JPH10252016A - Method for replacing bearing device - Google Patents

Method for replacing bearing device

Info

Publication number
JPH10252016A
JPH10252016A JP7917697A JP7917697A JPH10252016A JP H10252016 A JPH10252016 A JP H10252016A JP 7917697 A JP7917697 A JP 7917697A JP 7917697 A JP7917697 A JP 7917697A JP H10252016 A JPH10252016 A JP H10252016A
Authority
JP
Japan
Prior art keywords
temporary
bearing
bearing device
upper structure
replacing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP7917697A
Other languages
Japanese (ja)
Other versions
JP2980567B2 (en
Inventor
Takashi Maeda
隆志 前田
Masanori Takahara
正則 高原
Keizo Yamashita
圭三 山下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Oriental Construction Co
Original Assignee
Oriental Construction Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Oriental Construction Co filed Critical Oriental Construction Co
Priority to JP9079176A priority Critical patent/JP2980567B2/en
Publication of JPH10252016A publication Critical patent/JPH10252016A/en
Application granted granted Critical
Publication of JP2980567B2 publication Critical patent/JP2980567B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a method for performing the work of replacing a bearing device by safely installing a temporary support member with good operating efficiency in a small space between the upper end of a bridge pier and the lower surface of a bridge girder. SOLUTION: A method for replacing a bearing device, in a bearing structure in which an upper structure is borne by the bearing device installed on the upper surface of a lower structure, includes floating the upper structure from the bearing device 5 using a temporary support jack 16, shifting the load reaction of the upper structure to the temporary bearing member 17 from the temporary support jack 16 using the temporary bearing member 17 to perform the work of replacing the old bearing device 5 with a new one, and dismantling the temporary bearing member 17 in a subsequent working process. In that case, the upper structure floated from the bearing device 17 by the temporary support jack 16 is pierced with an inlet vertically penetrating it, and a fluid filler that hardens with the lapse of time, injected through the inlet from above, is extracted toward the outer surface of the lower structure and is hardened into a block shape as a temporary bearing member 17, which is dismantled after the work of replacing the old bearing device 5 with a new one is finished.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、例えば連続箱桁橋
など各種の構造物において、メタル沓,ゴム沓等の固定
支承装置の交換方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for replacing a fixed bearing device such as a metal shoe and a rubber shoe in various structures such as a continuous box girder bridge.

【0002】[0002]

【従来の技術】連続箱桁橋などでは、一般に橋桁は、橋
脚の上部にメタル沓やゴム沓などの固定支承装置を介し
て支持されているが、この固定支承装置が耐用年数に達
している場合や、最近の阪神淡路大地震等の教訓から将
来の大地震に備えて、メタル沓をゴム沓に交換したり、
古いゴム沓を新しいゴム沓に交換するなど、全国の橋で
支承装置の交換作業が行なわれており、この交換作業は
今後増大すると予想される。
2. Description of the Related Art In a continuous box girder bridge or the like, a bridge girder is generally supported on a pier through a fixed bearing device such as a metal shoe or a rubber shoe, but the fixed bearing device has reached the end of its useful life. In case or lessons learned from the recent Great Hanshin-Awaji Earthquake, in preparation for a future large earthquake, replace metal shoes with rubber shoes,
Replacement of bearings is being carried out on bridges nationwide, such as replacing old rubber shoes with new rubber shoes, and this replacement work is expected to increase in the future.

【0003】橋桁を支持する沓(以下支承装置という)
を交換する場合は、通常は、仮受けジャッキを用いて橋
桁を持上げて支承装置から浮かし、この状態に仮保持し
たうえ、橋脚上端面と橋桁下面との間に固定設置されて
いる支承装置を、この橋脚上端面及び、橋桁下面から切
離して撤去し、その後、新しい支承装置を所定の場所に
固定設置し、再度この支承装置を橋脚上端面と橋桁下面
に固定して支承装置の交換作業を完了する。
A shoe for supporting a bridge girder (hereinafter referred to as a bearing device)
When replacing the bridge, usually lift the bridge girder using a temporary receiving jack and float it from the bearing device, temporarily hold it in this state, and fix the bearing device fixedly installed between the upper end surface of the pier and the lower surface of the bridge girder. After detaching from the upper end surface of the pier and the lower surface of the bridge girder and removing it, fix the new bearing device in place and fix it to the upper end surface of the pier and the lower surface of the bridge girder again to replace the bearing device. Complete.

【0004】[0004]

【発明が解決しようとする課題】橋脚における支承装置
の交換作業に際して、旧支承装置を解体撤去し、新支承
装置の設置固定が完了するまでには数箇月という長期間
を必要とし、その間は橋桁を若干持上げて作業すること
になるが、数百トンもある橋桁を仮受けジャッキで長期
間持上げ支持することは不可能である。このため通常
は、橋桁を一旦ジャッキで持上げて支承装置から浮かし
た後、角材やブロック等の仮受け部材を橋脚上面と橋桁
の下面にかませて、仮受けジャッキと仮受け部材との間
で橋桁荷重の受け変えを行なって仮受けジャッキを撤去
することが行なわれる。
When replacing a bearing device on a pier, it takes a long time of several months until the old bearing device is disassembled and removed and the installation and fixing of the new bearing device are completed. However, it is impossible to lift and support hundreds of tons of bridge girders with temporary jacks for a long time. For this reason, usually, once the bridge girder is lifted by the jack and floated from the bearing device, the temporary receiving members such as square members and blocks are squeezed on the upper surface of the pier and the lower surface of the bridge girder, and between the temporary receiving jack and the temporary receiving member. The bridge girder load is changed and the temporary receiving jack is removed.

【0005】しかし、比較的重量があって、取扱いも容
易でない角材やブロック等の仮受け部材を橋脚上端と、
橋桁の下面に位置する狭い空間に運び込むのは困難な作
業で、かつ安全性にも問題があり、さらに、工期の長期
化や施工費のコストアップの要因となるという問題があ
った。
[0005] However, a temporary receiving member such as a square member or a block which is relatively heavy and is not easy to handle is attached to the upper end of the pier,
It is a difficult task to carry into a narrow space located under the bridge girder, and there is also a problem with safety. Further, there is a problem that the construction period is prolonged and construction costs are increased.

【0006】本発明は前記の問題点を解決した支承装置
の交換方法を提供することを目的とする。
An object of the present invention is to provide a method of replacing a bearing device which solves the above-mentioned problems.

【0007】[0007]

【課題を解決するための手段】前記の目的達成のため本
発明は、橋脚など下部構造物の上面に設置した支承装置
により橋桁など上部構造物を支承している支承構造であ
って、上部構造物を仮受けジャッキで支承装置から浮か
した後、上部構造物の荷重反力を前記仮受けジャッキか
ら仮支承部材に移行させて新旧の支承装置の交換作業を
行ない、その後の作業工程で仮支承部材を撤去する支承
装置の交換方法において、前記仮受けジャッキで支承装
置から浮かした上部構造物に、その上下方向に貫通する
注入孔を開設し、この注入孔の上方から注入した経時硬
化性流動充填材を下部構造物の上面に設置の囲い型枠内
に注出し、ブロック形状に形成硬化させて仮支承部材と
し、新旧の支承装置の交換作業が終了後、この仮支承部
材を解体撤去することを特徴とする。また本発明は、前
記上部構造物が、上スラブと下スラブとを有し、かつ上
下のスラブ間に支点上隔壁と、これを挟んで設けられる
両側隔壁を有する箱桁であり、前記注入孔は前記下スラ
ブを貫通して設けられ、この注入孔を通して充填される
前記経時硬化性流動充填材で形成される仮支承部材は前
記両側隔壁の下部位置に設けられことを特徴とする。
According to the present invention, there is provided a bearing structure for supporting an upper structure such as a bridge girder by a bearing device installed on an upper surface of a lower structure such as a pier. After the object is lifted from the bearing device by the temporary receiving jack, the load reaction force of the upper structure is transferred from the temporary receiving jack to the temporary supporting member, and the old and new bearing devices are exchanged. In the method of replacing a bearing device for removing a member, an injection hole is formed in the upper structure floated from the bearing device by the temporary receiving jack so as to penetrate the upper structure in a vertical direction. The filling material is poured into the surrounding formwork installed on the upper surface of the lower structure, formed into a block shape and hardened to form a temporary bearing member, and after the replacement work of the old and new bearing devices is completed, the temporary bearing member is dismantled and removed. And wherein the door. Further, the present invention is the box girder, wherein the upper structure has an upper slab and a lower slab, and has a fulcrum upper partition between upper and lower slabs, and a partition on both sides provided therebetween. Is provided so as to penetrate the lower slab, and a temporary bearing member formed of the time-hardening fluid filling material filled through the injection hole is provided at a lower position of the partition walls on both sides.

