JP2000192469A - Cofferdam device used for double wall cofferdam construction method, and double wall cofferdam construction method - Google Patents

Cofferdam device used for double wall cofferdam construction method, and double wall cofferdam construction method

Info

Publication number
JP2000192469A
JP2000192469A JP10369877A JP36987798A JP2000192469A JP 2000192469 A JP2000192469 A JP 2000192469A JP 10369877 A JP10369877 A JP 10369877A JP 36987798 A JP36987798 A JP 36987798A JP 2000192469 A JP2000192469 A JP 2000192469A
Authority
JP
Japan
Prior art keywords
wire
materials
double
steel
steel sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP10369877A
Other languages
Japanese (ja)
Other versions
JP4009028B2 (en
Inventor
Koichi Tanaka
耕一 田中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP36987798A priority Critical patent/JP4009028B2/en
Publication of JP2000192469A publication Critical patent/JP2000192469A/en
Application granted granted Critical
Publication of JP4009028B2 publication Critical patent/JP4009028B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Revetment (AREA)

Abstract

PROBLEM TO BE SOLVED: To sufficiently resist earth pressure without particularly increasing the sections of coffering materials even when a ground surface on the front side is deepened and earth pressure from filled sand charged among the coffering materials by steel sheet piles or the like is augmented when a part under a water surface is to be coffered by a double wall cofferdam construction method, to facilitate handling, reduce the manufacturing cost of the coffering materials, and to improve workability. SOLUTION: The cofferdam device is used for the double wall cofferdam construction method, in which coffering materials such as steel sheet piles 11 or the like driven in two rows at intervals are connected mutually by tie materials. Binding sections 3a-3c for PC steel wires 1a, 1b as the tie materials are installed to the coffering materials 11 at a plurality of places along the height direction of the coffering materials, and connected to fixing sections, where a plurality of these binding sections are interlocked mutually and bound.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、河川・湾岸などの
水域における工事などで用いられる二重締切り工法で使
用する締切り装置および二重締切り工法に関するもので
ある。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a double cutoff method and a double cutoff method used in a construction work in a water area such as a river or a bay.

【0002】[0002]

【従来の技術】河川・湾岸などの水域において水面下に
構造物基礎などを構築する場合、かかる構築をドライで
行う方法がある。この場合、構築場所を締め切って周囲
の水から遮断することになるが、締切りの方法として従
来から二重締切り工法が知られている。
2. Description of the Related Art In the case of constructing a structure foundation or the like below the water surface in a water area such as a river or a bay, there is a method of performing such a construction in a dry manner. In this case, the construction site is closed and cut off from surrounding water, and a double closing method has been conventionally known as a method of closing.

【0003】この二重締切り工法は、仮設の締切りとし
て、例えば図12に示すように、鋼管矢板や鋼矢板11によ
る締切り材を間隔をおいて2列に水底の地盤12に打設
し、水面より上方に突出した鋼矢板11の頭部の部分をタ
イ材としてのタイロッド13で相互に結合し、2列の鋼矢
板11の間に水圧に抵抗するものとして中詰砂14を投入す
るものである。
In this double cutoff method, as a temporary cutoff, for example, as shown in FIG. 12, cutoff materials made of steel pipe sheet piles or steel sheet piles 11 are placed in two rows at intervals on the ground 12 at the bottom of the water, and The part of the head of the steel sheet pile 11 projecting upward is mutually connected by a tie rod 13 as a tie material, and a filling sand 14 is injected between the two rows of steel sheet pile 11 as a resistance to water pressure. is there.

【0004】このようにして二重の鋼矢板11で締め切ら
れ、水と遮断した範囲をドライにしてこの場所に構造物
基礎などを構築する。この場合、図13に示すように鋼矢
板11は内側から外側に向けては内部の中詰砂14の土圧を
受け、外側から内側に向けては土圧に抵抗するものとし
て下部では地盤12、上部ではタイロッド13からの力を受
ける。また、二重締切り工法は水中の締切りだけでは
く、盛土による二重締切りにも採用され、盛土の上部を
道路として利用することがある。
[0004] In this way, the area closed by the double steel sheet pile 11 and cut off from the water is dried to construct a structural foundation or the like at this location. In this case, as shown in FIG. 13, the steel sheet pile 11 receives the earth pressure of the internal filling sand 14 from the inside to the outside, and resists the earth pressure from the outside to the inside. The upper part receives the force from the tie rod 13. In addition, the double cutoff method is used not only for underwater cutoffs, but also for double cutoffs using embankment, and the upper part of the embankment may be used as a road.

【0005】[0005]

【発明が解決しようとする課題】二重締切り工法では、
前面側の地盤面が深くなると全体の安定性を確保するた
めに、鋼矢板による締切り材の間隔を大きくする必要が
ある。そのため、中詰砂の投入量が多くなり、また鋼矢
板に作用する土圧及びタイロッドに作用する張力も大き
くなる。
In the double closing method,
When the ground surface on the front side becomes deeper, it is necessary to increase the interval between the cutoff members made of steel sheet piles in order to secure the overall stability. Therefore, the amount of filling sand is increased, and the earth pressure acting on the steel sheet pile and the tension acting on the tie rod are also increased.

