JPS6311735A - Housing structure of factory building - Google Patents

Housing structure of factory building

Info

Publication number
JPS6311735A
JPS6311735A JP61151548A JP15154886A JPS6311735A JP S6311735 A JPS6311735 A JP S6311735A JP 61151548 A JP61151548 A JP 61151548A JP 15154886 A JP15154886 A JP 15154886A JP S6311735 A JPS6311735 A JP S6311735A
Authority
JP
Japan
Prior art keywords
floor
lattice
section
large space
frame structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP61151548A
Other languages
Japanese (ja)
Other versions
JPH0481012B2 (en
Inventor
一宏 畠山
文久 市川
豊 藤田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP61151548A priority Critical patent/JPS6311735A/en
Publication of JPS6311735A publication Critical patent/JPS6311735A/en
Publication of JPH0481012B2 publication Critical patent/JPH0481012B2/ja
Granted legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 産業上の利用分野゛ 本発明は鉄筋コンクリート造の工場用建染物の架構構造
に関し、とくに半導体製品のような精密機器の生産用工
場などで、柱間隔が大ぎく、架構物全体に振動特性上の
要求がきびしく、さらに室内の清澄度を必要とするよう
な建染物の架構構造に関するものである。
[Detailed Description of the Invention] Industrial Field of Application The present invention relates to the frame structure of a reinforced concrete factory building, particularly in a factory for the production of precision equipment such as semiconductor products. This relates to the structural structure of buildings that have strict requirements regarding the vibration characteristics of the whole object and also require a high level of clarity within the room.

従来の技術 高集禮度のIC製品の生産のような電子工業の発展に伴
い、建設産業自体も精密工業に属するようになって来て
おり、生産機械を配する生産室では微振動対策と室内空
気の清澄度が要求されるようになっている。従来の工場
では多層階とする場合でも生産室は1階に配することが
行われ、その撮動対策は大地の地盤上に強固な床を設け
、または建造物と絶縁した機械台を設けているのが実状
であり、さらに杭地業を加えることによって比較的簡易
に解決されていた。
With the development of the electronics industry, such as the production of IC products with a high level of conventional technology, the construction industry itself has come to belong to the precision industry, and the production rooms where production machines are installed are equipped with measures against micro-vibration and indoor air quality. Clarity is now required. In conventional factories, the production room is placed on the first floor even when the factory is multi-story, and the filming measures are to install a strong floor on the ground or to install a machine stand insulated from the building. The reality is that this problem can be solved relatively easily by adding piles.

また室内空気に関してはいわゆるクリーン・ルーム用の
設備に次第にグレードの向上がはかられ、気密を保持し
た室内に塵埃粒子の少ない清澄空気を供給しており、作
業床面ことと通路部分はグレーチング張りにして沈降塵
埃を吹き抜けさせるようにしている。従って清澄空気の
供給と排出のためにダクト配設のための空間を必要とし
ひいては工場床面精の増大罠も影響していた。
Regarding indoor air, so-called clean room equipment has been gradually upgraded to supply clear air with less dust particles into airtight rooms, and work floors and passageways are lined with gratings. This is done so that the settled dust can be blown out. Therefore, a space was required to install ducts for supplying and discharging clean air, which in turn was affected by the increased burden of factory floor cleaning.

発明が解決しようとする間萌点 電子工業用の生産工場は、IC製品の集積度の上昇のよ
うに技術革新が進み、生産機械そのものがそのような部
品を組込んで自動化され、生産品は大量生産の対象とな
る。従って、土地の有効利用の観点から、生産室を上層
にも有する立体的な多層工場が要求され、かつ下階にも
生産域を有することから、柱間隔もますます拡げたい要
求が伴う。
Manufacturing factories for the electronic industry, which the invention seeks to solve, are experiencing technological innovations such as the rise in the degree of integration of IC products, and the production machines themselves are automated by incorporating such parts, and the products are becoming more and more Subject to mass production. Therefore, from the point of view of effective land use, a three-dimensional multi-story factory with a production room on the upper floor is required, and since there is also a production area on the lower floor, there is a demand for increasingly wider column spacing.

