction method and pull mechanism of prefabricated reinforced retaining wall

Country Status (1)

Country Link
KR (1) KR100302139B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100453882B1 (en) * 2002-06-20 2004-10-20 보강기술주식회사 Tension apparatus of reinforcing band
KR100801480B1 (en) 2007-01-30 2008-02-12 동아에스텍 주식회사 Geogrid connecting structure of breast wall
KR101993403B1 (en) 2018-08-09 2019-06-26 강현재 connector between block and stripe type textile reinforcement, retaining wall having the same and method of making the retaining wall

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100404128B1 (en) * 2001-04-27 2003-10-30 이정수 Placementing Method of Reinforcing Strips for Constructing Precast Concrete Facing Panel and Pulling-up Device of Reinforcing Strips
KR102576395B1 (en) * 2021-04-09 2023-09-11 이장원 Reinforced earth walls

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100453882B1 (en) * 2002-06-20 2004-10-20 보강기술주식회사 Tension apparatus of reinforcing band
KR100801480B1 (en) 2007-01-30 2008-02-12 동아에스텍 주식회사 Geogrid connecting structure of breast wall
KR101993403B1 (en) 2018-08-09 2019-06-26 강현재 connector between block and stripe type textile reinforcement, retaining wall having the same and method of making the retaining wall

Also Published As

Publication number Publication date
KR20000038693A (en) 2000-07-05

Similar Documents

Publication Publication Date Title
EP1016767A1 (en) Structure for reinforcing concrete member and reinforcing method
US8375643B1 (en) Coupler for landfill tarp
KR100302139B1 (en) Construction method and pull mechanism of prefabricated reinforced retaining wall
KR100328621B1 (en) Constructing Method of Reinforcement For Precast Concrete Facing Panel
KR20000015749A (en) Supporting device of assembly type reinforcing soil retaining wall and construction method and device thereof
CN108603351B (en) Geosynthetic reinforced wallboard including earth reinforcement members
KR100605327B1 (en) Fiber reinforced panel Prestressing device and Concrete structure Strengthening method using thereof
US6669172B1 (en) Post puller
JP2000192469A (en) Cofferdam device used for double wall cofferdam construction method, and double wall cofferdam construction method
AU722154B2 (en) System for holding down underground storage tanks
DE19534945C1 (en) Saddle anchorage and method of attaching the same
KR100349985B1 (en) Methods and tools for Constructing Reinforcement of Precast Concrete Facing Panel
JP6868497B2 (en) Chute type transfer device
JP5387959B2 (en) Pile press-fitting device for mountain fastening
JP2994225B2 (en) Method and apparatus for reinforcing existing bridge
JP3347703B2 (en) Retaining wall method
JP2015517614A (en) Reinforced soil
JP2008303534A (en) Binding method for underground structure
JP2656453B2 (en) Tension steel unit used for earth anchor method
JPH02272151A (en) Method and tool for anchoring carbon fibre-reinforced plastic flat plate
WO2016064018A1 (en) Method for using strip type fiber-reinforced material as soil nail structure
JPS63261099A (en) Method of constructing tunnel and member for constructing tunnel
AT137462B (en) Ceiling construction.
JP3192483U (en) Sediment dropping device
JP4251341B2 (en) Block transfer method and block laying method

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20050629

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee