KR100222644B1 KR1019970027802A KR19970027802A KR100222644B1 KR 100222644 B1 KR100222644 B1 KR 100222644B1 KR 1019970027802 A KR1019970027802 A KR 1019970027802A KR 19970027802 A KR19970027802 A KR 19970027802A KR 100222644 B1 KR100222644 B1 KR 100222644B1
Authority
KR
South Korea
Prior art keywords
set box
assembly
conveyor
package set
unit
Prior art date
Application number
KR1019970027802A
Other languages
Korean (ko)
Other versions
KR19990003842A (en
Inventor
이수완
Original Assignee
배길성
삼성광주전자주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 배길성, 삼성광주전자주식회사 filed Critical 배길성
Priority to KR1019970027802A priority Critical patent/KR100222644B1/en
Publication of KR19990003842A publication Critical patent/KR19990003842A/en
Application granted granted Critical
Publication of KR100222644B1 publication Critical patent/KR100222644B1/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G47/00Article or material-handling devices associated with conveyors; Methods employing such devices
    • B65G47/02Devices for feeding articles or materials to conveyors
    • B65G47/04Devices for feeding articles or materials to conveyors for feeding articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65BMACHINES, APPARATUS OR DEVICES FOR, OR METHODS OF, PACKAGING ARTICLES OR MATERIALS; UNPACKING
    • B65B53/00Shrinking wrappers, containers, or container covers during or after packaging
    • B65B53/02Shrinking wrappers, containers, or container covers during or after packaging by heat
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G47/00Article or material-handling devices associated with conveyors; Methods employing such devices
    • B65G47/34Devices for discharging articles or materials from conveyor 
    • B65G47/46Devices for discharging articles or materials from conveyor  and distributing, e.g. automatically, to desired points
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G57/00Stacking of articles
    • B65G57/02Stacking of articles by adding to the top of the stack
    • B65G57/11Stacking of articles by adding to the top of the stack the articles being stacked by direct action of the feeding conveyor
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G2201/00Indexing codes relating to handling devices, e.g. conveyors, characterised by the type of product or load being conveyed or handled
    • B65G2201/02Articles
    • B65G2201/0235Containers
    • B65G2201/025Boxes

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Container Filling Or Packaging Operations (AREA)
  • Supplying Of Containers To The Packaging Station (AREA)

Abstract

본 발명은 청소기의 포장설비에 관한 것으로, 작업면적이 크게 줄어들고, 생산성을 2배로 증가되는 한편, 포장이 완성된 박스의 적재시 작업방경이 축소되어 작업능률이 향상됨은 물론, 포장된 박스가 컨베이어에서 낙하되는 경우가 크게 줄어들어 작업로스를 줄일 수 있도록 된 것이다.The present invention relates to a packaging facility of a vacuum cleaner, the work area is greatly reduced, the productivity is doubled, while the working diameter is reduced when loading the box is completed packaging, the work efficiency is improved, as well as the packed box in the conveyor Falling cases are greatly reduced to reduce the work loss.

본 발명은, 본체에 조립되는 부품을 조립셋트박스에 담아 공급하는 조립셋트공급공정부(10)와, 이 조립셋트공급공정부(10)에서 유입된 조립셋트박스를 상승시켜 후술하는 메인컨베이어(30)와 함께 이송되도록 조립자재컨베이어(40)에 적절한 시간간격으로 공급하는 업/다운자동공급장치(20)와, 이 업/다운자동공급장치(20)에서 공급된 조립셋트박스내의 부품을 집어 본체에 조립하면 다음공정으로 이송되도록 회전하는 메인컨베이어(30)와, 상기 조립셋트박스(a)를 이동시킬 수 있도록 설치된 조립자재컨베이어(40)와, 상기 메인컨베이어(30)의 소정위치에 설치되어 바디를 예열할 수 있도록 된 바디밴드예열기(50)와, 상기 메인컨베이어(30)를 따라 이송되면서 조립이 완료된 본체의 성능을 검사할 수 있도록 메인컨베이어(30)의 소정위치에 설치된 성능검사공정부(60)와, 완제품조립자재공급실(70)에서 슈티(71)를 매개로 포장물셋트박스를 성능검사공정부(60)쪽으로 이송하도록 된 포장물셋트박스이송컨베이어(80)와, 이 포장물셋트박스이송컨베이어(80)의 끝에 설치되어 메인컨베이어(30)로 포장물셋트박스를 공급할 수 있도록 된 포장물셋트박스공급장치(90)와, 상기 메인컨베이어(30)에 의해 이송된 포장물셋트박스의 중량을 검사하여 출고전에 조립부품의 누락을 방지할 수 있도록 됨과 더불어 이상이 없으면 다음공정으로 이송하도록 된 중량측정기(100)와, 이 중량측정기(100)를 통과한 포장물셋트박스가 롯트단위로 적재되는 위치까지 이송하는 포장물셋트박스이송부(200)로 이루어진 것을 특징으로 한다.The present invention, the main assembly to be described later by raising the assembly set supply process unit 10 for supplying the parts assembled in the main body in the assembly set box, and the assembly set box introduced from the assembly set supply process unit 10 ( 30) the up / down automatic supply device 20 for supplying the assembly material conveyor 40 at an appropriate time interval so as to be transported together, and the components in the assembly set box supplied from the up / down automatic supply device 20 are picked up. When assembled to the main body, the main conveyor 30 is rotated to be transferred to the next process, the assembly material conveyor 40 installed to move the assembly set box a, and the main conveyor 30 is installed at a predetermined position. The body band preheater 50, which is able to preheat the body, and the performance tester installed at a predetermined position of the main conveyor 30 so as to be transported along the main conveyor 30 to test the performance of the main assembly. The package set box transfer conveyor 80, which transfers the package set box to the performance test process unit 60 via the chute 71 from the unit 60, the finished product assembly material supply room 70, and the package set box. Installed at the end of the conveying conveyor 80 to inspect the package set box supply device 90 and the package set box conveyed by the main conveyor 30 to supply the package set box to the main conveyor (30) In order to prevent the omission of the assembly parts before leaving the factory, and if there is no problem, the weighing device 100 and the packing set box passing through the weighing device 100 are transferred to the next process until the position where the unit is loaded in a lot unit. Characterized in that consisting of the package set box transfer unit 200 to transfer.

Description

청소기의 포장설비Vacuum packaging equipment

본 발명은 청소기의 포장설비에 관한 것으로, 특히 작업면적이 크게 줄어들고, 생산성이 2배로 증가되는 한편, 포장이 완성된 박스의 적재시 작업반경이 축소되어 작업능률이 향상됨은 물론, 포장된 박스가 컨베이어에서 낙하되는 경우가 크게 줄어들어 작업손실을 줄일 수 있도록 된 청소기의 포장설비에 관한 것이다.The present invention relates to a packaging facility of a vacuum cleaner, and in particular, the work area is greatly reduced, the productivity is doubled, while the working radius is reduced when loading the finished box, the packaging efficiency is improved, as well as the packed box The present invention relates to a packaging facility for a cleaner, which reduces drastically from falling on a conveyor, thereby reducing work loss.

종래 청소기의 포장설비중 그 일예가 제1도에 도시되어 있는 바, 상부에 조립셋트박스(a)가 적재되어 있는 조립자재다이(P)에서 조립셋트박스(a)내의 부품을 집어 본체에 조립하면 다음 공정으로 이송되도록 회전하는 메인컨베이어(30)와, 상기 메인컨베이어(30)의 소정위치에 설치되어 바디를 예열할 수 있도록 된 바디밴드예열기(50)와, 상기 메인컨베이어(30)를 따라 이송되면서 조립이 완료된 본체의 성능을 검사할 수 있도록 메인컨베이어(30)의 소정위치에 설치된 성능검사공정부(60)와, 별도로 준비된 자재공급실에서 공급된 포장물셋트박스(b)를 적재하여 메인컨베이어(30)로 공급할 수 있도록 배치된 완성자재다이(Q)에서 포장물셋트박스를 메인컨베이어(30)로 이동시켜 상기 본체를 수용하여 포장을 완성한 뒤 이송된 포장물셋트박스(b)의 중량을 검사하여 출고전에 조립부품의 누락을 방지할 수 있도록 됨과 더불어 이상이 없으면 다음공정으로 이송하도록 된 중량측정기(100)와, 이 중량측정기(100)를 통과한 포장물셋트박스(b)가 롯트단위로 적재되는 위치까지 이송하는 포장물셋트박스이송부(110)로 이루어져 있다.An example of a conventional packaging device for a vacuum cleaner is shown in FIG. 1, and the parts in the assembly set box (a) are picked up from the assembly material die (P) having the assembly set box (a) loaded thereon, and assembled to the main body. The main conveyor 30 rotates to be transferred to the next process, a body band preheater 50 installed at a predetermined position of the main conveyor 30 to preheat the body, and the main conveyor 30. The main conveyor is loaded with a performance test process unit 60 installed at a predetermined position of the main conveyor 30 and a package set box (b) supplied from a separately prepared material supply room so as to check the performance of the main body completed assembling. In the finished material die Q arranged to be supplied to the 30, the package set box is moved to the main conveyor 30 to receive the main body to complete the package, and then inspect the weight of the package set box b transferred. It is possible to prevent the omission of the assembly parts before leaving the factory, and if there is no problem, the weighing apparatus 100, which is transferred to the next process, and the package set box (b) passing through the weighing apparatus 100 are loaded in the unit of lot. Package set box transfer portion 110 to transfer to the position is made up.

