JPS63297602A - Track beam construction method of high double track - Google Patents

Track beam construction method of high double track

Info

Publication number
JPS63297602A
JPS63297602A JP13463587A JP13463587A JPS63297602A JP S63297602 A JPS63297602 A JP S63297602A JP 13463587 A JP13463587 A JP 13463587A JP 13463587 A JP13463587 A JP 13463587A JP S63297602 A JPS63297602 A JP S63297602A
Authority
JP
Japan
Prior art keywords
girder
track
span
hand
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP13463587A
Other languages
Japanese (ja)
Inventor
坂井 裕親
村田 師男
岩池 昭二郎
一男 山田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KASADO KIKAI KOGYO KK
Original Assignee
KASADO KIKAI KOGYO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KASADO KIKAI KOGYO KK filed Critical KASADO KIKAI KOGYO KK
Priority to JP13463587A priority Critical patent/JPS63297602A/en
Publication of JPS63297602A publication Critical patent/JPS63297602A/en
Pending legal-status Critical Current

Links

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、跨座型モルレール等、高架軌道の複線部の軌
道桁の架設に好適な工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a construction method suitable for constructing a track girder for a double track section of an elevated track, such as a straddle-type mole rail.

〔従来の技術〕[Conventional technology]

従来、この種の軌道の架設工法としては、トラック・ク
レーン、手延式ガーダ、門構、ll製2又、仮設クレー
ン等による方法があり、それぞれ単独で、あるいは2以
上の工法が併用されているが、何れも地理的条件、架設
スピード即ち工期、あるいは工費等、何等かの制約を受
ける欠点を有している。
Traditionally, this type of track has been constructed using methods such as truck cranes, hand-stretched girders, gate structures, ll-made bifurcated cranes, and temporary cranes, each of which may be used alone or two or more of these methods may be used in combination. However, all of them have the disadvantage of being subject to some kind of restriction, such as geographical conditions, construction speed, construction period, or construction cost.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

モルレール軌道桁の架設において、一般的に広く利用さ
れている手延式ガーダ工法は、ガーダの繰出しに−々ト
ラック・クレーンを使用しなければならず、また地形上
トラック・クレーンが利用できない場所では、支柱上に
仮設クレーンを設置しなければならず、これが架設工期
の短縮を阻害するネックになっていた。本発明の目的は
、従来の架設工法の欠点を排除し、安価で工期の短い、
かつ安全な架設工法を提供することにあり、特に架設工
期の短縮にその特長を有するものである。
The hand-stretched girder construction method, which is generally widely used in the erection of Morrail track girders, requires the use of trucks and cranes to unroll the girders, and in places where trucks and cranes are not available due to terrain. However, a temporary crane had to be installed on the support pillars, which was a bottleneck in shortening the construction period. The purpose of the present invention is to eliminate the drawbacks of conventional erection methods, and to provide an inexpensive and short construction method.
The object of the present invention is to provide a safe construction method, which is particularly advantageous in shortening the construction period.

〔問題点を解決するための手段〕[Means for solving problems]

上記の問題点を解決するため、本発明では、門構クレー
ンの一部に、電動機及びピニオン・ラック等の水平方向
動力伝達装置を設けることにより、トラック・クレーン
等、他の吊上装置に頼ることなく、手延ガーダをいわゆ
る尺取虫的に、軌道支柱上を自動的に、水平移動させる
ことにより、軌道桁の架設を進めていくものである。
In order to solve the above problems, the present invention provides a part of the gate crane with a horizontal power transmission device such as an electric motor and a pinion rack, thereby relying on other lifting devices such as a truck crane. The construction of the track girder is proceeded by automatically moving the hand-stretched girder horizontally on the track support like a so-called inchworm.

〔実施例〕〔Example〕

以下、図面にもとづき、本発明の詳細な説明する。 Hereinafter, the present invention will be described in detail based on the drawings.