【0008】本発明によると、下部構造物の上面に設置
した支承装置によって上部構造物が支承されている構造
における前記支承装置の交換に際して、上部構造物を上
下方向に貫通する注入孔の上方から注入した硬化性流動
充填材を下部構造物の上面に設置の囲い型枠内に注出
し、ブロック形状に形成硬化させて上部構造の仮支承部
材を構築し、新旧支承装置の交換作業が終了後、この仮
支承部材を解体撤去するものであるから、支承装置が設
置される下部構造物の上面と、上部構造物の下面との間
の狭い空間において、前記仮支承部材を簡易な作業で構
築できる。また、上部構造物が隔壁で結合される上下の
スラブを有する箱桁であるときは、前記隔壁の下部に前
記仮支承部材を設置することで、箱桁の下部スラブを鉄
筋等で特別に補強する必要がなく、作業性が一層向上す
る。
According to the present invention, when replacing the bearing device in a structure in which the upper structure is supported by the bearing device installed on the upper surface of the lower structure, from above the injection hole vertically penetrating the upper structure. The poured hardening fluid filler is poured into the surrounding formwork installed on the upper surface of the lower structure, formed into a block shape and hardened to construct a temporary bearing member of the upper structure, and after the replacement work of the old and new bearing devices is completed Since the temporary bearing member is dismantled and removed, the temporary bearing member is constructed by a simple operation in a narrow space between the upper surface of the lower structure where the bearing device is installed and the lower surface of the upper structure. it can. Further, when the upper structure is a box girder having upper and lower slabs joined by partition walls, the lower slab of the box girder is specially reinforced with a reinforcing bar or the like by installing the temporary bearing member below the partition wall. There is no need to perform this, and workability is further improved.

【0009】[0009]

【発明の実施の形態】以下本発明の実施形態を図を参照
して説明する。図1には、支承装置(沓)で支持された
構造物の一具体例として連続箱桁橋の全体図が示されて
おり、例えば河川等の地盤1に一定の間隔をあけて複数
の橋脚2と橋台3が立設されており、橋脚2と橋台3の
上部4に設置されたメタル沓,ゴム沓等の支承装置5に
よって橋桁(橋桁)6が支持されている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings. FIG. 1 shows an overall view of a continuous box girder bridge as a specific example of a structure supported by a bearing device (a shoe). For example, a plurality of piers are provided at fixed intervals on the ground 1 such as a river. An abutment 2 and an abutment 3 are erected, and a bridge girder (bridge girder) 6 is supported by a bearing device 5 such as a metal shoe or a rubber shoe installed on the pier 2 and the upper part 4 of the abutment 3.

【0010】図2は図1のA部の拡大断面詳細図、図3
は図2の中央部たて断面図、図4は図2の橋脚上端部を
一部省略して示す平面説明図である。
FIG. 2 is an enlarged sectional detail view of a portion A in FIG.
2 is a vertical cross-sectional view of the center part of FIG. 2, and FIG. 4 is an explanatory plan view of the pier shown in FIG.

【0011】図2〜図11は既設の支承装置5を解体撤
去する作業工程を示し、図12〜図15は、新設の支承
装置5aを設置する作業工程を示す。
FIGS. 2 to 11 show work steps for dismantling and removing the existing support device 5, and FIGS. 12 to 15 show work steps for installing a new support device 5a.

【0012】支承装置解体の第1作業工程として示す図
2〜図3において、ゴム沓,メタル沓等の支承装置5は
下部構造物である橋脚上部4の上面7に1個又は複数設
置され、その下面が橋脚上部4に埋設の下部アンカーボ
ルト8により、当該橋脚上部4に固定されている。
In FIG. 2 to FIG. 3 shown as a first working process of disassembly of the bearing device, one or a plurality of bearing devices 5 such as rubber shoes and metal shoes are installed on the upper surface 7 of the pier upper part 4 which is a lower structure. The lower surface is fixed to the pier upper part 4 by a lower anchor bolt 8 buried in the pier upper part 4.

【0013】一方、橋脚上部4には、道路9が上面に設
けられた箱桁(橋桁)6が前記支承装置5を介して支持
されている。つまり、この箱桁6の下フランジ11の下
面12が前記支承装置5の上部にアンカーボルト(図示
省略する)を用いて固着されている。なお、図2に示さ
れるように支承装置5の直上位置及び、その両側位置に
おいて、箱桁6の上スラブ10と下スラブ11間に支点
上隔壁13と両側隔壁14,14が設けられている。
On the other hand, a box girder (bridge girder) 6 having a road 9 provided on the upper surface thereof is supported on the pier upper part 4 via the bearing device 5. That is, the lower surface 12 of the lower flange 11 of the box girder 6 is fixed to the upper portion of the bearing device 5 using an anchor bolt (not shown). As shown in FIG. 2, a fulcrum upper partition wall 13 and both side partition walls 14, 14 are provided between the upper slab 10 and the lower slab 11 of the box girder 6 at a position immediately above the bearing device 5 and at both side positions thereof. .

【0014】前記の橋桁支承構造における旧支承装置5
の交換作業の第1作業工程として、旧支承装置5を設置
する際に設けられた箱桁下面12と橋脚上面7のコンク
リートのジャッキ受け部15を取除く不陸整正作業を行
う。この作業に際しては、作業者が箱桁6の上面の道路
9と橋脚上面7の間に仮設したハシゴ(図示省略する)
を伝わって登り、降ろしながらこの橋脚上面7で作業す
る。また、橋脚上部4の周辺には、作業用の足場を設け
る(図示省略する)。
The old bearing device 5 in the bridge girder bearing structure described above.
As a first work step of the replacement work, the uneven ground adjustment work for removing the concrete jack receiving portion 15 of the box girder lower surface 12 and the pier upper surface 7 provided when the old bearing device 5 is installed is performed. In this work, a ladder (not shown) temporarily provided by the operator between the road 9 on the upper surface of the box girder 6 and the upper surface 7 of the pier.
Work on this pier upper surface 7 while climbing and descending. A work scaffold is provided around the pier upper part 4 (not shown).