여기서 상기 포장물셋트박스이송부(110)는, 상기 메인컨베이어(30)와 연장된 상태로 일직선을 이루면서 상기 중량측정기(100)를 통과한 포장물셋트박스(b)가 롯트단위로 적재되는 위치까지 설치되어 있다.Here, the package set box transfer unit 110 is installed to a position in which the package set box (b) passing through the weighing unit 100 while being in a straight line with the main conveyor 30 is loaded in a lot unit. have.

따라서 상기 메인컨베이어(30)를 따라 조립자재다이(P)에 적재된 조립셋트박스(a)에서 각각의 자재를 인출하여 조립하고, 이후 상기 바디밴드예열기(50)에서 바디밴드를 인출하여 결합하면 본체조립이 완료되게 된다.Therefore, withdraw each material from the assembly set box (a) loaded on the assembly material die (P) along the main conveyor (30), and then withdraw the body band from the body band preheater (50) to combine Assembly of the body is completed.

이후 상기 성능검사공정부(60)에서 본체의 성능을 검사한 후 완성자재다이(Q)에서 포장물자재박스(b)를 옮겨 각각의 자재 사이에 본체를 수용하게 되고, 이후 완성된 포장물은 상기 중량측정기(100)에서 중량검사를 거쳐 기준 중량에 미달하거나 크게 초과하지 않으면 다음 공정 즉, 상기 포장물셋트박스이송부(110)로 이동되게 된다.Thereafter, after the performance of the main body is inspected by the performance inspection process unit 60, the packing material box (b) is moved from the finished material die (Q) to accommodate the main body between the respective materials, and the finished package is then weighed. If the weight is less than or less than the reference weight through the weight tester 100, the next step, that is to be moved to the package set box transfer unit (110).

이후 일직선을 이루는 상기 포장물셋트박스이송부(110)를 따라 이송공급된 포장물셋트박스(b)를 롯트단위로 적재할 수 있게 된다.Thereafter, the package set box (b) transported and supplied along the package set box transfer unit 110 forming a straight line may be loaded in a lot unit.

그러나 이와 같이 구성된 종래의 포장설비는, 조립작업에 따른 기계와 부자재의 공간이 많이 소요됨은 물론, 일직선으로 포장물셋트박스(b)를 이송하게 되어 포장이 완성된 박스의 적재시 작업방경이 넓어 작업능률이 저하되는 한편, 포장된 박스가 작업자의 이동반경에서 멀리 있어 컨베이어에서 낙하되는 경우가 발생하는 결점이 있었다.However, the conventional packaging facility configured as described above takes a lot of space between the machine and the subsidiary materials according to the assembling work, and also transfers the package set box (b) in a straight line, so that the working environment is wide when the box where the packaging is completed is wide. On the other hand, there was a drawback in that the packaged box fell away from the conveyor because it was far from the worker's moving radius.