従来の工場では、架構上の制約なしでは柱スノクンが6
mないし10mまでのものが多く、ことに精密生産のた
めの上階の生産室に対してさらに微振動対策を必要とす
る。
In a conventional factory, the pillar Sunokun would be 6 without structural constraints.
Many of them are up to 10m to 10m in length, and require further countermeasures against slight vibrations, especially in the production room on the upper floor for precision production.

また、工場内の環境条件としてクリーン・ルームのクリ
ーン度も高められ、グレーチング張りの床構造を採用す
るとき、この部分の床の剛性が下がり、ひいては機器を
設置する隣接の床の剛性が低下するばかりでなく、床全
体の質量が減少することになって生産性の精密化と相反
する条件におかれるから、微振動対策はまことに苛酷な
課題である。
In addition, the cleanliness of the clean room is also increased as an environmental condition in the factory, and when a grating floor structure is adopted, the rigidity of the floor in this area decreases, which in turn decreases the rigidity of the adjacent floor where equipment is installed. Not only that, but the mass of the entire floor is reduced, creating conditions that conflict with precision productivity, making countermeasures for microvibrations a truly severe challenge.

一方、柱の存在は機器の配置上ことに工場計画の変更に
伴う後日の変化への対応に大きな障害となり、制約が大
きい。
On the other hand, the presence of pillars poses a major constraint, especially in terms of equipment placement, and in dealing with later changes due to changes in the factory plan.

本発明はとくに精密機器工場を対象として、通常の耐愛
性のほかに架構構造に与えられる微振動対策を主眼とし
て開発され併せてクリーン・ルームの特性にも適合させ
るようにしたものである。この発明はまず柱間隔を従来
概念の数倍となるように定めて生産室の機器配置の自由
度を高め、このような大空間の区画を広大な工場内に連
設するときにその中間に通路区画を設け、これらに隣接
して機械室、電気室等を兼ねる設備用区画を配置し、こ
のような区分構成を多層階に積層した建築物とすること
を要旨としている。そして、このために大空間区画の床
は一体の格子状梁を組んでこれにプレストレスを適用し
て大スノやンの剛性低下に対応させるとともに、床全体
を二重床構成にしてクリーン・ルームの要件に適合させ
、通路区画は単なる接続構造、設備用区画は通常の鉄筋
コンクリート軸組造としたことを特徴としている。そし
てこの発明はとくに電子工業の今後の急速な進展に対し
てそのニーズを先取りした工場建築物の架構構造を提供
する。
The present invention was developed especially for precision equipment factories, with a focus on microvibration countermeasures given to the frame structure in addition to normal wear resistance, and was also adapted to the characteristics of clean rooms. This invention first sets the column spacing to be several times larger than the conventional concept, increasing the degree of freedom in arranging equipment in the production room. The main idea is to provide a passageway section and place adjacent to it an equipment section that also serves as a mechanical room, an electrical room, etc., and to create a building with such a sectioned structure stacked on multiple floors. For this purpose, the floor of the large space section is made of integrated lattice beams and pre-stressed to cope with the decrease in rigidity of the large snow shed, and the entire floor is constructed with double floors to ensure a clean and comfortable environment. In order to suit the requirements of the room, the passage section is a simple connection structure, and the equipment section is a normal reinforced concrete frame structure. This invention particularly provides a frame structure for factory buildings that anticipates the needs of future rapid progress in the electronics industry.

実施例 本発明の架構構造を適用した実施例を図面に基づいて説
明する。第1図は精密機器の生産工場の平面図を代表的
な一部で示す概略図であり、第2図は第1図のII −
n 憩に沿う断面図である。
Embodiment An embodiment to which the frame structure of the present invention is applied will be described based on the drawings. Fig. 1 is a schematic diagram showing a representative part of the plan view of a precision equipment production factory, and Fig. 2 is a schematic diagram showing a representative part of the plan view of a precision equipment production factory.
It is a sectional view along the n break.

この工場建築物は鉄筋コンクリート造であって、図にお
いて、1は等間隔に配置された柱であり、2はそれらを
一連に連続させる壁体で各階に梁を内蔵して耐力壁を形
成している。3は上部の屋根である。対向する柱1.1
の間には梁が架けわたされて一体の格子梁4を形成し、
格子梁4は柱間隔の長さを1辺とする単位の格子5を有
し、この例では柱間隔5〜6mとした6スi’?ンによ
って、4面の壁体2に囲まれた1辺30〜36mの大空
間を形成している。このような規模の工場にあっては中
央に中柱6を有していることが望ましい。
This factory building is constructed of reinforced concrete, and in the diagram, 1 is columns arranged at equal intervals, and 2 is a wall that connects them in a series, with beams built into each floor to form a load-bearing wall. There is. 3 is the upper roof. Opposing pillars 1.1
A beam is spanned between them to form an integrated lattice beam 4,
The lattice beam 4 has a unit lattice 5 with the length of the column spacing as one side, and in this example, the column spacing is 5 to 6 m. A large space of 30 to 36 m on a side is formed surrounded by walls 2 on four sides. In a factory of such a scale, it is desirable to have a central pillar 6 in the center.

上記のような大空間に区画された区画10には工場計画
に従って生産機械が配備され生産室とたつ、ている。隣
位の大空間区画10との間は通路区画20によって接続
されており、通路区画20はまた生産室のための機械、
電気などの設備を有する設備用区画30と大空間区画1
0とをも連接させて−・る。
In the section 10, which is divided into a large space as described above, production machines are arranged according to the factory plan and serve as a production room. The adjacent large space section 10 is connected by a passage section 20, which also contains machines for the production room,
Facility section 30 and large space section 1 with equipment such as electricity
Also concatenate it with 0.

次に格子梁4が構成する大空間区画10の各階の床7に
ついて説明する。床7は格子梁4の面に構成される構造
床8とその上方で作業面となる二重床9とから成立って
いる。
Next, the floors 7 of each floor of the large space section 10 constituted by the lattice beams 4 will be explained. The floor 7 consists of a structural floor 8 formed on the surface of the lattice beam 4 and a double floor 9 above which serves as a work surface.

まず構造床8は第3図で示すように、格子梁4が柱1に
接続する外周の格子5の上面にX状の水平筋違81を有
し℃いる。個々の格子5にあっては第4図(1)に示す
ような軽量コンクリートのプレキャスト板(20版)8
2を載置してある。83は周枠であり、84は中央リブ
であって、20版82は格子梁4にボルト締めで固着す
るのが好ましい。
First, as shown in FIG. 3, the structural floor 8 has X-shaped horizontal braces 81 on the upper surface of the outer periphery of the lattice 5 where the lattice beams 4 connect to the columns 1. For each grid 5, a lightweight concrete precast board (20th edition) 8 as shown in Figure 4 (1) is used.
2 is listed. 83 is a peripheral frame, 84 is a central rib, and the 20th plate 82 is preferably fixed to the lattice beam 4 by bolting.

第4図(2)には二重床9を示す。二重床9は格子梁4
の上面に立設した束柱91によって周枠 、92を支持
し、周枠92にはpc造小梁93を架設してその上面に
グレーチング・パネル94を敷設する。二重床9の構造
体である束柱91と周枠92:ま鉄筋コンクリート造で
あり、格子梁4とともにフイーレンデイール梁の構成と
するとき、構造床8と2層一体の剛性評価が可能である
A double bed 9 is shown in FIG. 4(2). Double floor 9 is lattice beam 4
A peripheral frame 92 is supported by bundle pillars 91 erected on the upper surface, a small PC beam 93 is erected on the peripheral frame 92, and a grating panel 94 is laid on the upper surface. The bundled columns 91 and surrounding frame 92, which are the structure of the double floor 9, are made of reinforced concrete, and when they are configured as Vierendeel beams with the lattice beams 4, it is possible to evaluate the rigidity of the structural floor 8 and the two layers. be.

構造床8と二重床9の両者の空間は大空間区画10月に
供給される清澄空気のためのダクト配管に用いられ、排
気は床7の上面のグレーチング94を通じて行われる。
The spaces of both the structural floor 8 and the double floor 9 are used for duct piping for the clean air supplied to the large space compartment, and the exhaust air is carried out through the grating 94 on the upper surface of the floor 7.

地上階の床は71と表示してある。これは上記床と同様
としてもよいが、構造床8は地下ダクト構造に変更され
る。
The ground floor floor is marked as 71. This may be similar to the floor described above, but the structural floor 8 is changed to an underground duct structure.

中柱6は格子梁4の中央の交点を支持するように配置さ
れる。この中柱6は第5図に示すようにできるだけ水平
断面を小さくするように鋼管内面にコンクリートとの付
着遮断層すを設けて充填コンクリートと鋼管との付着を
なくしたアンボンド充填鋼管コンクリート造とする。6
1は鋼管であり、格子梁4の交点の水平ノ・ンチ部41
による厚肉部において格子梁4を支持して(・る。62
は柱内のたての鉄筋63はそのスパイラル・フープであ
って、このフープは鉄筋62外周に螺旋方向に取付け、
かご形に組んだものを鋼管61内に挿入し、高強度コン
クリート64を充填して中柱6を形成する。中柱の外径
は70cm前後とする。
The middle pillar 6 is arranged to support the central intersection of the lattice beams 4. As shown in Fig. 5, the middle pillar 6 is made of unbonded filled steel pipe concrete, with a concrete adhesion blocking layer provided on the inner surface of the steel pipe to prevent adhesion between the filled concrete and the steel pipe, so as to minimize the horizontal cross section as much as possible. . 6
1 is a steel pipe, with horizontal notches 41 at the intersections of the lattice beams 4;
The lattice beam 4 is supported in the thick part by (.62
The vertical reinforcing bar 63 inside the column is its spiral hoop, and this hoop is attached to the outer circumference of the reinforcing bar 62 in a spiral direction,
The cage-shaped assembly is inserted into a steel pipe 61 and filled with high-strength concrete 64 to form a central column 6. The outer diameter of the middle pillar is approximately 70cm.

中柱6と格子梁4との接続部65は純然と鉄筋コンクリ
ートであり、鉄筋62は上下に貫通して上方に延長され
ている。フープ筋63もそれに従って取付けられている
が、接合部の上下にわたってさらに二重フープ筋66を
加えて逆回旋方向に巻回してあり、この部分でむまスノ
クイラルのピッチを短縮させて鋼管61におき換えであ
る。そして格子梁4の上下面での鋼管61の接合は緩衝
材を介して水平間隙を残して結合する。これによって格
子梁4の荷重はコンクリート64のみによって伝達され
、その意味では鋼管61には適宜に水平スリットを設け
てもよい。
The connecting portion 65 between the middle pillar 6 and the lattice beam 4 is made of purely reinforced concrete, and the reinforcing bars 62 penetrate vertically and extend upward. The hoop reinforcement 63 is also attached in accordance with this, but a double hoop reinforcement 66 is further added above and below the joint and wound in the opposite rotational direction, and the pitch of the Muma-Snoquiral is shortened in this part so that it can be attached to the steel pipe 61. It is a replacement. The steel pipes 61 are joined on the upper and lower surfaces of the lattice beams 4 through cushioning materials, leaving horizontal gaps. As a result, the load of the lattice beam 4 is transmitted only by the concrete 64, and in this sense, horizontal slits may be provided in the steel pipe 61 as appropriate.

通路区画20は二重床9の床面7に上面を有する鉄筋コ
ンクリートスラブからなり、隣り合う大空間区画10.
10及び大空間区画10と設備用区画30とを床版のみ
によって接続している。
The passageway section 20 consists of a reinforced concrete slab having an upper surface on the floor surface 7 of the double floor 9, and is connected to the adjacent large space section 10.
10 and the large space section 10 and the equipment section 30 are connected only by a floor slab.

最後に設備用区画30は通常の鉄筋コンクリート造の柱
31、梁32によってラーメン架構を構成する部分であ
って特記する事項はないが、前記した大空間区画10な
らびに通路区画20に対してずつと剛性が高い。そして
その階高は通路区画20と同一とする。
Finally, the equipment section 30 is a part that constitutes a rigid frame structure with ordinary reinforced concrete columns 31 and beams 32, and there is nothing special to note, but it has a higher rigidity than the large space section 10 and passage section 20 described above. is high. The floor height thereof is assumed to be the same as that of the aisle section 20.