第1〜6図は、本発明による高架複線軌道桁の架設工法
を、各ステップ毎に示したものであり、第1図は、架設
すべき新桁の搬入準備が完了した状態を示す、即ち、1
は軌道桁支柱、2は既架設桁、4.5は手延ガーダ(4
はガーダ、5はパイロット)、且は門構クレーン、Aは
新桁の架設スパンを示す、先ず、トラック・クレーン等
により、手延ガーダ4,5を新桁架設スパンAを含む支
柱1,1上に設置し、その上に門構クレーン旦を設置し
、新桁架設スパンAの一つ前方の(図の左側)スパン上
に待機させる(第1図)0次に、桁運搬台車7,7によ
り、新桁3を搬入し、スパンAの支柱1,1上に降ろす
(第2図)0桁運搬台車7,7は、既設の桁上を図の右
側に移動させ、続いて門構クレーン且を1図の右方向に
移動させて、新桁架設スパンA上の定位ユに固定する(
第3図)1次に、門構クレーンに設けた電動機及びピニ
オン・ラック等の水平方向動力伝達装置により、手延ガ
ーダ4,5を図の左方向へ1スパン分前進させる(第4
図)。門構クレーン6の構造。
Figures 1 to 6 show each step of the method for constructing an elevated double track girder according to the present invention, and Figure 1 shows a state in which preparations for carrying in a new girder to be erected have been completed, i.e. ,1
is the track girder support, 2 is the existing girder, 4.5 is the hand-stretched girder (4
is the girder, 5 is the pilot), and gate crane, and A is the span of the new girder. First, a truck crane or the like is used to move the manual girders 4 and 5 to the supports 1 and 1, including the span A where the new girder is to be erected. A gate crane is installed on top of it, and the gate crane is placed on standby on the span one span ahead of the new girder erection span A (on the left side of the figure) (Figure 1).Next, the girder transport trolley 7, 7, the new girder 3 is carried in and lowered onto the pillars 1 and 1 of span A (Fig. 2). The 0 girder transport carts 7 and 7 move the existing girder to the right side of the figure, and then move the Move the crane to the right in Figure 1 and fix it to the positioning unit on the new girder construction span A (
(Fig. 3) First, the hand girders 4 and 5 are advanced by one span to the left in the figure by the horizontal power transmission device such as the electric motor and pinion rack installed on the gate crane (Fig. 3).
figure). Structure of gate crane 6.

機能については後述する6手延ガーダ4,5を前進させ
た後、門構クレーン6によって、新桁3をスパンA上の
正規の位置にセットし、固定する(第5図)。門構クレ
ーン6は、次の架設スパンA′の一つ前方の(図の左側
)スパンまで移動させ。
After advancing the six-hand girders 4 and 5 whose functions will be described later, the new girder 3 is set and fixed at the proper position on the span A by the gate crane 6 (Fig. 5). The gate crane 6 is moved to the span one span ahead of the next erection span A' (to the left in the figure).

桁運搬台車7,7により、新桁3′を次の架設スパンA
′の定位置に搬入する(第6図、第2図)。以下、第2
図からの手順を繰返し、1スパン宛、新桁を架設して行
く。
The new girder 3' is moved to the next erection span A using the girder transport carts 7 and 7.
(Fig. 6, Fig. 2). Below, the second
Repeat the steps from the diagram to erect a new girder for each span.

次に1本架設工法の主体をなす門構クレーン旦の機能を
、第7,8図により説明する。第7図は門構クレーン旦
の概略構造を、第8図はその動力部の片側を示す、門構
クレーン旦を、新桁架設スパンA上の定位置に移動せし
め(第3図)、門構11の端部に設置した固定腕13と
、支柱1に設けたブラケット15とを、ビン等で結合し
、門構クレーンを支柱に固定する(第7図)1次いで。
Next, the functions of the gate crane, which is the main body of the single-line construction method, will be explained with reference to Figures 7 and 8. Figure 7 shows the schematic structure of the gate crane, and Figure 8 shows one side of its power section.The gate crane is moved to a fixed position on the new girder construction span A (Figure 3) First, the fixed arm 13 installed at the end of the structure 11 and the bracket 15 provided on the support column 1 are connected with a bottle or the like, and the gate crane is fixed to the support support (FIG. 7).

電動機16により、スプロケット・チェノ19を介して
、ピニオン17を図の時計方向に回転せしめる0手延ガ
ーダ4には、ピニオン17と噛合うラック18を設けて
いるので、ピニオン17の時計方向の回転に伴ない、ラ
ックは図の左方向へ押出され(第8図)、同時に手延ガ
ーダ4は、支柱上に設けた案内軸2o上を左方向に繰出
され、第4図の位置で停止させる。門構クレーン且の揚
重装[12は、横方向にシフトできる構造になっている
ので(第7図)、第4図の如く支柱1上に置かれた新桁
3は、既設桁2・に準じてシフトされ(第5図)、支柱
1,1に固定されて架設を完了する。最後に、固定腕1
3とブラケット15の結合ピンを解放し、門構クレーン
旦は第6図の位置に移動して、1サイクルの作業を終了
する。なお、手延ガーダの繰出し機構(ピニオン・ラッ
ク)は第7図に示す如く、左右両側に設けることもでき
、左右の電動機を、従って左右のピニオン・ラックを、
別々に制御することによって、手延ガーダの繰出しを、
左右別々に調整することも可能である。
The electric motor 16 rotates the pinion 17 clockwise in the figure via the sprocket/cheno 19.The manual girder 4 is provided with a rack 18 that meshes with the pinion 17, so that the clockwise rotation of the pinion 17 is prevented. Accordingly, the rack is pushed out to the left in the figure (Figure 8), and at the same time, the hand-stretched girder 4 is pushed out to the left on the guide shaft 2o provided on the support column, and is stopped at the position shown in Figure 4. . The gate crane and lifting equipment [12] have a structure that can be shifted laterally (Fig. 7), so the new girder 3 placed on the support column 1 as shown in Fig. 4 is (Fig. 5), and is fixed to the pillars 1, 1 to complete the erection. Finally, fixed arm 1
3 and the bracket 15 are released, and the gate crane moves to the position shown in FIG. 6, completing one cycle of work. Note that the hand girder feeding mechanism (pinion rack) can be provided on both the left and right sides as shown in Fig. 7, and the left and right electric motors, and therefore the left and right pinion racks,
By separately controlling the feeding of the hand-stretched girder,
It is also possible to adjust the left and right sides separately.

発明の効果 本発明によれば、あるスパンの新桁架設終了後次のスパ
ンの架設に当って1手延ガーダはトラック・クレーン、
m製二又等の吊上装置を使用することなく、門構クレー
ンの動力によって、支柱上を1スパン分、横移動するこ
とができるので、架設工期を大巾に短縮できると共に、
工費を低減できる等の効果がある。特に、地理的条件か
らトラック・クレーンが利用できない個所での新桁架設
には、大きな効果を発揮することができる。
Effects of the Invention According to the present invention, after completing the construction of a new girder for a certain span, when constructing the next span, one hand-stretched girder is constructed using a truck crane,
Since it is possible to move horizontally one span on the support using the power of the gate crane without using a lifting device such as a bifurcated lifting device made by M, the construction period can be greatly shortened, and
This has the effect of reducing construction costs. It can be especially effective when erecting new girders in locations where trucks and cranes cannot be used due to geographical conditions.

また、手延ガーダの繰出し機構(横移動装置)を左右に
設け1個々に制御することによって、手延ガーダの繰出
しを、左右別々に調整することができる。
Further, by providing hand girder feeding mechanisms (lateral movement devices) on the left and right sides and controlling each one individually, the hand girder feeding can be adjusted separately for the left and right sides.

【図面の簡単な説明】[Brief explanation of drawings]

第1図;新桁架設準備完了 第2図;新桁を架設スパン上に搬入 第3図;門構クレーンを架設スパン上に移動第4図;手
延ガーダを1スパン分繰出し第5図;新桁を架設定位置
にセット、固定第6図;門構クレーンが移動し、次の新
桁架設準備完了 第7図;門構クレーンの概略構造 第8図;手延ガーダの繰出し機構 符号の説明 1;軌道桁支柱 2;既架設桁 3.3’;新架設桁、 A、 A’ ;新架設スパン4
;手延ガーダ(ガーダ部分) 5;手延ガーダ(パイロット部分) 且;門構クレーン 7;桁運搬台車 (8,9,10;欠番) 11;門構クレーン 門構 12;同上 揚重装置 13;同上 固定腕 14;同上 門構支持車輪 15;門構クレーン固定ブラケット及びピン16;門構
クレーン 電動機 17;同上 ピニオン 18;ラック(手延ガーダ側) 19;門構クレーン スプロケット・チェノ20:手延
ガーダ案内軸 \〜% < e’−cq 区         図 −二=コ   ロゝロ=コ   印 大°            狩 23図 tデー−−ス7’o 7/ト、ナエノ ん
Fig. 1: Preparation for erection of new girder Fig. 2: New girder is carried onto the erected span Fig. 3: Gate crane is moved onto the erected span Fig. 4: Manual girder is paid out for one span Fig. 5; The new girder is set and fixed in the frame setting position Fig. 6; The gate crane moves and the preparation for the next new girder erection is completed. Fig. 7; Schematic structure of the gate crane Fig. 8; Manual girder feeding mechanism code Description 1; Track girder support 2; Existing girder 3.3'; Newly erected girder, A, A'; Newly erected span 4
;Hand-stretched girder (girder part); 5;Hand-stretched girder (pilot part); and;Gateway crane 7;Girder transport trolley (8, 9, 10; missing numbers) 11;Gateway crane Gatework 12;Same as above Lifting device 13 Same as above Fixed arm 14; Same as above Gate support wheel 15; Gate crane fixing bracket and pin 16; Gate crane electric motor 17; Same as above Pinion 18; Rack (hand girder side) 19; Gate crane sprocket/cheno 20: Hand Extended girder guide shaft \ ~ % <e'-cq ward Figure 2 = Kororo = Ko Indai° Kari 23 Figure t Date 7'o 7/To, Naenon

Claims (1)

【特許請求の範囲】[Claims] 門構クレーン、手延ガーダ、桁運搬台車を使用して行な
う高架複線軌道の桁架設方法において、門構クレーンの
一端に設けた電動機及び動力伝達装置により、手延ガー
ダに設置したラックを駆動せしめ、手延ガーダが支柱上
を1スパン分あて、水平移動できるようにしたことを特
長とする、高架複線軌道の軌道桁架設方法。
In a girder erection method for an elevated double-track track using a gate crane, hand girder, and girder carrier, a rack installed on the hand girder is driven by an electric motor and power transmission device installed at one end of the gate crane. , a method for constructing a track girder for an elevated double-track track, characterized in that the hand-stretched girder rests on the support for one span so that it can move horizontally.
JP13463587A 1987-05-28 1987-05-28 Track beam construction method of high double track Pending JPS63297602A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13463587A JPS63297602A (en) 1987-05-28 1987-05-28 Track beam construction method of high double track

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13463587A JPS63297602A (en) 1987-05-28 1987-05-28 Track beam construction method of high double track

Publications (1)

Publication Number Publication Date
JPS63297602A true JPS63297602A (en) 1988-12-05

Family

ID=15132980

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13463587A Pending JPS63297602A (en) 1987-05-28 1987-05-28 Track beam construction method of high double track

Country Status (1)

Country Link
JP (1) JPS63297602A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102852090A (en) * 2012-09-07 2013-01-02 北京交通大学 High-speed railway long-span bridge unit-type ballastless track seamless line design method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102852090A (en) * 2012-09-07 2013-01-02 北京交通大学 High-speed railway long-span bridge unit-type ballastless track seamless line design method

Similar Documents

Publication Publication Date Title
CN205688903U (en) A kind of vertical circulation mechanical parking storehouse
CN101942807B (en) Flow type bridge erecting machine
JP2000230205A (en) Elevated track construction method and device
JPS63297602A (en) Track beam construction method of high double track
CN105421239B (en) Hoisting method for large-span highway-railway dual-purpose steel truss girder bridge deck slab
CN111996911A (en) Bridge girder erection machine and bridge girder erection method thereof
JPS61155075A (en) Car body assembly apparatus
CN212688732U (en) Rush-repair beam erecting device
JPH08326002A (en) Rail conveyor
JP2000230206A (en) Elevated track construction method and device
JP2638908B2 (en) Bridge crane leg structure
JP2000230204A (en) Elevated track construction method and device
CN212612014U (en) Bridge erecting machine
JPH1181242A (en) Precast block installation device
CN218116174U (en) Quick span-changing single-girder four-leg universal bridge girder erection machine
SU493541A1 (en) Movable support for working platform suspension
CN111519548A (en) First-aid repair beam erecting device and method
JPS5833614A (en) Temporary construction of overhead bridge
CN211920697U (en) Full-prefabricated cover beam cross-line type erection gantry crane
JPS6388500A (en) Method and device for cutting high radioactive solid waste
JP2690345B2 (en) Bridge construction method and equipment
JP3718033B2 (en) Precast block erection device
JP2747597B2 (en) Position fine adjustment device
JPS6187060A (en) Distributor apparatus
JPS6055165A (en) Construction apparatus of building peripheral wall surface