JPS6116827B2 - - Google Patents

Info

Publication number
JPS6116827B2
JPS6116827B2 JP13823681A JP13823681A JPS6116827B2 JP S6116827 B2 JPS6116827 B2 JP S6116827B2 JP 13823681 A JP13823681 A JP 13823681A JP 13823681 A JP13823681 A JP 13823681A JP S6116827 B2 JPS6116827 B2 JP S6116827B2
Authority
JP
Japan
Prior art keywords
floor
beams
small
slab
small beams
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP13823681A
Other languages
Japanese (ja)
Other versions
JPS5841157A (en
Inventor
Hiroshi Nakaoka
Goro Iritani
Takeshi Tsunematsu
Yoshinori Matsuyama
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Haseko Corp
Original Assignee
Hasegawa Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hasegawa Komuten Co Ltd filed Critical Hasegawa Komuten Co Ltd
Priority to JP13823681A priority Critical patent/JPS5841157A/en
Publication of JPS5841157A publication Critical patent/JPS5841157A/en
Publication of JPS6116827B2 publication Critical patent/JPS6116827B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、鉄骨造、現場打ちによる鉄骨鉄筋コ
ンクリート造、あるいは、プレキヤスト製など、
剛性の高い柱、大梁を有し、且つ小梁をプレキヤ
スト製小梁材と現場打ちコンクリートとの合成小
梁とした複数階層建築物における一般階の床版、
特に現場打ちコンクリートによる床版又は現場打
ちコンクリートとプレキヤスト部材とによつて合
成される床版を構築する方法に関する。
[Detailed Description of the Invention] [Industrial Application Field] The present invention is applicable to steel structures, cast-in-place steel reinforced concrete structures, precast structures, etc.
A floor slab for a general floor in a multi-story building that has highly rigid columns and large beams, and the small beams are composite small beams made of precast small beam materials and cast-in-place concrete,
In particular, the present invention relates to a method of constructing a floor slab made of cast-in-place concrete or a composite floor slab made of cast-in-place concrete and precast members.

〔従来の技術〕[Conventional technology]

従来、小梁をプレキヤスト製小梁材と現場打ち
コンクリートとの合成小梁とした複数階層建築物
においては、合板製の型枠を下方から多数のポス
トで支持した状態で、型枠上にスラブ配筋、コン
クリート打設を行い、コンクリートの養生後、前
記ポストを徹去して上方のコンクリート打設階に
揚重転用し、順次下から上へと床版を構築して行
く床版構築方法が採用されていた。
Conventionally, in multi-story buildings where the beams are composite beams made of precast beams and cast-in-place concrete, slabs are placed on top of the formwork with plywood formwork supported from below by a number of posts. A floor slab construction method in which reinforcement is placed, concrete is placed, and after the concrete has cured, the posts are removed and the lifting load is diverted to the concrete floor above, and the slab is constructed sequentially from the bottom to the top. had been adopted.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

しかし、上記の従来方法においては、床版コン
クリートの養生期間が終了するまで、該床版の下
階に多数のポストが存置されているため、これら
が後工程である設備工事や仕上げ材の搬入作業を
進めるのに障害となり、設備配管等の工事や仕上
げ工事の先行による工期短縮を困難にしていた。
However, in the above conventional method, a large number of posts remain on the lower floor of the concrete floor slab until the curing period of the concrete floor slab ends, so these posts are used for the subsequent process of equipment construction and the delivery of finishing materials. This was an impediment to the progress of the work, making it difficult to shorten the construction period by conducting equipment piping work and finishing work in advance.

また、ポストは、圧縮材として使用される必要
上、かなりの重量物となつており、コンクリート
打設階への揚重、転用に多大の手間を必要とする
ものであつた。
In addition, since the posts are used as compressed materials, they are quite heavy, and require a great deal of effort to lift and repurpose them to the floor where concrete is to be poured.

これらの従来欠点の解消策としては、合成小梁
作製用のプレキヤスト製小梁材を複数階層分大梁
間に架設し、下階の小梁材を上階の小梁材に吊り
棒を介して吊下げ支持させ、この状態で下階の小
梁材間に仮受梁を架設し、該仮受梁上に床版用型
枠を敷込んで、スラブ配筋、コンクリート打設を
行う方法が先ず考えられる。
As a solution to these conventional shortcomings, precast small beams for making composite small beams are installed between the girders for multiple floors, and the small beams on the lower floor are connected to the small beams on the upper floor via hanging rods. The method is to suspend the slab, erect temporary support beams between the small beams on the lower floor in this state, lay the formwork for the slab on top of the temporary support beams, and perform slab reinforcement and concrete pouring. I can think of it first.

しかしながら、従来公知の合成小梁作製用プレ
キヤスト製小梁材は、いずれもスターラツプの上
端側部分をプレキヤストコンクリート部分の上面
から突出させた形状に成型されており、プレキヤ
ストコンクリート部分の上面全体が現場打ちコン
クリートとの打ち継ぎ面となつている。
However, all of the conventionally known precast beam materials for making synthetic beams are formed in such a shape that the upper end of the stirrup protrudes from the upper surface of the precast concrete portion, and the entire upper surface of the precast concrete portion is It serves as a joint surface with cast-in-place concrete.

従つて、上階の小梁材に下階の小梁材を吊り棒
を介して吊り下げる場合、次の問題が派生するこ
とになる。
Therefore, when suspending a small beam on the lower floor from a small beam on the upper floor via a hanging rod, the following problem arises.

例えば、小梁材の上面近傍と下面近傍に夫々雌
ねじ状のインサート金物を埋設しておき、上階の
小梁材下面のインサート金物に吊り棒の上端部を
ねじ込み、当該吊り棒の下端部を下階の小梁材上
面のインサート金物にねじ込んで、下階の小梁材
を上階の小梁材で吊り下げる場合には、現場打ち
コンクリートの厚さに相当する吊り棒部分に現場
打ちコンクリートとの付着を防止する部材を巻き
つけるといつた何らかの縁切り作業が必要であ
り、施工性が悪くなる。
For example, female-threaded metal inserts are buried near the top and bottom of the small beam, and the upper end of the hanging rod is screwed into the metal insert on the bottom of the small beam on the upper floor. When screwing into the insert metal fittings on the top surface of the small beams on the lower floor and suspending the small beams on the lower floor from the small beams on the upper floor, insert the cast-in-place concrete into the hanging rod part that corresponds to the thickness of the cast-in-place concrete. Some kind of edge cutting work is required, such as wrapping a material around the material to prevent it from adhering to the surface of the material, which impairs workability.

また、上記のように、インサート金物を埋設し
た場合、プレキヤストコンクリート部分の有効断
面積が小さく、インサート金物に作用する引抜き
力によつて、インサート金物の周囲のプレキヤス
トコンクリート部分が欠損する虞れがある。
In addition, as mentioned above, when insert hardware is buried, the effective cross-sectional area of the precast concrete part is small, and there is a risk that the precast concrete part around the insert hardware may be damaged due to the pull-out force acting on the insert hardware. There is.

本発明の目的は、下階の合成小梁作製用プレキ
ヤスト製小梁材を上階の合成小梁作製用プレキヤ
スト製小梁材に吊り棒を介して吊下げ支持させ、
この状態で下階の小梁材間に仮受梁を架設し、該
仮受梁上に床版用型枠を敷込んで、スラブ配筋、
コンクリート打設を行うことにより、上述した従
来欠点を解消すると共に、下階の合成小梁作製用
プレキヤスト製小梁材を上階の合成小梁作製用プ
レキヤスト製小梁材に吊り棒を介して吊下げ支持
させることによつて派生する上記の問題点を解決
することにある。
The purpose of the present invention is to suspend and support a precast small beam material for making a composite small beam on the lower floor by suspending it from a precast small beam material for making a synthetic small beam on the upper floor via a hanging rod,
In this state, a temporary support beam was erected between the small beams on the lower floor, and the formwork for the floor slab was laid on top of the temporary support beam, and slab reinforcement was constructed.
By pouring concrete, the above-mentioned conventional drawbacks can be solved, and the precast beams for making composite beams on the lower floor can be connected to the precast beams for making composite beams on the upper floor via hanging rods. The object of the present invention is to solve the above-mentioned problems caused by suspension support.

