JPS6251335B2 - - Google Patents

Info

Publication number
JPS6251335B2
JPS6251335B2 JP13088081A JP13088081A JPS6251335B2 JP S6251335 B2 JPS6251335 B2 JP S6251335B2 JP 13088081 A JP13088081 A JP 13088081A JP 13088081 A JP13088081 A JP 13088081A JP S6251335 B2 JPS6251335 B2 JP S6251335B2
Authority
JP
Japan
Prior art keywords
concrete
precast
slab
stirrup
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP13088081A
Other languages
Japanese (ja)
Other versions
JPS5833655A (en
Inventor
Seiji Matsuo
Akira Ehashi
Tadamitsu Sato
Hitoshi Yamaguchi
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP13088081A priority Critical patent/JPS5833655A/en
Publication of JPS5833655A publication Critical patent/JPS5833655A/en
Publication of JPS6251335B2 publication Critical patent/JPS6251335B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 本発明は鉄骨鉄筋コンクリート構造体の構築工
法に関するものである。この種構築工法には従来
より各種工法が提案され又実施されている。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a construction method for a steel reinforced concrete structure. Various construction methods have been proposed and implemented for this type of construction method.

例えば天井および床スラブ、梁、柱のいずれを
も現場で配筋して現場打ちコンクリートにより構
築する工法や、予め工場でプレキヤスト構造体
(以下PC構造体と称す)としてスターラツプ筋等
の補強材をコンクリート内に埋設され、柱と梁と
が一体に接合したものを製造しておき、現場にて
スラブコンクリート打設時に一体に接合する工法
がある。
For example, there are construction methods in which ceilings, floor slabs, beams, and columns are all reinforced on-site and constructed using cast-in-place concrete, and reinforcing materials such as stirrup bars are installed in advance in a factory as a precast structure (hereinafter referred to as a PC structure). There is a construction method in which columns and beams are embedded in concrete and joined together, and then they are joined together at the site when slab concrete is poured.

前者はいずれも現場打ちコンクリートで一体に
接合するために各部相互間の接合強度が極めて良
好である長所を備えているが、反面配筋およびコ
ンクリート打設作業は不安定な足場上でその都度
行なわなければならないために作業能率が悪く、
安全性の上でも好ましくない等の欠点があつた。
The former has the advantage that the joint strength between each part is extremely good because they are joined together with cast-in-place concrete, but on the other hand, reinforcement and concrete pouring work must be done each time on unstable scaffolding. Work efficiency is poor due to having to
There were drawbacks such as undesirable safety issues.

一方後者は階上および階下に各配設したPC構
造体相互間を、現場打ちスラブコンクリートによ
り一体に接合するのみであるため、梁主筋やスタ
ーラツプ筋の配筋作業および梁に対するコンクリ
ート打設が不要なために作業能率は良好である
が、反面予め打設されているPC構造体のコンク
リートと現場打ちされるスラブコンクリートとの
接合強度が弱い欠点があつた。
On the other hand, in the latter case, the PC structures placed on the upper and lower floors are simply connected together using cast-in-place slab concrete, so there is no need for reinforcing work for beam main reinforcements or stirrup reinforcements, and for placing concrete on the beams. Therefore, the work efficiency is good, but on the other hand, there is a drawback that the bonding strength between the pre-cast concrete of the PC structure and the slab concrete poured on site is weak.

そこで本発明は上記各工法の欠点を補うため
に、プレキヤストコンクリート壁(以下PC壁と
称す)に基部を埋設する態様で少くとも梁スター
ラツプ筋の一部を予め取付けておき、施工現場で
の配筋作業を容易にすると共に、スラブコンクリ
ート打ちの際同時に梁コンクリートを現場打ちす
ることにより、各PC壁相互間および各PC壁とス
ラブ梁間を強固に一体接合することができる構築
工法を提供することものである。
Therefore, in order to compensate for the drawbacks of each of the above construction methods, the present invention has been developed by attaching at least a part of the beam stirrup bars in advance by burying the base in a precast concrete wall (hereinafter referred to as a PC wall), so that it can be easily installed at the construction site. To provide a construction method that facilitates reinforcing work and enables strong integral connection between each PC wall and between each PC wall and slab beam by pouring beam concrete on-site at the same time as slab concrete pouring. It is a thing.

以下に本発明の一実施例を図面により説明す
る。第1図および第2図は予め工場で組立てられ
たPC構造体Aの側面図と正面図である。このPC
構造体AはPC壁1と、該PC壁の上端に突設させ
たH鋼による梁鉄骨2と、基部がPC壁内に装着
されたスターラツプ筋3と、該スターラツプ筋の
下側屈曲内面に接合した下側梁主筋4と、PC壁
下端に突設させた接合用鉄筋5とから構成されて
いる。
An embodiment of the present invention will be described below with reference to the drawings. FIGS. 1 and 2 are a side view and a front view of a PC structure A that has been preassembled at a factory. This PC
Structure A consists of a PC wall 1, a beam steel frame 2 made of H steel protruding from the upper end of the PC wall, a stirrup reinforcement 3 whose base is installed inside the PC wall, and a lower bent inner surface of the stirrup reinforcement. It consists of a joined lower beam main reinforcement 4 and a joining reinforcement 5 protruding from the lower end of the PC wall.

PC壁1は必要に応じて交差状のブレース1a
を内装して前記梁鉄骨2と溶接したり、図示しな
いが鉄筋等の補強材を適宜設けると共に、前記梁
鉄骨2の下面と溶接されたアンカー棒2aと接合
用鉄筋5の基部を各々埋設した状態でコンクリー
ト打設する。尚、前記スターラツプ筋3の基部側
をPC壁内に装着する方法として、コンクリート
打設前に予め配筋しても良いし、予め抜型を埋設
しておきコンクリート硬化後に抜型を外してその
透孔にスターラツプ筋を挿通させるようにするこ
ともできる。又各スターラツプ筋3は下側梁主筋
4,4を囲繞する態様で所定間隔毎に配備し、各
スターラツプ筋の端部はいずれか一方側の梁主筋
に繋着されると共に、各梁主筋と溶接あるいは束
線により接合する。尚接合用鉄筋5に代え鋼棒や
長尺の鉄板を接合用部材として用いる場合もあ
る。次に第3図は他の実施例によるPC構造体B
の側面図を示すものである。
PC wall 1 has cross-shaped braces 1a as required.
The anchor rods 2a welded to the lower surface of the beam steel frame 2 and the bases of the joining reinforcing bars 5 were buried, respectively. Concrete is poured in the same condition. In addition, as a method for installing the base side of the stirrup reinforcement 3 in the PC wall, it is possible to arrange the reinforcement in advance before concrete is poured, or to bury a cutting die in advance and remove the cutting die after the concrete has hardened and insert the through hole. It is also possible to insert the Starrup muscle into the muscle. In addition, each stirrup reinforcement 3 is arranged at a predetermined interval so as to surround the lower beam main reinforcements 4, 4, and the end of each stirrup reinforcement is connected to the beam main reinforcement on either side, and is connected to each beam main reinforcement. Join by welding or bundled wire. Note that instead of the joining reinforcing bars 5, a steel rod or a long iron plate may be used as the joining member. Next, FIG. 3 shows a PC structure B according to another embodiment.
FIG.

該PC構造体のうち同一符号で示すものはいず
れも前記第1図および第2図のPC構造体Aと同
様構成であるが、スターラツプ筋を基部側6と上
部側7とに分割したものである。すなわち基部側
6を前記実施例のスターラツプ筋3のようにPC
壁1のコンクリート打設前に埋設するか、抜型を
外した透孔内に挿通させるかして装着し、これら
基部側スターラツプ筋6に隣接させて下側梁主筋
4,4に各々上部側スターラツプ筋7の両下端部
を繋着させるようにしたものである。尚この構造
体はスターラツプ筋の加工および取付が容易にで
きる利点がある。このようにして予め工場で組立
てられたPC構造体AあるいはBは施工現場に持
ち込まれ、第4図に示すように現場打ちコンクリ
ートにより一体に構築される。
All of the PC structures indicated by the same reference numerals have the same structure as the PC structure A shown in FIGS. 1 and 2, but the stirrup muscle is divided into a base side 6 and an upper side 7. be. That is, the proximal side 6 is PC like the stirrup muscle 3 in the above embodiment.
The upper stirrup reinforcements are installed adjacent to these base stirrup reinforcements 6 and attached to the lower beam main reinforcements 4, 4, either by burying them before concrete pouring of the wall 1 or by inserting them into the through holes from which the cutting mold has been removed. Both lower ends of the striations 7 are connected. This structure has the advantage that the stirrup muscles can be easily processed and attached. The PC structure A or B, which has been preassembled in the factory in this manner, is brought to the construction site and is constructed integrally with cast-in-place concrete, as shown in FIG.

すなわち2枚のPC構造体を用意し、階下の天
井であり階上の床となるスラブ11の施工位置を
挾んで当該PC構造体A2,A1を上下に配備し、ス
ラブ11および梁12の施工区域下部に型枠13
を装着すると共に、PC構造体A1のスターラツプ
筋3の上部側に内接して上部梁主筋14,15,
16を挿通せしめ、溶接あるいは束線で接合させ
て配筋を行う。尚この場合図示しないがスラブ1
1側にも必要な鉄筋が配筋されることはもちろん
である。
That is, two PC structures are prepared, and the PC structures A 2 and A 1 are placed above and below the construction position of the slab 11, which is the ceiling of the lower floor and the floor of the upper floor, and the slab 11 and the beam 12 are placed in between. Formwork 13 is installed at the bottom of the construction area.
At the same time, the upper beam main reinforcements 14, 15,
16 is inserted through the bar, and the reinforcement is arranged by welding or joining with wire bundles. Although not shown in this case, slab 1
Needless to say, the necessary reinforcing bars are placed on the first side as well.

そして型枠13で区画された施工区域内にコン
クリートを打設し、スラブ11と梁12とを施工
すると共に、各PC構造体A1,A2のPC壁1,1相
互間を埋設された梁鉄骨2および接合用鉄筋5を
介して一体に接合させるものである。
Concrete was then placed in the construction area divided by the formwork 13, and the slab 11 and beam 12 were constructed, and concrete was buried between the PC walls 1 and 1 of each PC structure A 1 and A 2 . They are joined together via beam steel frame 2 and joining reinforcing bars 5.

尚上記実施例中、スターラツプ筋3,6,7お
よび下部側梁主筋4を予め工場にて組立てるよう
にしたが、予めPC壁1内に埋設する場合を除い
ては施工区域に設置される以前の現場にて組立て
ることも出来る。
In the above example, the stirrup bars 3, 6, 7 and the lower side beam main bars 4 were assembled in advance at the factory, but unless they are buried in the PC wall 1 in advance, they are not installed in the construction area. It can also be assembled on-site.

このようにして上記実施例による構築工法は、
プレキヤストコンクリートで予め製造した壁1
と、該壁に装着される梁部材であつて少くともス
ラブ11内に配筋される図示しない鉄筋に通路を
阻害される恐れのある上部側梁主筋14,15,
16を除いた下部側梁主筋4,4およびスターラ
ツプ筋3,6,7を、施工区域外の工場あるいは
現場で予め組立てることが出来るので安全性の確
保と作業能率の向上を計ることができる。又現場
打ちスラブコンクリートと同時に梁コンクリート
を打設して階上下の各壁を相互に連結させること
により、スラブ11、梁12、壁A1,A2の3者
を打設したコンクリートと、梁鉄骨2、接合用鉄
筋5、スターラツプ筋3および各梁主筋を介して
強固に一体化することができる。
In this way, the construction method according to the above embodiment is
Wall prefabricated with precast concrete 1
and upper side beam main reinforcements 14, 15, which are beam members attached to the wall and whose passage may be obstructed by at least unillustrated reinforcing bars arranged within the slab 11.
Since the lower side beam main reinforcements 4, 4 and the stirrup reinforcements 3, 6, 7, excluding 16, can be assembled in advance at a factory or on-site outside the construction area, it is possible to ensure safety and improve work efficiency. In addition, by pouring beam concrete at the same time as the slab concrete poured in-situ and interconnecting the walls on the upper and lower floors, the concrete cast for the slab 11, beam 12, walls A 1 and A 2 , and the beam It is possible to firmly integrate the steel frame 2, the connecting reinforcing bars 5, the stirrup bars 3, and each beam main bar.

次に第5図は他の実施例によるPC構造体と、
この構造体による構築工法を示すものである。こ
のPC構造体C1,C2は前記実施例と同様にPC壁1
と、梁鉄骨2および接合用鉄筋5を各々備えてい
るが、基端部がPC壁1を挿通したスターラツプ
筋8が下部側梁主筋9,9および上部側梁主筋1
0,10を囲繞すると共に、梁鉄骨2の両側から
内方に屈曲させたものである。そしてこのPC構
造体は、上部側梁主筋10,10がスラブ11内
の図示しない鉄筋側に突出していないためにこれ
らに阻害されず、従つてその全てを工場あるいは
スラブ施工区域に設置する以前の現場にて予め組
立てすることが出来るために極めて作業能率が良
く、組立後前記実施例と同様に型枠13内に打設
されたコンクリートによりスラブ10と梁12を
施工すると共に、上下階の各壁1,1を一体に接
合するものである。
Next, FIG. 5 shows a PC structure according to another embodiment,
This figure shows the construction method for this structure. These PC structures C 1 and C 2 are connected to the PC wall 1 as in the previous embodiment.
The stirrup reinforcement 8 whose base end penetrates the PC wall 1 is connected to the lower side beam main reinforcements 9, 9 and the upper side beam main reinforcement 1.
0 and 10, and is bent inward from both sides of the beam steel frame 2. This PC structure is not hindered by the upper side beam main reinforcements 10, 10 because they do not protrude to the reinforcing bars (not shown) in the slab 11, and therefore, all of them are installed in the factory or in the slab construction area. Work efficiency is extremely high because they can be pre-assembled on site.After assembly, the slab 10 and beams 12 are constructed using concrete placed in the formwork 13 in the same way as in the previous embodiment, and each of the upper and lower floors is This is to join the walls 1, 1 together.

この実施例のものは前記実施例のものより一段
と作業能率が良く、又前記従来例の壁と梁とが一
体のPC構造のものよりスラブおよび上下階の壁
相互間の接合強度は改善されるが、前記実施例の
ものに比べてスラブ11側にPC構造体が突出し
ていない分だけ接合強度は劣る。
The work efficiency of this embodiment is much higher than that of the previous embodiment, and the joint strength between the slab and the walls of the upper and lower floors is improved compared to the conventional PC structure in which the walls and beams are integrated. However, compared to the example described above, the bonding strength is inferior to the extent that the PC structure does not protrude toward the slab 11 side.

以上のように本発明による構築工法は、鉄骨梁
材や接合部材を各々装着したプレキヤストコンク
リート壁を予め工場で製造し、当該プレキヤスト
コンクリート壁に対して基部を貫通状に装着した
スターラツプ筋とこのスターラツプ筋に接合され
た少くとも下部側梁主筋とを工場又は安全作業が
可能な現場近くの加工場等で予め組立ててプレキ
ヤスト構造体とすることにより、足場を築いて施
工域内で全てを組立てるものに比べ作業の安全確
保と作業能率の向上を計ることができるものであ
る。
As described above, in the construction method of the present invention, a precast concrete wall to which steel beams and joint members are attached is manufactured in advance in a factory, and stirrup reinforcement is attached to the precast concrete wall with its base penetrating. By assembling at least the main reinforcement of the lower side beam connected to this stirrup reinforcement in advance at a factory or a processing plant near the site where work can be done safely to create a precast structure, scaffolding is built and everything is assembled within the construction area. It is possible to ensure work safety and improve work efficiency compared to other methods.

又上記プレキヤスト構造体2枚をスラブを挾ん
で上下階の壁が形成されるよう所定の施工区域内
に設置し、残りの上部側梁主筋等の配筋作業を完
了させたのち、スラブ施工域および梁施工域に
各々添装された型枠内に同時にコンクリート打設
することにより、梁およびスラブの施工を行うと
共に、これらの各プレキヤスト壁相互間とを一体
に接合するものであるが、梁とスラブとをいずれ
も現場打ちコンクリートで同時に行うために従来
のPC梁と現場打ちコンクリートスラブの組合せ
た工法に比べコンクリートを介しての接合強度に
おいて格段の相違がある。更にこれらスラブおよ
び梁と各プレキヤスト壁相互間は、打設されたコ
ンクリートと、このコンクリート内に埋設された
壁に装着している鉄骨梁材、接合部材およびスタ
ーラツプ筋を介して強固に連結されることができ
る。
In addition, the two precast structures mentioned above were installed in the designated construction area so that the walls of the upper and lower floors were formed by sandwiching the slab, and after completing the reinforcement work such as the remaining upper side beam main reinforcements, the slab construction area was installed. By simultaneously pouring concrete into the formwork attached to the beam construction area, the beam and slab are constructed, and these precast walls are integrally joined. Because both the concrete beam and the slab are constructed at the same time using cast-in-place concrete, there is a significant difference in the strength of the joint through the concrete compared to the conventional construction method that combines a PC beam and a cast-in-place concrete slab. Furthermore, these slabs and beams and each precast wall are firmly connected through the poured concrete, the steel beam materials, joint members, and stirrup reinforcements attached to the walls embedded in this concrete. be able to.

【図面の簡単な説明】[Brief explanation of the drawing]

図面はいずれも本願の実施例を示し、第1図は
プレキヤスト構造体の側面図、第2図は同正面
図、第3図は他の実施例によるプレキヤスト構造
体の側面図、第4図は施工態様の説明図、第5図
は他の実施例による施工態様の説明図である。 符号の説明、1…プレキヤスト壁、2…鉄筋
梁、3,6,7,8…スターラツプ筋、4,9,
10,14,15,16…梁主筋、5…接合用鉄
筋、11…スラブ、12…梁、13…型枠、A,
A1,A2,B,C,C2…プレキヤスト構造体。
The drawings all show embodiments of the present application; FIG. 1 is a side view of a precast structure, FIG. 2 is a front view of the same, FIG. 3 is a side view of a precast structure according to another embodiment, and FIG. 4 is a side view of the precast structure. FIG. 5 is an explanatory diagram of a construction mode according to another embodiment. Explanation of symbols, 1... Precast wall, 2... Reinforced beam, 3, 6, 7, 8... Stirrup reinforcement, 4, 9,
10, 14, 15, 16... Beam main reinforcement, 5... Connection reinforcing bar, 11... Slab, 12... Beam, 13... Formwork, A,
A 1 , A 2 , B, C, C 2 ... precast structure.

Claims (1)

【特許請求の範囲】[Claims] 1 上端に鉄骨梁材を下端に鉄骨又は鉄筋による
接合部材を各々装着したプレキヤストコンクリー
ト壁に基部を貫通する態様でスターラツプ筋を装
着すると共に、当該スターラツプ筋に少くとも下
部側梁主筋を装着させたプレキヤスト構造体を施
工前に予め組立てておき、前記プレキヤスト構造
体2枚を施工域内に上下に設置して残りの配筋作
業を完了させたのち、添装された型枠内にスラブ
コンクリートと同時に梁コンクリートを現場打ち
することにより、スラブおよび梁を施工せしめ且
つこれらと各プレキヤスト構造体相互間を一体に
接合させたことを特徴とする鉄骨鉄筋コンクリー
ト構造体の構築工法。
1. Attach stirrup reinforcements to the precast concrete wall in such a manner as to penetrate through the base of the precast concrete wall, each with a steel beam material attached to the upper end and a joint member made of steel frames or reinforcing bars at the lower end, and attach at least the lower side beam main reinforcement to the stirrup reinforcements. The precast structures are assembled in advance before construction, and the two precast structures are installed one above the other in the construction area to complete the remaining reinforcement work, and then the slab concrete is placed in the attached formwork. A construction method for a steel-framed reinforced concrete structure, characterized in that a slab and a beam are constructed by simultaneously pouring beam concrete on-site, and these and each precast structure are integrally connected to each other.
JP13088081A 1981-08-21 1981-08-21 Construction of reinforced concrete structure Granted JPS5833655A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13088081A JPS5833655A (en) 1981-08-21 1981-08-21 Construction of reinforced concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13088081A JPS5833655A (en) 1981-08-21 1981-08-21 Construction of reinforced concrete structure

Publications (2)

Publication Number Publication Date
JPS5833655A JPS5833655A (en) 1983-02-26
JPS6251335B2 true JPS6251335B2 (en) 1987-10-29

Family

ID=15044846

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13088081A Granted JPS5833655A (en) 1981-08-21 1981-08-21 Construction of reinforced concrete structure

Country Status (1)

Country Link
JP (1) JPS5833655A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59158844A (en) * 1983-03-02 1984-09-08 佐藤工業株式会社 Construction of structure

Also Published As

Publication number Publication date
JPS5833655A (en) 1983-02-26

Similar Documents

Publication Publication Date Title
JPS6251335B2 (en)
JPH0480444A (en) Connection unit of reinforced concrete pole and steel framed beam
JPH1121915A (en) Connecting method of pile head
JP3008795B2 (en) Joint structure of reinforced concrete beams
JP2903873B2 (en) Beam joint structure of centrifugally formed hollow PC column
JPH01137032A (en) Method of lap joint construction of main reinforcement in post and beam joining section
JPH0868113A (en) Connecting structure for steel beam and reinforced concrete beam
JP2917159B2 (en) Column, beam joining method
JPH0732706Y2 (en) Reinforcement structure of precast reinforced concrete columns and crossed steel frames for joining steel beams
JPH0745783B2 (en) Construction method of precast column beam and precast earthquake resistant wall.
JPS6335773B2 (en)
JP3039260B2 (en) Building method using PC members
JP2574630Y2 (en) Half PC beam structure
JPH0350846B2 (en)
JP2542279B2 (en) Joining method of main bar in wall type frame method
JP2978011B2 (en) U-shaped beam formwork and method of constructing beam and beam joint using the same
JPH026901B2 (en)
JPH0588331B2 (en)
JPH03281855A (en) Floor framing construction for building
JPH0420639A (en) Pc small beam
JP2984882B2 (en) Precast reinforced concrete column-beam joint structure
JPH0250262B2 (en)
JPS5952042A (en) Joint of iron skeletal and iron wire
JPH0349334B2 (en)
JPH0448143B2 (en)