JPS6351568A - Construction of concrete structure and support member - Google Patents

Construction of concrete structure and support member

Info

Publication number
JPS6351568A
JPS6351568A JP19567786A JP19567786A JPS6351568A JP S6351568 A JPS6351568 A JP S6351568A JP 19567786 A JP19567786 A JP 19567786A JP 19567786 A JP19567786 A JP 19567786A JP S6351568 A JPS6351568 A JP S6351568A
Authority
JP
Japan
Prior art keywords
anchor
fitting
concrete
concrete structure
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP19567786A
Other languages
Japanese (ja)
Other versions
JPH068572B2 (en
Inventor
恒則 原田
宇田 斉史
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ohbayashi Gumi Ltd
Obayashi Corp
Original Assignee
Ohbayashi Gumi Ltd
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ohbayashi Gumi Ltd, Obayashi Corp filed Critical Ohbayashi Gumi Ltd
Priority to JP61195677A priority Critical patent/JPH068572B2/en
Publication of JPS6351568A publication Critical patent/JPS6351568A/en
Publication of JPH068572B2 publication Critical patent/JPH068572B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Movable Scaffolding (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Abstract] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は型枠の架台を兼ねる作業足場枠組が先行打設し
たコンクリート構造物外壁を支えとして順次に上昇移功
するコンクリート構造物の構築方法並びに支持部材に関
する。
[Detailed Description of the Invention] (Industrial Application Field) The present invention is a method for constructing a concrete structure in which a work scaffolding framework, which also serves as a frame for formwork, is sequentially moved up and down using the external wall of a concrete structure cast in advance as support. and a support member.

(従来の技術) 一般建築構造物の外壁や橋脚などのコンクリート構造物
に用いられている型枠作業等の作業足場枠組の架設はタ
ワークレーン等の大型揚更改を使用するので、現場での
鉄骨、鉄筋、架設材等の荷揚げと相俟って揚重計画が過
密になる一因となっていた。
(Conventional technology) The construction of work scaffolding frameworks for formwork work, etc. used for concrete structures such as external walls of general building structures and bridge piers, requires the use of large lifting equipment such as tower cranes. This, together with the unloading of reinforcing bars, construction materials, etc., contributed to the overcrowding of the lifting plan.

この事は、架設材のストックヤードが狭ければ尚更であ
り、積極的に揚重吊の低減を計るべき要請を生んでいる
This is especially true if the stockyard for construction materials is small, creating a demand for proactive efforts to reduce lifting loads.

そのために従来は先行打設コンクリート構造物に、足場
枠組の架台受はアンカ一部材を鉛直方向に幾つか取付け
るとともに、これらアンカ一部材によって鉛直方向に固
定止むした支+1を設けていた。そして、この支柱に上
って足場枠組を支持していた。
To this end, conventionally, in a pre-cast concrete structure, several anchor members were attached vertically to the pedestal support of the scaffolding frame, and a support +1 was provided which was fixed in the vertical direction by these anchor members. They then climbed onto these pillars to support the scaffolding framework.

足場枠組を次の行程に移動させる■)には、支柱を上方
のアンカ一部材に吊持したチェーンブロック等で引き上
げることにより、クレーンの使用を要しないものである
。例えば公間特公報昭57−33669号があった。
Moving the scaffolding framework to the next step (2) does not require the use of a crane, as the pillars are lifted up using chain blocks or the like suspended from an upper anchor member. For example, there was the Official Publication No. 57-33669.

この足場枠組では、その移動方向を確実にするために、
支柱の長さは少なくとも3階分に凹敵する位に長尺であ
る。したがって、重はも比較的に重くなるため、支社を
鞘構造とし、その軸方向中空内に補助支柱を貫通挿通し
、この補助支社を従前の如く長尺なものとし、鞘構造の
支柱部分は短尺にして足場枠組のフレーム等に固定する
ことにより、支柱に沿って足場枠組の移動作業を容易に
・「るとともに、支柱の軽量化を計ったものである。
In this scaffolding framework, in order to ensure the direction of movement,
The length of the pillars is so long that it spans at least three floors. Therefore, since it is relatively heavy, the branch is made into a sheath structure, and the auxiliary column is inserted through the hollow in the axial direction.The auxiliary branch is made as long as before, and the column part of the sheath structure is By making it short and fixing it to the frame of the scaffolding framework, it is possible to easily move the scaffolding framework along the support, and the weight of the support is also reduced.

で発明が解決しようとする問題点) しかし、それでも補助支柱は長尺であり・長尺1゛ある
ことから重量もあって取扱は面倒であるとy、。lわれ
る。また、補助支柱を受けるブラウン1〜の〕・ンカ一
部材と足場枠組を受けるアンカ一部材と14別にせざる
を1!7ずそれたけ手間がかかる欠点があった。
However, the auxiliary support is still long, and since it is 1゜ long, it is heavy and difficult to handle. I will be beaten. In addition, there was a drawback that it took a lot of time and effort to separate the anchor parts (14) for the Brown 1-1 anchors that received the auxiliary supports and the anchor parts 14 that received the scaffolding framework.

本発明は上述事情に鑑みてなされたものであって、その
目的は支柱を用いることなく、しかも簡略な揚重癲で簡
i1iに足場枠組を次工程へ移動させ得るコンクリート
構造物の構築方法と、そのために最適な架台受はアンカ
一部材等の支持部材を提供するにある。
The present invention has been made in view of the above-mentioned circumstances, and its purpose is to provide a method for constructing a concrete structure in which a scaffolding framework can be easily moved to the next process by simple lifting without using supports. For this purpose, the most suitable pedestal support is to provide a support member such as an anchor member.

(問題点を解決するための手[2> 上記目的を達成するために、本発明に係るコンクリート
構造物の構築方法は、コンクリート型枠と、これを支持
できる足場枠組と、先行打設コンクリート構造物外壁面
に固定可能l家アンh−金具と、足場枠組に一体的に固
定され、かつアンカー金具に係−止可能な係止金具とを
備え、直前にコンクリートの打設を終了したコンクリー
ト構造物の上部にアンカー金具を固定装″11シ、これ
に携帯揚千灘を取り付け、足場枠組の・系止金具に携帯
揚重機の吊上げワイヤを係止させ、然る後にコンクリー
ト型枠を伴う足場枠組を次のコンクリート打設位置迄必
要充分に吊り上げ上Hさせて、足場枠組の係止金具をア
ンカー金具に係止し、次いでhrr m機をアンカー金
具から取り外し、足場枠組上のコンクリート型枠を所定
位置に1.[zえつけ、コンクリートを打設し、これら
の順序を繰り返しながらコンクリート構造物を順次に上
方へ構築施工するものである。
(Measures to Solve the Problems [2] In order to achieve the above object, the method for constructing a concrete structure according to the present invention includes a concrete formwork, a scaffolding framework capable of supporting the same, and a pre-cast concrete structure. A concrete structure that is equipped with a metal fitting that can be fixed to the exterior wall surface of a building and a locking metal fitting that is integrally fixed to the scaffolding framework and can be locked to the anchor metal fitting, and that has just finished concrete pouring. Fix the anchor fittings to the top of the object, attach the mobile lift to it, lock the lifting wire of the portable lifting machine to the system locking fittings of the scaffolding framework, and then attach the scaffolding with the concrete formwork. The framework is hoisted up as far as necessary to the next concrete placement position, and the locking metal fittings of the scaffolding framework are locked to the anchor metal fittings.Then, the hrr m machine is removed from the anchor metal fittings, and the concrete formwork on the scaffolding framework is lifted up. 1) Place concrete in a predetermined position, and repeat these steps to construct a concrete structure upwards.

前記足場枠組をボンクリート構造物の外壁面に支持する
ための支持部材は、前記アンカー金具と前記係止金具ど
からなり、次の各ljら成要件を具えて成るのである。
The supporting member for supporting the scaffolding framework on the outer wall surface of the Boncrete structure is made up of the anchor fittings, the locking fittings, etc., and has the following components.

(a)係止金具は足場枠組の側端部に一体的に固定する
こと。
(a) The locking metal fittings shall be integrally fixed to the side edges of the scaffolding framework.

(b)係止金具は下方へ漸次拡大形成し、下方へ拡張開
放した案内切り欠きを有すること。
(b) The locking metal fitting has a guide notch that gradually expands downward and opens downward.

(c)アンカー金具はコンクリート構造物に設置したア
ンカーボルトに着脱自在なボルト孔を有すること。
(c) The anchor fittings shall have bolt holes that can be attached and detached to anchor bolts installed in the concrete structure.

(d)アンカー金具にはコンクリート構造物の外面から
離隔する方向へ突設した支承片を設けていること。
(d) The anchor fitting shall be provided with a bearing piece that projects in a direction away from the outer surface of the concrete structure.

(e)アンカー金具の支承片には上記係止金具の案内切
り欠き内に係止して係止金具を支承する支軸を着脱自在
に設けること。
(e) The support piece of the anchor fitting is removably provided with a support shaft that locks in the guide notch of the locking metal fitting and supports the locking metal fitting.

(f)アンカー金具の支承片の内側には係止金具を支承
片の内側へ案内する案内片を設けていること。
(f) A guide piece is provided inside the support piece of the anchor metal fitting to guide the locking metal fitting to the inside of the support piece.

(g>アンカー金具には揚重機の支柱を回動自在に支承
するために上方からU字状に切り欠いた支承溝を設ける
こと。
(g> Provide a U-shaped support groove cut out from above in the anchor fitting to rotatably support the column of the lifting machine.

(作 用) コンクリート構造物の外壁に、予め幾つかを鉛直方向に
整列埋設しているアンカーボルトにアンカー金具のポル
I〜孔を通し、ナツトを緊締螺合して上記)壁面上にア
ンカー金具を固定する。
(Function) Pass the hole I of the anchor fitting through the hole I of the anchor fitting through the anchor bolts which are lined up vertically and buried in the outer wall of the concrete structure in advance, tighten the nut and screw the anchor fitting onto the wall surface (above). to be fixed.

次に、アンカー金具の支承片に支軸を装着し、足場枠組
を上方からアンカー金具に降すのであるが、その際には
係止金具をアンカー金具の案内片に沿わせてそのまま降
ろすと、係止金具の案内切欠きの切欠き端縁に沿ってそ
の上端縁に支軸が収まる。
Next, the support shaft is attached to the support piece of the anchor metal fitting, and the scaffolding framework is lowered onto the anchor metal fitting from above, but when doing so, the locking metal fitting is lowered along the guide piece of the anchor metal fitting. The support shaft is accommodated along the notch edge of the guide notch of the locking fitting and on the upper edge thereof.

すなわち、足場枠組は係止金具をアンカー金具に掛り合
せてコンクリート構造物の外壁面側に支持される。
That is, the scaffolding framework is supported on the outer wall side of the concrete structure by engaging the locking metal fittings with the anchor metal fittings.

以上の段取りとは逆に、足場枠組を上方へ吊り揚げれば
、係止金具の案内切り欠きは下方が開放されているので
、足場枠組はそのままアンカー金具から離脱する。そし
て、その下方に設けたアンカー金具で支持しているチェ
ーンブロック、ジヤツキ等比較的小型で携帯可能な揚重
橙で次工程に合せた位置迄足場枠組の上昇操作を行うも
のである。
Contrary to the above setup, if the scaffolding framework is lifted upward, the guide notch of the locking fitting is open at the bottom, so the scaffolding framework can be detached from the anchoring fitting as it is. Then, using a relatively small and portable lifting device such as a chain block or jack supported by an anchor fitting provided below, the scaffolding framework is lifted to a position suitable for the next process.

(実施例) 以下、本発明の好適な実施例について、図面を参照にし
て説明する。
(Embodiments) Hereinafter, preferred embodiments of the present invention will be described with reference to the drawings.

第1図から第3図迄はコンクリート構造物1の構築方法
を順次に示しており、第1図はコンクリート構造物1の
2階(2F)から4階(4F)部分迄が打設を完了して
養生をN V:L、lている処を示している。次に4上
部分の養生中のコンクリート強度が作業足場枠組2を支
持できる程度に達し次第、その次の工程である5F部分
を構築する[1的で、コンクリート型枠3を4F部分迄
の既施工コンクリートhM ’rFa ’ll!I 1
上にせり上げるものである。
Figures 1 to 3 sequentially show the construction method of concrete structure 1, and Figure 1 shows the completion of pouring from the second floor (2F) to the fourth floor (4F) of concrete structure 1. It shows where the curing is done. Next, as soon as the strength of the curing concrete in the upper part of 4 reaches a level that can support the work scaffolding framework 2, the next step is to construct the 5F part. Construction concrete hM 'rFa 'll! I 1
It is something that is raised upwards.

足場枠組2は約2階建に相当する高さで、その高さ方向
を四等分するように上下と中間とを合せて5段階の作業
′を場4を有し、それぞれ下から1段ステージ4a、2
段ステージ4b、3段ステージ4C14段ス1−ジ4d
、5段ステージ4eを備え、3段ステージ4C上には上
階構築用のコンクリ−1−型枠3が載置されるので、4
段、5段ステージ4d、40は、内側(建物側)への跳
出し部分を欠く。
The scaffolding framework 2 has a height equivalent to about two stories, and has a work site 4 in five stages including the top, bottom and middle so as to divide the height into four equal parts, each with one stage from the bottom. Stage 4a, 2
Stage 4b, 3rd stage 4C14 stage 1-4d
, a 5-stage stage 4e is provided, and concrete 1-formwork 3 for constructing the upper floor is placed on the 3-stage stage 4C.
The five-stage stages 4d and 40 lack a portion that protrudes inward (towards the building).

また、1段ステージ4aと3段ステージ4Cとの近傍に
」ま足場枠組2のフレームに一体に固定した係止金具5
があり、その対応位置においてコンクリート構造物1の
壁面に取り付けたアンカー金具6があり、係止金具5を
アンカー金具6に止着することにより、足場枠組2をコ
ンクリート構造物1の外壁面に取り付けている。
In addition, a locking metal fitting 5 integrally fixed to the frame of the scaffolding framework 2 is provided near the first stage 4a and the third stage 4C.
There is an anchor fitting 6 attached to the wall surface of the concrete structure 1 at the corresponding position, and by fixing the locking fitting 5 to the anchor fitting 6, the scaffolding framework 2 is attached to the outer wall surface of the concrete structure 1. ing.

さて、コンクリート構造物1の4上部分にある程度の強
度がでた段階で次の工程へ移行するに当たっては次の手
順による。
Now, when the upper part 4 of the concrete structure 1 has a certain degree of strength, the next step is to proceed according to the following procedure.

まず、新しい躯体であるところの4上部分に残るコンク
リート型枠3を外し、作業足場403段ステージ4C上
に取り込む。それから第2図のように4上部分の上端付
近にアンカー金具6を取り付け、これに油圧ジヤツキ支
柱7を固定し、油圧ジヤツキ8(商品名油圧チルホール
)をジヤツキ支柱7に吊下する。次いでジτ・ツキ8か
ら垂下したワイV9の先端を3段ステージ4C近傍の係
止金具5に11トけ、ジヤツキ8で足場枠組2を吊持し
ている状態と成し、下方の1段ステージ4a近傍にある
アンカー金具6および、3段ステージ4C近傍にあるア
ンカー金具6の支軸15を撤去する。
First, the concrete formwork 3 remaining on the upper part of the new frame is removed and placed on the work scaffolding 403 stage 4C. Then, as shown in FIG. 2, an anchor fitting 6 is attached to the vicinity of the upper end of the upper part of 4, a hydraulic jack column 7 is fixed thereto, and a hydraulic jack 8 (trade name: Hydraulic Chill Hole) is suspended from the jack column 7. Next, put the tip of the wire V9 hanging from the jack 8 to the locking fitting 5 near the third stage 4C, so that the scaffold framework 2 is suspended by the jack 8, and the lower one stage The anchor fitting 6 near the stage 4a and the support shaft 15 of the anchor fitting 6 near the third stage 4C are removed.

然る後にジヤツキ8で足場枠組2を吊り上げる。After that, the scaffolding framework 2 is lifted up by the jack 8.

3段ステージ4Cがコンクリ−1〜構造物1の4F部分
頂部に設定したジヤツキ支柱7のアンカー金具6近くま
でくるように吊り上げ、更に、3段ステージ4Cの所に
ある係止金具5がジヤツキ支柱のアンカー金具6の位置
よりも少し上の位置になるよう上げ越す。それから第3
図に示ず如く足場枠組2の中段および最下段である3段
ステージ4Cおよび1段ステージ4a付近のアンカー金
具6゜6の対応位置にきた係止金具5がこれに掛り合う
ように各アンカー金具6,6に支軸15をセットし、前
記上げ越し分だけ足場枠組2を下部させ、上下の係止金
具5と上下のアンカー金具6とを係合連結する。なお、
足場枠組の荷重の支持は、上側のアンカーにより行わせ
、下側のアンカーは振れ止め作用のみ行わせるため、上
下の係止金具の間隔を、上下のアンカー金具の間隔より
若干小さくしておく(第4図の係止金具の位置関係を参
照)次に、−ワイヤ9の先端部を3段ステージ4Cの所
の係止金具5から外し、ワイヤ9を巻き上げてジヤツキ
支社7及び油圧ジヤツキ8を撤去し、コンクリート型枠
3を水平方向へ前進さけ、コンクリート構造物1の5F
部分に該当する構造物を構築するために型枠3をセット
して、足場枠組2、コンクリート型枠3、作業足場4の
リフトアップ作業は完結する。なお、リフトアップの際
の振れを少なくするために、アンカー金具6に水平ガイ
ドアーム22を取付け、その先端に切欠き加工した鋼管
を取付けて水平ガイド23となし、これを足場枠組2の
建地2aに係合させる。ただし、リフトアップ作業は、
強風時には行わないので建地に特別の補強をすることを
要しない。
Lift the 3rd stage 4C so that it comes close to the anchor fitting 6 of the jacking post 7 set at the top of the 4F section of the concrete 1 to structure 1, and then lift the locking fitting 5 at the 3rd stage 4C to the jacking post. Raise it so that it is slightly above the position of the anchor fitting 6. then the third
As shown in the figure, the anchor fittings 5, which have come to the corresponding positions of the anchor fittings 6°6 near the third stage 4C and the first stage 4a, which are the middle and lowest stages of the scaffolding framework 2, engage with each anchor fitting. The supporting shafts 15 are set on the shafts 6, 6, the scaffolding framework 2 is lowered by the above-mentioned lifting amount, and the upper and lower locking fittings 5 and the upper and lower anchoring fittings 6 are engaged and connected. In addition,
The load of the scaffold framework is supported by the upper anchor, and the lower anchor only acts as a steady rest, so the distance between the upper and lower locking metal fittings should be made slightly smaller than the distance between the upper and lower anchor metal fittings ( (Refer to the positional relationship of the locking metal fittings in Fig. 4) Next, remove the tip of the wire 9 from the locking metal fitting 5 at the third stage 4C, wind up the wire 9, and connect the jack branch 7 and the hydraulic jack 8. Remove it, move the concrete formwork 3 horizontally, and move it to the 5th floor of concrete structure 1.
The formwork 3 is set to construct the structure corresponding to the part, and the lifting work of the scaffolding framework 2, concrete formwork 3, and work scaffolding 4 is completed. In order to reduce vibration during lift-up, a horizontal guide arm 22 is attached to the anchor fitting 6, and a notched steel pipe is attached to the tip of the arm to form a horizontal guide 23. 2a. However, lift-up work
Since this is not done during strong winds, there is no need for special reinforcement of the building site.

油圧ジヤツキ8の代りにチェーンブロックでも充分であ
り、タワークレーン等の楊重滋は一切使用せずに済む。
A chain block is also sufficient in place of the hydraulic jack 8, and there is no need to use a tower crane or the like at all.

以下、叙述したコンクリート構造物の構築方法にRNh
係止金具5とアンカー金具6とについて第4図以下に示
す。
Below, the method for constructing the concrete structure described is RNh.
The locking fitting 5 and the anchor fitting 6 are shown in FIG. 4 and below.

足場枠組2の両端には係止金具5を取り付けてあって、
その対応位置にはアンカー金具6を取り付けるためのア
ンカーボルト・10がコンクリート構造物1に埋設しで
ある。アンカーボルト10の先端が壁面外に残らないよ
うシーボルトを使用し、アンカー金具6をコンクリート
構造物1の覆面から取り外す際にシーボルトも共に撒去
する。
Locking fittings 5 are attached to both ends of the scaffolding framework 2,
Anchor bolts 10 for attaching anchor fittings 6 are buried in the concrete structure 1 at corresponding positions. A Siebold is used so that the tip of the anchor bolt 10 does not remain outside the wall surface, and the Siebold is also removed when the anchor fitting 6 is removed from the covering surface of the concrete structure 1.

係止金具5G、1板状体で、その下辺から上方へ切り込
まれた切り込みは板状体側面中央位冒から下辺へ向けて
案内切り欠き11としている。
The locking fitting 5G is a plate-like body, and a notch cut upward from the lower side forms a guide notch 11 extending from the center of the side surface of the plate-like body toward the lower side.

アンカー金具6は基板12上に並行に立;pした二枚の
支承片13−13を有し、この二枚の支承片13−13
の各側面略中央位置にボルト孔14−14を穿設し、こ
れにボルトを通し、ナツトで止め、支軸15としている
The anchor fitting 6 has two supporting pieces 13-13 that stand parallel to each other on the base plate 12, and these two supporting pieces 13-13
A bolt hole 14-14 is formed at approximately the center of each side surface of the shaft, a bolt is passed through the hole, and the shaft is secured with a nut to form a support shaft 15.

また、支承片13−13の上辺からU字状に切り欠かれ
た窪み状の支承溝16−16が設置プられ、ざらに支承
片13−13の内側上下の各端部から各上下方向へ延出
された案内片17−17を協えている。
In addition, a U-shaped notch-shaped support groove 16-16 is installed from the upper side of the support piece 13-13, and is roughly extended from each upper and lower end of the inside of the support piece 13-13 in each vertical direction. The extended guide pieces 17-17 are aligned.

上記支−承溝16−16は油圧ジヤツキ支柱7の支持軸
を受は止めるものである。
The support groove 16-16 serves to receive the support shaft of the hydraulic jack column 7.

ところで、油圧ジヤツキ8のワイヤ9は係止金具5に引
!3にけるのがよいので、ワイヤ9の先端に設けたシャ
ンクル等を連結ザる連結孔18を係止金具5の比較的上
方に貫通形成している。
By the way, the wire 9 of the hydraulic jack 8 is pulled to the locking metal fitting 5! 3, a connecting hole 18 for connecting a shank or the like provided at the tip of the wire 9 is formed through the locking fitting 5 relatively above.

第8図に油圧ジヤツキ8と係止金具5等の状態をポリ。Figure 8 shows the condition of the hydraulic jack 8, locking fitting 5, etc.

コンクリート構造・物1の4F部分頂部に取り付けたア
ンカー金具6の支承溝16にジヤツキ支社7を支える支
し’r軸である横方向への係止ピン19を載置し、支社
7をアンカー金具6で支える。ずなわち、係止ピン19
を回動軸にして支柱7は若干コンクリ−1−構造物1の
方向または足場枠組2の方向へ僅かながら回動でさるよ
うになっている。
A horizontal locking pin 19, which is a supporting axis for supporting the jack branch 7, is placed in the support groove 16 of the anchor fitting 6 attached to the top of the 4F portion of the concrete structure/object 1, and the branch 7 is attached to the anchor fitting. Support with 6. That is, the locking pin 19
The support column 7 can be rotated slightly in the direction of the concrete 1-structure 1 or in the direction of the scaffolding framework 2 using the axis of rotation.

この回動角をA整づるために二枚の19120−20a
をジヤツキ支柱7の下端部内側(構造物1側〉に介設し
ている。
In order to adjust this rotation angle to A, two pieces of 19120-20a were used.
is interposed inside the lower end of the jack post 7 (on the structure 1 side).

これは、ジヤツキ支柱7の係止ピン19を回動軸とする
ジヤツキ支t↑7の傾斜角を調整するためのもので、コ
ンクリート構造物1寄りの楔20−208を打ち込めば
、ジヤツキ支柱7は躯体側(構造物1側)へ傾き、逆に
模20−208を引き扱けば足場枠組2の方へ傾く。そ
の傾き角は楔2O−20aの打ち込み深さにJ:って微
妙な調整が可能である。なお、支柱の左右方向(壁面に
平行な方向)の調整は、アンカー金具6の水平プレート
6aに取付番プた建入れ調整用ボルト24−24の上端
に支柱7の下端面を載せることにより、行なう。
This is to adjust the inclination angle of the jack support t↑7, which has the locking pin 19 of the jack support post 7 as its rotation axis. tilts toward the frame (structure 1 side), and conversely, when the model 20-208 is handled, it tilts toward the scaffolding framework 2. The angle of inclination can be finely adjusted by adjusting the driving depth of the wedge 2O-20a. In addition, adjustment of the column in the left-right direction (direction parallel to the wall surface) can be done by placing the lower end surface of the column 7 on the upper end of the erection adjustment bolt 24-24 whose mounting number is attached to the horizontal plate 6a of the anchor fitting 6. Let's do it.

油圧ジヤツキ8をジヤツキ支柱7に取り付けるには、ア
ンカー金具6の支軸15を支承片13−13から外して
支承片13−13をはさむ形で支柱7−7をはめこみ、
その係止ビン19を支承溝16−16内に収めればよい
。その前後への傾斜角はP!!2O−20aで調整する
。このようにしてアンカー金具6で支持した支柱7の上
端部に油圧ジヤツキ8の吊り下げフックを掛ける。
To attach the hydraulic jack 8 to the jack post 7, remove the support shaft 15 of the anchor fitting 6 from the support piece 13-13, and insert the support piece 7-7 into the support piece 13-13.
The locking pin 19 may be accommodated within the support groove 16-16. The angle of inclination to the front and back is P! ! Adjust with 2O-20a. The hanging hook of the hydraulic jack 8 is hung on the upper end of the column 7 supported by the anchor fitting 6 in this manner.

ジヤツキ8のワイヤ9先端に取り付けた吊点シャックル
21は係止金具5のM結孔18にボルトで連結する。
A hanging point shackle 21 attached to the tip of the wire 9 of the jack 8 is connected to the M connection hole 18 of the locking fitting 5 with a bolt.

以上の様にして、ジヤツキ8を作動してシVツクル21
を上昇させると、3段ステージ4Cの所の係止金具5は
その案内切り欠き11の下辺が開放されているので、そ
のままアンカー金具6の支軸15から離脱し、足場枠組
2はジヤツキ8で直上方向へ上界する。
In the above manner, the jack 8 is operated and the vehicle 21 is
When the locking metal fitting 5 at the third stage 4C is raised, the lower side of its guide notch 11 is open, so it separates from the support shaft 15 of the anchor metal fitting 6, and the scaffolding framework 2 is lifted by the jacks 8. It rises directly above.

更にそのまま上昇させると、係止金具5は」二方でジヤ
ツキ支柱7を支えているアンカー金具6に至る。また更
に上昇すると、その支承片13−13の間に案内片17
−17で誘導案内されながら支承片13−13間内に収
まる。そこで前述の通りボルト孔14に支@15をセッ
トし、足場枠組の荷重を支持する。
When raised further, the locking metal fitting 5 reaches the anchor metal fitting 6 that supports the jack post 7 on two sides. When it rises further, the guide piece 17 is placed between the support pieces 13-13.
-17 and fits between the supporting pieces 13-13. Therefore, as described above, the support @15 is set in the bolt hole 14 to support the load of the scaffolding framework.

(効 果) 以上詳しく述べたように、本発明に係るコンクリート構
造物の構築方法によれば、コンクリート構造物に着脱自
在なアンカー金具に係脱自在な小型の揚重機を軸支さU
、これによって型枠と共に足場枠組を引き上げるので、
タワークレーン等現場での鉄筋や鉄骨および架設材を揚
げたり支持する揚重機を使用せずに済む。したがって、
揚重計画の負担が軽減され、現場でのストックヤードの
問題とも相俟って作業工程の流れの効率化が図れる。
(Effects) As described in detail above, according to the method for constructing a concrete structure according to the present invention, a small lifting machine that can be freely connected to and detached from a concrete structure is pivotally supported by an anchor fitting that can be attached to and detached from a concrete structure.
, this will raise the scaffolding framework along with the formwork,
There is no need to use lifting equipment such as tower cranes to lift and support reinforcing bars, steel frames, and construction materials on site. therefore,
The burden of lifting plans will be reduced, and together with on-site stockyard problems, the work flow will become more efficient.

しかも、足場枠組を上昇させるための支柱は作業者が携
帯移動可能であり、支柱6呂が容易となるため、足場枠
組のリフトアップ作業が作業者に与える負担も軽くなっ
ている。
Furthermore, the support for lifting the scaffolding framework can be carried and moved by the worker, making it easier to lift up the support, thereby reducing the burden on the worker of lifting the scaffolding framework.

また本発明に係る支持部材によれば、係止金具には案内
切り欠きが設けられており、アンカー金具に71脱自在
な支軸から上方へ垂直に移動さけるだけで簡単に外れ、
係合させる時は逆に垂直方向上方から下方へ移動させる
だけでよい。したがって、足場枠組の上下運動で係脱が
可能であり、前後左右方向への運動機能を持たない携帯
楊重戊によって足場枠組を上下動させる場合には好都合
である。
Further, according to the support member according to the present invention, the locking metal fitting is provided with a guide notch, and the anchor metal fitting can be easily removed by simply moving vertically upward from the removable support shaft.
When engaging, it is only necessary to move from vertically upward to downward. Therefore, the scaffolding framework can be engaged and disengaged by vertical movement, which is convenient when the scaffolding framework is moved up and down by a mobile device that does not have a movement function in the front, rear, left, and right directions.

アンカー金具には上方からU字状に切り欠いた支承溝が
設けられているので、携帯揚重vtの支柱は上か、6j
!’L、込むだけで設置でき、容易に回動自在に軸支さ
せることが可能である。このことによって躯体、ベース
プレートの部の精度が悪い場合の支柱は入れ調整はもと
より、旋回は能を持たず、昇降は能だけの揚重機に多少
の前後傾斜角を与えることができるので、作業性の向上
に繋がる。このように、アンカー金具tま支柱の支持と
足場枠11の支持とを兼ねるのでアンカー設置数を少な
くひきる利点も有する。
The anchor fittings have a U-shaped support groove cut out from the top, so the support for the mobile lifting VT can be placed on the top or on the 6j.
! 'L, can be installed by simply inserting it, and can be easily pivoted for rotation. This not only makes it possible to insert and adjust the support when the precision of the frame and base plate is poor, but also to give a slight longitudinal inclination angle to the lifting machine, which has no turning ability but only lifting ability. This will lead to an improvement in In this way, since the anchor metal fittings serve both to support the pillars and to support the scaffolding frame 11, there is also the advantage that the number of anchors to be installed can be reduced.

さらに、アンカー金具には平行に立設した二枚の支承r
;があり、その上下両端に案内片が設けであるので、係
止金具をアンカー金具の所定位置に誘導することも簡単
に行える等、以上の如く種々の効果を奏するものである
Furthermore, the anchor fitting has two supports r installed in parallel.
; Since the guide pieces are provided at both the upper and lower ends, the locking metal fitting can be easily guided to a predetermined position of the anchor metal fitting, and various effects are achieved as described above.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図乃至第3図は方法の実施例を工程手順別に説明す
るために8χ略の側面を格別に示した側面図、第4図は
足場枠組の支持状態を示す側面図、第5図はアンカー金
具と係止金具との係合状態を示す横断面図、第6図は第
4図中のアーア矢視線で示す矢視図、第7図は同様に第
4図中のイーイ矢視枳で示す矢視図、第8図は足場枠組
をリフトアップする時の様子を示す側面図、第9図は第
8図中のウーウ矢視線で楔を示す矢視図である。 1・・・コンクリート構造物 2・・・足場枠組3・・
・コンクリート型枠  4・・・作業足場5・・・係止
金具      6・・・アンカー金具7・・・油圧シ
ャツ、ヤ支柱  8・・・ジヤツキ9・・・ワイヤ  
     11・・・案内切り欠き13・・・支承片 
     14・・・ボルト孔15・・・支 軸   
   16・・・支承溝17・・・案内片      
19・・・係止ビン特許出願人       株式会社
 大 林 組代 理 人       弁理士 −色 
健 捕間         弁理士 松 本 !lIt
  利第1図 第2図 第4図 第5図 a 第6図  第7図 第8図 手続有t1正書(自発) 昭和62年11月lO日 特許庁長官 小 川 邦 夫 殿 1、事件の表示 昭和61年特許願第195677号 2、発明の名称 コンクリート構造物の構築方法 並びに支持部材 3、補正をする者 事件との関係  特許出願人 住 所 大阪府大阪市東区京橋3丁目37番地名 称(
054)株式会社 大 林 組4、代理人 住 所 東京都港区新橋2丁目12番7号労金新橋ビル
71昔 TEt508−0336 (代)氏 名 (7
128>弁理士 −色 健 輔住  所  同  上 氏 名 (8768)弁理士 松 本 雅 利5、補正
の対象 明MJ8の「発明の詳細な説明」の欄 6、補正の内容 明細書第12頁の17行目と18行目の間に以下の文を
挿入する。
Figures 1 to 3 are side views showing the side of the 8x in order to explain the embodiment of the method step by step; Figure 4 is a side view showing the supporting state of the scaffolding framework; Figure 5 is a side view showing the supporting state of the scaffolding framework; A cross-sectional view showing the engaged state of the anchor metal fitting and the locking metal fitting, FIG. 6 is a view taken from the direction of arrow A in FIG. 4, and FIG. 7 is a view taken from arrow A shown in FIG. 8 is a side view showing the situation when lifting up the scaffolding framework, and FIG. 9 is a view showing the wedge in the direction of the arrow in FIG. 8. 1... Concrete structure 2... Scaffolding framework 3...
・Concrete formwork 4...Working scaffolding 5...Locking fittings 6...Anchor fittings 7...Hydraulic shirt, support column 8...Judges 9...Wire
11...Guide notch 13...Support piece
14... Bolt hole 15... Support shaft
16...Support groove 17...Guide piece
19... Locking bottle patent applicant Obayashi Corporation Representative Patent attorney - Color
Ken Torima Patent Attorney Matsumoto! lIt
Fig. 1 Fig. 2 Fig. 4 Fig. 5 a Fig. 6 Fig. 7 Fig. 8 Procedures t1 official document (spontaneous) November 1988 Indication Patent Application No. 195677 of 1985 2, Name of the invention Method for constructing concrete structures and supporting members 3, Relationship with the case of the person making the amendment Patent applicant address 3-37 Kyobashi, Higashi-ku, Osaka-shi, Osaka Prefecture Name (
054) Obayashi Gumi Co., Ltd. 4, Agent Address: 71 Rokin Shinbashi Building, 2-12-7 Shinbashi, Minato-ku, Tokyo TEt508-0336 (Representative) Name (7)
128> Patent Attorney - Kensuke Color Address Same as above Name (8768) Patent Attorney Masatoshi Matsumoto 5, Subject of Amendment MJ8, "Detailed Description of the Invention" column 6, Specification of Contents of Amendment, Page 12 Insert the following statement between lines 17 and 18.

Claims (2)

【特許請求の範囲】[Claims] (1)コンクリート型枠と、これを支持できる足場枠組
と、先行打設コンクリート構造物外壁面に固定可能なア
ンカー金具と、該足場枠組に一体的に固定され、かつ該
アンカー金具に係止可能な係止金具とを備え、直前にコ
ンクリートの打設を終了したコンクリート構造物の上部
にアンカー金具を固定装着し、これに携帯揚重機を取り
付け、該足場枠組の該係止金具に該携帯揚重機の吊上げ
ワイヤを係止させ、然る後に該コンクリート型枠を伴う
該足場枠組を次のコンクリート打設位置迄必要充分に吊
り上げ上昇させて、該足場枠組の該係止金具をアンカー
金具に係止し、次いで該揚重機を該アンカー金具から取
り外し、足場枠組上のコンクリート型枠を既設コンクリ
ート構造物の上階の所定位置に据え、コンクリートを打
設し、これらの順序を繰り返しながらコンクリート構造
物を順次に上方へ構築施工することを特徴とするコンク
リート構造物の構築方法。
(1) A concrete formwork, a scaffolding framework that can support it, an anchor fitting that can be fixed to the outer wall surface of the pre-cast concrete structure, and an anchor fitting that is integrally fixed to the scaffolding framework and can be latched to the anchor fitting. Fix the anchor fitting to the top of the concrete structure where concrete has just been poured, attach the portable lifting device to this, and attach the portable lifting device to the anchoring fitting of the scaffolding framework. The lifting wire of the heavy machinery is locked, and then the scaffolding framework with the concrete form is lifted up as far as necessary to the next concrete placement position, and the locking metal fittings of the scaffolding frame are connected to the anchor metal fittings. The lifting machine is then removed from the anchor fittings, the concrete formwork on the scaffolding framework is placed in a predetermined position on the upper floor of the existing concrete structure, concrete is poured, and the concrete structure is constructed by repeating these steps. A method of constructing a concrete structure characterized by sequentially constructing the concrete structures upward.
(2)前記足場枠組をコンクリート構造物の外壁面に支
持するための支持部材は、前記アンカー金具と前記係止
金具とからなり、次の各構成要件を具備することを特徴
とする。 (a)該係止金具は足場枠組の側端部に一体的に固定す
ること。 (b)該係止金具は下方へ漸次拡大形成し、下方へ拡張
開放した案内切り欠きを有すること。 (c)該アンカー金具は該コンクリート構造物に設置し
たアンカーボルトに着脱自在なボルト孔を有すること。 (d)該アンカー金具には該コンクリート構造物の外面
から離隔する方向へ突設した支承片を設けていること。 (e)該アンカー金具の支承片には上記係止金具の該案
内切り欠き内に係止して該係止金具を支承する支軸を着
脱自在に設けること。 (f)該アンカー金具の支承片の内側には該係止金具を
該支承片の内側へ案内する案内片を設けていること。 (g)該アンカー金具には揚重機の支柱を回動自在に支
承するために上方からU字状に切り欠いた支承溝を設け
ること。
(2) The support member for supporting the scaffolding framework on the outer wall surface of the concrete structure is characterized by comprising the anchor fitting and the locking fitting, and having the following constituent requirements. (a) The locking fittings shall be integrally fixed to the side ends of the scaffolding framework. (b) The locking metal fitting has a guide notch that gradually expands downward and opens downward. (c) The anchor fitting has a bolt hole that can be freely attached to and detached from an anchor bolt installed in the concrete structure. (d) The anchor fitting is provided with a support piece that projects in a direction away from the outer surface of the concrete structure. (e) The support piece of the anchor fitting is removably provided with a support shaft that locks in the guide notch of the locking metal fitting and supports the locking metal fitting. (f) A guide piece is provided inside the support piece of the anchor metal fitting to guide the locking metal fitting to the inside of the support piece. (g) The anchor fitting should be provided with a U-shaped support groove cut out from above in order to rotatably support the column of the lifting machine.
JP61195677A 1986-08-22 1986-08-22 Construction method of concrete structure and supporting member Expired - Lifetime JPH068572B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61195677A JPH068572B2 (en) 1986-08-22 1986-08-22 Construction method of concrete structure and supporting member

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61195677A JPH068572B2 (en) 1986-08-22 1986-08-22 Construction method of concrete structure and supporting member

Publications (2)

Publication Number Publication Date
JPS6351568A true JPS6351568A (en) 1988-03-04
JPH068572B2 JPH068572B2 (en) 1994-02-02

Family

ID=16345162

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61195677A Expired - Lifetime JPH068572B2 (en) 1986-08-22 1986-08-22 Construction method of concrete structure and supporting member

Country Status (1)

Country Link
JP (1) JPH068572B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0293453U (en) * 1989-01-10 1990-07-25
DE4216150A1 (en) * 1991-05-15 1992-11-19 Koji Hashimoto Highly corrosion-resistant amorphous alloy contg. chromium@ and titanium@ and/or zirconium@
JP2006241967A (en) * 2005-02-03 2006-09-14 Japan Steels International Inc External wall climbing device and external wall climbing method
JP2014111867A (en) * 2012-12-05 2014-06-19 Takenaka Komuten Co Ltd Building curing frame
JP2015048621A (en) * 2013-08-30 2015-03-16 川崎重工業株式会社 Low temperature storage tank and construction method thereof
CN115059041A (en) * 2022-06-23 2022-09-16 合肥工业大学 Self-lifting assembly type formwork for gate head box structure concrete

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5115021U (en) * 1974-07-20 1976-02-03
JPS5792266A (en) * 1980-11-28 1982-06-08 Shimizu Construction Co Ltd Installation of wall type construction with large form

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5115021U (en) * 1974-07-20 1976-02-03
JPS5792266A (en) * 1980-11-28 1982-06-08 Shimizu Construction Co Ltd Installation of wall type construction with large form

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0293453U (en) * 1989-01-10 1990-07-25
JPH0740030Y2 (en) * 1989-01-10 1995-09-13 株式会社大林組 Scaffold lifting support
DE4216150A1 (en) * 1991-05-15 1992-11-19 Koji Hashimoto Highly corrosion-resistant amorphous alloy contg. chromium@ and titanium@ and/or zirconium@
DE4216150C2 (en) * 1991-05-15 1997-02-13 Koji Hashimoto Process for the production of a highly corrosion-resistant amorphous alloy
JP2006241967A (en) * 2005-02-03 2006-09-14 Japan Steels International Inc External wall climbing device and external wall climbing method
JP4719517B2 (en) * 2005-02-03 2011-07-06 ジャパン スチールス インターナショナル株式会社 Exterior wall climbing apparatus and exterior wall climbing method
JP2014111867A (en) * 2012-12-05 2014-06-19 Takenaka Komuten Co Ltd Building curing frame
JP2015048621A (en) * 2013-08-30 2015-03-16 川崎重工業株式会社 Low temperature storage tank and construction method thereof
CN115059041A (en) * 2022-06-23 2022-09-16 合肥工业大学 Self-lifting assembly type formwork for gate head box structure concrete
CN115059041B (en) * 2022-06-23 2024-02-20 合肥工业大学 Self-lifting assembled form for lock head empty box structure concrete

Also Published As

Publication number Publication date
JPH068572B2 (en) 1994-02-02

Similar Documents

Publication Publication Date Title
US5469684A (en) Concrete building frame construction method
US5216867A (en) Well mast structure
US3185265A (en) Hoisting apparatus
US6021910A (en) Construction crane base
TW200532076A (en) The quick method of constructing strip foundations with longitudinal socket
CN114150766A (en) Prefabricated reinforced concrete column connecting joint and construction method thereof
JPS6351568A (en) Construction of concrete structure and support member
JP4511657B2 (en) Climbing crane support method and apparatus
CN114382170B (en) Construction method of upper prefabricated vertical component
US2825115A (en) Apparatus for handling forms
JP3023869B2 (en) Reinforcement structure of base frame when moving building
JP2009299346A (en) Construction method of building
CN111622347A (en) Cross-shaped node connecting structure of assembled frame structure and construction method thereof
JP3532161B2 (en) Tower construction machine and tower construction method
CN110872843B (en) Construction method for controlling verticality of foundation pit section steel lattice column
CN215249200U (en) Hoist device for assembly type building construction
CN214656379U (en) Integral steelframe platform rollover construction system of high mound hydraulic jacking
JP2000248632A (en) Floor climbing method of tower crane
CN212002184U (en) Hanging basket device for decoration of outer vertical surface of high-rise building
JP2712121B2 (en) Reinforcing bar mounting method, hanging jig used in the mounting method, and guide device
JPH02503582A (en) Method and device for constructing buildings by lifting slabs
JP3020023B2 (en) Structure removal method
JP2961299B2 (en) Inner scaffold for caisson, erection method and dismantling method
JPH09296610A (en) Outside curing unit
JPH0455094Y2 (en)