【0015】図5には、第2作業工程が示されている。
ここでは、既設の支承装置5の両側に仮受けジャッキ
(850t)16をセットし、支承装置5のボルト関係
の緩みの確認を行ない、仮受けジャッキ16を作動して
支承装置5が受けていた箱桁6からの荷重反力をこの仮
受けジャッキ16に移行する。
FIG. 5 shows a second operation step.
Here, the temporary receiving jacks (850t) 16 are set on both sides of the existing bearing device 5, the bolts of the bearing device 5 are checked for looseness, and the temporary receiving jack 16 is actuated to receive the bearing device 5. The load reaction force from the box girder 6 is transferred to the temporary receiving jack 16.

【0016】図6には、第3作業工程が示されている。
ここでは、箱桁6からの荷重反力を仮受けジャッキ16
で支承した状態で、この仮受けジャッキ16から仮支承
部材17に移行させるため、この仮支承部材17を構築
する。
FIG. 6 shows a third operation step.
Here, the load reaction force from the box girder 6 is applied to the temporary receiving jack 16.
The temporary support member 17 is constructed in order to transfer from the temporary receiving jack 16 to the temporary support member 17 in a state where the temporary support member 17 is supported.

【0017】この仮支承部材17の構築方法が本発明の
主要素であり、図7に示す方法で行なわれる。図7にお
いて、箱桁6の下スラブ11の上下面に貫通して複数の
注入孔18を開設する。各注入孔18の上端は両側隔壁
14,14の下部に近接位置して下スラブ11の上面2
2に開口している。注入孔18の下端は、既設支承装置
5の両側において、仮受けジャッキ16の両隣りに開口
している。
The method of constructing the temporary bearing member 17 is the main element of the present invention, and is performed by the method shown in FIG. In FIG. 7, a plurality of injection holes 18 are opened through the upper and lower surfaces of the lower slab 11 of the box girder 6. The upper end of each injection hole 18 is located close to the lower part of both side walls 14, 14 and the upper surface 2 of lower slab 11
It is open to 2. The lower end of the injection hole 18 opens on both sides of the existing bearing device 5 on both sides of the temporary receiving jack 16.

【0018】また、注入孔18が囲い型枠の上部開放部
に位置するように橋脚上面7と箱桁6の下スラブ下面1
2との間に平面矩形に囲い型枠20を組む。(図7
(A)に示す)この場合、特に囲い型枠20は、前記各
両側隔壁14,14のそれぞれの真下になるように設け
る。
Further, the upper surface 7 of the pier and the lower surface 1 of the lower slab of the box girder 6 are so arranged that the injection hole 18 is located at the upper open portion of the surrounding formwork.
2 and form an enclosing formwork 20 in a plane rectangle. (FIG. 7
In this case, the enclosing form 20 is provided so as to be directly below each of the partition walls 14, 14, respectively.

【0019】つづいて、図7(A)に示すように、経時
硬化性流動充填材の一例として、無収縮モルタル21を
下スラブ上面22から注入孔18を通して平面矩形の囲
い型枠20の内側に注入し、箱桁6の下スラブ下面12
に届くまで充填する。このようにして充填した無収縮モ
ルタル21が時間経過に伴って乾燥硬化した後、型枠2
0を離型することで、ブロック形状の仮支承部材17が
橋脚上面7の上面で、かつ両側隔壁14,14のそれぞ
れの真下に構築される。その後、注入孔18は適宜の手
段で密閉する。
Subsequently, as shown in FIG. 7 (A), as an example of a time-curable fluid filler, a non-shrink mortar 21 is inserted from the upper surface 22 of the lower slab through the injection hole 18 into the inside of the flat rectangular enclosure form 20. Inject and lower lower slab 12 of box girder 6
Fill until it reaches. After the non-shrink mortar 21 thus filled is dried and hardened with the lapse of time, the mold 2
By releasing the 0, the block-shaped temporary bearing member 17 is constructed on the upper surface of the pier upper surface 7 and directly below each of the partition walls 14, 14. Thereafter, the injection hole 18 is sealed by an appropriate means.

【0020】図8には、第4作業工程が示されている。
この作業工程では、仮支承部材17が構築された後、仮
受けジャッキ16を収縮させて撤去することにより、こ
の仮受けジャッキ16で受けていた箱桁6の荷重反力を
仮支承部材17に移行させる。
FIG. 8 shows a fourth operation step.
In this work process, after the temporary bearing member 17 is constructed, the temporary receiving jack 16 is contracted and removed, so that the load reaction force of the box girder 6 received by the temporary receiving jack 16 is applied to the temporary bearing member 17. Migrate.

