JPS62291317A - Quick construction of wide-width underground wall - Google Patents

Quick construction of wide-width underground wall

Info

Publication number
JPS62291317A
JPS62291317A JP13451586A JP13451586A JPS62291317A JP S62291317 A JPS62291317 A JP S62291317A JP 13451586 A JP13451586 A JP 13451586A JP 13451586 A JP13451586 A JP 13451586A JP S62291317 A JPS62291317 A JP S62291317A
Authority
JP
Japan
Prior art keywords
steel
steel pipe
concrete
sheet piles
wide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP13451586A
Other languages
Japanese (ja)
Inventor
Masayuki Okimoto
沖本 真之
Kaigo Iwai
岩井 開悟
Ryoichi Sugano
良一 菅野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP13451586A priority Critical patent/JPS62291317A/en
Publication of JPS62291317A publication Critical patent/JPS62291317A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To shorten the time of operation to a great extent by a simple constructing method in a method in which, the ground where a parallel two- armed coupler is to be penetrated is softened, a steel sheet pile is driven into the ground, and concrete is placed. CONSTITUTION:The grounds 8a and 8b for penetrating steel tubular sheet piles are softened by a long-drill excavation method, and a steel sheet pile 1 is driven into the ground by hammer. The steel sheet piles 1a-1c are orderly driven and coupled, and the inside grounds 11a-11e are excavated at adequate time. The excavated soil is discharged and concrete is placed. The wall faces of the holes 11a-11e are attached with lath or expandable metals to increase the bonding strength of concrete. The mechanical strength and water-stopping performance of the steel tubular sheet piles can be improved, permitting wide and long underground wall to be constructed.

Description

【発明の詳細な説明】 3、発明の詳細な説明 〔産業上の利用分野〕 本発明は、土木及び建築分野における地中壁特に広幅の
地中壁の構築法に関する。
Detailed Description of the Invention 3. Detailed Description of the Invention [Field of Industrial Application] The present invention relates to a method for constructing underground walls, particularly wide underground walls, in the fields of civil engineering and construction.

〔従来の技術〕[Conventional technology]

土木、l!築分野では土留、基礎あるいはピント区画用
として地中壁を構築する場合が多く、特に大荷重に対応
するためには壁厚が厚くかつ建込み深さの大きい広幅地
中壁を構築することが要求される。
Civil engineering, l! In the field of construction, underground walls are often constructed for earth retaining, foundations, or pinto sections, and in order to handle especially large loads, it is necessary to construct wide underground walls with thick walls and a large construction depth. required.

このような広幅地中壁を構築する方法として、特開昭5
5−68921号公報記載の発明(以下A発明という)
が知られている。
As a method of constructing such wide underground walls,
Invention described in Publication No. 5-68921 (hereinafter referred to as invention A)
It has been known.

この方法は一端に係止部、他端にガイド部を有する二枚
の止水鋼板間に仕切8板を溶接してボックス形のガイド
鋼枠を製造し、該ガイド鋼枠をあらかじめ掘削した構内
において逐次接続し、ついでコンクリートを打設する方
法であって、前記ガイド鋼枠がインターロッキングパイ
プ、止水板及びジヨイントを兼ねるので施工が簡便で施
工期間も短いとされている。
This method involves manufacturing a box-shaped guide steel frame by welding eight partition plates between two water-stop steel plates that have a locking part at one end and a guide part at the other end, and then attaching the guide steel frame to a pre-excavated site. This is a method in which the guide steel frame serves as an interlocking pipe, a water stop plate, and a joint, so construction is simple and the construction period is short.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

前記A発明は、広幅で大深度の地中壁を構築する目的に
対し優れた方法であるが、あらかじめ装入用の掘削溝を
掘削ビ、継手部(A発明では係止部及びガイド部)を屈
曲させないように注意して装入し接続せねばならぬため
、施工時間が長くなり、また掘削溝の崩れ防止に格別の
対策が必要であるという問題点があり、施工コストの点
で課題が残されている。
Invention A is an excellent method for the purpose of constructing a wide and deep underground wall. Since the material must be charged and connected carefully so as not to bend, the construction time becomes longer and special measures are required to prevent the excavated trench from collapsing, which poses an issue in terms of construction cost. is left behind.

〔問題点を解決するための手段〕[Means for solving problems]

本発明は施工が簡単で作業時間が極めて短くしかも頑丈
な広幅地中壁を構築する方法を提供するもので、両側に
それぞれ平行双腕継手を備えた鋼管矢板を建込み広幅地
中壁を構築するにあたり、あらかじめ前記平行双腕継手
の貫入予定地を軟弱化するかもしくは軟弱化しつつ鋼管
矢板を打設もしくは圧入したのち中掘し、ついでコンク
リートを充填する手段を要旨とする。
The present invention provides a method for constructing a wide underground wall that is easy to construct, takes extremely short work time, and is sturdy.The present invention provides a method for constructing a wide underground wall that is easy to construct, takes extremely short work time, and is strong. In order to do so, the gist is a method of weakening the planned penetration site of the parallel double-arm joint in advance, or driving or press-fitting the steel pipe sheet pile while weakening the area, excavating it, and then filling it with concrete.

〔作用〕[Effect]

本発明の方法に使用される鋼管矢板の構造および作用に
続き、本発明方法を詳述する。
Following the structure and operation of the steel pipe sheet pile used in the method of the present invention, the method of the present invention will be explained in detail.

第4図は本発明に係る鋼管矢vi、1の平面図で、角形
鋼管2の角部3a〜3dのそれぞれに継手48〜4dが
角形鋼管2のフランジ壁2a、2bの中心を通る軸線X
 + −X + 、  X !  X zの方向に沿つ
て溶接法により固着されている。
FIG. 4 is a plan view of the steel pipe arrow vi, 1 according to the present invention, in which joints 48 to 4d are attached to the corners 3a to 3d of the square steel pipe 2, respectively, and the axis X passing through the center of the flange walls 2a and 2b of the square steel pipe 2
+ -X +, X! It is fixed along the Xz direction by a welding method.

本発明では前述のように、鋼管のそれぞれの側において
平行に取り付けられた継手4a、4b及び4c。
In the present invention, as mentioned above, the joints 4a, 4b and 4c are mounted in parallel on each side of the steel tube.

4dを平行双腕継手という。4d is called a parallel double arm joint.

また、第5図は円筒鋼管5に平行双腕継手68〜6dを
固着した鋼管矢417の平面図であって、前記平行双腕
継手6a〜6dは円筒鋼管5の軸心を通る中心線Xs 
 Xsを中心として対称な平行線X s −X s。
FIG. 5 is a plan view of a steel pipe 417 in which parallel double-arm joints 68 to 6d are fixed to a cylindrical steel pipe 5, and the parallel double-arm joints 6a to 6d are connected to a center line Xs passing through the axis of the cylindrical steel pipe 5.
Parallel lines X s −X s symmetrical about Xs.

X、−X、に沿って該円筒鋼管5の両側から延伸してい
る。
It extends from both sides of the cylindrical steel pipe 5 along the lines X and -X.

前記平行双腕継手4a〜4d、 6a〜6dは圧延法に
よって製造した直&lI鋼矢板を縦に半裁して構成した
継手が継手強度、止水性及び作業性の点で他の継手たと
えば丸鋼管や形鋼あるいは綱板加工継手に対して格段に
優れている。
The parallel double-arm joints 4a to 4d and 6a to 6d are constructed by vertically cutting straight & lI steel sheet piles produced by rolling into halves, and are superior to other joints such as round steel pipes or round steel pipes in terms of joint strength, water-stopping properties, and workability. Much superior to shaped steel or steel plate joints.

本発明にかかる鋼管矢板は前述のように構成されている
ので、所望の幅(壁厚)特に広幅の地中壁の構築に対し
て所望の外径を備えた鋼管を選定することによって自由
に対応できる。
Since the steel pipe sheet pile according to the present invention is constructed as described above, the desired width (wall thickness) can be freely selected by selecting steel pipes with the desired outer diameter for constructing particularly wide underground walls. I can handle it.

次に打設において前記A発明では打設時止水鋼板と仕切
鋼板の溶接部が破損する恐れが多いが、本発明の鋼管矢
板1.7は本体が鋼管2.5であるため打設に際し、鋼
管本体に内外から加えられる圧縮力や引張力あるいは捻
回力に対し非常に大きな抵抗力を有するため、あらかじ
め#A管本体部分すなわち)121管部分の貫入予定地
を軟弱化しておく必要はない、このm9部分の強度が大
きいこと、すなわち曲がりのないことが平行双腕継手の
溶接接合部の破損を少なくする作用を存する。
Next, during pouring, in the invention A, there is a high risk that the welded part between the water stop steel plate and the partition steel plate will be damaged during pouring, but the steel pipe sheet pile 1.7 of the present invention has a main body made of steel pipe 2.5, so it is difficult to , has a very large resistance to compressive force, tensile force, or twisting force applied to the steel pipe body from the inside and outside, so there is no need to soften the planned penetration site of the #A pipe body part (i.e.) 121 pipe part in advance. , the fact that the strength of this m9 portion is high, that is, there is no bending, has the effect of reducing damage to the welded joint of the parallel double-arm joint.

第1図は鋼管矢板lを打設する要領を示す平面図で、打
設前にあらかじめ平行双腕継手4a〜4dの破線で示す
貫入予定地8a、8bを長尺ドリル掘削工法たとえばア
ースオーガあるいはジェットカッタ等を用いる掘削工法
によって軟弱化しておき、ついで11管矢vi、1をハ
ンマーあるいはパイプレーク−等を用いて打設もしくは
圧入する。
FIG. 1 is a plan view showing the procedure for driving steel pipe sheet piles 1. Before driving, the planned penetration areas 8a and 8b, indicated by the broken lines of the parallel double-arm joints 4a to 4d, are drilled using a long drill method, such as an earth auger. It is softened by an excavation method using a jet cutter or the like, and then pipes 11 and 1 are driven or press-fitted using a hammer or pipe rake.

本発明における軟弱化とは前述のアースオーガ等による
穿孔など土砂の排除を積極的に行わない地盤の改質をい
う。
In the present invention, softening refers to soil modification in which earth and sand are not actively removed, such as by drilling with the aforementioned earth auger or the like.

次に第2図は鋼管矢4.Fi1の平行双腕継手4cの先
端爪部9の直近位置に高圧水噴射ノズルlOを縦設し、
その先端10aから爪部9の最下端9aに向けて高圧水
を噴射し、貫入予定地を軟弱化しつつ鋼管矢板1を打設
する施工要領を示す部分断面斜視図である。
Next, Figure 2 shows steel pipe arrow 4. A high-pressure water injection nozzle lO is installed vertically in the vicinity of the tip claw part 9 of the parallel double-arm joint 4c of Fi1,
It is a partial cross-sectional perspective view showing the construction procedure of driving the steel pipe sheet pile 1 while weakening the planned penetration site by injecting high-pressure water from the tip 10a toward the lowest end 9a of the claw portion 9.

この施工要領によれば、平行双腕継手を破損や屈曲など
を生ずることな(正常な形態を保って鋼管矢板を打設す
ることが可能になる。
According to this construction procedure, it is possible to drive the steel pipe sheet pile without damaging or bending the parallel double-arm joint (maintaining its normal form).

前述の第1図もしくは第2図に示す打設要領で施工した
地中壁50の平面図を第3図に示す。
FIG. 3 shows a plan view of the underground wall 50 constructed according to the casting procedure shown in FIG. 1 or 2 above.

la〜1cは順次打設係合した鋼管矢板であって、その
内腔11a〜118については打設中もしくは打設後適
宜な時期に掘削して土砂を排除しコンクリートを充填す
る。
Reference numerals la to 1c are steel pipe sheet piles that are successively cast and engaged, and their inner cavities 11a to 118 are excavated during or at an appropriate time after casting to remove soil and fill with concrete.

前記内腔1t a −n eの壁面にはラスやエキスバ
ンドメタルなどを被着しておくとコンクリートの付着強
度が増加し、地中壁50の機械的強iを高めることがで
きる。
If lath, expanded metal, or the like is applied to the wall surface of the inner cavity 1ta-ne, the adhesion strength of concrete increases, and the mechanical strength i of the underground wall 50 can be increased.

【実施例〕【Example〕

断面略正方形の角鋼管で外径600 X 600vwの
ものを本体とし、双腕継手を直線鋼矢板の半裁体幅28
0mm、長さ20mで製造し、前記角鋼管のそれぞれの
角部に溶接して鋼管矢板を製造し建込深さ20m。
The main body is a rectangular steel tube with an approximately square cross section and an outer diameter of 600 x 600vw, and the double arm joint is a half piece of straight steel sheet pile with a width of 28 mm.
0mm, length 20m, and welded to each corner of the square steel pipe to produce a steel pipe sheet pile with a construction depth of 20m.

長さ40mの地中壁を構築したが、礒手損偶の事故は全
くなく、工期はA発明の方法に比して約35%短縮する
ことに成功した。
An underground wall with a length of 40 m was constructed, but there were no accidents involving broken or damaged joints, and the construction period was successfully shortened by about 35% compared to the method of invention A.

また、他の例として外径1000 x iooommの
角鋼管を本体とする鋼管矢板を製造し、建込深さ30m
In addition, as another example, we manufacture steel pipe sheet piles whose main body is square steel pipes with an outer diameter of 1000 x iooomm, and the construction depth is 30 m.
.

長さ100 mの地中壁を構築したが、この場合へ発明
方法の50%の工期で施工できた。
An underground wall with a length of 100 m was constructed, and in this case it was completed in 50% of the construction time using the invented method.

一般に予定地の±賞によって能率に差が生ずるが、本発
明の方法は従来法より20〜60%工期を短縮すること
ができる。
Although efficiency generally varies depending on the location of the planned site, the method of the present invention can shorten the construction period by 20 to 60% compared to the conventional method.

〔発明の効果〕〔Effect of the invention〕

本発明の構築法はあらかじめ全面的掘削を行ったり、又
は土砂の排除を必要としないので、施工が迅速であり、
また地中壁構築要素である鋼管矢板が機械的に頑丈で止
水性がよいので広幅でかつ長大な地中壁を経済的に構築
することができる。
The construction method of the present invention does not require full-scale excavation or removal of earth and sand, so construction is quick.
In addition, the steel pipe sheet piles that are the building blocks for underground walls are mechanically strong and have good water-tightness, so wide and long underground walls can be constructed economically.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の方法にかかる打設要領を示す平面図、
第2図は商工水噴射ノズルを用いる打設要領図、第3図
は本発明方法によって施工した地中壁の概略平面図、第
4図、第5図は本発明の方法に用いられる鋼管矢板の概
略平面図である。
FIG. 1 is a plan view showing the pouring procedure according to the method of the present invention;
Figure 2 is a construction procedure using a shoko water injection nozzle, Figure 3 is a schematic plan view of an underground wall constructed by the method of the present invention, and Figures 4 and 5 are steel pipe sheet piles used in the method of the present invention. FIG.

Claims (1)

【特許請求の範囲】[Claims] 1、両側にそれぞれ平行双腕継手を備えた鋼管矢板を建
込み広幅地中壁を構築するにあたり、あらかじめ前記平
行双腕継手の貫入予定地を軟弱化するかもしくは軟弱化
しつつ鋼管矢板を打設もしくは圧入したのち中掘し、つ
いでコンクリートを充填することを特徴とする広幅地中
壁の迅速構築法。
1. When constructing a wide underground wall by erecting steel pipe sheet piles with parallel double-arm joints on both sides, weaken the area where the parallel double-arm joints are planned to penetrate in advance, or drive the steel pipe sheet piles while weakening the area. Alternatively, a method for quickly constructing wide underground walls is characterized by press-fitting, excavating, and then filling with concrete.
JP13451586A 1986-06-09 1986-06-09 Quick construction of wide-width underground wall Pending JPS62291317A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13451586A JPS62291317A (en) 1986-06-09 1986-06-09 Quick construction of wide-width underground wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13451586A JPS62291317A (en) 1986-06-09 1986-06-09 Quick construction of wide-width underground wall

Publications (1)

Publication Number Publication Date
JPS62291317A true JPS62291317A (en) 1987-12-18

Family

ID=15130129

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13451586A Pending JPS62291317A (en) 1986-06-09 1986-06-09 Quick construction of wide-width underground wall

Country Status (1)

Country Link
JP (1) JPS62291317A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0266215A (en) * 1988-08-30 1990-03-06 Nippon Steel Corp H-steel sheet pile
CN105421339A (en) * 2015-12-14 2016-03-23 中冶集团武汉勘察研究院有限公司 Novel combined concrete protection wall for manual rectangular anti-slide digging pile and installation method of novel combined concrete protection wall
CN106168034A (en) * 2015-09-30 2016-11-30 洛阳武轩重工机械有限公司 A kind of retaining wall plate
CN108487230A (en) * 2018-04-04 2018-09-04 中建筑港集团有限公司 A kind of sheet pile pile sinking process and its pile foundation slot

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0266215A (en) * 1988-08-30 1990-03-06 Nippon Steel Corp H-steel sheet pile
CN106168034A (en) * 2015-09-30 2016-11-30 洛阳武轩重工机械有限公司 A kind of retaining wall plate
CN105421339A (en) * 2015-12-14 2016-03-23 中冶集团武汉勘察研究院有限公司 Novel combined concrete protection wall for manual rectangular anti-slide digging pile and installation method of novel combined concrete protection wall
CN108487230A (en) * 2018-04-04 2018-09-04 中建筑港集团有限公司 A kind of sheet pile pile sinking process and its pile foundation slot

Similar Documents

Publication Publication Date Title
JP2005299202A (en) Steel sheet pile, earth retaining structure using the same, and construction method of earth retaining structure
JP5268732B2 (en) Wall member for underground continuous wall, underground continuous wall construction method, and underground continuous wall
JP2018024982A (en) Reinforcement method and reinforcement structure of existing pile foundation
JP5235748B2 (en) Wall metal fittings and underground continuous wall construction method
JP2008019608A (en) Steel pipe sheet pile, steel pipe sheet pile wall, steel pipe for pipe roof and pipe roof
JP6007036B2 (en) Steel pipe sheet pile placing method
JPS62291317A (en) Quick construction of wide-width underground wall
CN109113071B (en) Construction method for deep well retaining wall steel structure support
JPH08184037A (en) Double pipe steel pipe pile
JPH09125417A (en) Basement wall body and asymmetrically closed section steel pile
KR102325623B1 (en) Construction method of retaining wall
JP2003027462A (en) Construction method of underground continuous wall, and construction method of underground structure
JP2663106B2 (en) Construction method of outer wall of propulsion pipe and large cavity
JP2899668B2 (en) Simple underground construction
JPH11158865A (en) Underground structure having wall using steel sheet pile as core and method for constructing the same
CN219772980U (en) Underground combined supporting structure of deep foundation pit adjacent building
JPS61257529A (en) Underground continuous wall construction work
JP2006009468A (en) Driving method of inner excavation type steel pipe sheet pile and the steel pipe sheet pile used therefor
JPS62291318A (en) Connection of underground wall
KR102655503B1 (en) Messershield sphere, variable end reinforcement device, and tunnel excavation method using the same
CN212296372U (en) Reinforcing cage connecting structure at entrance and exit portal position of shield tunneling machine in end well
JPS6248011B2 (en)
JP2003328357A (en) Steel pipe sheet pile method
JPH1113062A (en) Simplified pneumatic caisson earth retaining construction method
JPH0415791Y2 (en)