【0006】このため、前面側の地盤面が深くなった場
合に、中詰砂14からの大きな土圧に抵抗するには、鋼矢
板11の断面及びタイロッドの径を大きくしていた。その
結果、鋼矢板11の製造コストが嵩み、重量や体積の増す
ために運搬などの取扱いも手間を要するようになる。
For this reason, when the ground surface on the front side is deepened, the cross section of the steel sheet pile 11 and the diameter of the tie rod have been increased in order to resist a large earth pressure from the filling sand 14. As a result, the manufacturing cost of the steel sheet pile 11 increases, and handling such as transportation becomes troublesome in order to increase the weight and volume.

【0007】本発明の目的は前記従来例の不都合を解消
し、二重締切り工法で締め切る場合に、前面側の地盤面
が深くなって鋼矢板などによる締切り材の間に投入した
中詰砂からの土圧が大きなものになっても、締切り材の
断面を特に大きくせずに土圧に十分耐えることができ、
取扱いが容易で締切り材の製造コストの低減も図ること
ができ、また、施工性もよい二重締切り工法で使用する
締切り装置および二重締切り工法を提供することにあ
る。
SUMMARY OF THE INVENTION An object of the present invention is to solve the disadvantages of the prior art, and when closing off by the double closing method, the ground surface on the front side becomes deeper and the sand from the filling material inserted between the closing materials such as steel sheet piles is used. Even if the earth pressure becomes large, it can withstand the earth pressure sufficiently without making the cross section of the cutoff material particularly large,
An object of the present invention is to provide a double cutoff method and a double cutoff method which can be easily handled, can reduce the production cost of the cutoff material, and can be easily used.

【0008】[0008]

【課題を解決するための手段】本発明は前記目的を達成
するため、第1に、間隔をおいて2列に打設した鋼矢板
などの締切り材を相互にタイ材で連結する二重締切り工
法で使用する締切り装置であって、前記締切り材にその
高さ方向にそって複数箇所にタイ材の緊結部を設け、こ
れらの複数の緊結部を相互に連動して緊結する定着部に
接続したことを要旨とするものである。
SUMMARY OF THE INVENTION In order to achieve the above object, the present invention firstly provides a double cut-off for connecting cut-off materials such as steel sheet piles which are placed in two rows at intervals with a tie material. A closing device used in a construction method, wherein a plurality of binding portions of a tie material are provided on a plurality of locations along the height direction of the closing material, and the plurality of binding portions are connected to a fixing portion which is tightly coupled in a mutual manner. The gist is that it has been done.

【0009】第2に、タイ材はPC鋼線などの線材で構
成し、対向する締切り材間に千鳥状に掛け渡すことを要
旨とするものである。
Second, the tie material is composed of a wire material such as a PC steel wire, and has a gist that the tie material is staggered between opposing cutoff materials.

【0010】第3に、タイ材はPC鋼線などの2本の線
材で構成し、対向する締切り材間に交差させて千鳥状に
掛け渡すことを要旨とするものである。
Third, the tie material is composed of two wires, such as PC steel wires, and is to be crossed between opposing cut-off materials so as to be staggered.

【0011】第4に、タイ材はPC鋼線などの線材で構
成し、締切り材に設けた複数の緊結部のうち中間に位置
するものにはローラを設け、線材の途中を該ローラに巻
回することを要旨とするものである。
Fourth, the tie material is made of a wire such as a PC steel wire, and a roller is provided at a middle portion among a plurality of binding portions provided on the cut-off material, and the wire is wound around the roller in the middle of the wire. It is intended to be turned.

【0012】第5に、線材を一対の取付部材間に掛け渡
し、該取付部材を締切り材に着脱自在に装着することを
要旨とするものである。
Fifthly, the gist of the present invention is to extend the wire between a pair of mounting members and detachably mount the mounting member to the closing member.

【0013】第6に、鋼矢板などの締切り材を間隔をお
いて2列に打設し、一方、対向する一対の取付部材間に
PC鋼線などの線材を千鳥状に掛け渡し、この取付部材
を上部から下部へとおろしながら前記締切り部材に装着
して、締切り部材間に線材を張設することを要旨とする
ものである。
Sixth, shut-off members such as steel sheet piles are placed in two rows at intervals, while a wire member such as a PC steel wire is staggered between a pair of opposed mounting members. The gist is that the member is attached to the shutoff member while being lowered from the upper part to the lower part, and a wire is stretched between the shutoff members.

