- JPS62178622A JPS62178622A JP1763586A JP1763586A JPS62178622A JP S62178622 A JPS62178622 A JP S62178622A JP 1763586 A JP1763586 A JP 1763586A JP 1763586 A JP1763586 A JP 1763586A JP S62178622 A JPS62178622 A JP S62178622A
- Authority
- JP
- Japan
- Prior art keywords
- ground
- sheet pile
- pile
- jet water
- sheet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 17
- 239000002689 soil Substances 0.000 claims abstract 2
- 238000010276 construction Methods 0.000 claims description 11
- 238000000034 method Methods 0.000 abstract description 5
- 238000011084 recovery Methods 0.000 abstract description 3
- 101100334009 Caenorhabditis elegans rib-2 gene Proteins 0.000 abstract 2
- 239000004576 sand Substances 0.000 description 4
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
Abstract
Description
【発明の詳細な説明】 産業上の利用分野 この発明は矢板の建込み工法に関する。[Detailed description of the invention] Industrial applications This invention relates to a construction method for sheet piles.
発明が解決しようとする問題点
矢板の先端部からジェット水あるいは空気を混入したジ
ェット水を噴射し、矢板周囲の地盤を弛め、無振動、無
騒音で矢板を圧入する工法がある。ところがこの工法は
周囲の地盤を弛めるが、土砂を系外に搬出できないので
、矢板建込みの能率が必ずしも高くはなかった。また、
周囲の地盤に多量の水が圧入されて地盤沈下をもたらす
等の欠点があった。Problems to be Solved by the Invention There is a construction method in which jet water or jet water mixed with air is injected from the tip of the sheet pile, loosening the ground around the sheet pile, and press-fitting the sheet pile without vibration or noise. However, although this construction method loosens the surrounding ground, it does not allow the earth and sand to be carried out of the system, so the efficiency of building sheet piles was not necessarily high. Also,
There were drawbacks such as large amounts of water being forced into the surrounding ground, causing ground subsidence.
この発明は上記問題点に着目しなされたものである。そ
の目的は矢板建込みの能率が高く、周囲地盤への影響が
少ない矢板の建込み工法を提案するにある。This invention has been made in view of the above-mentioned problems. The purpose is to propose a method of erecting sheet piles that is highly efficient and has less impact on the surrounding ground.
問題点を解決するための手段
この矢板の建込み工法は、矢板先端部からジェット水を
噴射して周囲地盤を弛め矢板を建込む工法において、矢
板上下端に開口する吸引孔路を設け、前記地盤内に噴射
した後の滞留する水を土砂と共に吸引孔路を経由して地
盤上に回収することを特徴とする。Means to Solve the Problem This method of erecting sheet piles is a method of erecting sheet piles by injecting jet water from the tip of the sheet piles to loosen the surrounding ground. Suction holes opening at the top and bottom ends of the sheet piles are provided. The present invention is characterized in that the water that remains after being injected into the ground is collected on the ground together with earth and sand via a suction hole path.
第1図はこの工法で用いるコンクリート矢板1であり、
幅方向両側縁は断面コ形に折曲しリブ部2をなし、それ
ぞれの縁部に上下端に開口する吸引孔路3が穿設しであ
る。Figure 1 shows the concrete sheet pile 1 used in this construction method.
Both edges in the width direction are bent into a U-shaped cross section to form rib portions 2, and suction holes 3 opening at the upper and lower ends are perforated in each edge.
この矢板を地盤内に建込むには、第2図のごとく、矢板
1の表裏両面側の幅方向中央部に矢板1の下端部に開口
し、上下方向に長いジェノト水の噴射管4,4を取付け
、この管4を経由してシェツト水あるいは空気を混入し
たジェット水を地盤5内に噴射する。ジェット水は地盤
5を弛め、同時に下方向の応力を矢板に加えて、矢板1
を地盤5内に圧入する。この圧入の工程において、地盤
内で余剰となったジェット水は弛めた地盤の土砂と共に
吸引孔路3を経由して地盤5上に回収する。図において
、孔路3の上端開口部には回収管6が連結しである。In order to erect this sheet pile in the ground, as shown in Fig. 2, an opening is made at the lower end of the sheet pile 1 at the center in the width direction on both the front and back sides of the sheet pile 1, and vertically long jetting pipes 4, 4 for jetting water are opened. is installed, and jet water mixed with shet water or air is injected into the ground 5 via this pipe 4. The jet water loosens the ground 5 and at the same time applies downward stress to the sheet pile, causing the sheet pile 1 to loosen.
into the ground 5. In this press-in process, the jet water that is surplus in the ground is collected on the ground 5 through the suction hole path 3 together with the loosened earth and sand of the ground. In the figure, a recovery pipe 6 is connected to the upper end opening of the hole passage 3.
作用および考案の効果
この発明は以上の構成からなる。この建工み工法では、
地盤内に滞留する余分の水を回収するのて地山を過大に
乱すことがなく、地盤沈下が防止できる。また、水の回
収と同時に弛んだ地盤の土砂を搬出するので矢板の圧入
が容易となり建込みの能率が向上する。Operation and Effects of the Invention The present invention consists of the above-mentioned configuration. In this construction method,
By collecting excess water that remains in the ground, the ground is not disturbed excessively, and ground subsidence can be prevented. In addition, since loosened earth and sand from the ground are removed at the same time as water is recovered, it becomes easier to press in sheet piles, improving construction efficiency.
以上の通り、この工法によれば周囲地盤への影響を極小
に抑えて、能率よく矢板の建込みができる。As mentioned above, this construction method allows efficient erection of sheet piles with minimal impact on the surrounding ground.
第1図はこの工法で用いる矢板の斜視図、第2図はこの
工法による矢板の建込み状態を示す一部断面で示す斜視
図である。
1・・矢板、2・・リブ部、3・・吸引孔路、4・・噴
射管、5・・地盤、6・・回収管。
第1図
第2図FIG. 1 is a perspective view of a sheet pile used in this construction method, and FIG. 2 is a perspective view, partially in cross section, showing the state of erection of the sheet pile by this construction method. 1. Sheet pile, 2. Rib section, 3. Suction hole path, 4. Injection pipe, 5. Ground, 6. Recovery pipe. Figure 1 Figure 2
Claims (1)
弛め矢板を建込む工法において、矢板上下端に開口する
吸引孔路を設け、前記地盤内に噴射した後の滞留する水
を土砂と共に吸引孔路を経由して地盤上に回収すること
を特徴とする矢板の建込み工法。(1) In a construction method in which jet water is injected from the tip of the sheet pile to loosen the surrounding ground and erect the sheet pile, suction holes that open at the top and bottom ends of the sheet pile are provided, and the water that remains after being injected into the ground is removed from the soil. A construction method for building sheet piles, which is characterized in that the sheet piles are recovered onto the ground via a suction hole.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1763586A JPS62178622A (en) | 1986-01-29 | 1986-01-29 | Constructing work for sheet pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1763586A JPS62178622A (en) | 1986-01-29 | 1986-01-29 | Constructing work for sheet pile |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS62178622A true JPS62178622A (en) | 1987-08-05 |
Family
ID=11949322
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP1763586A Pending JPS62178622A (en) | 1986-01-29 | 1986-01-29 | Constructing work for sheet pile |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS62178622A (en) |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS534311A (en) * | 1976-07-02 | 1978-01-14 | Raito Kougiyou Kk | Method of continuous underground wall |
-
1986
- 1986-01-29 JP JP1763586A patent/JPS62178622A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS534311A (en) * | 1976-07-02 | 1978-01-14 | Raito Kougiyou Kk | Method of continuous underground wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS62178622A (en) | Constructing work for sheet pile | |
JP2863487B2 (en) | Pile pull-out method and device | |
JP3838011B2 (en) | Leakage recovery device in submersible construction method | |
JP2002004263A (en) | Ground improving method | |
RU2074924C1 (en) | Method for construction of combination drainage | |
JPS6120107Y2 (en) | ||
JPS6421119A (en) | Concrete sheet pile having water-conveyance hole and driving said pile | |
JPH1150456A (en) | H-shaped steel pile cutting method in ground | |
JP2650539B2 (en) | Construction method of underground diaphragm wall | |
JP2002146774A (en) | Soil-cement column-row wall construction method | |
JPH10195865A (en) | Method for constructing continuous underground wall, and press fitting plate | |
JPS62101715A (en) | Slime processor | |
JPS6145760B2 (en) | ||
JPH09228365A (en) | Washing method of steel material for underground continuous wall, and washing device | |
JPH08284163A (en) | Pile-driving method | |
JPH0416693A (en) | Liner plate | |
JP2778319B2 (en) | Slime removal method for excavation trench for underground wall construction | |
JPH0434116A (en) | Constructing method of underground structure body | |
JP4022867B2 (en) | Pre-drilling method for soft and viscous ground with high groundwater level | |
JP2610555B2 (en) | Drilling method for foundation ground and its drilling equipment | |
JP3022914U (en) | Square compound scoop | |
JPH0452319A (en) | Slope stabilization and retaining wall | |
JPH04146325A (en) | Slime removing device in pile hole | |
JPH04194191A (en) | Tunnel excavation method and device | |
JPS5925051B2 (en) | Earth retaining method |