作用 本発明の作用を実施例の工程にもとづ℃・て説明する。action The effect of the present invention will be explained in terms of degrees Celsius based on the steps of Examples.

大空間区画10は大スパンの生産室を構成する部分で1
区画についてはまず柱1と壁体2とを外周に構築する。
The large space section 10 is a part that constitutes a large span production room.
Regarding the division, first, pillars 1 and walls 2 are constructed around the outer periphery.

次に格子梁4を構築するために、単位の格子5ごとに統
一規格の型枠を組立て、それらを各交点ごとに仮設支柱
で支持するように連接し、鉄筋とプレストレス用のレー
スを先組みして配置したのち、コンクリートを打設する
。コンクリートの硬化を待って、格子94にプレストレ
スを導入する。このプレストレスは対向する柱1.1の
外面から導入し、有効緊張力も大空間区画内に格子状に
導入され。
Next, in order to construct the lattice beams 4, formwork of uniform standards is assembled for each unit lattice 5, and they are connected so as to be supported by temporary supports at each intersection, and reinforcing bars and prestressing races are placed first. After assembling and placing, concrete is poured. After waiting for the concrete to harden, prestress is introduced into the grid 94. This prestress is introduced from the outer surface of the opposing column 1.1, and the effective tension is also introduced in the form of a grid within the large space section.

格子梁4はあたかも版体のように応力を生じて設定され
た犬ス・ぐンに適合するようになる。
The lattice beam 4 generates stress as if it were a plate and conforms to the set dog.

次には格子梁4の外周格子に筋違81を入れpc版82
を載せ、構造床8を構築する。ついで構造床8の上面に
外部から仮設の簡易移動装置を配備し、これを使用しな
がら、構造床8上で二重床9を施工する。二重床9は格
子梁4と同様の周枠92を格子状に有し、束柱91とと
もに柱1.1のス・やン間にわたってフイーレンデイー
ル架、t?の剛な梁体を形成する。そして周枠92を4
周とする単位の格子間にpc造の小梁93を架けわたし
、グレーチング・パネル94を敷設して二重床9が完成
する。もちろん、生産用の機誠またはその機械台等の配
置に従っては該当する二重床の単位格子面は開口として
残される。また、構造床8の20版82をおかず、格子
梁4の下面鉄筋コンクリート・スラブとすることも可能
である。
Next, add braces 81 to the outer lattice of the lattice beam 4 and PC version 82
, and construct the structural floor 8. Next, a temporary simple moving device is placed on the upper surface of the structural floor 8 from the outside, and the double floor 9 is constructed on the structural floor 8 while using this. The double floor 9 has a peripheral frame 92 similar to the lattice beam 4 in a lattice shape, and together with the bundle columns 91, a Vierendeel frame, t? form a rigid beam body. And the surrounding frame 92 is 4
The double floor 9 is completed by spanning the small beams 93 made of PC between the lattice units of the circumference and laying the grating panels 94. Of course, depending on the layout of the production machine or its machine stand, the corresponding unit grid surface of the double floor is left as an opening. It is also possible to replace the 20th plate 82 of the structural floor 8 with a reinforced concrete slab on the lower surface of the lattice beam 4.

大空間区画10の架構は上記によって完結し、全体の耐
震設計は、格子梁4の水平力がこの酬な構面を介して区
画ごとに周囲の耐力壁(柱1+壁体2)で支持されろ。
The structure of the large space section 10 is completed as described above, and the overall seismic design is such that the horizontal force of the lattice beams 4 is supported by the surrounding load-bearing walls (column 1 + wall 2) for each section via this complementary structure. reactor.

このことは、階高が増大しても物質量の増分があるだけ
であって、水平力の処理に際して柱、格子梁には負担が
増加せず、鉛直荷重のみで設計されることを意味する。
This means that even if the floor height increases, there is only an increase in the amount of material, and there is no increase in the burden on columns and lattice beams when handling horizontal forces, and the design is designed with only vertical loads. .

中央の中柱6の採用も、大スパンの格子梁4の鉛直荷重
への対処手段である。この中柱6の作用は鉛直軸力のコ
ンクリート特性による支持にある。中柱6は中心部の鉄
筋コンクリート64つV格子梁4のコンクリート(また
は地表では基礎コンクリート)に接続し、鉛直力を伝え
る。従って前記したような構成に従って、鋼管61は圧
縮材としては機能せず、内部コンクリート64の套管と
して「だが」の機能のみを負担し、その内面と内部コン
クリート外面との間には相互移動が許されており、コン
クリート自体は高圧縮強度を有していて、このような鋼
管コンクリートは「スーパーコンクリート」と呼称され
ている。なお、この詳細は本出願人の先の出jJにかか
る特願昭60−42979号の明細書に開示されている
。従って、格子梁4の上下に中柱が接続されるときには
梁断面部分内には鋼管61を有していないから、この部
分には十分鉄筋を配置して円滑な力の伝達をはかつてい
る。
The adoption of the central column 6 is also a means of coping with the vertical load of the large-span lattice beam 4. The function of this center column 6 is to support the vertical axial force due to concrete characteristics. The middle pillar 6 is connected to the concrete (or foundation concrete at the ground surface) of the 64 reinforced concrete V-lattice beams 4 in the center, and transmits vertical force. Therefore, according to the above-mentioned configuration, the steel pipe 61 does not function as a compression material, but only acts as a jacket for the internal concrete 64, and there is no mutual movement between its inner surface and the outer surface of the internal concrete. The concrete itself has a high compressive strength, and such steel pipe concrete is called "super concrete". The details are disclosed in the specification of Japanese Patent Application No. 60-42979 filed by the present applicant. Therefore, when the middle columns are connected above and below the lattice beam 4, there is no steel pipe 61 in the cross section of the beam, so sufficient reinforcing bars are placed in this section to ensure smooth force transmission.

通路区画200床面は二重床9と上面を揃えた鉄筋コン
クリート造となり、通常は幅3m内外であって、大空間
区画10の壁体2に支持させろ。従って、剛性が小さく
、他の区画10.30との間の相互の振動の伝播を小さ
くしている。また、この部分の床版には積極的に膨張継
手を設けて、他の区画ことに区画30と構造的に絶縁さ
せるようにしてもよい。
The floor of the passage section 200 is made of reinforced concrete with the upper surface aligned with the double floor 9, and is usually about 3 meters wide and supported by the wall 2 of the large space section 10. Therefore, the rigidity is small, and the mutual vibration propagation between the partitions 10.30 and other partitions 10.30 is reduced. Furthermore, an expansion joint may be actively provided in the floor slab of this portion to provide structural insulation from the other sections and the section 30.

設備用区画30は通常の鉄筋コンクリート造であるから
施工に関する特記事項はない。装備される機械類には防
振材を採用して設置するようにする。
Since the equipment section 30 is constructed of ordinary reinforced concrete, there are no special notes regarding construction. Anti-vibration materials should be used and installed in the machinery to be equipped.

発明の効果 本発明の特記すべき特徴は生産室を1階または上階のい
ずれにも設定することができ、かつその犬ス・センの構
成によって大空間区画を形成していることである。従っ
て生産工場として機械類の配置に柱の制約がなく、格子
状に形成した梁による支持も単位の格子ごとに自由度が
大きい。さら九、小単位の格子によって等方向に区画さ
れているから工場計画の変化に対して追随性が大きく、
フレキシブルな大空間を望むニーズにこたえることがで
きる。
Effects of the Invention A particularly noteworthy feature of the present invention is that the production room can be located either on the first floor or on the upper floor, and its structure forms a large spatial division. Therefore, as a production factory, there are no pillar restrictions on the arrangement of machinery, and support by beams formed in a lattice has a large degree of freedom for each unit lattice. Furthermore, because it is partitioned in equal directions by a grid of small units, it is highly responsive to changes in the factory plan.
It can meet the needs of large, flexible spaces.

このような効果は主としてプレストレスト・コンクリー
ト造とした格子梁によって剛性の高い架構構造を得たこ
とによるものであり、あわせて二重床の構成によってク
リーン・ルームの条件にも適合させ、機器の振動に対す
る絶縁手段にも自由度を与えている。
These effects are mainly due to the high rigidity of the frame structure made of lattice beams made of prestressed concrete, and the double floor structure also meets clean room conditions and reduces equipment vibration. It also gives flexibility in the insulation means.

また、格子梁を規則正しい単位格子を基準として構成し
てあるから、仮設用材の転用が可能でコストダウンがは
かられ、格子交点の支持の間に側面型枠の早期脱型が可
能であって、その転用によって工期の短縮が可能である
。部材のコンクリートにあっても小型のプレキャスト部
材を使用することにより、ここでも工期短縮とコストダ
ウンが達成できる。
In addition, since the lattice beams are constructed based on regular unit grids, materials for temporary construction can be reused, reducing costs, and the side formwork can be demolded quickly while supporting the lattice intersections. , it is possible to shorten the construction period by repurposing it. By using small precast members for the concrete components, construction time and costs can be shortened here as well.

プレストレスの導入は明らかに1工程の一工種を増加さ
せているが、作業は規格化されたものの繰返しであって
効率がよく、大ス・ぐンの格子梁を得る効果の大きさに
比べて決して損失とはならない。
The introduction of prestressing clearly increases the number of workpieces in each process, but the work is standardized and repetitive, so it is efficient and compared to the magnitude of the effect of obtaining large lattice beams. It is never a loss.

【図面の簡単な説明】[Brief explanation of drawings]

図面は本発明の実施例を示し、第1図は生産工場の平面
図、第2図は第1図の■−■線に沿う断面図、第3図は
水平筋違の説明図、第4図は床の要部の平面図であって
(1)図は構造床、(2)図は二重床を示す。第5図は
中柱の説明図である。 1 柱、     2 壁体、 3 屋根、     4 格子梁、 5 単位の格子、 6 中柱、 7 各階床、   8 構造床、
The drawings show an embodiment of the present invention, and FIG. 1 is a plan view of a production factory, FIG. 2 is a sectional view taken along the line ■-■ in FIG. 1, FIG. The figures are plan views of the main parts of the floor, with (1) the structural floor and (2) the double floor. FIG. 5 is an explanatory diagram of the middle pillar. 1 Column, 2 Wall, 3 Roof, 4 Lattice beam, 5 Unit lattice, 6 Middle column, 7 Each floor, 8 Structural floor,

Claims (5)

【特許請求の範囲】[Claims] (1)精密機器などの生産室となる大空間区画と、それ
らの区画を連接する通路区画と、生産室に隣接した機械
動力の設備用区画とからなり、全体に多層構造とした建
築物において、大空間区画は外周に柱、壁体を有して耐
力壁を構成し、それに支持される床は、柱間隔を単位と
する大きさの格子をもつ格子梁をプレストレスト・鉄筋
コンクリート構造で構成し、その上面に構造床と二重床
を構成してあり、設備用区画は鉄筋コンクリート造の剛
性の架構構造であつて、これらの区画は通路区画で接続
されていることを特徴とする工場建築物の架構構造。
(1) A building with a multi-layer structure as a whole, consisting of a large space section that serves as a production room for precision equipment, a passage section connecting these sections, and a section for mechanically powered equipment adjacent to the production room. The large space section has columns and walls on the outer periphery to constitute a load-bearing wall, and the floor supported by it consists of a prestressed reinforced concrete structure consisting of lattice beams with a lattice size with the column spacing as a unit. A factory building comprising a structural floor and a double floor on its upper surface, the equipment compartment having a rigid frame structure made of reinforced concrete, and these compartments being connected by a passage compartment. frame structure.
(2)大空間区画の構造床は、単位格子間にプレキャス
ト・コンクリート版を架設してあり、二重床はプレキヤ
スト・コンクリート造の小梁を介してグレーチング・パ
ネルを敷設し、束柱を含むフイーレンデイール架構によ
つて格子梁上に支持してある特許請求の範囲第1項に記
載の架構構造。
(2) For the structural floor of the large space section, precast concrete slabs are constructed between unit grids, and for the double floor, grating panels are laid through small beams made of precast concrete, and bundled columns are installed. The frame structure according to claim 1, which is supported on a lattice beam by a Vierendeel frame.
(3)格子梁は、外周部分の単位格子面に水平筋違を有
している特許請求の範囲第1項または第2項に記載の架
構構造。
(3) The frame structure according to claim 1 or 2, wherein the lattice beam has horizontal braces on the unit lattice plane of the outer peripheral portion.
(4)通路区画は床版のみで隣接する大空間区画または
大空間区画と設備用空間とを接続している特許請求の範
囲第1項に記載の架構構造。
(4) The frame structure according to claim 1, wherein the passage section connects the adjacent large space section or the large space section and the equipment space only by a floor slab.
(5)大空間区画は中央に鋼管コンクリート造の中柱を
有し、格子梁の交点において軸方向荷重を支持している
特許請求の範囲第1項ないし第4項のいずれか1項に記
載の架構構造。
(5) The large space section has a central column made of steel pipes and concrete in the center, and supports axial loads at the intersections of the lattice beams, as set forth in any one of claims 1 to 4. frame structure.
JP61151548A 1986-06-30 1986-06-30 Housing structure of factory building Granted JPS6311735A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61151548A JPS6311735A (en) 1986-06-30 1986-06-30 Housing structure of factory building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61151548A JPS6311735A (en) 1986-06-30 1986-06-30 Housing structure of factory building

Publications (2)

Publication Number Publication Date
JPS6311735A true JPS6311735A (en) 1988-01-19
JPH0481012B2 JPH0481012B2 (en) 1992-12-22

Family

ID=15520923

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61151548A Granted JPS6311735A (en) 1986-06-30 1986-06-30 Housing structure of factory building

Country Status (1)

Country Link
JP (1) JPS6311735A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0335964A (en) * 1989-06-30 1991-02-15 Ohbayashi Corp Solid automation factory
JPH03115664A (en) * 1989-09-28 1991-05-16 Ohbayashi Corp Three-dimensional factory

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8629360B2 (en) * 2012-04-30 2014-01-14 Raytheon Company RF micro-electro-mechanical system (MEMS) capacitive switch

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0335964A (en) * 1989-06-30 1991-02-15 Ohbayashi Corp Solid automation factory
JPH03115664A (en) * 1989-09-28 1991-05-16 Ohbayashi Corp Three-dimensional factory

Also Published As

Publication number Publication date
JPH0481012B2 (en) 1992-12-22

Similar Documents

Publication Publication Date Title
JP5523179B2 (en) Building construction method and room module
JP4316161B2 (en) Power plant construction method
JPS6311735A (en) Housing structure of factory building
US6745533B2 (en) Building and construction method therefor
CN111364642A (en) Assembled energy-consumption shear wall system and construction method thereof
JP2866993B2 (en) Prefabricated building
JP3831545B2 (en) Unit building
KR101266215B1 (en) Improved seismic performance of Staggered wall system with central hall
CN212153819U (en) Assembled power consumption shear force wall system
JP2000328652A (en) Multi-story building
JP7316910B2 (en) building
JP3779797B2 (en) Seismic isolation system for steel frame ramen construction
JP2021031930A (en) Method for designing foundation structure of detached building
JP5375174B2 (en) Construction method of column beam frame
JP4193708B2 (en) Steel concrete composite floor
JP7120700B2 (en) Structure
JPH0827937A (en) Flat slab-column joint part in reinforced concrete structure
JP3207276B2 (en) How to build a unit building
JPH0524755Y2 (en)
KR100228016B1 (en) Framed structure having ductility and method for manufacturing the same
JP2023019882A (en) Steel skelton structure, and method of mixing steel pipe column into steel rigid-frame skelton
KR20230142045A (en) Block module and block modular building construction method
JPS63247439A (en) Construction of ramen structure body
JP2024009003A (en) steel pipe concrete column
JP2020505540A (en) Method of manufacturing a beamless composite skeleton of a building having a dynamic foundation