【0014】請求項1記載の本発明によれば、鋼矢板な
どの締切り材にその高さ方向にそって複数箇所にタイ材
の緊結部を設けたから、間隔をおいて2列に打設した締
切り材の間に投入した中詰砂から締切り材に加わる土圧
に対して、複数箇所でこれに抵抗できる。よって、前面
側の地盤面が深くなっても締切り材の断面を特に大きく
せずに土圧に対処できる。また、複数箇所の緊結部での
緊結は、一か所の定着部での緊結作業で行えるから、緊
結部が複数箇所存在してもそれぞれ一か所毎の緊結作業
は不要で、全体を一挙に緊結できるから作業性のよいも
のである。
According to the first aspect of the present invention, since the tie material is provided at a plurality of locations along the height direction of the shutoff material such as a steel sheet pile, the tie material is punched in two rows at intervals. It can resist earth pressure applied to the cutoff material from the filling sand injected between the cutoff materials at a plurality of locations. Therefore, even if the ground surface on the front side becomes deep, it is possible to cope with the earth pressure without particularly increasing the cross section of the cutoff material. In addition, since tying at multiple tying parts can be performed by tying work at one fixing part, even if there are multiple tying parts, tying work at each place is unnecessary, and the whole The workability is good because it can be tied to.

【0015】請求項2記載の本発明によれば、前記作用
に加えて、タイ材をPC鋼線などの線材とすることで、
1本の線材を対向する鋼矢板などの締切り材に対して交
互に掛止していけばよいから、複数箇所に容易に緊結で
きる。
According to the second aspect of the present invention, in addition to the above function, the tie material is made of a wire such as a PC steel wire.
Since it is sufficient that one wire is alternately hooked to the opposing cutoff material such as a steel sheet pile, it can be easily tied to a plurality of locations.

【0016】請求項3記載の本発明によれば、請求項1
記載の本発明の作用に加えて、2本のPC鋼線などの線
材を対向する締切り材間に交差させて千鳥状に掛け渡す
ことで、対向する締切り材に対して互いに内側に引き合
う力をバランスよく確実に付与でき、中詰砂による土圧
に十分かつ確実に抵抗できる。
According to the third aspect of the present invention, a first aspect is provided.
In addition to the operation of the present invention described above, by crossing a wire such as two PC steel wires between the opposing cutoff materials in a staggered manner, a force that pulls the opposing cutoff materials inward toward each other is obtained. Can be applied reliably and in a well-balanced manner, and can sufficiently and surely resist the earth pressure caused by the filling sand.

【0017】請求項4記載の本発明によれば、前記作用
に加えて、PC鋼線などの線材の途中を、締切り材に設
けたローラに巻回することにより締切り材に容易に掛止
できるだけでなく、線材の一端を引っ張るだけで線材全
体を緊張でき、締切り材全体に内側に引き合う力を付与
できる。
According to the fourth aspect of the present invention, in addition to the above-described operation, by winding a wire such as a PC steel wire around a roller provided on the cutoff member, the wire can be easily hooked on the cutoff member. Instead, it is possible to tension the entire wire by simply pulling one end of the wire, and to apply an inward pulling force to the entire cutoff material.

【0018】請求項5記載の本発明によれば、前記作用
に加えて、線材を一対の取付部材間に掛け渡し、該取付
部材を締切り材に着脱自在に装着することで、簡単に線
材を締切り材に装着できる。
According to the fifth aspect of the present invention, in addition to the above-described operation, the wire can be easily spanned between the pair of mounting members, and the mounting member can be detachably mounted on the closing member, so that the wire can be easily formed. Can be attached to cut-off materials.

【0019】請求項6記載の本発明によれば、施工法と
して、締切り部材への線材の取り付けは、一対の対向す
る取付部材に予め線材を張設しておき、この線材が張設
された取付部材を上部から下部へおろし、締切り部材に
装着するだけでよいから、施工性が向上する。
According to the sixth aspect of the present invention, as a construction method, when the wire is attached to the shutoff member, the wire is stretched in advance on a pair of opposed attaching members, and the wire is stretched. Since it is only necessary to lower the mounting member from the upper part to the lower part and attach it to the shutoff member, workability is improved.

【0020】[0020]

【発明の実施の形態】以下、図面について本発明の実施
の形態を詳細に説明する。図10は本発明の二重締切り工
法およびこの工法で使用する締切り装置の実施形態の正
面図で、図中、図12に示した従来例と同一の構成要素に
は同一の参照符号を付してある。
Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 10 is a front view of an embodiment of the double cutoff method of the present invention and a cutoff device used in this method. In the drawing, the same components as those of the conventional example shown in FIG. 12 are denoted by the same reference numerals. It is.

【0021】本発明の二重締切り工法も基本構成は従来
と同様、鋼矢板11による締切り材を間隔をおいて2列に
例えば水底の地盤12に打設し、この2列の鋼矢板11の間
に水圧に抵抗するものとして中詰砂14を投入するもので
あり、この対向する鋼矢板11間に、該鋼矢板11を相互に
連結するタイ材として、2本のPC鋼線1a,1bなど
の線材を千鳥状に掛け渡して張設した。
The double cut-off method of the present invention has the same basic construction as that of the prior art, in which cut-off materials made of steel sheet piles 11 are placed in two rows at intervals, for example, on the ground 12 at the bottom of the water. In between the steel sheet piles 11 facing each other, two PC steel wires 1a and 1b are used as tie members for connecting the steel sheet piles 11 to each other. Such wires are staggered and stretched.

