KR0128103B1 - Pile cap structure and connecting structure for pile cap and base plate - Google Patents

Pile cap structure and connecting structure for pile cap and base plate

Info

Publication number
KR0128103B1
KR0128103B1 KR1019940001379A KR19940001379A KR0128103B1 KR 0128103 B1 KR0128103 B1 KR 0128103B1 KR 1019940001379 A KR1019940001379 A KR 1019940001379A KR 19940001379 A KR19940001379 A KR 19940001379A KR 0128103 B1 KR0128103 B1 KR 0128103B1
Authority
KR
South Korea
Prior art keywords
pile
pile shoe
tension
shoe
plate
Prior art date
Application number
KR1019940001379A
Other languages
Korean (ko)
Other versions
KR950023808A (en
Inventor
라병준
Original Assignee
라병준
주식회사영풍콘크리트
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 라병준, 주식회사영풍콘크리트 filed Critical 라병준
Priority to KR1019940001379A priority Critical patent/KR0128103B1/en
Publication of KR950023808A publication Critical patent/KR950023808A/en
Application granted granted Critical
Publication of KR0128103B1 publication Critical patent/KR0128103B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/72Pile shoes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0046Production methods using prestressing techniques
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Abstract

When the support plate(200,300) is completed to be fabricated on the pile shoe(6), the tension tool(500) is provided on the one support plate(300) and the PC steel rod(91) is increased by this tension tool. As the PC steel rod is increased with the tension tool, its passage is as follows : Tension shaft(502), tension plate(503), binding band(505), support plate(300), penetrating body of combining member(B), fastening body of combining member, pile shoe(6) and PC steel rod(91)

Description

말뚝슈 및 말뚝슈와 지지판과의 조합구조Pile shoe and combination structure of pile shoe and support plate

제1도는 종래의 말뚝슈의 사시도.1 is a perspective view of a conventional pile shoe.

제2도는 제1도의“가”부분 확대도.FIG. 2 is an enlarged view of a part of FIG.

제3도는 제2도의 A-A 선 단면도.3 is a cross-sectional view taken along the line A-A of FIG.

제4도는 제2도의 B-B 선 단면도.4 is a cross-sectional view taken along the line B-B in FIG.

제5도는 제2도의 C-C 선 단면도.5 is a cross-sectional view taken along the line C-C of FIG.

제6도는 종래의 말뚝슈의 다른 실시예도.6 is another embodiment of a conventional pile shoe.

제7도는 제6도의“나”부분 확대도.FIG. 7 is an enlarged view of part “I” of FIG.

제8도는 제7도의 D-D 선 단면도.8 is a cross-sectional view taken along the line D-D of FIG.

제9도는 제7도의 E-E 선 단면도.9 is a sectional view taken along the line E-E of FIG.

제10도는 제7도의 F-F 선 단면도.10 is a cross-sectional view taken along the line F-F of FIG.

제11도는 종래의 말뚝슈의 제조 공정도.11 is a manufacturing process diagram of a conventional pile shoe.

제12도는 종래 말뚝슈의 제조 공정도의 다른 실시예도.12 is another embodiment of the manufacturing process diagram of the conventional pile shoe.

제13도는 말뚝을 만들기 위한 철근롱의 사시도.13 is a perspective view of a reinforcing bar for making a pile.

제14도는 말뚝슈에 장착한 철근롱을 하몰드에 수납하고 있는 상태의 사시도.14 is a perspective view of a state in which a reinforcing bar mounted on a pile shoe is stored in a lower mold.

제15도는 말뚝슈에 PC 강봉을 장착하는 방법을 도시한 사시도.FIG. 15 is a perspective view illustrating a method of mounting a PC steel rod to a pile shoe. FIG.

제16도는 제15도의“다”부분 확대도.FIG. 16 is an enlarged view of the portion of FIG.

제17도는 제16도의 G-G 선 단면도.FIG. 17 is a cross-sectional view taken along line G-G of FIG.

제18도는 말뚝슈에 PC 강봉을 장착하는 방법을 도시한 사시도.18 is a perspective view showing a method of mounting a PC steel rod to the pile shoe.

제19도는 제18도의“라”부분 확대도.19 is an enlarged view of the "d" part of FIG.

제20도는 제19도의 H-H 선 단면도.FIG. 20 is a sectional view taken along the line H-H in FIG. 19. FIG.

제21도는 말뚝슈에 마구리판 및플레이트를 조립하는 공정도.21 is on the stakes Process diagram for assembling the plate.

제22도는플레이트에 인장장치의 밴드를 결합하는 공정도.22 is Process diagram for joining band of tensioning device to plate.

제23도는 말뚝슈에 인장볼트를 장착한 상태의 평면도.23 is a plan view of the tension bolt is mounted on the pile shoe.

제24도는 제23도의 K-K 선 단면도.24 is a cross-sectional view taken along the line K-K in FIG.

제25도는 말뚝슈에 인장장치를 장착한 상태도.25 is a state in which the tension device is mounted on the pile shoe.

제26도는 인장장치로 인장할 때의 PC 강봉과 인장볼트에 작용하는 인장력의 작용방향을 나타내는 개념도.Fig. 26 is a conceptual diagram showing the direction of action of the tensile force acting on the PC steel rod and the tension bolt when tensioning with the tensioning device.

제27도는 본원 발명에 따른 말뚝슈의 사시도.27 is a perspective view of a pile shoe according to the present invention.

제28도는 제27도의“마”부분 확대도.FIG. 28 is an enlarged view of the section "e" of FIG.

제29도는 제28도의 L-L 선 단면도.FIG. 29 is a cross-sectional view taken along line L-L in FIG. 28. FIG.

제30도는 제28도의 M-M 선 단면도.30 is a cross-sectional view taken along the line M-M of FIG.

제31도는 제28도의 N-N 선 단면도.FIG. 31 is a sectional view taken along the line N-N in FIG. 28;

제32도는 본원 발명에 따른 말뚝슈의 다른 실시예도.32 is another embodiment of the pile shoe according to the present invention.

제33도는 제32도의“바”부분 확대도.33 is an enlarged view of the portion “bar” of FIG.

제34도는 제33도의 O-O 선 단면도.34 is a cross-sectional view taken along the line O-O of FIG.

제35도는 제33도의 P-P 선 단면도.35 is a sectional view taken along the line P-P of FIG.

제36도는 제33도의 Q-Q 선 단면도.36 is a cross-sectional view taken along line Q-Q of FIG.

제37도는 본원 발명에 따른 말뚝슈의 제조 공정도.37 is a manufacturing process of the pile shoe according to the present invention.

제38도는 본원 발명에 따른 다른 말뚝슈의 제조 공정도.38 is a manufacturing process diagram of another pile shoe according to the present invention.

제39도는 본원 발명에 따른 말뚝슈에 PC 강봉과 말뚝슈를 장착한 상태의 부분도.Figure 39 is a partial view of the PC steel rod and the pile shoe mounted on the pile shoe according to the present invention.

제40도는 제39도의 R-R 선 단면도.40 is a cross-sectional view taken along the line R-R of FIG. 39;

* 도면의 주요부분에 대한 부호 설명* Explanation of symbols on the main parts of the drawings

1, 6 : 말뚝슈 11, 66 : 말뚝슈판체1, 6: pile shoe 11, 66: pile shoe plate

13, 67 : 강봉장착부 14 : 인장볼트체결부13, 67: steel rod mounting portion 14: tension bolt connection portion

15, 69 : 연통로 68 : 결합부배장착부15, 69: communication path 68: coupling part mounting part

본 발명은 토목공사나 건축공사를 함에 있어 구조물의 하중을 지지지반에 분산 또는 전달시키기 위한 기초공사에 사용되는 말뚝의 선단이나 두부 또는 말뚝과 말뚝과의 연결부에 장착하게 되는 말뚝슈와 이 말뚝슈를 인장 지지판과 결합하는 조합구조에 관한 것이다.The present invention is a pile shoe and the pile shoe to be mounted to the tip or head of the pile or the connection between the pile and the pile used in the foundation work for distributing or transmitting the load of the structure to the support ground in civil engineering or building construction It relates to a combination structure to engage the tension support plate.

