JPS6121218A - Constructing method of ground improvement - Google Patents
Constructing method of ground improvementInfo
- Publication number
- JPS6121218A JPS6121218A JP14069884A JP14069884A JPS6121218A JP S6121218 A JPS6121218 A JP S6121218A JP 14069884 A JP14069884 A JP 14069884A JP 14069884 A JP14069884 A JP 14069884A JP S6121218 A JPS6121218 A JP S6121218A
- Authority
- JP
- Japan
- Prior art keywords
- layer
- superior
- earth
- soil
- surface soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
Description
【発明の詳細な説明】
本発明は軟弱層、ヘドロ、廃棄物等のある土質改良を要
する表土層の下部に、良質材を有する中間層が存在する
地盤の改良工法に係るものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a soil improvement method in which an intermediate layer containing high-quality materials exists below a topsoil layer that requires soil improvement, including a soft layer, sludge, waste, etc.
従来この種の改良工法においては、大規模な開掘工皇が
行なわれ、建設機械の出入、施工資材の搬入等を確保す
るための仮設道路が必要になり、工期が延引し、工費が
嵩む等の問題点があった。Conventionally, this type of improved construction method involves large-scale excavation work, which requires temporary roads to ensure the access of construction machinery and the delivery of construction materials, which lengthens the construction period and increases construction costs. There was a problem.
本発明はこのような問題点を解決するために提案された
ものであって、軟弱表土層を貫通して同層下部の中間良
質層に達する吸引装置を配設し、同吸引装置を介して前
記中間良質層の土砂を地表部に吸上けて前記軟弱表土層
上に核上することを特徴とする地盤改良工法に係るもの
である。The present invention has been proposed to solve these problems, and includes a suction device that penetrates the soft topsoil layer and reaches the middle quality layer at the bottom of the layer. The present invention relates to a ground improvement method characterized in that the soil of the intermediate good quality layer is sucked up to the ground surface and deposited on the soft topsoil layer.
本発明においては前記したように、土砂の吸引装置を軟
弱表土層を貫通して同層1部の中間良質層に達するよう
に配設し、前記吸引装置によって中間良質層の土砂を上
表部に吸上げて軟弱表土層上に覆土して表土層を中間良
質層の土砂と置換し、軟弱地盤を改良するようにしたも
のである。In the present invention, as described above, the soil suction device is disposed so as to penetrate through the soft topsoil layer and reach the intermediate good quality layer of one part of the same layer, and the suction device removes the soil of the middle good quality layer from the upper surface layer. This method improves the soft ground by siphoning it up and covering it on top of the soft topsoil layer, replacing the topsoil layer with sand and sand from an intermediate layer of good quality.
従って本発明によれば前記吸引装置を地盤内に負犬する
ための削孔作業を行なうだけでよく、大規模な建設機械
等が不要になり、同機械の通行、施工資材の搬入等のた
めの仮設道路も不要となり、施工が容易になり、施工能
率が向上する。また施工区域内の道路々床材、埋設物基
礎側を搬入しないで区域内確保も可能となる。Therefore, according to the present invention, it is only necessary to perform the drilling work to place the suction device into the ground, and large-scale construction machines etc. are not required, and it is necessary to carry out the passage of the machines, carry in construction materials, etc. This eliminates the need for temporary roads, making construction easier and improving construction efficiency. In addition, it is possible to secure the construction area within the construction area without having to bring in road flooring materials and foundations for buried objects.
更に本発明によれば軟弱表土層を同層1部の中間良質層
の土砂と置換するので、表土覆T用の良質土砂の搬入が
少量、または不要になり、また塵芥、不良上等を地中深
く押込むことが可能と7fす、排水性の良好な表土地盤
を保持した優良造成地を確保で、きる。更にまた地表附
近の土質が改良されることによって、杭め横抵抗が増大
し、経済性の優れた基礎杭の設計が可能となる等、本発
明は多くの利点を有するものである。Furthermore, according to the present invention, since the soft topsoil layer is replaced with sand from the middle good quality layer of the same layer, the need to bring in a small amount of good quality sand for the topsoil covering T becomes unnecessary, and dust, defective soil, etc. are removed from the ground. It is possible to push it deeply into the ground by securing a high quality development site with a top soil base with good drainage. Furthermore, the present invention has many advantages, such as improving the soil quality near the ground surface, increasing the lateral resistance of piles, and making it possible to design foundation piles with excellent economic efficiency.
以下本発明を図示の実施例について説明する。The present invention will be described below with reference to the illustrated embodiments.
第1図において(1)は軟弱層、ヘドロ及びその他の塵
芥廃棄物等を有する表土層、(2)は同層下部の中間良
質層である。In Figure 1, (1) is a soft layer, a topsoil layer containing sludge and other garbage, and (2) is an intermediate quality layer at the bottom of the same layer.
前記表土層(1)を貫通し中間良質層(2)に達する小
規模な削孔を行ない、同削孔部(3)に送吸引管(4)
を貫挿し、ポンプ(5)を介して中間良質層(2)の良
質土砂(6)を地表部に吸上げ、同良質土砂(6)を前
記送吸引管(4)や、ベルトコンベアー・ダンプトラッ
ク等の運搬敷ならし装置等を介して表土層(1)−Fに
覆土1、、表土層(1)を良質土砂(6)層と置換して
地盤の改良を行なうものである。A small hole is drilled through the topsoil layer (1) to reach the middle quality layer (2), and a suction pipe (4) is installed in the drilled hole (3).
The high-quality soil (6) of the intermediate high-quality layer (2) is sucked up to the ground surface through the pump (5), and the high-quality soil (6) is transferred to the above-mentioned feed/suction pipe (4) or belt conveyor/dump. The ground is improved by covering the topsoil layer (1)-F with soil 1 and replacing the topsoil layer (1) with a layer of high-quality soil (6) via a transportation and leveling device such as a truck.
前記実施例の方法によれば従来のような大規模な開削作
業を行なうことなく、送吸引管(4)を貫挿するだめの
小規模な削孔作業だけでよく、大型の建設機械等が不要
となり、同機械の通行、施工資材搬入用の仮設道路が不
要となり、工期が縮減さ゛ れ、工費が節減される。ま
た軟弱表土層(1)が同層(1)下部の中間良質層(2
)の土砂と置換されるので、表土覆工用の良質土砂の搬
入が少量、または不要になり、廃棄塵芥、不良上等を地
中深く押込むことができ、排水性の良好な表土地盤が保
りされる。According to the method of the above embodiment, only a small-scale drilling operation for inserting the feed/suction pipe (4) is required, without the need for large-scale excavation work as in the conventional method, and large construction machines, etc. This eliminates the need for temporary roads for the passage of the machinery and the delivery of construction materials, reducing construction time and construction costs. In addition, the soft topsoil layer (1) is the middle good quality layer (2) below the same layer (1).
), it eliminates the need to bring in a small amount of high-quality soil for topsoil lining, and it is possible to push discarded trash, defective materials, etc. deep into the ground, creating a surface soil with good drainage. is maintained.
第2図は前記送吸引管(4)を表土層(1)及び中間良
質層(2)に亘って斜方向に貫入した場合を示I〜、第
3図は表土層(1)及び中間良質層(2)に亘って竪孔
(7)を掘削し、同竪孔(力より中間良負′層(2)内
に送吸引管(4)の先端を水平に貫入したものである。Figure 2 shows the case where the suction pipe (4) penetrates diagonally across the topsoil layer (1) and the middle quality layer (2), and Figure 3 shows the case where the topsoil layer (1) and the middle quality layer are penetrated in the diagonal direction. A vertical hole (7) was excavated across the layer (2), and the tip of the suction pipe (4) was inserted horizontally into the vertical layer (2).
なお第2図及び第3図中、前記第1図に示す実施例と均
等部分に同一符号が附されている。In FIGS. 2 and 3, parts that are equivalent to the embodiment shown in FIG. 1 are given the same reference numerals.
以上本発明な実施例について説明したが、本発明は勿論
このような実施例にだけ局限されるものではなく、本発
明の精神を逸脱しない範囲内で種々の設計の改変を施し
うるものである。Although the embodiments of the present invention have been described above, the present invention is, of course, not limited to these embodiments, and can be modified in various ways without departing from the spirit of the present invention. .
第1図は本発明に係る地盤改良方法の一実施例の実施状
況を示す縦断面図、第2図及び第3図は夫々本発明の方
法の他の実施例の実施状況を示す縦断面図である。
(1)・・・表土層、(2)・・・中間良質層、(4)
・・・送吸引管、(5)・・・ポンプ、(6)・・・良
質土砂代理人 弁理士 岡 本 重 文
外3名FIG. 1 is a longitudinal cross-sectional view showing the implementation status of one embodiment of the soil improvement method according to the present invention, and FIGS. 2 and 3 are longitudinal cross-sectional views showing the implementation status of other embodiments of the method of the present invention, respectively. It is. (1) ... Topsoil layer, (2) ... Intermediate quality layer, (4)
...Suction pipe, (5) ...Pump, (6) ...High-quality earth and sand agent Patent attorney Shige Okamoto 3 other people
Claims (1)
引装置を配設し、同吸引装置を介して前記中間良質層の
土砂を地表部に吸上げて前記軟弱表土層上に覆土するこ
とを特徴とする地盤改良工法。A suction device is provided that penetrates the soft topsoil layer and reaches the middle good quality layer at the bottom of the same layer, and the soil in the middle good quality layer is sucked up to the ground surface through the suction device and covered with soil on the soft topsoil layer. A ground improvement method characterized by:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14069884A JPS6121218A (en) | 1984-07-09 | 1984-07-09 | Constructing method of ground improvement |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14069884A JPS6121218A (en) | 1984-07-09 | 1984-07-09 | Constructing method of ground improvement |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS6121218A true JPS6121218A (en) | 1986-01-29 |
Family
ID=15274657
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP14069884A Pending JPS6121218A (en) | 1984-07-09 | 1984-07-09 | Constructing method of ground improvement |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6121218A (en) |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5129578A (en) * | 1974-05-10 | 1976-03-12 | Olin Corp |
-
1984
- 1984-07-09 JP JP14069884A patent/JPS6121218A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5129578A (en) * | 1974-05-10 | 1976-03-12 | Olin Corp |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4358221A (en) | System for pollution control | |
CN105887889B (en) | A kind of ultra-wide hyposmosis mud method of excavation of deep foundation pit | |
US20220098817A1 (en) | Method for constructing structure | |
US4797031A (en) | Caisson sinking method | |
CN108797618A (en) | One kind being used for Urban Underground pipe gallery drainage of foundation pit structure and its construction method | |
JPS5985028A (en) | Steel pipe pile and laying work thereof | |
KR101946930B1 (en) | Method for Excavating Vertical Hole using Raise Boring Machine and Packed Steel Pipe | |
JPS6121218A (en) | Constructing method of ground improvement | |
JP2916595B2 (en) | Wastewater discharge method in the pneumatic caisson method | |
KR0148437B1 (en) | Pile construction method in underground boulder zone | |
JPS62242011A (en) | Method and apparatus for constructing shallow ground-improving pile | |
JPS6115209B2 (en) | ||
JP2743055B2 (en) | Liquefaction prevention method for sand ground | |
JP3000497B2 (en) | Construction method for high strength cast-in-place concrete piles | |
GB2137678A (en) | Method and apparatus for pile construction | |
CN110284506A (en) | A kind of foundation pit enclosure method for the expansion construction that deep basal pit is cheated to shallow foundation | |
JP3318495B2 (en) | Method of forming a permeable layer on soil cement underground wall | |
JP4022867B2 (en) | Pre-drilling method for soft and viscous ground with high groundwater level | |
JPS6129786Y2 (en) | ||
JPS6192235A (en) | Fixing of embedded pipe | |
SU1409717A1 (en) | Method of constructing water removal ditch | |
US3890791A (en) | Method of building a tunnel and tunnel built according to said method | |
SU1652431A1 (en) | Method for construction of cast-in-place pile | |
JP2587949B2 (en) | Manufacturing method of piles on site using electrochemical injection method | |
JP3041323B2 (en) | Septic tank equipment and septic tank installation method |