JPS6334242B2 - - Google Patents

Info

Publication number
JPS6334242B2
JPS6334242B2 JP1164480A JP1164480A JPS6334242B2 JP S6334242 B2 JPS6334242 B2 JP S6334242B2 JP 1164480 A JP1164480 A JP 1164480A JP 1164480 A JP1164480 A JP 1164480A JP S6334242 B2 JPS6334242 B2 JP S6334242B2
Authority
JP
Japan
Prior art keywords
pavement
grooves
work
day
cut
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP1164480A
Other languages
Japanese (ja)
Other versions
JPS56108403A (en
Inventor
Norihei Fukami
Kazutada Yamamoto
Yukihisa Kitamura
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sanwa Kizai Co Ltd
Original Assignee
Sanwa Kizai Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sanwa Kizai Co Ltd filed Critical Sanwa Kizai Co Ltd
Priority to JP1164480A priority Critical patent/JPS56108403A/en
Publication of JPS56108403A publication Critical patent/JPS56108403A/en
Publication of JPS6334242B2 publication Critical patent/JPS6334242B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Road Repair (AREA)

Description

【発明の詳細な説明】 この発明は、舗装道路に水道管等を埋設する場
合等に行われる舗装道路の掘削方法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for excavating a paved road, which is used when burying a water pipe or the like in the paved road.

一般に舗装道路に水道管等を埋設する作業は交
通の途絶えた夜間に行わなければならない。そこ
で従来は、まずカツターにより舗装面に必要間隔
をあけて2本の30mm〜50mmの溝巾の溝を切削し、
ついでブレーカーにより両溝間の舗装層を破壊剥
離した後、該破壊物を排出し、ついで舗装層の剥
離された凹みに砕石等を埋戻し、路面を仮復旧し
て第1日目の夜間作業を終了し、次に第2日目の
夜間作業として砕石を除くと共に路床に溝を開削
し、該溝内に水道管を埋設するという方法を採つ
ていたが、作業が繁雑で非能率的であり、切削さ
れた溝巾が広いためその凹みに砕石等を埋戻して
も自動車、オートバイ、自転車等の通行に支障を
来たす欠点があつた。
Generally, work to bury water pipes in paved roads must be done at night when traffic is interrupted. Therefore, conventionally, first, two grooves with a groove width of 30 mm to 50 mm were cut on the pavement surface with the necessary interval, using a cutter.
Next, after the pavement layer between both grooves was destroyed and peeled off using a breaker, the destroyed materials were discharged, and the dents in the pavement layer where the pavement layer had been peeled off were then backfilled with crushed stones, etc., the road surface was temporarily restored, and the night work began on the first day. The method was to remove the crushed stones, excavate a groove in the roadbed, and bury water pipes in the groove as night work on the second day, but the work was complicated and inefficient. The cut groove width was wide, so even if the groove was backfilled with crushed stone, etc., there was a drawback that it was a hindrance to the passage of cars, motorcycles, bicycles, etc.

本発明は作業の簡略化及び能率化を実現する新
規な舗装道路の掘削方法を提供することを目的と
するもので、その特徴は、第1日目の作業とし
て、舗装層の必要範囲内に該舗装層が剥離し易く
なるように適数本の切溝を小間隔で施し、次に第
2日目の作業として上記切溝の施こされた範囲の
舗装層を切溝から分割しつつ剥離し、ついで路床
に所要の掘削を施すところにある。
The purpose of the present invention is to provide a new paved road excavation method that simplifies and improves the efficiency of the work. An appropriate number of grooves are made at small intervals so that the pavement layer can be easily peeled off, and then as part of the work on the second day, the pavement layer in the area where the grooves have been made is divided from the grooves. The process involves stripping and then making the necessary excavations in the roadbed.

以下水道管埋設のための舗装道路掘削方法に実
施した例を示す図面を参照して本発明の詳細を説
明する。
The details of the present invention will be explained below with reference to drawings showing an example of a method for excavating a paved road for burying water pipes.

まず第1日目の夜間作業として、第1図示のよ
うに、円盤の周縁に切削ビツトを突設してなるカ
ツターデイスクを有する舗装切削機により、舗装
道路の舗装層1に、水道管埋設のための開削溝幅
dの範囲内で該舗装層1のほぼ全厚さに食い込む
多数本の30mm〜50mmの相当広い溝巾の切溝2……
を互に小間隔をあけて平行に切削し、それにより
上記開削溝幅dの範囲内の舗装層を切溝2……で
区分される多数の突条舗装ブロツク1′……に分
割する。上記切溝2……の間隔もしくは舗装ブロ
ツク1′……の幅は、該舗装ブロツク1′……が路
床3から剥離し易くなるような200mm〜250mmの小
間隔もしくは小幅である。
First, as night work on the first day, as shown in Figure 1, water pipes were buried in the pavement layer 1 of the paved road using a pavement cutting machine equipped with a cutter disc with cutting bits protruding from the periphery of the disc. A large number of cut grooves 2 having a considerably wide groove width of 30 mm to 50 mm cut into almost the entire thickness of the pavement layer 1 within the range of cut groove width d for...
are cut parallel to each other at small intervals, thereby dividing the pavement layer within the range of the cut groove width d into a large number of ridge pavement blocks 1' divided by the cut grooves 2 . The intervals between the grooves 2 and the widths of the paving blocks 1' are such small intervals or widths of 200 mm to 250 mm that the paving blocks 1' easily peel off from the roadbed 3.

上記カツターデイスクによる切溝2……の切削
時に生ずる切削ズリ4は舗装層1及び舗装ブロツ
ク1′……の上面に堆積する。
Cutting sludge 4 generated when cutting grooves 2 .

ついで、第2図示のように上記切削ズリ4を切
溝2……内に埋戻し、これで第1日目の作業を終
了する。このように切溝2……に切削ズリを埋戻
した舗装層は自動車、オートバイ、自転車等の通
行にほとんど支障がない。
Then, as shown in the second figure, the cutting sludge 4 is backfilled into the kerf groove 2, and the work for the first day is completed. The pavement layer in which cut grooves 2 have been backfilled with cutting waste in this way has almost no hindrance to the passage of cars, motorcycles, bicycles, etc.

次に、上記第1日目作業の翌日もしくは複数日
後の第2日目夜間作業として、バケツトにより上
記舗装ブロツク1′……を路床3から剥離して排
除し、ついで露出した路床3内に第3図示のよう
に所定幅及び深さの溝5を開削し、そして該溝5
内に水道管を埋設する。上記舗装ブロツク1′…
…の剥離作業は容易に行われる。
Next, on the second day's night work the day after or several days after the first day's work, the paving blocks 1'... are peeled off from the subgrade 3 using a bucket and removed, and then the exposed subgrade 3 is removed. A groove 5 of a predetermined width and depth is cut as shown in the third figure, and the groove 5 is
Water pipes will be buried inside. The above paving block 1'...
...The peeling work is easily done.

本発明の他の実施例として、舗装層に上例にお
ける平行切溝2……とこれら平行切溝2……と交
錯する他の多数の平行切溝を施し、それにより該
舗装層を多数の柱状舗装ブロツクに分割し、他の
構成は上例と実質的に同一とした例も得られる。
As another embodiment of the present invention, the pavement layer is provided with the parallel grooves 2 in the above example and a large number of other parallel grooves that intersect with these parallel grooves 2..., thereby forming the pavement layer into a large number of parallel grooves. An example can also be obtained in which the pavement is divided into pillar-shaped pavement blocks and the other configurations are substantially the same as the above example.

本発明の舗装道路の掘削方法によれば、従来方
法における第1日目の作業のブレーカーによる破
壊、破壊物の排出及び砕石投入の各作業を省略で
きると共に舗装層の剥離が容易に行えるから、作
業全体が大巾に簡略化され極めて能率化できるも
のであり、しかも第1日目の作業後の30mm〜50mm
等の相当広い溝巾の切溝に切削ズリを埋戻した舗
装面は自動車、オートバイ、自転車等の通行にほ
とんど支障がないばかりでなく、従来方法の砕石
を入れた仮復旧の路面よりも通行に有利となる利
点もあり、その使用価値は極めて高いものであ
る。
According to the paved road excavation method of the present invention, it is possible to omit the operations of breaking with a breaker on the first day, discharging debris, and inserting crushed stones in the conventional method, and the pavement layer can be easily peeled off. The entire work has been greatly simplified and can be made extremely efficient, and what's more, the work has been completed by 30mm to 50mm after the first day's work.
Pavement surfaces made by backfilling cutting waste into fairly wide grooves, such as kerosene, etc., not only have almost no hindrance to the passage of cars, motorcycles, bicycles, etc., but are also easier to pass through than temporary restoration roads made with conventional methods of putting crushed stone in. It also has advantages that are advantageous to the user, and its value in use is extremely high.