말뚝(Pile)은 지반이 견고하지 못하여 기초판을 견고한 지층에 직접 지지시킬 수 없을 때에 하중을 지반 전체에 분포시키든가 혹은 깊은 층에 전달시킴으로써 불충분한 지반 조건을 개선하기 위하여 사용하게 되는 것으로, 그 종류로는 나무말뚝, 강말뚝(steel pile), 그리고 콘크리트에 프리스트레스(prestress)를 주어 말뚝의 휨에 대한 저항력을 높이도록 만들어진 PC말뚝(프리텐숀 방식 원심력 PC말뚝 : pretensioned spun concrete piles)과 PHC말뚝(프리텐숀 방식 원심력 고강도 콘크리트 말뚝 : pretensioned spun High strength concerte piles)(이하 프리스트레스를 주어 만드는 말뚝을“PC말뚝”이라 칭함) 등이 있다. 그리고 이와 같이 지반기초 작업에 사용되는 말뚝을 만들 때에는 말뚝머리와 말뚝 끝에 말뚝슈(pile shoe)를 끼움으로서, 햄머와 같은 말뚝박기 기계로 지질이 굳거나 자갈이나 돌이 섞인 지반에 말뚝을 때려 박을 때에는 상기 말뚝슈는 말뚝의 파손을 방지하면서 말뚝을 소요의 깊이에까지 충분히 관입되는 강도를 유지할 수 있도록 하는 것이며, 특히 PC말뚝용 말뚝슈는, 말뚝에 프리스트레스(prestress)를 가하기 위하여 PC강봉을 걸어 잡아 당기는데 사용되는 인장고정 지그(jig)로서의 용도를 겸하게 되는 것이다. 말뚝슈(pile shoe)에는 말뚝의 끝단에 끼우는 마밀라슈(mamilla shoe), 말뚝머리에 끼우는 두부보강캡(head cap), 하나의 말뚝과 다른 하나의 말뚝을 연결하고자 할 때에 연결구의 기능을 겸하는 앵커링(anchor ring)과 같은 종류가 있으며, 제1도에서 제5도까지 에는 종래의 PC말뚝에 사용되는 말뚝슈로서 마밀라슈 또는 두부보강캡을, 그리고 제6도에서 제10도까지에는 종래의 PC말뚝의 말뚝슈로서 하나의 PC말뚝에 다른 하나의 PC말뚝을 연결할 때에 이들 사이에 연결 부재로 사용되는 앵커링을 각각 사시도 및 평면도로 도시하고 있다.Piles are used to improve inadequate ground conditions by distributing loads throughout the ground or by transferring it to deeper layers when the ground is not strong and the base plate cannot be supported directly on a solid bed. Types include PC piles (steel piles) and PC piles (pretensioned spun concrete piles) and PHC piles made to give resistance to pile bending by giving prestress to concrete. Pretensioned spun high strength concerte piles (hereinafter referred to as "PC piles"). And when making piles used for ground foundation work, by putting a pile shoe at the end of the pile head and piles, the pile pile machine such as hammer hammers the pile on the ground where the soil is hardened or gravel or stone is mixed. When the pile shoe is to prevent the damage of the pile to maintain the strength enough to penetrate the pile to the required depth, in particular, the pile shoe for PC pile, to hold the PC steel rod to apply prestress to the pile It also serves as a tension fixing jig used for pulling. The pile shoe has the function of a connector when connecting a pile to a pile, a mamilla shoe fitted to the end of the pile, a head cap fitted to the pile head, and a pile There is the same kind of anchor ring, and in Fig. 1 to Fig. 5, it is a pile shoe used in conventional PC piles. The anchoring used as a connecting member between them when connecting another PC pile to one PC pile as a pile shoe of the PC pile is shown in a perspective view and a plan view, respectively.

말뚝슈(1)는 말뚝의 강도를 유지하도록 하며, 특히 PC말뚝을 제조할 때에 콘크리트에 프리스트레스를 가하기 위하여 사용되는 PC강봉을 끼워 장착한 다음 이 PC강봉을 잡아 당기는 프리스트레스 공정을 수행하는 기능을 갖도록 하는 것으로, 원환형(圓環形) 또는 원통형(圓筒形)으로하여 판체(11)를 형성하고, 필요에 따라 판체(11)의 원둘레 가장자리를 따라 강도보강밴드(H)를 형성 고정하고 있다. 그리고 판체(11)는 PC강봉을 장착하기 위한 강봉장착부(13)와, 인장볼트(B)를 나사체결하기 위한 인장볼트체결부(14)를 형성하며, 강봉장착부(13)와 인장볼트체결부(14)와의 사이에는 연통로(15)를 가공하여 이 연통로(15)는 PC강봉의 조립통로로 사용하도록 구성하고 있다. 강봉장착부(13)는 PC강봉(91)의 로드(91A) 부분이 끼워지는 로드관통구멍(13A)과 PC강봉(91)의 헤드(91B)가 걸려 안착되는 헤드시트부(13B)로 되고, 인장볼트체결부(4)에는 인장볼트(B)의 숫나사부와의 나사체결이 가능하도록 암나사(14N)를 가공하고 있으며, 연통로(15)는 PC강봉(91)의 로드(91A)이 충분히 통과할 수 있는 크기로 하여 가공하고 있다.The pile shoe (1) is to maintain the strength of the pile, in particular, when manufacturing the PC pile is fitted with a PC steel rod used to apply prestress to the concrete, and then have a function to perform the pre-stress process to pull the PC steel rod The plate 11 is formed in an annular or cylindrical shape, and the strength reinforcing band H is formed and fixed along the circumferential edge of the plate 11 as necessary. . The plate body 11 forms a steel rod mounting portion 13 for mounting a PC steel rod, and a tension bolt coupling portion 14 for screwing the tension bolt B, and the steel rod mounting portion 13 and the tension bolt coupling portion. The communication path 15 is processed between (14), and this communication path 15 is comprised so that it may be used as an assembly path of PC steel bars. The steel rod mounting portion 13 includes a rod through hole 13A into which the rod 91A portion of the PC steel rod 91 is fitted and a head seat portion 13B on which the head 91B of the PC steel rod 91 is caught and seated. The female bolt 14N is machined into the tension bolt fastening portion 4 so as to allow screwing with the male thread portion of the tension bolt B, and the communication path 15 has sufficient rod 91A of the PC steel bar 91. It is processed to the size that can pass.

제11도에는 PC말뚝용 말뚝슈로서 마밀라슈(또는 두부캡)의 말뚝슈(1)를 가공하는 가공 공정도를 평면도(상단도면)와 단면도(하단도면)로 도시하고 있다. 마밀라슈(또는 두부캡)의 판체는 앵커링의 판체 보다는 비교적 작은 두께(8∼12t)의 철판을 사용하여 주로 프레스작업에 의해 강봉장착부 및 인장볼트체결부를 가공하고 있는 것으로 공정순에 따라 가공 방법을 살펴보기로 한다. 판체(11)에 강봉장착부(13)를 형성하기 위하여, 강봉로드(91A)가 관통할 수 있는 크기를 갖는 로드관통구멍(13A)과, PC강봉(91)이 관통할 수 있는 크기로 하여 인장볼트체결부(14)가 되는 암나사를 가공하기 위한 나사가공구멍(14E)을 각각 피어싱(piercing) 가공(가-1, 가-2)을 한 다음, 상기 로드관통구멍(13A)과 나사가공구멍(13A,14E)에 엠보싱(Embossing)가공(나-1, 나-2)을 하므로서, 로드관통구멍(13A)의 상단부에는 PC강봉(91)의 헤드(91B)가 걸려 장착되는 부위인 헤드시트부(13B)로 가공되어 강봉장착부(3)가 형성되고, 나사가공구멍(14E)은 암나사부를 가공하기에 충분한 길이로 되어, 이 나사가공구멍(14E)에는 태피 가공(다-1, 다-2)으로 암나사(14N)를 가공하므로서 인장볼트(B)를 나사체결할 수 있는 인장볼트체결부(14)가 형성되는 것이며, 이와 같이 형성된 인장볼트체결부(14)와 강봉장착부(13)와의 사이를 밀링기로 밀링 가공하여 PC강봉(91)의 로드(91A)가 통과할 수 있는 크기로 하여 연통로(15)를 형성한다.(라-1,라-2)11 shows a processing process diagram for processing the pile shoe 1 of mamilache (or the head cap) as a pile shoe for PC piles in a plan view (upper view) and a cross section (lower view). The plate of mamilache (or tofu cap) is mainly used to process steel rod fitting and tension bolt fastening part by press work using iron plate of relatively small thickness (8 ~ 12t) than the plate of anchoring. Let's look at it. In order to form the steel rod mounting portion 13 in the plate body 11, the rod through hole 13A having a size through which the steel rod rod 91A can penetrate, and the PC steel rod 91 can be penetrated in tension. After the piercing processing (A-1 and T-2) of the threaded holes 14E for machining the female thread to be the bolted portion 14, respectively, the rod through hole 13A and the threaded hole are provided. Embossing (B-1 and B-2) on the 13A and 14E, so that the upper end of the rod through hole 13A is the head seat which is the part where the head 91B of the PC steel bar 91 is caught. The steel rod mounting portion 3 is formed by the portion 13B, and the threaded hole 14E has a length sufficient to process the female threaded portion. 2) A tension bolt fastening portion 14 capable of screwing the tension bolt B is formed by machining the female thread 14N, and the tension bolt fastening portion 14 thus formed is formed. ) And the steel rod mounting portion 13 is milled by a milling machine to form a communication path 15 to a size through which the rod 91A of the PC steel rod 91 can pass. )

제12도에는 PC말뚝용 말뚝슈로서 앵커링 말뚝슈를 가공하는 가공 공정도를 평면도(상단부)와 단면도(하단부)로 도시하고 있다. 앵커링 말뚝슈는 비교적 두께가 두꺼운(12∼16t)철판을 사용하여 주로 절삭작업에 의해 판체(13E)를 가공하고 있는 것으로 공정순서에 따라 가공 방법을 살펴보기로 한다. 말뚝슈판(11)에 강봉장착부(3)를 형성하기 위하여 강봉로드(91A)가 관통할 수 있는 크기를 갖는 로드관통구멍(13A)과, PC강봉(91)이 관통할 수 있는 크기로 하여, 인장볼트체결부(14)의 암나사를 가공하기 위한 나사가공구멍(14E)을 각각 드릴링 가공(마-1,마-2)한 다음, 상기 로드관통구멍(13A)의 상단부를 카운터 싱킹(counter sinking)가공을 하여 테이퍼가 크고 단면이 접시모양의 구멍을 형성하므로서, 이렇게 로드관통구멍(13A)의 상단부에 형성된 이 접시모양의 구멍은 PC강봉(91)의 헤드(91B)가 걸려 장착되는 부위인 헤드시트부(13B)가 되는 것이다. (바-1,바-2) 그리고 상기 나사가공구멍(14E)에는 태핑가공(사-1,사-2)을 하여 암나사(14N)를 가공하므로서 이 암나사(14)는 인장볼트(B)를 나사 체결하는 인장볼트체결부(14)가 되는 것이며, 이와 같이 형성된 인장볼트체결부(14)와 강봉장착부(13)와의 사이를 밀링가공하여 PC강봉(91)의 로드(91A)가 통과할 수 있는 크기로 하여 연통로(15)를 형성한다. (아-1,아-2)In FIG. 12, the process drawing which processes an anchoring pile shoe as a pile shoe for PC piles is shown by the top view (upper part) and sectional drawing (lower end part). The anchoring pile shoe is mainly used to cut the plate body 13E by cutting, using a relatively thick (12 to 16t) iron plate. In order to form the steel rod mounting portion 3 in the pile shoe plate 11, the rod through hole 13A having a size that the steel rod rod 91A can penetrate, and the size of the PC steel rod 91 can penetrate, After drilling (M-1 and M-2), respectively, the threaded holes 14E for machining the female threads of the tension bolt fastening portion 14, and countersink the upper end of the rod through hole 13A. This tapered hole is formed at the upper end of the rod through hole 13A by forming a tapered, cross-sectional, plate-shaped hole, which is a site where the head 91B of the PC steel bar 91 is caught. It becomes the head seat | seat part 13B. (Bar-1, Bar-2) The female thread 14 is provided with a tensioning bolt B by tapping (thread-1 and thread-2) to the female threaded hole 14E. It becomes the tension bolt fastening portion 14 to be screwed, and milling between the tension bolt fastening portion 14 and the steel rod mounting portion 13 formed in this way can pass the rod (91A) of the PC steel bar (91). The communication path 15 is formed in the size which is. (Ah-1, ah-2)

제13도에서 제26도까지에는 위의 말뚝슈를 사용하여 말뚝을 제조하는 공정도를 도시하고 있다. 여러개의 PC강봉(91, 철근)을 철근 편성기에 의해 편성하여 만든 철근롱(90:鐵筋籠)을 하몰드(100)안에 끼워넣고 철근롱(90)의 양쪽 끝단부에 말뚝슈(1)를 조립한다. 철근롱(90)에 말뚝슈(1)를 조립할 때에는 먼저 PC강봉(91)을 인장볼트체결부(14)에 끼운 다음(제15도, 제16도, 제17도), 상기 PC강봉(91)을 강봉장착부(3)쪽으로 밀어 넣으면, PC강봉(91)의 로드(91B)부분이 말뚝슈(1)의 연통로(15)를 따라 이동하여 PC강봉(91)의 헤드(91B)부분은 헤드시트부(32)에 걸리는 상태로 PC강봉(91)은 강봉장착부(3)에 자리잡게 된다.(제18도, 제19도, 제20도)13 to 26 illustrate a process diagram for manufacturing a pile using the pile shoe above. Reinforcing bars (90: 鐵 筋 籠) made by knitting a plurality of PC steel bars (91, reinforcing bars) by a rebar knitting machine are inserted into the lower mold 100 and pile shoes (1) at both ends of the reinforcing bars (90). Assemble When assembling the pile shoe 1 on the reinforcing rod 90, first, the PC steel bar 91 is inserted into the tension bolt fastening portion 14 (FIG. 15, 16, 17), and the PC steel bar 91 ) Is pushed toward the steel rod mounting portion 3, the rod 91B portion of the PC steel rod 91 moves along the communication path 15 of the pile shoe 1, and the head 91B portion of the PC steel rod 91 The PC steel bar 91 is settled in the steel rod mounting part 3 in the state which caught by the head seat part 32. (FIG. 18, 19, 20)

위와 같이 PC강봉(91)이 강봉장착부(3)에 장착되면, PC말뚝에 프리스트레스를 가하기 위하여 철근롱(90)을 인장하여야 하는 것으로, 철근롱(90)의 어느 한쪽은 인장반대측으로 하여 (제21도에서 보아 우측),이 인장반대측 말뚝슈(1)에 지지판(200,마구리판)을 밀착시키고, 이 지지판(200)에 가공된 관통구멍(201)쪽에서 인장볼트(B)를 관통시키며 이렇게 지지판(200)의 관통구멍(201)을 관통하여 돌출되어 나온 연장볼트(B)를 다시 말뚝슈(1)에 형성된 인장볼트체결부(14)에 맞춰 나사체결을 하며, 철근롱(90)의 다른 한쪽은 인장측으로 하여 (제21도에 보아 왼쪽)이 인장측 말뚝슈(1)에는 지지판(300,플레이어)를 밀착시키고, 이 지지판(300)에 가공된 관통구멍(301)쪽에서 인장볼트(B)를 관통시킨 다음 다시 상기 인장볼트(B)를 말뚝슈(1)의 인장볼트체결부(14)에 맞춰 나사체결을 하면 (제21도, 제22도), 제24도에 도시된 단면도와 같이 양쪽 말뚝슈(1)는 철근롱(90)을 장착한 상태로 지지판(200, 300)에 단단히 결합됨으로서, 말뚝슈(1)의 강봉장착부(13)안에 수납되어 있는 철근롱(90)의 PC강봉(91)은 인장될 수 있는 상태로 조립되어 지는 것이며, 이렇게 조립된 인장측 말뚝슈(1)에 조립된 지지판(300)에는 다시 인장장치(500)를 결합한다. (제25도) 인장장치(500)는 제21도 및 제22도에 도시된 바와 같이, 마구리판(501), 인장축(502), 인장판(503), 체결너트(504), 연결밴드(505)로 구성되어 있는 것으로, 마구리판(501)은 하몰드(100)의 한쪽에 고정되어 있으며, 이 마구리판 (501)의 중앙에는 관통구멍을 가공하여 이 관통구멍을 통하여 나사가 가공된 인장축(502)을 전후 이동이 가능하게 조립한다. 그리고 위와 같이 조립된 인장축(502)의 한쪽 끝단(마구리판(501)을 중심으로 하여 몰드안쪽)에는 인장판(503)을 고정하고, 인장축(502)의 다른 한쪽에는 체결너트(504)를 나사 조립하고 있으며, 상기 인장판(503)과 인장측 말뚝슈(1)에 결합하고 있는 지지판(300)과는 연결밴드(505)로 결합한다.When the PC steel bar 91 is mounted to the steel rod mounting portion 3 as described above, the reinforcing rod 90 must be tensioned to apply prestress to the PC pile, and either side of the reinforcing rod 90 is placed opposite to the tension side (the As seen from the right in FIG. 21, the support plate 200 (curling plate) is brought into close contact with the tension opposite side shoe shoe 1, and the support plate 200 penetrates the tension bolt B from the side of the through hole 201 processed in the support plate 200. An extension bolt B protruding through the through-hole 201 of the 200 is screwed in accordance with the tension bolt fastening portion 14 formed in the pile shoe 1 again, and the other of the rebar long 90 One side is the tension side (left side as shown in FIG. 21). Player), the tension bolt B is penetrated from the through hole 301 side of the support plate 300, and the tension bolt B is connected to the tension bolt fastening portion 14 of the pile shoe 1 again. When the screw is fastened in accordance with (Figs. 21 and 22), as shown in the cross section shown in Fig. 24, both pile shoes 1 are firmly attached to the support plates 200 and 300 with the rebar long 90 mounted. By being combined, the PC steel bar 91 of the reinforcing rod 90, which is accommodated in the steel rod mounting portion 13 of the pile shoe 1 is to be assembled in a tensionable state, the tension-side pile shoe 1 thus assembled The tension plate 500 is coupled to the support plate 300 assembled in the back). (FIG. 25) As shown in FIGS. 21 and 22, the tensioning device 500 includes a copper plate 501, a tension shaft 502, a tension plate 503, a fastening nut 504, and a connection band ( 505, the copper plate 501 is fixed to one side of the lower mold 100, the through-hole is drilled in the center of the copper plate 501, the threaded shaft through the through hole ( 502 is assembled to be movable back and forth. Then, the tension plate 503 is fixed to one end of the tension shaft 502 assembled as described above (inside the mold around the copper plate 501), and the fastening nut 504 is attached to the other end of the tension shaft 502. Screw assembly, the support plate 300 is coupled to the tension plate 503 and the tension-side pile shoe (1) is coupled to the connection band 505.

이와 같이 하몰드(100)에서 철근롱(90)과 말뚝슈(1)와 인장장치(500)의 조립과 결합이 완료되면, 하몰드(100)를 콘크리트를 투입하는 투입대차에 올려놓고 콘크리트 투입기를 사용하여 하몰드(100)를 콘크리트를 투입하는 투입대차에 올려놓고 콘크리트 투입기를 사용하여 하몰드(100)안에 콘크리트를 고르게 투입한 다음, 상몰드(도시하지 않음)를 하몰드(100)위에 덮어 맞춰 상하 몰드를 체결볼트로 체결하고, 인장장치(500)의 인장축(502)에는 인장용 유압잭크(도시하지 않음)를 연결한 후 소정의 인장력을 가하여 PC강봉 즉 철근롱(90)을 인장한다. 인장장치(500)로 PC강봉(91)을 인장할 때에 인장측으로부터 PC강봉(91)에 인장력이 전달되는 경로는 인장축(502)→인장판(503)→연결밴드(505)→지지판(300)→인장볼트(B)→말뚝슈(1)→PC강봉(91)의 경로로 전달되며, 이때 인장 반대측은 역으로 PC강봉(91)→말뚝슈(1)→인장볼트(B)→지지판(200)의 경로로 인장력이 전달된다.As such, when the assembly and coupling of the reinforcing rod 90, the pile shoe 1, and the tensioning device 500 are completed in the lower mold 100, the lower mold 100 is placed on an input trolley for injecting concrete and a concrete input machine. Place the lower mold 100 on the input truck to inject concrete using the concrete injector evenly put the concrete in the lower mold 100, and then the upper mold (not shown) on the lower mold 100 The upper and lower molds are fastened with fastening bolts, and a tensioning hydraulic jack (not shown) is connected to the tension shaft 502 of the tensioning device 500, and then a predetermined tensile force is applied to the PC steel bar, that is, the steel bar 90. To seal. When the PC steel bar 91 is tensioned by the tensioning device 500, a path through which tensile force is transmitted from the tensioning side to the PC steel bar 91 is a tension axis 502 → a tension plate 503 → a connection band 505 → a support plate ( 300) → tension bolt (B) → pile shoe (1) → PC steel bar (91) is transferred to the path, the opposite side of the tension PC steel bar (91) → pile shoe (1) → tension bolt (B) → Tensile force is transmitted to the path of the support plate 200.

위와 같이 인장력이 작용하면 말뚝슈(1)를 중심으로 하여, 인장볼트(B)와 PC강봉(91)에 작용하는 인장력의 작용방향(S와T)은 제26도에서 보아 알수 있는 것과 같이, 서로 반대 방향이 되는 것이며 이로서 인장볼트(B)와 PC강봉(91)은 서로 반대 방향의 인장력(S와T)이 말뚝슈(1)에 대하여 전단응력으로 작용하게 되어 인장볼트(B)의 하단부는 연통로(15)쪽 방향(V방향)으로 이동(회전)하려고 하는 전단력이 작용하게 되며, 한편 PC강봉(91)은 연통로(15)쪽 방향(W방향)으로 이동(회전)하려고 하는 전단력이 작용하게 되는 것이다. PC강봉(91)을 인장용 유압잭크로 인장하여 PC강봉이 늘어나게 되면 이렇게 늘어난 길이 만큼 인장축(502)이 후퇴(제25도에서 보아 좌측)하면서 인장축(502)과 함께 체결너트(504)도 후퇴하게 되는 것이며, 이렇게 하여 체결너트(504)가 마구리판(501)으로부터 떨어져 일정한 간격이 벌어지게 되면, 체결너트(504)를 조여 다시 마구리판(501)에 밀착하여 놓으므로서 인장용 유압잭크의 인장력을 해제하더라도 양쪽 말뚝슈 사이의 PC강봉의 인장력은 소멸되지 아니하고 계속 그 상태를 유지하도록 되는 것이다.As described above, when the tensile force acts on the pile shoe (1), the direction of action (S and T) of the tensile force acting on the tension bolt (B) and PC steel bar (91), as can be seen in Figure 26, The tension bolt (B) and PC steel bar (91) is the opposite direction to each other so that the tension force (S and T) in the opposite direction to each other act as a shear stress against the pile shoe (1) the lower end of the tension bolt (B) Is a shear force that tries to move (rotate) in the direction of the communication path 15 (V direction), while the PC steel bar 91 tries to move (rotate) in the direction (W direction) of the communication path 15. Shear force will act. As the PC steel bar is stretched by tensioning the PC steel bar 91 with the hydraulic jack for tensioning, the tension shaft 502 is retracted (left side in FIG. 25) as much as the length thereof, and the tightening nut 504 together with the tension shaft 502 is also used. When the tightening nut 504 is separated from the curling plate 501 by a predetermined distance, the tightening nut 504 is tightened and placed in close contact with the curling plate 501 so that the tensioning force of the tensioning hydraulic jack is retracted. Even if the tension is released, the tensile strength of the PC steel rods between the two pile shoes is not destroyed and will continue to be maintained.

위와 같이 PC강봉에 일정한 인장력을 유지하도록 한 다음 이 상태로 몰드를 원심성형기에 올려 놓고 원심성형을한 다음 70-80℃의 증기로 양생을 실시한다. 양생공정으로 PCnAKFeNR의 양생작업이 완료되면 하몰드에서 상몰드를 해체하고 제품을 하몰드에서 탈형한 다음 제품의 인장측에 있는 지지판(300)과 인장반대측에 있는 지지판(200)을 해체한 다음, 제품을 오토클레이브양생조(Auto clave)안에 넣고 고온 고압 포화중기로 2차 양생을 행하며 양생을 마친 제품은 마무리 작업을 하여 PC말뚝의 완제품이 만들어 지는 것이다. 지금까지 종래의 말뚝슈와 이 말뚝슈로 PC말뚝을 제조하는 공정을 살펴보았으나 이와 같은 종래의 말뚝슈는 그 만드는 공정이 복잡하고 이러한 종래의 말뚝슈를 사용하여 PC말뚝을 제조하는데 따른 많은 문제점이 발생되고 있는 바 이의 문제점들을 열거하여 보면 다음과 같다.Maintain a constant tensile force on the PC steel bar as above, and then put the mold in the centrifugal molding machine in this state and centrifugal molding and curing with steam at 70-80 ℃. After curing of PCnAKFeNR in the curing process, the upper mold is dismantled from the lower mold, the product is demolded from the lower mold, and then the support plate 300 on the tension side of the product and the support plate 200 on the opposite side of the tension are dismantled. The product is placed in an auto clave and secondary curing with a high temperature and high pressure saturated medium. After finishing the curing, the finished product of PC pile is made. So far, we have looked at the conventional pile shoe and the process of manufacturing PC piles with this pile shoe, but the conventional pile shoe is complicated in its manufacturing process, and there are many problems in manufacturing the PC pile using the conventional pile shoe. This problem is listed as follows.

종래의 PHC말뚝슈의 제조에 따른 문제점Problems caused by the manufacture of conventional PHC pile shoe

1. PC강봉 장착부와 인장볼트 장착부를 가공함에 있어 마밀라 슈(또는 두부보강캡)는 각 구멍을 피어싱 가공으로 뚫고 엠보싱 가공하여 인장볼트 장착부를 태핑가공한 다음 강봉 장착부와 인장볼트 장착부의 사이를 밀링 가공하여 연통로를 형성하여야 하며, 또한 앵커링은 강봉 장착부의 끼움 구멍을 드릴로 뚫어 카운터싱킹(Counter sinking)가공하고, 인장볼트 장착부의 끼움 구멍을 드릴로 뚫어 태핑가공 한다음 강봉 장착부와 인장볼트 장착부의 사이를 밀링 가공하여 연통로를 형성하여야 하는 것으로 가공 공정이 많고 또한 여러개의 인장볼트 장착부의 끼움구멍을 동시에 탭 가공을 할 때 어느 하나의 탭이 불량 할 때에는 그 가공 제품을 불량 처리하여야 하는 등 생산성이 극히 저하되는 문제점이 있으며, 2. 인장기로 PC강봉을 인장할 때 에 PC강봉에 간한 인장력이 작용하게 되는 것으로 이때에 제26도에 도시된 바와 같이 PC강봉(91)의 헤드부와 인장볼트(B)의 하단부가 각각 연통로(5)쪽으로 이동하는 강한 전단력이 발생하여 연통로(5)부분이 쉽게 굴곡 되거나 찢어짐으로, 이를 예방하기 위하여는 말뚝슈를 제조하는 철판을 두께가 두꺼운 것을 사용하여야 하기 때문에 원자재비가 상승하게 되며 두꺼운 철판을 가공하는데 따른 가공비 상숭과 불량율의 증가 원인이 되고 있고 3. 위에서와 같이 두꺼운 철판을 사용하여 많은 가공 공정을 거쳐야 하는 것으로 프레스기등 각 공정 가공에 사용되는 가공기가 대형화되어야 하므로 설비 투자비가 대형화되는 문제점이 있는 것이다.1. In processing PC steel rod mounting part and tension bolt mounting part, Mila shoe (or head reinforcement cap) is drilled through each hole by piercing process and embossed, tapping the tension bolt mounting part, and then The milling process should form a communication path, and anchoring should be done by drilling the fitting holes of the steel rod mounting part by countersinking, drilling the tapping holes of the tension bolt mounting part by tapping, and then tapping the steel rod mounting part and the tension bolt. In order to form a communication path by milling between the mounting parts, there are many processing processes and when one tab is defective when tapping the fitting holes of several tension bolt mounting parts at the same time, the processed product must be treated poorly. Productivity is extremely low, etc. 2. When tensioning PC steel bar with tensioner, As shown in FIG. 26, a tensile force is applied, and as shown in FIG. 26, a strong shearing force is generated in which the head of the PC steel rod 91 and the lower end of the tension bolt B move toward the communication path 5, respectively. (5) As the part is easily bent or torn, to prevent this, the steel plate for manufacturing the pile shoe should be made of thick ones, which increases the raw material cost, and increases the processing cost and increase the defective rate due to the processing of the thick steel plate. 3. It is necessary to go through many machining processes using a thick steel plate as described above, the machine used in each process, such as a press machine has to be large, there is a problem that the investment in equipment is large.

비고 : 종래의 말뚝슈판(1)에 있어 나사가공구멍 인장볼트 끼움구멍(41)은 나사를 가공하기 위한 구멍이며 단순히 인장볼트를 관통시키기 위한 구멍이 아닌 것으로 상기 인장볼트구멍(4)을 뚫을 때에는 인장볼트가 끼워들어갈 수 없는 작은 크기의 구멍으로 가공하여야 하는 것이나, 본원발명의 인장볼트 끼움구멍은 나사의 외직경(보다)크게 가공하여 인장볼트가 충분히 관통하여 나올 수 있도록 가공하여야 하는 것임.Note: In the conventional pile shoe plate 1, the threading hole tension bolt fitting hole 41 is a hole for processing a screw, and is not a hole for penetrating the tension bolt. Tightening bolts should be machined into small sized holes that cannot be inserted, but the tensioning bolt fitting holes of the present invention should be machined so that the tensile bolts can fully penetrate through the outer diameter of the screw.

종래의 PHC말뚝슈를 사용하여 PHC말뚝을 제조하는데 따른 문제점Problems in manufacturing PHC pile using conventional PHC pile shoe

1. PHC말뚝슈 자체의 무게가 매우 무거운 것으로 인장볼트를 사용하여 마구리판이나플레이트를 말뚝슈에 조립할 때에는 인장볼트를 모두 조립할 때까지 계속하여 작업자가 무거운 마구리판이나플레이트를 직접 들고 조립 작업을 하여야 하기 때문에 생산성이 떨어지고, 1. 말뚝슈에 탭가공시 드릴의 가공각도가 수직이 아니고 경시지게 되는 등 탭가공 불량품이 있을 때에는 이와 같이 경사 가공된 볼트구멍을 통하여 말뚝슈에 마구리판 및플레이트를 조립할 때에 볼트가 기울어지거나 삽입이 안 되는 불량품이 발생하며, 3. PC강봉을 인장할 때 인장력은 장착볼트 나사와 탭의 지압응력에 의존하고 말뚝슈에 가공되 강봉 장착부와 인장볼트 장착부의 한쪽면이 개방(연통로 가공으로 인하여)되어 있기 때문에 볼트가 장착부에서 이탈할 우려가 있으며 또한 볼트를 반복하여 사용하므로 볼트가 마모 하였을 때에는 볼트가 장착부에서 이탈하기 쉬워 인장 불량품이 발생하기 쉬운 문제점이 있는 것이다.1. The PHC pile shoe itself is very heavy. Use tension bolts to When assembling the plate on the pile shoe, continue to work until the heavy bolts are assembled. Productivity decreases because the assembly work must be done by holding the plate directly. 1. When there is a defective product in tapping such as the drilling angle of the drill is not vertical and negligible during tapping on the pile shoe, the pile is inclined through the bolt hole inclined like this. Shu guripan and When assembling the plate, the bolt is inclined or the defective product cannot be inserted. 3. When tensioning the PC steel rod, the tensile force depends on the pressure stress of the mounting bolt screw and tab and is processed on the pile shoe. Since one side is open (due to the communication path processing), the bolt may come off from the mounting part. Also, because the bolt is repeatedly used, it is easy to detach the bolt from the mounting part when the bolt is worn out, so that it is easy to cause defective tensile parts. It is.

본원 발명은 위와 같은 문제점을 해결하고자 하여 발명된 것으로 첨부 도면과 함께 기재하기로 한다.The present invention will be described with the accompanying drawings as invented to solve the above problems.

본원 발명에서는 말뚝슈를 형성함에 있어 말뚝슈판체에 PC강봉의 로드관통 구멍과 헤드시트부로 되는 강봉장착부를 형성하고 있는 구성부분은 종래의 것과 유사한 것이나, 말뚝슈 판체에 형성하고 있는 인장볼트체결부의 구성 부분은 종래의 것과 달리 하고 있는 것으로, 본원 발명에 있어서는 인장볼트를 장착하는 장착부의 구성을 함에 있어, 말뚝슈판체 자체에 인장볼트를 직접 체결이 가능한 나사체결부를 가공하지 아니하고, 다만 말뚝슈판체에 인장볼트와 같은 결합부재의 관통구멍만을 가공하여 말뚝슈를 형성하는 점에 특징이 있는 것이며, 또한 위와 같이 형성된 말뚝슈를 사용하여 상기 지지판을 결합 할 때에는 결합부재를 별도로 준비하고, 지지판을 말뚝슈판에 맞대고 상기 지지판과 말뚝슈판에 형성되어 있는 결합부재관통구멍을 통하여 결합부재를 끼워 넣은 다음 이렇게 말뚝슈판을 관통하여 나온 결합부재의 생크부에 별도로 준비하고 있는 체결부재(너트)를 결합하여 조입으로서 말뚝슈와 지지판을 단단히 고정하도록 하는 조합구조에 특징이 있는 것이다. 따라서 본원 발명에 따른 말뚝슈를 사용하여 지지판과 말뚝슈를 결합하는데 있어서 결합부재로서는 인장볼트와 같은 관통체와 이 관통부재를 단단히 체결하도록 된 너트와 같은 체결체로 되는 결합부재가 많이 활용되고 있으나 반드시 결합부재로서 인장볼트와 너트로 되는 결합부재가 아니라 하더라도, 지지판과 말뚝슈를 결합 또는 분해할 수 있는 결합수단이라고 하며, 예를들어 한쪽에는 헤드가 없는 리벳트생크(rivet shank)에 키 또는 스냅링 등을 끼우는 방법 등에 의한 결합수단이 결합부재로 사용될 수도 있는 것이다.In the present invention, in forming the pile shoe, the structural part forming the rod mounting hole including the rod through hole and the head seat portion of the PC steel rod in the pile shoe plate body is similar to the conventional one, but the tension bolt fastening portion formed in the pile shoe plate body. The components are different from the conventional ones, and in the present invention, in the configuration of the mounting portion for mounting the tension bolts, the screw fasteners capable of directly fastening the tension bolts to the pile shoe plate itself are not machined. It is characterized in that only the through-hole of the coupling member such as tension bolt to form a pile shoe, and when coupling the support plate using the pile shoe formed as described above, the coupling member is prepared separately, the support plate Butt through the coupling member through hole formed in the support plate and the pile shoe plate against the shoe plate After inserting the coupling member is coupled to the fastening member (nut) prepared separately in the shank portion of the coupling member thus penetrating the pile shoe plate is characterized in a combination structure to secure the pile shoe and the support plate as a fastening. Therefore, in coupling the support plate and the pile shoe using the pile shoe according to the present invention, a coupling member including a penetrating member such as a tension bolt and a fastening member such as a nut for fastening the penetrating member is widely used. Although it is not a coupling member consisting of a tension bolt and a nut as a coupling member, it is referred to as a coupling means for coupling or disassembling the support plate and the pile shoe. For example, a key or snap ring on a rivet shank without a head on one side. The coupling means may be used as the coupling member by fitting the back.

본원 발명에 따른 말뚝슈로서 제27도에서 제3도에까지에는 마밀라슈 또는 두부캡을, 제32도에서 제36도까지에는 앵커링을 사시도 및 단면도로 각각 도시하고 있다. 본원 발명에 따를 말뚝슈(6)를 형성함에 있어 판체(66)에 PC강동(91)을 장착하기 위한 구성으로, 로드관통부(67A)와 헤드장착부(67B)로 되는 강봉장착부(67)를 가공하고 있으며, 또한 판체(66)에는 결합부재의 관통체가 관통할 수 있는 크기로 하여 결합부배장착부(68)를 형성하고, 상기 강봉장착부(67)와 결합 부재장착부(68)와의 사이에 연통로(69)를 가공하고 있다. 제37도에는 본원 발명에 따른 마밀라슈(또는 두부캡)의 가공 공정도를 평면도(상단부)와 단면도(하단부)로 도시하고 있다. 본원 발명에 따른 마밀라슈(또는 두부캡)의 말뚝슈판은 종래의 마밀라슈의 말뚝슈판 두께(8∼12t)보다는 얇은 철판(6∼9t)을 사용하여 주로 프레스 작업에 의해 가공하고 있는 것으로, 강봉장착부 및 결합부재장착부를 가공하는 방법을 가공 공정순에 따라 살펴보기로 한다. 말뚝슈판체(66)에 강봉장착부(67)를 형성하기 위한 강봉장착소재부(67E)와 결합부재장착부(68)를 형성하기 위한 결합부재장착소재부(68E)를 각각 엠보싱 가공(자-1, 자-2)한다음, 상기 장착소재부(67E, 68E) 및 연통로(69)를 동시에 피어싱 가공 (차-1, 차-2)을 하므로서 강봉장착소재부(17E)는 강봉(91)의 로드(91A)가 끼워지는 부위인 로드관통구멍(67A)이 되고, 강봉(91)의 헤드(91B)가 걸리어 안착되는 부위인 헤드 시트부(67B)로 되는 강봉장착부(67)가 형성되는 것이며, 결합부재장착소재부(68E)는 결합부재(B) 관통체의 생크부를 관통하여 끼울 수 있는 크기의 결합부재장착부(68)가 형성됨과 동시에 결합부재장착부(68)와 강봉장착부(67) 사이의 연통로(9)도 함께 형성되는 것이다.A pile shoe according to the present invention is shown in FIG. 27 through FIG. 3 with a mamilache or head cap, and with FIG. 32 through FIG. 36 with an anchoring in a perspective and sectional view, respectively. In forming the pile shoe 6 according to the present invention, the steel rod mounting portion 67 comprising the rod through portion 67A and the head mounting portion 67B is configured to mount the PC steel 91 to the plate body 66. In addition, the plate body 66 has a size through which the penetrating member of the coupling member can penetrate to form a coupling part mounting portion 68, and a communication path between the steel rod mounting portion 67 and the coupling member mounting portion 68. (69) is processed. FIG. 37 shows a machining process diagram of the mamilache (or head cap) according to the present invention in a plan view (upper end) and a cross section (lower end). The pile shoe plate of mamilache (or tofu cap) according to the present invention is mainly processed by press working using a thin iron plate (6 to 9t) rather than the thickness of the pile shoe plate (8 to 12t) of the conventional mamilache. The method of processing the steel rod mounting portion and the coupling member mounting portion will be described according to the processing process order. Embossing of the steel rod mounting material portion 67E for forming the steel rod mounting portion 67 on the pile shoe plate 66 and the coupling member mounting material portion 68E for forming the coupling member mounting portion 68, respectively. 2) Then, the steel rod mounting material portion 17E is a steel bar 91 while the piercing processing (car-1, car-2) of the mounting material portions 67E and 68E and the communication path 69 are simultaneously performed. Steel rod mounting portion 67 formed as a rod through hole 67A, which is a portion into which the rod 91A is fitted, and a head sheet portion 67B, which is a portion where the head 91B of the steel rod 91 is caught. In the coupling member mounting material portion 68E, a coupling member mounting portion 68 having a size that can be inserted through the shank portion of the coupling member B through body is formed, and the coupling member mounting portion 68 and the steel rod mounting portion 67 are formed. The communication path 9 between) is also formed together.

제38도에는 본원 발명에 따른 앵커링의 가공 공정도를 평면도(상단부)와 단면도(하단부)로 도시하고 있다.38 shows a machining process diagram of the anchoring according to the present invention in a plan view (upper end) and a cross section (lower end).

본원 발명에 따른 앵커링 말뚝슈의 판체는 두께가 얇은 철판(12t) 또는 두께가 두꺼운 철판(16t)으로 만들 때를 구별하여 가공 방법을 살펴보기로 한다. 두께가 얇은 철판으로 말뚝슈(6)를 가공할 때에는 판체(66)에 PC강봉(91)의 로드(91A)를 끼우는 로드관통구멍(67A)과, 결합부배(B)를 끼우는 결합부재관통구멍(68A)과 연통로(69)를 프레스가공으로 동시에 가공(타-1, 타-2) 한다음 강봉 로드관통구멍(67A)의 상단부를 카운터 싱킹 가공하여 PC강봉헤드가 걸려 안착되는 헤드시트부(67B)를 가공하므로서, 로드관통구멍(67A)과 헤드시트부(67B)로 되는 강봉장착부(67)가 형성되는 것이며, 결합부재관통구멍(68A)은 연통로(69)와 연통되는 상태로 결합부재장착부(68)가 형성되는 것이다. (파-1, 파-2)The plate body of the anchoring pile shoe according to the present invention will look at the processing method by distinguishing when it is made of a thin iron plate 12t or a thick iron plate 16t. When machining the pile shoe 6 from a thin steel plate, a rod through hole 67A for fitting the rod 91A of the PC steel bar 91 to the plate body 66, and a coupling member through hole for fitting the coupling portion B. (68A) and the communication path (69) are simultaneously processed by press working (ta-1, ta-2), and then the counter seat sinks the upper end of the steel rod rod through hole (67A) to seat the PC steel bar head to be seated. By processing the 67B, the steel rod mounting portion 67, which constitutes the rod through hole 67A and the head seat portion 67B, is formed, and the engaging member through hole 68A is in communication with the communication path 69. The coupling member mounting portion 68 is formed. (Par-1, par-2)

두께가 두꺼운 철판으로 말뚝슈(6)를 가공할 때에는 판체(66)에 PC강봉로드(91A)를 끼우는 로드관통구멍(67A)과 결합부재(B)를 끼우는 결합부재관통구멍(68A)을 각각 드릴로 뚫고(카-1,카-2), 로드관통구멍(67A)과 결합부재관통구멍(68A)을 연결하는 연통로(69)를 프레스가공(타-1,타-2) 한 다음, 로드관통구멍(67A)의 상단부를 카운터 싱킹 가공을 하여 PC강봉헤드가 걸려 안착되는 헤드시트부(67B)을 가공하므로서 로드관통구멍(67A)과 헤드시트부(67B)로 되는 강봉 장착부(17)가 형성되는 것이며, 결합부재관통구멍(68A)은 연통로(69)로 연통된 상태로 결합부재장착부(68)가 되는 것이다. (파-1, 파-2)When machining the pile shoe 6 from a thick steel plate, a rod through hole 67A for fitting the PC steel rod rod 91A to the plate body 66 and a coupling member through hole 68A for fitting the coupling member B, respectively, are provided. After drilling (ka-1, ka-2), press-processing (ta-1, ta-2) the connecting passage 69 connecting the rod through hole 67A and the coupling member through hole 68A, The steel rod mounting portion 17 which becomes the rod through hole 67A and the head seat portion 67B while processing the head seat portion 67B on which the PC steel rod head is caught and seated by performing countersinking on the upper end portion of the rod through hole 67A. Is formed, and the coupling member through-hole 68A becomes the coupling member mounting portion 68 in a state of being communicated with the communication path 69. (Par-1, par-2)

위와 같이 형성되는 말뚝슈를 지지판과 결합하는 조합구조에 대하여 살펴보기로 한다. 제39도와 제40도에는 결합부재의 하나로서 관통체의 생크에 나사부가 가공되어 있으며 체결체로는 너트를 사용하는 볼트형결합부재(B)를 사용하여 본원 발명에 따른 말뚝슈(6)에 지지판(200,300)을 결합하는 조합구조에 대하여 도시하고 있다. 철근롱(90)을 하몰드(100)안에 넣고 철근롱(90)의 양쪽 끝단부에 말뚝슈(6)를 조립하고 말뚝슈(6)의 강봉장착부(67)에 PC강봉(91)을 조립하는 조립 공정은 제13도에서 제 20 도까지 도시하고 있는 종래의 말뚝슈로 말뚝을 조립하는 공정과 유사한 것이다. 상기 철근롱(90) 양쪽 단부의 말뚝슈(6)에 지지판(200,300)을 각각 체결 조립 할 때에는, 지지판(200,300)을 말뚝슈(6)에 밀착시켜 맞댄 다음, 지지판(200,300)에 가공되어 있는 관통구멍(201,301)과 말뚝슈(6)에 가공되어 있는 관통구멍(68)을 통하여 결합부재(B)인 관통체의 생크 부분을 관통하여 끼워넣고, 이렇게 끼워져 말뚝슈(6)의 관통구멍(68)의 밖으로 돌출되어 나온 관통체의 생크끝단 나사부에 체결체인 너트(N)를 체결하고 인장 볼트 체결구(impact wrench)로 상기 결합부재를 견고하게 조인다.Let us look at the combination structure that combines the pile shoe formed as described above with the support plate. 39 and 40, one of the coupling members is threaded to the shank of the penetrating body, and the support plate to the pile shoe 6 according to the present invention using a bolt-type coupling member (B) using a nut as a fastener A combination structure combining (200, 300) is shown. Insert the reinforcing rod 90 into the lower mold 100, assemble the pile shoe 6 at both ends of the reinforcing rod 90, and assemble the PC steel bar 91 to the steel rod mounting portion 67 of the pile shoe 6. The assembling process is similar to the process of assembling the pile with the conventional pile shoe shown in FIGS. 13 to 20. When fastening and assembling the support plates 200 and 300 to the pile shoes 6 at both ends of the rebar long 90, the support plates 200 and 300 are brought into close contact with the pile shoes 6, and then processed to the support plates 200 and 300. Through the through-holes 201 and 301 and the through-hole 68 processed in the pile shoe 6, it penetrates through the shank part of the through-body which is the coupling member B, and is inserted so that the through-hole of the pile shoe 6 ( 68. The nut (N), which is a fastening body, is fastened to the shank end screw portion of the penetrating member projecting out of the through body, and the fastening bolt is firmly tightened with an tension wrench.

이와 같이 말뚝슈(6)에 지지판(200,300)의 조립이 완료되면 한쪽지지판(300)에 인장기(500)를 장착하고, 인장기(500)로 PC강봉(91)을 종래의 방법과 같은 종래의 방법으로 인장을 한다. 인장기(500)로 PC강봉(91)을 인장할 때에 인장축으로부터 PC강봉(91)에 인장력이 전달되는 경로는 인장축(502)→인장판(503)→연결밴드(505)→지지판(300)→결합부재(B)의 관통체→결합부재(B)의 체결체(너트N)→말뚝슈(6)→PC강봉(91)의 경로로 전달되며, 인장측 반대측은 PC강봉(91)→말뚝슈(6)→결합부재(B)의 체결체(너트N)→결합부재(B)의 관통체→지지판(200)의 경로로 인장력이 전달된다.When the assembly of the support plates 200 and 300 is completed on the pile shoe 6, the tensioner 500 is mounted on one of the support plates 300, and the PC steel bar 91 is tensioned by the tensioner 500 as in the conventional method. Tension by the method of. When the PC steel bar 91 is tensioned by the tensioner 500, a path through which tensile force is transmitted from the tension axis to the PC steel bar 91 is obtained by the tension axis 502 → tension plate 503 → connection band 505 → support plate ( 300) → the penetrating member of the coupling member (B) → the fastener (nut N) of the coupling member (B) → the pile shoe (6) → the PC steel bar (91), and the opposite side of the tension side is the PC steel bar (91). The tension force is transmitted to the path of the fastener (nut N) of the coupling shoe (B) → the coupling member (B) → the penetrating member of the coupling member (B) → the support plate (200).

위에서 보아 알 수 있는 바와 같이 결합부재(B)에 작용하는 인장력은 너트(N)를 경유하여 말뚝슈(6)에 전달되기 때문에 결합부재(B)의 인장력은 말뚝슈(6)의 강봉장착부(67)나 결합부재장착부(68)에 국부적으로 작용하지 아니하고 너트(N)의 단면적 전체에 작용하기 때문에 결합부재(B)나 연통로(69)쪽으로 굴곡되어 결합부재(B) 또는 PC강봉(91)이 말뚝슈(6)으로부터 이탈하는 일이 없게 되는 것이다. 인장기(500)로 인장하고 인장기 체결너트 (504)로 인장력을 조정하여 PC강봉에 일정한 인장력을 가한 상태로 원심 성형기로 말뚝을 성형하고 지지판(300,200)에 체결된 결합부재(B)를 해체하면 결합부재(B)에 체결되어 있던 너트(N)는 말뚝슈(6)의 안쪽에 남겨진 상태로 제품의 성형이 완료되는 것이다. 제40도의 (c), (d)도에 있어서는 본원 발명에 따른 말뚝슈의 조합방법과는 다른 조합방법을 도시하고 있는 것으로, 결합부재(B)를 체결하고 있는 체결체(너트N)를 체결한 상태에서 너트(N)의 측면체가 PC강봉(91)에 접촉되도록 하므로서 너트(N)의 지지력에 의해 PC강봉(91)을 단단히 지지하도록 하고자 하는 것이다. 지금까지 기재하고 있는 본원 발명에 따른 말뚝슈와 PC말뚝슈를 제조하는 공정 및 말뚝을 제고하는 공정의 장점을 종래의 것과 비교하여 열거하여 보면 다음과 같다.As can be seen from above, since the tensile force acting on the coupling member B is transmitted to the pile shoe 6 via the nut N, the tensile force of the coupling member B is the steel rod mounting portion of the pile shoe 6. 67 does not locally act on the coupling member mounting portion 68, but acts on the entire cross-sectional area of the nut N, so that it is bent toward the coupling member B or the communication path 69 to engage the coupling member B or the PC steel bar 91. ) Does not come off from pile shoe (6). Tension with the tensioner 500 and tensioning force with the tensioner fastening nut 504 to form a pile with a centrifugal molding machine while applying a constant tensile force to the PC steel bar and dismantle the coupling member (B) fastened to the support plates (300, 200) The nut (N), which has been fastened to the lower coupling member (B), is to be completed in the form of the product in the state left inside the pile shoe (6). 40 (c) and 40 (d) show a combination method different from that of the pile shoe according to the present invention, and the fastening body (nut N) fastening the coupling member B is fastened. It is intended to firmly support the PC steel bar 91 by the bearing force of the nut (N) while the side body of the nut (N) in contact with the PC steel bar (91) in one state. The advantages of the process of manufacturing the pile shoe and the PC pile shoe according to the present invention described so far and the process of improving the pile are listed in comparison with the conventional ones as follows.

본 발명에 따른 PC말뚝슈 제조방법의 장점Advantages of PC pile shoe manufacturing method according to the present invention

1. 본 발명에 따른 PC말뚝슈에 있어서는 결합부재 장착부를 형성함에 있어, 결합부재의 관통구멍만을 가공하고 나사부는 가공하지 아니하므로 태핑 가공이 생략되는 것이며, 또한 연통로는 프레스 가공으로 가능하므로 밀링기에 의한 밀링 가공이 생략되는 등 가공공정이 단순화 되는 것으로 생산성이 극히 향상됨과 동시에 가공이 어려운 태핑 가공 생략에 따른 제품 불량이 없어지는 것이며, 2. 인장기로 PC강봉을 인장할 때에 작용하는 결합부재(B)의 인장력은 말뚝슈(6)에 대하여 국부적인 응력으로 작용하지 아니하고 넓은 면적에 분포되어 작용하기 때문에 말뚝슈(6)의 연통로(69) 부분이 굴곡되거나 찢어지는 일이 없으므로 얇은 철판으로 제조할 수 있어 원자재비가 감소되는 것이며 가공비가 절감되고 불량율 발생이 적어지고, 3. 위에서 검토한 바와 같은 얇은 철판을 사용하고 많은 공정이 생략 또는 단순화 되기 때문에 공정 생략에 따른 가공기가 생략될 뿐 아니라 필요한 가공기의 경우에도 소형화할 수 있으므로 설비투자비가 감소한다.1. In the PC pile shoe according to the present invention, in forming the coupling member mounting portion, since only the through-hole of the coupling member is processed and the thread portion is not processed, the tapping processing is omitted, and the communication path is possible by press working, so that the milling machine is used. Productivity is greatly improved by eliminating the milling process by the milling process, and product defects due to the omission of tapping processing, which are difficult to process, are eliminated. Since the tensile force of B) does not act as a local stress on the pile shoe 6 but is distributed and acts in a large area, the portion of the communication path 69 of the pile shoe 6 is not bent or torn, so that Can reduce the cost of raw materials, reduce the processing cost and reduce the occurrence of defective rate, 3. Since the same thin steel plate is used and many processes are omitted or simplified, the machine is not only omitted, but the required machine can be miniaturized, thus reducing the capital investment.

본 발명에 따른 PC말뚝슈를 사용하여 PC말뚝dmf 제조하는데 따른 장점Advantages of manufacturing PC pile dmf using PC pile shoe according to the present invention

1. PC말뚝슈 자체의 무게가 가볍기 때문에 취급이 용이하며 말뚝슈에 마구리판이나플레이트와 같은 지지판을 조립할 때에 결합부재를 모든 관통 구멍에 일단 삽입시켜 놓은 다음에 결합부재를 체결하는 체결부재로 체결하기 때문에 작업자가 지지판의 무게를 부담하는 시간이 짧기 때문에 생산성이 향상되며, 2. 말뚝슈에 탭가공을 하지 아니하므로 탭 또는 결합부재의 불량으로 인한 조립 불량이 발생하지 아니하는 것이고 3. PC강봉을 인장할 때 PC강봉의 인장력은 장착볼트와 너트의 지압응력 및 말뚝슈판의 전단 응력을 동시에 받기 때문에 볼트가 볼트 구멍에서 이탈할 우려가 극히 적으며 4. 볼트가 다소 마모 되었더라도 너트의 산수가 말뚝슈 등에 가공된 탭의 산수보다 많으므로 볼트가 너트에서 이탈하는 불량이 극히 적고 5. 너트는 기성품으로 KS제품을 사용하므로 불량 너트에 의한 제조불량은 전혀 없으며, 또한 말뚝슈의 성형 제조가 완료된다음 탈형시에 너트가 말뚝안에 잔존하여 너트의 재사용은 불가능하지만 너트의 단가는 저렴한 것이며 종래의 말뚝슈의 제작시 필수적으로 하여야 하는 탭 가공에 따른 가공비, 불량발생율, 가공시간, 조립시간 등으로 인한 원가 부담에 비교하면 너트의 사용에 따른 원가부담은 거의 없는 것이다.1.The weight of PC pile shoe itself is easy to handle. When assembling a supporting plate such as a plate, the coupling member is once inserted into all the through holes and then fastened by a fastening member for fastening the coupling member, thereby improving productivity because the operator takes a short time to bear the weight of the supporting plate. Since there is no tap machining on the pile shoe, no assembly failure occurs due to the failure of the tab or coupling member. Since the bolts are stressed at the same time, the bolts are very unlikely to break out of the bolt holes. Since nut uses KS product as ready-made product, there is no manufacturing defect due to bad nut and also the performance of pile shoe. After manufacturing is completed, the nut remains in the pile when demolding, so it is impossible to reuse the nut, but the unit price of the nut is inexpensive. Compared to the cost burden due to such a cost, there is almost no cost burden due to the use of nuts.

Claims (3)

판체에 강봉장착부와 결합부재장착부와 연통로를 갖도록 된 말뚝슈를 형성함에 있어서, 상기 결합부재장착부는 결합부재의 관통체가 관통할 수 있는 크기의 관통구멍으로 형성되는 것을 특징으로 하는 말뚝슈.In forming a stake shoe having a steel rod mounting portion and a coupling member mounting portion in the plate body, the coupling member mounting portion is characterized in that the coupling shoe is formed with a through hole of a size that can penetrate the through member of the coupling member. PC강봉을 장착하고 있는 말뚝슈에 지지판을 조립함에 있어, 상기 말뚝슈에 지지판을 맞대고, 지지판과 말뚝슈의 관통구멍을 통하여 결합부재의 관통체를 관통하며, 이렇게 삽입 관통하여 돌출되어 나온 결합부재의 관통체에는 체결과 분해가 가능하도록 된 체결체를 체결하여, 결합하도록 된 말뚝슈와 지지판을 조립하는 조합구조.In assembling the support plate to the pile shoe on which the PC steel rod is mounted, the support plate is brought into contact with the pile shoe, and the penetrating member penetrates the through member through the through hole of the support plate and the pile shoe. Combination structure for assembling the pile shoe and the support plate to be coupled to the fastener to enable fastening and disassembly to the through body. 제2항에 있어서, 상기와 같은 조합 상태에서 결합부재의 체결체는 PC강봉에 밀착되어 PC강봉의 지지력을 강화하도록 되는 조합구조.The combination structure according to claim 2, wherein the fastening member of the coupling member is in close contact with the PC steel bar in such a combined state to reinforce the supporting force of the PC steel bar.
KR1019940001379A 1994-01-26 1994-01-26 Pile cap structure and connecting structure for pile cap and base plate KR0128103B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019940001379A KR0128103B1 (en) 1994-01-26 1994-01-26 Pile cap structure and connecting structure for pile cap and base plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019940001379A KR0128103B1 (en) 1994-01-26 1994-01-26 Pile cap structure and connecting structure for pile cap and base plate

Publications (2)

Publication Number Publication Date
KR950023808A KR950023808A (en) 1995-08-18
KR0128103B1 true KR0128103B1 (en) 1998-04-08

Family

ID=19376259

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019940001379A KR0128103B1 (en) 1994-01-26 1994-01-26 Pile cap structure and connecting structure for pile cap and base plate

Country Status (1)

Country Link
KR (1) KR0128103B1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100715504B1 (en) * 2005-05-02 2007-05-08 주식회사 삼성씨케이 Formation method for iron rod frame of pretensioned spun high strength concrete piles
WO2011142534A2 (en) * 2010-05-13 2011-11-17 Song Ki-Yong Concrete pile and method for producing same
WO2011159115A2 (en) * 2010-06-18 2011-12-22 Song Ki-Yong Complex pile, and method for fabricating the complex pile
KR101150854B1 (en) * 2009-09-30 2012-06-13 이엑스티 주식회사 Reinforcing plate integrated phc pile and the manufacturing method for the same
CN102689358A (en) * 2012-06-21 2012-09-26 江苏建华管桩有限公司 Tensioning component and tensioning method of prestressed endless sheet pile and pile including component
KR101241994B1 (en) * 2010-03-11 2013-03-11 송기용 Reinforcing block used in concrete pile and concrete pile using the same
KR102136949B1 (en) 2019-02-27 2020-08-13 한국기술교육대학교 산학협력단 Pretentioned spun high strength concrete piles

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100739499B1 (en) * 2005-12-13 2007-07-18 이호경 the coupling structure of pile with sliding locking joint

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100715504B1 (en) * 2005-05-02 2007-05-08 주식회사 삼성씨케이 Formation method for iron rod frame of pretensioned spun high strength concrete piles
KR101150854B1 (en) * 2009-09-30 2012-06-13 이엑스티 주식회사 Reinforcing plate integrated phc pile and the manufacturing method for the same
KR101241994B1 (en) * 2010-03-11 2013-03-11 송기용 Reinforcing block used in concrete pile and concrete pile using the same
WO2011142534A2 (en) * 2010-05-13 2011-11-17 Song Ki-Yong Concrete pile and method for producing same
WO2011142534A3 (en) * 2010-05-13 2012-03-01 Song Ki-Yong Concrete pile and method for producing same
WO2011159115A2 (en) * 2010-06-18 2011-12-22 Song Ki-Yong Complex pile, and method for fabricating the complex pile
WO2011159115A3 (en) * 2010-06-18 2012-05-03 Song Ki-Yong Complex pile, and method for fabricating the complex pile
CN102689358A (en) * 2012-06-21 2012-09-26 江苏建华管桩有限公司 Tensioning component and tensioning method of prestressed endless sheet pile and pile including component
CN102689358B (en) * 2012-06-21 2014-07-16 江苏建华管桩有限公司 Tensioning component and tensioning method of prestressed endless sheet pile and pile including component
KR102136949B1 (en) 2019-02-27 2020-08-13 한국기술교육대학교 산학협력단 Pretentioned spun high strength concrete piles

Also Published As

Publication number Publication date
KR950023808A (en) 1995-08-18

Similar Documents

Publication Publication Date Title
AU667758B2 (en) Non-metallic reinforcing rod and method of use in supporting a rock formation
EP3559484B1 (en) System for joining or reinforcing components
KR0128103B1 (en) Pile cap structure and connecting structure for pile cap and base plate
DE2457427A1 (en) Tunnel or shaft hoop support liner - uses snap-lock bush and bolts transfer shield force to linr for placement
JPH10131303A (en) Joint construction of reinforcement
EP2151592A2 (en) Nail-shaped attachment element
EP0724085A1 (en) Fastening anchor with undercut and form-locking action
DE1775527A1 (en) Multipart expansion dowel
JPH1181304A (en) Connection structure of steel pipe
KR100615514B1 (en) structure and method for jointing steel members and jointing member with expansion and shear action to be used therefor
JP3989474B2 (en) Prestress force introduction device anchoring structure and prestressed joint structure
KR101793693B1 (en) End tip for driven concrete pile and driven concrete pile therewith
KR101445369B1 (en) Soil Nailing Device Using Connector and Construction Method Using the Same
JP2000034842A (en) Reinforcing tool for concrete bar-shaped structure and reinforcing method using the same
KR200202715Y1 (en) Ruggdness pouring type contrete structure
TW202012756A (en) Joint utilizing incomplete thread of male threaded portion
KR0141054B1 (en) Device for tensing wire in prestressed concrete work
JP3453642B2 (en) How to join columns, foundations and foundations
JP2517918Y2 (en) Rock bolt for civil engineering
JP2002194735A (en) Pile clamping structure and clamping tool
CN211517928U (en) Device convenient to demolish precast beam tip mould
US4064785A (en) Threaded connections
JP2001311399A (en) Fixing device for bar-like member to rock, rock bolt using this device, and hoisting device for rock
CN216641154U (en) One sleeve hoops two tile tightly-clamped steel bar joints
EP3957803A1 (en) Anchor holder, anchor rail and arrangement with the anchor rail

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20101206

Year of fee payment: 14

LAPS Lapse due to unpaid annual fee