JPS6123350B2 - - Google Patents

Info

Publication number
JPS6123350B2
JPS6123350B2 JP53035317A JP3531778A JPS6123350B2 JP S6123350 B2 JPS6123350 B2 JP S6123350B2 JP 53035317 A JP53035317 A JP 53035317A JP 3531778 A JP3531778 A JP 3531778A JP S6123350 B2 JPS6123350 B2 JP S6123350B2
Authority
JP
Japan
Prior art keywords
groove
stage
rock
jet water
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP53035317A
Other languages
Japanese (ja)
Other versions
JPS54127801A (en
Inventor
Tsutomu Morie
Juji Ono
Takahito Kusada
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP3531778A priority Critical patent/JPS54127801A/en
Publication of JPS54127801A publication Critical patent/JPS54127801A/en
Publication of JPS6123350B2 publication Critical patent/JPS6123350B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 <産業上の利用分野> この発明は高圧ジエツト水を岩盤に噴射して溝
を掘削し、削岩岩石採掘等を行うようにした溝掘
削方法に関する発明であり、特に、数千気圧の高
圧ジエツト水により岩盤等に溝を掘削して地盤を
弱所化し、続いて破砕作用を与え、これを反復し
て溝を形成し、トンネル掘削、岩石切出し等を行
うようにした高圧ジエツト水による溝掘削方法に
係る発明である。
[Detailed Description of the Invention] <Industrial Application Field> This invention relates to a method for excavating a trench by injecting high-pressure jet water into a bedrock to perform rock drilling, etc. , high-pressure jet water of several thousand atmospheres is used to excavate grooves in rock, etc. to weaken the ground, then apply a crushing action, and this process is repeated to form grooves and perform tunnel excavation, rock cutting, etc. This invention relates to a trench excavation method using high-pressure jet water.

<従来技術> 従来、岩石採掘、トンネル掘削においては発
破、さく岩等の種々の手段が溝ぜられてきたが、
いづれも激しい衝撃振動が伴うため壁面の岩盤が
損傷を受け、肌落ちや崩落の膚があり、事後施工
にも補修ライニング等を必要とし、工数も多く、
期間も長くかかり、コスト高になる不利点があつ
た。
<Prior art> Conventionally, various methods such as blasting and rock drilling have been used in rock mining and tunnel excavation.
In both cases, the rock of the walls was damaged due to severe shock vibrations, and there were areas where the walls fell off and collapsed, and subsequent construction required repair lining, etc., which required a lot of man-hours.
The disadvantages are that it takes a long time and costs are high.

又、危険も多く、振動に伴う落盤等も生ずる欠
点があり、更に、衝撃音や振動音も大きく、作業
環境を著るしく阻害する難点もあつた。
In addition, there are many dangers, and there are drawbacks such as cave-ins caused by vibrations.Furthermore, the impact noise and vibration noise are large, which significantly impedes the working environment.

ところで、水を高圧にして噴射すると、その動
圧は機械的エネルギーに変換され、当該高圧ジエ
ツト水を固体に衝突させた場合、そのインパクト
作用により極めて静粛に固体を破砕、切削するこ
とが出来る。
By the way, when high-pressure water is injected, the dynamic pressure is converted into mechanical energy, and when the high-pressure jet water collides with a solid, the impact action can crush and cut the solid very quietly.

<発明が解決しようとする問題点> 而して、これまでの高圧水技術によればジエツ
ト水の吐水圧は50〜400Kg/cm2程度であり、その
ためインパクトによる固体破砕、切削の態様は採
炭、スラグ洗浄、断層部の岩盤処理等に利用され
る程度のものであり、岩盤掘削を行うことは不可
能であつた。
<Problems to be solved by the invention> According to the conventional high-pressure water technology, the discharge pressure of jet water is about 50 to 400 kg/ cm2 , and therefore the mode of solid crushing and cutting by impact is similar to coal mining. It was only used for cleaning slag, treating rock at faults, etc., and it was impossible to excavate rock.

さりながら、近時高圧ジエツト水の吐水圧は数
千気圧まで高めることが技術的に可能になり、設
計によつては花崗岩等の硬岩盤を切削することも
出来るようになつた。
However, recently it has become technologically possible to increase the discharge pressure of high-pressure jet water to several thousand atmospheres, and depending on the design, it has become possible to cut hard rock such as granite.

この発明の目的は前述岩盤に対する掘削の問題
点を解決すべき技術的課題とし、上記高圧力水の
高圧ジエツト化技術を用い、高圧ジエツト水によ
り指向された方向のみの破砕を行わせるように
し、静粛に、安定して硬質岩盤を切削破砕するよ
うにして建設産業における掘削技術利用分野に益
する優れた高圧ジエツト水による溝掘削方法を提
供せんとするものである。
The object of this invention is to solve the above-mentioned problem of excavation of rock, and to use the above-mentioned high-pressure jetting technology to cause the high-pressure jet water to crush only in the oriented direction. It is an object of the present invention to provide an excellent trench excavation method using high-pressure jet water that quietly and stably cuts and crushes hard rock, thereby benefiting the field of application of excavation technology in the construction industry.

<問題点を解決するための手段・作用> 上述目的に沿い先述特許請求の範囲を要旨とす
るこの発明の構成は前述問題点を解決するため
に、硬質岩盤を掘削するに際し高圧ジエツト水を
予定の掘削大溝線に沿つて集中的に細条化して岩
盤の所定部位に噴射衝突させて細条の第1段の先
行切削により溝を掘削形成し、先行切削溝部の地
盤を弱所化させ、第1段の先行切削溝を設定深度
に形成後、さく岩、高圧水ジエツト、デイスクカ
ツター等により該第1段の先行切削溝による弱所
化された部位を第2段的に破砕して大溝化し、形
成された大溝内にノズルを臨ましめて再び高圧ジ
エツト水を噴射衝突させて以下その工程を反復さ
せることにより極めて安全な状態で地肌を痛める
ことなく、実質的に無振動に溝を形成させる技術
的手段を溝じたものである。
<Means/effects for solving the problems> In order to solve the above-mentioned problems, the structure of the present invention, which is based on the above-mentioned claims in accordance with the above-mentioned object, is to use high-pressure jet water when excavating hard rock. excavation of the groove along the major groove line and inject it into a predetermined part of the rock to excavate and form a groove by the first stage of preliminary cutting of the strip, weakening the ground in the pre-cut groove part, After forming the first stage pre-cut groove to a set depth, the weakened area created by the first stage pre-cut groove is crushed in a second stage using rock drilling, high-pressure water jet, disc cutter, etc. A large groove is formed, the nozzle is faced into the formed large groove, and high-pressure jet water is sprayed and collided with it again, and the process is repeated. By doing so, the groove is formed in an extremely safe condition without damaging the skin and with virtually no vibration. It is a technical means to do so.

<実施例> 次にこの発明の実施例を図面に従つて説明すれ
ば以下の通りである。
<Example> Next, an example of the present invention will be described below with reference to the drawings.

第1、2図に示す様に所定のブーム1の先端に
複数のノズル2、2……(当該実施例では5ユニ
ツト)を岩盤の破砕面に於て設定幅よりやや広く
外側のノズル2″を外向きに開角して設け、それ
らの中位のノズル2′は中掘用として破砕面に向
くように形成させて設け、ブーム1内の導孔3を
介して図示しない高圧水源に接続するようにして
おく。
As shown in Figs. 1 and 2, a plurality of nozzles 2, 2... (5 units in this embodiment) are installed at the tip of a predetermined boom 1, and the nozzles 2'' are slightly wider than the set width on the crushed surface of the rock. The middle nozzle 2' is formed to face the fracture surface for medium excavation, and is connected to a high-pressure water source (not shown) through a guide hole 3 in the boom 1. Make sure to do so.

而して、ブーム1をして設定溝を掘削する岩盤
4の部位に対し第2図に示す様に臨ませて高圧力
水をブーム1に送給すると、高圧力水は各ノズル
2、2……より高圧ジエツト水となつて矢印に示
す様に噴出し破砕面に衝突し、その高速動圧のエ
ネルギーにより各ノズル2、2……よりの高圧ジ
エツト水は設定通り細条化され、集中化され、イ
ンパクト作用により岩盤4を掘孔して先行する第
1段の切削溝5、5……をそのエネルギー範囲の
深度に形成する。
Then, when the boom 1 is placed facing the part of the rock 4 where the setting groove is to be excavated as shown in Fig. 2 and high pressure water is fed to the boom 1, the high pressure water flows through each nozzle 2, 2. ...It becomes higher-pressure jet water and blows out as shown by the arrow, colliding with the fracture surface, and due to the energy of the high-speed dynamic pressure, the high-pressure jet water from each nozzle 2, 2... is fragmented and concentrated as set. is applied, and the impact action excavates the rock 4 to form the preceding first-stage cutting grooves 5, 5, . . . to a depth within the energy range.

この場合、各ノズル2についてはその噴出高圧
水ジエツトの方向を予定の掘削大溝の形成線6、
6の中にあるようにして確実に後段の掘削に際し
ブーム1が挿入され易いように5ユニツトのノズ
ル2、2……のうち外側ノズル2″を設定通り外
方に向け、内側の中掘りノズル2′は大溝形成線
6、6の中間に指向するようにしておく。
In this case, for each nozzle 2, the direction of the high-pressure water jet is set at the formation line 6 of the planned excavation groove.
In order to ensure that the boom 1 is inserted easily when digging the latter stage, the outer nozzle 2'' of the 5 unit nozzles 2, 2... is directed outward as set, and the inner medium digging nozzle is 2' is oriented midway between the large groove forming lines 6, 6.

そして、このような先行する第1段の切削溝
5、5……の切削を第2図の紙面垂直方向に、即
ち、第3図矢印方向にブーム1を横向に移動しつ
つ予定の掘削幅を成す大溝形成線6、6……に沿
つて第1段的に形成していく。
Then, the cutting grooves 5, 5, etc. of the preceding first stage are cut by moving the boom 1 laterally in the direction perpendicular to the paper surface of FIG. 2, that is, in the direction of the arrow in FIG. The grooves are formed in a first step along the large groove forming lines 6, 6, . . .

したがつて、矢印側方への移動するブーム1に
よる先行する第1段の切削溝5、5……は第3図
に示す様に相互に予定の大溝形成線6、6に対し
て平行に形成されていく。
Therefore, the preceding first-stage cutting grooves 5, 5, . It is being formed.

次に、該先行する第1段の切削溝5、5……を
設定長だけ予定の大溝形成線6、6に沿つて切削
形成して作業を行つた後は第4図に示す様に先行
切削溝5、5……に対してさく岩機7によるさく
岩作用を予定の大溝形成線6、6に沿つて行つて
いくと、先行する第1段の切削溝5、5……によ
り弱所化されている部位が容易に破砕されて最外
側の先行する第1段の切削溝5、5間の岩石が中
掘り除去されて大溝8が形成され、第2段の作業
が終了する。
Next, the cutting grooves 5, 5, . When the rock drilling machine 7 performs the rock drilling action on the cutting grooves 5, 5... along the planned large groove formation lines 6, 6, it becomes weaker due to the preceding first stage cutting grooves 5, 5... The crushed portion is easily crushed, and the rock between the cutting grooves 5, 5 of the outermost preceding first stage is removed by digging to form a large groove 8, and the second stage work is completed.

尚、当該第4図の実施例によれば、さく岩機7
の使用によつて僅かながら騒音、振動等が発生す
るが、第5図に示す様に先述の5ユニツト中の内
側の高圧力水の中掘用のノズル2′よりのみ高圧
力水ジエツト10を噴射して同様に先行する第1
段の切削溝5、5……の弱所部位を容易に第2段
的に破砕し中掘りして大溝8を形成しても良い
し、又、第6図に示す様にデイスクカツター11
を作動させて同じく第2段の破砕による大溝10
の中掘りを行うようにしても良い。
According to the embodiment shown in FIG. 4, the rock drill 7
However, as shown in Fig. 5, the high-pressure water jet 10 is only supplied from the inner high-pressure water nozzle 2' of the 5 units mentioned above. The first one that injects and similarly precedes the
The weak points of the cut grooves 5, 5... of the steps may be easily crushed in a second step and the large grooves 8 can be formed by digging in the middle, or the disk cutter 11 may be used as shown in FIG.
The large groove 10 is also created by the second stage of crushing.
It is also possible to perform digging in the middle of the hole.

それらの破砕手段の採用選択は岩盤の質、性
状、先行切削溝5、5……の間隔、破砕速度等に
より適宜行えば良い。
The selection of these crushing means may be made as appropriate depending on the quality and properties of the rock, the spacing between the preceding cutting grooves 5, 5, etc., the crushing speed, etc.

このようにして、先行する第1段の切削溝5、
5……間の所定の破砕除去による第2段の中掘作
業が終了すれば、それによつて形成された第1段
の大溝8がブーム1の外径より大であるため、ブ
ーム1を大溝8に挿入して上述同様に再び高圧ジ
エツト水を噴射して大溝8内の端部に次回の先行
する第1段の切削溝5、5……を掘削してブーム
1を予定の大溝形成線6、6に沿わせ、即ち、初
回形成の大溝8をガイドとしてスライドさせて作
業を終え、次に前述同様第2段の破砕を先行する
第1段の切削溝5、5……の弱所に付与して行
い、以下同様に反復し、例えば、2サイクルの施
工を行うと、所定深度の先行する第1段の切削溝
5、5……、第2段の破砕作用を行うことによ
り、第7図に示す様に掘削溝12が形成される。
In this way, the cutting groove 5 of the preceding first stage,
5... When the second stage medium excavation work by predetermined crushing and removal between 8 and inject high-pressure jet water again in the same manner as described above to excavate the next preceding first stage cutting grooves 5, 5, etc. at the end of the large groove 8, and move the boom 1 to the planned large groove forming line. 6, 6, that is, slide the first-formed large groove 8 as a guide to finish the work, and then, as described above, precede the second-stage crushing by cutting the weak points of the first-stage cutting grooves 5, 5... The process is repeated in the same way, for example, when two cycles of construction are carried out, the first stage cutting grooves 5, 5... of a predetermined depth are applied, and the second stage crushing action is performed. An excavated groove 12 is formed as shown in FIG.

而して、該溝12の内側面は実質的に先行する
第1段の切削溝5、5……によつて形成されるた
め溝面は極めて平滑で肌落ちもなく、地盤強度等
も損うことがない。
Since the inner surface of the groove 12 is substantially formed by the preceding first-stage cutting grooves 5, 5, etc., the groove surface is extremely smooth and there is no skin drop, and the strength of the ground etc. is also reduced. It never happens.

尚、上述実施例はブーム1のノズル数は5ユニ
ツトであるが、設計によつては中位の中掘りノズ
ル2′は1ユニツトでも良く、又、ノズル数配
置、径、移動速度、等は掘削条件、設計条件によ
り適宜に選択可能である。
In the above embodiment, the number of nozzles in the boom 1 is 5 units, but depending on the design, the intermediate nozzle 2' may be 1 unit, and the nozzle number arrangement, diameter, moving speed, etc. It can be selected as appropriate depending on excavation conditions and design conditions.

第8、9図に示す実施例はトンネル溝築におけ
る溝掘削の態様であるが、岩盤4にトンネル溝築
の予定の大溝形成線6、6に対して施工台車13
の可動アーム14に前延付設したブーム1から前
述の如く高圧ジエツト水を噴出させてそのインパ
クト作用により先行する第1段の切削溝5を大溝
形成線6、6に沿わせて形成させると共にその後
さく岩機7によりトレースして掘削させ、第2段
の中掘り作業を行つて大溝8を形成させるように
して前述同様にしてトンネルとしての予定の大溝
形成線6、6間に溝12を形成させて該溝12が
設定深度に達した後、施工台車13を後退させて
内側の予定の大溝形成線6内のトンネル形成部分
Aを発破により崩し、礫屑を排出した後は該形成
部分A内に再び施工台車13を進出させて上述同
様に溝12を形成させ、その作業を反復させるこ
とによりトンネルを形成させる。
The embodiment shown in FIGS. 8 and 9 is a mode of trench excavation in tunnel construction.
As mentioned above, high-pressure jet water is ejected from the boom 1 which is attached to the movable arm 14 in front, and the impact action of the jet water causes the preceding first-stage cutting groove 5 to be formed along the large groove forming lines 6, 6, and after that. A rock drill 7 is used to trace and excavate the rock, and a second stage of medium digging is performed to form a large groove 8, and in the same manner as described above, a groove 12 is formed between the large groove forming lines 6 and 6 that are planned to form a tunnel. After the groove 12 reaches the set depth, the construction cart 13 is moved backward, and the tunnel forming part A within the planned inner large groove forming line 6 is broken down by blasting, and after the debris is discharged, the forming part A is The construction cart 13 is again advanced into the tunnel to form the groove 12 in the same manner as described above, and this operation is repeated to form the tunnel.

その場合、トンネルの壁面は前述同様に外方先
行する第1段の切削溝5の面により極めて平滑に
形成される。
In this case, the wall surface of the tunnel is formed to be extremely smooth by the surface of the first stage cut groove 5 which precedes outward.

尚、この発明の実施態様は上述各実施例に限る
ものでないことは勿論であり、例えば、明り工
事、採石切出等にも使用出来る等種々の態様が採
用可能である。
It goes without saying that the embodiments of the present invention are not limited to the above-mentioned embodiments, and various embodiments can be adopted, such as being able to be used for lighting construction, stone quarrying, etc.

<発明の効果> 前述の如く、この発明によれば、岩盤に溝を掘
削する方法において、吐出圧数千気圧に昇圧可能
な高圧力水を集中的に細条化し所定の岩盤部位に
噴射してそのインパクト作用により先行する第1
段の切削溝を形成させ、その後先行する第1段の
切削溝による弱所形成部に適宜に第2段の破砕作
用を与えて中掘りし、先行する第1段の切削溝を
大溝に形成し、続いて該大溝から再び次回の先行
する第1段の切削溝を形成させ、以下同様に反復
して溝を掘削することにより結果的に相当に硬い
岩盤に対しても実質的に無振動無騒音で施工を行
うことが可能となる効果がある。
<Effects of the Invention> As described above, according to the present invention, in a method of excavating a groove in a rock, high-pressure water that can be pressurized to a discharge pressure of several thousand atmospheres is intensively divided into strips and injected into a predetermined part of the rock. The impact effect causes the first
Step cutting grooves are formed, and then the weak point formed by the preceding first stage cutting groove is appropriately subjected to a second stage crushing action to perform medium digging, and the preceding first stage cutting groove is formed into a large groove. Then, the next leading first-stage cutting groove is formed again from the large groove, and the grooves are repeatedly excavated in the same manner, resulting in virtually no vibration even in extremely hard rock. This has the effect of allowing construction to be carried out without noise.

したがつて、岩盤に亀裂を生ぜしめて岩盤に損
傷を与えたり、肌落ちが生ずる膚が無く、作業が
安全に出来るうえに補修工事の必要もなく、又、
溝面は高圧力水ジエツト切削による一種の鏡面仕
上げも可能になるために掘削精度も良く、後工事
のライニングもやり易い等の利点もあり、切出岩
石の製品品質をも向上させることが出来る効果が
ある。
Therefore, there is no possibility of causing cracks in the bedrock, causing damage to the bedrock, or causing skin to fall off, making the work safe and eliminating the need for repair work.
The groove surface can be finished to a kind of mirror finish by high-pressure water jet cutting, which improves the accuracy of excavation, and has the advantage of making lining work easier afterward, and improves the quality of the cut rock product. effective.

そして、先行する第1段の切削に続いて該先行
する第1段の切削によつて弱所化された内部を第
2段として破砕するために中掘りが確実であるう
えに深度が大きい掘削が出来、更に動力も少くて
済み、工事の安全性が保証され、経済性も得られ
るという効果がある。
Then, following the preceding first stage cutting, in order to crush the interior weakened by the preceding first stage cutting as a second stage, medium excavation is reliable and deep excavation is performed. It also has the effect of requiring less power, ensuring construction safety, and being economical.

又、これまで一部に強大圧を利用する所謂スム
ースブラステイング法等もあるが、該スムースブ
ラステイング法に比しても混成法を使用せず、切
削面に直角方向の応力がかからないため、土木工
事としては申し分のない円滑性、高精度を得るこ
とが出来る効果がある。
In addition, there have been some so-called smooth blasting methods that use strong pressure, but compared to the smooth blasting method, it does not use a hybrid method and does not apply stress in the perpendicular direction to the cutting surface. It has the effect of providing perfect smoothness and high precision for civil engineering work.

【図面の簡単な説明】[Brief explanation of the drawing]

図面はこの発明の実施例を示すものであり、第
1図はブームのノズルの正面図、第2図は先行切
削溝の形成側面図、第3図は先行切削溝の横方向
形成側面図、第4図は破砕工程断面図であり、第
5、6図は第4図相当他の実施例の断面図、第7
図は溝形成の模式斜視図、第8、9図はトンネル
掘削態様の実施例の側部及び横断面図である。 4……岩盤、12……溝、2″……外ノズル、
5……先行する第1段の切削溝、2′……中掘用
ノズル、2……ノズル、8……大溝。
The drawings show an embodiment of the present invention, in which FIG. 1 is a front view of the nozzle of the boom, FIG. 2 is a side view of the formation of the preceding cutting groove, and FIG. 3 is a side view of the formation of the preceding cutting groove in the lateral direction. Figure 4 is a sectional view of the crushing process, Figures 5 and 6 are sectional views of other embodiments equivalent to Figure 4, and Figure 7 is a sectional view of the crushing process.
The figure is a schematic perspective view of groove formation, and Figures 8 and 9 are side and cross-sectional views of an embodiment of the tunnel excavation mode. 4...Bedrock, 12...Groove, 2''...Outer nozzle,
5... Leading first stage cutting groove, 2'... Nozzle for medium digging, 2... Nozzle, 8... Large groove.

Claims (1)

【特許請求の範囲】[Claims] 1 岩盤等にジエツト水を噴射して所定幅の溝を
掘削する方法において、破砕面にて上記所定幅よ
りやや広く開角して設けた両側の外ノズルとそれ
らの中間に所要数設けた中掘用ノズルとの複数ユ
ニツトのノズルから予定掘削部位に対し高圧ジエ
ツト水を噴射して第1段の切削溝を形成すると共
に、ついで該第1段の切削溝内に第2段の破砕作
用を与えて上記第1段の切削溝部を中掘りして大
溝に形成し、続いて上記ノズルを前進させ、該大
溝内にて高圧ジエツト水の噴射を行い、以下上記
第1段切削と第2破砕過程を反復して所定幅の溝
を形成するようにしたことを特徴とする高圧ジエ
ツト水による溝掘削方法。
1 In a method of excavating a groove of a predetermined width by injecting jet water into rock, etc., outer nozzles on both sides are set slightly wider than the above-mentioned predetermined width at the fracture surface, and a required number of inner nozzles are installed between them. A first-stage cut groove is formed by injecting high-pressure jet water onto the planned excavation site from a plurality of nozzles including an excavation nozzle, and then a second-stage crushing action is applied within the first-stage cut groove. Then, the first stage cutting groove part is dug to form a large groove, and then the nozzle is moved forward and high pressure jet water is injected into the large groove, and then the first stage cutting and second crushing are performed. A trench excavation method using high-pressure jet water, characterized in that the process is repeated to form a trench of a predetermined width.
JP3531778A 1978-03-29 1978-03-29 Groove drilling method by high pressure jet water Granted JPS54127801A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3531778A JPS54127801A (en) 1978-03-29 1978-03-29 Groove drilling method by high pressure jet water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3531778A JPS54127801A (en) 1978-03-29 1978-03-29 Groove drilling method by high pressure jet water

Publications (2)

Publication Number Publication Date
JPS54127801A JPS54127801A (en) 1979-10-04
JPS6123350B2 true JPS6123350B2 (en) 1986-06-05

Family

ID=12438420

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3531778A Granted JPS54127801A (en) 1978-03-29 1978-03-29 Groove drilling method by high pressure jet water

Country Status (1)

Country Link
JP (1) JPS54127801A (en)

Also Published As

Publication number Publication date
JPS54127801A (en) 1979-10-04

Similar Documents

Publication Publication Date Title
US3865202A (en) Water jet drill bit
CN110439586B (en) Non-blasting type mine roadway water cutting tunneling method
CN106677788A (en) Mechanical excavation method for hard-rock tunnel with medium-short length
CN106194200A (en) A kind of efficient construction of hard rock tunnel
KR101634119B1 (en) Tunnel excavation method for kerfing outer surface of tunnel for decreasing blasting vibration
KR102207796B1 (en) Rock splitting system having rock splitter of disc bit type, and rock splitting method using the same
WO1991016524A1 (en) Method of excavating tunnel
JPS6123350B2 (en)
JP2908420B1 (en) Underground obstacle cutting method and device by shield excavator
US4673218A (en) Tunnel excavation method
JP4780473B2 (en) Tunnel construction method
KR101604705B1 (en) Method for enlarging train tunnel using dual protector considering operation of railroad, and method for the same
KR101649888B1 (en) Water jet excavator and method of construction for rock excavition having water jet excavator
JP2996097B2 (en) Tunnel excavation method
CN113236250B (en) Impact-prevention method for rock burst coal seam
KR20120063203A (en) Tunnel constructing method applying space for reducing vibration
JPH0563591B2 (en)
Xu et al. The use of waterjets in the pre-profiling of underground excavations
JPH0132360B2 (en)
JPS603396A (en) Tunnel drilling method
Ip et al. Water jet rock cutting and its application to tunnelling machine performance
CN114658427A (en) Tunnelling device for rock exploitation
JPH06221075A (en) Boring machine by double header drill and soil improvement work method
JPH0261288A (en) Bedrock drilling method
JPH0422960Y2 (en)