〔問題点を解決するための手段〕 上記の目的を達成するため、本発明は、長手方
向複数個所に上下方向の貫通孔を設けると共に、
当該貫通孔の周辺部のみその上面が現場で構築さ
れる床版の天端と面一状となるような隆起部を成
型してなる合成小梁作製用のプレキヤスト製小梁
材を複数階層分大梁間に架設し、下階の小梁材を
上階の小梁材に、これら両奨梁材の貫通孔にわた
つて挿通され、且つ上階の小梁材の上面に対する
係止部と下階の小梁材の下面に対する係止部とを
有する吊り棒を介して吊下げ支持させた状態で、
下階の小梁材間に仮受梁を架設し、該仮受梁上に
床版用型枠を敷込み、配筋及びコンクリート打設
を行つて床版を構築するように構成したのであ
る。
[Means for Solving the Problems] In order to achieve the above object, the present invention provides vertical through holes at multiple locations in the longitudinal direction, and
Multiple levels of precast beam material for fabricating composite beams are formed by molding a raised part only around the through hole so that its upper surface is flush with the top of the slab to be constructed on site. It is installed between the girders, and the small beam on the lower floor is inserted into the small beam on the upper floor, across the through holes of both of these girders, and the locking part for the upper surface of the small beam on the upper floor and the bottom In a state where it is suspended and supported via a hanging rod having a locking part for the lower surface of the small beam of the floor,
The structure was such that temporary support beams were erected between the small beams on the lower floor, the formwork for the floor slab was laid on top of the temporary support beams, and the floor slab was constructed by arranging reinforcement and pouring concrete. .

〔作用〕[Effect]

上記の構成によれば、隆起部の上面が、現場打
ちコンクリートによる床版の天端と面一状である
ため、吊り棒と現場打ちコンクリートとの縁切り
をするための作業が必要である。
According to the above configuration, since the upper surface of the raised portion is flush with the top end of the cast-in-place concrete floor slab, it is necessary to perform an operation to cut the edge between the hanging rod and the cast-in-place concrete.

下階の小梁材による荷重が上階の小梁材の隆起
部上面に作用し、下階の小梁材はその下面が支持
されることになり、小梁材の有効断面積が大き
い。
The load from the small beams on the lower floor acts on the upper surfaces of the raised parts of the small beams on the upper floor, and the lower surfaces of the small beams on the lower floor are supported, so the effective cross-sectional area of the small beams is large.

〔実施例〕〔Example〕

以下、本発明の実施例を図面に基づいて説明す
る。
Embodiments of the present invention will be described below based on the drawings.

第1図、第2図は本発明方法に用いる合成小梁
作製用のプレキヤスト製小梁材Aの一例を示す。
この小梁材Aは、長手方向に適当間隔を隔てた複
数個所(この実施例では2個所であるが、3個所
以上であつてもよい。)に、上下方向の貫通孔1
を設けると共に、各貫通孔1の周辺部のみ、コン
クリートを増し打ちしてその上面が現場で構築さ
れる床版Bの天端と面一状になるような隆起部2
を予め成型したものである。前記各貫通孔1には
両端に適当幅にわたる雄ねじ部を有する鋼棒3を
挿通し、鋼棒3には前記隆起部2の上面に対する
係止部を構成する座金4a及びナツト5aと小梁
材Aの下面に対する係止部を構成する座金4b及
びナツト5bが装着されている。6はターンバツ
クルであり、ターンバツクル6とこれにより連結
された上下の鋼棒3,3とによつて、吊り棒7を
形成すべく構成してある。ターンバツクル6は鋼
棒3の下端部に螺着してもよく、あるいは小梁材
Aをレツカー等で揚重する際の吊りワイヤ係止部
となるように鋼材3の上端部に螺着してもよい。
8aは合成小梁の上主筋、8bは下主筋、8cは
スターラツプ、9は鉄骨9aを内蔵する大梁であ
る。尚、この実施例では、大梁9がプレキヤスト
製耐震壁10と一体成型されているが、ラーメン
構造における大梁であつてもよい。11は仮受梁
取付金物である。
FIGS. 1 and 2 show an example of a precast beam material A for producing a composite beam used in the method of the present invention.
This small beam material A has vertical through-holes 1 at multiple locations (in this example, there are two locations, but three or more locations may be provided) at appropriate intervals in the longitudinal direction.
At the same time, additional concrete is poured only around the periphery of each through hole 1, and a raised part 2 is formed so that the upper surface thereof is flush with the top of the floor slab B to be constructed on site.
It is pre-molded. A steel rod 3 having a male thread of an appropriate width at both ends is inserted into each of the through holes 1, and a washer 4a, a nut 5a, and a small beam member are attached to the steel rod 3, which constitute a locking portion for the upper surface of the raised portion 2. A washer 4b and a nut 5b, which constitute a locking portion for the lower surface of A, are attached. Reference numeral 6 denotes a turnbuckle, and the turnbuckle 6 and the upper and lower steel rods 3, 3 connected by the turnbuckle 6 form a hanging rod 7. The turnbuckle 6 may be screwed to the lower end of the steel rod 3, or it may be screwed to the upper end of the steel rod 3 so as to serve as a suspension wire locking part when lifting the small beam A with a retcher or the like. Good too.
8a is the upper main reinforcement of the composite beam, 8b is the lower main reinforcement, 8c is the stirrup, and 9 is the girder incorporating the steel frame 9a. In this embodiment, the girder 9 is integrally molded with the precast shear wall 10, but it may be a girder in a rigid frame structure. 11 is a temporary support beam mounting hardware.

