JPS61142221A - Construction of underground wall - Google Patents

Construction of underground wall

Info

Publication number
JPS61142221A
JPS61142221A JP26418884A JP26418884A JPS61142221A JP S61142221 A JPS61142221 A JP S61142221A JP 26418884 A JP26418884 A JP 26418884A JP 26418884 A JP26418884 A JP 26418884A JP S61142221 A JPS61142221 A JP S61142221A
Authority
JP
Japan
Prior art keywords
concrete
box
bearing wall
cover plate
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP26418884A
Other languages
Japanese (ja)
Other versions
JPH0259890B2 (en
Inventor
Munetaka Kubota
久保田 宗孝
Kazuo Sato
一男 佐藤
Shigekazu Nishimura
西村 重和
Akira Mizobuchi
溝渕 彬
Toshihiko Murata
俊彦 村田
Yoshinori Murao
村尾 義則
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP26418884A priority Critical patent/JPS61142221A/en
Publication of JPS61142221A publication Critical patent/JPS61142221A/en
Publication of JPH0259890B2 publication Critical patent/JPH0259890B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To exactly support horizontal forces to be applied by a method in which a bearing wall, a form box, and a reinforcing bag cage are set in a trench, the bearing walls on both ends of the form box are connected with tie rods, concrete is placed into the form box, and cover plates are set in front of the excavating direction. CONSTITUTION:A given depth of trench 1 is excavated in the ground, and a form box 2 consisting of a bearing wall 3 and side plates 4 and reinforcing bars 6 are integrally penetrated into the trench 1. The form box 2 is fixed with tie rods 10 through the wall 3 by using nuts 11. Concrete 13 is placed in the rare part of the excavating direction of the box 2, and cover plates 14 are set in front of the excavating direction of the box 2 to close the trench 1. The ground in front is excavated. The underground wall can thus be exactly constructed without causing the displacement of the form box because of support by the tie-rods and can withstand the horizontal forces such as soil pressure, etc.

Description

【発明の詳細な説明】 産業上の利用分野 この発明は地下壁の構築方法に関するものである。[Detailed description of the invention] Industrial applications This invention relates to a method of constructing underground walls.

従来技術 従来鉄筋コンクリートの土留壁を施工するに際し、1パ
ネルづつ鉄筋かごを吊り降し、コンクリートを打設する
工法が採用されている。このような工法において問題と
なるのは打継部分において、鉄筋が連結されておらず、
その為水圧及び土圧等による水平力に充分抵抗させるこ
とができないことであった。
Prior Art Conventionally, when constructing a reinforced concrete earth retaining wall, a construction method has been adopted in which a reinforcing cage is suspended one panel at a time and concrete is poured. The problem with this construction method is that the reinforcing bars are not connected at the joints,
Therefore, it was not possible to sufficiently resist horizontal forces caused by water pressure, earth pressure, etc.

このような問題点を解消するために特公昭47−331
0号公報に記載された発明が開発されている。
In order to solve these problems, the Special Publication Publication No. 47-331
The invention described in Publication No. 0 has been developed.

該発明は鉄筋篭の端部を断面コ字状の保護策から突出せ
しめておき、該鉄筋篭と保護策を溝内に吊り降して保護
策には閉鎖板を差し込んで鉄筋端部を保護する。保護策
の進行方向後方にコンクリートを打設し、コンクリート
硬化後閉鎖板を引き抜いて、次の鉄筋篭を吊り降す。既
設の鉄筋篭の端部と保護筒内にて重ね合せて、打継部分
の連結を強固にするものである。
In this invention, the end of the reinforcing bar cage is made to protrude from a protective measure having a U-shaped cross section, the reinforcing bar cage and the protecting measure are suspended in a groove, and a closing plate is inserted into the protective measure to protect the end of the reinforcing bar. do. Concrete is poured behind the protective measure in the direction of travel, and after the concrete hardens, the closing plate is pulled out and the next reinforcing cage is lowered. It is overlapped with the end of the existing reinforcing bar cage inside the protective cylinder to strengthen the connection of the spliced part.

この発明が解決すべき問題点 上記のような発明において問題となるのは以下の点であ
る。
Problems to be Solved by the Invention Problems to be solved by the invention as described above are as follows.

■ コンクリートを打設すると、コンクリートの側圧が
保護策にかかり、和尚な重量を有するものでないと保護
策の位置がズしてしまい正確な施工が行えなかった。
■ When concrete is poured, the lateral pressure of the concrete is applied to the protective measures, and unless the concrete has a reasonable weight, the protective measures will be misaligned, making it impossible to perform accurate construction.

@ 打設したコンクリートが地山と保護筒側板間の隙間
を通って流れ、保護筒内に流入するため、保護筒先端に
閉鎖板を挿入しなければならなかった。
@ Because the poured concrete flows through the gap between the ground and the side plate of the protection tube and flows into the protection tube, a closing plate had to be inserted at the tip of the protection tube.

問題点を解決するための手段 この発明にかかる地中壁の構築方法は、地中に掘削した
溝内に断面略コ字状の型枠函と、型枠函の支圧壁を貫通
する鉄筋を挿入し、先行して挿入した型枠函をタイロッ
ドにより連結し、コンクリートの側圧をタイロッドによ
り支持するようにして型枠函の後方にコンクリートを打
設するとともにシール材によって側板と地山間へのコン
クリートの流入を防止することによって上記の問題点を
解消するものである。
Means for Solving the Problems The method for constructing an underground wall according to the present invention includes a formwork box having a substantially U-shaped cross section in a trench excavated underground, and reinforcing bars penetrating the bearing wall of the formwork box. Insert the mold box, connect the previously inserted form box with a tie rod, pour concrete behind the form box so that the lateral pressure of the concrete is supported by the tie rod, and use sealing material to seal between the side plate and the ground. The above problem is solved by preventing the inflow of concrete.

また型枠函の掘削方向前方には支圧壁より延びる支持部
の先端に溝を閉塞するカバープレートを位置せしめ、該
カバープレートの掘削方向前方に砕石を埋設し、型枠函
の後方に打設したコンクリートの側圧をタイロッド及び
砕石によって支持するものである。
In addition, a cover plate that closes the groove is placed at the tip of the support extending from the bearing wall in front of the form box in the excavation direction, crushed stone is buried in front of the cover plate in the excavation direction, and crushed stone is placed behind the form box. The lateral pressure of the installed concrete is supported by tie rods and crushed stone.

実施例 以下第1図及び第2図に示す一実施例に基づきこの出願
にかかる一方の発明を施工順に沿って説明する。
EXAMPLE One of the inventions according to this application will be explained in accordance with the construction order based on an example shown in FIGS. 1 and 2.

〈1〉溝掘削 地中に所要深さの溝1を掘削する。溝1の幅は構築する
地中壁の幅と同一である。
<1> Trench excavation A trench 1 of the required depth is excavated into the ground. The width of trench 1 is the same as the width of the underground wall to be constructed.

〈2〉型枠函の挿入 溝1内に型枠函2を挿入する。型枠函2は支圧壁3と該
支圧壁3の両端から掘削進行方向に延びる二枚の側板4
,4から横断面略コ字状に形成されている。支圧壁6の
幅は溝1の幅と略同−である。側板4,4は支圧壁3よ
りも掘削進行方向に若干突出せしめられ、該後端にシー
ル材5が各々上下方向に連続して取付けられている。
<2> Insert the form box 2 into the insertion groove 1 of the form box. The formwork box 2 includes a bearing wall 3 and two side plates 4 extending from both ends of the bearing wall 3 in the direction of excavation progress.
, 4 in a substantially U-shaped cross section. The width of the bearing wall 6 is approximately the same as the width of the groove 1. The side plates 4, 4 are made to protrude slightly in the direction of excavation progress than the bearing wall 3, and a sealing material 5 is attached to the rear end thereof in a continuous manner in the vertical direction.

シール材5はゴム等の弾性材料によって形成されている
The sealing material 5 is made of an elastic material such as rubber.

