JPS63304819A - Construction method of continuous underground wall - Google Patents

Construction method of continuous underground wall

Info

Publication number
JPS63304819A
JPS63304819A JP13769387A JP13769387A JPS63304819A JP S63304819 A JPS63304819 A JP S63304819A JP 13769387 A JP13769387 A JP 13769387A JP 13769387 A JP13769387 A JP 13769387A JP S63304819 A JPS63304819 A JP S63304819A
Authority
JP
Japan
Prior art keywords
panels
formwork
panel
trailing
underground wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP13769387A
Other languages
Japanese (ja)
Other versions
JPH0437203B2 (en
Inventor
Kunihiko Mino
三野 邦彦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP13769387A priority Critical patent/JPS63304819A/en
Publication of JPS63304819A publication Critical patent/JPS63304819A/en
Publication of JPH0437203B2 publication Critical patent/JPH0437203B2/ja
Granted legal-status Critical Current

Links

Abstract

PURPOSE:To make it possible to construct a curved continuous underground wall by forming a form into a right angled triangle section and setting so as the end of a construction joint in the preceding panel is at right angles to an axis of the succeeding excavated trench in the case of drawing the form. CONSTITUTION:Both sides of the preceding excavated trench 10 are partitioned into trapezoids by inserting a hollow form 12 having a right angled triangle section, which size is correspondent to that of the width of the trench, into the construction joint section. Then, an area enclosed by the hollow form 12 in the preceding excavated trench 10 is filled with concrete, and start to solidify. And, it is set so as to cross at right angles with the center axis l2 of the succeeding excavated trench 16. According to the constitution, a jointing of successive pours between the preceding panel and the succeeding panel is executed smoothly without making unbalance of excavation.

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は、円形土留壁などに適用される近似曲面形状
をした連続地中壁の構築工法に関する。
DETAILED DESCRIPTION OF THE INVENTION (Industrial Application Field) The present invention relates to a construction method for a continuous underground wall having an approximate curved shape, which is applied to a circular earth retaining wall or the like.

(従来の技術) 連続地中壁の築造にあたり、先行パネルに後行パネルを
打継いでいく工法として、インターロッキングパイプ工
法と、カッディングジヨイント工法がある。
(Prior Art) When constructing a continuous underground wall, there are two methods: the interlocking pipe method and the cudding joint method, in which a trailing panel is joined to a leading panel.

前者のインターロッキングパイプ工法は、一対の先行工
区の両端にロッキングパイプを挿入し、各ロッキングパ
イプで仕切られた区間にコンクリートを打設して先行パ
ネルを築造した後ロッキングパイプを引き抜き、後行工
区を掘削し、後行パネルを打ち継いでいく工法である。
In the former interlocking pipe construction method, locking pipes are inserted at both ends of a pair of preceding sections, concrete is poured in the sections separated by each locking pipe, the preceding panels are built, and then the locking pipes are pulled out and the subsequent sections are separated. This method involves excavating the area and installing subsequent panels.

また、後者のカッティングジヨイント工法は、先行工区
に形成された直方体状の先行パネルの打継面を後行工区
の掘削溝を形成する際にハイドロカッターなどによって
切削し、打継部における不良コンクリートなどの脆弱な
部分を除去した後コンクリートを打設して後行パネルを
打継いでいく工法である。
In addition, in the latter cutting joint construction method, the joint surface of the rectangular parallelepiped leading panel formed in the preceding work section is cut with a hydrocutter etc. when forming the excavation groove for the succeeding work section, and the defective concrete in the joint section is removed. This is a construction method in which weak parts such as walls are removed, concrete is poured, and subsequent panels are poured.

(発明が解決しようとする問題点) これら各工法はそれぞれに一長一短があるが、直線状の
連続地中壁の構築工法としてはいずれも有効である。
(Problems to be Solved by the Invention) Each of these construction methods has its own merits and demerits, but all of them are effective as construction methods for linear continuous underground walls.

しかし円形土留壁などのように近似曲面形状の連続地中
壁を横築する場合には、以下の欠点があった。
However, when constructing a continuous underground wall with an approximate curved shape horizontally, such as a circular retaining wall, there are the following drawbacks.

すなわち、これらの工法ではいずれもが所定の曲率に沿
った多角形状とすることによって曲面形状に適合するこ
とになる。
That is, in all of these construction methods, the polygonal shape along a predetermined curvature is adapted to the curved surface shape.

そして、前記インターロッキングパイプ工法では、第6
図に示ずように、ロッキングパイプ3の中心を交差点と
してその直径に応じた単一掘削幅の直線上の先、後行パ
ネル1.2を円の曲率に沿って形成し、多角形状となす
ことで曲面に適合することになるが、曲率が大きくなる
と、先、後行パネル1.2間での交差角度が小さくなり
、ロッキングパイプ3を引き抜いた後の先、後行パネル
1.2間の打継部に重なりが生じ、後行の掘削溝を掘削
する時に先行パネル1の湾曲状をなした打継面が掘削機
に干渉するため、後行パネル2を形成するための掘削が
困難になるという問題があった。
In the interlocking pipe construction method, the sixth
As shown in the figure, the front and trailing panels 1.2 are formed along the curvature of a circle on a straight line with a single excavation width corresponding to the diameter of the rocking pipe 3 with the center of the rocking pipe 3 as its intersection point, forming a polygonal shape. However, as the curvature increases, the intersection angle between the leading and trailing panels 1.2 becomes smaller, and the intersection angle between the leading and trailing panels 1.2 after the locking pipe 3 is pulled out. The curved joint surface of the leading panel 1 interferes with the excavator when excavating the trailing excavation trench, making it difficult to excavate to form the trailing panel 2. There was a problem with becoming.

また、カッティングジヨイント工法において、単一掘削
幅の単純な組み合わせの場合、第7図に示すように、先
行パネル1の端面を後行パネル2の直方体形状に合わせ
るために、カッティングジヨイント部5を斜線で示す楔
状にカッティングしなければならず、切削抵抗が内、外
でアンバランスとなり、掘削能力や、打継部での精度が
低下し易く、特に深い部分はど斜線で示すようには切削
されず、施工精度が低いものとなっていた。
In addition, in the case of a simple combination of a single excavation width in the cutting joint construction method, as shown in FIG. must be cut in the wedge shape shown by the diagonal lines, and the cutting resistance becomes unbalanced between the inside and outside, which tends to reduce excavation ability and accuracy at the joint, especially in deep parts, as shown by the diagonal lines. It was not cut and the construction accuracy was low.

本発明は以上の問題点に鑑みてなされたものであり、そ
の目的は、この種の曲面形状の連続地中壁を施工するに
あたり、前述のカッティグ工法を適用するとともに、カ
ッティング工法の欠点であつた切削のアンバランスがな
く、先行パネルと後行パネル間を良好に打継ぐことがで
きるようにした連続地中壁の構築工法を提供するもので
ある。
The present invention has been made in view of the above problems, and its purpose is to apply the above-mentioned cutting method when constructing this kind of continuous underground wall with a curved surface shape, and to solve the problems of the cutting method. The present invention provides a method for constructing a continuous underground wall in which there is no unbalance in cutting and a good joint can be made between the leading panel and the trailing panel.

(問題点を解決するための手段) 前記目的を達成するため、この発明は、所定の曲率で近
似曲面となるように多角形状に連続する地中壁を構築す
るにあたり、前記曲面に沿って直線状の先行掘削溝を形
成し、これら各先行掘削溝の打継部に型枠を挿入し、こ
の型枠で仕切られた区分にコンクリートを打設して一対
の先行パネルを形成し、次いで隣り合う先行パネル間を
直線状に結んだ状態で掘削するとともに、前記先行パネ
ルの打継端面を切削し、形成された後行掘削溝内にコン
クリートを打設して後行パネルを先行パネル間に所定の
交差角度で打継ぐようにした連続地中壁の構築工法にお
いて; 前記型枠は、溝幅に応じた直角三角状断面に形成され、
かつその斜辺部によって先行パネルの打継部を仕切るよ
うにしたものであって、この型枠の引抜き時において先
行パネルの打継ぎ端面が後行掘削溝の軸線に対して直交
すべく前記型枠の斜辺部の傾斜角度が設定されているこ
とを特徴とする。
(Means for Solving the Problems) In order to achieve the above object, the present invention provides a method for constructing a continuous underground wall in a polygonal shape so as to form an approximate curved surface with a predetermined curvature. Formwork is inserted into the joining part of each of these pre-excavation trenches, and concrete is poured into the section separated by the formwork to form a pair of pre-excavation panels. While excavating the matching leading panels in a straight line, cutting the joint end faces of the preceding panels and pouring concrete into the formed trailing excavation groove, the trailing panels are connected between the leading panels. In a method for constructing a continuous underground wall in which concrete is connected at a predetermined crossing angle;
The formwork is arranged so that the joining part of the preceding panel is partitioned by the oblique side thereof, and the joining part of the preceding panel is perpendicular to the axis of the trailing excavation groove when the formwork is pulled out. The inclination angle of the oblique side portion is set.

(作 用) 先行パネル間を直線状に結んで後行掘削溝を掘削する状
態では、後行掘削溝の両端にその軸線と直交した状態で
先行パネルの打継面が露出し、カッティングする際の切
削面が平行な状態で当接し、アンバランスを生ずること
がない。
(Function) When a trailing excavation groove is excavated by connecting the preceding panels in a straight line, the joint surfaces of the preceding panels are exposed at both ends of the trailing excavation groove in a state perpendicular to the axis of the trailing excavation groove. The cutting surfaces of the two abut against each other in a parallel state, and no imbalance occurs.

(実 施 例) 以下、この発明の一実施例を図面を用いて詳細に説明す
る。第1図ないし第5図はこの発明の施工順序を示して
いる。
(Example) Hereinafter, an example of the present invention will be described in detail using the drawings. 1 to 5 show the construction order of this invention.

第1図において、一対の先行掘削溝10は、得ようとす
る曲面しに沿って夫々の中心軸線j1の延長上で所定の
交差角度をなして交わるように適度な長さおよび幅をも
って泥水を満たしつつそれぞれ断面直方体形状をなして
所定の深度まで掘削される。
In FIG. 1, a pair of pre-excavated grooves 10 have appropriate lengths and widths to drain muddy water so that they intersect at a predetermined intersection angle on the extension of the respective central axes j1 along the curved surface to be obtained. Each hole is excavated to a predetermined depth with a rectangular parallelepiped cross section.

次いで、第2図に示すように各掘削溝10の両端部、す
なわち打継部に溝幅に応じた寸法で直角三角形状断面を
した中空型枠12を挿入し、この型枠の斜辺部12aに
よって先行掘削溝10の両側を台形状に仕切る。
Next, as shown in FIG. 2, a hollow formwork 12 having a right triangular cross-section and a dimension corresponding to the groove width is inserted into both ends of each excavated groove 10, that is, the joint part, and the hypotenuse part 12a of this formwork is inserted. Both sides of the preceding excavation groove 10 are partitioned into a trapezoidal shape.

この中空型枠12の一辺12bは溝幅の寸法aに等しく
、先行掘削溝10の幅方向に位置する。
One side 12b of this hollow formwork 12 is equal to the groove width dimension a, and is located in the width direction of the preceding excavated groove 10.

また、前記斜辺部12aは後述する後行パネルの軸線と
直交する傾斜角度に設定されており、したがって、先行
パネルと後行パネルの交差角度が定まると、簡単な関数
比で他の一辺12cの長さが設定され、中空型枠12の
各部の寸法関係が定まることになる。
Further, the oblique side 12a is set at an inclination angle perpendicular to the axis of the trailing panel, which will be described later. Therefore, once the intersection angle between the leading panel and the trailing panel is determined, the other side 12c can be adjusted by a simple function ratio. The length is set, and the dimensional relationship of each part of the hollow formwork 12 is determined.

次に、この中空型枠12によって仕切られた区間内に鉄
筋篭(図示省略)を建込み、その後トレミー管などを用
いてコンクリートを打設し、掘削溝10の内部に満たさ
れている泥水と置換する。
Next, a reinforcing bar cage (not shown) is erected within the section partitioned by the hollow formwork 12, and then concrete is poured using tremie pipes, etc., and the muddy water filling the inside of the excavated trench 10 is poured. Replace.

以上の作業によって、第2図に示すように先行掘削溝1
0内の中空型枠12で囲われた区域にコンクリートが充
填され、固化が始まる。
Through the above operations, the pre-excavated trench 1 is completed as shown in Figure 2.
The area surrounded by the hollow formwork 12 inside 0 is filled with concrete and hardening begins.

この状態から中空型枠12を振動などによって徐々にコ
ンクリートと縁切りしつつ引抜き、その後のコンクリー
トの完全固化によって、第3図に示すように台形状断面
の先行パネル14の築造を完成する。
From this state, the hollow formwork 12 is pulled out while gradually cutting off the concrete by vibration or the like, and then the concrete is completely solidified to complete the construction of the preceding panel 14 having a trapezoidal cross section as shown in FIG.

先行パネル14の築造完成後、後行掘削溝16を泥水を
満しつつ掘削する。
After the construction of the preceding panel 14 is completed, the trailing excavation groove 16 is excavated while being filled with muddy water.

第3図の想像線で示すように、この掘削溝16は前記各
先行パネル14の端面である打継面14a間の幅方向両
側を結んだ線上であり、その中心軸線92は先行パネル
14の中心軸線11に対し、所定の交差角度で交わる。
As shown by the imaginary line in FIG. 3, this excavated groove 16 is on a line connecting both sides in the width direction between the joining surfaces 14a, which are the end faces of each preceding panel 14, and its central axis 92 is on the line connecting both sides in the width direction between the joining surfaces 14a, which are the end surfaces of each preceding panel 14. It intersects with the central axis 11 at a predetermined crossing angle.

ここで、前記中空型枠12の斜辺部t2aの傾斜角度は
前述のごとく後行掘削溝16の中心軸線j2と直交した
角度で交わるようにあらかじめ設定されている。
Here, the inclination angle of the oblique side portion t2a of the hollow formwork 12 is set in advance so as to intersect with the central axis j2 of the trailing excavation groove 16 at an angle perpendicular to it, as described above.

したがって、第4図に示すように掘削と同時に先行パネ
ル14の打継面14aを切削する状態では、カッター1
8は打継面14aに平行に当り、均一な厚みdで打継面
14aを切削する。
Therefore, as shown in FIG. 4, when cutting the joint surface 14a of the preceding panel 14 simultaneously with excavation,
8 hits parallel to the joint surface 14a and cuts the joint surface 14a to a uniform thickness d.

以上により、前記カッター18が打継面とある交差角度
で交わる従来の場合と比べて、均一な厚みで切削するこ
とが可能であり、最深部まで精度良く切削を行えること
になる。
As a result, compared to the conventional case in which the cutter 18 intersects with the joint surface at a certain angle, it is possible to cut with a uniform thickness, and it is possible to cut to the deepest part with high precision.

掘削および切削作業終了後は前記先行パネル14と同一
要領で鉄筋篭の建込みと、コンクリートの打設作業を行
えば、第5図に示すように先行パネル14間に後行パネ
ル20が築造され、その打継ぎを完了するのである。
After the excavation and cutting work is completed, the reinforcing cages are erected and the concrete is placed in the same manner as the preceding panel 14, and the trailing panel 20 is constructed between the leading panels 14 as shown in FIG. , completing the transition.

(効 果) 以上実施例によって詳細に説明したように、この発明に
よる連続地中壁の構築工法にあっては、先行パネル間を
直線上に結んで後行掘削溝を掘削する状態では後行掘削
溝の両端にその軸線と直交した状態で先行パネルの打継
面が露出するため、カッターが打継面に平行に当接し、
切削作業を行うので、アンバランスを生ずることがない
(Effects) As explained in detail using the embodiments above, in the continuous underground wall construction method according to the present invention, when the preceding panels are connected in a straight line and the trailing excavation trench is excavated, the trailing excavation trench is excavated. Since the joint surface of the preceding panel is exposed at both ends of the excavated groove in a state perpendicular to the axis, the cutter comes into contact with the joint surface in parallel,
Since cutting work is performed, there is no possibility of imbalance.

したがって、この発明によれば、カッティングジヨイン
ト工法の欠点であった切削のアンバランスがなく、先行
パネルと後行パネル間を良好に打継ぐことができる。
Therefore, according to the present invention, there is no unbalance in cutting, which is a drawback of the cutting joint construction method, and it is possible to successfully connect the leading panel and the trailing panel.

【図面の簡単な説明】[Brief explanation of drawings]

第1図ないし第5図はこの発明に係る連続地中壁の構築
工法を示す工程説明図、第6図は従来のインターロッキ
ングパイプを用いた構築工法を示す説明図、第7図は従
来のカッティングジヨイント工法による構築工法を示す
説明図である。 10・・・先行掘削溝 12・・・中空型枠   12a・・・斜辺部14・・
・先行パネル  14a・・・打継部16・・・後行掘
削溝  18・・・カッター20・・・後行パネル
Figures 1 to 5 are process explanatory diagrams showing the construction method of a continuous underground wall according to the present invention, Figure 6 is an explanatory diagram showing a construction method using conventional interlocking pipes, and Figure 7 is an explanatory diagram showing the construction method using conventional interlocking pipes. It is an explanatory view showing a construction method using a cutting joint construction method. 10... Advance excavation groove 12... Hollow formwork 12a... Oblique side part 14...
- Leading panel 14a... Connection part 16... Trailing excavation groove 18... Cutter 20... Trailing panel

Claims (1)

