JPS6249236B2 - - Google Patents
Info
- Publication number
- JPS6249236B2 JPS6249236B2 JP56095200A JP9520081A JPS6249236B2 JP S6249236 B2 JPS6249236 B2 JP S6249236B2 JP 56095200 A JP56095200 A JP 56095200A JP 9520081 A JP9520081 A JP 9520081A JP S6249236 B2 JPS6249236 B2 JP S6249236B2
- Authority
- JP
- Japan
- Prior art keywords
- block
- pipes
- hull
- hydraulic pipes
- piping
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000010276 construction Methods 0.000 claims description 8
- 238000003466 welding Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 239000004677 Nylon Substances 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000002452 interceptive effect Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 229920001778 nylon Polymers 0.000 description 1
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L25/00—Constructive types of pipe joints not provided for in groups F16L13/00 - F16L23/00 ; Details of pipe joints not otherwise provided for, e.g. electrically conducting or insulating means
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Supports For Pipes And Cables (AREA)
- Protection Of Pipes Against Damage, Friction, And Corrosion (AREA)
Description
【発明の詳細な説明】
本発明は、各種弁の油圧管等を配設した船体ブ
ロツク建造における配管施工法に関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing piping in the construction of a hull block in which hydraulic pipes for various valves and the like are arranged.
従来、この種の船舶において、油圧管等を多数
配管した船体ブロツクの接合部は、第1図ないし
第2図a,bに示すように施工されていた。すな
わち各種弁を有する101〜10oを配設したブ
ロツクaと、油圧管111〜11oを配設したブ
ロツクbとを連結する場合、各ブロツクa,bに
おける油圧管101〜10o,111〜11oの配
管は、ブロツク合わせの際に双方の管が干渉して
ブロツク合わせの障害となるのを防止するため、
必らずブロツク継手面より引つ込めて配設されて
おり、各ブロツクaとbとを組付けた後、油圧管
101〜10o,111〜11oとの間に短管12
1〜12oと管接続スリーブ131〜13oを上、
下に使用して溶接などにより連結されていた。 Conventionally, in this type of ship, joints between hull blocks having a large number of hydraulic pipes and the like were constructed as shown in FIGS. 1 and 2 a and b. That is, when connecting block a, which has various valves 10 1 to 10 o , and block b, which has hydraulic pipes 11 1 to 11 o , the hydraulic pipes 10 1 to 10 o in each block a and b are connected. , 11 1 to 11 o , to prevent both pipes from interfering with each other and becoming an obstacle to block alignment.
It is always retracted from the block joint surface, and after each block a and b are assembled, a short pipe 12 is inserted between the hydraulic pipes 10 1 - 10 o and 11 1 - 11 o .
1 ~ 12 o and pipe connection sleeve 13 1 ~ 13 o on top,
It was used at the bottom and connected by welding etc.
しかしながら、油圧管101〜10o,111
〜11oと連結するのに短管121〜12oの上下
2ケ所に管接続スリーブ131〜13oが使用さ
れるため、1系統毎に管接続スリーブが2個必要
になり、取付配管工事に多大の工数が必要である
とともに、船体における管の接続部は、甲板下に
ほぼ50%程配設されているので高所危険作業とな
る等の難点があつた。 However, the hydraulic pipes 10 1 to 10 o , 11 1
Since pipe connecting sleeves 13 1 to 13 o are used at two locations above and below the short pipes 12 1 to 12 o to connect with the short pipes 12 1 to 11 o , two pipe connecting sleeves are required for each system, and the installation piping is Not only did the construction require a large amount of man-hours, but it also had the disadvantage of requiring dangerous work at heights, as approximately 50% of the pipe connections in the ship's hull were located below deck.
本発明は、上述した従来例の施工法を改善し、
各ブロツクに配設した油圧管等の端面をブロツク
継手面より突き出すとともに先端部に管と管との
干渉を防止するキヤツプを被せ、各ブロツクの接
合後に管の重なり寸法を切断して連結を行ない、
管接続スリーブの削減、管の接続配管工事を簡素
化することを目的とした船体ブロツク建造におけ
る配管工法を提供するものである。 The present invention improves the conventional construction method described above,
The end faces of the hydraulic pipes, etc. installed on each block are made to protrude from the block joint surface, and a cap is placed on the tip to prevent interference between the pipes. After each block is joined, the pipes are connected by cutting the overlapping dimension of the pipes. ,
This invention provides a piping method for constructing a hull block with the aim of reducing the number of pipe connection sleeves and simplifying the pipe connection work.
以下、本発明による実施例を第3図ないし第4
図を参照して具体的に説明する。図において、
A,Bは船体ブロツクであり、例えば上部船体ブ
ロツクAの油圧管11〜1oはブロツク継手面よ
り若干引つ込めて配設し、下部船体ブロツクBの
油圧管21〜2oはブロツク継手面より突き出し
て配設されている。これら油圧管11〜1oと油
圧管21〜2oはそれぞれ可撓性が保たれる距離
(例えば、20mmφ〜100mmφの油圧管では1m程
度)その先端から引込んだ位置でブラケツト2
0,21を介してブロツクA,Bに取付けられて
いる。なお、ブラケツト20,21に取付けられ
ている油圧管11〜1o,21〜2oは、互いに接
続される管が同一軸線上で対向するように配設さ
れており、ブロツクAとBとを接合するときに後
述のように油圧管11〜1o,21〜2oが撓んで
交互に重なり合う。 Embodiments according to the present invention will be described below with reference to FIGS. 3 to 4.
This will be explained in detail with reference to the drawings. In the figure,
A and B are hull blocks. For example, the hydraulic pipes 1 1 to 1 o of the upper hull block A are arranged slightly retracted from the block joint surface, and the hydraulic pipes 2 1 to 2 o of the lower hull block B are arranged in the blocks. It is arranged so as to protrude from the joint surface. These hydraulic pipes 1 1 - 1 o and hydraulic pipes 2 1 - 2 o are retracted from their ends at a distance that maintains their flexibility (for example, about 1 m for hydraulic pipes of 20 mmφ to 100 mmφ), and then the bracket 2 is inserted.
It is attached to blocks A and B via pins 0 and 21. The hydraulic pipes 1 1 - 1 o and 2 1 - 2 o attached to the brackets 20 and 21 are arranged so that the pipes connected to each other face each other on the same axis. When these are joined, the hydraulic pipes 1 1 to 1 o and 2 1 to 2 o are bent and overlapped alternately as will be described later.
上記各ブロツクA及びBの油圧管11〜1o及
び21〜2oの先端開口部には、先端を尖らせた
尖先キヤツプ31〜3o及び41〜4oを被せて、
ブロツクAとBを接合する際に互いに管端が衝突
するのを防止している。すなわち、尖先キヤツプ
31〜3oと41〜4oとが当接して摺り合うこと
により油圧管11〜1o及び21〜2oが撓み、管
端同士の衝突が防止される。 The tip openings of the hydraulic pipes 1 1 - 1 o and 2 1 - 2 o of each of the blocks A and B are covered with pointed caps 3 1 - 3 o and 4 1 - 4 o , which have sharpened tips.
This prevents the tube ends from colliding with each other when blocks A and B are joined. In other words, the tip caps 3 1 - 3 o and 4 1 - 4 o come into contact with each other and rub against each other, thereby bending the hydraulic pipes 1 1 - 1 o and 2 1 - 2 o , thereby preventing the pipe ends from colliding with each other. .
ここで、上記ブロツクAに配設した油圧管11
〜1oはブロツク継手面より200mm程引つ込めてブ
ラケツト20に取付け、ブロツクBに配設した油
圧管21〜2oをブロツク継手面より300mm程突き
出してブラケツト21に取付け、しかも、各管端
に被せた尖先キヤツプ31〜3o及び41〜4o
は、透明なナイロンホース等を斜めに切断したも
のを嵌め、斜めの切り口を加熱して圧着させたも
のである。 Here, the hydraulic pipes 1 1 disposed in the block A
~1 o is retracted about 200 mm from the block joint surface and attached to the bracket 20, and the hydraulic pipes 21 ~ 2 o arranged on block B are installed on the bracket 21 so as to protrude about 300 mm from the block joint surface, and each pipe is Pointed caps 3 1 - 3 o and 4 1 - 4 o placed on the ends
This is a transparent nylon hose or the like cut diagonally and fitted, and the diagonal cut end is heated and crimped.
従つて、上記ブロツクAとブロツクBとの接合
時には、尖先キヤツプ31〜3o,41〜4oによ
り、各油圧管11〜1oと21〜2oは互いに衝突
して損傷することなく交互に100mm程重なり合つ
て配設される。そこでブロツクAとBとを接合後
は、各尖先キヤツプを取り外し、互いに重なり合
つたほぼ100mm程の寸法を切断し、管接合部に管
接続スリーブ51〜5oを嵌め込み、重なり合う
ことにより撓められていた油圧管11〜1oと2
1〜2oとを同軸状態に復帰させて溶接にて連結
する。 Therefore, when the blocks A and B are joined, the hydraulic pipes 11 to 1o and 21 to 2o collide with each other due to the point caps 31 to 3o and 41 to 4o , causing damage. They are placed alternately overlapping each other by about 100mm without any overlap. Therefore, after joining blocks A and B, remove each tip cap, cut out a section of about 100 mm that overlaps each other, fit the pipe connecting sleeves 51 to 5o into the pipe joint, and bend by overlapping them. Hydraulic pipes 1 1 to 1 o and 2
1 to 2 o are returned to a coaxial state and connected by welding.
なお、上記したブロツクAとブロツクBとの接
合時に、油圧管11〜1o(21〜2o)側の一対
の管の間に油圧管21〜2o(11〜1o)側の管
が2本以上入り込もうとしても、油圧管11〜1
o及び21〜2oが撓んで互いに逃げるため、一対
の管の間に2本以上の管が挾まれてこれら管が衝
突したり無理に変形したりすることはない。従つ
て、尖先キヤツプ31〜3o及び41〜4oは管端
同士の衝突を避ける作用を奏すれば良く、その切
り口を一定にせずとも第3図に示すように任意の
向きに向かせて設けて良い。すなわち、尖先をも
つたキヤツプであれば良く、円錐状等の任意の形
状とすることができる。 In addition, when joining the above-mentioned block A and block B, the hydraulic pipes 21 to 2o ( 11 to 1o ) are connected between the pair of pipes on the side of the hydraulic pipes 11 to 1o ( 21 to 2o ). Even if two or more side pipes try to enter, the hydraulic pipes 1 1 to 1
Since o and 2 1 to 2 o bend and escape from each other, two or more tubes will not collide or be forcibly deformed when two or more tubes are sandwiched between a pair of tubes. Therefore, the tip caps 3 1 - 3 o and 4 1 - 4 o only have to function to avoid collisions between the tube ends, and can be oriented in any direction as shown in Fig. 3 without having to make the cut ends constant. You can set it facing the other direction. That is, the cap may have any shape as long as it has a pointed tip, such as a conical shape.
なお、ここで隣り合う管の切断位置を交互にず
らすことにより、管の連結作業が格段に簡素化さ
れる。 Incidentally, by alternately shifting the cutting positions of adjacent tubes, the operation of connecting the tubes is greatly simplified.
以上詳述したように、本発明による船体ブロツ
ク建造における配管施工法は、船体ブロツク継手
部の現場合わせ用の短管が不要となり、船体ブロ
ツク継手部での配管の重なりを予め計画し、各船
体ブロツクを接合後、管の重なり寸法を切断し
て、1系統に1個の管接続スリーブを嵌め込み、
溶接にて連結するようにしたものであり、従来の
現場合わせ施工法に比べて管接続スリーブが半減
し、材料費、作業工数が大巾に削減できる。ま
た、管端部に尖先キヤツプを被せてあるので、船
体ブロツクの接合時に相互に管の干渉がなくな
り、管の連結作業までの間、管内に異物が入るの
を防止する役目を果している。 As described in detail above, the piping construction method for building a hull block according to the present invention eliminates the need for short pipes for on-site alignment of the hull block joints, and allows the overlapping of piping at the hull block joints to be planned in advance to ensure that each hull After joining the blocks, cut the overlapping dimensions of the pipes, fit one pipe connection sleeve into each system,
The pipes are connected by welding, and the number of pipe connection sleeves is halved compared to the conventional on-site construction method, which greatly reduces material costs and man-hours. In addition, since the tube ends are covered with pointed caps, the tubes do not interfere with each other when the hull blocks are joined, and this serves to prevent foreign matter from entering the tubes until the tubes are connected.
さらに、各管端連結部は、船体ブロツクの接合
後に現場にて重なり合つた寸法のみ切断されるの
で正確に仕上げることができる等の効果を奏する
ものである。 Further, each tube end connecting portion is cut on site after the hull blocks are joined to only the overlapping dimensions, so that accurate finishing can be achieved.
第1図ないし第2図a,bは従来例の施工法を
示す説明図、第3図ないし第4図は本発明による
施工法を示す説明図である。
図面中、11〜1o,21〜2oは油圧管、31
〜3o,41〜4oは尖先キヤツプ、51〜5oは
管接続スリーブ、A,Bは船体ブロツクである。
1 to 2 a and b are explanatory diagrams showing a conventional construction method, and FIGS. 3 to 4 are explanatory diagrams showing a construction method according to the present invention. In the drawings, 1 1 to 1 o , 2 1 to 2 o are hydraulic pipes, and 3 1
3o , 41 to 4o are pointed caps, 51 to 5o are pipe connection sleeves, and A and B are hull blocks.
Claims (1)
おける双方の配管の端部に尖先キヤツプを被せ、
一方の船体ブロツクの配管を上記ブロツク継手面
より若干引つ込めると共に、他方の船体ブロツク
の配管を上記ブロツク継手面より突き出して、各
配管が相互に重なり合うように配設し、上記船体
ブロツク同士の接合後、配管端部の重なる部分を
切断して配管同士を締結するようにしたことを特
徴とする船体ブロツク建造における配管施工法。1. Cover the ends of both pipes in the hull block that are joined at the block joint surface with pointed caps,
The piping of one hull block is slightly retracted from the joint surface of the block, and the piping of the other hull block is protruded from the joint surface of the block, so that each piping overlaps with the other. A piping construction method for building a hull block, characterized in that after joining, the overlapping portions of the pipe ends are cut and the pipes are connected to each other.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP56095200A JPS58477A (en) | 1981-06-22 | 1981-06-22 | Piping method in hull block sequence joining |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP56095200A JPS58477A (en) | 1981-06-22 | 1981-06-22 | Piping method in hull block sequence joining |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS58477A JPS58477A (en) | 1983-01-05 |
JPS6249236B2 true JPS6249236B2 (en) | 1987-10-19 |
Family
ID=14131104
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP56095200A Granted JPS58477A (en) | 1981-06-22 | 1981-06-22 | Piping method in hull block sequence joining |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS58477A (en) |
-
1981
- 1981-06-22 JP JP56095200A patent/JPS58477A/en active Granted
Also Published As
Publication number | Publication date |
---|---|
JPS58477A (en) | 1983-01-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU681122B2 (en) | Kit and method for producing a connector for fluid-conducting elements | |
US4694628A (en) | Metal building panel with standing seam edge formations | |
US5635675A (en) | Bendable protective tube for buried cables | |
US5405174A (en) | Kit and method for producing a connector for fluid pipe elements | |
JPS6249236B2 (en) | ||
US4579273A (en) | Welded pipe connection | |
JPH088392Y2 (en) | Submarine laying protective tube for long body | |
JP2500810Y2 (en) | Split pipe | |
CN212571974U (en) | Wire pipe connecting structure for modular building and modular building | |
CN219554452U (en) | Waterproof rubber sleeve and waterproof rubber structure for wire passing of automobile wire harness | |
JPH0350931Y2 (en) | ||
CN220099666U (en) | Lead wire bundle penetrating assembly suitable for ultra-long complex wavy prestressed pipeline | |
JPH0626615Y2 (en) | U-shaped groove connection structure | |
SU538840A1 (en) | The construction of the welded joint of pipes with internal coating | |
JPS6033147Y2 (en) | Steel pipe piles for medium excavation method | |
JPS6313486B2 (en) | ||
JPH0842751A (en) | Unit pipe device | |
JPH0344874Y2 (en) | ||
GB2030278A (en) | Prefabricated chimney-shaft | |
JPS58189412A (en) | Steel plate cell structure | |
JPS641712B2 (en) | ||
JPS62113983A (en) | Burying method to ground of pipe made of synthetic resin | |
JPH0355714B2 (en) | ||
JPS6123435B2 (en) | ||
JPH09257189A (en) | Flexible pipe body made by forming steel wire into spiral form |