이에 본 발명은 상기와 같은 제반 결점을 해결하기 위해 안출된 것으로, 조립셋트공급공정부와 업/다운자동공급장치 및 슈터등을 이용하여 조립공정중 대차나 박스를 적재할 필요가 없어 조립작업공간이 크게 줄어들고, 또 포장물셋트박스의 적재를 위해 포장물셋트박스를 이송하는 포장물셋트박스이송부를 롯트단위로 적재하는 장소를 중심으로 맴돌도록 설치함으로써, 적재 포장이 완성된 박스의 적재시 작업반경이 축소되어 작업능률이 향상됨은 물론, 포장된 박스가 컨베이어에서 낙하되는 경우가 크게 줄어들어 작업손실을 줄일 수 있도록 된 청소기의 포장설비를 제공하는 데 그 목적이 있다.Accordingly, the present invention has been made to solve the above-mentioned shortcomings, using the assembly set supply process unit and the up / down automatic supply device and the shooter, etc. There is no need to load the cart or box during the assembly process assembling work space Significantly reduced, and by installing the package set box transfer unit for transporting the package set box for loading the package set box so as to revolve around the place of loading in the unit of a lot, the working radius when loading the box with the finished package is reduced The purpose of the present invention is to provide a packaging facility for a cleaner that can improve work efficiency, as well as reduce the loss of work by greatly reducing the case where the packed box falls from the conveyor.

제1도는 종래 기술에 따른 청소기용 포장설비의 개략적인 공정흐름도.1 is a schematic process flow diagram of a packaging facility for a cleaner according to the prior art.

제2도는 종래 기술에 따른 포장설비용 포장물셋트박스이송부의 설치구조를 나타내는 설명도.2 is an explanatory view showing the installation structure of the package set box transfer unit for packaging equipment according to the prior art.

제3도는 본 발명에 따른 청소기용 포장설비의 개략적인 공정흐름도.3 is a schematic process flow diagram of a packaging facility for a cleaner according to the present invention.

제4도는 본 발명에 따른 청소기의 포장설비용 포장물셋트박스이송부의 설치구조를 나타내는 설명도이다.Figure 4 is an explanatory view showing the installation structure of the package set box transfer unit for packaging equipment of the cleaner according to the present invention.

* 도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings

a : 조립셋트박스 b : 포장물셋트박스a: Assembly set box b: Package set box

10 : 조립셋트공급공정부 20 : 업/다운자동공급장치10: assembly set supply process unit 20: up / down automatic supply device

30 : 메인컨베이어 40 : 조립자재컨베이어30: main conveyor 40: assembly material conveyor

50 : 바디밴드예열기 60 : 성능검사공정부50: body band preheater 60: performance test process

70 : 완제품조립자재공급실 71 : 슈터70: finished product assembly material supply room 71: shooter

80 : 포장물셋트박스이송컨베이어 90 : 포장물셋트박스공급장치80: package set box transport conveyor 90: package set box supply device

100 : 중량측정기 200 : 포장물셋트박스이송부100: Weigher 200: Package set box transfer unit

상기와 같은 목적을 달성하기 위한 본 발명은, 공급된 조립셋트박스내의 부품을 집어 본체에 조립하면 다음 공정으로 이송되도록 회전하는 메인컨베이어와, 이 메인컨베이어의 소정위치에 설치되어 바디를 예열할 수 있도록 된 바디밴드예열기와, 상기 메인컨베이어를 따라 이송되면서 조립이 완료된 본체의 성능을 검사할 수 있도록 메인컨베이어의 소정위치에 설치된 성능검사공정부와, 이 성능검사공정부를 기준으로 조립자재컨베이어가 설치된 반대쪽에 일정거리를 두고 배설되어 일정높이를 갖도록 된 완제품조립자재공급실에서 슈터를 매개로 포장물셋트박스를 성능검사공정부쪽으로 이송하도록 된 포장물셋트박스이송컨베이어와, 이 포장물셋트박스이송컨베이어의 끝에 설치되어 메인컨베이어로 포장물셋트박스를 공급할 수 있도록 된 포장물셋트박스공급장치와, 상기 메인컨베이어에 의해 이송된 포장물셋트박스의 중량을 검사하여 출고전에 조립부품의 누락을 방지할 수 있도록 됨과 더불어 이상이 없으면 다음공정으로 이송하도록 된 중량측정기와, 이 중량측정기를 통과한 포장물셋트박스가 롯트단위로 적재되는 위치까지 이송하는 포장물셋트박스이송부로 이루어진 구조로 되어 있다.The present invention for achieving the above object, the main conveyor is rotated so as to be transported to the next step when the assembly of the supplied assembly set box is picked up to the main body, and installed in a predetermined position of the main conveyor can preheat the body A body band preheater, a performance inspection process unit installed at a predetermined position of the main conveyor so as to inspect the performance of the assembled body while being transported along the main conveyor, and an assembly material conveyor is installed based on the performance inspection process unit. In the finished product assembly room, which is installed at a certain distance on the opposite side and has a certain height, it is installed at the end of the package set box conveying conveyor and the package set box conveying conveyor which transfers the package set box to the performance test process part through the shooter. Can be used to supply package set boxes to the main conveyor. It is possible to prevent the omission of the assembly parts before leaving the factory by inspecting the weight of the water set box supplying device and the package set box conveyed by the main conveyor, and if there is no abnormality, the weight measuring device which is to be transferred to the next process, and this weight The package set box transfer part transfers the package set box that has passed through the measuring device to the position where it is loaded in the unit of lot.

