JPS6388495A - Method of constructing housing for nuclear power plant - Google Patents

Method of constructing housing for nuclear power plant

Info

Publication number
JPS6388495A
JPS6388495A JP61233165A JP23316586A JPS6388495A JP S6388495 A JPS6388495 A JP S6388495A JP 61233165 A JP61233165 A JP 61233165A JP 23316586 A JP23316586 A JP 23316586A JP S6388495 A JPS6388495 A JP S6388495A
Authority
JP
Japan
Prior art keywords
floor
loading section
power plant
nuclear power
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP61233165A
Other languages
Japanese (ja)
Inventor
広兼 常男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP61233165A priority Critical patent/JPS6388495A/en
Publication of JPS6388495A publication Critical patent/JPS6388495A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Monitoring And Testing Of Nuclear Reactors (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Abstract] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔発明の目的〕 (産業上の利用分野) この発明は、原子力発電所の建屋げ殿方法に関する。[Detailed description of the invention] [Purpose of the invention] (Industrial application field) The present invention relates to a method for building a nuclear power plant.

(従来の技術) 従来の原子力発電所のLl屋建設方法を第1図(B)お
よび第3図を参照して説明する。
(Prior Art) A conventional method for constructing a L1 building for a nuclear power plant will be explained with reference to FIG. 1(B) and FIG. 3.

k!股手順は、まずに削を実誇し、岩盤を検査する。こ
の検査完了後、原子炉建屋1の9声体工事をマット3工
事から開始し、順次地下階の床5および壁7を建設する
。第1図(B)中地下1階を81Fと略称する。地下2
.3階等についても同様に示す。
k! The first step is to demonstrate the cutting and inspect the bedrock. After this inspection is completed, the construction of the 9 body parts of the reactor building 1 will begin with the construction of the mat 3, and then the floor 5 and walls 7 of the basement floor will be constructed. The first basement floor in FIG. 1(B) is abbreviated as 81F. Underground 2
.. The same applies to the third floor, etc.

地下1階のg7を完成した後、地上1階の床5工事と並
行して、本設大物mzm人部9の基礎11を構榮する。
After completing G7 on the first basement floor, in parallel with the construction on floor 5 on the first floor above ground, we will construct the foundation 11 of the main MZM Human Department 9.

これら地下1階の床5および大物搬入部のり礎11の完
了後、原子戸建pA1の地上階の拳体工事を地下階に引
き続いて実施づる。この地上階の躯体工事と並行して、
原子炉ti屋1の周りを埋め戻しし、本設大物機器搬入
部9の帽体工事を開始する。なお、第1図(B)では地
上1階をFlと略称する。地上2,3.・・・階につい
ても同様に示す。
After completion of the floor 5 of the first basement floor and the foundation 11 of the large item loading area, the construction work on the ground floor of the detached house pA1 will be carried out following the basement floor. In parallel with this ground floor frame work,
The area around the reactor tidying house 1 will be backfilled, and construction of the cap body of the main large equipment loading section 9 will begin. In addition, in FIG. 1(B), the first floor above the ground is abbreviated as Fl. On the ground 2, 3. ...The same applies to floors.

原子炉建屋1の地上1階の完成と木設犬物+、1 +シ
搬入部9の完成を持って、原子炉建屋1内への1械・電
気品の搬入据付工事を開始する。こうして、原子炉建屋
1を最上階まで完成し、機械・電気計装工事を引き続き
実施して、原子力発電所の建屋を完成させる。
Once the first floor above ground of the reactor building 1 is completed and the wooden dog equipment +, 1 + transport section 9 is completed, the work to transport and install machinery and electrical equipment into the reactor building 1 will begin. In this way, the reactor building 1 is completed up to the top floor, and mechanical and electrical instrumentation work is continued to complete the nuclear power plant building.

(発明が解決しようとする問題点) ところが、このような従来の原子力U’1所の建屋建設
方法では、地上1階の完成と本設人物機器搬入部9の完
成を待って、原子炉建屋1内への機械・電気品の搬入・
据付工事を着手しなければならない。そのため、第1図
(B)に示すように、地下階の躯体工事が完了しても、
地下階へ機械・電気品を搬入・据付することができない
。その結果、地下階への機械・電気品搬入据付工事開始
時期の遅れが、原子力発電所の全体建設期間におけるク
リティカルバスとなり、全体建設工期が長期に及ぶ原因
となっている。
(Problems to be Solved by the Invention) However, in such a conventional building construction method for nuclear power station U'1, the reactor building is constructed after the completion of the first floor above ground and the main equipment loading section 9. Bringing machinery and electrical items into 1.
Installation work must begin. Therefore, as shown in Figure 1 (B), even if the basement floor construction is completed,
Mechanical and electrical items cannot be brought into or installed on the basement floor. As a result, the delay in the start of the installation work for bringing machinery and electrical equipment into the basement floor becomes a critical bus in the overall construction period of the nuclear power plant, causing the entire construction period to take a long time.

この発明は、上記事実を考慮してなされたものであり、
原子力発電所の建設工JtIJを大幅に短縮することが
できる原子力発電所の建屋建設方法を提供することを目
的とする。
This invention was made in consideration of the above facts,
An object of the present invention is to provide a method for constructing a building for a nuclear power plant that can significantly shorten construction work JtIJ for a nuclear power plant.

〔発明の構成〕[Structure of the invention]

(問題点を解決するための手段) この発明は、地下階建設後地上階を建設する原子力発電
所のi!屋11設方法において、地下階建設時に、この
地下階内部へ機器を搬入する仮設機器搬入部を上記地下
階に連通して設け、この仮設機器搬入部の設置箇所が、
後の地上階建設工程でこの地上階に設けられる本設機器
搬入部の直下であるよう174成されたものである。
(Means for Solving the Problems) This invention provides an i! In the building 11 construction method, when constructing a basement floor, a temporary equipment loading section for transporting equipment into the basement floor is provided in communication with the basement floor, and the installation location of this temporary equipment loading section is as follows:
It was constructed so that it would be located directly below the main equipment loading section that will be provided on the ground floor in the later ground floor construction process.

(作用) したがって、この発明に係る原子力発電所の建屋建設方
法によれば、地上階の本設機器搬入部の完成を持たずに
、地下階への機械・電気品のIIQ入据付工事を9期に
開始することができる。また、仮設機器搬入部が本設機
器搬入部の直下に設りられるので、この仮設機器搬入部
を本設機器搬入部の基礎に兼用することができる。
(Function) Therefore, according to the nuclear power plant building construction method according to the present invention, IIQ entry and installation of mechanical and electrical components to the basement floor can be carried out at 9:00 AM without completing the main equipment loading section on the ground floor. It can be started in the period. Furthermore, since the temporary equipment loading section is provided directly below the permanent equipment loading section, this temporary equipment loading section can also be used as the foundation of the permanent equipment loading section.

(実施例) 以下、この発明の実論例を図面に基づいてt説明する。(Example) Hereinafter, a practical example of this invention will be explained based on the drawings.

第1図(A)はこの発明に係る原子力発電所の建屋建設
方法における一実施例のU設工程を示す図である。また
、第2図はこの実hN例により建設された原子炉ll屋
を示す断面図である。なお、第2図において従来と同様
な部分は同一の符号を付す。
FIG. 1(A) is a diagram showing the U installation process of an embodiment of the nuclear power plant building construction method according to the present invention. Moreover, FIG. 2 is a sectional view showing a nuclear reactor house constructed according to this practical example. In addition, in FIG. 2, the same parts as the conventional one are given the same reference numerals.

第2図に示す原子炉建屋21は、建屋内に原子炉格納容
品23を収納するものである。その他、原子炉1!!屋
21内には、原子炉を運転するための各種機器・装置や
配管・′?J3気計装品(図示せず)が据え付けられる
。原子炉1!屋21の地上1階部分には木設大物鳴器搬
入部9が設けられる。この本設大物橢お搬入部9は、地
下階完成後に原子炉社屋21内へ機械・電気品を搬入す
るものである。
The reactor building 21 shown in FIG. 2 houses a reactor containment vessel 23 inside the building. Others, nuclear reactor 1! ! Inside Building 21, there are various equipment, equipment, piping, etc. for operating the reactor. J3 instrumentation (not shown) is installed. Nuclear reactor 1! On the first floor of the building 21, a large wooden sounder carrying section 9 is provided. This large-scale transport unit 9 is used to transport mechanical and electrical items into the reactor building 21 after the basement floor is completed.

また、この本設人物機器搬入部9の直下に仮設1器搬入
as 25が設けられる。この仮設機器搬入部25は地
下階建設時に地下階1階部分に連通して設けられ、本設
大物機器搬入部9の完成前に地下階内部へ機械・電気品
を搬入するものである。
Further, a temporary one-device carry-in AS 25 is provided directly below this permanent personal equipment carry-in section 9. This temporary equipment loading section 25 is provided in communication with the first floor of the basement floor during construction of the basement floor, and is used to transport machinery and electrical items into the basement floor before the permanent large equipment loading section 9 is completed.

次に、上述の原子炉建屋の建屋建設方法を第1図(A)
を参照して説明する。
Next, the building construction method of the above-mentioned reactor building is shown in Figure 1 (A).
Explain with reference to.

まず、大地26を掘削し、掘削完了後岩盤検査を実施す
る。この検査完了後原子炉建屋21の躯体工事をマット
3工事から開始し、順次地下階の床5および壁7を横築
する。第1図(△)中地下1階は、BIFと略称する。
First, the ground 26 is excavated, and after the excavation is completed, a rock mass inspection is performed. After completion of this inspection, the construction of the reactor building 21 will begin with the mat 3 construction, and the basement floor 5 and walls 7 will be laterally constructed. The first basement floor in Figure 1 (△) is abbreviated as BIF.

地下2.3階についても同様に略称する。The 2nd and 3rd basement floors are also abbreviated in the same way.

地下2階の壁7完成後、地下1階の床5工事と並行して
、仮設機器搬入部25の基礎27および床28を構築す
る。さらに、地下1階の壁7エ事および地上1階の床5
工事と並行して、仮設機器搬入部25の壁29を構築し
、仮設機器搬入部25を完成する。その世、地上1階壁
工事、地上2階床工事等順次実施し、地下階を(1が築
する。第1図(A)′cは地上1階を1F、!:略称す
る。以下、地上2,3階等についても同様に略称する。
After the wall 7 on the second basement floor is completed, the foundation 27 and floor 28 of the temporary equipment loading section 25 will be constructed in parallel with the construction of the floor 5 on the first basement floor. In addition, wall 7 on the first basement floor and floor 5 on the first floor above ground
In parallel with the construction, the wall 29 of the temporary equipment loading section 25 is constructed to complete the temporary equipment loading section 25. At that time, wall work on the first floor above ground, construction on the second floor above ground, etc. were carried out sequentially, and the basement floor (1) was constructed. Figure 1 (A)'c shows the first floor above ground as 1F, !: Abbreviation. Hereinafter, The second and third floors above the ground are also abbreviated in the same way.

この地上階の工事と並行して、本設人物機器搬入部9を
構築する。この本設大物機器搬入部9の完成1なも地上
階の躯体工事を最−L階まで引ぎ続き実施する。
In parallel with this construction on the ground floor, a permanent human equipment loading section 9 will be constructed. Once this main large equipment loading section 9 has been completed, the structural work on the ground floor will continue up to the Lth floor.

原子炉建屋21内への機器・電気品搬入据付工事は、原
子戸建M27の地下1r!IJの完成および仮設機器搬
入部25の完成後に開始し、機械の電気計装工事を実施
する。原子炉建屋21の地上階完成後も引き続き機械・
電気計装工事を実施し、原子炉建屋21を完成させる。
Equipment and electrical equipment will be transported and installed inside the reactor building 21 in the basement 1r of the nuclear detached house M27! The electrical instrumentation work for the machine will begin after the completion of the IJ and the temporary equipment loading section 25. Even after the completion of the ground floor of reactor building 21, machinery and
Electrical instrumentation work will be carried out and reactor building 21 will be completed.

上記実施例によれば、地下階の建設工事と並行して仮設
機器搬入部を構築し、この仮設FfM器搬器部入部成後
この搬入部から機器・電気品を搬入させることから、地
上階に設けられる本設大物機:S搬入部9の完成を待た
ずに地下階へ機械・電気品を搬入し据付iノることかで
きる。したがって、機械・電気品を早期に搬入・据付で
きるので、配管工事等の機械工事や電気計装工事の完成
時期を早めることができる。故に、原子力発電所の建設
工期を大幅に短縮することができる。
According to the above embodiment, a temporary equipment loading section is constructed in parallel with the construction work on the basement floor, and after the construction of the temporary FfM equipment carrier section, equipment and electrical items are brought in from this loading section. It is possible to carry machinery and electrical items into the basement floor and install them without waiting for the completion of the main equipment: S carrying-in section 9. Therefore, mechanical and electrical items can be brought in and installed quickly, so that mechanical work such as piping work and electrical instrumentation work can be completed earlier. Therefore, the construction period for nuclear power plants can be significantly shortened.

また、仮設機器搬入部25が本設大物a器部入部9の直
下に設けられることから、仮設機♂搬入部25を本設大
物機器搬入部9の基礎に兼用することができる。したが
って、従来のような基礎11(第3図に示す)を設ける
必要がなく、原子力発電所の建設に伴う費用の低減を図
ることができる。
Further, since the temporary equipment loading section 25 is provided directly below the permanent large equipment section 9, the temporary machine male loading section 25 can also be used as the foundation of the permanent large equipment loading section 9. Therefore, there is no need to provide a foundation 11 (shown in FIG. 3) as in the conventional case, and it is possible to reduce costs associated with the construction of a nuclear power plant.

さらに、仮設機器搬入部25は原子力発電所社殿完了後
に機材置場や定期点検時のメンテナンススペース等に有
効利用することができる。
Furthermore, the temporary equipment loading section 25 can be effectively used as an equipment storage area or a maintenance space during periodic inspections after the nuclear power plant building is completed.

なお、上記実施例では、原子力発電所の原子炉建屋につ
き説明したが、タービン建屋であってもよい。
In addition, although the said Example demonstrated about the nuclear reactor building of a nuclear power plant, a turbine building may be sufficient.

〔発明の効果〕〔Effect of the invention〕

以上のように、この発明に係る原子力発電所の建屋建設
方法によれば、地下階建設時にこの地下階に連通して仮
設機器搬入部を設け、しかもこの仮設機器搬入部の設置
箇所が地上階に設けられる本設機4搬入部の直下である
ように構成されたことから、機械・電気品を地下階へ早
期に搬入することができ、原子力発電所の建設工期を大
幅に短縮できるとともに、仮設機器搬入部を本設大物様
器搬入部の基礎として発電所建設に伴う費用を低減する
ことができる。
As described above, according to the nuclear power plant building construction method according to the present invention, when constructing a basement floor, a temporary equipment loading section is provided in communication with the basement floor, and the installation location of this temporary equipment loading section is on the ground floor. Because it is configured so that it is located directly below the main installation equipment 4 loading section installed in Costs associated with power plant construction can be reduced by using the temporary equipment loading area as the basis for the permanent large equipment loading area.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図(A)および(B)はこの発明に係る原子力発電
所の建屋建設方法における一実施例の建設工程と従来の
建設工程とをそれぞれ示ず図、第2図は第1図(A)の
一実施例により建設された原子炉建屋を示す縦断面図、
第3図は従来の建屋建設方法により建設された原子炉建
屋を示すmIgi面図である。 9・・・本設大物機お搬入部、11・・・原子炉建屋2
5・・・仮設機器搬入部。 代理人弁理士  則 近 憲 fti 同         三  俣  弘  文第2図 第3図
1(A) and 1(B) are diagrams that do not show the construction process of one embodiment of the nuclear power plant building construction method according to the present invention and the conventional construction process, respectively, and FIG. ) A vertical cross-sectional view showing a nuclear reactor building constructed according to an embodiment,
FIG. 3 is an mIgi plan view showing a reactor building constructed using a conventional building construction method. 9...Main large aircraft loading section, 11...Reactor building 2
5...Temporary equipment loading section. Representative Patent Attorney Ken Chika FTI Hiroshi Mitsumata Figure 2 Figure 3

Claims (1)

【特許請求の範囲】[Claims] 地下階建設後地上階を建設する原子力発電所の建屋建設
方法において、地下階建設時に、この地下階内部へ機器
を搬入する仮設機器搬入部を上記地下階に連通して設け
、この仮設機器搬入部の設置箇所が、後の地上階建設工
程でこの地上階に設けられる本設機器搬入部の直下であ
ることを特徴とする原子力発電所の建屋建設方法。
In a nuclear power plant building construction method in which the ground floor is constructed after the basement floor is constructed, when constructing the basement floor, a temporary equipment loading section for transporting equipment into the basement floor is provided in communication with the basement floor. A nuclear power plant building construction method, characterized in that the installation location of the section is directly below a main equipment loading section that will be installed on the ground floor in a later ground floor construction process.
JP61233165A 1986-10-02 1986-10-02 Method of constructing housing for nuclear power plant Pending JPS6388495A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61233165A JPS6388495A (en) 1986-10-02 1986-10-02 Method of constructing housing for nuclear power plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61233165A JPS6388495A (en) 1986-10-02 1986-10-02 Method of constructing housing for nuclear power plant

Publications (1)

Publication Number Publication Date
JPS6388495A true JPS6388495A (en) 1988-04-19

Family

ID=16950740

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61233165A Pending JPS6388495A (en) 1986-10-02 1986-10-02 Method of constructing housing for nuclear power plant

Country Status (1)

Country Link
JP (1) JPS6388495A (en)

Similar Documents

Publication Publication Date Title
Strickland Fukushima's next 40 years
JPS6388495A (en) Method of constructing housing for nuclear power plant
JPH05107381A (en) Method for constructing nuclear power plant reactor
JP2519896B2 (en) Reactor dismantling method
JPS6221100A (en) Underground treating method of radioactive waste
JP3340897B2 (en) Reactor building
JPS62242899A (en) Nuclear reactor processing method
JPH0513225B2 (en)
Ballinger et al. A History of Major Hanford Facilities and Processes Involving Radioactive Material
Kurnosov Chernobyl''Sarcophagus''safety analysis and proposals for modernization
Macci et al. Optimization study and preliminary design for Latina NPP early core retrieval and reactor dismantling
Giraud et al. Cost Advantages of Large Underground Nuclear Parks
JP5905790B2 (en) Spent fuel storage facility
JPS6333678B2 (en)
JPS6325315B2 (en)
JPS59111095A (en) Method of constructing tank room of atomic power plant
Wall et al. Retrieval of Intermediate Level Waste at Trawsfyndd Nuclear Power Station
Biurrun et al. Status of Equipment Development for a High-Level Waste Repository in Germany-9552
Hoorelbeke et al. The research in France on disposal concepts for high level and long lived radioactive waste in deep clay formation
JPS62206497A (en) Shielding partition wall
JPS62233789A (en) Method of building nuclear power plant
JPH10104398A (en) Storage facility for radioactive waste
WESTRA Sludge treatment facility preliminary siting study for the sludge treatment project (A-13B)
Kibbe US working draft on repository physical descriptions in a salt formation
Ballinger et al. A history of major Hanford facilities and processes involving radioactive material.[Contains glossary]