【0022】鋼矢板11へのPC鋼線1a,1bの張設構
造は、図3〜図6に詳細に示すように鋼矢板11への取付
部材として、該鋼矢板11とは別体の例えば周知のH形鋼
のウェブの部分を切断して製作した断面形状がT字形の
CT鋼2を用い、このCT鋼2の長さ方向にPC鋼線1
a,1bの緊結部3a,3b,3cを適宜間隔で複数箇
所(図示の例では3か所)に設ける。
As shown in detail in FIGS. 3 to 6, the structure for extending the PC steel wires 1a and 1b to the steel sheet pile 11 is provided as an attachment member to the steel sheet pile 11, for example, separately from the steel sheet pile 11. A T-shaped CT steel 2 manufactured by cutting a web portion of a well-known H-section steel is used, and a PC steel wire 1 is arranged in the longitudinal direction of the CT steel 2.
The binding portions 3a, 3b, 3c of a, 1b are provided at a plurality of locations (three locations in the illustrated example) at appropriate intervals.

【0023】上端と下端に位置する緊結部3a,3bは
同様の構造で、図5、図6にも示すようにCT鋼2のウ
ェブ2aを両側から挟むようにして2枚の取付用のプレ
ート4a,4bの基部を溶接などにより固定し、その先
端部分をCT鋼2から突出させる。このプレート4a,
4bの形状は、先端面がPC鋼線1a,1bの張設方向
と直交するように図6に示すような三角形状または図5
に示すような先端部を斜めにカットした矩形状に形成し
た。
The binding portions 3a and 3b located at the upper end and the lower end have the same structure, and as shown in FIGS. 5 and 6, the two mounting plates 4a and 4a sandwich the web 2a of the CT steel 2 from both sides. The base of 4b is fixed by welding or the like, and the tip of the base is projected from the CT steel 2. This plate 4a,
4b has a triangular shape as shown in FIG. 6 or a triangular shape as shown in FIG. 5 so that the tip surface is orthogonal to the direction in which the PC steel wires 1a and 1b are stretched.
As shown in the figure, the tip was formed obliquely cut into a rectangular shape.

【0024】なお、プレートは前記のような2枚ものに
限定されるものではなく、ウェブ2aへの取付のための
基部は一体ものとして、ここにウェブ2aを挿入するた
めの溝を設けておいてもよい。
Incidentally, the plate is not limited to the two plates as described above, and the base for attachment to the web 2a is integrated, and a groove for inserting the web 2a is provided here. May be.

【0025】中間に位置する緊結部3cは、図3、図4
に示すようにCT鋼2のウェブ2aを両側から挟むよう
にして2枚ものの取付用のプレート5a,5bを先端が
ウェブ2aから突出するようにして溶接などによりウェ
ブ2aに固定し、このプレート5a,5bの突出部分に
おいてその間に形成された隙間にローラ6を設けた。こ
の場合、該ローラ6とウェブ2aの先端との間にはPC
鋼線1a,1bが挿入できるだけの隙間を確保してお
く。
The binding portion 3c located in the middle is shown in FIGS.
As shown in the figure, two mounting plates 5a and 5b are fixed to the web 2a by welding or the like so that the tips protrude from the web 2a so as to sandwich the web 2a of the CT steel 2 from both sides, and these plates 5a and 5b The roller 6 is provided in the gap formed between the protruding portions. In this case, PC is provided between the roller 6 and the tip of the web 2a.
A gap is provided to allow the steel wires 1a and 1b to be inserted.

【0026】一方、PC鋼線1a,1bの端部には、該
PC鋼線1a,1bを貫通させて定着プレート8を取り
付けておき、該定着プレート8より突出する部分をネジ
部7に形成し、該ネジ部7の基部に締めつけ用のナット
9を取り付けておく。
On the other hand, a fixing plate 8 is attached to the ends of the PC steel wires 1a and 1b so as to penetrate the PC steel wires 1a and 1b, and a portion protruding from the fixing plate 8 is formed in the screw portion 7. Then, a tightening nut 9 is attached to the base of the screw portion 7.

【0027】かかる二重締切り装置を使用して、河川や
湾岸などの水域で締切り工事を行うには、第1工程とし
て図1、図2に示すように締切り材である鋼矢板11の一
方の側面に長さ方向にチャンネル状の継ぎ手10を溶接な
どにより取り付けておく。この場合、鋼矢板11の下方部
分は水底の地盤12に打設されるから、この下方部分より
上方部分に取り付ける。
In order to perform a cutoff work in a water area such as a river or a bay by using such a double cutoff device, one of the steel sheet piles 11 which is a cutoff material as shown in FIGS. A channel-shaped joint 10 is attached to the side surface in the length direction by welding or the like. In this case, since the lower part of the steel sheet pile 11 is driven into the ground 12 at the bottom of the water, the steel sheet pile 11 is mounted above the lower part.

【0028】継ぎ手10を取り付けた鋼矢板11を間隔をお
いて対向させて2列に水底の地盤12に打設し、頭部は水
上に突出させる。このとき継ぎ手10の箇所は向かい合わ
せにする。
The steel sheet piles 11 to which the joints 10 are attached are placed in two rows on the ground 12 at the bottom of the water so as to face each other at an interval, and the head is projected above the water. At this time, the joints 10 should face each other.

【0029】一方、図3に示すように対向する一対のC
T鋼2に設けてある緊結部3a,3b,3cに2本のP
C鋼線1a,1bをそれぞれ交差させて対向するCT鋼
2間をぬうようにして千鳥状に掛け渡しておく。すなわ
ち、例えば一方のPC鋼線1aについては、その上端と
下端とを一方のCT鋼2の上下の緊結部3a,3bにそ
れぞれ固定し、中間部分を他方のCT鋼2の中間位置に
ある緊結部3cに掛止する。なお、上部の緊結部3aへ
の固定は仮止めとし、該緊結部3aからさらに水上の上
方にPC鋼線1a,1bを突出させてその先端を図示は
省略するが、該PC鋼線1a,1bを引っ張るジャッキ
などを用いる定着部に接続しておく。
On the other hand, as shown in FIG.
Tightening parts 3a, 3b, 3c provided on T steel 2
The C steel wires 1a and 1b cross each other and are staggered so as to wipe between the opposed CT steels 2. That is, for example, for one PC steel wire 1a, the upper end and the lower end thereof are fixed to the upper and lower binding portions 3a, 3b of one CT steel 2, respectively, and the intermediate portion is located at the intermediate position of the other CT steel 2. Hooks on part 3c. Note that the PC steel wires 1a and 1b are further fixed to the upper binding portion 3a by temporarily fixing, and the PC steel wires 1a and 1b are further projected above the water from the binding portion 3a. 1b is connected to a fixing unit using a jack or the like that pulls 1b.

【0030】上下位置の緊結部3a,3bへのPC鋼線
1aの固定は、図5、図6に示すように緊結部3a,3
bのプレート4a,4bの間に先端のネジ部7を挿入
し、定着プレート8をプレート4a,4bの端部に当接
し、この状態でナット9を締めつければ、定着プレート
8がプレート4a,4bに圧着してPC鋼線1aが緊結
部3a,3bに固定される。
As shown in FIGS. 5 and 6, the fastening of the PC steel wire 1a to the upper and lower binding portions 3a and 3b is performed.
b, the screw 7 at the tip is inserted between the plates 4a and 4b, the fixing plate 8 is brought into contact with the ends of the plates 4a and 4b, and the nut 9 is tightened in this state. 4b, and the PC steel wire 1a is fixed to the binding portions 3a, 3b.

【0031】中間の緊結部3cへのPC鋼線1aの掛止
は、図4に示すように上下いずれかの緊結部3a,3b
へのPC鋼線1aの固定を行う前段階で、PC鋼線1a
をローラ6に巻回すればよい。他方の鋼線1bについて
も同様に行う。
As shown in FIG. 4, the fastening of the PC steel wire 1a to the intermediate binding portion 3c is performed by either the upper or lower binding portion 3a, 3b.
Before fixing the PC steel wire 1a to the PC steel wire 1a,
May be wound around the roller 6. The same is performed for the other steel wire 1b.

【0032】このようにして対向する一対のCT鋼2に
設けてある緊結部3a,3b,3cに2本のPC鋼線1
a,1bがそれぞれ横V字状の交差状態で張設される。
よって、かかるPC鋼線1a,1bが張設されたCT鋼
2を第2工程として図7、図8に示すように鋼矢板11に
取り付けてある継ぎ手10に挿着する。この挿着は、CT
鋼2のフランジ2bの部分を継ぎ手10の溝内に上方から
挿入することにより行う。
The two PC steel wires 1 are connected to the binding portions 3a, 3b, 3c provided on the pair of opposed CT steels 2 in this manner.
a and 1b are each stretched in a crossing state of a horizontal V-shape.
Accordingly, the CT steel 2 on which the PC steel wires 1a and 1b are stretched is inserted into a joint 10 attached to a steel sheet pile 11 as shown in FIGS. 7 and 8 as a second step. This insertion is CT
This is performed by inserting a portion of the flange 2b of the steel 2 into the groove of the joint 10 from above.

【0033】以上のようにしてCT鋼2を継ぎ手10に挿
着することにより、PC鋼線1a,1bが間隔をおいて
打設されている鋼矢板11間に配設されたならば、次に図
9に示すように第3工程として、水面上に突出している
上部の緊結部3aにおいて、ここから突出しているPC
鋼線1a,1bをさらに引っ張って複数箇所のすべての
緊結部3a,3b,3cにおいて同時に一挙に緊張し
て、最終的に緊結部3aに定着する。
By inserting the CT steel 2 into the joint 10 as described above, if the PC steel wires 1a and 1b are disposed between the steel sheet piles 11 which are driven apart from each other, the following process is performed. As shown in FIG. 9, as a third step, the PC projecting from the upper binding portion 3 a projecting above the water surface
The steel wires 1a, 1b are further pulled to simultaneously tighten all of the plurality of binding portions 3a, 3b, 3c at once, and finally settle to the binding portions 3a.

【0034】そして、最後に第4工程として図10に示す
ように対向する鋼矢板11間に中詰砂14を投入する。これ
により二重締切りが完了する。
Finally, as a fourth step, as shown in FIG. 10, a filling sand 14 is put between the steel sheet piles 11 facing each other. This completes the double cutoff.

【0035】かかる二重締切りにおいては、図11に示す
ように2本のPC鋼線1a,1bが鋼矢板11に対して高
さ方向の複数箇所、実施形態では3か所で緊結されてい
るから、中詰砂による鋼矢板11への内側からの土圧に対
して、鋼矢板11の外側から複数箇所で抵抗できる。な
お、前記した実施形態は、水中での二重締切りに実施す
る場合であるが、本発明はこれに限定されるものではな
く、盛土による二重締切りにも実施可能であり、この場
合は盛土の上面を道路として利用することができる。
In such a double cut-off, as shown in FIG. 11, two PC steel wires 1a and 1b are fastened to the steel sheet pile 11 at a plurality of locations in the height direction, in this embodiment at three locations. Therefore, it is possible to resist the earth pressure from the inside to the steel sheet pile 11 due to the filling sand at a plurality of locations from the outside of the steel sheet pile 11. In addition, although the embodiment described above is a case where the double cutoff is performed in water, the present invention is not limited to this, and the present invention can also be performed with a double cutoff by embankment. Can be used as a road.

【0036】[0036]

【発明の効果】以上述べたように本発明の二重締切り工
法で使用する締切り装置および二重締切り工法は、鋼矢
板などによる締切り材を間隔をおいて2列に打設する二
重締切り工法で水面下を締め切る場合に、前面側の地盤
面が深くなったときに対向する締切り材の間に投入した
中詰砂や土からの土圧が大きなものになっても、締切り
材の断面を特に大きくせずに土圧に十分耐えることがで
き、取扱いが容易で締切り材の製造コストの低減も図る
ことができ、また、そのための施工も複数箇所の緊結部
における緊結は、一か所の定着部での緊結作業で行える
から、緊結部が複数箇所存在してもそれぞれ一か所毎の
緊結作業は不要で、全体を一挙に緊結できるから施工性
もよいものである。
As described above, the cutoff device and the double cutoff method used in the double cutoff method of the present invention are a double cutoff method in which cutoff materials such as steel sheet piles are placed in two rows at intervals. In the case of closing below the water surface, even if the ground pressure on the front side becomes deep, the cross section of the cutoff In particular, it can withstand the earth pressure without increasing the size, it is easy to handle, and the manufacturing cost of the shutoff material can be reduced. Since the fastening operation can be performed by the fastening operation at the fixing unit, even if there are a plurality of fastening portions, the fastening operation is not required for each location, and the entirety can be fastened at once, so that the workability is good.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の二重締切り工法の実施形態の第1工程
を示す正面図である。
FIG. 1 is a front view showing a first step of an embodiment of a double closing method according to the present invention.

【図2】本発明の二重締切り工法の実施形態の第1工程
を示す平面図である。
FIG. 2 is a plan view showing a first step of the embodiment of the double cutoff method of the present invention.

【図3】本発明の二重締切り装置の要部の正面図であ
る。
FIG. 3 is a front view of a main part of the double cutoff device of the present invention.

【図4】本発明の二重締切り装置の要部である中間の緊
結部の横断平面図である。
FIG. 4 is a cross-sectional plan view of an intermediate binding portion, which is a main part of the double cutoff device of the present invention.

【図5】本発明の二重締切り装置の要部である端部の緊
結部の正面図である。
FIG. 5 is a front view of a binding portion at an end which is a main part of the double cutoff device of the present invention.

【図6】本発明の二重締切り装置の要部である端部の緊
結部の斜視図である。
FIG. 6 is a perspective view of a binding portion at an end which is a main part of the double cutoff device of the present invention.

【図7】本発明の二重締切り工法の実施形態の第2工程
を示す正面図である。
FIG. 7 is a front view showing a second step of the embodiment of the double cutoff method of the present invention.

【図8】本発明の二重締切り工法の実施形態の第2工程
を示す平面図である。
FIG. 8 is a plan view showing a second step of the embodiment of the double cutoff method of the present invention.

【図9】本発明の二重締切り工法の実施形態の第3工程
を示す正面図である。
FIG. 9 is a front view showing a third step of the embodiment of the double cutoff method of the present invention.

