JPS63289122A - Construction of cut-off wall - Google Patents

Construction of cut-off wall

Info

Publication number
JPS63289122A
JPS63289122A JP12482887A JP12482887A JPS63289122A JP S63289122 A JPS63289122 A JP S63289122A JP 12482887 A JP12482887 A JP 12482887A JP 12482887 A JP12482887 A JP 12482887A JP S63289122 A JPS63289122 A JP S63289122A
Authority
JP
Japan
Prior art keywords
water
stop sheet
sheet
water stop
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP12482887A
Other languages
Japanese (ja)
Inventor
Shigeaki Hiraoka
成明 平岡
Yoshiaki Ikeuchi
池内 義明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP12482887A priority Critical patent/JPS63289122A/en
Publication of JPS63289122A publication Critical patent/JPS63289122A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To simplify the construction work of cut-off walls by a method in which a water-stop sheet is set in an excavated pit for preceding element, a solidifying agent is placed, a water-stop sheet is also set in an excavated pit for following element, and both elements are connected to each other. CONSTITUTION:A water-stop sheet 6 having bonding parts 7a on its left and right-handed ends is set with a guide metal 5 in an excavated pit 3 for preceding element, and the ends 6 of the sheet are protected by coupler metals 4. A solidifying agent 20, e.g., concrete, is placed into the pit 3. An excavated pit 13 for following element is then formed, metals 4 are removed, and a water-stop sheet 6 having bonding parts 7b on its left and right-handed ends are hung down into the pit 13 by unwinding the sheet 6. The sheets 6 for preceding elements are connected at the bonding parts 7a and 7b, the guide metal 5 is removed, and the agent 20 is placed into the pit 13 to form a continuous cut-off wall with both elements 6 and 14. The construction work can thus be attained economically without the need for reinforcing bars.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、建築基礎工事や土木工事における止水壁の構
築方法に関する。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for constructing a water-stop wall in building foundation work or civil engineering work.

〔従来の技術とその問題点〕[Conventional technology and its problems]

止水壁は通常の連続地中壁によることが多く、これは周
知のごとく横長掘削孔内に鉄筋カゴを建込みコンクリー
トを打設して連続する鉄筋コンクリートパネルを地中に
造成していく。かかる連続地中壁は施工に手間がかかり
、また多量のコンクリートや鉄筋を使用するため経済的
に高いものとなり、土留として耐力的なものを必要とす
る場合以外はコスト高となる。
Water cutoff walls are often made of ordinary continuous underground walls, which, as is well known, are constructed by building a reinforcing cage in a horizontally long excavated hole and pouring concrete to create a continuous reinforced concrete panel underground. Such a continuous underground wall takes time and effort to construct, and is economically expensive because it uses a large amount of concrete and reinforcing steel, and is expensive unless a strong earth retaining structure is required.

しかも、コンクリートパネルでのクランクの発生や鉄筋
の腐食、壁体相互の継手部分の漏水処理の難しさなどに
より確実な止水は期待できないことが多い。
Moreover, reliable water stoppage cannot often be expected due to the occurrence of cranks in concrete panels, corrosion of reinforcing bars, and difficulty in treating water leakage at joints between walls.

また現場を掘削することで発生した土砂を、セメント等
と混合してフィルモルタルの止水壁とすることもあるが
、これも確実な止水は期待できない。
In addition, earth and sand generated by excavating the site may be mixed with cement and other materials to form water-stop walls for fill mortar, but this method cannot be expected to provide a reliable water stop.

そこで、止水処理のみを目的とする場合は地中に防水材
による止水膜を形成し、これで止水を行うことが考えら
れる。例えば、特公昭62−2084号公報に示される
ものは、掘削溝の深さに等しい横幅の防水シートをロー
ル状態で専用台車上に載せておき、該防止シートの先端
を引き出して掘削溝内に垂直に挿入し、かつ溝内で直角
に折り曲げて台車を移動させながら順次建込み、地中に
埋設していく。
Therefore, if the purpose is only to stop the water, it may be possible to form a water-stop membrane using a waterproof material underground and use this to stop the water. For example, in the method disclosed in Japanese Patent Publication No. 62-2084, a waterproof sheet with a width equal to the depth of an excavated trench is placed in a roll on a special trolley, and the tip of the prevention sheet is pulled out and inserted into the excavated trench. It is inserted vertically and bent at right angles in the trench, and the truck is moved to gradually build it and bury it underground.

しかし、この特公昭62−2084号公報のものは一度
溝内に垂直に挿入してから横方向に直角に折り曲げ、防
水シートの展延方向を変えなければならないので、ロー
ル全体が横方向に引張られてズレやすく、スムーズにシ
ートを繰り出すことができないので施工を困難にしてい
る。
However, the waterproof sheet disclosed in Japanese Patent Publication No. 62-2084 has to be inserted vertically into the groove and then bent horizontally at right angles to change the spreading direction of the waterproof sheet, so the entire roll is stretched horizontally. This makes construction difficult because the sheets tend to shift and cannot be rolled out smoothly.

また、防水シートを横引きして敷設していくので止水壁
の深さと対応した防水シートの幅は取り扱い上限界があ
り、地中深い止水壁の施工は不可能なものである。
Furthermore, since the waterproof sheet is laid horizontally, there is a limit to the width of the waterproof sheet that corresponds to the depth of the water cutoff wall, making it impossible to construct water cutoff walls deep underground.

本発明の目的は、前記従来例の不都合を解消し、構造が
簡単で部材数が少なく、簡単かつ安価に施工でき、しか
も確実な止水効果が得られ、また深度の大きい止水壁で
も構築可能な止水壁の構築方法を提供することにある。
The purpose of the present invention is to solve the disadvantages of the conventional example, to have a simple structure, a small number of members, to be able to be constructed easily and inexpensively, to obtain a reliable water-stopping effect, and to be able to construct a water-stopping wall with a large depth. The purpose of the present invention is to provide a method for constructing a water-stop wall.

〔問題点を解決するための手段〕[Means for solving problems]

本発明は前記目的を達成するため、先行エレメント用掘
削孔内に、左右端縁に接着部を形成した止水シートをガ
イド金物で支持するようにして建込み、該止水シート端
部を継手金物等で防護して先行エレメント用掘削孔内に
コンクリート、モルタル等固結材の打設を行い、次いで
後行エレメント用掘削孔を造成後継手金物等を撤去し、
後行エレメント用掘削孔内に左右端縁に接着部を形成し
た止水シートを順次巻戻しながらロールごと吊降ろし先
行エレメントの止水シートと接着部同士の接合で連結し
、ガイド金物撤去後に、後行エレメント用掘削孔にコン
クリートまたはモルタル等の固結材を打設して先行、後
行両エレメントで連続する止水壁を形成することを要旨
とするものである。
In order to achieve the above object, the present invention installs a water stop sheet with adhesive parts formed on the left and right edges in the excavation hole for the preceding element so as to support it with guide metal fittings, and connects the ends of the water stop sheet with joints. Consolidating materials such as concrete and mortar are placed in the excavated hole for the preceding element while protecting it with hardware, etc. Next, the excavated hole for the succeeding element is created and the successor hardware is removed.
The water stop sheet with adhesive parts formed on the left and right edges is sequentially unwound into the excavation hole for the trailing element and suspended in its entirety, connected to the water stop sheet of the leading element by joining the adhesive parts together, and after removing the guide hardware. The gist of this method is to pour a solidifying material such as concrete or mortar into the excavation hole for the trailing element to form a continuous water-stop wall between both the leading and trailing elements.

〔作用〕[Effect]

本発明によれば、止水シートは垂直方向に建込むもので
あるから、深度の大きい止水壁を造成できる。
According to the present invention, since the water-stop sheet is erected in the vertical direction, a water-stop wall with a large depth can be constructed.

また、先行エレメント用掘削孔の止水シートと後行エレ
メント用掘削孔の止水シートは端同士を重なり合うよう
にして接着接合され一体連続的なものとなり、しかもそ
の外側はコンクリート、モルタル等の固結材で充填され
ているので確実に止水が得られる。
In addition, the water stop sheet in the drilling hole for the leading element and the water stop sheet in the drilling hole for the trailing element are adhesively bonded so that their edges overlap and are continuous, and the outside is covered with concrete, mortar, etc. Filled with binder to ensure water stoppage.

〔実施例〕〔Example〕

以下、図面について本発明の実施例を詳細に説明する。 Embodiments of the present invention will be described in detail below with reference to the drawings.

先に、先行エレメントを間隔を存して形成し、その間に
後行エレメントを形成する場合について説明すると、ま
ず、第1図に示すように、ガイドウオール1に沿って、
安定液2を使用して崩壊防止を図りながら、また適宜ス
ライム処理を行って地盤を所定深さまで掘削し、先行エ
レメント用の横長帯状の掘削孔3を造成する。
First, the case where the leading elements are formed at intervals and the trailing elements are formed in between is explained. First, as shown in FIG. 1, along the guide wall 1,
The ground is excavated to a predetermined depth by using a stabilizing liquid 2 to prevent collapse and by appropriately treating the slime to create an oblong belt-shaped excavation hole 3 for the preceding element.

以上は、一般の地中連続壁の施工と同じである。The above is the same as the construction of a general underground continuous wall.

次いで、第2図に示すように該先行エレメント用掘削孔
3の左右端にロッキングプレート又はパイプのごとき継
手金物4をセットし、鉄骨を組合せ両側面に鉄板を貼り
合わせた柱状のガイド金物5をその内側にセットする。
Next, as shown in FIG. 2, fitting fittings 4 such as locking plates or pipes are set at the left and right ends of the drilling hole 3 for the preceding element, and a columnar guide fitting 5 with steel frames and steel plates bonded to both sides is set. Set it inside.

そして、ガイド金物5に沿ってビニールシートやゴムシ
ートのごとき止水シート6を掘削孔3内に建込み、かつ
ガイド金物5間で止水シート6を仮固定する。
Then, a water stop sheet 6 such as a vinyl sheet or a rubber sheet is built into the excavation hole 3 along the guide hardware 5, and the water stop sheet 6 is temporarily fixed between the guide hardware 5.

該止水シート6は左右端縁にマジックテープ(登録商標
名)のごとき布製ファスナーによる接着部7aを形成し
たもので、建込みに際しては第7図に示すようにロール
状にして地上に設置し、その引出端に重錘8を取付けて
、ガイド金物5に沿って順次繰出していくようにする。
The water stop sheet 6 has adhesive parts 7a formed on the left and right edges using cloth fasteners such as Velcro tape (registered trademark), and when installing it, it is rolled and placed on the ground as shown in Fig. 7. A weight 8 is attached to the end of the drawer so that the metal fitting 5 is sequentially drawn out along the guide hardware 5.

図中19はこの場合のガイドローラで、ガイド金物5の
上端に取付けた。
Reference numeral 19 in the figure represents a guide roller in this case, which was attached to the upper end of the guide hardware 5.

なお、この止水シート6の仮固定の一例として左右端に
は予め電磁石9を連続または適宜間隔で取り付けておき
、止水シート6をガイド金物5に沿って建込んだあと、
該電磁石9に通電すれば、磁力で止水シート6をガイド
金物5に固定することができる。
As an example of temporarily fixing the water stop sheet 6, electromagnets 9 are attached in advance to the left and right ends continuously or at appropriate intervals, and after the water stop sheet 6 is erected along the guide hardware 5,
When the electromagnet 9 is energized, the water stop sheet 6 can be fixed to the guide hardware 5 by magnetic force.

また、止水シート6の左右端に信号発信ケーブル10を
取付け、これで左右端の位置を確認することも可能であ
る。
Furthermore, it is also possible to attach the signal transmission cables 10 to the left and right ends of the water stop sheet 6 and confirm the positions of the left and right ends.

次に、第3図に示すよう、チューブ状のパッカー11を
バッカーガイド12によって支持しつつ継手金物4の内
側に設置し、空気圧や液体圧によりパフカー11を膨ら
まして止水シート6の端部をガイド金物5との間に挟み
込み固定する。このようにすれば、止水シート6端は継
手金物4内でガイド金物5とバンカー11とに囲まれて
外部に露出せず、防護される。
Next, as shown in FIG. 3, the tubular packer 11 is supported by the backer guide 12 and installed inside the fitting 4, and the puffer 11 is inflated by air pressure or liquid pressure to seal the end of the water stop sheet 6. It is inserted and fixed between the guide hardware 5. In this way, the end of the water stop sheet 6 is surrounded by the guide metal fitting 5 and the bunker 11 within the joint metal fitting 4, and is protected without being exposed to the outside.

そして、第4図に示すように掘削孔3内にフィルモルタ
ルを含むモルタル、コンクリート等の固結材20を止水
シート6の端部を残して前後に打設する。
Then, as shown in FIG. 4, a consolidating material 20 such as mortar, concrete, etc. including fill mortar is placed in the excavated hole 3 in the front and rear directions, leaving the ends of the water stop sheet 6 intact.

固結材20の硬化後隣接個所を掘削して後行エレメント
用の横長帯状の掘削孔13を造成し、第5図に示すよう
バンカー11内の圧を減少しパッカーガイド12と共に
撤去し、ガイド金物5を残して継手金物4を引き抜(。
After hardening of the consolidating material 20, an adjacent location is excavated to create an oblong strip-shaped excavation hole 13 for the trailing element, and as shown in FIG. 5, the pressure inside the bunker 11 is reduced and the bunker is removed together with the packer guide 12, and the guide Pull out the fitting hardware 4 leaving the hardware 5 (.

すると、掘削孔13の両側方に止水シート6の端部が現
れる。
Then, the ends of the waterstop sheet 6 appear on both sides of the excavated hole 13.

第9図に示すように、前記先行エレメント用の止水シー
ト6と同様な帯状のビニールシートや合成ゴムシート等
の防水素材によるシートで、表側の左右両端縁に止水シ
ート6の接着部7aと接着可能な接着部7bを形成した
後行エレメント用の止水シート14を準備し、これをロ
ール状態に巻き、前方に圧着ローラ15を設けた吊下具
16に取付けておく。
As shown in FIG. 9, it is a sheet made of a waterproof material such as a band-shaped vinyl sheet or a synthetic rubber sheet similar to the water stop sheet 6 for the preceding element, and the adhesive portion 7a of the water stop sheet 6 is attached to both left and right edges of the front side. A water stop sheet 14 for the trailing element having an adhesive portion 7b that can be bonded thereto is prepared, wound into a roll, and attached to a hanging tool 16 provided with a pressure roller 15 in front.

止水シート6の接着部7aがマジックテープのごとき布
製ファスナーによる場合は、止水シート14の接着部7
bもこのファスナーの一方片を利用する。
When the adhesive part 7a of the water stop sheet 6 is made of a cloth fastener such as Velcro, the adhesive part 7a of the water stop sheet 14
b also uses one piece of this fastener.

なお、他の実施例としてこれら接着部?a、7bを形成
するマジックテープ(登録商標名)のごとき布製接着材
以外に粘着性テープを用いることでもできるし、他にも
接着剤をテープ状に塗布したものでもよい。
In addition, as another example, what about these adhesive parts? In addition to the fabric adhesive such as Magic Tape (registered trademark) forming the portions a and 7b, an adhesive tape may be used, or another adhesive may be applied in the form of a tape.

第8,9図に示すように、すでに建込んである止水シー
ト6端の接着部7aと、接着部7bとが合致するように
吊下具16でロール状の止水シート14をロールごと掘
削孔13内に吊下げ、止水シート14の先端を繰り出し
てガイドウオール1に固定する。そして、止水シート6
端を信号発信ケーブルlOからの信号でキャッチして、
接着部7aと接着部7bとが常に重なり合うように位置
を修正しつつ、順次巻戻しながら掘削孔13内に吊り降
ろしていき、前方にせり出す圧着用ローラ15によって
ガイド金物5で反力を取り去りながら接合し、止水シー
ト6と止水シート14とを一体連続化し、1枚の止水膜
とする。
As shown in FIGS. 8 and 9, the roll-shaped water-stop sheet 14 is held up by the hanging tool 16 so that the adhesive part 7a at the end of the water-stop sheet 6 that has already been installed is aligned with the adhesive part 7b. It is suspended in the excavation hole 13, and the tip of the water stop sheet 14 is drawn out and fixed to the guide wall 1. And water stop sheet 6
Catch the end with the signal from the signal transmission cable lO,
While correcting the position so that the bonded parts 7a and the bonded parts 7b always overlap, they are lowered into the excavated hole 13 while being unwound one by one, and the reaction force is removed by the guide hardware 5 by the crimping roller 15 that protrudes forward. The water-stop sheet 6 and the water-stop sheet 14 are joined together to form a single water-stop film.

次に第6図に示すように、ガイド金物5を撤去してから
、掘削孔13内にフィルモルタル、モルタル、コンクリ
ート等固結材20を上水シート6との接着部7bを含め
て止水シート14の前後に打設する。
Next, as shown in FIG. 6, after removing the guide hardware 5, a solidifying material 20 such as fill mortar, mortar, concrete, etc. is placed in the excavated hole 13, including the adhesive part 7b with the water supply sheet 6, to stop water. It is poured before and after the sheet 14.

このようにして前記した工程をくり返し、先行、後行エ
レメント毎に止水シートを一体連続し、かつその外側を
固結材20で固定して連続する止水壁を構築していく。
In this manner, the above-described process is repeated to construct a continuous water-stop wall by integrally and continuously forming the water-stop sheet for each of the leading and trailing elements, and fixing the outer side with the consolidating material 20.

なお、大深度の止水壁を構築する場合には掘削孔3.1
3も、より深いものとなるが、この場合は、第10図に
示すように、止水シート6の表側の先端縁に接着部17
aを形成し、これに接着可能な接着部17bを裏側の先
端縁に形成してロール状にした第2建込止水シート18
を、ロールごと掘削孔3に吊り降ろし長尺な止水シート
として建込むこともできる。
In addition, when constructing a water cutoff wall at great depth, drilling hole 3.1
3 is also deeper, but in this case, as shown in FIG.
A, a second built-in water stop sheet 18 is formed into a roll shape by forming an adhesive part 17b that can be adhered thereto on the tip edge of the back side.
It is also possible to suspend the whole roll into the excavation hole 3 and install it as a long water stop sheet.

また、前記実施例は先行エレメント用の掘削孔3を間隔
を存して複数光に形成し、その間に後行エレメント用の
掘削孔13を形成する場合について説明したが、各エレ
メント用の掘削孔を順次形成し、横に伸びてい(ような
施工方法についても同様である。
Furthermore, in the embodiment described above, a plurality of drilling holes 3 for the preceding element are formed at intervals, and a drilling hole 13 for the following element is formed between them. The same applies to construction methods such as sequentially forming and extending horizontally.

〔発明の効果〕〔Effect of the invention〕

以上説明したように、本発明の止水壁の構築方法は、シ
ート端同士が接着されて重なり合い、かつ、そのシート
が一体連続化してコンクリート等の固結材の躯体中に埋
めこまれているので、止水性が高くシート同士の継目か
らの漏水はないし、固結材の打継目とシート同士の接合
部の位置がずれているので確実な止水も行うことができ
るものとなる。
As explained above, in the method of constructing a water stop wall of the present invention, the ends of the sheets are glued together and overlapped, and the sheets are integrated and continuous and embedded in a frame of solidified material such as concrete. Therefore, water-stopping properties are high, and there is no water leakage from the joints between the sheets, and since the joints of the consolidation material and the joints between the sheets are misaligned, water can be reliably stopped.

また、止水シートを垂直に建込み、左右端縁で接合する
ので、止水シートの幅と地中に構築する止水壁の深さと
は関係なく、地中深い止水壁を構築できるし、止水シー
トの建込み時には、順次巻戻しながら垂直に降ろしてい
くので、ズレることなくスムーズに繰り出し可能で、簡
単に施工できる。
In addition, since the water-stop sheet is installed vertically and joined at the left and right edges, it is possible to construct a water-stop wall deep underground, regardless of the width of the water-stop sheet and the depth of the water-stop wall to be built underground. When installing the water stop sheet, it is unrolled and lowered vertically in sequence, so it can be unrolled smoothly without shifting, making it easy to install.

このように、止水膜によって確実に止水を行うことがで
きるので、止水壁の厚さを薄(しても充分であり、使用
するモルタル等の量を少なくすることができ、鉄筋を使
わないので経済的であり、特に固結材としてフィルモル
タルを使えば安価に施工できるものとなる。
In this way, water can be reliably stopped by the water stop film, so it is sufficient to make the water stop wall thin (even if it is thin), the amount of mortar, etc. used can be reduced, and the reinforcement It is economical because it is not used, and especially if fill mortar is used as the consolidation material, it can be constructed at a low cost.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図〜第6図は本発明の止水壁の構築方法の施工工程
を示す平面図、第7図は同上第2図のA−Aの矢視図、
第8図は同上後行エレメント内に止水シートの建込を示
す側面図、第9図は後行エレメントに止水シートを建込
む状態を示す正面図、第10図は本発明の止水壁の構築
方法の第2実施例を示し、先行エレメント用の掘削孔に
止水シートを建込む状態を示す側面図である。 1・・・ガイドウオール  2・・・安定液3・・・先
行エレメントの掘削孔 4・・・継手金物     5・・・ガイド金物6・・
・先行エレメント用の止水シート8・・・重錘    
   7a、7b・・・接着部10・・・信号発信ケー
ブル 9・・・電磁石11・・・バッカー 12・・・パッカーガイド 13・・・後行エレメント用の掘削孔 14・・・後行エレメント用の止水シート15・・・圧
着ローラ 16・・・吊下具      17a、 17b・・・
接着部18・・・第2建込止水シート
FIGS. 1 to 6 are plan views showing the construction process of the water-stop wall construction method of the present invention, FIG. 7 is a view taken along arrow A-A in FIG.
FIG. 8 is a side view showing how the water stop sheet is installed in the trailing element, FIG. 9 is a front view showing how the water stop sheet is installed in the trailing element, and FIG. 10 is the water stop sheet according to the present invention. It is a side view which shows the 2nd Example of the construction method of a wall, and shows the state in which a water stop sheet is built into the excavation hole for a preceding element. 1...Guide wall 2...Stabilizing liquid 3...Drilling hole of preceding element 4...Joint hardware 5...Guide hardware 6...
・Water stop sheet 8 for the preceding element... weight
7a, 7b...Adhesive part 10...Signal transmission cable 9...Electromagnet 11...Backer 12...Packer guide 13...Drilled hole 14 for trailing element...For trailing element water stop sheet 15...pressure roller 16...hanging tool 17a, 17b...
Adhesive part 18...Second built-in water stop sheet

Claims (1)

【特許請求の範囲】[Claims] 先行エレメント用掘削孔内に、左右端縁に接着部を形成
した止水シートをガイド金物で支持するようにして建込
み、該止水シート端部を継手金物等で防護して先行エレ
メント用掘削孔内にコンクリート、モルタル等固結材の
打設を行い、次いで後行エレメント用掘削孔を造成後継
手金物等を撤去し、後行エレメント用掘削孔内に左右端
縁に接着部を形成した止水シートを順次巻戻しながらロ
ールごと吊降ろし先行エレメントの止水シートと接着部
同士の接合で連結し、ガイド金物撤去後に、後行エレメ
ント用掘削孔にコンクリートまたはモルタル等の固結材
を打設して先行、後行両エレメントで連続する止水壁を
形成することを特徴とする止水壁の構築方法。
A water stop sheet with adhesive parts formed on the left and right edges is installed in the excavation hole for the preceding element, supported by guide hardware, and the ends of the water stop sheet are protected with joint hardware, etc., and excavation for the preceding element is started. Consolidating materials such as concrete and mortar were placed in the hole, and then an excavation hole for the trailing element was created. Successor hardware, etc. was removed, and adhesive parts were formed on the left and right edges in the excavation hole for the trailing element. The water stop sheet is unwound in sequence and suspended in its entirety. Connected to the water stop sheet of the preceding element by joining the adhesive parts, and after removing the guide hardware, concrete or mortar or other consolidating material is poured into the excavated hole for the following element. 1. A method for constructing a water cutoff wall, characterized in that a continuous water cutoff wall is formed using both leading and trailing elements.
JP12482887A 1987-05-20 1987-05-20 Construction of cut-off wall Pending JPS63289122A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12482887A JPS63289122A (en) 1987-05-20 1987-05-20 Construction of cut-off wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12482887A JPS63289122A (en) 1987-05-20 1987-05-20 Construction of cut-off wall

Publications (1)

Publication Number Publication Date
JPS63289122A true JPS63289122A (en) 1988-11-25

Family

ID=14895107

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12482887A Pending JPS63289122A (en) 1987-05-20 1987-05-20 Construction of cut-off wall

Country Status (1)

Country Link
JP (1) JPS63289122A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015132074A (en) * 2014-01-10 2015-07-23 前田建設工業株式会社 Method and device for connecting seepage control sheet under water, and cut-off construction method for continuous underground wall
JP2020097820A (en) * 2018-12-17 2020-06-25 鹿島建設株式会社 Construction method of earth retaining wall on slope and construction method of waste disposal site on slope

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015132074A (en) * 2014-01-10 2015-07-23 前田建設工業株式会社 Method and device for connecting seepage control sheet under water, and cut-off construction method for continuous underground wall
JP2020097820A (en) * 2018-12-17 2020-06-25 鹿島建設株式会社 Construction method of earth retaining wall on slope and construction method of waste disposal site on slope

Similar Documents

Publication Publication Date Title
CN108239984A (en) The assembled building enclosure and its construction method that terraced corrugated sheet steel is combined with steel truss
JPS63289122A (en) Construction of cut-off wall
JPH09125417A (en) Basement wall body and asymmetrically closed section steel pile
PT2364399E (en) Modular lining for tunnels
JP2001164563A (en) Underground wall using steel member used for wall of underground structure as core
JP2665801B2 (en) Locking box for the middle reading wall
JP2000297590A (en) Excavation wall construction method
JP3002697B2 (en) External waterproof sheet laying method for continuous underground wall
KR100969778B1 (en) Composite Wall Using Angled Channel and Constructing Method thereof
JP2969607B1 (en) Method for constructing box culvert without pulling out pile retaining pile and panel member used in this method
JPH073777A (en) Method for constructing self-supporting land slide protection wall
JP7341928B2 (en) Construction method for underground structures
JPS63122817A (en) Construction of cut-off wall using water-impermeable sheet and water-impermeable sheet therefor
CN109140046B (en) Method for plugging end of pipe jacking pipe curtain
JPS63304821A (en) Construction work of underground continuous cut-off wall
JP2565452B2 (en) Construction method of self-supporting retaining wall
JP2605941B2 (en) Construction method for underground structures
JPH101942A (en) Device and method for arranging flexible reinforcing bar
JPH028086B2 (en)
JPH07305345A (en) Device for building cutoff film and building method using same
JPS61191722A (en) Drawing and removing work for steel sheet pile
JP2872537B2 (en) Water blocking wall and method of constructing the same
JPS63297625A (en) Underground continuous cut-off wall construction work
JPH07127051A (en) Construction and erecting method for reinforcement cage for continuous underground wall execution
JP2556415B2 (en) Construction method of self-supporting retaining wall