【図面の簡単な説明】[Brief explanation of drawings]

図面はこの発明の実施例を示し、第1図は切溝
を施した舗装道路の一部断面図、第2図は切削ズ
リを埋戻した同上断面図、第3図は路床に溝を開
削した同上断面図である。 1……舗装層、1′……舗装ブロツク、2……
切溝。
The drawings show an embodiment of the present invention; Fig. 1 is a partial sectional view of a paved road with cut grooves, Fig. 2 is a sectional view of the same with the cut grooves backfilled, and Fig. 3 is a cross-sectional view of the same with grooves cut in the roadbed. It is a sectional view of the same as the above after excavation. 1...paving layer, 1'...paving block, 2...
kerf.

Claims (1)

【特許請求の範囲】 1 第1日目の作業として、舗装層の必要範囲内
に該舗装層が剥離し易くなるように適数本の相当
広い溝巾の切溝を小間隔で切削し、それにより該
舗装層を適数の舗装ブロツクに分割し、ついで上
記切削時のズリを切溝内に埋戻し、 次に第2日目の作業として、上記舗装ブロツク
を剥離し、ついで路床に所要の掘削を施す、 ことを特徴とする舗装道路の掘削方法。
[Claims] 1. As work on the first day, an appropriate number of fairly wide grooves are cut at small intervals within the required range of the pavement layer so that the pavement layer can be easily peeled off. As a result, the pavement layer is divided into an appropriate number of pavement blocks, and the gaps created during the cutting are then backfilled into the grooves.Then, as part of the work on the second day, the pavement blocks are peeled off, and then the pavement is laid on the subgrade. A method for excavating a paved road characterized by performing the required excavation.
JP1164480A 1980-02-02 1980-02-02 Method of excavating paved road Granted JPS56108403A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1164480A JPS56108403A (en) 1980-02-02 1980-02-02 Method of excavating paved road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1164480A JPS56108403A (en) 1980-02-02 1980-02-02 Method of excavating paved road

Publications (2)

Publication Number Publication Date
JPS56108403A JPS56108403A (en) 1981-08-28
JPS6334242B2 true JPS6334242B2 (en) 1988-07-08

Family

ID=11783653

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1164480A Granted JPS56108403A (en) 1980-02-02 1980-02-02 Method of excavating paved road

Country Status (1)

Country Link
JP (1) JPS56108403A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0350635U (en) * 1989-09-21 1991-05-16
JPH0516843U (en) * 1991-08-19 1993-03-02 山富産業株式会社 Concrete block for retaining wall construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0350635U (en) * 1989-09-21 1991-05-16
JPH0516843U (en) * 1991-08-19 1993-03-02 山富産業株式会社 Concrete block for retaining wall construction

Also Published As

Publication number Publication date
JPS56108403A (en) 1981-08-28

Similar Documents

Publication Publication Date Title
JPS6334242B2 (en)
JPS6147251B2 (en)
JP2000130096A (en) Method for installing invert into batholith of existing mountain tunnel
CN112359854A (en) Emergency repair method for road tunnel collapse damage
JP2000145386A (en) Member and method for repairing batholith of existing mountain tunnel
Hamburger A new inscription from the Caesarea aqueduct
Keppie et al. Some rescue excavation on the line of the Antonine Wall, 1973-6
JPS60226908A (en) Opening construction of paved road surface
JP3600934B2 (en) Renovation method for outdoor grounds
TWI258530B (en) Tunnel-face excavation construction method using water jet device
JP2587309B2 (en) Protective structure of concrete underground structure and its construction method
Drossell BIG EARTHMOVERS AND REVISED JOB-PHASING SPEED HIGHWAY CONSTRUCTION
Crawford et al. Excavations at Fregellae, 1978–84: An Interim Report on the Work of the British Team
JPS60226907A (en) Opening construction of paved road surface
JPS6239146Y2 (en)
JPH07293748A (en) Laying construction method for pipe body
Politis The stepped dam at Wadi el-Jilat
JP2000045675A (en) Service pipe laying method and device used in such method
RU2017888C1 (en) Drainage system
JPH02140396A (en) Annular excavating device
SU901408A1 (en) Method for conducting earth moving operations in laying pipelines
JPS59154205A (en) Test boring of paved road
RU95104482A (en) Method for reclamation of slopes in open cutting
SU589991A1 (en) Method of curbing the spread of forest fires
CN109667229A (en) A kind of contrary sequence method foundation pit top temporary trestle bridge plate method for dismounting