JPS6282123A - Protecting construction process for concrete on face of slope or the like - Google Patents

Protecting construction process for concrete on face of slope or the like

Info

Publication number
JPS6282123A
JPS6282123A JP22162985A JP22162985A JPS6282123A JP S6282123 A JPS6282123 A JP S6282123A JP 22162985 A JP22162985 A JP 22162985A JP 22162985 A JP22162985 A JP 22162985A JP S6282123 A JPS6282123 A JP S6282123A
Authority
JP
Japan
Prior art keywords
concrete
formwork
unit
length
construction surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP22162985A
Other languages
Japanese (ja)
Other versions
JPH0324929B2 (en
Inventor
Tomoji Umeki
梅基 友治
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SENI DOBOKU KAIHATSU KK
Original Assignee
SENI DOBOKU KAIHATSU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SENI DOBOKU KAIHATSU KK filed Critical SENI DOBOKU KAIHATSU KK
Priority to JP22162985A priority Critical patent/JPS6282123A/en
Publication of JPS6282123A publication Critical patent/JPS6282123A/en
Publication of JPH0324929B2 publication Critical patent/JPH0324929B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Revetment (AREA)

Abstract

PURPOSE:To form a concrete protection layer at a uniform precision, by filling up molds with ready mixed concrete while sending out the molds in sequence, after the unit molds made of a fabric which is water-permeable and cement- grain-impermeable are arranged on the surface for the execution of work. CONSTITUTION:Water-permeable and cement-grain-impermeable textiles 1, 2 are connected to each other on the periphery 3 and at connecting points 4, 5, and a mold C made of fabric is formed. Then, the unit mold 6 of the mold C is taken up, and is drawn out on the surface 7 for the execution of work by traction devices 11, 12 for sending out the mold freely, to be arranged. After that, the traction devices 11, 12 are slightly moved back in the sending-out direction, and a clearance is allowed by the unit mold 6, and the mold 6 is filled up with ready mixed concrete through an opening section 18. Besides, the molds are sent out by the traction devices 11, 12, and are repeated to be filled up with ready mixed concrete through an opening section 19 and after that, through an opening section 20, to form a protection layer 21.

Description

【発明の詳細な説明】 産業上の利用分野 本発明は、布帛製型枠を用いて法面、河川床等にコンク
リート保護層を構成するコンクリート保護工法の改良に
関するものである。
DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application The present invention relates to an improvement in a concrete protection method for constructing a concrete protection layer on slopes, riverbeds, etc. using fabric forms.

従来の技術 法面等のコンクリート保護工に使用される布帛製型枠と
しては、既に特公昭5 B−45536号公報、特公昭
58−47521号公報または特公昭59−42145
号公報等に示されるもの等が公知となっているが、これ
等の布帛製型枠は、生コンクリート充填前には扁平であ
るものの、生コンクリートを充填されると、第5図に示
されるように、充填されたコンクリートAのために、上
下方向に嵩のある膨隆体Bとなる。
Conventional technology Fabric formwork used for concrete protection work on slopes, etc. has already been disclosed in Japanese Patent Publication No. 5 B-45536, Japanese Patent Publication No. 58-47521, or Japanese Patent Publication No. 59-42145.
The molds shown in the above publications are publicly known, but these fabric forms are flat before being filled with fresh concrete, but when filled with fresh concrete, they become as shown in Figure 5. Because of the filled concrete A, the bulge B becomes bulky in the vertical direction.

このため、布帛製型枠Cは、幅方向D、長さ方向Eにお
いて、約20%乃至30%の寸法が収縮するものである
Therefore, the fabric formwork C shrinks in size by about 20% to 30% in the width direction D and the length direction E.

上述の収縮のうち幅方向りの収縮は隣接配置する布帛製
型枠のオーバーラツプで吸収、消去されるものの、長さ
方向Eの収縮は、予め収縮量を見込んだ長さの布帛製型
枠を施工面上に配置したうえで、生コンクリートを充填
する工法で、吸収、消去する工法が採用されている。
Of the above-mentioned shrinkage, the shrinkage in the width direction is absorbed and eliminated by the overlap of adjacent fabric forms, but the shrinkage in the length direction E is achieved by using fabric forms with a length that takes into account the amount of shrinkage in advance. This is a construction method in which the concrete is placed on the construction surface and then filled with ready-mixed concrete, which absorbs and erases it.

発明が解決しようとする問題点 上述の従来の工法では、長さに余裕を持たせて施工面上
に配置した布帛製型枠に対する生コンクリート充填時の
布帛製型枠の位置決め、張力管理等が困難であるため、
形成されるコンクリート保護層の寸法精度、形態の均−
性等を保持するための作業に熟練を要し、布帛製型枠の
張設、生コンクリートの充填に熟練作業員を要する点に
問題が存している。
Problems to be Solved by the Invention In the conventional construction method described above, it is difficult to position the fabric formwork, tension control, etc. when filling fresh concrete with respect to the fabric formwork, which is placed on the construction surface with a margin in length. Because it is difficult,
The dimensional accuracy and uniformity of the formed concrete protective layer
The problem lies in the fact that the work required to maintain its properties requires skill, and skilled workers are required to stretch the fabric formwork and fill it with ready-mixed concrete.

このため、本発明は、形成されるコンクリート保護層の
寸法精度、形態の均一性の保持が容易であシ、そのため
の布帛製型枠の張力管理。
Therefore, the present invention makes it easy to maintain the dimensional accuracy and uniformity of the form of the concrete protective layer to be formed, and to manage the tension of the fabric formwork for this purpose.

生コンクリートの充填量の管理等を容易に行ないうる布
帛製型枠を用いたコンクリート保護工法を提供すること
を目的としている。
The purpose of this invention is to provide a concrete protection method using fabric formwork that allows easy control of the amount of fresh concrete filled.

問題点を解決するだめの手段 上述の目的を達成するため、本発明では、水は透過させ
るもののセメント粒子は透過させない密度に織成されて
いる合成繊維製の上下の生地が、周縁および縦横方向に
均等間隔を存した全面多数個所で連結されて袋体をなし
ているコンクリート充填用の布帛製の単位型枠を、コン
クリート保護層を設置すべき施工面に単位型枠の幅方向
に複数枚並列配置するに当シ、単位型枠の長さを、前記
並列方向と直交する方向の施工面長さより所定長さだけ
長くしておき、少なくとも単位型枠の長さ方向のl端縁
を、巻取シ。
Means for Solving the Problems In order to achieve the above-mentioned object, in the present invention, upper and lower fabrics made of synthetic fibers are woven with a density that allows water to pass through but not cement particles. A plurality of fabric unit formworks for concrete filling, which are connected at multiple points on the entire surface at equal intervals to form a bag body, are placed in the width direction of the unit formwork on the construction surface where the concrete protection layer is to be installed. When arranging the unit forms in parallel, the length of the unit forms is made a predetermined length longer than the length of the construction surface in the direction orthogonal to the parallel direction, and at least the l edge in the length direction of the unit forms is Take-up.

繰シ出し自在の牽引装置によシ、施工面外に引き出して
該型枠を施工面に展張配置したのち、該単位型枠内へ生
コンクリートを充填しつつ、生コンクリートの充填に伴
なう単位型枠の膨隆のための長さ方向の長さ収縮量を、
牽引装置による単位型枠の前記所定長さ分の施工面への
順次繰り出しで充足しつゝ、生コンクリートの充填を継
続すると言う工法とすることにより、布帛製の単位型枠
の張カ管理、生コンクリート充填量の管理等を容易とし
、寸法精度が高く、形態の均一性の保たれたコンクリー
ト保護層を形成しうるようにしたものである。
After pulling out the formwork outside the construction surface using a freely retractable traction device and placing the formwork on the construction surface, the unit formwork is filled with ready-mixed concrete while filling with ready-mixed concrete. The length contraction amount in the longitudinal direction due to the expansion of the unit formwork is
By adopting a construction method in which filling the unit formwork with ready-mixed concrete is continued while the unit formwork is sequentially drawn out to the construction surface for the predetermined length using a traction device, the tension of the unit formwork made of fabric can be managed; This makes it easy to manage the amount of fresh concrete filled, and forms a concrete protective layer with high dimensional accuracy and uniformity of form.

作用 本発明では単位型枠の並列方向と直交する方向の施工面
の長さ如対し、生コンクリート充填に伴なう該型枠の長
さの収縮量に相当する所定長さだけ長くした単位型枠を
、施工面に配置し、少なくとも単位型枠の長さ方向の1
端を牽引装置によって牽引して施工面外へ引き出してお
き、その牽引によって施工面に張設される単位型枠に所
定の張力を付与したうえで該型枠内へ生コンクリートを
充填する。
Function In the present invention, the unit form is lengthened by a predetermined length corresponding to the amount of shrinkage of the length of the form due to filling of fresh concrete, with respect to the length of the construction surface in the direction orthogonal to the parallel direction of the unit form. Place the frame on the construction surface, and at least 1 part in the length direction of the unit formwork
The ends are pulled out of the construction surface by a traction device, and a predetermined tension is applied to the unit formwork stretched over the construction surface by the traction, and ready-mixed concrete is filled into the formwork.

布帛製の単位型枠は、牽引によって与えられた張力に応
じて充填される生コンクリートの内圧によシ膨隆する。
The unit formwork made of fabric swells due to the internal pressure of the fresh concrete filled in response to the tension applied by traction.

この膨隆の度合は、前記張力によって、最大限度以下の
範囲で調節される。
The degree of this swelling is adjusted by the tension within a range below the maximum limit.

上述の膨隆による長さの短縮分は牽引装置による前記引
き出し分の施工面側への繰り出しによシ補足される。
The reduction in length due to the above-mentioned bulge is supplemented by the pulling out of the drawer toward the construction surface side by the traction device.

上述のように牽引装置によって長さ方向に張力の付与さ
れた状態で生コンクリートが充填され、膨隆して行くの
で、上下の生地が縦横方向に均等間隔を存して全面多数
個所で連結されている単位型枠は、その連結点が該型枠
の長さ方向に整然と並んだ状態で膨隆し、所謂筋が通っ
た形態の均一なコンクリート保護層が形成される。
As mentioned above, the fresh concrete is filled with tension in the longitudinal direction by the traction device and swells, so that the upper and lower fabrics are connected at multiple points on the entire surface with equal intervals in the vertical and horizontal directions. The unit formwork is swollen with its connecting points aligned in an orderly manner in the length direction of the formwork, forming a uniform concrete protective layer with a so-called striated form.

なお生コンクリートの充填は単位型枠の下方から順次上
方へと複数回に別けて行なわれる。
The filling of fresh concrete is carried out in multiple steps starting from the bottom of the unit formwork and working upwards.

実施例 第1図乃至第4図は実施の一例の施工状態を示しており
、第5図にも示されているように、水は透過させるもの
のセメント粒子は透過させない密度に織成されている合
成繊維製の上下の生地1.2が1周縁3および縦横方向
に均等間隔を存して全面多数個所の連結点4,5で連結
されて袋体を形成しているコンクリート充填用の布帛製
型枠Cは第1図に示されるように、一定の幅Wと一定の
長さしとよりなる単位型枠6とされ、施工面7上に、前
記幅W方向に僅かにオーバーラツプされて、施工面7の
全幅を覆いうるように並列配置される。
Embodiment Figures 1 to 4 show the construction state of an example of implementation, and as shown in Figure 5, the fabric is woven with a density that allows water to pass through but not cement particles. Made of fabric for concrete filling, in which upper and lower synthetic fiber fabrics 1.2 are connected at a peripheral edge 3 and at multiple connecting points 4, 5 on the entire surface at equal intervals in the vertical and horizontal directions to form a bag body. As shown in FIG. 1, the formwork C is a unit formwork 6 consisting of a constant width W and a constant length, and is slightly overlapped in the width W direction on the construction surface 7. They are arranged in parallel so that the entire width of the construction surface 7 can be covered.

また単位型枠6の長さしは、施工面7の長さ看より、後
述するように生コンクリートの充填による該型枠6の膨
隆に伴なう長さの収縮量に相当する所定長さMだけ長く
設定されている。
In addition, the length of the unit formwork 6 is determined from the length of the construction surface 7 to a predetermined length corresponding to the amount of shrinkage in length due to swelling of the formwork 6 due to filling with fresh concrete, as described later. It is set to be longer by M.

図示例の単位型枠6は、施工面γの上端側の1端縁8が
全幅に亘る袋部9とされ、この袋部9内にパイプ10が
挿入され、該パイプ10の両端がウィンチ、チェンブロ
ック等の牽引装置11.12のローゾ、テエン等の索条
13,14図示例では施工面7の下端において単位型枠
6の下端縁15が、押え板16.アンカー17で施工面
7側に固定され、施工面7に展張された単位型枠6の1
端縁8は、前記牽引装置11゜12によって、前記収縮
量に相当する所定長さMだけ、施工面7外に引き出され
、施工面70単位型枠6に所定の張力が付与されている
In the unit formwork 6 of the illustrated example, one end edge 8 on the upper end side of the construction surface γ is a bag portion 9 spanning the entire width, a pipe 10 is inserted into the bag portion 9, and both ends of the pipe 10 are attached to a winch. In the illustrated example, the lower end edge 15 of the unit formwork 6 is attached to the lower end of the construction surface 7 at the lower end of the construction surface 7. 1 of the unit formwork 6 fixed to the construction surface 7 side with the anchor 17 and stretched on the construction surface 7
The edge 8 is pulled out of the construction surface 7 by a predetermined length M corresponding to the amount of contraction by the pulling devices 11 and 12, and a predetermined tension is applied to the construction surface 70 unit formwork 6.

また単位型枠6にはその長さ方向1幅方向の複数個所に
、生コンクリートの充填用の開口部18.19.20が
開設されているが、これ等の開口部は、生コンクリート
の充填後に当て布の縫着等の適宜手段で閉塞されるもの
である。
In addition, the unit formwork 6 has openings 18, 19, and 20 for filling with fresh concrete at multiple locations in the length direction and width direction; It is then closed by an appropriate means such as sewing a patch.

第1図、第2図は、上述した如く施工面7に単位型枠6
が展張され、未だ生コンクリートが充填されない状態を
示している。
1 and 2 show unit formwork 6 on construction surface 7 as described above.
It shows a state in which the concrete has been expanded and has not yet been filled with fresh concrete.

第1図、第2図に示される状態から、牽引装置11.1
2を繰り出し方向に僅かに戻し、単位型枠6に前述の所
定長さMのl/3程度のゆとりを持たせたうえで開口部
18から生コンクリートを充填すると、単位型枠6を形
成している上下の生地1.2は、施工面7の下方部分に
おいて、第3図に示されるよう連結点4,5間の生地が
膨隆し、コンクリート層を形成する。
From the state shown in FIGS. 1 and 2, the traction device 11.1
2 is returned slightly in the drawing direction, and the unit formwork 6 is filled with ready-mixed concrete from the opening 18 after leaving a space of about 1/3 of the predetermined length M described above, to form the unit formwork 6. As shown in FIG. 3, the upper and lower fabrics 1.2 bulge in the lower part of the construction surface 7 between the connection points 4 and 5, forming a concrete layer.

続いて再び牽引装置11.12の繰り出しによシ、単位
型枠6の残部に、当初と同一の張力を付与したうえで、
開口部19、次いで開口部20からの生コンクリートの
充填を繰り返すことにより第4図に示されるように%施
工面7の全面に亘シ、単位型枠6内に均等に生コンクリ
ートが充填された保護層21が形成される。
Then, by letting out the traction device 11, 12 again, the same tension as at the beginning was applied to the remaining part of the unit formwork 6, and then
By repeating the filling of fresh concrete from the opening 19 and then from the opening 20, the unit formwork 6 was evenly filled with fresh concrete over the entire surface of the construction surface 7, as shown in FIG. A protective layer 21 is formed.

なお、前述の開口部18,19.20は、生コンクリー
トの充填後に適宜手段で閉塞される。
Note that the aforementioned openings 18, 19, and 20 are closed by appropriate means after being filled with fresh concrete.

なお、保護層21の上端縁22は、適宜手段で施工面7
側に固定され、その後牽引装置11゜12、索条13,
14、パイプ10を撤去し、隣接配置される次位の単位
型枠について同様の生コンクリートの充填を繰り返すも
のである。
Note that the upper edge 22 of the protective layer 21 is attached to the construction surface 7 by appropriate means.
It is fixed to the side, and then the traction device 11, 12, cable 13,
14. The pipe 10 is removed and the same filling of ready-mixed concrete is repeated for the next unit formwork placed adjacent to it.

図示例では単位型枠60下端縁15を施工面7側に固定
しているが、固定するのを上端縁側とし、下端縁15側
を牽引装置によって施工面外に引き出すようにしてもよ
いし、単位型枠の上下両端縁を牽引装置によって施工面
外に引き出すようにしてもよいことは勿論である。
In the illustrated example, the lower edge 15 of the unit formwork 60 is fixed to the construction surface 7 side, but it may be fixed to the upper edge side and the lower edge 15 side pulled out of the construction surface by a traction device, Of course, both upper and lower edges of the unit formwork may be pulled out of the construction surface by a traction device.

効果 本発明は、以上説明した構成1作用のものであって、生
コンクリートの充填による膨隆に伴なって単位型枠に生
ずる長さ方向の寸法の収縮に見合う所定長さを牽引装置
によって施工面外に引き出しておき、生コンクリートの
充填による単位型枠の膨隆に必要な余裕長さのみを牽引
装置による繰シ出しによって単位型枠に付与し、生コン
クリートを充填し、膨隆させることを順次繰り返して施
工面全長に亘って保護層を形成するものであるから、生
コンクリートの充填時に単位型枠に付与すべき張力の制
御、管理を牽引装置の繰シ出し量によって容易に行なう
ことができる効果があり、その張力の大小によって生コ
ンクリートの充填量の制御、管理、従って単位型枠の膨
隆度合の制御、管理も行ないうるので、均一な寸法精度
のコンクリート保護層を容易に形成しうる効果がある。
Effects The present invention has the above-described configuration 1, in which the construction surface is moved by a traction device to a predetermined length commensurate with the shrinkage in the longitudinal dimension that occurs in the unit formwork as it bulges due to filling with fresh concrete. Pull out the unit formwork outside, add only the extra length necessary for the unit formwork to bulge by filling it with ready-mixed concrete, give it to the unit formwork by feeding it out using a traction device, fill it with ready-mixed concrete, and swell it, and repeat this process sequentially. Since a protective layer is formed over the entire length of the construction surface, the tension to be applied to the unit formwork when filling with fresh concrete can be easily controlled and managed by the amount of feed of the traction device. The filling amount of fresh concrete can be controlled and managed by the magnitude of the tension, and therefore the degree of swelling of the unit formwork can also be controlled and managed, making it possible to easily form a concrete protective layer with uniform dimensional accuracy. be.

また制御された張力の下で生コンクリートの充填を行な
うので、単位型枠の膨隆形態が等しくなり、完成された
コンクリート保護層の形態を均一ならしめうる効果もあ
る。
In addition, since the fresh concrete is filled under controlled tension, the bulges of the unit formwork become uniform, which has the effect of making the completed concrete protective layer uniform in shape.

更に、牽引装置の操作のみで単位型枠の張力を制御、管
理しうるので、熟練作業を要する部分が少なく、作業性
を向上させうる効果も有している。
Furthermore, since the tension of the unit formwork can be controlled and managed only by operating the traction device, less skilled work is required, which also has the effect of improving workability.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は、単位型枠の展張状態の実施の一例の略示平面
図、第2図は第1図に示すものの略示側面図、第3図は
生コンクリート充填初期における第2図と同様の略示側
面図、第4図は生コンクリート充填完了時における第2
図と同様の略示側面図、第5図はコンクリートの充填さ
れた布帛製型枠の一例の膨隆状態を示す切欠斜面図であ
る。 1.2:上下の生地、4.5:連結点、6:単位型枠、
7:施工面、8:l端縁、11,12:牽引装置、L二
単位型枠の長さ、2:施工面の長さ、M:所定の長さ、
W:単位型枠の幅。
Fig. 1 is a schematic plan view of an example of the unit formwork in the expanded state, Fig. 2 is a schematic side view of what is shown in Fig. 1, and Fig. 3 is similar to Fig. 2 at the initial stage of filling fresh concrete. Figure 4 is a schematic side view of the second stage at the time of completion of fresh concrete filling.
FIG. 5 is a schematic side view similar to the figure, and a cutaway slope view showing an example of a bulging state of a fabric formwork filled with concrete. 1.2: Upper and lower fabrics, 4.5: Connection points, 6: Unit formwork,
7: construction surface, 8: l edge, 11, 12: traction device, length of L two-unit formwork, 2: length of construction surface, M: predetermined length,
W: Width of unit formwork.

Claims (1)

【特許請求の範囲】[Claims] 水は透過させるもののセメント粒子は透過させない密度
に織成されている合成繊維製の上下の生地が、周縁およ
び縦横方向に均等間隔を存した全面多数個所で連結され
て袋体をなしているコンクリート充填用の布帛製の単位
型枠を、コンクリート保護層を設置すべき施工面に単位
型枠の幅方向に複数枚並列配置するに当り、単位型枠の
長さを、前記並列方向と直交する方向の施工面長さより
所定長さだけ長くしておき、少なくとも単位型枠の長さ
方向の1端縁を、巻取り、繰り出し自在の牽引装置によ
り、施工面外に引き出して該型枠を施工面に展張配置し
たのち、該単位型枠内へ生コンクリートを充填しつつ、
生コンクリートの充填に伴なう単位型枠の膨隆のための
長さ方向の長さ収縮量を、牽引装置による単位型枠の前
記所定長さ分の施工面への順次繰り出しで充足しつゝ、
生コンクリートの充填を継続する法面等におけるコンク
リート保護工法。
Concrete is a bag made by connecting upper and lower synthetic fiber fabrics, which are densely woven to allow water to pass through but do not allow cement particles to pass through, at multiple points on the entire surface at equal intervals in the periphery and in the vertical and horizontal directions. When arranging a plurality of fabric unit formwork for filling in parallel in the width direction of the unit formwork on the construction surface where the concrete protective layer is to be installed, the length of the unit formwork should be set perpendicular to the parallel direction. The formwork is constructed by making it a predetermined length longer than the length of the construction surface in the direction, and pulling out at least one edge in the length direction of the unit formwork out of the construction surface using a traction device that can be freely rolled up and fed out. After spreading and arranging it on the surface, while filling the unit formwork with fresh concrete,
The amount of contraction in length in the longitudinal direction due to expansion of the unit formwork due to filling with fresh concrete is satisfied by sequentially drawing out the predetermined length of the unit formwork onto the construction surface using a traction device. ,
Concrete protection method for slopes, etc. where fresh concrete is continuously filled.
JP22162985A 1985-10-04 1985-10-04 Protecting construction process for concrete on face of slope or the like Granted JPS6282123A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP22162985A JPS6282123A (en) 1985-10-04 1985-10-04 Protecting construction process for concrete on face of slope or the like

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP22162985A JPS6282123A (en) 1985-10-04 1985-10-04 Protecting construction process for concrete on face of slope or the like

Publications (2)

Publication Number Publication Date
JPS6282123A true JPS6282123A (en) 1987-04-15
JPH0324929B2 JPH0324929B2 (en) 1991-04-04

Family

ID=16769759

Family Applications (1)

Application Number Title Priority Date Filing Date
JP22162985A Granted JPS6282123A (en) 1985-10-04 1985-10-04 Protecting construction process for concrete on face of slope or the like

Country Status (1)

Country Link
JP (1) JPS6282123A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001064972A (en) * 1999-08-26 2001-03-13 Seni Doboku Kaihatsu Kk Fabric form for molding mortar and concrete

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001064972A (en) * 1999-08-26 2001-03-13 Seni Doboku Kaihatsu Kk Fabric form for molding mortar and concrete

Also Published As

Publication number Publication date
JPH0324929B2 (en) 1991-04-04

Similar Documents

Publication Publication Date Title
DE2651023C2 (en) Method for producing an in-situ concrete pile with a foot extension and device for carrying out the method
US3786640A (en) Means and method for producing stepped concrete slope structures
TWI695803B (en) Bags for civil engineering and structures for civil engineering
US3225413A (en) Inflatable form for a concrete building
DE4408173C2 (en) Process for stabilizing the subsoil and for removing structural and traffic loads
DK152897B (en) PROCEDURE AND FORM FOR MOLDING OF CONCRETE PLATES.
JPS6282123A (en) Protecting construction process for concrete on face of slope or the like
US20010040307A1 (en) Process and device for the production of foam slabs of angular cross-section in a flock composite
JPS58529A (en) Method and apparatus for producing concrete casting structure
DE2046845C3 (en) Fabric formwork
DE1634302C3 (en) Prefabricated structural element made of reinforced concrete for the production of a retaining wall or the like
JPH07207669A (en) Concreting method using form made of cloth and form made of cloth
US1894676A (en) Wall construction
JPH0454011B2 (en)
JP4652353B2 (en) Block mat and block mat manufacturing method
US1968774A (en) Apparatus for molding lithic
KR100654884B1 (en) Geogrid puller and method for covering soil using it
JPH04108917A (en) Construction method for reinforced banking body
JPH0673727A (en) Method of constructing soil pile column row earth retaining wall and special h-shaped steel bar
US1020919A (en) Hollow concrete wall.
DE1915688A1 (en) Waterproof sheet laying appliance for use in trenches - in the ground
JPH0527531Y2 (en)
KR20220101902A (en) Installing Method of Protect Film on Concrete Surface using Deck Finisher
AT329427B (en) SHAPE AND METHOD OF MANUFACTURING BEAMS
JPH05295726A (en) Top processing method for reinforced concrete structure