이하 본 발명에 의한 일실시예를 첨부된 예시도면을 참조하여 상세하게 설명한다.Hereinafter, an embodiment according to the present invention will be described in detail with reference to the accompanying drawings.

제3도는 본 발명에 따른 청소기용 포장설비의 개략적인 공정흐름도이고, 제4도는 본 발명에 따른 청소기의 포장설비용 포장물셋트박스이송부의 설치구조를 나타내는 설명도로서, 종래 기술을 설명하는 제1도 및 제2도와 동일한 부분에는 동일한 부호를 붙이면서 그 설명은 생략한다.Figure 3 is a schematic process flow diagram of a packaging facility for cleaners according to the present invention, Figure 4 is an explanatory view showing the installation structure of the package set box transfer unit for packaging facilities of the cleaner according to the present invention, a first description of the prior art The same reference numerals are given to the same parts as in Fig. 2 and the description thereof is omitted.

본 발명에 따른 청소기용 포장설비는, 본체에 조립되는 부품을 조립셋트박스에 담아 공급하는 조립셋트공급공정부(10)와, 이 조립셋트공급공정부(10)에서 유입된 조립셋트박스를 상승시켜 후술하는 메인컨베이어(30)와 함께 이송되도록 조립자재컨베이어(40)에 적절한 시간간격으로 공급하는 업/다운자동공급장치(20)와, 이 업/다운자동공급장치(20)에서 공급된 조립셋트박스내의 부품을 집어 본체에 조립하면 다음 공정으로 이송되도록 회전하는 메인컨베이어(30)와, 상기 조립셋트박스(a)를 이동시킬 수 있도록 설치된 조립자재컨베이어(40)와, 상기 메인컨베이어(30)의 소정위치에 설치되어 바디를 예열할 수 있도록 된 바디밴드예열기(50)와, 상기 메인컨베이어(30)를 따라 이송되면서 조립이 완료된 본체의 성능을 검사할 수 있도록 메인컨베이어(30)의 소정위치에 설치된 성능검사공정부(60)와, 이 성능검사공정부(60)를 기준으로 조립자재컨베이어(40)가 설치된 반대쪽에 일정거리를 두고 배설되어 일정높이를 갖도록 된 완제품조립자재공급실(70)에서 슈터(71)를 매개로 포장물셋트박스를 성능검사공정부(60)쪽으로 이송하도록 된 포장물셋트박스이송컨베이어(80)와, 이 포장물셋트박스이송컨베이어(80)의 끝에 설치되어 메인컨베이어(30)로 포장물셋트박스를 공급할 수 있도록 된 포장물셋트박스공급장치(90)와, 상기 메인컨베이어(30)에 의해 이송된 포장물셋트박스의 중량을 검사하여 출고전에 조립부품의 누락을 방지할 수 있도록 됨과 더불어 이상이 없으면 다음공정으로 이송하도록 된 중량측정기(100)와, 이 중량측정기(100)를 통과한 포장물셋트박스가 롯트단위로 적재되는 위치까지 이송하는 포장물셋트박스이송부(200)로 이루어져 있다.The packaging device for a cleaner according to the present invention, the assembly set supply process unit 10 for holding and supplying the parts to be assembled to the assembly set box, and the assembly set box introduced from the assembly set supply process unit 10 rises. Up and down automatic supply device 20 for supplying the assembly material conveyor 40 at an appropriate time interval to be transported with the main conveyor 30 to be described later, and the assembly supplied from the up / down automatic supply device 20 When the parts in the set box are picked up and assembled to the main body, the main conveyor 30 rotates to be transferred to the next process, the assembly material conveyor 40 installed to move the assembly set box a, and the main conveyor 30. The body band preheater 50 installed at a predetermined position of the main body 30 to preheat the body, and the main conveyor 30 to inspect the performance of the assembled body while being transported along the main conveyor 30. Performance inspection process unit 60 is installed at the position and the finished product assembly material supply room is arranged to have a certain height to be disposed at a predetermined distance on the opposite side on which the assembly material conveyor 40 is installed based on the performance inspection process unit 60 (70) ) And the package set box transfer conveyor 80 to transfer the package set box to the performance test process unit 60 via the shooter 71, and the package set box transfer conveyor 80 is installed at the end of the main conveyor (80). 30) to check the weight of the package set box supply device 90 and the package set box conveyed by the main conveyor 30 to supply the package set box to prevent the omission of the assembly parts before shipping. In addition, if there is no abnormality, the weighing set 100 which is to be transferred to the next process and the packing set foil which is transferred to the position where the package set box passing through the weighing unit 100 is loaded in a lot unit It consists of a feed unit 200.