【0021】図9には、第5作業工程が示されている。
この作業工程では、箱桁6の荷重を仮支承部材17で受
けたうえ、既設の支承装置5の上下部(上沓と下沓)を
ワイヤーソーで分断し、さらに小分割に切断して搬出撤
去する。
FIG. 9 shows a fifth operation step.
In this work process, the load of the box girder 6 is received by the temporary support member 17, and the upper and lower portions (upper and lower shoes) of the existing support device 5 are separated by a wire saw, and further cut into small portions and carried out. Remove it.

【0022】図10には、第6作業工程が示されてい
る。この作業工程では橋脚上面7において、アンカー部
のハツリと下部アンカーボルト8の撤去を行ない、新設
の支承装置のためのアンカーボルトの設置部まで、ハツ
リ位置24として示す範囲のハツリを行なう。また、箱
桁6の下スラブ下面12にある支承装置上部のアンカー
切断箇所25(図9に示す)の不陸整正を行なう。以上
で既設支承装置5の撤去が完了する。
FIG. 10 shows a sixth operation step. In this work process, on the pier upper surface 7, the anchor portion and the lower anchor bolt 8 are removed, and the area shown as the file position 24 is set up to the anchor bolt installation portion for the newly installed bearing device. In addition, irregularity adjustment of an anchor cutting portion 25 (shown in FIG. 9) at the upper part of the bearing device on the lower slab lower surface 12 of the box girder 6 is performed. Thus, the removal of the existing bearing device 5 is completed.

【0023】さらに、図10には新設の支承装置の組立
の最部の作業工程であり、まず箱桁6の下スラブ11を
貫通してアンカーボルト挿入孔26に上部アンカーボル
ト27を挿入し、上部をアンカーナットで止める。
Further, FIG. 10 shows the last operation step of assembling the newly installed bearing device. First, the upper anchor bolt 27 is inserted into the anchor bolt insertion hole 26 through the lower slab 11 of the box girder 6. Stop the upper part with an anchor nut.

【0024】図11、図12には、第7、第8作業工程
が示されている。この作業工程では、下スラブ下面12
にソールプレート28を当てがい、そのボルトを上部ア
ンカーボルト27に嵌合したうえ、アンカーナット30
で固定する。下スラブ下面12とソールプレート28と
の隙間は、樹脂、モルタル等で埋める。さらに、この作
業工程では、予めゴム沓である新設の支承装置5aのフ
ランジプレート31をセットボルト(図示省略)の中央
側6本で地組固定しておき、次に所定の位置に、ソール
プレート28と新設の支承装置5aのフランジプレート
を地組したものを、外側6本のセットボルトで固定す
る。
FIGS. 11 and 12 show the seventh and eighth working steps. In this work process, the lower slab lower surface 12
To the upper anchor bolt 27, and the anchor nut 30.
Fix with. The gap between the lower slab lower surface 12 and the sole plate 28 is filled with resin, mortar, or the like. Further, in this work process, the flange plate 31 of the newly-installed bearing device 5a, which is a rubber shoe, is fixed to the ground with six center bolts (not shown), and then the sole plate is placed at a predetermined position. 28 and the flange plate of the newly installed bearing device 5a are grounded and fixed with six set bolts on the outside.

【0025】図13には、第9作業工程が示されてい
る。この作業工程では、新設の支承装置5aにベッドプ
レート31、下部アンカーボルト32の固定をセットボ
ルトで行なう。
FIG. 13 shows a ninth working step. In this work process, the bed plate 31 and the lower anchor bolt 32 are fixed to the newly installed bearing device 5a with set bolts.

【0026】図14には、第10作業工程が示されてい
る。この作業工程では、橋脚上部4のハツリ位置24に
コンクリート33を打設して、その内部に下部アンカー
ボルト32を埋設させ、さらに、支承装置5aの支承座
34となる無収縮モルタルを打設する。つづいて、仮支
承部材17をワイヤーソーにより切断し解体撤去して支
承装置の交換作業は完了する。図15には、作業完了時
の状況が示されている。本発明では、前記作業工程を経
て橋脚上部において、新旧の支承装置の交換作業が円滑
に行われるものである。
FIG. 14 shows the tenth working step. In this work process, concrete 33 is cast at the scribing position 24 of the pier upper part 4, the lower anchor bolt 32 is buried therein, and further, a non-shrink mortar serving as a bearing seat 34 of the bearing device 5a is cast. . Subsequently, the temporary bearing member 17 is cut with a wire saw, disassembled and removed, and the replacement of the bearing device is completed. FIG. 15 shows a state at the time of completion of the work. According to the present invention, the operation of replacing the old and new bearing devices is performed smoothly in the upper part of the pier through the above-mentioned work process.

