JPS61294097A - Method of concrete placing construction in tunnel - Google Patents

Method of concrete placing construction in tunnel

Info

Publication number
JPS61294097A
JPS61294097A JP60135774A JP13577485A JPS61294097A JP S61294097 A JPS61294097 A JP S61294097A JP 60135774 A JP60135774 A JP 60135774A JP 13577485 A JP13577485 A JP 13577485A JP S61294097 A JPS61294097 A JP S61294097A
Authority
JP
Japan
Prior art keywords
concrete
invert
pier
tunnel
bottom floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP60135774A
Other languages
Japanese (ja)
Other versions
JPH0415880B2 (en
Inventor
佐賀 美夫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SAGA KOGYO KK
Original Assignee
SAGA KOGYO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SAGA KOGYO KK filed Critical SAGA KOGYO KK
Priority to JP60135774A priority Critical patent/JPS61294097A/en
Publication of JPS61294097A publication Critical patent/JPS61294097A/en
Publication of JPH0415880B2 publication Critical patent/JPH0415880B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明はトンネル内のコンクリート打設工法に関し、特
にトンネル内の底床部のコンクリートの打設工法に関す
るものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method for placing concrete in a tunnel, and particularly to a method for placing concrete in a bottom floor of a tunnel.

(従来の技術) トンネル内の底床部にコンクリートを打設するには従来
は、インバートフオームとその上に架設されている桟橋
が一体に移動されるようにしたコンクリート打設装置が
使用されていた。
(Prior art) Conventionally, to place concrete on the bottom floor of a tunnel, a concrete placing device was used in which the inverted form and the pier built on it were moved together. Ta.

このコンクリート打設装置は移動させる場合にトンネル
Aの側壁にハンチB(第8図)が必要である。そのため
従来はトンネル内の側面から天井にかけて二次覆工のア
ーチコンクリ−)Cを先に打設し、その後で底床部にイ
ンバートコンクリートDを打設しなければならなかった
When moving this concrete placing device, corbels B (Fig. 8) are required on the side walls of tunnel A. For this reason, conventionally, it was necessary to first place a secondary lining of arch concrete (C) from the sides to the ceiling of the tunnel, and then invert concrete (D) to be placed on the bottom floor.

(発明が解決しようとする問題点) 」−記した従来方法は次のような各種問題があった。(Problem to be solved by the invention) The conventional method described above had the following problems.

(イ)アーチコンクリートCを打設してからインバート
コンクリ−1−Dを打設するため、インバートコンクリ
ートDを打設するときにはトンネルAの底の上かいたん
でヘドロ化17てどろどろになる。そのためインバート
コンクリートDを打設する前にそのヘドロを除去しなけ
ればならずその作業が大変である。また底の排水作業も
しにくかった(口)底からの湧水により地11.が損傷
し易く、1−土盤の支持が弱まって、アーチ支保の支持
並びに強度が期待できない。
(a) Since the invert concrete 1-D is poured after the arch concrete C is poured, when the invert concrete D is poured, the bottom of the tunnel A is scratched and becomes sludge 17. Therefore, the sludge must be removed before pouring the invert concrete D, which is a difficult task. Also, it was difficult to drain the bottom (mouth) due to spring water coming from the bottom. 1- The support of the soil base is weakened, and the support and strength of the arch supports cannot be expected.

(ハ)ゆるみ領域の拡大が防+t−されにくいため変状
の9期収縮(11!!山の安定)が期待できない。
(c) Since the expansion of the loosened region is difficult to be prevented +t-, the 9th stage contraction of the deformity (11!! mountain stabilization) cannot be expected.

(闇題点を解決するための1段) 本発明の目的は二次覆工のアーチコンクリートCより先
に底床部のインバートコンクリートDを打設して従来の
諸問題を解決し、17かもインバートコンクリートDを
打設しながらトンネル内の切羽やベンチ部1の掘削とす
りの搬出を並行して行って品質の優れたトンネルを迅速
に施「できるようにすることにある。
(First step to solve the dark problems) The purpose of the present invention is to solve the conventional problems by pouring the invert concrete D for the bottom floor before the arch concrete C for the secondary lining, and to The purpose is to quickly construct a tunnel of excellent quality by simultaneously excavating the tunnel face and bench part 1 and carrying out the pickpocket while pouring invert concrete D.

本発明の方法は第1図〜第5図に示すようにトンネル内
の切羽又はベンチ部lの近くの底床部にインy<−1−
フオーム2 ヲ設a l/、同フオーム2の−ににそれ
と別体成形された桟橋3を架設し、この状態で底床部に
インバートコンクリ−1−4を打設し、この打設と並行
して又はその後で桟橋3の−1−を走行する搬送車両で
トンネル内のずりを搬出し、その後にインバートフォー
1.2の1一部桁5に沿って桟橋3を作業の進行方向に
移動し、この後でインバートフオーム2を桟橋3の移動
方向と同じ方向に移送し、この移送後にインバートコン
クリート4を打設し、以後、切羽又はベンチ部lの掘削
及びずりの搬出、桟橋3の移動、インバートフオーム2
の移動、インバートコンクリート4の打設を繰り返すよ
うにしたものである。
As shown in FIGS. 1 to 5, the method of the present invention is to apply an ink y<-1-
Form 2 was installed, a pier 3 formed separately from it was erected on the bottom of form 2, and in this state, invert concrete 1-4 was poured on the bottom floor, and in parallel with this pouring. or after that, transport the shear in the tunnel with a transport vehicle running on -1- of pier 3, and then move pier 3 in the direction of progress of the work along the 1 part girder 5 of invert four 1.2. After this, the invert form 2 is transferred in the same direction as the moving direction of the pier 3, and after this transfer, the invert concrete 4 is placed, and thereafter, the face or bench portion l is excavated, the shear is removed, and the pier 3 is moved. , invert form 2
The movement of the invert concrete 4 and the pouring of the invert concrete 4 are repeated.

(実 施 例) 第1図〜第5図において6は桟橋スロープ、7は前側の
桟橋用メインジヤツキ、8は後側の桟橋用メインジヤツ
キ、9は桟橋用移動ローラ、IOは自走装置、11はイ
ンバートフオーム用の前側メインジヤツキ、12はイン
バートフオーム用の後側メインジヤツキである。
(Example) In Figs. 1 to 5, 6 is the pier slope, 7 is the front pier main jack, 8 is the rear pier main jack, 9 is the pier moving roller, IO is the self-propelled device, and 11 is the pier main jack. A front main jack for the inverted form, and 12 a rear main jack for the inverted form.

(作 用) 本発明の施工は例えば次の順序で行なう。(for production) The construction of the present invention is carried out, for example, in the following order.

(1)桟m3の下のインバートフオーム2の下にインバ
ートコンクリート4を打設する。
(1) Place invert concrete 4 under the invert form 2 under the crosspiece m3.

(2)インバートコンクリート4を打設した後で次のよ
うにして桟橋3を移動する。
(2) After placing the invert concrete 4, move the pier 3 as follows.

イ、桟橋3のメインジヤツキ7.8を縮めて桟橋用移動
ローラ9をインバートフオーム2のL部桁5の1−に休
ませる。
B. The main jack 7.8 of the pier 3 is retracted to rest the pier moving roller 9 on the L section girder 5 1- of the invert form 2.

口、桟橋3のメインジヤツキ7.8を更に縮めて同ジヤ
ツキを浮かせる。
Further shorten the main jack 7.8 on pier 3 and let it float.

ハ、自走装置10により桟橋3をインバートフオーム2
の1一部桁5に沿って必要量だけ前方へ移動させる。
C. Invert form 2 of pier 3 by self-propelled device 10
Move it forward by the required amount along the 1st part of the digit 5.

二、所定位置で桟橋3のメインジヤツキ7.8を伸ばし
て桟橋3をセットする。
2. Set the pier 3 by extending the main jack 7.8 of the pier 3 at the specified position.

ホ、桟橋3の1−を走行する搬送車両で切羽又はベンチ
f41からすりを搬出する。このすり出し作業はコンク
リート打設と並行に施工することも可能である。
E. The pickpocket is carried out from the face or bench f41 by a transport vehicle running on 1- of the pier 3. This rolling out work can also be carried out in parallel with concrete pouring.

(3)上記イ〜ホの作業を繰り返し行なって次回のコン
クリート打設に必要な長さの分だけずり出しを行なう。
(3) Repeat operations I to E above to offset the length required for the next concrete pouring.

(4)次にインバートフオーム2を移動する。その移動
は次のようにして行なう。
(4) Next, move the invert form 2. The movement is performed as follows.

イ、底床部の既設レール13の前に前側レール14を継
ぎ足す。
B. Add the front rail 14 in front of the existing rail 13 on the bottom floor.

口、インバートフオーム2のメインジヤツキ11.12
を伸ばして同フオーム2を先に打設したインバートコン
クリート4から引き離す。
Mouth, main jack of invert form 2 11.12
Stretch and separate the form 2 from the invert concrete 4 that was placed earlier.

ハ、自走装置により次にインバートコンクリートを打設
する長さだけインバートフオーム2を移動させる。
C. The self-propelled device moves the invert form 2 by the length for which the next invert concrete is to be poured.

ニー 移動完7’ 後インバートフオーム川メインジヤ
ツキ11.12を縮めてイン/曳−トフオーム2をセッ
トする。
After completing the knee movement 7', shorten the invert form river main jack 11.12 and set the in/towing form 2.

ホ、インバートフオーム2の付属品(資金U)をセット
する。
E. Set the accessories (fund U) for invert form 2.

(5)インバートフオーム2の下にインバートコンクリ
ート4を打設する。
(5) Place invert concrete 4 under the invert form 2.

以上の工程を繰り返してトネルの底床部にインバートコ
ンクリート4を連続的に打設する。
The above steps are repeated to continuously cast invert concrete 4 on the bottom floor of the tunnel.

(発明の効果) 本発明は以上のようにインバートコンクリート4を二次
覆工のアーチコンクリートより先に打設するため次のよ
うな各種効果がある。
(Effects of the Invention) As described above, the present invention has the following various effects because the invert concrete 4 is cast before the secondary lining arch concrete.

(1)トンネルの底の土がヘドロ化しないためヘドロの
除去作業が必要ない。
(1) The soil at the bottom of the tunnel does not turn into sludge, so there is no need to remove sludge.

(2)トンネルの底から湧水しないため地山が損傷せず
、アーチ支保の支持並びに強度が確実になる。
(2) Since water does not spring up from the bottom of the tunnel, the ground is not damaged, and the support and strength of the arch support is ensured.

(3)ゆるみ領域の拡大が防1にされ、地山が安定する
(3) Expansion of the loose area is prevented to 1, and the ground is stabilized.

(4)インバートコンクリート4がアーチコンクリート
より先に打設されているため硬化したインバートコンク
リート4の上を二次覆工用型枠を移動させてセットでき
る。このためインバートコンクリート4とアーチの吹き
付はコンクリートが早期に切れ目なく連続する。
(4) Since the invert concrete 4 is placed before the arch concrete, the secondary lining formwork can be moved and set on the hardened invert concrete 4. Therefore, when spraying the invert concrete 4 and the arch, the concrete continues seamlessly at an early stage.

(5)桟橋3に接近又は重複した位置迄最終覆工用の型
枠をセットできるため、インバートコンクリート4とア
ーチコンクリートがより早期にリングを形成する。
(5) Since the formwork for the final lining can be set up to a position approaching or overlapping the pier 3, the invert concrete 4 and the arch concrete form a ring more quickly.

(6)上半盤の掘削、ズリ出しを桟橋を利用して並行し
て行なうことができるため、作業能率が非常に良く、施
工を迅速に短期間で行なうことができる。
(6) Since the excavation and scraping of the upper half can be done in parallel using the pier, work efficiency is very high and construction can be carried out quickly and in a short period of time.

(7)下半盤も上半盤上のバックホウにより掘削やすり
出しができるため作業が容易になる。
(7) The lower half can also be excavated and removed by the backhoe on the upper half, making the work easier.

(8)インバートフオームと桟橋が別体であるためイン
バートコンクリートの打設時や養生時に桟橋のトをトラ
・ンクなどを走行させてすりを搬出してもその振動がイ
ンバートフオームや打設されたインバートコンクリート
に伝わりにくい。このため打設や養生と並行してずりの
搬出を行なってもインバートコンクリートがきれいに什
−ヒる。
(8) Since the invert form and the pier are separate bodies, even if the pier is run on a truck or trunk during the pouring or curing of invert concrete and the pickpocket is carried out, the vibrations may be transmitted to the invert form or concrete. Difficult to transmit to inverted concrete. For this reason, even if the shear is removed at the same time as pouring and curing, the inverted concrete remains clean.

【図面の簡単な説明】[Brief explanation of drawings]

第1図〜第5図は本発明の詳細な説明図、第6図はイン
バートフオーム前側支承部と桟橋前側支承部の説明図、
第7図はインバートフオーム後側支承部と桟橋後側支承
部の説明図、第8図は従来の工法の説明図である。 lはベンチ部 2はインバートフオーム 3は桟橋 4はインバートコンクリート 5は−L部桁
Figures 1 to 5 are detailed explanatory views of the present invention, Figure 6 is an explanatory view of the inverted form front support part and the pier front support part,
FIG. 7 is an explanatory diagram of the inverted form rear support part and the pier rear support part, and FIG. 8 is an explanatory diagram of the conventional construction method. l is bench part 2 is inverted form 3 is pier 4 is inverted concrete 5 is -L part girder

Claims (1)

【特許請求の範囲】[Claims] トンネル内の底床部にインバートコンクリートを打設し
、その後でアーチの二次覆工用コンクリートを打設する
ようにしたトンネル内のコンクリート打設工法において
、底床部を掘削した後で切羽又はベンチの直近にの底床
部にインバートフォームを設置し、その上にインバート
フォームと別体成形された桟橋を架設し、この状態で底
床部にコンクリートを打設し、この打設と並行して又は
その後に桟橋の上を走行する搬送車両でトンネル内のず
りを搬出し、その後でインバートフォームの上部桁に沿
って桟橋を作業の進行方向に移動し、その後にインバー
トフォームを桟橋の移動方向と同じ方向に移送し、この
移送後に底床部にコンクリートを打設し、以後、トンネ
ルの掘削及びずりの搬出、桟橋の移動、インバートフォ
ームの移動、底床部へのコンクリートの打設を繰り返す
ようにしたことを特徴とするトンネル内のコンクリート
打設工法。
In a concrete casting method for tunnels, in which invert concrete is poured into the bottom floor of the tunnel, and then secondary lining concrete for the arch is poured, after the bottom floor has been excavated, the face or Invert foam was installed on the bottom floor closest to the bench, a pier formed separately from the invert foam was built on top of it, and in this state, concrete was poured on the bottom floor, and in parallel with this pouring. or after that, transport the shear in the tunnel using a transport vehicle running on the pier, then move the pier along the upper girder of the invert form in the direction of work progress, and then move the invert form in the direction of movement of the pier. After this transfer, concrete is placed on the bottom floor, and the process of excavating the tunnel, removing shear, moving the pier, moving the invert form, and placing concrete on the bottom floor is repeated. A concrete pouring method for tunnels, which is characterized by:
JP60135774A 1985-06-20 1985-06-20 Method of concrete placing construction in tunnel Granted JPS61294097A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP60135774A JPS61294097A (en) 1985-06-20 1985-06-20 Method of concrete placing construction in tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP60135774A JPS61294097A (en) 1985-06-20 1985-06-20 Method of concrete placing construction in tunnel

Publications (2)

Publication Number Publication Date
JPS61294097A true JPS61294097A (en) 1986-12-24
JPH0415880B2 JPH0415880B2 (en) 1992-03-19

Family

ID=15159542

Family Applications (1)

Application Number Title Priority Date Filing Date
JP60135774A Granted JPS61294097A (en) 1985-06-20 1985-06-20 Method of concrete placing construction in tunnel

Country Status (1)

Country Link
JP (1) JPS61294097A (en)

Also Published As

Publication number Publication date
JPH0415880B2 (en) 1992-03-19

Similar Documents

Publication Publication Date Title
CN105952482B (en) Self-propelled tunnel inverted arch lining trolley
CN108589737A (en) Underground speedy way hands over the construction method that section is built jointly with rail under a kind of major urban arterial highway
CN109518544A (en) A kind of subway precast track plate railway roadbed laying method
CN112610240A (en) Secondary lining construction process for mountain tunnel
CN105927247A (en) Large section full-automatic mechanical numeric control bogie and construction method thereof
JPS61294097A (en) Method of concrete placing construction in tunnel
JP3356048B2 (en) Construction method of elevated structure using building girder
CN109881592A (en) A kind of trapezoidal draining ditch construction method using single side formwork
CN114370070A (en) Construction method for post-cast strip settlement back-to-top support
CN205777506U (en) A kind of buttress early torn open more than 8m ground beam bottom board for span
CN107461209A (en) The construction method of mid-board top reserved steel bar in a kind of Tunnel Engineering
CN110685719A (en) Quick construction method for double-span simply-supported inverted arch trestle
JP2668648B2 (en) Construction method of underground structure and starting pit used for it
CN108277823A (en) A kind of construction method of subway platform layer totality
CN113565522B (en) Tunnel Boring Machine (TBM) station-passing bracket between mountain tunnels and station-passing method
RU97106133A (en) METHOD FOR ESTABLISHING A DEEP SUBMISSION METRO STATION
JPH03110293A (en) Construction of sloped tunnel in city
CN211734897U (en) Support structure attached to mountain cliff for supporting tunnel
JP3359144B2 (en) Pre-finishing method for tunnel invert concrete
CN111577319A (en) Tunnel double-trestle inverted arch construction method
JP2878254B1 (en) Open shield method
JP2007170095A (en) Construction method of underground structure, and jacking machine
EP0500221A1 (en) Method and apparatus for constructing long span, shell-shaped, substantially horizontal concrete structures
SU699105A1 (en) Foundation construction method
SU1465472A1 (en) Method of working water-saturated weak loose materials

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term