次に、床版Bの構築方法について述べる。 Next, a method for constructing floor slab B will be described.

先ず、第3図イ、ロ、ハに示すように、地中梁
12、1階の床版13を在来工法によつて構築
し、かつ、所定階層分の柱14の建込み、柱14
間への大梁9,9′の架設を行つた後、2階の小
梁材A2を大梁9間に架設し、該小梁材A2を3階
の小梁材A3に、前述した吊り棒7を介して吊下
げ支持させる。2階の小梁材A2間、並びに当該
小梁材A2と大梁9′間に夫々トラスガーダー等の
仮受梁15を架設し、これら仮受梁15の上部
に、床版用型枠16を敷込む。3階の小梁材A3
は4階の小梁材A4に、4階の小梁材A4は5階の
小梁材A5に夫々吊下げ支持させるといつたよう
に、上記の工程を順次下から上へと進めて行く。
First, as shown in FIG.
After constructing the girders 9 and 9' between the girders 9 and 9', the second floor's small beam A 2 was erected between the girders 9, and the small beam A 2 was replaced with the third floor's small beam A 3 as described above. It is suspended and supported via a hanging rod 7. Temporary support beams 15 such as truss girders are erected between the small beams A 2 on the second floor and between the small beams A 2 and the girder 9', and the formwork for the floor slab is installed on top of these temporary support beams 15. Insert 16. 3rd floor small beam A 3
The above steps are carried out sequentially from the bottom to the top , as shown in the following example. Let's move on.

一方、これと併行して、2階の型枠16上に床
配筋、コンクリート打設を行い、9〜10日/1階
分、程度で順次3階、4階へと打ち上げて行く。
Meanwhile, in parallel with this, floor reinforcement and concrete pouring will be carried out on the formwork 16 on the second floor, and the work will be carried out to the third and fourth floors one floor at a time for 9 to 10 days.

そして、5階の小梁材A5の架設を完了した
後、2階の吊り棒7及び仮受梁15、型枠16を
徹去し、これら7,15,16を5階に揚重し
て、該吊り棒7で4階の小梁材A4と5階の小梁
材A5を連結し、4階の小梁材A4を5階の小梁材
A5に吊下げ支持させると共に、前記の揚重した
仮受梁15を5階の小梁材A5間、小梁材A5と大
梁9′間に架設する。
After completing the erection of the small beam A5 on the 5th floor, the hanging rods 7, temporary support beams 15, and formwork 16 on the 2nd floor were removed, and these 7, 15, and 16 were lifted to the 5th floor. Then, connect the small beam A 4 on the 4th floor and the small beam A 5 on the 5th floor using the hanging rod 7, and connect the small beam A 4 on the 4th floor to the small beam A 4 on the 5th floor.
A5 is suspended and supported, and the above-mentioned lifted temporary support beam 15 is installed between the small beams A5 on the 5th floor and between the small beams A5 and the main beam 9'.

以下、3階の吊り棒7及び仮受梁15、型枠1
6を6階に、4階の吊り棒7及び仮受梁15、型
枠16を7階へと順次転用して行き、現場打ちコ
ンクリート床版B及び合成小梁を構築して行くの
である。
Below are the hanging rods 7, temporary support beams 15, and formwork 1 on the third floor.
6 to the 6th floor, and the hanging rods 7, temporary support beams 15, and formwork 16 from the 4th floor to the 7th floor, and the cast-in-place concrete slab B and composite beams will be constructed.