여기서 상기 포장물셋트박스이송부(200)는, 포장물셋트박스(b)가 롯트단위로 적재하는 장소를 중심으로 맴돌도록 설치된 구조로 되어 있다.Here, the package set box transfer part 200 has a structure installed so as to revolve around a place where the package set box b is loaded in a lot unit.

또한 상기 포장물셋트박스이송부(200)가 본 발명의 실시예에서는 90도 방향으로 방향이 전환되어 적재장소를 중심으로 맴도는 경우만 도시되어 있으나, 원호형상으로 방향전환컨베이어를 설치하게 되면 원형의 이송부를 제공할 수 있다.In addition, in the embodiment of the present invention, the package set box transfer part 200 is shown only when the direction is turned around in the 90 degree direction and revolves around the loading place, but when the direction conversion conveyor is installed in an arc shape, the circular transfer part is provided. Can provide.

이와같이 구성된 본 발명의 작용효과를 설명한다.The effects of the present invention configured as described above will be described.

따라서 상기 조립셋트공급공정부(10)에서 각각의 부재를 넣은 조립셋트박스(a)를 업/다운자동공급장치(20)로 밀어넣어주면, 이 업/다운자동공급장치(20)는 상기 조립셋트박스(a)를 상기 메인컨베이어(30)와 조립자재컨베이어(40)를 따라 성능검사공정부(60)로 이송하게 되는 바, 이때 상기 조립셋트박스(a)의 자재를 인출하여 본체에 결합하고 바디밴드예열기(50)에서 바디밴드를 인출하여 결합하면 본체조립이 완료되면서 이송하게 된다.Therefore, when the assembly set box (a) in which each member is inserted in the assembly set supply process unit 10 is pushed into the up / down automatic supply device 20, the up / down automatic supply device 20 is assembled to the assembly. The set box (a) is transferred to the performance inspection process unit 60 along the main conveyor 30 and the assembly material conveyor 40. At this time, the material of the assembly set box (a) is taken out and coupled to the main body. And take out the body band from the body band preheater 50 to combine and transfer the body assembly is completed.

이후 상기 성능검사공정부(60)에서 본체의 성능을 검사한 후 성능검사공정부(60)의 우측에 위치된 메인컨베이어(30)로 이송될 때 이 성능검사공정부(60)를 기준으로 조립자재컨베이어(40)가 설치된 반대쪽에 일정거리를 두고 배설되어 일정높이를 갖도록 된 완제품조립자재공급실(70)에서 슈터(71)를 매개로 포장물셋트박스를 성능검사공정부(60)쪽으로 이송하도록 된 포장물셋트박스이송컨베이어(80)와 포장물셋트박스공급장치(90)에 의해 방향전환을 하여 성능검사공정부(60)의 우측에 위치된 메인컨베이어(30)로 공급된 포장물셋트박스(b)에 본체를 넣어 중량측정기(100)로 이송하게 된다.Thereafter, after the performance test process unit 60 checks the performance of the main body, it is assembled based on the performance test process unit 60 when transported to the main conveyor 30 located on the right side of the performance test process unit 60. In the finished product assembly material supply room 70, which is disposed at a predetermined distance on the opposite side where the material conveyor 40 is installed and has a predetermined height, the package set box is transferred to the performance test process unit 60 via the shooter 71. The package set box transfer conveyor 80 and the package set box supply device 90 are switched to the package set box (b) supplied to the main conveyor 30 located on the right side of the performance test process unit 60. The main body is transferred to the weighing apparatus 100.

