JPS6128680A - Rising construction method of transmission iron tower - Google Patents

Rising construction method of transmission iron tower

Info

Publication number
JPS6128680A
JPS6128680A JP14747084A JP14747084A JPS6128680A JP S6128680 A JPS6128680 A JP S6128680A JP 14747084 A JP14747084 A JP 14747084A JP 14747084 A JP14747084 A JP 14747084A JP S6128680 A JPS6128680 A JP S6128680A
Authority
JP
Japan
Prior art keywords
tower
steel pipe
steel
arm
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP14747084A
Other languages
Japanese (ja)
Other versions
JPH0320550B2 (en
Inventor
藤掛 和男
涌井 善吾
山田 昭二
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sanwa Koki Co Ltd
Original Assignee
Sanwa Koki Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sanwa Koki Co Ltd filed Critical Sanwa Koki Co Ltd
Priority to JP14747084A priority Critical patent/JPS6128680A/en
Publication of JPS6128680A publication Critical patent/JPS6128680A/en
Publication of JPH0320550B2 publication Critical patent/JPH0320550B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)
  • Electric Cable Installation (AREA)
  • Suspension Of Electric Lines Or Cables (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 送電用鉄塔において、近年都市近郊の過密化に伴い、既
設の送電線に接近して建造物が建設される場合に送電線
と建造物との離隔距離が不足することから、送電線の高
さを更に高い位置に移設する必要が生ずる。
[Detailed Description of the Invention] [Industrial Application Field] In recent years, with the increasing density in urban areas, power transmission towers are being constructed in close proximity to existing power transmission lines. Due to the insufficient separation distance between the lines, it becomes necessary to relocate the power transmission lines to a higher position.

本発明は、かかる事情に際し、塔高を増加させる鉄塔の
かさ」二げ工法に関するものである。
The present invention relates to a construction method for increasing the height of a steel tower in such a situation.

〔従来技術と問題点〕[Prior art and problems]

従来、この種のかさ上げ工法には、鉄塔の外側に枠組構
成体を設け、上部鉄塔を支承する上部梁をシリンダによ
りせり上げたり、或いは枠組構成体の内部に設けた昇降
台−上に乗せた鉄塔上部を下方よりせり上げたりして、
その下方に鉄塔下部を取付りる工法等がみられる(特公
昭50−32526号、特公昭48−26614号公報
)。
Conventionally, this type of raising method involves installing a frame structure on the outside of the steel tower and raising the upper beam that supports the upper steel tower using a cylinder, or placing it on a lifting platform provided inside the frame structure. The upper part of the steel tower was raised from below,
There are methods of attaching the lower part of the steel tower below it (Japanese Patent Publication No. 50-32526, Japanese Patent Publication No. 48-26614).

しかし、これらの工法では、特に枠組構成体を鉄塔の外
側に設けるため、大きな作業用地を必要とし、かかる用
地のない狭い場所又は用地確保の困難な場合にはかさ上
げ作業の施行が不可能である欠点があった。
However, these construction methods require a large work site, especially since the framework structure is installed outside the tower, and it is impossible to carry out the raising work in narrow spaces where such land is not available or in cases where it is difficult to secure land. There was a certain drawback.

また、枠組構成体の組立てに時間がかかることがら°、
かさ上げ作業のために長時間停電するか、バイパス送電
のための仮鉄塔の建設を必要とする欠点があった。
In addition, since it takes time to assemble the framework structure,
The disadvantages were that the raising work required long power outages or the construction of temporary towers for bypass power transmission.

〔問題点を解決するための手段〕[Means for solving problems]

本発明は上記欠点を解消するもので、その手段は、既設
鉄塔の塔体頂部に取付けた上部滑車ロープ等により単位
鋼管を順次連結しながら塔芯に沿い頂部までせり上げ、
地線を塔体頂部のアームに一時移設し、所定本数の単位
鋼管の連結により構成される単柱鋼管塔を鉄塔の下方に
取付けた下部滑車ロープ等により塔頂よりさらに所定高
さまでせり上げ、単柱鋼管塔の最下部に接続した単位鋼
管の下端を基礎コンクリート社固定し、鉄塔のかさ上げ
作業後、単柱鋼管塔を鉄塔の対辺材により固定支持し、
単柱鋼管塔に地線を移設すると共にアームを取付け、該
アームに鉄塔の旧アームの電線を移設し、旧アーム及び
旧アーム部分の塔体を解体除去することにあり、せり上
げた単柱鋼管塔をかさ上げ鉄塔として使用するものであ
る。
The present invention solves the above-mentioned drawbacks, and its means include raising unit steel pipes along the tower core to the top while sequentially connecting unit steel pipes using an upper pulley rope or the like attached to the top of the tower body of an existing steel tower.
The ground wire was temporarily relocated to the arm at the top of the tower, and the single-column steel pipe tower, which was constructed by connecting a predetermined number of unit steel pipes, was raised to a predetermined height from the top of the tower using a lower pulley rope attached to the bottom of the tower. The lower end of the unit steel pipe connected to the lowest part of the single-column steel pipe tower is fixed by the basic concrete company, and after the tower is raised, the single-column steel pipe tower is fixed and supported by the opposing side members of the steel tower.
The purpose was to relocate the ground wire to the single-column steel pipe tower and install an arm, relocate the electric wires from the old arm of the steel tower to the arm, and dismantle and remove the old arm and the tower body of the old arm part. A steel pipe tower is used as a raised steel tower.

〔実施例〕〔Example〕

本発明の実施例を図面を参照して説明する。 Embodiments of the present invention will be described with reference to the drawings.

第1図において、1は既設鉄塔であり、この鉄塔1内に
単柱鋼管塔2を建設する。
In FIG. 1, 1 is an existing steel tower, and a single column steel pipe tower 2 will be constructed within this steel tower 1.

而して、この単柱鋼管塔2は次の工法により組立てられ
る。
This single-column steel pipe tower 2 is assembled by the following construction method.

(a)第2図に示すように、鉄塔1の塔体頂部に上部滑
車3を吊設すると共に鉄塔1内の作業の邪魔になる対辺
材を取外す。
(a) As shown in FIG. 2, the upper pulley 3 is suspended from the top of the tower body of the steel tower 1, and the opposing sap material that gets in the way of work inside the steel tower 1 is removed.

(b)地上に設置した上部巻上げ機4の巻胴から繰り出
した上部ワイヤーロー15を案内滑車を介して上記の上
部滑車3に掛は回して鉄塔1内に吊下する。
(b) The upper wire row 15 unwound from the winding drum of the upper hoist 4 installed on the ground is hooked onto the above-mentioned upper pulley 3 via a guide pulley and is suspended within the steel tower 1.

(c)鉄塔1内の地上に所定長さの単位鋼管2aを必要
本数搬入する。
(c) The required number of unit steel pipes 2a of a predetermined length are carried onto the ground within the steel tower 1.

(d)鉄塔1の塔体頂部力)ら塔高の約1/3下った位
置でかつ水平材1aのある個所と、地上から塔高の約1
/3上った同様の個所に夫々ガイド機構6を取付ける。
(d) At a position approximately 1/3 of the tower height below the tower body top force of steel tower 1 and where the horizontal member 1a is located, and approximately 1 tower height from the ground.
/3 Attach the guide mechanisms 6 to the same locations up respectively.

このガイド機構6は第6図に示すように、複数のp゛イ
ドローラー6a有する枠体6bに締結した4本の支持ワ
イヤーロープ6cの他端を、ガイドローラ6aが鉄塔1
の中心に位置するように水平材1aの四隅に締結する。
As shown in FIG. 6, in this guide mechanism 6, a guide roller 6a connects the other end of four support wire ropes 6c fastened to a frame 6b having a plurality of pid rollers 6a to a steel tower.
Fasten it to the four corners of the horizontal member 1a so that it is located at the center of the horizontal member 1a.

(e)上部ワイヤーロープ5の吊下端に上記搬入された
単位鋼管2aの上端を結着し、上部巻上げ機4を操作し
て単位鋼管2aを吊上げ、その下に次の単位鋼管2aを
フランジ結合しながら」1記ガイドローラー6a内を通
して順次結合吊上げ、上部ワイヤーローブ50巻き代限
度(塔体頂部近く)まで吊上げる。
(e) Tie the upper end of the carried-in unit steel pipe 2a to the hanging end of the upper wire rope 5, operate the upper hoisting machine 4 to lift the unit steel pipe 2a, and flange-join the next unit steel pipe 2a below it. While passing through the guide rollers 6a in item 1, the wires are successively connected and lifted until the upper wire lobe 50 winding allowance limit (near the top of the tower body) is reached.

(f)第3図に示すように、鉄塔1の地上から適宜11
〕1さ位i+Y (1(l m程度)で、水平lit 
1 aのある個所の対角に夫々下部滑車7を吊下げ、地
上に設置した2個の下部巻上げ機8のを胴から上記所定
本数の単位鋼管2aを連結した単柱鋼管塔2をせり上げ
る下部ワイヤーロープ9を繰り出し、案内滑車を介して
」−記下部沿車7に掛は回わして鉄塔1内に吊下げる。
(f) As shown in Figure 3, from the ground of steel tower 1, 11
] 1 degree i + Y (1 (about l m), horizontal lit
1 Lower pulleys 7 are suspended diagonally from a location a, and a single-column steel pipe tower 2 connected with the predetermined number of unit steel pipes 2a is raised from the shell of two lower hoists 8 installed on the ground. The lower wire rope 9 is let out, looped around the lower track 7 via the guide pulley, and suspended within the steel tower 1.

(g)塔体頂部のアーム1bに仮アームIOを取付け、
この仮アーム10に塔頂の地線11を一時移設し、塔頂
を解体除去する。
(g) Attach temporary arm IO to arm 1b at the top of the tower body,
The ground wire 11 at the tower top is temporarily relocated to this temporary arm 10, and the tower top is dismantled and removed.

(h)下部ワイヤーロープ9の各先端のフックを単柱鋼
管塔2の最下部の単位鋼管2aの下部に掛け、(この際
、上部滑車3を取除く)下部巻上げtJ18を操作して
小柱鋼管2を塔頂より上方へせり上げる。
(h) Hook the hooks at each tip of the lower wire rope 9 to the lower part of the lowest unit steel pipe 2a of the single-column steel pipe tower 2 (at this time, remove the upper pulley 3), and operate the lower hoisting tJ18 to Raise the steel pipe 2 above the top of the tower.

(i)所定高さまでのせり上げには、単柱鋼管塔2の最
下端に単位鋼管2aを必要率継ぎ足し、この単位鋼管2
aを予め地上に打設した基礎コンクリート15のアンカ
ーボルトに固定する。
(i) To raise the height to a predetermined height, add unit steel pipes 2a to the lowest end of the single-column steel pipe tower 2 at the required rate, and
A is fixed to anchor bolts of foundation concrete 15 cast on the ground in advance.

(j)第4図に示すように、鉄塔1の所要個所に対辺)
fAICを取付け、この対辺材1cに単柱鋼管塔2を塔
芯に位置するように固定する。
(j) As shown in Figure 4, the opposite side is placed at the required location on the steel tower 1)
The fAIC is attached, and the single-column steel pipe tower 2 is fixed to the opposite side member 1c so as to be located at the tower core.

(k)単柱鋼管塔2の頂部に地線11を移設する。(k) Relocate the ground wire 11 to the top of the single-column steel pipe tower 2.

(j2)片側送電回線を停止して、単柱鋼管塔2に片側
の各アーム12,13.14を取付け、これに旧アーム
の各電線を移設する。
(j2) Stop the power transmission line on one side, attach each arm 12, 13, and 14 on one side to the single-column steel pipe tower 2, and transfer each electric wire of the old arm to this.

上記旧アームを解体除去し、上記片側送電回線を復旧す
る。
The old arm will be dismantled and removed, and the one-sided power transmission line will be restored.

(m)他側Jス゛【h回船+jfについて、上記(p)
と同様の作業をする。
(m) Other side J゛ [h times + jf, above (p)
Do the same work.

(n)両送型回線の旧アーム部分の塔体を解体除去゛J
る。
(n) Dismantle and remove the tower body of the old arm part of the double-feed line.
Ru.

以上により、第5図に示すかさ上げ鉄塔が完成Jる。Through the above steps, the raised steel tower shown in Fig. 5 is completed.

〔すj 果〕[Suj fruit]

(a)既設鉄塔を、その敷地内で安全かつ短期間にかさ
」−げすることができる。
(a) Existing steel towers can be raised safely and quickly within the site.

(b)やぐら形の鉄塔部分が単柱術管塔の最下段のアー
ムの下方部分を包囲し、かつ対辺月で単柱鋼管塔を固定
支持するので、やくら形の鉄塔部分が水平荷重を分担し
、車柱鋼管塔は垂直荷重のみを分担すればよく、したが
って、その外径は小さくて済み経済的である。
(b) The tower-shaped steel tower section surrounds the lower part of the lowest arm of the single-column steel pipe tower, and the opposite side supports the single-column steel pipe tower, so the tower-shaped steel tower section absorbs horizontal loads. The vehicle column steel pipe tower only needs to share the vertical load, so its outer diameter can be small and economical.

(C)小径の単柱鋼管塔にアームが取付のられるので、
その張り出し巾は旧鉄塔部分のアームの張り出し巾より
小さくすることが可能であり、電線下用地も少なくて済
む。
(C) Since the arm is attached to a small-diameter single-column steel pipe tower,
Its overhang width can be made smaller than the arm overhang width of the old steel tower, and less land is required under the electric wires.

(d)やぐら形の鉄塔部分で風向きに対する乱流が起る
ので、単柱鋼管塔に整流が起生じ難く、したがって振動
の発生を抑制し得る。
(d) Since turbulence with respect to the wind direction occurs in the tower-shaped steel tower portion, rectification is less likely to occur in the single-column steel pipe tower, and therefore the occurrence of vibration can be suppressed.

なお、本発明においては、既設鉄塔のかさ上げ工法につ
いて説明したが、上記のように、基礎コンクリートに固
設した単柱鋼管塔の下半部をやぐら形の鉄塔で包囲し、
かつ鋼管基を対辺祠で支持し、単柱鋼管塔は垂直荷重を
、やぐら形の鉄塔が水平荷重を夫々分担する構成となっ
ているので、これを新設の送電用鉄塔を建設する場合の
構成に適用することも可能である。
In addition, in the present invention, the method of raising the height of an existing steel tower has been described, but as mentioned above, the lower half of a single-column steel pipe tower fixed to the foundation concrete is surrounded by a tower-shaped steel tower.
In addition, the steel pipe base is supported by the opposite side shrine, and the single-column steel pipe tower takes the vertical load, and the tower-shaped steel tower takes the horizontal load, so this is the configuration when constructing a new power transmission tower. It is also possible to apply it to

【図面の簡単な説明】[Brief explanation of drawings]

第1図は既設鉄塔の正面図、第2図〜第4図は本発明に
係るかさ上げ工法の実施例の説明図、第5図はかさ上げ
完了後の正面図、第6図はガイド機構の説明図である。 1・・・既設鉄塔、2・・・単柱鋼管塔、2a・・・単
位鋼管、3・・・上部滑車、4・・・上部巻上げ機、5
・・・上部ワイヤーローブ、6・・・ガイド機構、7・
・・下部滑車、8・・・下部巻上げ機、9・・・下部ワ
イヤーロープ、10・・・仮アーム、11・・・地線、
12,13,14・・・アーム、15・・・基礎コンク
リート。 特 許 出 願 人  山加電業株式会社同     
 三和鋼器株式会社 第3因 筑4図  第5 ・ 圓
Figure 1 is a front view of the existing steel tower, Figures 2 to 4 are explanatory diagrams of an embodiment of the raising method according to the present invention, Figure 5 is a front view after the raising is completed, and Figure 6 is the guide mechanism. FIG. 1... Existing steel tower, 2... Single column steel pipe tower, 2a... Unit steel pipe, 3... Upper pulley, 4... Upper hoisting machine, 5
... Upper wire lobe, 6... Guide mechanism, 7.
...Lower pulley, 8...Lower hoist, 9...Lower wire rope, 10...Temporary arm, 11...Ground wire,
12, 13, 14...Arm, 15...Foundation concrete. Patent applicant: Yamaka Dengyo Co., Ltd.
Sanwa Koki Co., Ltd. Figure 3 Inchiku 4 No. 5 En

Claims (1)

【特許請求の範囲】[Claims] 既設鉄塔の塔体頂部に取付けた上部滑車ロープ等により
単位鋼管を順次連結しながら塔芯に沿い頂部までせり上
げ、地線を塔体頂部のアームに一時移設し、所定本数の
単位鋼管の連結により構成される単柱鋼管塔を鉄塔の下
方に取付けた下部滑車ロープ等により塔頂よりさらに所
定高さまでせり上げ、単柱鋼管塔の最下部に接続した単
位鋼管の下端を基礎コンクリートに固定し、鉄塔のかさ
上げ作業後、単柱鋼管塔を鉄塔の対辺材により固定支持
し、単柱鋼管塔に地線を移設すると共にアームを取付け
、該アームに鉄塔の旧アームの電線を移設し、旧アーム
及び旧アーム部分の塔体を解体除去することを特徴とす
る送電用鉄塔のかさ上げ工法。
The unit steel pipes are successively connected using an upper pulley rope attached to the top of the existing steel tower, and raised along the tower core to the top.The ground wire is temporarily relocated to the arm at the top of the tower, and a predetermined number of unit steel pipes are connected. A single-column steel pipe tower consisting of is raised from the top of the tower to a specified height using a lower pulley rope attached to the bottom of the tower, and the lower end of the unit steel pipe connected to the lowest part of the single-column steel pipe tower is fixed to the foundation concrete. , After raising the height of the steel tower, the single-column steel pipe tower is fixedly supported by the opposing side members of the steel tower, the ground wire is transferred to the single-column steel pipe tower, and an arm is attached, and the electric wire of the old arm of the steel tower is transferred to the arm, A method of raising the height of a power transmission tower, which is characterized by dismantling and removing the old arm and the tower body of the old arm part.
JP14747084A 1984-07-18 1984-07-18 Rising construction method of transmission iron tower Granted JPS6128680A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14747084A JPS6128680A (en) 1984-07-18 1984-07-18 Rising construction method of transmission iron tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14747084A JPS6128680A (en) 1984-07-18 1984-07-18 Rising construction method of transmission iron tower

Publications (2)

Publication Number Publication Date
JPS6128680A true JPS6128680A (en) 1986-02-08
JPH0320550B2 JPH0320550B2 (en) 1991-03-19

Family

ID=15431110

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14747084A Granted JPS6128680A (en) 1984-07-18 1984-07-18 Rising construction method of transmission iron tower

Country Status (1)

Country Link
JP (1) JPS6128680A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006316409A (en) * 2005-05-10 2006-11-24 Kansai Electric Power Co Inc:The Compound steel pipe steel tower and construction method therefor
JP2012012892A (en) * 2010-07-02 2012-01-19 Tokyo Electric Power Co Inc:The Reconstruction method of existing steel tower

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006316409A (en) * 2005-05-10 2006-11-24 Kansai Electric Power Co Inc:The Compound steel pipe steel tower and construction method therefor
JP2012012892A (en) * 2010-07-02 2012-01-19 Tokyo Electric Power Co Inc:The Reconstruction method of existing steel tower

Also Published As

Publication number Publication date
JPH0320550B2 (en) 1991-03-19

Similar Documents

Publication Publication Date Title
CN111039194A (en) Super-large crane final assembly process
CN210012524U (en) Hoisting device for indoor hoisting of prefabricated combined pipeline
CN110065892B (en) Hoisting device and hoisting method for indoor hoisting of prefabricated combined pipeline
CN210460016U (en) Integrated form single power lift material platform
JP2008248664A (en) Hoisting method of curtain wall
CN213417832U (en) Enclosing purlin mounting structure
JPS6128680A (en) Rising construction method of transmission iron tower
JPH10195826A (en) Bridge construction method and device thereof
JP3700306B2 (en) Wind power generator construction method
JP2004036235A (en) Construction method for heightening steel tower
JPS5935822B2 (en) Construction elevator installation method
CN2292781Y (en) Self-lifting device of lifter for gantry construction
JP2720339B2 (en) Cable laying method
CN205555870U (en) Hoisting equipment for engineering
JP3297196B2 (en) Composite balance and method for loading heavy objects using composite balance
JPS6222904A (en) Method of lifting steam drum
CN210012530U (en) Portable two rope hoist device of prefabricated combination pipeline of hoist and mount
CN113772531B (en) Hoisting equipment and construction mode thereof
CN113789725B (en) Suspension bridge construction method and lifting device
JP2817208B2 (en) Construction method of rack steel frame
CN2144641Y (en) Self-erecting crane
JPH11209026A (en) Installation method for elevator
CN115321380A (en) Super high-rise roof steel pipe hoisting equipment and construction method thereof
JPH07197694A (en) Method of construction of connection type columnar body
JPS6035512B2 (en) Erection equipment for tower-like structures