尚、貫通孔1は、鋼棒3の転用後、モルタル等
で閉塞される。また、少なくとも最上階の床版
(屋根スラブ)は在来工法によつて構築される。
柱14及び大梁9,9′は、鉄骨造、現場打ちに
よる鉄骨鉄筋コンクリート造、あるいは、プレキ
ヤスト製など、剛性の高いものであれば、いずれ
を採用しても上記の床版構築方法が可能である。
また、この実施例では、現場打ちコンクリートに
よる床版Bの構築方法についてのみ説明したが、
現場打ちコンクリートとプレキヤストコンクリー
ト製埋込み型枠とで構成される合成床版について
も上記の構築方法を適用できる。
Note that the through hole 1 is closed with mortar or the like after the steel rod 3 is diverted. Furthermore, at least the roof slab on the top floor will be constructed using conventional construction methods.
The above deck construction method is possible for the columns 14 and the girders 9, 9', as long as they are of high rigidity, such as steel construction, cast-in-place steel reinforced concrete construction, or precast construction. .
In addition, in this example, only the method of constructing the floor slab B using cast-in-place concrete was explained.
The above construction method can also be applied to composite slabs made of cast-in-place concrete and embedded formwork made of precast concrete.

鋼棒3としてねじ節鉄筋を用いる場合には、タ
ーンバツクル6に代え、ねじ節鉄筋接合用のカツ
プラーを使用することができる。
When a threaded reinforcing bar is used as the steel rod 3, a coupler for joining the threaded reinforcing bar can be used in place of the turnbuckle 6.

〔発明の効果〕〔Effect of the invention〕

本発明は、上述した構成よりなるため次の効果
を奏し得るのである。
Since the present invention has the above-described configuration, it can achieve the following effects.

合成小梁作製用のプレキヤスト製小梁材を複
数階層分大梁間に架設し、下階の小梁材を上階
の小梁材に吊下げ支持させ、床版の自重及び施
工時荷重を支えるため、ポストを省略でき、床
版下にポストが林立しないため、設備配管等の
工事や仕上げ工事の先行が可能であり、工期を
短縮できる。
Pre-cast small beams for making composite beams are installed between the large beams for multiple floors, and the small beams on the lower floor are suspended and supported by the small beams on the upper floor to support the own weight of the floor slab and the load during construction. Therefore, the posts can be omitted and there are no posts standing under the floor slab, so construction work such as equipment piping and finishing work can be carried out in advance, and the construction period can be shortened.

吊り棒は、引張材として用いられているの
で、座屈に対する強度を考慮する必要がなく、
径小かつ軽量なもので足り、上階への揚重、転
用自体もポストに比べて非常に容易である。
Since the hanging rod is used as a tension member, there is no need to consider buckling strength.
It only needs to be small in diameter and lightweight, and it is much easier to lift it to the upper floor and convert it to other uses than a post.

小梁材に形成した吊り棒挿通用の貫通孔の周
辺部には、上面を現場打ちコンクリートによる
床版の天端と面一状とした隆起部を形成してあ
るので吊り棒と現場打ちコンクリートとの縁切
りをするための作業が不要であり、施工性が良
い。
Around the through-hole formed in the small beam material for the insertion of the hanging rod, a raised part is formed so that the upper surface is flush with the top of the cast-in-place concrete floor slab, so that the hanging rod and the cast-in-place concrete can be inserted easily. There is no need to do any work to cut the edges, and the construction is easy.

下階の小梁材による荷重が上階の小梁材の隆
起部上面に作用し、下階の小梁材はその下面が
支持されることになり、小梁材の有効断面積が
大きくて、小梁材のプレキヤストコンクリート
が部分的に欠損する虞れがない。
The load from the small beams on the lower floor acts on the upper surface of the raised part of the small beams on the upper floor, and the lower surface of the small beams on the lower floor is supported, and the effective cross-sectional area of the small beams is large. , there is no risk of partial loss of the precast concrete of the small beams.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明の一実施例を示し、第1図は要部
の斜視図、第2図は要部の縦断面図、第3図イ、
ロ、第4図イ、ロは構築手順の説明図、第5図は
平面図である。 1……貫通孔、2……隆起部、7……吊り棒、
9,9……大梁、15……仮受梁、16……型
枠、A……合成小梁作製用プレキヤスト製小梁
材、B……床版。
The drawings show one embodiment of the present invention, and FIG. 1 is a perspective view of the main part, FIG. 2 is a vertical sectional view of the main part, and FIG.
4A and 4B are explanatory diagrams of the construction procedure, and FIG. 5 is a plan view. 1... Through hole, 2... Protrusion, 7... Hanging rod,
9,9...Large beam, 15...Temporary support beam, 16...Formwork, A...Precast beam material for making composite beams, B...Floor slab.

