JPS6353329B2 - - Google Patents
Info
- Publication number
- JPS6353329B2 JPS6353329B2 JP14709483A JP14709483A JPS6353329B2 JP S6353329 B2 JPS6353329 B2 JP S6353329B2 JP 14709483 A JP14709483 A JP 14709483A JP 14709483 A JP14709483 A JP 14709483A JP S6353329 B2 JPS6353329 B2 JP S6353329B2
- Authority
- JP
- Japan
- Prior art keywords
- pilot
- stirring head
- rod
- starting shaft
- stirring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000003756 stirring Methods 0.000 claims description 32
- 238000009412 basement excavation Methods 0.000 claims description 17
- 238000000034 method Methods 0.000 claims description 11
- 239000000463 material Substances 0.000 claims description 10
- 238000005553 drilling Methods 0.000 claims description 9
- 238000007711 solidification Methods 0.000 claims description 4
- 230000008023 solidification Effects 0.000 claims description 4
- 239000002689 soil Substances 0.000 claims description 3
- 238000010586 diagram Methods 0.000 description 11
- 238000010276 construction Methods 0.000 description 9
- 229910000831 Steel Inorganic materials 0.000 description 6
- 239000010959 steel Substances 0.000 description 6
- 230000002265 prevention Effects 0.000 description 5
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 3
- 238000005452 bending Methods 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 239000008267 milk Substances 0.000 description 1
- 210000004080 milk Anatomy 0.000 description 1
- 235000013336 milk Nutrition 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2/00—General structure of permanent way
- E01B2/006—Deep foundation of tracks
Description
【発明の詳細な説明】
本発明は、土木工事における水平地盤改良を行
う方法に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for horizontal ground improvement in civil engineering work.
なお、本発明における「水平」とは、施工上差
支えない程度の傾斜を含むものとする。 Note that "horizontal" in the present invention includes an inclination that does not cause any problem during construction.
土木工事においてトンネル又は地下構造物等を
作る場合、掘削による地山のゆるみや地表面の変
形を抑止するとともに安全にトンネル等を掘削す
る必要があり、第1図に示す如く鉄道線路2下で
地表近くにトンネル1を掘削する場合はトンネル
1掘削に先立つてその上部及び両側の地盤がゆる
まない様な施工を行うことが必要である。 When building tunnels or underground structures during civil engineering work, it is necessary to prevent the loosening of the ground and deformation of the ground surface due to excavation, and to excavate the tunnels safely. When tunnel 1 is excavated near the ground surface, it is necessary to carry out construction work to prevent the ground above and on both sides from loosening prior to excavating tunnel 1.
従来、上記要件を満たすためにはパイプルーフ
工法が用いられた。この工法は第2図aに示す如
く、オーガー掘進機3にて水平に掘進しつつ鋼管
4を圧入する工法で、第2図bの連結方式と第2
図cの独立方式がある。第2図bは特殊な継手5
aを使用した鋼管矢板5を用いると周辺地山から
の漏水や崩壊がない。第2図cは鋼管4の周囲に
セメントミルク6を注入してルーフを形成したも
のである。 Conventionally, pipe roof construction methods have been used to meet the above requirements. As shown in Figure 2a, this construction method involves press-fitting the steel pipe 4 while horizontally digging with an auger excavator 3.
There is an independent method shown in Figure c. Figure 2b shows special joint 5
If the steel pipe sheet pile 5 using a is used, there will be no water leakage or collapse from the surrounding ground. In FIG. 2c, cement milk 6 is poured around the steel pipe 4 to form a roof.
以上の如き従来のパイプルーフ工法は、鋼管矢
板や鋼管を使用するので材料費が高く、鋼管等の
重量物運搬と取り扱いに手間がかかる欠点があつ
た。 Conventional pipe roof construction methods as described above have the drawbacks of high material costs due to the use of steel pipe sheet piles and steel pipes, and the time and effort required to transport and handle heavy objects such as steel pipes.
本発明は上述した事情に鑑みてなされたもので
あり、先ずパイロツトロツドによるパイロツト掘
削を行い、次にパイロツトロツドを撹拌ヘツドと
交換した後、パイロツト掘削孔にそつて撹拌ヘツ
ド基部の噴出口より地盤固化材を噴出せしめなが
ら上記撹拌ヘツドを回転・撹拌・引抜きすること
により改良柱を形成することを特徴とする水平地
盤改良の方法及び上記工程により改良柱をトンネ
ル掘削に先立ち該トンネル上部及び両側に所定本
数施工して柱列壁を設置することを特徴とする水
平地盤改良の方法を提供せんとするものである。 The present invention has been made in view of the above-mentioned circumstances. First, pilot excavation is carried out using a pilot rod, and then, after replacing the pilot rod with a stirring head, the ground solidification material is injected from the spout at the base of the stirring head along the pilot excavation hole. A horizontal ground improvement method characterized by forming an improved column by rotating, stirring, and pulling out the stirring head while ejecting water, and by the above process, a predetermined number of improved columns are formed at the top and both sides of the tunnel prior to tunnel excavation. It is an object of the present invention to provide a method for horizontal ground improvement characterized by constructing and installing columnar walls.
以下第3図〜第6図に基づいて詳細に説明す
る。第3図aは本発明の一実施例を示すパイロツ
ト掘削の説明図、第3図bは同、撹拌ヘツドによ
る撹拌・引抜きの説明図、第4図はパイロツトロ
ツドの斜視図、第4図bは撹拌ヘツドの側面図、
第4図cは同、正面図、第5図は本発明の施工順
序の説明図、第6図は本発明の柱列壁の配置説明
図である。 A detailed explanation will be given below based on FIGS. 3 to 6. Fig. 3a is an explanatory diagram of pilot excavation showing one embodiment of the present invention, Fig. 3b is an explanatory diagram of stirring and drawing by the stirring head, Fig. 4 is a perspective view of the pilot rod, and Fig. 4b is an explanatory diagram of the pilot excavation. Side view of the stirring head,
FIG. 4c is a front view of the same, FIG. 5 is an explanatory diagram of the construction order of the present invention, and FIG. 6 is an explanatory diagram of the arrangement of column walls of the present invention.
第3図aにおいて7はボーリング機で、発進立
坑8に据付けられ掘削ロツド9の先端には第4図
aに示す如き先端にビツト10aを有するパイロ
ツトロツド10がねじ等で取着されている。11
は到達立坑である。本発明を実施するには、先ず
第5図a,bに示す如く、発進立坑側からボーリ
ング機によりパイロツトロツド10を取着した掘
削ロツド9を回転・給進せしめ、無水あるいは有
水(極少量)掘削を行う。第5図c、第3図aに
示す如くパイロツトロツド10が到達立坑11に
貫通してパイロツト掘削が完了すると、第5図d
の如くパイロツトロツド10を取外し、eの如く
撹拌ヘツド12を取着する。撹拌ヘツド12は第
4図B,Cに示す例では数箇所に撹拌翼12aを
有し、撹拌ヘツド12の基部には地盤固化材の噴
出口12bが穿設されている。12cは共まわり
防止翼12dを有する共まわり防止装置で、回転
する撹拌翼12aと回転しない共まわり防止翼1
2dとで撹拌が効率良く行われるもので、本発明
の出願人が先に特願昭55−056970号(特開昭56−
153013号)として出願済みのものであるが、この
共まわり防止装置12cを有する撹拌ヘツドを使
用した方が本発明は有効に実施できるが、本発明
の方法は上記共まわり防止装置12cを有する撹
拌ヘツドを使用することに限定するものではなく
撹拌翼のみを有する撹拌ヘツドを使用しても良
い。第5図eに示す如く撹拌ヘツド12を取着す
ると同時に、第3図bにも示す如く地盤固化材の
注入ホース13aを有するスイベル13を掘削ロ
ツド9のボーリング機側端に取着する。次に第5
図f,gに示す如く、撹拌ヘツド12基部の噴出
口12b(第4図b)より地盤固化材を噴出せし
めつつ、先に貫通したパイロツト掘削孔にそつ
て、てん充・掘削・撹拌・引抜きを行う。上記作
業を発進立坑まで行つて撹拌翼を発進立坑側に引
抜くと一本の改良柱14が形成される。引続き第
6図に示す如く、施工すべきトンネル1の上部及
び両側に前以つて所定本数の改良柱14を施工す
ることにより柱列壁15を設置する。 In FIG. 3a, reference numeral 7 denotes a boring machine, which is installed in a starting shaft 8, and a pilot rod 10 having a bit 10a at its tip, as shown in FIG. 4a, is attached to the tip of a drilling rod 9 with screws or the like. 11
is the reaching shaft. To carry out the present invention, first, as shown in FIGS. 5a and 5b, the drilling rod 9 to which the pilot rod 10 is attached is rotated and fed by a boring machine from the starting shaft side, and the drilling rod 9 is rotated and fed from the starting shaft side, and the drilling rod 9 is rotated and fed from the starting shaft side. Perform excavation. When the pilot rod 10 penetrates the reaching shaft 11 and the pilot excavation is completed as shown in Fig. 5c and Fig. 3a,
Remove the pilot rod 10 as shown in (e) and attach the stirring head 12 as shown in (e). In the example shown in FIGS. 4B and 4C, the stirring head 12 has stirring blades 12a at several locations, and the base of the stirring head 12 is provided with spouts 12b for the ground solidifying material. 12c is a co-rotation prevention device having a co-rotation prevention blade 12d, which includes a rotating stirring blade 12a and a non-rotating co-rotation prevention blade 1.
The applicant of the present invention previously filed Japanese Patent Application No. 55-056970 (Japanese Unexamined Patent Application Publication No. 56-056-2000).
153013), the present invention can be carried out more effectively by using a stirring head having this co-rotation prevention device 12c, but the method of the present invention can be carried out more effectively by using a stirring head having the co-rotation prevention device 12c. The present invention is not limited to the use of a stirring head, and a stirring head having only stirring blades may be used. At the same time as the stirring head 12 is attached as shown in FIG. 5e, the swivel 13 having the soil solidification material injection hose 13a is attached to the boring machine side end of the excavation rod 9 as shown in FIG. 3b. Next, the fifth
As shown in Figures f and g, the ground solidifying material is jetted out from the spout 12b (Figure 4b) at the base of the stirring head 12, and the material is filled, excavated, stirred, and pulled out along the pilot drilling hole that was penetrated earlier. I do. When the above operation is performed up to the starting shaft and the stirring blade is pulled out toward the starting shaft, one improved column 14 is formed. Subsequently, as shown in FIG. 6, column walls 15 are installed by previously constructing a predetermined number of improved columns 14 at the top and both sides of the tunnel 1 to be constructed.
上記柱列壁15は、第6図bに示す如く、改良
柱14間が隙間を有する如く施工するか、第6図
aに示す如く改良柱14が互にラツプするよう、
改良柱の軸心間のピツチpを改良柱外径以下とす
ることができる。 The column walls 15 are constructed so that there are gaps between the improved columns 14, as shown in FIG. 6b, or so that the improved columns 14 overlap each other, as shown in FIG. 6a.
The pitch p between the axes of the improved column can be made equal to or less than the outer diameter of the improved column.
第6図aの如き互にラツプした柱列壁を施工す
るには、先ず1本置きに改良柱を施工し、次に該
改良柱間に改良柱を施工すると、パイロツト掘削
孔の曲りが少なく、改良柱相互のラツプ状態も完
全に仕上るものである。上記改良柱は互にラツプ
しているので周辺地山からの漏水を防止すること
ができる。 To construct a row of pillars that wrap around each other as shown in Figure 6a, first construct an improved pillar at every other pillar, and then construct improved pillars between the improved pillars to reduce the bending of the pilot excavation hole. , the lap condition between the improved pillars is also completely completed. Since the improved pillars overlap each other, water leakage from the surrounding ground can be prevented.
以上詳細に説明した如く、本発明の方法によれ
ば、パイロツト掘削により施工精度が保て、なお
かつ安価で能率良く水平地盤改良を行うことがで
き、トンネル又は地下構造物等を作るに先立つて
本発明による水平地盤改良を実施すると、掘削に
よる地山のゆるみや地表面の変形を抑止すること
ができる。 As explained in detail above, according to the method of the present invention, construction accuracy can be maintained through pilot excavation, horizontal ground improvement can be carried out at low cost and efficiently, and basic preparations can be carried out before constructing a tunnel or underground structure. By implementing the horizontal ground improvement according to the invention, loosening of the ground and deformation of the ground surface due to excavation can be suppressed.
第1図は鉄道線路下で地表近くにトンネルを施
工する場合の水平地盤改良の説明図、第2図は従
来の水平地盤改良のパイプルーフ工法の説明図、
第3図aは本発明の一実施例を示すパイロツト掘
削の説明図、第3図bは同、撹拌ヘツドによる撹
拌・引抜きの説明図、第4図aはパイロツトロツ
ドの斜視図、第4図bは撹拌ヘツドの側面図、第
4図cは同、正面図、第5図は本発明の施工順序
の説明図、第6図は本発明の柱列壁の配置説明図
である。
1……トンネル、7……ボーリング機、8……
発進立坑、9……掘削ロツド、10……パイロツ
トロツド、10a……ビツト、11……到達立
坑、12……撹拌ヘツド、12b……噴出口、1
4……改良柱、15……柱列壁、p……ピツチ、
D……改良柱外径。
Figure 1 is an explanatory diagram of horizontal ground improvement when constructing a tunnel near the ground surface under railway tracks, Figure 2 is an explanatory diagram of the conventional pipe roof construction method for horizontal ground improvement,
Fig. 3a is an explanatory diagram of pilot excavation showing one embodiment of the present invention, Fig. 3b is an explanatory diagram of stirring and drawing by the stirring head, Fig. 4a is a perspective view of the pilot rod, Fig. 4b 4c is a side view of the stirring head, FIG. 4c is a front view thereof, FIG. 5 is an explanatory diagram of the construction order of the present invention, and FIG. 6 is an explanatory diagram of the arrangement of column walls of the present invention. 1...tunnel, 7...boring machine, 8...
Starting shaft, 9...Drilling rod, 10...Pilot rod, 10a...Bit, 11...Achievement shaft, 12...Stirring head, 12b...Ejection port, 1
4...Improved pillar, 15...Column row wall, p...Pitzchi,
D...Improved column outer diameter.
Claims (1)
置したボーリング機を用いて、先端にビツトを有
するパイロツトロツドを取付けた掘削ロツドを回
転・給進せしめることにより、水平にパイロツト
掘削を行い、上記パイロツトロツドが到達坑に貫
通後、該パイロツトロツドを撹拌ヘツドと交換
し、次にパイロツト掘削孔にそつて撹拌ヘツド基
部の噴出口より地盤固化材を噴出せしめながら上
記撹拌ヘツドを回転・撹拌・引抜きすることによ
り土壌と地盤固化材とを強制撹拌して発進立坑ま
で引抜き、改良柱を形成することを特徴とする水
平地盤改良の方法。 2 発進立坑と到達立坑との間を、発進立坑に設
置したボーリング機を用いて、先端にビツトを有
するパイロツトロツドを取着した掘削ロツドを回
転・給進せしめることにより、水平にパイロツト
掘削を行い、上記パイロツトロツドが到達坑に貫
通後、該パイロツトロツドを撹拌ヘツドと交換
し、次にパイロツト掘削孔にそつて撹拌ヘツド基
部の噴出口より地盤固化材を噴出せしめながら上
記撹拌ヘツドを回転・撹拌・引抜きすることによ
り土壌と地盤固化材とを強制撹拌して発進立坑ま
で引抜き、改良柱を形成し、引続き上記工程で、
掘削すべきトンネル、地下埋設物等の上部及び両
側に前以つて所定本数の改良柱を形成することに
より、柱列壁を設置することを特徴とする水平地
盤改良の方法。 3 柱列壁を形成する改良柱間に隙間を有するこ
とを特徴とする特許請求の範囲第2項記載の水平
地盤改良の方法。 4 柱列壁を形成する改良柱の軸心間のピツチを
改良柱外径以下としたことを特徴とする特許請求
の範囲第2項記載の水平地盤改良の方法。[Scope of Claims] 1. A drilling machine installed in the starting shaft is used to rotate and feed a drilling rod equipped with a pilot rod having a bit at the tip, so that the distance between the starting shaft and the destination shaft is horizontal. Pilot excavation is carried out, and after the pilot rod has penetrated the reaching hole, the pilot rod is replaced with a stirring head, and then the stirring head is rotated while spouting the ground solidifying material from the spout at the base of the stirring head along the pilot excavation hole. - A horizontal ground improvement method characterized by forcibly stirring the soil and ground solidifying material by stirring and pulling it out to the starting shaft to form an improvement column. 2 Pilot excavation is performed horizontally between the starting shaft and the destination shaft by rotating and feeding a drilling rod equipped with a pilot rod with a bit at the tip using a boring machine installed in the starting shaft. After the pilot rod penetrates the reaching hole, the pilot rod is replaced with a stirring head, and then the stirring head is rotated, stirred, and pulled out while jetting the ground solidification material from the spout at the base of the stirring head along the pilot excavation hole. By this, the soil and ground solidification material are forcibly stirred and pulled out to the starting shaft to form an improved pillar, and then in the above steps,
A method of horizontal ground improvement characterized by installing column walls by forming a predetermined number of improvement columns in advance on the top and both sides of tunnels, underground structures, etc. to be excavated. 3. The method for horizontal ground improvement according to claim 2, characterized in that there is a gap between the improved pillars forming the pillar row wall. 4. The method for horizontal ground improvement according to claim 2, characterized in that the pitch between the axes of the improved columns forming the column walls is set to be equal to or less than the outer diameter of the improved columns.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14709483A JPS6040413A (en) | 1983-08-11 | 1983-08-11 | Improvement of horizontal ground |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14709483A JPS6040413A (en) | 1983-08-11 | 1983-08-11 | Improvement of horizontal ground |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS6040413A JPS6040413A (en) | 1985-03-02 |
JPS6353329B2 true JPS6353329B2 (en) | 1988-10-24 |
Family
ID=15422339
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP14709483A Granted JPS6040413A (en) | 1983-08-11 | 1983-08-11 | Improvement of horizontal ground |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6040413A (en) |
-
1983
- 1983-08-11 JP JP14709483A patent/JPS6040413A/en active Granted
Also Published As
Publication number | Publication date |
---|---|
JPS6040413A (en) | 1985-03-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102839661A (en) | Construction technology of reelingly stirring to eject anchor tube pile | |
WO2001023711A1 (en) | Ground reinforcing method | |
JP2806217B2 (en) | Underground excavator | |
JPS6353329B2 (en) | ||
JPS6353330B2 (en) | ||
JPH1150443A (en) | Underground consolidated body construction device and construction method thereof | |
JP2014177827A (en) | Core material and soil cement continuous wall construction method using the same | |
JP2933476B2 (en) | Underground pipe laying method | |
JPS5827366B2 (en) | Head reinforcement pile construction equipment | |
JPS594029B2 (en) | Penetration piping method and equipment that simultaneously strengthens the consolidation of the ground | |
JP2004218378A (en) | Removing method for existing pile | |
JP2645322B2 (en) | Construction method of soil cement composite pile | |
JPH02125016A (en) | Hollow drilling grouting method | |
JPS6332930B2 (en) | ||
JP2020169455A (en) | Construction method of soil cement continuous wall | |
JP3450639B2 (en) | Rock bolt driving method and rock bolt driving machine | |
JP3170604B2 (en) | Steel pipe construction method by medium digging method | |
JPS63300109A (en) | Method and apparatus for improving ground | |
JP3182586B2 (en) | Construction method of soil cement composite pile | |
JPH0941369A (en) | Method of remodeling and reinforcing construction of pile | |
JP7191327B2 (en) | How to remove steel pipe piles | |
JPH0637767B2 (en) | Ground improvement method combining agitation blades and high-pressure injection | |
JPH06100080B2 (en) | Large-section tunnel construction method and ground solidification column construction device | |
JPH0280790A (en) | Soil receiving work by horizontal auger | |
JP3146375B2 (en) | Existing structure retention method |