이후 상기 중량측정기(100)는, 상기 메인컨베이어(30)에 의해 이송된 포장물셋트박스의 중량을 검사하여 출고전에 조립부품의 누락을 방지할 수 있도록 됨과 더불어 이상이 없으면 다음공정으로 이송하고, 이 이송은 포장물셋트박스이송부(200)에 의해 포장물셋트박스가 롯트단위로 적재되는 위치까지 이송하게 된다.Thereafter, the weighing apparatus 100 may check the weight of the package set box transferred by the main conveyor 30 to prevent the omission of the assembly parts before leaving the factory, and if there is no abnormality, transfer the process to the next step. The transfer is carried by the package set box transfer unit 200 to a position where the package set box is loaded in a lot unit.

상기 롯트단위의 적재장소를 중심으로 맴돌도록 설치된 포장물셋트박스이송부(200)를 따라 공급되는 포장물셋트박스(b)를 적은 이동량으로 롯트단위로 적재할 수 있게 된다.The package set box (b) supplied along the package set box transfer unit 200 installed to revolve around the loading place of the lot unit can be loaded in a lot unit with a small amount of movement.

또한 상기 적재장소를 중심으로 맴돌도록 설치된 포장물셋트박스이송부(200)를 따라 포장물셋트박스(b)가 공급되어 작업자와의 거리가 가까우므로 포장물셋트박스(b)가 떨어지는 경우가 크게 줄어들게 된다.In addition, the package set box (b) is supplied along the package set box transfer part 200 installed to revolve around the loading place, so that the distance to the worker is close, so that the case of the package set box (b) falls greatly.

이에 따라 불필요한 작업로스를 예방할 수 있음은 미루어 짐작할 수도 있을 것이다.As a result, it is possible to guess that unnecessary work loss can be prevented.

이상 설명한 바와 같이 본 발명에 의하면, 적재를 위해 포장물셋트박스를 이송하는 포장물셋트박스이송부를 롯트단위로 적재하는 장소를 중심으로 맴돌도록 설치함으로써, 적재 포장이 완성된 박스의 적재시 작업방경이 축소되어 작업능률이 향상됨은 물론, 포장된 박스가 컨베이어에서 낙하되는 경우가 크게 줄어들어 작업로스를 줄일 수 있어 조립생산성이 향상되는 효과가 있다.As described above, according to the present invention, by installing the package set box transfer unit for transporting the package set box for loading so as to revolve around the place of loading in the unit of the lot, the working environment is reduced when loading the box is completed packaging As well as improving the work efficiency, the case where the packaged box falls off the conveyor is greatly reduced, thereby reducing the work loss, thereby improving the assembly productivity.

Claims (2)