【図10】本発明の二重締切り工法の実施形態の第4工
程を示す正面図である。
FIG. 10 is a front view showing a fourth step of the embodiment of the double cutoff method of the present invention.

【図11】本発明の二重締切り装置に加わる力の説明図
である。
FIG. 11 is an explanatory view of a force applied to the double cutoff device of the present invention.

【図12】従来の二重締切り工法の正面図である。FIG. 12 is a front view of a conventional double cutoff method.

【図13】従来の二重締切り装置に加わる力の説明図で
ある。
FIG. 13 is an explanatory diagram of a force applied to a conventional double cutoff device.

【符号の説明】[Explanation of symbols]

1a,1b…PC鋼線 2…CT鋼 2a…ウェブ 2b…フランジ 3a,3b,3c…緊結部 4a,4b…プレー
ト 5a,5b…プレート 6…ローラ 7…ネジ部 8…定着プレート 9…ナット 10…継ぎ手 11…鋼矢板 12…地盤 13…タイロッド 14…中詰砂
1a, 1b: PC steel wire 2: CT steel 2a: Web 2b: Flange 3a, 3b, 3c: Tightening portion 4a, 4b: Plate 5a, 5b: Plate 6: Roller 7: Screw portion 8: Fixing plate 9: Nut 10 ... Joints 11 ... Steel sheet piles 12 ... Ground 13 ... Tie rods 14 ... Filled sand

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 間隔をおいて2列に打設した鋼矢板など
の締切り材を相互にタイ材で連結する二重締切り工法で
使用する締切り装置であって、前記締切り材にその高さ
方向にそって複数箇所にタイ材の緊結部を設け、これら
の複数の緊結部を相互に連動して緊結する定着部に接続
したことを特徴とする二重締切り工法で使用する締切り
装置。
1. A cut-off device used in a double cut-off method for connecting cut-off materials such as steel sheet piles, which are placed in two rows at intervals, to each other with a tie material. A closing device used in a double closing method, wherein a plurality of tying portions of tie material are provided along a plurality of locations, and the plurality of tying portions are connected to a fixing portion which is tied in conjunction with each other.
【請求項2】 タイ材はPC鋼線などの線材で構成し、
対向する締切り材間に千鳥状に掛け渡す請求項1記載の
二重締切り工法で使用する締切り装置。
2. The tie is made of a wire such as a PC steel wire.
The shut-off device used in the double shut-off method according to claim 1, wherein the shut-off device is staggered between opposing cut-off materials.
【請求項3】 タイ材はPC鋼線などの2本の線材で構
成し、対向する締切り材間に交差させて千鳥状に掛け渡
す請求項1または請求項2に記載の二重締切り工法で使
用する締切り装置。
3. The double cutoff method according to claim 1, wherein the tie material is composed of two wires, such as PC steel wires, and is crossed between the opposing cutoff materials in a staggered manner. The cut-off device to use.
【請求項4】 タイ材はPC鋼線などの線材で構成し、
締切り材に設けた複数の緊結部のうち中間に位置するも
のにはローラを設け、線材の途中を該ローラに巻回する
請求項1から請求項3のいずれかに記載の二重締切り工
法で使用する締切り装置。
4. The tie is made of a wire such as a PC steel wire.
The double closing method according to any one of claims 1 to 3, wherein a roller is provided at an intermediate position among the plurality of binding portions provided on the closing material, and a wire is wound around the roller in the middle of the wire. The cut-off device to use.
【請求項5】 線材を一対の取付部材間に掛け渡し、該
取付部材を締切り材に着脱自在に装着する請求項1から
請求項4のいずれかに記載の二重締切り工法で使用する
締切り装置。
5. The shut-off device used in the double shut-off method according to claim 1, wherein the wire is stretched between a pair of mounting members, and the mounting member is removably mounted on the shut-off member. .
【請求項6】 鋼矢板などの締切り材を間隔をおいて2
列に打設し、一方、対向する一対の取付部材間にPC鋼
線などの線材を千鳥状に掛け渡し、この取付部材を上部
から下部へおろしながら前記締切り部材に装着して、締
切り部材間に線材を張設することを特徴とする二重締切
り工法。
6. Closing members such as steel sheet piles at intervals.
On the other hand, a wire such as a PC steel wire is hung in a staggered manner between a pair of opposed mounting members, and the mounting members are mounted on the closing member while being lowered from the upper part to the lower part. A double closing method characterized by stretching a wire rod.
JP36987798A 1998-12-25 1998-12-25 Deadline equipment and double deadline method used in double deadline method Expired - Fee Related JP4009028B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP36987798A JP4009028B2 (en) 1998-12-25 1998-12-25 Deadline equipment and double deadline method used in double deadline method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP36987798A JP4009028B2 (en) 1998-12-25 1998-12-25 Deadline equipment and double deadline method used in double deadline method

Publications (2)

Publication Number Publication Date
JP2000192469A true JP2000192469A (en) 2000-07-11
JP4009028B2 JP4009028B2 (en) 2007-11-14