【特許請求の範囲】[Claims] (1)所定の曲率で近似曲面となるように多角形状に連
続する地中壁を構築するにあたり、前記曲面に沿って直
線状の先行掘削溝を形成し、これら各先行掘削溝の打継
部に型枠を挿入し、この型枠で仕切られた区分にコンク
リートを打設して一対の先行パネルを形成し、次いで隣
り合う先行パネル間を直線状に結んだ状態で掘削すると
ともに、前記先行パネルの打継端面を切削し、形成され
た後行掘削溝内にコンクリートを打設して後行パネルを
先行パネル間に所定の交差角度で打継ぐようにした連続
地中壁の構築工法において; 前記型枠は、溝幅に応じた直角三角状断面に形成され、
かつその斜辺部によって先行パネルの打継面を仕切るよ
うにしたものであって、この型枠の引抜き時において先
行パネルの打継ぎ端面が後行掘削溝の軸線に対して直交
すべく前記型枠の斜辺部の傾斜角度が設定されているこ
とを特徴とする連続地中壁の構築工法。
(1) When constructing a continuous polygonal underground wall with a predetermined curvature and an approximated curved surface, a linear pre-excavated trench is formed along the curved surface, and the joints of each of these pre-excavated trenches are A formwork is inserted into the area, and concrete is poured into the sections partitioned by the formwork to form a pair of preceding panels. Next, adjacent preceding panels are connected in a straight line and excavation is carried out, and the preceding panels are A continuous underground wall construction method in which the joint end faces of panels are cut, concrete is poured into the trailing excavation grooves formed, and the trailing panels are joined at a predetermined crossing angle between the leading panels. ; The formwork is formed in a right triangular cross section according to the groove width,
The formwork is such that the joining surface of the preceding panel is partitioned by the oblique side thereof, and the joining surface of the preceding panel is perpendicular to the axis of the trailing excavation groove when the formwork is pulled out. A continuous underground wall construction method characterized by having a set inclination angle of the hypotenuse.
JP13769387A 1987-06-02 1987-06-02 Construction method of continuous underground wall Granted JPS63304819A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13769387A JPS63304819A (en) 1987-06-02 1987-06-02 Construction method of continuous underground wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13769387A JPS63304819A (en) 1987-06-02 1987-06-02 Construction method of continuous underground wall

Publications (2)

Publication Number Publication Date
JPS63304819A true JPS63304819A (en) 1988-12-13
JPH0437203B2 JPH0437203B2 (en) 1992-06-18

Family

ID=15204601

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13769387A Granted JPS63304819A (en) 1987-06-02 1987-06-02 Construction method of continuous underground wall

Country Status (1)

Country Link
JP (1) JPS63304819A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0339573A (en) * 1989-07-05 1991-02-20 Kajima Corp Construction method of underground wall of structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0339573A (en) * 1989-07-05 1991-02-20 Kajima Corp Construction method of underground wall of structure

Also Published As

Publication number Publication date
JPH0437203B2 (en) 1992-06-18

Similar Documents

Publication Publication Date Title
JPS63304819A (en) Construction method of continuous underground wall
JPS61122320A (en) Method of coupling continuous underground wall with underground structure
JPS63125727A (en) Method and apparatus for construction of vertical coupler mortise for underground continuous wall
JPH02136421A (en) Construction method of underground circular continuous wall
JPH05339936A (en) Column strip type underground continuous wall process
JP3584416B2 (en) Tunnel and its construction method
JPS6375216A (en) Underground continuous wall construction work
JP2782284B2 (en) Method of forming precast building columns
JPH0437202B2 (en)
JP2509072B2 (en) Tunnel construction method
JPS62291317A (en) Quick construction of wide-width underground wall
JPH0315624Y2 (en)
JPS63125722A (en) Construction of underground continuous wall
JP2569991B2 (en) Concrete removal method for reinforced concrete joints
JPH0734451A (en) Structure of underground wall
JPS63125724A (en) Construction of underground continuous wall
JP2790005B2 (en) How to build a continuous underground wall
JPH09317397A (en) Large cross-sectional tunnel and constructing method thereof
JPH10102488A (en) Method of introducing prestress into diaphragm wall
JPS62291319A (en) Construction of underground wall
JPS63304820A (en) Construction method of continuous underground wall
JPH093879A (en) Building material made of steel having concrete flow hole and building method for concrete structure using the building material made of steel
JPS62178621A (en) Construction work of underground structure
JPH07238538A (en) Continuous underground wall construction method
JPS6355212A (en) Construction of latticed continuous underground wall