型枠函2には鉄筋6が連結されている。鉄筋6はあらか
じめ縦横に組み上げられたもので、先端が支圧壁3を貫
通して両側板4,4間に位置せしめられている。鉄筋6
は型枠函2の側板4との間隔をスペーサー7によって保
持されている。実施例としてはスペーサー7としてL型
鋼が使用されている。
Reinforcing bars 6 are connected to the formwork box 2. The reinforcing bars 6 are assembled in advance vertically and horizontally, and their tips penetrate through the bearing wall 3 and are positioned between the side plates 4, 4. Rebar 6
is maintained at a distance from the side plate 4 of the formwork box 2 by a spacer 7. In the embodiment, L-shaped steel is used as the spacer 7.

また支圧壁3を貫通して異形鉄筋8が表裏面から突出せ
しめられている。異形鉄筋8の先端にはナツト9が固定
されている。
Further, deformed reinforcing bars 8 are made to penetrate through the bearing wall 3 and protrude from the front and back surfaces. A nut 9 is fixed to the tip of the deformed reinforcing bar 8.

以上のような構成を有する型枠函2と鉄筋6を一体に溝
1内に挿入する。
The formwork box 2 and the reinforcing bars 6 having the above-described configuration are inserted into the groove 1 together.

〈3〉クイロッドによる連結 型枠函2は先行して挿入した型枠函2とタイロッド10
により連結する。タイロッド10は型枠函2の支圧壁3
を貫通してナツト11により固定する。12はタイロッ
ド補強筋である。
<3> The formwork box 2 connected by the tie rod is connected to the formwork box 2 and tie rod 10 inserted in advance.
Connect by. The tie rod 10 is the bearing wall 3 of the formwork box 2
is passed through and fixed with a nut 11. 12 is a tie rod reinforcing bar.

〈4〉コンクリートの打設 型枠函2の掘削進行方向後方にコンクリート13を打設
する。型枠函2の側板4と地山間の隙間への流入はシー
ル材5によって防止する。
<4> Concrete pouring Concrete 13 is poured behind the form box 2 in the direction of excavation progress. The sealing material 5 prevents the water from flowing into the gap between the side plate 4 of the formwork box 2 and the ground.

支圧壁3へかかるコンクリート13の側圧はタイロッド
10により支持する。
The lateral pressure of the concrete 13 applied to the bearing wall 3 is supported by tie rods 10.

〈5〉溝の延長掘削 型枠函2の掘削方向前方にカバープレート14を位置せ
しめて溝1を閉塞する。カバープレート14は一端が支
圧壁3に固定された掘削方向前方に延びる支持部15に
直交するよう取付けられている。カバープレート14の
両側端は型枠函2の側板4,4の内側面、若しくは地山
に近接する位置まで延びている。支持部15の表裏面に
は上下方向に各々清掃機用ガイド16が取付けられてい
る。実施例ではH型鋼が清掃機用ガイド16として固定
されている。
<5> Extension excavation of the groove A cover plate 14 is positioned in front of the form box 2 in the excavation direction to close the groove 1. The cover plate 14 is attached such that one end thereof is perpendicular to a support portion 15 fixed to the bearing pressure wall 3 and extending forward in the excavation direction. Both ends of the cover plate 14 extend to the inner surfaces of the side plates 4, 4 of the form box 2, or to a position close to the ground. Cleaner guides 16 are attached to the front and back surfaces of the support portion 15 in the vertical direction, respectively. In the embodiment, an H-shaped steel is fixed as the cleaner guide 16.

カバープレート14の前方を掘削して溝1を延長する。The groove 1 is extended by excavating the front of the cover plate 14.

掘削土はカバープレート14によって型枠函2内に入り
込むのが阻止される。
The excavated soil is prevented from entering the formwork box 2 by the cover plate 14.

支持部15の清掃機用ガイド16を使用して清掃機を走
行させ、型枠函2内の鉄筋6を清掃する。
The cleaning machine is run using the cleaning machine guide 16 of the support part 15 to clean the reinforcing bars 6 in the formwork box 2.

〈6〉コンクリートの打ち継ぎ 支持部15と一体になったカバープレート14を撤去し
、型枠函2と一体となった鉄筋6を溝1内に吊り降す。
<6> The cover plate 14 integrated with the concrete pouring support part 15 is removed, and the reinforcing bar 6 integrated with the form box 2 is suspended into the groove 1.

型枠函2内には鉄筋6が突出しているため、鉄筋6が相
互に重なり合うことになる。
Since the reinforcing bars 6 protrude into the form box 2, the reinforcing bars 6 overlap each other.

以上の状態で既述のように溝1内にコンクリート13を
打設する。コンクリートの打ち継ぎ部分には鉄筋6が重
なり合っているため、土圧等による水平力に充分に耐え
ることが可能となる。
In the above state, concrete 13 is poured into groove 1 as described above. Since the reinforcing bars 6 are overlapped at the concrete joint, it is possible to sufficiently withstand horizontal forces caused by earth pressure and the like.

〈7〉他の発明の一実施例 次に第6図及び第4図に示す他の発明の実施例につき説
明する。
<7> Another embodiment of the invention Next, another embodiment of the invention shown in FIGS. 6 and 4 will be described.

第3図に示すのはコンクIJ −ト15の側圧をタイロ
ッド10及びカバープレート14の前方に埋設した砕石
17によって支えるものである。
What is shown in FIG. 3 is a structure in which the lateral pressure of the concrete IJ-t 15 is supported by crushed stones 17 buried in front of the tie rods 10 and the cover plate 14.

すなわち型枠函2の支圧壁3の表面の左右に上下方向に
延びるガイド溝18が各々形成され、該ガイド溝1日に
、カバープレート14の支持部15の左右に平行に突設
したガイド部19を各々嵌合してガイドプレート14を
型枠函2後方にコンク’)−ト15を打設する以前に取
付ける。
That is, guide grooves 18 extending vertically are formed on the left and right sides of the surface of the bearing wall 3 of the formwork box 2, and in the guide grooves 1, guides protruding parallel to the left and right sides of the support portion 15 of the cover plate 14 are formed. The guide plate 14 is installed by fitting the parts 19 into each other before pouring the concrete 15 behind the formwork box 2.

尚、カバープレート14の左右両端にはシール材20が
上下方向に連続して突設されている。
Incidentally, a sealing material 20 is provided continuously projecting in the vertical direction at both left and right ends of the cover plate 14.

カバープレート14の前方に砕石17を埋設し、その後
コンクリート13を型枠函2後方に打設する。コンクリ
ート13の側圧はタイロッド10及び、支持部15、カ
バープレート14を介して砕石17によって支える。
Crushed stone 17 is buried in front of the cover plate 14, and then concrete 13 is poured behind the form box 2. The lateral pressure of concrete 13 is supported by crushed stone 17 via tie rods 10, support portions 15, and cover plate 14.

コンクリート16の硬化後砕石17、カバープレート1
4、支持部15、ガイド部19を溝1から取り出し、既
述のようなコンクリートの打ち継ぎ作業を行う。
After hardening of concrete 16, crushed stone 17, cover plate 1
4. Take out the support part 15 and guide part 19 from the groove 1, and perform the concrete pouring work as described above.

更に第5図に示すのは他の実施例であって、型枠函2の
支圧壁3の表面にカイト溝21を形成し、支持部15の
先端のブラケット22を係止し、カバープレート14の
取付け、取外しを容易にしたものである。
Furthermore, FIG. 5 shows another embodiment in which a kite groove 21 is formed on the surface of the bearing wall 3 of the formwork box 2, a bracket 22 at the tip of the support part 15 is locked, and the cover plate is fixed. 14 is made easy to install and remove.

発明の効果 この発明は以上のような構成を有するため以下のような
効果を得ることができる。
Effects of the Invention Since the present invention has the above configuration, the following effects can be obtained.

■ コンクリートの打継ぎ部分にて鉄筋を重ね合せるた
め、土庄等の水平力に充分に耐え得ることができる。
■ Since the reinforcing bars are overlapped at the joints of the concrete, it can sufficiently withstand horizontal forces such as those caused by tonosho.

@ コンクリートの側圧をタイロッドによって支えるた
め、薄鋼板等で形成した軽量のものであっても型枠函が
ズレることなく正確な施工が可能となる。
@ Since the lateral pressure of concrete is supported by tie rods, accurate construction is possible without shifting the formwork box, even if it is lightweight made of thin steel plate.

θ シール材によって型枠函の側板と地山間にコンクリ
ートが流れ込むのを防止するため、型枠園内にコンクリ
ートが流入することがない。
θ The sealing material prevents concrete from flowing into the space between the side plate of the formwork box and the ground, so concrete does not flow into the formwork garden.

Oまたコンクリートの側圧をタイロッドによって支える
とともに支持部、カバープレートを介して埋設した砕石
によって支えるため、より強固に型枠函を支持すること
ができる。
Also, since the lateral pressure of the concrete is supported by the tie rods and by the buried crushed stone via the support section and cover plate, the form box can be supported more firmly.

【図面の簡単な説明】[Brief explanation of drawings]

第1図及び第2図はこの出願にかかる一方の発明の一実
施例の施工順序平面図、第5図及び第4図は他の発明の
一実施例の施工順序平面図、第5図はその他の実施例の
平面図である。 1・・溝、2・・型枠函、3・・支圧壁、4・・側板、
5・・シール材、6・・鉄筋 7・春スペーサー、10
・・タイロッド、13・φコンクリート、14・・カバ
ープレート、15・・支持部、16・・清掃機用カイト
、17・・砕石。 il  図
1 and 2 are construction order plan views of one embodiment of one invention related to this application, FIGS. 5 and 4 are construction order plan views of an embodiment of the other invention, and FIG. FIG. 7 is a plan view of another embodiment. 1. Groove, 2. Form box, 3. Bearing wall, 4. Side plate,
5. Sealing material, 6. Reinforcing bar 7. Spring spacer, 10
・・Tie rod, 13・φ concrete, 14・・Cover plate, 15・・Support part, 16・・Kite for cleaning machine, 17・・・Crushed stone. il figure

Claims (2)

【特許請求の範囲】[Claims] (1)地中に所要深さの溝を掘削し、支圧壁と該支圧壁
の両端から掘削進行方向に延びる二枚の側板から成る断
面略コ字状の型枠函と、該型枠函の支圧壁を貫通し、先
端が両側板間に位置する鉄筋かごを前記溝内に挿入し、
該型枠函は両端の支圧壁をタイロッドにより連結し、支
圧壁に作用するコンクリートの側圧をタイロッドにより
支持するようにして型枠函の掘削進行方向後方にコンク
リートを打設するとともにシール材によつて側板と地山
間へのコンクリートの流入を防止し、さらに型枠函の掘
削方向前方には支圧壁より延びる支持部の先端に溝を閉
塞するカバープレートを位置せしめ、カバープレート前
方を掘削することを特徴とする地下壁の構築方法。
(1) A trench of a required depth is excavated in the ground, and a formwork box with a substantially U-shaped cross section consisting of a bearing wall and two side plates extending in the excavation progress direction from both ends of the bearing wall, and the mold Inserting a reinforcing cage into the groove that penetrates the bearing wall of the frame box and whose tip is located between the both side plates,
The bearing walls at both ends of the formwork box are connected by tie rods, and the lateral pressure of concrete acting on the bearing walls is supported by the tie rods, and concrete is poured behind the formwork box in the direction of excavation progress, and a sealing material is applied. This prevents concrete from flowing into the gap between the side plate and the ground, and furthermore, a cover plate that closes the groove is placed at the tip of the support extending from the bearing wall at the front of the formwork box in the excavation direction, and the front of the cover plate is A method of constructing an underground wall, which is characterized by excavation.
(2)地中に所要深さの溝を掘削し、支圧壁と該支圧壁
の両端から掘削進行方向に延びる二枚の側板から成る断
面略コ字状の型枠函と、該型枠函の支圧壁を貫通し、先
端が両側板間に位置する鉄筋かごを前記溝内に挿入し、
該型枠函は両端の支圧壁をタイロッドにより連結し、型
枠函の掘削方向前方には支圧壁より延びる支持部の先端
に溝を閉塞するカバープレートを位置せしめ、該カバー
プレートの掘削方向前方に砕石を埋設し、型枠函の掘削
方向後方にはコンクリートを打設するとともにシール材
によつて側板と地山間へのコンクリートの流入を防止し
、コンクリートの側圧はタイロッドと、支持部カバープ
レートを介して砕石によつて支持し、コンクリート硬化
後カバープレート前方を掘削することを特徴とする地中
壁の構築方法。
(2) A trench of a required depth is excavated in the ground, and a form box with a substantially U-shaped cross section consisting of a bearing wall and two side plates extending in the excavation progress direction from both ends of the bearing wall, and the mold Inserting a reinforcing cage into the groove that penetrates the bearing wall of the frame box and whose tip is located between the both side plates,
The formwork box connects the bearing walls at both ends with tie rods, and a cover plate that closes the groove is placed at the tip of the support part extending from the bearing wall at the front of the formwork box in the direction of excavation. Crushed stone is buried in the front direction, concrete is placed behind the formwork box in the excavation direction, and sealing material is used to prevent concrete from flowing between the side plate and the ground.The lateral pressure of the concrete is controlled by tie rods and supporting parts. A method for constructing an underground wall characterized by supporting it with crushed stone through a cover plate and excavating in front of the cover plate after the concrete hardens.
JP26418884A 1984-12-14 1984-12-14 Construction of underground wall Granted JPS61142221A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26418884A JPS61142221A (en) 1984-12-14 1984-12-14 Construction of underground wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26418884A JPS61142221A (en) 1984-12-14 1984-12-14 Construction of underground wall

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP31797788A Division JPH07897B1 (en) 1988-12-16 1988-12-16

Publications (2)

Publication Number Publication Date
JPS61142221A true JPS61142221A (en) 1986-06-30
JPH0259890B2 JPH0259890B2 (en) 1990-12-13

Family

ID=17399695

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26418884A Granted JPS61142221A (en) 1984-12-14 1984-12-14 Construction of underground wall

Country Status (1)

Country Link
JP (1) JPS61142221A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4917005A (en) * 1972-06-10 1974-02-15
JPS5738836U (en) * 1980-08-18 1982-03-02

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55132480A (en) * 1979-04-04 1980-10-15 Kubota Ltd Metal pipe

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4917005A (en) * 1972-06-10 1974-02-15
JPS5738836U (en) * 1980-08-18 1982-03-02

Also Published As

Publication number Publication date
JPH0259890B2 (en) 1990-12-13

Similar Documents

Publication Publication Date Title
CN103343538B (en) Supporting and construction method of steel sheet pile under soft foundation of high flow plastic deep layer
US4055927A (en) Concrete walls and reinforcement cage therefor
JPH11303087A (en) Retaining wall using corrosion-resistant structure anchor
KR20210078779A (en) Underground roadway removed upper structure between upper slab and surface of road after constructing the steel continuous wall in the earth by top-down method and method for constructing the same
JPS61142221A (en) Construction of underground wall
JPH01207521A (en) Construction of underground wall
JPS61122320A (en) Method of coupling continuous underground wall with underground structure
JP3218518B2 (en) Excavator guide wall in underground diaphragm wall method
JPH0988105A (en) Excavation method for underground structure
US5505564A (en) Method for providing a sheet pile wall in the ground and a prefabricated wall element for carrying out such method
JP2004019100A (en) Construction method for underground structure, and underground structure
KR100401330B1 (en) A method of construction for earth-protection walls of building
JP3713117B2 (en) How to build the foundation
JP3889113B2 (en) Construction method of solidified water wall
JP2001164559A (en) Construction method of continuous underground wall guide wall making use of l-type precast member
JP2947083B2 (en) Construction method of deep groove block
JPH041811B2 (en)
JPS6017898B2 (en) Construction method of pile foundation with underground wall
JPH1088592A (en) Concrete retaining wall
JPH0144849B2 (en)
JPS6012491B2 (en) Continuous underground wall construction method
JPH0477764B2 (en)
JP4399062B2 (en) Construction method of viaduct underground beam
JPS60133116A (en) Structure of joint part for steel pipe sheet pile
JP2629482B2 (en) Underground beam and its construction method