Family

ID=18495539

Family Applications (1)

Application Number Title Priority Date Filing Date
JP36987798A Expired - Fee Related JP4009028B2 (en) 1998-12-25 1998-12-25 Deadline equipment and double deadline method used in double deadline method

Country Status (1)

Country Link
JP (1) JP4009028B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100711602B1 (en) 2006-08-11 2007-05-02 주식회사 도화종합기술공사 Temporary levee protector using crossed pile for repairing underwater structure
CN102587398A (en) * 2012-04-09 2012-07-18 中铁二十二局哈尔滨铁路建设集团有限责任公司 Double-wall cofferdam with partitioned cabins
CN109371997A (en) * 2018-12-04 2019-02-22 中铁六局集团有限公司 A kind of double-wall cofferdam and pier construction method
CN113152499A (en) * 2021-03-19 2021-07-23 国网河北省电力有限公司邢台供电分公司 Cofferdam backfill reinforced foundation and construction method
CN113684848A (en) * 2021-09-03 2021-11-23 安徽省公路桥梁工程有限公司 Construction process of steel cofferdam with deep water steep undulating rock surface
CN115162366A (en) * 2022-08-05 2022-10-11 广州市市政工程机械施工有限公司 Construction method for pre-grooving deep-water double-wall steel cofferdam on pebble bed river bed and cleaning pebbles in groove

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102121251A (en) * 2011-01-30 2011-07-13 中铁八局集团第一工程有限公司 Construction method for pouring main tower pier foundation of bridge on deep-water oblique river bed
CN102704501B (en) * 2012-05-16 2015-11-18 中铁大桥局集团第二工程有限公司 Ejection for water plugging cofferdam and construction method thereof
CN102817342A (en) * 2012-08-27 2012-12-12 中铁九桥工程有限公司 Construction technology of in-situ assembly under pile foundation construction platform of double-wall steel cofferdam

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100711602B1 (en) 2006-08-11 2007-05-02 주식회사 도화종합기술공사 Temporary levee protector using crossed pile for repairing underwater structure
CN102587398A (en) * 2012-04-09 2012-07-18 中铁二十二局哈尔滨铁路建设集团有限责任公司 Double-wall cofferdam with partitioned cabins
CN109371997A (en) * 2018-12-04 2019-02-22 中铁六局集团有限公司 A kind of double-wall cofferdam and pier construction method
CN113152499A (en) * 2021-03-19 2021-07-23 国网河北省电力有限公司邢台供电分公司 Cofferdam backfill reinforced foundation and construction method
CN113684848A (en) * 2021-09-03 2021-11-23 安徽省公路桥梁工程有限公司 Construction process of steel cofferdam with deep water steep undulating rock surface
CN115162366A (en) * 2022-08-05 2022-10-11 广州市市政工程机械施工有限公司 Construction method for pre-grooving deep-water double-wall steel cofferdam on pebble bed river bed and cleaning pebbles in groove
CN115162366B (en) * 2022-08-05 2023-09-15 广州市市政工程机械施工有限公司 Construction method for pre-forming groove on pebble layer riverbed of deep water double-wall steel cofferdam and cleaning pebbles in groove

Also Published As

Publication number Publication date
JP4009028B2 (en) 2007-11-14

Similar Documents

Publication Publication Date Title
KR100904857B1 (en) A constructing method of underground structure using steel pipe and segment
JP2000192469A (en) Cofferdam device used for double wall cofferdam construction method, and double wall cofferdam construction method
JP4703233B2 (en) Building foundation reinforcement method and structure
JP4568766B2 (en) Rock fall prevention fence
JPH10183624A (en) Reinforcing fill-up wall employing retaining wall block
US8632278B2 (en) Mechanically stabilized earth welded wire facing connection system and method
US10883243B2 (en) Resilient erosion control apparatus and installation method
KR100513136B1 (en) Rock slope reinforcement structure and construction method thereof
JP4108690B2 (en) Rock fall prevention fence
JP3007241B2 (en) Temporary closing method using steel sheet pile or steel sheet pile
JP6192972B2 (en) Calvert
JPH02261122A (en) Reinforced soil retaining wall
JPH0725035U (en) Retaining wall block anchor
JP4419456B2 (en) Method of joining reinforced concrete member and steel pipe concrete
JP3580410B2 (en) Wall material reinforced earth construction method
JP2563848B2 (en) How to build a reinforced embankment
JPH0352257Y2 (en)
KR102197094B1 (en) Wall structure and method for constructing the same
JP3035693B2 (en) Tree planting stabilizer
US20240011236A1 (en) Sediment control device
JPH1082055A (en) Method of earthquake-resisting pile foundation construction
JPH0332586Y2 (en)
JP2952823B2 (en) Construction method of greening method frame
JPS6391522U (en)
JP3357631B2 (en) Construction method of slope protection work

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050405

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070115

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070522

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070723

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070828

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070831

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100907

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees