JPS6315434Y2 - - Google Patents

Info

Publication number
JPS6315434Y2
JPS6315434Y2 JP11886282U JP11886282U JPS6315434Y2 JP S6315434 Y2 JPS6315434 Y2 JP S6315434Y2 JP 11886282 U JP11886282 U JP 11886282U JP 11886282 U JP11886282 U JP 11886282U JP S6315434 Y2 JPS6315434 Y2 JP S6315434Y2
Authority
JP
Japan
Prior art keywords
frame body
frame
formwork
tunnel
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP11886282U
Other languages
Japanese (ja)
Other versions
JPS5924497U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP11886282U priority Critical patent/JPS5924497U/en
Publication of JPS5924497U publication Critical patent/JPS5924497U/en
Application granted granted Critical
Publication of JPS6315434Y2 publication Critical patent/JPS6315434Y2/ja
Granted legal-status Critical Current

Links

Description

【考案の詳細な説明】 本考案は、車両等の通過の邪魔にならないよう
に構成されたトンネル側壁の型枠切梁装置に関す
る。
[Detailed Description of the Invention] The present invention relates to a formwork strut device for a tunnel side wall that is constructed so as not to obstruct the passage of vehicles and the like.

トンネルの掘削方法は種々知られており、例え
ば第1図および第2図に示すように、トンネルの
アーチ部分1を掘削してアーチコンクリート2を
打設し、その後大背部分3を掘削し、最後に側壁
部分4および5を掘削し、掘削した部分の側壁5
にコンクリートを打設する工法が広く実施されて
いる。
Various tunnel excavation methods are known. For example, as shown in FIGS. 1 and 2, an arch portion 1 of the tunnel is excavated, arch concrete 2 is poured, and then a large back portion 3 is excavated. Finally, side wall sections 4 and 5 are excavated, and side wall 5 of the excavated section is
The method of pouring concrete is widely practiced.

そしてこの工法によるときは側壁部分はアーチ
コンクリートジヨイント部分の足付(約3.0m)
を1間(約10.5m)とばしに土平掘削され、この
掘削された部分に側壁型枠を切梁装置によつてセ
ツトし、両側壁は交互にコンクリート打設される
が、本考案はこのような型枠を支持する切梁装置
に関し、具体的には第3図に示されているよう
に、側壁5に立設された型枠10を支持する切梁
装置20に関するものである。
When using this construction method, the side wall part is attached to the arch concrete joint part (approximately 3.0 m).
A flat earthen excavation is carried out over 1 meter (approximately 10.5 m), and side wall formwork is set in this excavated area using a beam cutting device, and concrete is poured alternately on both sides. The present invention relates to a strut device for supporting such a formwork, and specifically relates to a strut device 20 for supporting a formwork 10 erected on a side wall 5, as shown in FIG.

ところで、上記説明からも明らかであるが、側
壁型枠10はトンネルの向い合つた両側壁にセツ
トされるので、切梁装置はトンネルの掘削作業す
なわちトロツコ、コンクリート圧送車、或いは作
業員の交通の邪魔にならないように設ける必要が
ある。また打設されたコンクリートの養生が終る
と、型枠は取り外されて次の土平掘削された部分
へ移動されるので、組立、分解の容易なものが要
求される。そしてこれらの要求を満たすために、
従来から例えばガントリタイプ、ロツクボルトに
よる方法、胴張式、二回打による方法、或いは付
近の岩から切梁する方法等が提案されている。し
かしながら、これらの方法には一長一短があり、
最も効果のある切梁装置が望まれていた。すなわ
ち、トンネルの掘削に伴う作業の支障となること
なく、またセツト及び移動が簡単に出来、しかも
トンネル内を車両が通過するときも打設されたコ
ンクリートの養生の障害にならない切梁装置が望
まれていた。本考案は、このような事情のもとに
なされたものであつて、上記の要望事項は、トン
ネルの床面に載置される枠体と、該枠体と側壁型
枠とに枢着される伸長部材とから切梁装置を構成
し、該切梁装置に接触しないように覆工板と敷鉄
板とを設けることによつて達成される。
By the way, as is clear from the above explanation, since the side wall formwork 10 is set on the opposite side walls of the tunnel, the strut device is used for tunnel excavation work, that is, for transportation of trolleys, concrete pumping trucks, or workers. It must be placed so that it does not get in the way. Furthermore, once the poured concrete has finished curing, the formwork is removed and moved to the next excavated area, so it is required to be easy to assemble and disassemble. And to meet these demands,
Conventionally, methods such as a gantry type, a lock bolt method, a trunk type, a two-stroke method, and a method of cutting beams from nearby rocks have been proposed. However, these methods have advantages and disadvantages,
The most effective strut device was desired. In other words, it is desirable to have a strut device that does not interfere with the work associated with tunnel excavation, is easy to set up and move, and does not interfere with the curing of poured concrete when vehicles pass through the tunnel. It was rare. The present invention was developed under these circumstances, and the above requirements are met by a frame body placed on the floor of the tunnel, and a frame body that is pivotally connected to the side wall formwork. This is achieved by constructing a strut device from an elongated member, and providing a lining plate and a steel plate so that they do not come into contact with the strut device.

以下、本考案の一実施例を第3図ないし第5図
によつて説明する。
An embodiment of the present invention will be described below with reference to FIGS. 3 to 5.

トンネル側壁の型枠10は、それ自体公知のも
ので第3図および第4図に示すように、補強枠1
1と、これに取付けられた面板12とから成つて
いる。そして面板12の適所にはコンクリート圧
送口13が形成されている。この型枠10はその
上部は例えばすでに打設したアーチコンクリート
2にアンカーボルトを打込んで支持してもよく、
或いは岩盤にアンカーボルトを打込んでセパレー
タで位置決めして支持することもできる。
The formwork 10 for the tunnel side wall is of a known type, and as shown in FIGS. 3 and 4, a reinforcing frame 1 is used.
1 and a face plate 12 attached thereto. A concrete pumping port 13 is formed at a proper location on the face plate 12. The upper part of this formwork 10 may be supported, for example, by driving anchor bolts into the arch concrete 2 that has already been cast.
Alternatively, anchor bolts can be driven into the rock and positioned and supported using separators.

切梁装置20については、第4図および第5図
を参照して詳述するが、概略は第3図に示すよう
に、トンネルの床面5に載置される枠体30と、
該枠体と前記補強枠11との間に設けられる伸長
部材40とから構成されている。そしてこの枠体
には覆工板と敷鉄板とが該枠体に接触しないよう
に設けられている。
The strut device 20 will be described in detail with reference to FIGS. 4 and 5, but as schematically shown in FIG. 3, it includes a frame 30 placed on the floor surface 5 of the tunnel,
It is comprised of an elongated member 40 provided between the frame and the reinforcing frame 11. The frame is provided with a lining plate and an iron plate so as not to come into contact with the frame.

枠体30は、第4図に示すように例えばH型鋼
(H200×200×8×12)から井桁状に構成されて
いる。すなわち一対の縦部材31,31と一対の
横部材32,32とから井桁状に構成され、横部
材32,32の下面にはキヤンバー(ソリ板)3
3,33が設けられトンネル床面5からの高さ調
整が出来るようになつている。
As shown in FIG. 4, the frame body 30 is made of, for example, H-shaped steel (H200×200×8×12) in the shape of a parallel cross. In other words, it is constructed in a cross-shaped structure from a pair of vertical members 31, 31 and a pair of horizontal members 32, 32, and a camber (sled plate) 3 is provided on the lower surface of the horizontal members 32, 32.
3 and 33 are provided so that the height from the tunnel floor surface 5 can be adjusted.

伸長部材40は、ターンバツクルでもよいし、
また油圧によつて作動するピストンシリンダユニ
ツト型式のものでもよいが、第4図ではターンバ
ツクル型式のものが図示されている。そしてその
一方端41,41……は型枠10の補強枠11に
枢着42,42……され、他端43,43……は
枠体30の横部材32に枢着44,44……され
ている。
The elongated member 40 may be a turnbuckle,
It may also be a piston-cylinder unit type operated by hydraulic pressure, but a turnbuckle type is shown in FIG. One end 41, 41... is pivotally mounted 42, 42... to the reinforcing frame 11 of the formwork 10, and the other end 43, 43... is pivotally mounted 44, 44... to the horizontal member 32 of the frame 30. has been done.

覆工板50は、井桁状に構成された枠体30の
内側に設けられるもので、しかも枠体30に接触
しないように設けられる。従つて該板50を支持
する部材51,51は縦枠31より大きなH型鋼
(例えばH350×350×10−16)で構成され、この
部材51,51に第5図に示すように溶接などに
よつて固着されている。また部材51,51の両
外側すなわち覆工板50が設けられていない両外
側には、例えば200×90×8の溝型鋼の一方のフ
ランジ部分を切落して構成され支持部材52,5
2が溶着され、この部材上に敷鉄板60,60が
溶接或いは単なる設置などによつて、その一方端
が支持されている。このように部材51,51の
空間に、枠体30の縦部材31が設けられている
が、覆工板50と敷鉄板60は、枠体30に接し
ないことになる。なお敷鉄板60の両側縁には補
強部材61,61が設けられている。また必要に
よつては、この補強部材61,61を結合する部
材62,62も設けられている。
The lining board 50 is provided inside the frame body 30 configured in a cross-shaped cross-section, and is provided so as not to come into contact with the frame body 30. Therefore, the members 51, 51 supporting the plate 50 are made of H-beam steel (for example, H350 x 350 x 10-16) larger than the vertical frame 31, and the members 51, 51 are welded or the like as shown in FIG. It is twisted and fixed. Further, on both outer sides of the members 51, 51, that is, on both outer sides where the lining plate 50 is not provided, supporting members 52, 5 are constructed by cutting off one flange part of, for example, 200 x 90 x 8 channel steel.
2 is welded, and one end of the steel plates 60, 60 is supported on this member by welding or mere installation. Although the vertical member 31 of the frame body 30 is thus provided in the space between the members 51, 51, the lining board 50 and the paving iron plate 60 do not come into contact with the frame body 30. Note that reinforcing members 61, 61 are provided on both side edges of the iron plate 60. Further, if necessary, members 62, 62 for connecting the reinforcing members 61, 61 are also provided.

本考案は、以上のように構成されているので、
その使用法について説明すると、側壁の土平掘削
された部分にコンクリート側壁の形枠10および
切梁装置20をセツトする。この場合伸長部材4
0は、形枠10の補強枠11と枠体30の横部材
32とに対して枢着されているので、その角度は
任意に屈曲できる。従つて枠体30はトンネル床
面5に水平に載置され、伸長部材40は水平面か
らある角度傾斜することになる。概略のセツトが
終つたらキヤンバー33,33によつて高さ調整
をし、伸長部材40を伸長して形枠10を強固に
セツトする。なお覆工板50と敷鉄板60も、伸
長部材で形枠をセツトする前にセツトしておく方
が望ましい。
Since the present invention is configured as described above,
To explain how to use it, the form 10 of the concrete side wall and the strut device 20 are set in the excavated portion of the side wall. In this case, the extension member 4
0 is pivotally attached to the reinforcing frame 11 of the frame 10 and the horizontal member 32 of the frame body 30, so its angle can be bent arbitrarily. Therefore, the frame 30 is placed horizontally on the tunnel floor 5, and the elongated member 40 is inclined at a certain angle from the horizontal plane. After the rough setting is completed, the height is adjusted using the cambers 33, 33, and the extension member 40 is extended to firmly set the frame 10. Note that it is preferable to set the lining board 50 and the iron plate 60 before setting the frame using the extension members.

形枠10のセツトが終つたら、面板12に形成
されたコンクリート圧送口13から、コンクリー
トを圧送吹込み、コンクリート打設をする。そし
て固化養生を待つ。この養生期間中に車両等が切
梁装置20上を通過しても振動は枠体30、従つ
てコンクリート型枠10には伝わらないので、コ
ンクリートの養生の支障となることはない。トン
ネルの掘削作業の障害にならないことは明らかで
ある。養生が終つたら、伸長部材40の枢着点
で、型枠10から枠体30を分離する。この場合
伸長部材40は型枠10の方へ付けていても、ま
たは枠体30の方へ付けていてもよいことは明ら
かである。分離された枠体30すなわち切梁装置
はトラクタシヨベル等によつて次のコンクリート
打設個所まで牽引する。そして同様の手順によつ
てコンクリートの打設を行う。
After the form frame 10 is set, concrete is forced into the concrete through the concrete injection port 13 formed in the face plate 12, and concrete is poured. Then wait for curing. Even if a vehicle or the like passes over the strut device 20 during this curing period, the vibrations will not be transmitted to the frame 30, and therefore the concrete formwork 10, and will not interfere with the curing of the concrete. It is clear that this will not impede tunnel excavation work. After curing is completed, the frame body 30 is separated from the formwork 10 at the pivot point of the elongated member 40. It is clear that in this case the elongated member 40 can be attached either towards the formwork 10 or towards the frame 30. The separated frame 30, ie, the strut device, is towed by a tractor shovel or the like to the next concrete placement location. Concrete is then placed using the same procedure.

以上説明したように、本考案によると、切梁装
置は枠体と、該枠体とコンクリート型枠との間に
設けられる伸長部材とから構成され、伸長部材は
枠体と型枠とに枢着されているので、枠体はトン
ネルの床面に水平に載置でき、また移動のための
分解は枢着点で行うことができるので、トンネル
の掘削作業の邪魔にならず、また移動も簡単に出
来るものである。また車両等の通過を良くするた
めの覆工板および敷鉄板は枠体に接触しないよう
に設けられているので、車両等の通過がコンクリ
ートの養生の障害とならないという優れた効果を
有する。
As explained above, according to the present invention, the strut device is composed of a frame body and an elongated member provided between the frame body and the concrete formwork, and the elongated member is pivotally connected to the frame body and the concrete formwork. The frame body can be placed horizontally on the tunnel floor, and disassembly for movement can be done at pivot points, so it does not interfere with tunnel excavation work and can be easily moved. It's something that can be done easily. Furthermore, since the lining plate and the steel plate for facilitating the passage of vehicles, etc. are provided so as not to contact the frame, this has the excellent effect that the passage of vehicles, etc. does not impede the curing of the concrete.

本考案は、以上の実施例に限定されることな
く、色々変形が可能である。例えば覆工板50は
部材51,51に溶接することなく、単に台5
3,53上に載置するようにしてもよい。また敷
鉄板60は支持部材52,52に枢着するように
してもよい。その他色々変形可能であるが、それ
らはいちいち説明されていないだけである。
The present invention is not limited to the above embodiments, and can be modified in various ways. For example, the lining plate 50 is simply attached to the base 5 without being welded to the members 51, 51.
3, 53. Further, the paving iron plate 60 may be pivotally attached to the supporting members 52, 52. Many other variations are possible, but they are not explained in detail.

【図面の簡単な説明】[Brief explanation of drawings]

第1図および第2図は本考案を実施するそれぞ
れトンネルの掘削方法の一例を示すための横及び
縦断面図、第3図は本考案の装置の使用状態を示
す斜視図、第4図は本考案の一実施例を示す平面
図、第5図は第4図における矢視−でみた断
面図である。 4……トンネル側壁、10……トンネル側壁の
型枠、30……枠体、40……伸長部材、42,
44……枢着点、50……覆工板、60……敷鉄
板。
1 and 2 are horizontal and vertical cross-sectional views showing an example of the tunnel excavation method according to the present invention, FIG. 3 is a perspective view showing how the device of the present invention is used, and FIG. 4 is a FIG. 5 is a plan view showing an embodiment of the present invention, and FIG. 5 is a sectional view taken in the direction of the arrow - in FIG. 4. 4... Tunnel side wall, 10... Formwork for tunnel side wall, 30... Frame body, 40... Extension member, 42,
44... Pivot point, 50... Lining board, 60... Laying iron plate.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 型鋼から略井桁状に形成されてトンネルの床面
の中央部分に載置される枠体と、一端が該枠体
に、そして他端がトンネル側壁の型枠に枢着され
る伸長部材とから成り、前記枠体は覆工板の両外
側に設けた部材の外側に離れて設けられ、その外
側に設けた部材の高さは前記枠体の高さより高
く、その外側に設けた部材に支持された敷鉄板
と、前記覆工板とは前記枠体と空間を有している
ことを特徴とするトンネル側壁の型枠切梁装置。
A frame body formed from shaped steel into a substantially cross-shaped frame and placed in the center of the floor of the tunnel, and an elongated member having one end pivoted to the frame body and the other end pivoted to the formwork of the tunnel side wall. The frame body is provided apart from the members provided on both outside sides of the lining board, the height of the member provided on the outside is higher than the height of the frame body, and the frame body is supported by the member provided on the outside. A formwork strut device for a tunnel side wall, characterized in that the laid iron plate and the lining plate have a space with the frame body.
JP11886282U 1982-08-06 1982-08-06 Formwork strut device for tunnel side walls Granted JPS5924497U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11886282U JPS5924497U (en) 1982-08-06 1982-08-06 Formwork strut device for tunnel side walls

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11886282U JPS5924497U (en) 1982-08-06 1982-08-06 Formwork strut device for tunnel side walls

Publications (2)

Publication Number Publication Date
JPS5924497U JPS5924497U (en) 1984-02-15
JPS6315434Y2 true JPS6315434Y2 (en) 1988-04-28

Family

ID=30273030

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11886282U Granted JPS5924497U (en) 1982-08-06 1982-08-06 Formwork strut device for tunnel side walls

Country Status (1)

Country Link
JP (1) JPS5924497U (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62147757U (en) * 1986-03-12 1987-09-18

Also Published As

Publication number Publication date
JPS5924497U (en) 1984-02-15

Similar Documents

Publication Publication Date Title
US3785608A (en) Jig for precasting a plurality of panels
US5383319A (en) Method of erecting a foundation structure for a building substructure
JP2769936B2 (en) Construction method of beams and slabs in underground skeleton construction
JPS6315434Y2 (en)
JP4083334B2 (en) Underground structure having arch roof and method for constructing the same
CN106049256A (en) Profiled steel sheet-corrugated steel web-truss combined beam and construction method thereof
JPH08177059A (en) Footing block, and integrated method for constructing continuous footing employing footing block
JPH03199528A (en) Steel frame foundation of construction
JP2757032B2 (en) Construction method of underground building with pillars with capital by reverse hitting method
JP2864906B2 (en) Precast wall joining method
JPS6312987B2 (en)
JP2725572B2 (en) Small beam construction method in reinforced concrete construction
JP2853019B2 (en) Precast concrete foundation block and foundation formation method
FI90106C (en) FOERFARANDE FOER ATT BYGGA EN VAEGBAEDD OCH DESS ANVAENDNING
JP2534009B2 (en) Form support for overhang
JP2002146711A (en) Coupling type floor plate construction body
JP3047696U (en) Building with steel aerial foundation beam structure
JP2677189B2 (en) Steel beam for joining reinforced concrete columns
JP3656873B2 (en) Foundation construction method
JPH084343A (en) Garage
JP2784449B2 (en) Steel reinforced concrete foundation
JP4399062B2 (en) Construction method of viaduct underground beam
JP3002794B2 (en) How to build a building with a basement
JP3416793B2 (en) Construction method of stepped floor
JPH02157307A (en) Erection for pc snow shelter