공급된 조립셋트박스내의 부품을 집어 본체에 조립하면 다음공정으로 이송되도록 회전하는 메인컨베이어와, 이 메인컨베이어의 소정위치에 설치되어 바디를 예열할 수 있도록 된 바디밴드예열기와, 상기 메인컨베이어를 따라 이송되면서 조립이 완료된 본체의 성능을 검사할 수 있도록 메인컨베이어의 소정 위치에 설치된 성능검사공정부와, 이 성능검사공정부를 기준으로 조립자재컨베이어가 설치된 반대쪽에 일정거리를 두고 배설되어 일정높이를 갖도록 된 완제품조립자재공급실에서 슈터를 매개로 포장물셋트박스를 성능검사공정부쪽으로 이송하도록 된 포장물셋트박스이송컨베이어와, 이 포장물셋트박스이송컨베이어의 끝에 설치되어 메인컨베이어로 포장물셋트박스를 공급할 수 있도록 된 포장물셋트박스공급장치와, 상기 메인컨베이어에 의해 이송된 포장물셋트박스의 중량을 검사하여 출고전에 조립부품의 누락을 방지할 수 있도록 됨과 더불어 이상이 없으면 다음공정으로 이송하도록 된 중량측정기와, 이 중량측정기를 통과한 포장물셋트박스가 롯트단위로 적재되는 위치까지 이송하는 포장물셋트박스이송부로 이루어진 것을 특징으로 하는 청소기의 포장설비.The main conveyor rotates to be transported to the next process when the parts in the supplied assembly set box are picked up and assembled to the main body, a body band preheater installed at a predetermined position of the main conveyor to preheat the body, and the main conveyor along the main conveyor. In order to inspect the performance of the main body after assembly, the performance test process part installed at a predetermined position of the main conveyor and the assembly material conveyor are installed at a certain distance from the opposite side where the assembly material conveyor is installed to have a certain height. The package set box transfer conveyor, which transfers the package set box to the performance test process part through the shooter in the finished product assembly material supply room, and is installed at the end of the package set box transfer conveyor to supply the package set box to the main conveyor. To the package set box supply device and the main conveyor By checking the weight of the package set box transported by the user, it is possible to prevent the omission of the assembly parts before leaving the factory. If there is no problem, the weighing unit which is transferred to the next process and the package set box that has passed this weighing unit are in the unit of lot. Packaging equipment for a vacuum cleaner, characterized in that consisting of a package set box transfer unit for transporting up to the position to be loaded. 제1항에 있어서, 상기 포장물셋트박스이송부는, 포장물셋트박스가 롯트 단위로 적재하는 장소를 중심으로 맴돌도록 설치된 것을 특징으로 하는 청소기의 포장설비.According to claim 1, wherein the package set box transfer unit, the packaging equipment of the vacuum cleaner, characterized in that installed so as to revolve around the place to place the package set box in a lot unit.
KR1019970027802A 1997-06-26 1997-06-26 Packing apparatus for cleaning machine KR100222644B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019970027802A KR100222644B1 (en) 1997-06-26 1997-06-26 Packing apparatus for cleaning machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019970027802A KR100222644B1 (en) 1997-06-26 1997-06-26 Packing apparatus for cleaning machine

Publications (2)

Publication Number Publication Date
KR19990003842A KR19990003842A (en) 1999-01-15
KR100222644B1 true KR100222644B1 (en) 1999-10-01

Family

ID=19511493

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019970027802A KR100222644B1 (en) 1997-06-26 1997-06-26 Packing apparatus for cleaning machine

Country Status (1)

Country Link
KR (1) KR100222644B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101915864B1 (en) * 2016-12-26 2018-11-06 주식회사 한화 System and method for removing safety pin and detonator clip of dual purpose submunition

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101915864B1 (en) * 2016-12-26 2018-11-06 주식회사 한화 System and method for removing safety pin and detonator clip of dual purpose submunition

Also Published As

Publication number Publication date
KR19990003842A (en) 1999-01-15

Similar Documents

Publication Publication Date Title
KR100290152B1 (en) Manufacturing system
CN109649760A (en) A kind of LED board detection baling line
EP0167404A3 (en) Nuclear waste packaging facilities
CN108521207A (en) Motor chassis assembles producing line
KR100222644B1 (en) Packing apparatus for cleaning machine
JP7381300B2 (en) Packing system and method
JPH0395026A (en) Unloader for bottle
KR100227220B1 (en) Test process part of performance of wrapping apparatus for cleaner
KR19980066648A (en) Product inspection system of home appliance assembly line
JP2000142968A (en) Individual feeder with line independent carrying part
CN217918654U (en) Automatic weighing and loading device for electronic commerce logistics
KR102650184B1 (en) Apparatus for packing laundry drying stand parts automatically
KR200159356Y1 (en) Box feeding apparatus for packing apparaus for cleaning m/c
CN219029881U (en) Bottle spraying system
KR100226414B1 (en) Box feeding apparatus for packing apparatus for cleaning m/c
JPH0834234B2 (en) Wafer transfer device
KR950006130Y1 (en) Soldering device of semiconduct device
CN213832404U (en) Automatic filling equipment of reloading
JP3819251B2 (en) Package transport apparatus and transport method
CN208539758U (en) Motor chassis assembles producing line
JP2780052B2 (en) Automatic packaging method
JPH1159616A (en) Egg container transporting equipment and egg processor using the same
JPS61244431A (en) Automatic assembling apparatus for parts
JPH08337213A (en) Apparatus for filling and transferring tray of packaged food
KR20230039945A (en) bulk bag stocker

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee