JPS6360315A - Construction of mass-concrete structure - Google Patents

Construction of mass-concrete structure

Info

Publication number
JPS6360315A
JPS6360315A JP19998886A JP19998886A JPS6360315A JP S6360315 A JPS6360315 A JP S6360315A JP 19998886 A JP19998886 A JP 19998886A JP 19998886 A JP19998886 A JP 19998886A JP S6360315 A JPS6360315 A JP S6360315A
Authority
JP
Japan
Prior art keywords
concrete
formwork
space
formwork device
poured
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP19998886A
Other languages
Japanese (ja)
Inventor
Yoji Nagaya
長屋 洋司
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP19998886A priority Critical patent/JPS6360315A/en
Publication of JPS6360315A publication Critical patent/JPS6360315A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To raise the efficiency of operations by a method in which disposable formworks are formed by hardening concrete, and concrete is placed into the space between the disposable formworks to form a concrete structure. CONSTITUTION:A formwork device 1 is set, a concrete hose is inserted into the upper ends of sheathing boards 2, and concrete is placed into the space between the sheathing boards 2. After the concrete hardens, the formwork device is upwardly moved to a given height, concrete is placed into the space between the sheathing boards 2, and anchor bolts 7 are fixed to the disposable formwork 6 of concrete. Concrete is then placed into the space between the formworks 6 to form an intermediate concrete part 8. The needs for detaching anchor bolts for setting the formwork can thus be eliminated.

Description

【発明の詳細な説明】 (1)産業上の利用分野 本発明はダム等のマスコンクリート構造物を形成する施
工方法に関する。
DETAILED DESCRIPTION OF THE INVENTION (1) Industrial Application Field The present invention relates to a construction method for forming mass concrete structures such as dams.

(2)従来の技術 従来、第4図の如く型枠フレーム(a)の内側の上半部
にせき板(b)を固定して形成した型枠装こを、硬化し
たコンクリートブロック(C)に前記型枠フレーム(a
)の下半部においてアンカーボルト(d)により固定し
、該コンクリートブロック(C)上にコンクリートを打
設し、この打設したコンクリートが硬化した後型枠装置
をクレーン等で吊上げてから前述と同様に該硬化したコ
ンクリートブロックにアンカーポル) (d)により前
記型枠フレーム(a)の下半部を固定し、以後これらの
施工を繰り返してダム等を形成していた。
(2) Conventional technology Conventionally, as shown in Fig. 4, a formwork frame (a) is formed by fixing a weir plate (b) to the upper half of the inside of the formwork frame, and then a hardened concrete block (C) is used. The formwork frame (a
) is fixed with anchor bolts (d) at the lower half of the concrete block (C), concrete is poured onto the concrete block (C), and after the poured concrete has hardened, the formwork equipment is lifted with a crane etc. and then the above-mentioned process is carried out. Similarly, the lower half of the form frame (a) was fixed to the hardened concrete block using anchor poles (d), and these operations were repeated to form a dam or the like.

(3)発明が解決しようとする問題点 この従来の施工によればアンカーボルトの脱着等を人手
で実施しているので作業能率が悪く、又このような人手
作業を高所で行うことが多く危険である等の問題点があ
った。 本発明はこれらの問題点を解消した施工方法を
提供することを目的とする。
(3) Problems to be solved by the invention According to this conventional construction method, work efficiency is poor because the anchor bolts are manually installed and removed, and such manual work is often performed at high places. There were problems such as being dangerous. An object of the present invention is to provide a construction method that eliminates these problems.

(4)17! !Jl’l 占t;−@+h ナスf−
、V’l m f= E%この目的を達成すべく本発明
は1間隔を存して平行な左右のせき板の上端部間を連結
板により連結固定し、該連結板にジヤツキを設けた型枠
装この前記左右のせき板間にコンクリートを打設し、上
方に突出する鉄筋に反力をとって前記ジヤツキにより前
記型枠装置を上動する施工方法において、前記コンクリ
ートの硬化により捨型枠を形成し、該すて型枠間にコン
クリートを打設してコンクリート構造物を形成すること
を特徴とする。
(4) 17! ! Jl'l fortune t;-@+h eggplant f-
, V'l m f= E% In order to achieve this object, the present invention connects and fixes the upper ends of parallel left and right weir plates with one interval between them using a connecting plate, and provides a jack on the connecting plate. Formwork installation In this construction method, concrete is cast between the left and right weir plates, and the formwork device is moved upward by the jacks by taking a reaction force from the reinforcing bars protruding upward, and the mold is discarded as the concrete hardens. A concrete structure is formed by forming a frame and pouring concrete between the cast forms.

(5)作用 左右のせき板間にコンクリ−トを打設し、該コンクリー
トの硬化検鏡コンクリートに立設した鉄筋に反力をとっ
てジャー2キにより型枠装置を上動して前記せき板間に
コンクリートを打設する2以上の施工を繰り返して捨型
枠を形成し、該すて型枠間にコンクリートを打設してダ
ム等を形成する。
(5) Action: Concrete is poured between the left and right weir plates, and the reaction force is taken by the reinforcing bars set up on the hardened specular concrete, and the formwork device is moved upward with a jar to form the weir. A waste form is formed by repeating two or more construction steps in which concrete is poured between the boards, and a dam or the like is formed by pouring concrete between the waste forms.

(6)実施例 本発明の1実施例を第1図乃至第3図に従って説明する
(6) Embodiment One embodiment of the present invention will be described with reference to FIGS. 1 to 3.

(1)は型枠装置を示し、該型枠装置(1)は間隔を存
して平行な左右のせき板(2)(2)と、これらを連結
固定する連結板(3)と、該連結板(3)に所定間隔を
以って設けた複数のジヤツキ(4)とからなる。
(1) shows a formwork device, and the formwork device (1) has left and right weir plates (2) (2) parallel to each other with an interval between them, a connecting plate (3) that connects and fixes these, and a It consists of a plurality of jacks (4) provided at predetermined intervals on a connecting plate (3).

次に上記型枠装置を用いたダムの施工について説明する
Next, construction of a dam using the above formwork device will be explained.

先ず形成予定のダムの両側端に当る位置にそれぞれ型枠
装22(1)をセットする。そしてせき板(2)(2)
の上端部間にコンクリートホースを挿入してこれらせき
板(2)(2)間にコンクリートを打設する。この打設
したコンクリートの硬化後ジヤツキ(4)は硬化したコ
ンクリートに立設の鉄筋(5)を反力にし第1図の如く
型枠装置(1)を上動する。そして所定の高さ上動じた
後前述の如くせき板(2)(2)間にコンクリートを打
設すると共に第2図の如く硬化したコンクリートの捨型
枠(6)にアンカーボルト(7)を固定する。
First, form fittings 22(1) are set at positions corresponding to both ends of the dam to be formed. And the weir plate (2) (2)
A concrete hose is inserted between the upper ends of the weir plates (2) and concrete is poured between the weir plates (2). After the cast concrete has hardened, the jack (4) uses the reinforcing bars (5) erected in the hardened concrete as a reaction force to move the formwork device (1) upward as shown in FIG. After moving up to a predetermined height, concrete is poured between the weir plates (2) and (2) as described above, and anchor bolts (7) are installed in the hardened concrete waste forms (6) as shown in Figure 2. Fix it.

その後第3図の如くこの両槽型枠(6)(6)間にコン
クリートを打設してコンクリート中間部(8)を形成す
る。以後以上の施工を繰り返してダムを形成してい〈。
Thereafter, as shown in FIG. 3, concrete is poured between the two tank forms (6) to form a concrete intermediate portion (8). After that, the above construction was repeated to form the dam.

(7)発明の効果 このように本発明の施工方法によると間隔を存して主行
な左右のせき板の上端部間を、ジヤツキを設けた連結板
により連結固定して構成した型枠装置を、立設した鉄筋
に反力をもたせて前記ジヤツキにより上動しながら前記
せき板間にコンクリートを打設して両槽型枠を形成し、
これら両槽型枠間にコンクリートを打設してダム等のマ
スコンクリート構造物を形成するようにしたので、従来
の如く型枠のセットのためのアンカーボルトの脱着が不
必要となり、又作業が全て内側で行うので危険な作業が
なくなると共に、型枠装置の移動セットの自動化が可能
となって作業能率が格段に向上する等の効果を有する。
(7) Effects of the Invention As described above, according to the construction method of the present invention, a formwork device is constructed in which the upper ends of the left and right main weir plates are connected and fixed with a gap between them by connecting plates provided with jacks. and pouring concrete between the weir plates while applying a reaction force to the upright reinforcing bars and moving them upward by the jacks to form the formwork for both tanks;
By pouring concrete between these two tank formworks to form mass concrete structures such as dams, it is no longer necessary to attach and remove anchor bolts to set the formwork as in the past, and the work is simplified. Since everything is done inside, dangerous work is eliminated, and the moving set of the formwork device can be automated, which greatly improves work efficiency.

