JPS6223955Y2 JP1981128367U JP12836781U JPS6223955Y2 JP S6223955 Y2 JPS6223955 Y2 JP S6223955Y2 JP 1981128367 U JP1981128367 U JP 1981128367U JP 12836781 U JP12836781 U JP 12836781U JP S6223955 Y2 JPS6223955 Y2 JP S6223955Y2
Authority
JP
Japan
Prior art keywords
gondola
building
pipes
support frame
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP1981128367U
Other languages
Japanese (ja)
Other versions
JPS5833666U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP12836781U priority Critical patent/JPS5833666U/en
Publication of JPS5833666U publication Critical patent/JPS5833666U/en
Application granted granted Critical
Publication of JPS6223955Y2 publication Critical patent/JPS6223955Y2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Movable Scaffolding (AREA)
  • Forklifts And Lifting Vehicles (AREA)
  • Hooks, Suction Cups, And Attachment By Adhesive Means (AREA)

Description

【考案の詳細な説明】 本考案は高層ビル用ゴンドラに係り、更に詳し
くはゴンドラの揺動を防止できるゴンドラに関す
るものである。
[Detailed Description of the Invention] The present invention relates to a gondola for a high-rise building, and more particularly to a gondola that can prevent the gondola from swinging.

従来のこの種のゴンドラは第1図及び第2図に
示すようにビル1の屋上に支柱2を設けこの支柱
2の上端にビーム3を固定しこのビーム3に走行
車4を設けることにより、ホイストクレーンを構
成し、走行車4から吊り下げられたワイヤー5に
ゴンドラ6を吊り下げ、ワイヤー5を操作するこ
とによりゴンドラ6を昇降させゴンドラ6に乗つ
た作業者がビルの外壁の清掃作業や壁面補修作業
を行なつていた。
As shown in FIGS. 1 and 2, the conventional gondola of this type has a support 2 on the roof of a building 1, a beam 3 fixed to the upper end of the support 2, and a traveling vehicle 4 mounted on this beam 3. A hoist crane is configured, and a gondola 6 is suspended from a wire 5 suspended from a traveling vehicle 4. By operating the wire 5, the gondola 6 is raised and lowered, and a worker riding on the gondola 6 can clean the outer wall of a building. Wall repair work was being carried out.

ところが、このようにゴンドラ6を単に吊り下
げただけでは第1図及び第2図に鎖線で示すよう
にゴンドラ6は、強風や作業による反作用により
ビルの壁面に沿つて揺れたり、壁面から離れる方
向に揺れたりして極めて危険な状態が生じる。特
に高層ビルでは風が加速現象を生じゴンドラは大
きく揺れ動き危険であるばかりでなく作業しづら
く、清掃作業や壁面補修作業を極めて困難なもの
にしていた。
However, if the gondola 6 is simply suspended in this way, the gondola 6 may sway along the wall of the building or move away from the wall due to strong winds or reaction from work, as shown by the chain lines in Figures 1 and 2. tremors, creating an extremely dangerous situation. Particularly in high-rise buildings, the wind accelerates and the gondolas shake violently, making it not only dangerous but also difficult to work on, making cleaning and wall repair work extremely difficult.

このような不都合を解消するためにビルの壁面
に小さなハツカーなどのゴンドラ係止装置を設け
たり、ゴンドラを案内するガイドレールを設けた
りする構造が提案されたが、ビルの美観を損ねた
り、建築費を高くするなどの問題が生じた。
In order to solve this inconvenience, structures have been proposed in which gondola locking devices such as small hookers are installed on the wall of the building, and guide rails are installed to guide the gondola, but these structures do not spoil the aesthetics of the building or interfere with the construction. Problems such as high costs arose.

本考案は以上のような従来の欠点を解消するた
めに成されたもので、極めて簡単な構造によりゴ
ンドラの揺動を防止することができるように構成
した高層ビル用ゴンドラを提供することを目的と
している。
The present invention was made to eliminate the above-mentioned conventional drawbacks, and the purpose is to provide a gondola for high-rise buildings that has an extremely simple structure that can prevent the gondola from swinging. It is said that

本考案においては、上記の目的を達成するため
になされたものである。すなわち、本考案はホイ
ストクレーンによりビルの壁面に沿つて吊り下げ
られる箱状の高層ビル用ゴンドラにおいて、複数
本のパイプを縦横に配置結合すると共に相互に連
通して形成した支持枠を前記ゴンドラに上下動自
在に設け前記支持枠におけるゴンドラの両側に位
置するパイプの両端を前記ビルの壁面方向に曲げ
ると共に該パイプの先端にパイプと連通していて
且つビルの壁面に吸着係合する吸着部材を設け、
前記支持枠にブロワを設けると共に、該ブロワと
前記支持枠とを連通して構成したことを特徴とす
る。
The present invention has been made to achieve the above object. That is, the present invention is a box-shaped gondola for high-rise buildings that is suspended along the wall of a building by a hoist crane, and the gondola is provided with a support frame formed by connecting a plurality of pipes vertically and horizontally and communicating with each other. Both ends of the pipe, which is movable up and down and located on both sides of the gondola in the support frame, are bent toward the wall of the building, and a suction member is provided at the tip of the pipe, communicating with the pipe and engaging with the wall of the building by suction. established,
The present invention is characterized in that the support frame is provided with a blower, and the blower and the support frame are communicated with each other.

以下、図面に示す実施例に基づいて本考案の詳
細を説明する。
Hereinafter, the present invention will be explained in detail based on embodiments shown in the drawings.

第3図及び第4図は本考案の一実施例を示すも
ので、各図中第1図及び第2図と同一部分には同
一符号を付し、その説明は省略する。
3 and 4 show one embodiment of the present invention, and in each figure, the same parts as in FIGS. 1 and 2 are designated by the same reference numerals, and their explanation will be omitted.

本実施例にあつては複数本のパイプ部材を縦横
に配置結合すると共に相互に連通して支持枠19
が形成され、該支持枠19がゴンドラ6に上下動
自在に設けられる。支持枠19をさらに説明する
と、作業者が乗るゴンドラ6の作業台7の両側の
上下端にゴンドラ6のフレームを利用して各々軸
受8を同一軸線上に設け、これら軸受8,8間に
縦に配置した両側パイプ9,9を上下動自在に嵌
合させてある。この両側パイプ9,9の両端部は
それぞれビルの壁面側に向つて折曲げてあると共
に、折曲げ先端部にはパイプ9,9と連通した吸
盤状の吸着部材9aが固着されている。
In this embodiment, a plurality of pipe members are arranged and connected vertically and horizontally and communicated with each other to form a support frame 19.
is formed, and the support frame 19 is provided on the gondola 6 so as to be vertically movable. To further explain the support frame 19, bearings 8 are provided on the same axis at the upper and lower ends of both sides of the work platform 7 of the gondola 6 on which the worker rides, using the frame of the gondola 6, and there is a vertical line between these bearings 8, 8. The pipes 9, 9 on both sides disposed in are fitted together so as to be vertically movable. Both ends of the pipes 9, 9 on both sides are respectively bent toward the wall of the building, and a suction member 9a in the form of a suction cup communicating with the pipes 9, 9 is fixed to the bent tip.

一方、両側パイプ9,9間には上下に所定距離
はなして平行に補強枠を兼ねたパイプ10,10
が横架されており、少なくとも下側のパイプ1
0,10は両側パイプ9,9の両者に連通してい
る。
On the other hand, between the pipes 9, 9 on both sides, pipes 10, 10, which also serve as reinforcing frames, run parallel to each other with a predetermined distance above and below.
is suspended horizontally, and at least the lower pipe 1
0 and 10 communicate with both pipes 9 and 9 on both sides.

また、上下のパイプ10,10間には水平方向
に所定距離はなして垂直な状態で2本の補強枠1
1,11が張架されており、補強枠11,11間
にはそのほぼ中央部において水平な補強枠12が
横架されている。
In addition, between the upper and lower pipes 10, two reinforcing frames 1 are placed in a vertical state with a predetermined distance in the horizontal direction.
1 and 11 are stretched, and a horizontal reinforcing frame 12 is horizontally suspended between the reinforcing frames 11 and 11 at approximately the center thereof.

さらに、補強枠11,11および12で囲まれ
た下方の空間には補強板13が張架されている。
この補強板13にはブロワケース14が固定され
ており、ブロワケース14内にはモータ15によ
つて回転されるブロワ16が収容されている。ま
た、パイプ10とブロワケース14とはパイプ1
7を介して連結されている。従つて、ブロワ16
が回転されるとブロワケース14内に負圧が生
じ、この負圧はパイプ17,10および両側パイ
プ9,9に導かれ吸着部材9aから空気が吸引さ
れた吸着部材9aはビルの壁面1aに吸着され
る。
Further, a reinforcing plate 13 is stretched in a lower space surrounded by the reinforcing frames 11, 11 and 12.
A blower case 14 is fixed to the reinforcing plate 13, and a blower 16 rotated by a motor 15 is housed within the blower case 14. In addition, the pipe 10 and the blower case 14 are the pipe 1
They are connected via 7. Therefore, blower 16
When the is rotated, negative pressure is generated in the blower case 14, and this negative pressure is guided to the pipes 17, 10 and the pipes 9, 9 on both sides, and the suction member 9a, which sucks air from the suction member 9a, is applied to the wall surface 1a of the building. It is adsorbed.

又、作業台7のフレーム7aの上端には支持板
7bが固定されており、この支持板7bに取り付
けられたプーリ18にワイヤ5を掛け回すことに
よりゴンドラ6全体が吊り下げられている。
Further, a support plate 7b is fixed to the upper end of the frame 7a of the workbench 7, and the entire gondola 6 is suspended by passing the wire 5 around a pulley 18 attached to the support plate 7b.

次に、以上のように構成された本実施例の動作
につき説明する。
Next, the operation of this embodiment configured as above will be explained.

まずビルの屋上に設けられたビーム3に設けら
れているホイストクレーンの走行車4から吊り下
げられているワイヤ5を操作し、ゴンドラ6をビ
ルの壁面1aに沿つて所定の位置まで下降させ
る。そして、モータ15を作動させることにより
ブロワ16を回転させ負圧を発生させ、吸着部材
9aを介して壁面1aに吸着させる。この状態で
は両側パイプ9,9とゴンドラ6とは相対的に移
動できる状態であるため、両側パイプ9は自重に
よつて下降した位置にあり、ゴンドラ6は左右の
両側パイプ9,9間の上方に配置される状態にあ
る。
First, the gondola 6 is lowered to a predetermined position along the wall surface 1a of the building by operating a wire 5 suspended from a traveling vehicle 4 of a hoist crane provided on a beam 3 provided on the roof of the building. Then, by operating the motor 15, the blower 16 is rotated to generate negative pressure, and the suction member 9a is adsorbed onto the wall surface 1a. In this state, the pipes 9 on both sides and the gondola 6 are relatively movable, so the pipes 9 on both sides are in a lowered position due to their own weight, and the gondola 6 is moved upward between the left and right pipes 9, 9. It is in a state where it is placed in.

従つてワイヤ5をゆるめればゴンドラ6は固定
状態にある両側パイプ9,9に沿つてわずかずつ
下降すること可能である。
Therefore, by loosening the wire 5, the gondola 6 can be lowered little by little along the fixed pipes 9, 9 on both sides.

ブロワ16が回転している間は吸着部材9aを
介して両側パイプ9,9が壁面1aに固定されて
いるため、ゴンドラ6は強風や清掃作業の反力に
よつて揺動することはない。又、ブロワ16の回
転によつてブロワケース14の壁面1aと反対側
の開口端からは空気が噴射されるが、この時生じ
る噴射推進力はゴンドラ6を壁面1a側に押し付
ける作用を果し、ゴンドラの揺動は更に押えられ
る。
While the blower 16 is rotating, the pipes 9 on both sides are fixed to the wall surface 1a via the suction member 9a, so the gondola 6 will not swing due to strong winds or reaction forces from cleaning work. Also, as the blower 16 rotates, air is injected from the open end of the blower case 14 on the side opposite to the wall surface 1a, and the injection propulsion force generated at this time acts to press the gondola 6 toward the wall surface 1a. The rocking of the gondola is further suppressed.

このようにして吸着部材9aによつて両側パイ
プ9,9を一たん固定した後には両側パイプ9,
9が案内となり、ワイヤ5をゆるめることにより
両側パイプ9,9の長さの範囲内においてゴンド
ラ6をわずかずつ下降させることができ、連続し
た動作で各種の作業を行なうことができる。
After the pipes 9, 9 on both sides are once fixed by the adsorption member 9a in this way, the pipes 9, 9 on both sides,
9 serves as a guide, and by loosening the wire 5, the gondola 6 can be lowered little by little within the length range of the pipes 9 on both sides, allowing various operations to be performed in a continuous motion.

そして、ゴンドラ6が両側パイプ9,9の下端
部近傍にまで達した場合には、第3図に鎖線で示
すように両側パイプ9,9の上端はゴンドラ6の
上端から遠く離れた状態となる。
When the gondola 6 reaches near the lower ends of the pipes 9, 9 on both sides, the upper ends of the pipes 9, 9 on both sides become far away from the upper ends of the gondola 6, as shown by chain lines in FIG. .

これで両側パイプ9,9の長さによつて規制さ
れる一回分の作業範囲内の作業が終了したことに
なる。
This completes the work within the range of work regulated by the lengths of the pipes 9, 9 on both sides.

この時に、ブロワ16の回転をゆるめるかある
いは止めれば吸着部材9aによる吸着状態は解消
されるため両側パイプ9,9は自由になり自重に
よつて第3図に鎖線で示す位置から実線で示す位
置へと下降し、次の作業範囲が定められ、ブロワ
16を回転させれば両側パイプ9,9が固定され
前述したと同様にして各種の作業を行なうことが
できる。以下同様の動作を繰り返し、ゴンドラ6
が下降し各種の作業が行なわれる。
At this time, if the rotation of the blower 16 is loosened or stopped, the suction state by the suction member 9a is canceled, and the pipes 9 on both sides become free and move from the position shown by the chain line in FIG. 3 to the position shown by the solid line due to their own weight. When the blower 16 is rotated, the pipes 9 on both sides are fixed, and various operations can be performed in the same manner as described above. Repeat the same action below and gondola 6
is lowered and various operations are performed.

以上の説明から明らかなように本考案によれば
ゴンドラは支持枠と相対的に移動できる構成とさ
れると共に、該支持枠はパイプ部材からなり、両
側パイプの上下端にブロワの回転により壁面に吸
着される吸着部材を備えているため、壁面に対し
てゴンドラを固定することができ、風や作業の反
力によつて揺動することがなくゴンドラに乗つた
作業者は安全な状態で高層ビルの壁面に対する各
種の作業を行なうことができる。さらに、支持枠
をゴンドラの上下移動のつど操作しなくても所定
の範囲でゴンドラを移動させることができるので
作業能率も向上する。しかも支持枠自体がパイプ
部材で形成されているから特別の配管系統が必要
でなく、構成が簡潔である。
As is clear from the above description, according to the present invention, the gondola is configured to be movable relative to the support frame, and the support frame is made of a pipe member, and blowers are installed at the upper and lower ends of the pipes on both sides so that the gondola is movable relative to the wall surface. Since it is equipped with a suction member, the gondola can be fixed to the wall, and the gondola will not sway due to wind or work reaction forces, allowing workers to safely reach the high rise. Various types of work can be performed on building walls. Furthermore, since the gondola can be moved within a predetermined range without having to operate the support frame each time the gondola is moved up and down, work efficiency is also improved. Moreover, since the support frame itself is formed of a pipe member, no special piping system is required, and the structure is simple.

【図面の簡単な説明】[Brief explanation of drawings]

第1図及び第2図は従来構造を説明する側面図
及び正面図、第3図及び第4図は本考案の一実施
例を示す側面図及び正面図である。 5……ワイヤ、6……ゴンドラ、7……作業
台、8……軸受、9……両側パイプ、9a……吸
着部材、10……配管、14……ブロワケース、
16……ブロワ。
1 and 2 are a side view and a front view illustrating a conventional structure, and FIGS. 3 and 4 are a side view and a front view illustrating an embodiment of the present invention. 5... Wire, 6... Gondola, 7... Workbench, 8... Bearing, 9... Pipes on both sides, 9a... Adsorption member, 10... Piping, 14... Blower case,
16...Blower.

Claims (1)

【実用新案登録請求の範囲】 ホイストクレーンによりビルの壁面に沿つて吊
り下げられる箱状の高層ビル用ゴンドラにおい
て、 パイプ部材を縦横に配置結合すると共に相互に
連通して形成した支持枠を前記ゴンドラに上下動
自在に設け、 前記支持枠におけるゴンドラの両側に位置する
パイプの両端を前記ビルの壁面方向に曲げると共
に該パイプの先端にパイプと連通していて且つビ
ルの壁面に吸着係合する吸着部材を設け、 前記支持枠にブロワを設けると共に、該ブロワ
と前記支持枠とを連通して構成したことを特徴と
する高層ビル用ゴンドラ。
[Claims for Utility Model Registration] In a box-shaped gondola for high-rise buildings that is suspended along the wall of a building by a hoist crane, the gondola has a support frame formed by vertically and horizontally arranging and connecting pipe members and communicating with each other. is provided to be movable up and down, and both ends of the pipe located on both sides of the gondola in the support frame are bent toward the wall of the building, and a suction member is provided at the tip of the pipe that communicates with the pipe and engages with the wall of the building by adsorption. A gondola for a high-rise building, characterized in that: a member is provided, a blower is provided on the support frame, and the blower and the support frame are communicated with each other.
JP12836781U 1981-08-29 1981-08-29 Gondola for high-rise buildings Granted JPS5833666U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12836781U JPS5833666U (en) 1981-08-29 1981-08-29 Gondola for high-rise buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12836781U JPS5833666U (en) 1981-08-29 1981-08-29 Gondola for high-rise buildings

Publications (2)

Publication Number Publication Date
JPS5833666U JPS5833666U (en) 1983-03-04
JPS6223955Y2 true JPS6223955Y2 (en) 1987-06-18

Family

ID=29922068

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12836781U Granted JPS5833666U (en) 1981-08-29 1981-08-29 Gondola for high-rise buildings

Country Status (1)

Country Link
JP (1) JPS5833666U (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08120611A (en) * 1994-10-20 1996-05-14 Nichifu Co Ltd Snow melting unit for road
JP2014169608A (en) * 2013-03-05 2014-09-18 Takenaka Komuten Co Ltd Work range curing equipment and curing equipment replacement method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS425740Y1 (en) * 1964-03-03 1967-03-22
JPS4970460A (en) * 1972-11-09 1974-07-08

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS425740Y1 (en) * 1964-03-03 1967-03-22
JPS4970460A (en) * 1972-11-09 1974-07-08

Also Published As

Publication number Publication date
JPS5833666U (en) 1983-03-04

Similar Documents

Publication Publication Date Title
JP2587684B2 (en) Construction wall construction equipment
US3517774A (en) Tower elevator
CN113911906A (en) Bridge gantry crane hanging bracket and use method thereof
CN108455449A (en) A kind of interior rail type mobile curtain wall Lift-on/Lift-off System
JPS6223955Y2 (en)
CN211198471U (en) Material lifting device for constructional engineering
KR102599944B1 (en) Overhead moving type gondola apparatus
JP4067096B2 (en) Electric balance arm device for outdoor wall work
CN212671145U (en) Small-size slide rail formula portable hanging flower basket
JP2580734Y2 (en) Mobile hanging scaffolding equipment
CN113479767A (en) Control automatic fitment construction facilities of accurate stable building curtain
JPS647153Y2 (en)
JP3009139U (en) Working gondola device
CN215888171U (en) Gate wall operation platform
KR102590849B1 (en) Gondola apparatus of double rail structure
CN216743499U (en) Device applied to mounting of support and hanger
CN211215956U (en) Dust device is used in concrete mixing plant environmental protection
JPS623480Y2 (en)
CN218754714U (en) Suspension device for mounting curtain wall board
CN217054270U (en) Automatic elevator shaft construction platform that climbs
CN215558540U (en) Movable hanging basket
JPH0570080A (en) Suspension type conveying device
JPS6019856Y2 (en) gondola
JPS6226044Y2 (en)
JP4342252B2 (en) elevator