Claims (1)

【特許請求の範囲】[Claims] 1 剛性の高い柱、大梁を有し、且つ小梁をプレ
キヤスト製小梁材と現場打ちコンクリートとの合
成小梁とした複数階層建築物の床版を構築する
に、長手方向複数個所に上下方向の貫通孔を設け
ると共に、当該貫通孔の周辺部のみその上面が現
場で構築される床版の天端と面一状となるような
隆起部を成型してなる合成小梁作製用のプレキヤ
スト製小梁材を複数階層分大梁間に架設し、下階
の小梁材を上階の小梁材に、これら両小梁材の貫
通孔にわたつて挿通され、且つ上階の小梁材の上
面に対する係止部と下階の小梁材の下面に対する
係止部とを有する吊り棒を介して吊下げ支持させ
た状態で、下階の小梁材間に仮受梁を架設し、該
仮受梁上に床版用型枠を敷込み、配筋及びコンク
リート打設を行つて床版を構築することを特徴と
する複数階層建築物における床版構築方法。
1. When constructing a floor slab for a multi-story building that has highly rigid columns and large beams, and the small beams are composite beams made of precast small beams and cast-in-place concrete, it is necessary to A precast material for making a composite beam by providing a through hole and molding a raised part so that only the upper surface of the peripheral part of the through hole is flush with the top of the slab to be constructed on site. The small beams are installed between the large beams for multiple floors, and the small beams on the lower floor are inserted into the small beams on the upper floor, and the small beams on the upper floor are inserted through the through holes of both of the small beams. A temporary support beam is erected between the small beams on the lower floor while being suspended and supported via a hanging rod that has a locking part for the upper surface and a locking part for the lower surface of the lower floor beams. A method for constructing a floor slab in a multi-story building, characterized by constructing a floor slab by laying a formwork for the floor slab on a temporary support beam, arranging reinforcement and pouring concrete.
JP13823681A 1981-09-01 1981-09-01 Floor construction in plural staired building Granted JPS5841157A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13823681A JPS5841157A (en) 1981-09-01 1981-09-01 Floor construction in plural staired building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13823681A JPS5841157A (en) 1981-09-01 1981-09-01 Floor construction in plural staired building

Publications (2)

Publication Number Publication Date
JPS5841157A JPS5841157A (en) 1983-03-10
JPS6116827B2 true JPS6116827B2 (en) 1986-05-02

Family

ID=15217256

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13823681A Granted JPS5841157A (en) 1981-09-01 1981-09-01 Floor construction in plural staired building

Country Status (1)

Country Link
JP (1) JPS5841157A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0641552U (en) * 1992-11-20 1994-06-03 サンウエーブ工業株式会社 Heater switch structure

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6195141A (en) * 1984-10-15 1986-05-13 清水建設株式会社 Floor construction method using half pc small beam with yaw

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0641552U (en) * 1992-11-20 1994-06-03 サンウエーブ工業株式会社 Heater switch structure

Also Published As

Publication number Publication date
JPS5841157A (en) 1983-03-10

Similar Documents

Publication Publication Date Title
US10260224B1 (en) Simplified precast concrete system with rapid assembly formwork
US8161691B2 (en) Precast composite structural floor system
US5305572A (en) Long span post-tensioned steel/concrete truss and method of making same
US4023315A (en) Prefabricated buildings
US20210025164A1 (en) Pre-stressed intersecting modular truss and concrete decking floor system
CN111411687A (en) Novel assembly system
KR100830240B1 (en) Method for hybridizing light-weight composite wall and concrete floor in light-weight composite structure using adapter
US7219474B2 (en) Load bearing building panel
CN110670720A (en) Connecting structure of prefabricated column and superposed beam and construction method thereof
US3930348A (en) Reinforced concrete construction
US3763613A (en) Composite concrete construction of two-way slabs and flat slabs
WO1996021069A1 (en) A structural member
JPS6282147A (en) Novel prestressed synthetic beam and its construction
JPS6116827B2 (en)
JPH02300439A (en) Prefabricating method
JPH0520817Y2 (en)
CN211774531U (en) Connecting structure of prefabricated column and superposed beam
JPH0475322B2 (en)
KR100581224B1 (en) X shape cantilever column capital
JPH0718734A (en) Constructing method for reinforced concrete building structure
JPH02311639A (en) Construction of composite floor
JP2659329B2 (en) Construction method of PC structure
JPH03129034A (en) Construction of floor and connecting device between striking-in mold frame for floor slab and self erection type truss-shaped steel reinforcement
US1141160A (en) Reinforced-concrete building construction.
JPH06146472A (en) Precast ferro-concrete beam