【図面の簡単な説明】[Brief explanation of drawings]

第1図乃至第3図は本発明によりダムを施工する状態を
示す断面図、第4図は従来の方法によりダムを施工する
状態を示す断面図である。 (1)・・・型枠装置 (2)・・・せき板 (3)・・・連結板 (4)・・・ジヤツキ (5)・・・鉄筋 (6)・・・捨型枠 第1図 第3図 第2図 第4図
1 to 3 are cross-sectional views showing a state in which a dam is constructed according to the present invention, and FIG. 4 is a cross-sectional view showing a state in which a dam is constructed by a conventional method. (1)... Formwork device (2)... Weir plate (3)... Connecting plate (4)... Jacket (5)... Reinforcement bar (6)... Disposal formwork No. 1 Figure 3 Figure 2 Figure 4

Claims (1)

【特許請求の範囲】[Claims] 間隔を存して平行な左右のせき板の上端部間を連結板に
より連結固定し、該連結板にジャッキを設けた型枠装置
の前記左右のせき板間にコンクリートを打設し、上方に
突出する鉄筋に反力をとって前記ジャッキにより前記型
枠装置を上動する施工方法において、前記コンクリート
の硬化により捨型枠を形成し、該すて型枠間にコンクリ
ートを打設してコンクリート構造物を形成することを特
徴とするマスコンクリート構造物の施工方法。
The upper ends of the left and right weir plates that are parallel to each other with a gap between them are connected and fixed by a connecting plate, and concrete is poured between the left and right weir plates of a formwork device in which a jack is installed on the connecting plate, and In a construction method in which the formwork device is moved upward by the jack by taking reaction force from the protruding reinforcing bars, a waste form is formed by hardening the concrete, and concrete is poured between the waste forms to form concrete. A construction method for a mass concrete structure characterized by forming a structure.
JP19998886A 1986-08-28 1986-08-28 Construction of mass-concrete structure Pending JPS6360315A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP19998886A JPS6360315A (en) 1986-08-28 1986-08-28 Construction of mass-concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP19998886A JPS6360315A (en) 1986-08-28 1986-08-28 Construction of mass-concrete structure

Publications (1)

Publication Number Publication Date
JPS6360315A true JPS6360315A (en) 1988-03-16

Family

ID=16416922

Family Applications (1)

Application Number Title Priority Date Filing Date
JP19998886A Pending JPS6360315A (en) 1986-08-28 1986-08-28 Construction of mass-concrete structure

Country Status (1)

Country Link
JP (1) JPS6360315A (en)

Similar Documents

Publication Publication Date Title
JP4252177B2 (en) Steel / concrete composite structure pier construction method
CN104131635B (en) Method and platform for constructing peripheral shear wall of prefabricated staircase
JP3707006B2 (en) New method for opening openings in existing masonry walls
JPS6360315A (en) Construction of mass-concrete structure
CN214061940U (en) Precast concrete assembled structure with rib mold structure
JPH05280012A (en) Movable formwork process and device used therefor
JPH11158813A (en) Concrete pier constructing method
JPH1129910A (en) Method for constructing concrete pier
JPH1136229A (en) Construction method for reinforced concrete bridge pier
JPH10252016A (en) Method for replacing bearing device
CN215442620U (en) Assembly for non-dismantling type floor slab
CN217840571U (en) Be applied to outsourcing concrete steel beam in assembled steel structure system
JPH10121417A (en) Concrete frame, and method for constructing concrete structure using this concrete frame
CN217652327U (en) Quick plugging device of concrete post-cast strip
JPH0649982A (en) Formwork unit and its construction
CN208105863U (en) Super large template is poured in the tall and big thin-wall embodiment that can integrally transport
CN218467104U (en) High-rise outer frame-free unilateral masonry formwork
JPH1121860A (en) Construction method for wall-form concrete structure
JPH0236848Y2 (en)
CN113863671A (en) Assembled lattice column and construction method for connecting assembled lattice column with structural slab
JPH0533628Y2 (en)
JP2700852B2 (en) Construction method of building
CN114352002A (en) Handling method for placing scaffold cantilever beam on shear wall
SU1189966A1 (en) Method of constructing building skeleton
JPH06185202A (en) Form and construction method of concrete structure using the same