【0027】[0027]

【発明の効果】以上説明したように、本発明によると、
下部構造物の上面に設置した支承装置によって上部構造
物が支承されている構造における支承装置の交換に際し
て、上部構造物を上下方向に貫通する注入孔の上方から
注入した硬化性流動充填材を下部構造物の上面に設けた
囲い型枠内に注出し、ブロック形状に形成硬化させて上
部構造の仮支承部材を構築し、新旧の支承装置の交換作
業が終了後、仮支承部材を解体撤去するものであるか
ら、支承装置が設置される下部構造物の上面と、上部構
造物の下面との間の狭い空間において、前記仮支承部材
を簡易かつ安全な作業で構築でき、その仮支承は確実と
なり、かつこれを切断解体して撤去する作業も容易であ
るというすぐれた効果がある。また、上部構造物が、上
スラブと下スラブの間に隔壁を有した箱桁の場合は、前
記仮支承部材を前記下スラブの下部位置に施設置するこ
とにより、前記下スラブの補強が不要となるというすぐ
れた効果がある。
As described above, according to the present invention,
When replacing the bearing device in a structure in which the upper structure is supported by the bearing device installed on the upper surface of the lower structure, the curable fluid filler injected from above the injection hole vertically penetrating the upper structure is moved downward. Pour into the surrounding formwork provided on the upper surface of the structure, form and harden it into a block shape to build a temporary support member of the upper structure, dismantle and remove the temporary support member after the replacement work of the old and new bearing devices is completed Therefore, in a narrow space between the upper surface of the lower structure where the bearing device is installed and the lower surface of the upper structure, the temporary bearing member can be constructed by a simple and safe operation, and the temporary bearing is reliably mounted. In addition, there is an excellent effect that it is easy to cut and disassemble and remove it. When the upper structure is a box girder having a partition wall between the upper slab and the lower slab, the provision of the temporary bearing member at a position below the lower slab eliminates the need for reinforcement of the lower slab. Has an excellent effect.

【図面の簡単な説明】[Brief description of the drawings]

【図1】連続箱桁橋の全体図である。FIG. 1 is an overall view of a continuous box girder bridge.

【図2】本発明の第1作業工程の説明を兼ねて図示する
図1A部の拡大断面詳細図である。
FIG. 2 is an enlarged cross-sectional detailed view of a part A in FIG. 1 also illustrating a first operation step of the present invention.

【図3】図2の中央部たて断面図である。FIG. 3 is a vertical cross-sectional view of a central part of FIG. 2;

【図4】図2の橋脚上部の一部省略して示す平面説明図
である。
FIG. 4 is an explanatory plan view showing a part of an upper part of a pier in FIG. 2 with a part omitted;

【図5】(A)は本発明の支承装置交換方法の第2作業
工程における支承部構造の断面図、(B)は同図(A)
の中央部半截断面図である。
FIG. 5A is a sectional view of a bearing structure in a second operation step of the bearing device replacement method of the present invention, and FIG. 5B is a view of FIG.
3 is a half sectional view of a central part of FIG.

【図6】(A)は第3作業工程における支承部構造の断
面図、(B)は同図(A)の中央部半截断面図である。
FIG. 6A is a sectional view of a bearing structure in a third operation step, and FIG. 6B is a half sectional view of a central portion of FIG.

【図7】(A)は仮支承部材の構築作業工程を示す拡大
断面図、(B)は仮支承部材の構築完了条体を示す拡大
断面図である。
FIG. 7A is an enlarged cross-sectional view showing a construction process of a temporary support member, and FIG. 7B is an enlarged cross-sectional view showing a completed structure of the temporary support member.

【図8】(A)は第4作業工程における支承部構造の断
面図、(B)は同図(A)の中央部半截断面図である。
8A is a cross-sectional view of a bearing portion structure in a fourth operation step, and FIG. 8B is a half-sectional view of a central portion of FIG. 8A.

【図9】(A)は第5作業工程における支承部構造の断
面図、(B)は同図(A)の中央部半截断面図である。
9A is a sectional view of a bearing structure in a fifth operation step, and FIG. 9B is a half sectional view of a central portion of FIG. 9A.

【図10】(A)は第6作業工程における支承部構造の
断面図、(B)は同図(A)の中央部半截断面図であ
る。
FIG. 10A is a sectional view of a bearing portion structure in a sixth working step, and FIG. 10B is a half sectional view of a central portion of FIG.

【図11】(A)は第7作業工程における支承部構造の
断面図、(B)は同図(A)の中央部半截断面図であ
る。
11A is a cross-sectional view of a bearing structure in a seventh working process, and FIG. 11B is a half-sectional view of the center of FIG.

【図12】(A)は第8作業工程における支承部構造の
断面図、(B)は同図(A)の中央部半截断面図であ
る。
12A is a cross-sectional view of a bearing structure in an eighth working step, and FIG. 12B is a half-sectional view of a central portion of FIG.

【図13】(A)は第9作業工程における支承部構造の
断面図、(B)は同図(A)の中央部半截断面図であ
る。
13A is a cross-sectional view of a bearing structure in a ninth operation step, and FIG. 13B is a half-sectional view of a central portion of FIG.

【図14】(A)は第10作業工程における支承部構造
の断面図、(B)は同図(A)の中央部半截断面図であ
る。
14A is a sectional view of a bearing structure in a tenth working step, and FIG. 14B is a half sectional view of the center of FIG.

【図15】(A)は支承装置の交換作業完了状態におけ
る支承部構造の断面図、(B)は同図(A)の中央部半
截断面図である。
15A is a cross-sectional view of the support portion structure in a state where the replacement operation of the support device is completed, and FIG. 15B is a half-sectional view of the center of FIG.

【符号の説明】[Explanation of symbols]

1 地盤 2 橋脚 3 橋台 4 橋脚上部 5,5a 支承装置 6 箱桁 7 橋脚上面 8 下部アンカーボアルト 9 道路 10 上スラブ 11 下スラブ 12 下スラブ下面 13 支点上隔壁 14 両側隔壁 15 ジャッキ受部 16 仮受けジャッキ 17 仮支承部材 18 注入孔 20 型枠 21 無収縮モルタル 22 下スラブ上面 24 ハツリ位置 25 アンカー切断箇所 26 アンカーボルト挿入孔 27 上部アンカーボルト 28 ソールプレート 30 アンカーナット 31 フランジプレート 32 下部アンカーボルト 33 コンクリート 34 支承座 DESCRIPTION OF SYMBOLS 1 Ground 2 Bridge pier 3 Abutment 4 Upper pier 5,5a Bearing device 6 Box girder 7 Bridge pier upper surface 8 Lower anchor bolt 9 Road 10 Upper slab 11 Lower slab 12 Lower slab lower surface 13 Support point upper partition wall 14 Both side partition wall 15 Jack receiving portion 16 Temporary Receiving jack 17 Temporary bearing member 18 Injection hole 20 Formwork 21 Non-shrinkable mortar 22 Lower slab upper surface 24 Shearing position 25 Anchor cutting place 26 Anchor bolt insertion hole 27 Upper anchor bolt 28 Sole plate 30 Anchor nut 31 Flange plate 32 Lower anchor bolt 33 Concrete 34 bearing seat

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 下部構造物の上面に設置した支承装置に
より上部構造物を支承している支承構造であって、上部
構造物を仮受けジャッキで支承装置から浮かした後、上
部構造物の荷重反力を前記仮受けジャッキから仮支承部
材に移行させて新旧の支承装置の交換作業を行ない、そ
の後の作業工程で仮支承部材を撤去する支承装置の交換
方法において、前記仮受けジャッキで支承装置から浮か
した上部構造物に、その上下方向に貫通する注入孔を開
設し、この注入孔の上方から注入した経時硬化性流動充
填材を下部構造物の上面に設置の囲い型枠内に注出し、
ブロック形状に形成硬化させて仮支承部材とし、新旧の
支承装置の交換作業が終了後、この仮支承部材を解体撤
去することを特徴とする支承装置の交換方法。
1. A bearing structure for supporting an upper structure by a bearing device installed on an upper surface of a lower structure, wherein after the upper structure is lifted from the bearing device by a temporary receiving jack, the load on the upper structure is reduced. In the replacement method of the bearing device in which the reaction force is transferred from the temporary receiving jack to the temporary bearing member to replace the old and new bearing devices, and the temporary bearing member is removed in the subsequent work process, the temporary bearing jack is used to replace the bearing device. An injection hole that penetrates the upper structure floating vertically from the upper structure is opened, and the time-curable fluid filler injected from above the injection hole is poured into an enclosing formwork installed on the upper surface of the lower structure. ,
A method of replacing a bearing device, comprising forming and hardening a temporary support member into a block shape to form a temporary bearing member, and disassembling and removing the temporary bearing member after the replacement work of the old and new bearing devices is completed.
【請求項2】 前記上部構造物が、上スラブと下スラブ
とを有し、かつ上下のスラブ間に支点上隔壁と、これを
挟んで設けられる両側隔壁を有する箱桁であり、前記注
入孔は前記下スラブを貫通して設けられ、この注入孔を
通して充填される前記経時硬化性流動充填材で形成され
る仮支承部材は前記両側隔壁の下部位置に設けられこと
を特徴とする請求項1記載の支承装置の交換方法。
2. The injection box according to claim 2, wherein the upper structure is a box girder having an upper slab and a lower slab, and having a fulcrum upper partition between upper and lower slabs and both side partitions provided therebetween. 2. A temporary support member formed through the lower slab and formed of the time-curable fluid filling material filled through the injection hole is provided at a lower position of the partition walls on both sides. How to replace the bearing device described.
JP9079176A 1997-03-14 1997-03-14 How to replace the bearing device Expired - Fee Related JP2980567B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9079176A JP2980567B2 (en) 1997-03-14 1997-03-14 How to replace the bearing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9079176A JP2980567B2 (en) 1997-03-14 1997-03-14 How to replace the bearing device

Publications (2)

Publication Number Publication Date
JPH10252016A true JPH10252016A (en) 1998-09-22
JP2980567B2 JP2980567B2 (en) 1999-11-22

Family

ID=13682679

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9079176A Expired - Fee Related JP2980567B2 (en) 1997-03-14 1997-03-14 How to replace the bearing device

Country Status (1)

Country Link
JP (1) JP2980567B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103437304A (en) * 2013-09-04 2013-12-11 北京中交桥宇科技有限公司 Method for changing pot bearing by enlarging pier section
CN105350448A (en) * 2015-11-26 2016-02-24 四川省交通运输厅公路规划勘察设计研究院 Structure for preventing main beam of cable-stayed bridge structure system from generating negative reaction
JP2018204419A (en) * 2017-01-25 2018-12-27 オリエンタル白石株式会社 Bearing replacement method for existing concrete beam
CN110593114A (en) * 2019-09-27 2019-12-20 杭州悦为科技有限公司 Box girder construction method based on large-span box girder multi-hoop truss support bailey bracket
JP2020122356A (en) * 2019-01-31 2020-08-13 株式会社三井E&S鉄構エンジニアリング Method for replacing bridge bearing
CN113481882A (en) * 2021-06-30 2021-10-08 重庆建工第三建设有限责任公司 Bridge plate type rubber support and replacement construction method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103437304A (en) * 2013-09-04 2013-12-11 北京中交桥宇科技有限公司 Method for changing pot bearing by enlarging pier section
CN103437304B (en) * 2013-09-04 2016-04-13 北京中交桥宇科技有限公司 A kind of method increasing pier section replacing pot bearing
CN105350448A (en) * 2015-11-26 2016-02-24 四川省交通运输厅公路规划勘察设计研究院 Structure for preventing main beam of cable-stayed bridge structure system from generating negative reaction
JP2018204419A (en) * 2017-01-25 2018-12-27 オリエンタル白石株式会社 Bearing replacement method for existing concrete beam
JP2020122356A (en) * 2019-01-31 2020-08-13 株式会社三井E&S鉄構エンジニアリング Method for replacing bridge bearing
CN110593114A (en) * 2019-09-27 2019-12-20 杭州悦为科技有限公司 Box girder construction method based on large-span box girder multi-hoop truss support bailey bracket
CN113481882A (en) * 2021-06-30 2021-10-08 重庆建工第三建设有限责任公司 Bridge plate type rubber support and replacement construction method thereof

Also Published As

Publication number Publication date
JP2980567B2 (en) 1999-11-22

Similar Documents

Publication Publication Date Title
CN108951870B (en) Construction method of low-rise fully-assembled concrete shear wall structure system
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
CN108951869B (en) Low-rise fully-assembled concrete shear wall structure system
KR100837608B1 (en) J.K Bracket Method
JP2013518199A (en) Construction Method of Steel Composite Girder Bridge {ConstructionMethod SteelCompositeGirderBridge}
KR200418585Y1 (en) Steel support plate and we use this bearing swap method
JP2994222B2 (en) Construction method of cast-in-place slab of precast concrete girder and its formwork
JP7134070B2 (en) Construction method of top slab of underground structure
KR101954155B1 (en) Bridge with full-deck and protective wall, and construction method for the same
JP2980567B2 (en) How to replace the bearing device
KR101693767B1 (en) Method for constructing precast floor plate with expansion joint
JP5041481B2 (en) Updating method and structure of existing bearing device
JP2000045229A (en) Constructing method of bridge
KR101258841B1 (en) Precast concrete slab construction method of bridge
JP3824242B2 (en) Viaduct-free support construction method
KR200378428Y1 (en) Bridge bearing one body
JP7290461B2 (en) Connection structure of girders and precast floor slabs
CN214424101U (en) Unloading and column pulling structure of frame structure
KR20060079395A (en) Bridge bearing one body and installation method thereof
KR20010035151A (en) The manufacturing and construction method of composite girder with partial width slab concrete
JPH07233581A (en) Precast reinforced concrete board and concrete compond slab method
JP2022142330A (en) Method for replacing telescopic device
JP2011117234A (en) Method of constructing girder of viaduct or the like and precast girder lower part structural member used for the same
JP4555724B2 (en) Construction method of structures using precast concrete members
JPS59114313A (en) Construction of prestressed concrete floor panel in road bridge

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080917

Year of fee payment: 9

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080917

Year of fee payment: 9

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090917

Year of fee payment: 10

LAPS Cancellation because of no payment of annual fees